Lynda - Network Diagramming Practice
Lynda - Network Diagramming Practice
Cert Prep: Project Management Professional (PMP)® (2018) with Sandra Mitchell
1 of 3
1. Which path is the critical path and what is its duration?
2. What is the slack/float for activity F?
3. What is the slack/float for activity B?
4. If activity E now takes 4 instead of 2, how has the critical path changed?
5. Based on the information in question 4, what is the new critical path and what is its duration?
Start-A-B-H-Finish = 15
Start-C-B-H-Finish = 19
Start-C-D-E-F-G-H-Finish = 48 (CP)
Cert Prep: Project Management Professional (PMP)® (2018) with Sandra Mitchell
2 of 3
Network Diagram 2 Example Answers
Cert Prep: Project Management Professional (PMP)® (2018) with Sandra Mitchell
3 of 3