Lynda - Network Diagramming Practice

Lynda_ Network Diagramming Practice
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
63 views

Lynda - Network Diagramming Practice

Lynda_ Network Diagramming Practice
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Cert Prep: Project Management Professional (PMP)® (2018)

with Sandra Mitchell

Network Diagramming, Example 1:

Activity Preceding Activities Duration in Days


A Start 9
B A, C 3
C Start 13
D C 9
E D 2
F E 10
G F 11
H B, G 3

1. Which path is the critical path and what is its duration?


2. What is the slack/float for activity B?
3. Which path has the longest slack?
4. What is the slack of the path in question 3?
5. If activity B slips from 3 days to 6 days, what is the critical path?
6. With the duration adjustment in question 5, what is the new slack of activity B?

Network Diagramming, Example 2:

Activity Preceding Activities Duration in Days


A Start 8
B A 4
C A 10
D B, C 2
E D 2
F D 2
G D 3
H E, F, G 2
I H 1

Cert Prep: Project Management Professional (PMP)® (2018) with Sandra Mitchell
1 of 3
1. Which path is the critical path and what is its duration?
2. What is the slack/float for activity F?
3. What is the slack/float for activity B?
4. If activity E now takes 4 instead of 2, how has the critical path changed?
5. Based on the information in question 4, what is the new critical path and what is its duration?

Network Diagram 1 Example Answers

Start-A-B-H-Finish = 15
Start-C-B-H-Finish = 19
Start-C-D-E-F-G-H-Finish = 48 (CP)

1. Which path is the critical path and what is its duration?


A-B-H=15
C-B-H=19
C-D-E-F-G-H=48 (CP)

2. What is the slack/float for activity B? 29


3. Which path has the longest slack? A-B-H
4. What is the slack of the path in question 3? 33
5. If Activity B slips from 3 days to 6 days, what is the critical path? Critical path stays the same.
6. With the duration adjustment in question 5, what is the new slack of activity B? 26

Cert Prep: Project Management Professional (PMP)® (2018) with Sandra Mitchell
2 of 3
Network Diagram 2 Example Answers

1. Which path is the critical path and what is its duration?


A-B-D-E-H-I=19 + 2 =21
A-B-D-F-H-I=19
A-B-D-G-H-I=20
A-C-D-E-H-I=25 + 2 =27
A-C-D-F-H-I=25
A-C-D-E-H-I=26 (CP)
2. What is the slack/float for activity F? 1
3. What is the slack/float for activity B? 6
4. If activity E now takes 4 instead of 2, how has the critical path changed?
Critical path changes to A-C-D-E-H-I. It is now 27 days.
5. Based on the information in question 4, what is the new critical path and what is its duration?
A-C-D-E-H-I=27

Cert Prep: Project Management Professional (PMP)® (2018) with Sandra Mitchell
3 of 3