0% found this document useful (0 votes)
170 views

Pcd-f001 - Change Order Form

PT Dairi Prima Mineral has issued a change order to PT Dasa Malintas for construction work on a magazine. The change order includes three items: a magazine permit for Rp39.55 million, materials for a water tank, grass and retaining wall for Rp191.93 million, and equipment for a water system and security gate for Rp30.51 million, totaling an additional Rp261.99 million. This increases the original construction contract of Rp2.325 billion to a new amount of Rp2.586 billion. The change order requires approval from both the owner and contractor.

Uploaded by

Alonso Patiaraja
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
170 views

Pcd-f001 - Change Order Form

PT Dairi Prima Mineral has issued a change order to PT Dasa Malintas for construction work on a magazine. The change order includes three items: a magazine permit for Rp39.55 million, materials for a water tank, grass and retaining wall for Rp191.93 million, and equipment for a water system and security gate for Rp30.51 million, totaling an additional Rp261.99 million. This increases the original construction contract of Rp2.325 billion to a new amount of Rp2.586 billion. The change order requires approval from both the owner and contractor.

Uploaded by

Alonso Patiaraja
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 1

CHANGE ORDER FORM

PT Dairi Prima Mineral

CHANGE ORDER

Date:
Project: Construction of Magazine
Change Order #: 001
Owner: PT DAIRI PRIMA MINERAL
Contractor: PT DASA MALINTAS

TYPE OF CHANGE ORDER (Check one:) Standard Change Order


Unforeseen Site Condition (Justification attached)
Emergency (Authorization attached)
Substantial (Authorization attached)

Description of Change:

The following Proposed Change Order(s) are incorporated into the Contract by reference:

Ref. # Summary Description: Amount (Rp) Initiated by:


001 Magazine Permit 39,550,000.00 Mr. Drajat
002 Water Tank, Grass and Material for Retaining Wall 191,934,737.50 Mr. Drajat
003 Water Hose, Water Tank Concrete Base, Electrical 30,510,000.00 Mr. Drajat
Termination and Security Gate

Original Contract Amount: 2,325,000,000.00


Previous Change Order(s): 0.00
Contract Amount Prior to this Change Order: 2,325,000,000.00
Amount of this Change Order: 261,994,737.50

New Contract Amount Including this Change Order: 2,586,994,737.50

Contract Time will be ****INSERT DATA HERE**** by ****INSERT DATA HERE**** days.

Reviewed by:

PT. Dairi Prima Mineral: Date:

Contractor agrees to perform the above-described work in accordance with the above terms and in compliance with applicable sections
of the Project documents. The adjustment in the contract sum, if any, and the adjustment in the contract time, if any, set out in this
Change Order shall constitute the entire compensation and/or adjustment in the contract time due Contractor arising out of the change
in the work covered by this Change Order, unless otherwise provided in this Change Order. No additions or deletions to this Change
Order shall be allowed, except with written permission of PT Dairi Prima Mineral. Contractor accepts the terms and conditions stated
above as full and final settlement of any and all claims arising from this Change Order.

This Change Order is hereby agreed to, accepted and approved by:

Contractor: Date:

Owner: Date: