Beck-Thermoschrumpfer Operating Instructions
Beck-Thermoschrumpfer Operating Instructions
Beck-Thermoschrumpfer
Version: thB942v5
Table of contents
Table of contents
1. Safety instructions
1.1. Explanation
1.2. General safety instructions
1.3. Emissions
1.4. Integrating the machine into a production line
1.5. Maximum shrink temperature
3. Operation
3.1. Operational control elements
4. Installation
4.1. Checks before switch-on
4.2. Switch-on
5. Production setting
5.1. Shrinking of the film
5.2. Passage speed
5.3. Temperature
5.4. Control of air flow
6. Troubleshooting
7. Accessories
7.1. Film pressure rollers (optional)
7.2. Film blowing device (optional)
7.3. Pre-shrink station (optional)
7.4. Cooling station (optional)
7.5. Transport overrun (optional)
7.6. Rail for revolving bars (optional)
7.7. Production monitoring (optional)
8. Machine maintenance
8.1. Transport chain
8.2. Heating elements
8.3. Maintenance plan
1. Safety instructions
1.1. Explanation
In order to enable a safe handling of the machine possible danger spots are
marked with the key word CAUTION in these operating instructions.
SAFETY SHOES
PROTECTIVE HELMET
PROTECTIVE GLOVES
Please strictly notice and follow the thus marked safety instructions!
1. Safety instructions
• The machine is equipped with a line filter. The line filter is integrated
BEFORE the main switch. Before starting any maintenance or repair work
inside the control cabinet, the machine must be switched dead. Disconnect
the machine from the mains supply.
1.3. Emissions
Noise emissions
Further emissions
If the shrink temperature is too high or if there are film remains in the shrink
zone, corrosive vapours might be produced. Switch off the heating and remove
the film immediately.
For transporting the machine you must wear personal protective equipment,
such as: Safety shoes, protective helmet, protective gloves.
The machine can be transported by lifting the discharge end of the machine or
by lifting the machine crosswise to the working direction (left/right) using a
fork lift or an elevating truck. The required fork length is 1800 millimetres.
For installing the machine you must wear personal protective equipment, such
as: Safety shoes, protective helmet, protective gloves.
The required space depends on the work site conditions. See that the noise
levels do not add up and that there is enough clearance for maintenance and
repair work around the machine.
The machine needs a three-phase current supply with a loadable neutral lead.
The power consumption is mentioned on the type plate. You will find the type
plate inside the control cabinet.
On special request it is possible to adjust the machine to your power supply or
to add a mains transformer.
In special version the machine needs a connection for pneumatic air (optional).
You must provide the connection.
A maximum nominal pressure of 6 Bar may not be exceeded. The machine is
equipped with a maintenance unit.
Before switching on the machine for the first time the phase sequence rotation
of your electrical feed line needs to be checked by a qualified electrician. The
phase sequence must have a clockwise drive! After check-up the machine can
be switched on.
If the phase sequence is not right, you will have to exchange two phases on
your feed line.
3. Operation
3.1. Operational control elements
Picture 1 shows the operational control elements inside the control cabinet.
A B C D E F G H
picture 1
The main switch connects the machine with the supply mains. The line
filter is integrated BEFORE the main switch. Before starting any
maintenance or repair work inside the control cabinet, the machine must
be switched dead. Disconnect the machine from the mains supply.
Press the key P on the thermostat. After a short time the desired
temperature (set temperature) is displayed. Press arrow keys to
adjust the desired temperature. After adjustment of the desired
temperature press key P again to save the set desired temperature. At
the same time the temperature display changes to the actual value
(current shrink temperature).
Press the key P on the thermostat. After a short time the desired
temperature (set temperature) is displayed. Press arrow keys to
adjust the desired temperature. After adjustment of the desired
temperature press key P again to save the set desired temperature. At
the same time the temperature display changes to the actual value
(current shrink temperature).
Press the key OFF to switch off the control of the machine.
Press the key Heating to switch on the heaters for shrinking the film.
With the controller Transport speed you can steplessly adjust the
passage speed to shrink the products. Be sure to adapt the Transport
speed to the kind of product, the temperature setting, the film quality
and to the thickness of the film.
Press the key Emergency stop to interrupt the machine sequence in case
of emergency. At the same time the control of the machine is switched
off.
4. Installation
4.1. Checks before switch-on
4.2. Switch-on
• Switch on the Main switch (see picture 1, A). The machine is connected to
the mains supply.
• Switch on the key Heating (see picture 1, D). The shrink channel is heated
to the set temperature.
5. Product adjustment
The machine must be adjusted to the product and the film quality.
• Passage speed
• Temperature
• Control of air flow
5.3. Temperature
A B C B A
picture 2
At the upper casing on the left and right side of infeed and take-off there is the
upper air flow control bottom (see picture 2, A) respectively the upper air
flow control top (see picture 2,B). By adjusting the air control plates you can
dose and control the upper air supply.
6. Troubleshooting
film does not shrink properly • temperature too low
film does not shrink on top bring upper air deflectors to top
position
7. Accessories
Your Shrink tunnel can be equipped with several accessories. The equipment
depends on which accessories were included in your order.
The Film pressure rollers are fitted at the discharge end of the machine. The
Film pressure rollers will press the film to the sides of the pack, if the products
are sleeve-wrapped.
SETTING:
Open the clamping screws and make the necessary adjustment. Adjustment is
effected from the middle of the transport. Use a product as sample for your
adjustment. The Film pressure rollers must exert a slight pressure to the sides
on the still soft film. In doing so, be sure to observe the spring travel of the
Film pressure rollers.
The Film blowing device is used to blow the bottom film upwards, if products
are sleeve-wrapped. As a result the products are better closed on the sides.
SETTING:
The Film blowing device must be adjusted to the width of the packaging
product. Open the clamping screws in order to do so. Adjustment is effected
from the middle of the transport. In doing so, be sure to observe the angle in
which the air escapes. Use a product as sample for your adjustment.
The Pre-shrink station allows a prior fixing of collation packs. This might be
necessary for some products.
SETTING:
The Pre-shrink station is fitted at the infeed end of the machine. Please refer to
the appendix of this operation instructions for more details. The Pre-shrink
station is specific to design.
7. Accessories
When running at high speed or working very thick film the cooling process of
the film can be increased.
SETTING:
The Cooling station is fitted at the discharge end of the machine. You can
switch the Cooling station ON or OFF by a separate switch. Adjustment is not
necessary.
In case of a voltage drop the bars transport will overrun for a couple of
seconds. If the keys CONTROL OFF or EMERGENCY STOP are pressed,
the working sequence will be interrupted immediately.
SETTING:
You will find the turning lever for pressing the Rail for revolving bars towards
the transport beneath the machine infeed on the control cabinet side.
8. Machine maintenance
Maintenance work and repair work shall only be carried out by trained
personnel.
Be sure to disconnect the machine from the supply mains before starting any
maintenance or repair work on the machine.
In case of repair work on the transport chain, be sure to check the chain tension
upon completion of your work.
You will find the adjustment for tensioning the transport chain on the left and
right hand side of the machine infeed.
Be sure to disconnect the machine from the supply mains before starting any
maintenance or repair work on the machine.
If after a certain period of operation an efficiency loss is noticed, you will have
to check the heating elements.
Be sure to disconnect the machine from the supply mains before starting any
maintenance or repair work on the machine.
picture 3
8. Machine maintenance
Be sure to disconnect the machine from the supply mains before starting any
maintenance work on the machine.
Transport chain
The transport chain must be oiled with the supplied special oil every 200 hours.