Project Weightage - EPC

The document provides a progress summary of weightage for different categories and activities in a construction project. It shows that the overall project weightage is 100%, with construction activities making up 65% of the project. Within construction, the building category makes up 50.95%, with finishing works having the highest weightage at 23.66%. Other categories like the mosque, swimming pool, and external works make up the remaining construction weightage. Activities like substantial completion, pre-commissioning, commissioning and final handover make up the remaining 10% of the project weightage.

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
1K views1 page

Project Weightage - EPC

The document provides a progress summary of weightage for different categories and activities in a construction project. It shows that the overall project weightage is 100%, with construction activities making up 65% of the project. Within construction, the building category makes up 50.95%, with finishing works having the highest weightage at 23.66%. Other categories like the mosque, swimming pool, and external works make up the remaining construction weightage. Activities like substantial completion, pre-commissioning, commissioning and final handover make up the remaining 10% of the project weightage.

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Weightage - Progress Summary

Category Buildings Activity Weightage

Overall 100.00%
MOBILISATION & HSE CERTIFICATE 3.00%
ENGINEERING & DESIGN 2.00%
PROCUREMENT 20.00%
CONSTRUCTION 65.00%
BUILDING 50.95%

SUBSTRUCTURE 6.80%
SUPER STRUCTURE 16.55%
FINISHING WORKS (INTERNAL & EXTERNAL) 23.66%
MEP WORKS 3.94%
BLOCK 3.21%

UG WATER TANK 0.67%


SUBSTRUCTURE 0.45%
SUPER STRUCTURE 0.27%
FINISHING WORKS (INTERNAL & EXTERNAL) 1.64%
MEP WORKS 0.18%
SERVICE AREA 1.29%

SUBSTRUCTURE 0.19%
SUPER STRUCTURE 0.09%
FINISHING WORKS (INTERNAL & EXTERNAL) 0.99%
MEP WORKS 0.02%
MOSQUE 5.17%

SUBSTRUCTURE 0.72%
SUPER STRUCTURE 1.80%
FINISHING WORKS (INTERNAL & EXTERNAL) 2.53%
MEP WORKS 0.11%
SWIMMING POOL 1.38%

MAIN POOL 0.75%


PERIPHERAL STRUCTURE 0.54%
FINISHING WORKS (INTERNAL & EXTERNAL) 0.09%
MEP WORKS 0.00%
EXTERNAL WORKS 2.95%

COMPOUND WALL 1.33%


SEPTIC TANK WITH SOAK PIT 0.14%
SEWERAGE PIPELINE WORKS 0.09%
WATER PIPELINE WORKS 0.11%
FOOT BALL FIELD 0.27%
TENNIS YARD 0.25%
KERBSTONE 0.16%
INTERLOCK PAVEMENT 0.09%
ROAD WORKS 0.20%
LANDSCAPING & IRRIGATION 0.14%
OUTDOOR LIGHTING 0.18%
SUBSTANTIAL COMPLETION, PRE-COMMISIONING & COMMISIONING 5.00%
FINAL HANDOVER 5.00%