A. Preliminary Design Data: Overtop W Weir 0.667 0.667
A. Preliminary Design Data: Overtop W Weir 0.667 0.667
2. Orifice design:
Qd = 0.65 Cumecs
Assuming velocity, v = 1.5m/s
Area, A = Qd/v
= 0.65/1.5
= 0.433 sq.m.
0
Assuming orifice height h = 0.4m
Width of the orifice w = A/h = 0.433/ 0.4 = 1.08m
Assuming width of the orifice = 1.1m
Setting the bottom of orifice 0.2m above the riverbed level. This will minimize the bed load.
Also, set the datum at the river bed level.
Design flood level is about 3m above the river bed level
Set water level at head race canal Hr = 0.7m w.r.t. datum.
Normal water level (NWL) = 1.2m
Now,
Q = A x C x ((2 x g (NWL – Hr)) 1/2
Where C = 0.6 for roughly finished masonry orifice.
Q = 0.826Cumecs
Qred = 0.65 Cumecs
V = Q/A
= 0.65 / (1.1 x .55) = 1.074 m/s
Critical velocity;
Vc = (H x g)1/2
= 2.32 m/s
Therefore 80% of the critical velocity,
Vc = 0.8 x 2.32
= 1.856 m/s > 1.074, hence design is safe.
Calculate wetted perimeter and hydraulic radius:
Wetted perimeter P = 2H + B
= 2 x 0.55 + 1.1
= 2.2m
Thus, Hydraulic radius R = A/P
= 1.1 x 0.55/ 2.2
= 0.275m
Diameter of the particle,
D = 11RS
= 11 x 0.275 x 1/300
= 0.0108m
= 10.08 mm i.e. the particle larger than 10.08mm will settle in this
canal.
Check for canal bed slope:
From Manning’s equation,
V = 1/n R2/3S1/2
From this equation putting R = 0.275m and V = 1.074m/s, n = 0.02
We get S = 1 in 387, which is less than provided bed slope (1 in 300) so
The design is ok.
Design parameters:
Width of the canal B = 1.1m
Providing freeboard = 0.45m and water depth in the canal = 0.55m
Total height of the canal = 0.45 + 0.55 = 1m
Therefore, to avoid deposition upstream of settling basin the gravel trap must be then designed
to remove the particles greater than 10mm.
2
D. DESIGN OF GRAVEL TRAP
E. DESIGN OF SPILLWAY
Case II
Lspillway = 2 x Qspillway/Cw x Hovertop^1.5
= 1.07 x 2/ (1.6 x 0.21.5)
= 14.95m
Therefore Spillway of Length of 15m to be used.
With a mean river temperature of 15ºC during the high flow season, the fall velocity
w = 0.037m/s
For dlimit = 0.3mm.
Area = 2Q/w
= 2*0.65/0.037
= 35.135 m2
Set B=3m
L = 35.137/3 = 11.37m, set L = 12m
L/B = 4
2. d = (6 x Qd / (π x c x sqrt (Hbasin+Hflush)))0.5
3. d = (4 x Qd / (π x c x sqrt (Hflush)))0.5
Since we have placed the spillway along the headrace canal (u/s of settling basin) we make the
use of equation 2 and 3.
Q = 0.65 Cumecs
For stone masonry Manning’s coefficient n = 0.02
Bed slope (S) = 1 in 1000
For rectangular canal, N = 0, B = 2H
I. DESIGN OF PENSTOCK
Discharge through the penstock pipe,
Qd = 0.6175 m3/s
Head gross = 14m
Penstock material = uncoated mild steel
Setting velocity, V = 3m /s
Internal diameter of the pipe, d = (4xQ/πV)1/2
= (4x 0.6175/π x 3)1/2
= 0.511m
Adopt pipe diameter of 500mm.
Calculating wall loss, K = 0.006 mm
K/d = 0.06/500 = 0.00012
1.2Q/d = 1.2 x 0.6175/0.5 = 1.482
From Moody’s diagram, f = 0.016
Then a = 940.6m/s
Critical time (Tc) = (2*L)/a = 2 x 35.3/940.6
6
= 0.075 sec
Choose closure time T = 10 sec > 2Tc
Then, k = (L*V/g*Hgross*T) 2
= (35.3 x 3/9.81 x 14 x 10) 2
= 0.00594 < 0.01
Hsurge = Hgross x k^ (1/2) = 1.078m
Htotal = Hgross + Hsurge
= 14 + 1.078
= 15.078 m
t effective = 4/1.1x1.2 -1.5 = 1.53mm
Safety factor (S.F) = 200 x t effective x S / H total x d
= 200 x 1.53 x 320/ 15.078 x 500
= 12.98 > 3.5 ok.
Hence,
Length = 2.5m, Width = 2m, Height = 2m
8
M. DESIGN OF THE ANCHOR BLOCK
Type I
Calculations:
Htotal = 15.078m
Block volume excluding volume of pipe:
= 2.5 x 1.5 x 1.5 – π x 0.508² /4(0.75/cos 11.482˚ + 0.75/cos 36.063˚) – ½ x 1.5 x 0.4 x 1.5
= 4.84 m³
Unit weight of concrete = 22 KN/ m³
Weight of block = 22 x 4.84
= 106. 546 KN
Weight of pipe, Wp = π (d + t) x t x γsteel
= π (0.5 + 0.004) x 0.004 x 77
= 0.365 KN/m
Weight of water, Ww = π x 0.5²/4 x 9.81 = 1.924 KN/m
Therefore Wp + Ww = 0.365 + 1.924 = 2.29 KN/m
Resolution of forces:
α = 11.482˚ β = 36.063˚
Forces X- component (+) Y-component (+)
F3 = 12.35 F3 sin ((β+ α)/2) = 4.978 -F3 cos ((β+ α)/2) = -11.302
WB =106.546 0 106.546
------------------------------- ------------------------------------
Σ H = 25.841 KN (1) expansion Σ V = 124.135 KN (1 expansion.)
Σ H = -4.513 KN (2) contraction Σ V = 82.495 KN (2 contraction.)
The center of gravity of the block, from the u/s face by taking moment of mass about O. The
effect of pipe passing through the block is negligible.
= 0.728 m
i.e. the weight of the block WB acts 0.728m from point O.
Allowable bearing pressure for stiff clay and stiff sandy clay = 200 KN/m²
Since in the both cases Pbase < P allowable (200 KN/m²), so the structure is safe against bearing
capacity.
ΣH<µΣV
µ = 0.5 for concrete/masonry on soil.
12
Type II
Calculations:
Htotal = 15.078m
Resolution of forces:
α = 36.063˚ β =0˚
Forces X- component (+) Y-component (+)
(KN) (KN) (KN)
F8 = -1.18 F8 sin ((β + α)/2) = -0.365 -F8 cos ((β + α)/2) =1.122
WB =141.262 0 141.262
------------------------------- -----------------------------------
Σ H = 0.758 KN (1) expansion Σ V = 142.379 KN (1 expansion.)
Σ H = 11.466KN (2) contraction Σ V = 195.089 KN (2 contraction.)
The center of gravity of the block, from the u/s face by taking moment of mass about O. The
effect of pipe passing through the block is negligible.
= 0.722 m
i.e. the weight of the block WB acts 0.722m from point O.
Since in the both cases Pbase < Pallowable (200 KN/m²), so the structure is safe against bearing
capacity.
16
i.e 11.466< 0.5 x 195.089
< 97.54 KN hence ok .
Since Σ H < µ Σ V in both cases, the structure is safe against sliding.
Q = 0.6175 m³/s
Manning’s coefficient n = 0.02
Assuming velocity V = 1.5 m/s
Therefore, A = Q/V = 0.6175/1.5 = 0.412 m²
Taking B = 2H,
A= B x H
0.412 = 2H x H
H = 0.454m
Adopting, H = 0.5 m
Hence B = 2H = 2 x 0.5 = 1m
17
Height of canal H= 0.5 + 0.3 = 0.8m
Design data
Diameter of penstock (D) = 500mm
The pipe centerline is 550mm above the powerhouse floor
Design discharge (Qd) = 617.5 lps
Gross Head (H) = 14m
Maximum surge (Hsurge) = 1.078m
Water level in the tailrace canal = 0.5m
Weight of Turbine (WT) = 750Kg
Weight of Generator (WG) = 424 Kg
Design:
Total Head (Htotal) = Hgross + Hsurge
= 14+1.078
= 15.078m
Let us start the design by considering the following reinforcement and dimensioning
Force due to Htotal (FH) = pipe area x 15.078 x unit weight of water
= 3.14 x 0.5 x 0.5/4 x 15.078 x 9.81
= 29.0134KN
Weight of Turbine (WT) = 750 x 9.8
= 7350N
= 7.35KN
Weight of Generator (WG) = 424 x 9.8
= 4155.2N
= 4.1552KN
Place all the forces on the machine foundation and divide the foundation into the following
three parts
Refer Diagram
18
Distance through which the resultant acts
X = M/V
= 385.127/272.755
= 1.412m
2. Bearing Pressure
Pbase = V/A (1+ 6e/B)
= 272.755/ (3.3 x 2.5) (1 + 6 x 0.238/3.3)
= 47.3 KN/sq.m< 180 KN/sq.m
Hence, it is safe against pressure.
3. Sliding
Assume friction coefficient (µ) =0.6
Factor of safety against sliding = 0.6 x V/FH
= 0.6 x 272.755/29.0134
= 5.64 > 1.5 OK.
Hence, it is safe against sliding.
19