Project Integration Management With FIDIC
Project Integration Management With FIDIC
ABSTRACT
The article examines the implementation of the new trends in the Project Integration Management in
construction. The authors demonstrate how the knowledge from the latest editions of the PMBOK® and
its Construction Extension may be used to manage complex projects with several related FIDIC
contracts for design, construction, supervision, supply chain. The modern multi-party partnering form,
called the “Framework Alliance Contract FAC-1”, can integrate all related two-party FIDIC contracts
between the participants in the investment process. Practical examples demonstrate how several FIDIC
contracts can be managed more efficiently under the umbrella of FAC-1. FAC-1 enables collaboration,
BIM, lean practices and the transfer of knowledge.
1. INTRODUCTION
Integration throughout the project life cycle is of paramount importance. In the construction industry,
not only do the processes interact, but their management is greatly expanded to address multiple
performing organizations, operating simultaneously. Effectiveness and efficiency is dependent on
integration management. The need for increased communication and transparency, coupled with timely
and efficient decision making, makes collaboration a critical technique when countering the effect of
project complexity. [1]
For construction to be successful, an integrated organization needs to be created, the commercial
interests of the parties need to align around the efficiency of the project as a whole, and lean tools and
management methods should be deployed using the latest available technologies. [2]
McKinsey’s 2017 Report recommends several areas to be addressed to boost productivity on projects
by some 50 to 60 percent. One of the main factors is the procurement process. There is a need to move
away from the hostile contracting environment that characterizes many construction projects to a system
focused on collaboration and problem solving [3].
Collaborative activities require coordination and agreed timelines in order to create mutual confidence
among team members that each will create and share the data that they all need to deliver the project.
Collaborative contracts provide the machinery for coordination and the mutual commitments to agreed
activities and timelines [4].
The international standard for collaboration ISO 44001:2017 recognizes the need to:
ü Establish and agree s formal foundation for joint working, including contractual frameworks or
agreements, roles, responsibilities and ethical principles.
1
PhD Student, Eng., Dept. “Construction Management and Economics”, UACEG, Sofia, Bulgaria, email: [email protected]
2
Prof. Dr. Eng., Dept. “Construction Management and Economics”, UACEG, Sofia, Bulgaria, email:
[email protected]
3
Prof. Dr. Eng., Dept. “Construction Management and Economics”, UACEG, Sofia, Bulgaria, email: [email protected]
ü Determine clarity of purpose, encourage appropriate behavior and identify the potential impacts
on or conflict with the aims of collaborative working [5].
3. FAC-1 AS AN INTEGRATOR
In order to have a collaborative working environment, all participants in the construction using FIDIC
contracts may sign an alliance contract. This will ensure easier project management with tools for:
Ø Early warning;
Ø Innovations;
Ø Time & cost saving;
Ø BIM support [15];
Ø Easy transfer of data;
Ø Know-how transfer.
The 2016 modern multi-party Framework Alliance Contract FAC-1 is designed for international use to
integrate projects under FIDIC and any other project contract forms [16]. The Bulgarian Society of
Construction Law (BSCL), full member of the European Society of Construction Law, signed a license
agreement with the Association of Consultant Architects (ACA) and the author of FAC-1 Professor
David Mosey for the translation and adaptation of FAC-1 to comply with the Bulgarian law. The
Bulgarian version of FAC-1 was launched in 2019 [17]. The same was done in Italy and Brazil. The
German and Russian editions are under preparation.
An integrated FAC-1 multi-party Alliance, entered into with a group of selected consultants,
contractors, suppliers or other providers, enables:
ü Increased transparency, improved efficiency through data shared among Alliance Members;
ü Stronger joint commitment to share Objectives;
ü Closer working relationships on agreed Alliance Activities;
ü Improved joint engagement with the Supply Chain & Stakeholders;
ü Collective self-regulation through the Core Group;
ü More open measurement against agreed Targets;
ü More open motivation to earn agreed Incentives.
Stakeholders
Supervisor 1
Contractor 1
Supervisor 2
Contractor 2
Employer 1 Supervisor 3
Contractor 3
Employer 2
Contractor 4
Contractor 5 Alliance Manager Designer
Fig. 2 An energy efficiency housing framework alliance with FIDIC contracts, integrated by FAC-1
FAC-1 can successfully integrate the supply chain as well. Figure 3 presents an integrated multi-party
framework alliance for school/ sport infrastructure. FAC-1 led by the Alliance Manager integrates the
selected main contractor who signs FAC-1 and a FIDIC Red Book Contract, the important
subcontractors, signing FAC-1 and the FIDIC Subcontract form [20], the Employer’s Designer and
Engineer, signing the FAC-1 and the FIDIC White Book Agreement for Services.
Alliance Manager
Engineer
Employer
Designer
Subcontractor 1 Subcontractor 2
Contractor
Fig. 3 An integrated alliance for school/ sport infrastructure with FIDIC contracts, united by FAC-1
FAC-1 may be used to integrate the parties involved in complex single projects as well.
The German Federal Construction Agency approved the use of FAC-1 as an improved value tool,
integrating the supply chain, and as a BIM enabler, within the EPC FIDIC 1999 Silver Book Contract
for the New Chancery and Guardhouse of the German Embassy in Sofia. The EPC Contractor GBS will
lead the alliance formed with the subcontractors, able to create improved value and/or give timely inputs
to BIM. Figure 4 presents a similar example, considered by the Russian FIDIC Member Association for
implementation in nuclear projects. The EPC Contractor signs a FIDIC Silver Book contract. The
Employer signs a FIDIC White Book Agreement with the Employer’s Representative. The EPC
Contractor forms an alliance with his designer, subcontractors and suppliers. The designer signs FAC-1
and a FIDIC White Book Agreement with the EPC Contractor. The Subcontractors may sign the FIDIC
Subcontract, or Yellow/ Silver Book contracts. Subcontractors and suppliers may compete within the
alliance for additional work packages, thus striving for improved value and innovations.
Employer
Employer’s Representative
EPC Contractor
Alliance Manager
Designer
Sub 1
Sub 2
Sub 3 Supplier 2
Supplier 1 Supplier 3
Fig. 4 An EPC Contractor-led alliance for NPP/ TPP with FIDIC contracts, integrated by FAC-1
An integrated alliance may be formed under the umbrella of FAC-1 for complex infrastructure projects,
where connected sections and related facilities are executed by different contractors, sometimes with
different funds. Figure 5 demonstrates an example for high speed railway or water / sewage projects.
The contractors for different work packages sign different FIDIC contracts (Red or Yellow Book,
depending on the design responsibility), integrated by FAC-1. The FIDIC Engineers and Employer’s
Designers sign the FIDIC White Book Agreement and FAC-1. The Alliance Manager is facilitating the
integration management. The consistent FAC-1 documents establish shared Objectives and encourage a
collaborative approach to agreed Alliance Activities [21].
Alliance Manager
Employer
Subcontracts Designer 2
Contractor 4 Designer 1
Contractor 3 Engineer 2
Contractor 2
Engineer 1
Contractor 1
Fig. 5 An integrated alliance for infrastructure with FIDIC contracts, united by FAC-1
Employers who are not ready to form a multi-party alliance, can enter into separate FAC-1 contracts,
forming linked alliances with the contractors, designers, consultants, integrating the related projects with
the support of the Alliance Manager. Figure 6 shows an example for a high speed railway project, where
the Employer, the Alliance Manager and the FIDIC Engineer sign 3 similar FAC-1 contracts for the two
related sections (Red Book FIDIC contract for the construction, White Book FIDIC agreements for the
design) and the signaling (design-build FIDIC Yellow Book contract).
SOURCES
[1] PMI, Construction Extension to the PMBOK® Guide, 2016, pp.29-30
[2] Oakland. J. and Marosszeky, M., Total Construction Management. Lean quality in construction
delivery, 2017, p. 21
[3] McKinsey Global Institute (MGI’s) Reinventing construction: A route to higher productivity
report, 2017,
https://www.mckinsey.com/~/media/McKinsey/Industries/Capital%20Projects%20and%20Infrast
ructure/Our%20Insights/Reinventing%20construction%20through%20a%20productivity%20revo
lution/MGI-Reinventing-Construction-Executive-summary.ashx
[4] Mosey D., Collaborative Construction Procurement and Improved Value, 2019, ISBN
9781119151913, p. 135
[5] ISO 44001:2017 Collaborative business relationship management systems - Requirements and
framework, Sections 8.6.2.1, 8.6.10
[6] FIDIC (Federation Internationale Des Ingenieurs-Conseils), www.fidic.org
[7] Klee L., International Construction Contracts Law. 2nd ed Wiley-Blackwell, 2018, ISBN: 978-1-
119-43038-4 (Kindle ed) Loc 15119
[8] FIDIC, 1st ed 1999, 2nd ed 2017, Conditions of Contract for Plant and Design-Build. For Electrical
& Mech. Plant & For Building & Engineering Works Designed by the Contractor (Yellow Book)
[9] FIDIC, 1st ed 1999, 2nd ed 2017, Conditions of Contract for EPC/ Turnkey Projects (Silver Book)
[10] FIDIC, 2008, Conditions of Contract for Design, Build, Operate (Gold Book)
[11] FIDIC, 1st ed 1999, 2nd ed 2017, Conditions of Contract for Construction. For Building and
Engineering Works designed by the Employer (Red Book)
[12] FIDIC, MBD Harmonised Ed 2005, 2006,2010, Conditions of Contract for Construction (Pink
Book)
[13] Sioban, F., 2016, FIDIC Users’ Conference London
[14] Dedezade T., Clause 8: Commencement, Delays and Suspension, Corbett & Co Knowledge Hub,
http://corbett.co.uk/wp-content/uploads/Clause-8-Commencement-Delays-and-Suspension-.pdf
[15] King’s College London. Research report: Enabling BIM Through Procurement and Contracts,
2016. https://www.kcl.ac.uk/law/research/centres/construction/enabling-bim/ebimtpac-form.aspx
[16] Mosey D., Framework Alliance Contract FAC-1, 2016
[17] BSCL, Рамков договор на Алианса FAC-1, 2018
[18] FIDIC, FIDIC, 5th Ed 2017, Client/Consultant Model Services Agreement (White Book)
[19] FIDIC, 1st ed 1999, The Short Form of Contract (Green Book)
[20] FIDIC, 2011, Conditions of Subcontract for Construction For building and engineering works
designed by the Employer.
[21] Mosey D., FAC-1 Briefing Paper, 2016, p. 3