Modified Report
Modified Report
Telecom Sites:
Any location where we install the telecom equipment is called telecom site.
POI MSC
MSC
BSC
MSC BSC
MSC
Telecom Sites
1. MSC Site
2. BSC Site
3. Transcoder (XCDR)
4. BTS Site
5. Transmission Link
6. Repeater Site
7. Point of Interface (POI) Site
1
# MSC Site
MSC Performs:
Protocol Implementation & Management which are used for routing calls basically.
2
Alarm monitoring and management which are used for example, if the BTS is
hanged then alarm signal will send to OMC to reset the BTS.
Now
[No. of circle (Network)] [1 Active MSC + 1 Back up (Stand by)] [MSC HUB]
Vodafone - Ahmedabad
Airtel - Gurgaon
Reliance - Navi Mumbai
Idea - Noida
Tata Indicom - Chennai
3
BTS = RBS
BTS (Base Transceiver Station) is called by some companies. RBS (Radio Base
Station) is called by some companies).But both are same.
[GEO MSC fom African countries is located in Noida, India.]
Equipments on MSC
# BSC SITE
How many BSC’s are required in one network? What it depends one?
There should be at least one BSC (minimum). Unlimited no. of BSCs can be used but
it depends on no. of users. That means no. of BSC depends on no. of users).
In GSM,1TDMA = 8 Slots
At one frequency = 8 users
1TRX = 8 Calls
1TRX can handle 8 calls in FDMA channel.
1 TRX = 8 Calls
4
1 FDMA Channel
6 TRX = 1 BTS
(i.e. 6 x 8 calls = 48 calls)
i) BSC equipment
ii) Transmission Equipment
iii) Power Backup System
iv) Cooling System
v) Earthling System
vi) Transponder (optional)
vii) BTS (Optional)
Who can work on BSC Site?
BSC Engineer, BSC Engineer, Site Creation Engineer.
The site of BSC which contain BTS in called co-located BTS site.
BSC BSC
BTS BTS
BTS
5
Mobile BTS BSC MSC
16 kbps 16 kbps 16 kbps 64 kbps
BTS Site
MSC
for 3 G
RNC MSC for 4 G
Node B E-Node B
6
No. of BTS Site used: Atleast 1 BTS
(Depends on mobile users and GEO location)
Implementation Engineer:
In implementation works includes:
Installation work (means assembling)
Commissioning work (Addition application, software, setting as per
requirement)
Integration work (Network connectivity to use network, setting)
Testing work (calls, SMS, Data)
# Transmission Link
It is connectivity media through which two components can communicate with one
another (i.e. point to point).
7
What kind of connectivity is used in transmission Link?
Electrical Transmission Link
Wireless Transmission Line
Fiber Optic Transmission Line
BTS BTS
BSC
Microwave Link
1. Microwave
2. Fiber Optic Equipment (SDH/SONET/DWDM)
3. DDF (Digital Distribution Frame)
8
Transmission Engineer
# Repeater Site
MSC
BSC
REPEATER
BTS
Repeater: Receives the signal, the received signal is then handover to the other site.
9
BSC Site BTS Site
10
Chapter-2 Working of PIU in Details
ACDB
ALARM PANEL
MB
AMF PANEL
DG
STABILIZER
PIU (Power Interface Unit) has all the electrical equipments inbuilt inside the PIU.
PIU Consist of
1. ACDB
ACDB – AC Distribution Box which is used for distributing supply to all the
equipments in the site. It consists of 5 DP 32A MCB’s 8 SP 6A MCD’s used
for providing supply to different equipment. The ACDB supply comes from
AMF panel through a 32A. MCB.
2. Stabilizer
11
Stabilizer is used for removing the fluctuating voltage and to keep the voltage
stable. It is used in place where there is more fluctuation in voltage. The
stabilizer we used in telecom is a heavy duty stabilizer. In this stabilizer it has
an auto-transformer. And this stabilizer is called “servo stabilizer”.
3. Alarm Panel
It is used to interface with the alarms from the AMF panel and door shelter
and fire/smoke sensor to the DDF and the DG.
12
D=E => for 1 Ф 2 ½ C 16 sq.mm.
25 sq.mm.
________________________
for 3 Ф 3 ½ C 16 sq.mm.
25 sq.mm.
Al Armed Cable
Al Armed Cable
2 1 C = 1 + 1 + 1 (Size)
2 P N 2 Earthing
3 ½C= 1 + 1 + 1 + ½
P P N Earthing
13
Working Of AMF Panel
Condition
Condition:
2. When mains fail: The condition when mains fail, there is no is no input at X,
then the microcontroller send an instruction to generate an alarm “MAINS
FAIL” After this alarm had been sent, it will wait for 3 minutes to start the
DG. After waiting 3 minutes then a control pulse will be sent to the self of
D.G. through G. The duration fo this pulse is maximum 30 seconds.
a) DG Not Start.
After 30 seconds, when there, is no input received at Y. Then if will wait for
another 3 minutes and will send second control pulse to the self for 30
seconds. At this condition also DG doesn’t start, as a result of it, there is no
input at Y.
14
Then after waiting for 3 minute, a control pulse is send to the self for third
time for a duration of 30 second to the DG. After this third attempt if there is
no input at Y. Then it will generate an external alarm called “D.G. FAILS TO
START”
Alarm Status:
Now all equipments will work on site with DG. The controller will generate
on external alarm (SITE ON DG)
Alarms Status:
At this condition, as, the mains get back, now there is an input at X. Then the
controller will then shift to X from Y. The n controller cleans the alarm
“MAINS FAIL”
15
It will wait for 3 minute and it will load from Y To X. It clears the alarm
“SITE ON DG”. And then it will generate an external alarm “DG ON NO
LOAD” as the DG is running without load.
Alarm Status:
Now controller send control pulse to solenoid of the DG. The duration of that
pulse will be 30 seconds.
At this condition, if the DG does not stop, then it will wait for 3 minutes to
send the pulse. If the DG does not stop then it repeats to asend pulse. The
minimum attempt is only 3 times. After the third attempt is also fails and then
an external alarm “DG FAILS TO STOP” will generate.
Alarm Status:
DG ON NO LOAD (Active)
DG FAILS TO STOP (Active)
16
5. Condition: DG Stop:
DG ON NO LOAD (Clear)
Now there is no active alarm from AMF Panel.
17
Chapter-3
The External Alarms and Its Explanation
18
Definition : All the transmitting equipments inside the shelter
dissipate heat which cause the temperature to
increase inside the shelter.
Step 1:
Activity for alarm generation MCB of AC (both) is tripped and the supply to the AC
will stop and this tripping of MCB. AC will stop working and then the BTS and other
transmission equipment will dissipating the heat inside the shelter and the
temperature inside the shelter and when the temperature just reaches 350C then alarm
is generated.
Alarm Status:
“High Room Temperature” = Active
“AC Fails” = Active
Step 2:
Activity for clearing the alarm switches of the MCB is pushing back to the ON
Position. Then there will be supply to both the AC and both the AC will work till the
shelter room temperature reaches upto 270C after this particular temperature the
active alarm will be cleared.
19
2. “AC – 1 FAILS”
Causes : When
i) MCB of AC-1 is tripped
ii) Mains Supply and DG AC-1
iii) Wire fault.
iv) Supply from PIU fails
By tripping the MCB of AC-1 to the off position. The power supply to the AC-1 will
cut off and AC-1 will stop working. And this alarm will generate.
20
Step 2: Activity for Cleaning the Alarm:
The MCB Switch is push-up to the ON position and the power supply to the AC-I
will be available and it will start working. The alarm which was active will be
cleared off.
3. “AC-2 FAILS”
Alarm Generation
Step-1:
Activity for Generating alarm. Tripping the AC-2 MCB at off position. The supply to
the AC-2 through this MCB will cut off and therefore the AC-2 will stop working.
Thus the alarm “AC-2 FAILS” will be generated.
21
Current Alarm Status: AC -2 FAILS = Active
“HIGH ROOM TEMPERATURE”
Alarm may be active if AC-2 facts on off for a long
time.
Step 2:
Activity for cleaning the alarm. By pushing the MCB switch to the on position of the
AC-2, the AC-2 will get supply and then it will short working. Thus the alarm “AC-2
FAILS” will be cleared off.
4. “AC FAILS”
Name : AC FAIL
Source : Microcontroller
Path : Microcontroller to - DDF - BTS - - BSC - OMC
Root Cause : When both the AC-1 and AC-2 fails to work due to some
issues or power off.
Causes : When
i) Both the MCBs are tripped down
ii) Supply from the PIU fails
iii) Mains supply and DG supply to both the AC fails
iv) DDF Panel Fault
v) Wire fault
22
Definition : When both the MCBs of both AC-1 and AC-2are tipped
down due to some issues or mains failure then this alarm
generates.
Generation of Alarm:
By tripping the MCBs of both AC-2 and AC-2 to the down position i.e. at the OFF
position, the power supply to both the AC through these MCBs will cut off. Thus the
both the AC will stop working and then alarm will be generated.
Step: 2 Activity for cleaning this alarm. By pushing up the switches of both the
MCBs of both the AC to the ON position, then both the AC will get supply and it
will start working. Therefore the generated alarm will get cleared.
23
Root Cause : Fuel level is less than 40% of the fuel tank capacity
of DG.
Causes : 1. Floating Cap Sensor fault
2. Fuel leakage
3. Wire from the sensor is shorted
Definitions : When the floating cap sensor inside the fuel tank is below
the 40% of the fuel tank capacity, alarm Generation of
alarm.
Step 1:
Activity for generating the alarm. By shorting the wire coming one from the fuel
tank, warm will generate.
Step 2:
Activity for clearing the shorted wire that is coming out from the fuel tank is opened,
then the alarm will be cleared.
24
6. “LLOP”
Definitions : When the lubricating oil pressure inside the lubrication oil
tank gets low alarm is generated.
Step 1:
Activity for generating the alarm. By shorting the wire coming out from the
lubricating oil tank of DG, then alarm will generate.
Step 2:
Activity for clearing the alarm. By opening the shorted wire coming out from the
lubricating oil tank of DG then the alarm will get cleared.
25
7. “MAINS FAIL”
Generation of Alarm
Step 1:
Activity for generating the alarm. By tripping down the MCB of the mains supply
then the power supply will get cut off. Then the alarm will generate.
Step 2:
Activity for clearing the alarm. By pashing-up the MCB of the mains supply then the
power supply will come back. Then the alarm will get cleared.
Current alarm status = No active alarm.
8. “SITE ON DG”
26
Path : AMF Panel - DDF - BTS - BSC - OMC
Root Cause : i) Mains MCB is OFF
ii) DG is ON
Generation of Alarm
Step 1:
Activity for generating the alarm. By switching OFF the mains MCB and the DG is
ON then this alarm will be generated.
Step 2:
Activity for clearing the alarm. By switching on the mains MCB and the DG is
switched Off then this alarm will be cleared.
9. “DG ON NO LOAD”
27
Causes : i) Main MCB is OFF
ii) DG MCB is ON
Generation of Alarm
Step 1:
Step 2:
28
Alarm Generation
Current Alarm Status = No Active Alarm
Step 1:
Step 2:
Alarm Generation
Current Alarm Status = No Active Alarm
29
Step 1:
Step 2:
Step 1:
30
Activity for generating the alarm.
By tripping down the main input MCB, all the supply to the PSUs will fail and thus
the alarm generates.
Step 2:
Generation of Alarm:
31
Step 1:
Step 2:
Alarm Generation:
32
Step 1:
Step 2:
Generation of Alarm:
33
Step 1:
Step 2:
Alarm Generation:
34
Step 1:
Step 2:
35
Chapter-4
All the Connections of Battery Bank and Power Plant with
Requirements, Procedure and
Quality Check Points.
There are the connections which are carried out from power plant:-
Requirements:
36
Fig4.1 Routing of Power Cable from BTS to P.P.
Procedure:
1. First of all remove outer insulation of power cable with cutter or knife and put
the both end in crimping tool with lugs and crimp it and add PVC tape on it.
2. Rate the cable from BTS front side to back side and use cable tie to hold it
with cabinet.
5. Route the cable with PVC channel and reached at the indoor cable tray.
37
6. Now route the cable with cable tray to power plant.
7. After cable tray ended route it through the PVC channel in the back side of
power plant now make a loop of 100 mm and the cable in power plant after
remove its insulation and joining lugs with it.
8. Connect the cable with bus bar inside the power plant and properly attached it
with bus bar with lugs.
38
proper distance.
4. Distance between two No Distance at cable rail
cable rail should be is not maintained at
equal throughout the height.
height
5. There should be a No No labeling is done.
proper labeling on the
cable
Requirements:
39
Fig 4.2 Routing of Power Cable from DCBB to power Plant bus bar
Procedure:
1. First of all remove the insulation of power cable with knife and joined it with
lugs.
2. Now lugs of 35 Sq.mm should be properly crimped with hex cramp and it is
joined with DCPB.
3. Route the cable with equipment body and hold it with cable tie.
4. Now before PVC channel make a loop of 100 mm and put cable on the PVC
channel.
40
5. Route the cable with cable tray and reached at the backside of TRSM rack
with PVC channel and put the cable inside the B&B and joined it with the bus
bar.
41
5. Power cable should be No Cable is not
routed straight & perpendicular to
perpendicular to ground.
ground in case of
cable rail.
Requirements:
Procedure:
1. First of all remove the insulation of power cable with knife or cutters.
2. Fit the inner care of wire inside the lugs and properly crimped it with hex
crimp of same size and fit it with IGB and used PVC top on it.
3. Now route the cable with equipment body and fit it with cable ties.
42
5. After that before PVC channel make a 100 mm loop and than fit the cable
with PVC channel.
6. After that route the cable with PVC channel and after that route it through
cable tray.
7. After the cable tray near the rack it should be down to connect with IGB.
Fig 4.3 Routing of Cable from DCBB to power Plant bus bar
43
S.No. Particulars Status Punch Points Remarks
1. There should not be No 1. There is gap as
any gap between outer proper hex
insulation of lugs crimping is not
used.
2. Power cable should be No No PVC channel is
routed through using used
either PVC channel or
cable rail.
3. Distance between two No Distance between
cable rail should not two cable rail is
be greater than that of more than that of
250 mm. 250 mm
4. Cable Tie should be No 1. Cable tie are not
properly use. used at proper
distance.
2. Cable tie are not
cut down by tie
cutters.
5. Some colour of PVC No Different colour
Tape used at both end. PVC tapes are used.
44
Connection for Positive terminals of battery to power plant bus bar.
Requirements:
Procedure:
2. Add lugs and properly crimped the lugs and add PVC tape on it of same
colour.
3. Connect this cable with proper way to battery bank positive terminal.
4. Other end of this cable should be properly attached with bus bar.
45
Fig 4.4 Routing of Cable from +ve terminal of the Battery to power Plant
bus bar
46
Fig 4.5 Connection Negative Terminal of battery to MCB of power plant.
Routing of Cable from +ve terminal of the Battery to power
Plant bus bar.
Requirements:
47
Procedure:
1. First of all remove the outer insulation of power cable and use pin type lugs to
insert the cable inside MCB.
2. Then routing of cable should be done according to need and tie it with cable
tie.
3. Now route the cable down to battery bank negative terminals and use ring
type lugs. This lug should be properly hex crimped.
5. After that labeling should be properly done we should use labeling with
permanent marker.
48
Quality Check Points:
49
Chapter-5
Complete Indoor Installation
Indoor Installation:
These are the requirements which is used to indoor installation. In which the most
important part is TRSM rack and BTS Equipment and I/DCT, I4B and Battery Bank
is optional.
50
1. DDF
DDF stands for Digital Distribution Frame which is installed in transmission rack. It
is of 19” length: It contains of back mount frame which is used to install it on the
transmission rack.
Backmount Frame
Bottom
View
Top
View
Bottom View
Side View
51
2. Transmission Rack:
Transmission rack is basically a cabinet in which indoor equipment like DCDB etc.
are installed. All equipment installed in transmission rack has the length of 19 inch or
we can say width is of 19”.
The equipment inside the transmission rack should have a distance of 50 mm. to
other equipment.
It contains of PVC sticks. All the routing of cables and connections of equipment are
done inside the TRSM rack.
There is a grounding bar inside the shelter which is used to ground all the equipment
inside the transmission rack.
52
We use cage nut with TRSM rack to fix it on the floor. Basically there and of steel.
After that it should be properly install.
3. 9 ID Cable Tray:
We use cable tray to hold the cable inside the shelter. Basically there are two pattern
we use in Indoor cable tray one is ‘H’ pattern and another one is O’ pattern.
4. Grounding Bar:
Grounding bar is used to ground all the equipment inside the shelter. It is connected
to EGB (External Grounding Bar). This EGB is connected to the earthing kit. It is
made up of capper and width is 19”.
53
5. Battery Bank:
Battery bank is made up of cell of 2 volt and give output of 48 Volt is absence of
mains and DOG.
6. Anchor Fastener:
Anchor fastener is basically bolt type accessories which is used to grouting the
TRSM rack with concrete floor.
Bolt
Expansion Unit
(Sleeve Port)
54
7. PVC Washer:
PVC washers are basically used Chile grouting when we dries to fix TRSM rack then
after drilling first we fix the PVC washer and than anchor fastener.
Floor
Anchor Fastener
PVC Washer
8. Cage Nut:
Cage nut is basically used with TRSM rack to fix the DCDB and grounding bar. It is
made up of steel. It consists of bolt which can be attached with DCBS and grounding
bar.
9. Marker Pen:
We use marker pen of black colour to mark the area where we need drive.
To measure the level of the rack with rest to the horizontal place or vertical place.
55
Tools Required:
1. First of all we should take a measurement of floor where we want to fit our
TRSM rack.
56
3. After that we start drill, for concrete floor we take B No. bit to drill.
4. Now we put the plinth on the mark and put anchor fastener inside it
temporarily.
5. After that we put out anchor fastener and put PVC washer before anchor
fastener and fix it.
6. We use torque wrench to fix the anchor fastener but before it we will use sprit
level to check its position.
7. Now we have done fixing of plinth of rack and we put the TRSM rack on it
and fix cage nut on it.
8. Now we fix this TRSM rack on plinth and tightened its bolt with torque
wrench to 45 N-M.
57
distance maintaining.
3. Levelling of TRSM No 1. The level of
rack should be proper. TRSM rack is
not proper as one
side is raise high.
4. PVC washer should be No No use of PVC
used to align anchor washer is carried
fastener. out.
5. Torque wrench should No Anchor fasteners are
be use to tightened not tightened by
anchor fastener. torque wrench.
6. The equipment in the No DCDB have more
TRSM rack should than 50 mm
have a distance of 50 distance.
mm
7. Grounding bar is side No Grounding bar is of
the TRSM rack should 7”
be of 9”
8. Cage nut of TRSM No Cage nuts are loose,
Rack should be not properly
properly tightened tightened.
9. We should use four No No anchor fastener
anchor fastener for is used on the left
four different sides. top side.
10. Grounding bar of No Grounding is not
TRSM should be proper.
connected to IGB.
11. Battery bar X should No B.B. is not properly
be properly install. connected to SMPS.
12. There should be a No Bakelite is not used
58
Bakelite part with with IGB.
IGB.
13. Indoor cable tray must No It is loose not
be properly installed. properly connected
with bolts.
59
Chapter- 6 Outdoor Installation
Work Execution:
To execute the work of outdoor installation, we have to work according
to given RF Plan. There are the work which we have to done during
installation of antenna line:-
I. Antenna Assembling:
After assembling of clamp we arrange the Tilt for antenna according to RF Plan.
Mostly we use electrical tilt which is from O0 to 100.
60
For electrical tilt we have a knob (in case of Katherine) Hook (Andrew) Mostly we
used two lamp for proper assembling. All the work of clamp assembling and lilt
arrangement should be on ground.
On the port of panel antenna we connect the connector of jumper cable. These cable
have connectors of 7/8” Mall and 7/8” Female for connection. After that we connect
the cable to antenna port. These connections should be tool tight. After tightening the
connection we use weathering proofing Kit at the connection of jumper cable to
panel antenna.
The jumper cable have its open female port in other end. These open female port
should be covered by temporary sealing of polybags etc. we use temporary sealing to
protect the cable from sudden rain at the time of installing we make a circle of
pumper cable to prevent it from damage and we use two cable tie at this place. Fig
6.2 Jumper Cable Assembeling
Cable Tie
61
RF Cable Measurement:
Mostly at the sites the feeder cable we got in the form of bundle and in the bundle we
got to know that the cable we receive is of proper length. For length measurement the
permanent labels are percent on feeder cable which shows the length of cable.
We cut the cable according to RF plan let we need a cable of 47.5 meter we cut it by
the help of Andrew cutter or feeder cutter. After cutting of cable we should use
temporary sealing at every end of cable to present it from sudden rain or water etc.
for the duration of installation.
62
III. RF Clamp Assembling:
We use RF clamp to hold the feeder cable with cable tray. The cable tray may be
vertical or horizontal. At vertical cable tray the distance between two RF clamp
should be I to 1.5 meter and in horizontal cable tray we should maintain a distance of
0.6 to 9.
Let we are maintain a distance of 1 meter with VCT and O.8 meter at HCT.
The RF clamp should not be properly tight until we pass cable through it.
There should not be Zig-Zag routing for cable.
Tx Rx
III-Sector I-Sector
II-Sector II-Sector
C-Clamp
63
IV. Sector Selection:
We got RF Plan in which we see that we have to install panel antenna according to
sector given to it. To know the sector we have to use mirror compass and after that
we should see the position of sectors.
N
III-Sector I-Sector
45°
200°
300°
II-Sector
V. Antenna Hanging:
Before antenna hanging we write all the configuration by permanent marker on the
backside of antenna.
Now we have to use rope and pull or geared machine to carry the antenna from
ground to tower. We fit a pulley on a height of tower which is about 3 to 5 meter
more than the height of panel antenna. Now we fit a rope on this pulley and slowly
64
pull the rope which have one end tied with antenna and other end is pulled to carry
the antenna at tower height.
But in carrying of antenna from ground to tower we should be careful that antenna
should not be touched with tower body.
65
VI. Routing of RF Cable:
For routing of RF cable we should route the cable from to P to bottom. We should
route only two cables at same time rest cable should be in bend like structure.
According to the clamp we should open the feeder cable, we should not open the hole
band of cable in one time.
After putting the RF cable in the RF-clamp we should not tight RF clamp properly
because we may need more cable in the bottom.
Routing of RF cable should be through the Roxtec and using 2-band inside the
shelter.
The routing of cable should not be in Zig-Zag Way. It should be according to sector.
VII. RF Connectorization:
66
RF connectorization is the process in which we fit the connector in the RF cable.
For connectorization we should have male and female connector according to our
need.
For fitting the connector we should remove the outer insulation of Rf cable to ½ 11
and then fit connector on it. We remove the outer insulation by the help of 32”
spanner.
To assemble the earthing kit at feeder cable we have to remove the outer insulation of
feeder cable and then we should apply the cu-strip of earthing kit and after that we
close that connection by the help of weather proofing kit.
Earthing Kit should be use at 1 to 1.5 meter jumper feeder connection and should be
terminated with EGB or Tower body.
To terminated with tower body we have to remove the outer paint of tower with
scrubber and then we should terminate it.
67
For one cable we should use minimum two earthing kit and maximum according to
height of antenna.
Earthing kit
assembled on RF
Cable
68
IX. Dummy Clamp:
We should use dummy damp at bending point of feeder cable from VCT to HCT.
The dummy clamp is used according to feeder cable if no of feeder cable is size, then
we should use six dummy clamps.
X. Cable Tie:
We should use cable tie according to need at outdoor we mostly used 10” cable tie,
these cable tie are mostly of black colour.
In case of Indoor we must use cable tie of 6” size. The colour of tie in case of indoor
is black & white.
We should maintain a distance of 250-300 mm between two cable tie. The cable tie
should not be loss.
To entry of feeder cable any type of cable we use Roxtec. The cable pass through it
and we should connect the cable to surge arrestor. The connections should be hand
tight. There we do not need any weather proofing kit. We should properly connect
the surge arrestor to IGB by the help of 416 sq. mm grounding cable.
69
XII. Labeling:
Labeling is the most important part of installation we should use temporary labeling
as well as permanent labeling to know the cable location and which sector it is using
for.
70
Except this labeling we also use temporary labeling for particular sector according to
tx and rx sections.
After complete installation of site the site should be clean of unused accessories.
These any be cable insulations and nut and bolt, unused cable ties, cutting piece of
cable tie, cutting of cables etc. we should clean it as the person who visit at site
should not be disturbs by it.
The things which can be use should dismantlize and should send the warehouse.
71
Chapter-7
All the Indoor Grounding Connections of Site.
1-EGB
35 sq.mm.
Yellow-Green
Grounding Cable
1. BTS grounding
2. Cable Tray Grounding
3. TRSM rack grounding
4. DDF grounding
5. Battery Bank / P.P. Grounding
6. PIU Grounding
7. IGB Connection with EGB
8. Surge Arrester Connection with IGB
72
1. BTS Grounding:
Requirement:
1.
S.No. Particulars Specifications Quantity Remarks
1. Power Cable 35 Sq. mm Y-Green 2.5 meter
2. Lags Ur, Ring Type Size 2
35 Sq.mm
3. PVC Tape Green 1 Packet
4. Labels Transparent 1 Packet
5. PVC Channel 40x40x 650 mm 1
6. Screw ½ “, Full Threaded 3
7. Cable Tie 9/D, 6” 1 Packet
73
Procedure:
1. First of all remove the insulation of power cable by knife or cutter and put it
in the lugs.
2. Now crimp the lugs with hex crimp of 35 Sq. mm. crimping tool (small duty).
3. Apply PVC tape to cover it properly and use hot air gun to properly stickness.
4. Now fixing this lugs with grounding bar of BTS and route it through
equipment body.
6. Now in the back side of BTS make a loop of 100 mm and attach the lable
with PVC channel.
7. After routing of PVC channel cable reached at cable tray now route it through
cable tray and after that it is terminated with IGB with a loop of 100 mm.
74
than that of 100 mm
loop
3. Routing of Cable with No Routing of cable is
PVC channel should in Zig-Zag way.
be in perpendicular
direction.
4. Cable tie should be No 1. Distance
used properly. between cable
ties are not
followed
throughout
2. Knot of cable
ties are in the
down direction.
5. Proper labeling should No 1. No. labeling is
be done. done.
75
2. Cable Tray Grounding:
Requirement:
1.
S.No. Particulars Specifications Quantity Remarks
1. Power Cable 35 Sq. mm X-Green 9 meter
2. Lags Ur, 35 sq. mm. Ring 14
Type
3. Cable Ties 9/D 6” 1 Packet
4. PVC Tape Green Colour 1 Packet
5. Labels Transparant Tape 1 Packet
76
Procedure:
1. First of all cut the cable in 7 pieces in which six of 100 mm. and rest one is of
300 mm.
2. Remove the insulation of all cables and fit ring type lugs in it.
4. Now one piece of 300 mm. joined with IGB and cable pay as both ends
should be properly attached.
5. Now the second part of 100 mm. of cable is attached where the joint of cable
tray is present.
6. Now all the cables are done in proper manner where the joint is present.
7. Now labeling of the cable on the IGB is done by the keep of transparent tape.
77
4. Extra parts of Cable No No extra part of
tie should be cut cable tie is cut down
down.
5. Size of lugs should be No Size of lugs is more
according to size of than that of Size of
cables cable
Requirements:
1.
S.No. Particulars Specifications Quantity Remarks
1. Power Cable Cu, 35 Sq. mm 3.9 Meter
2. Lags U or Ring Type 35 2
Sq. mm
3. Cable Channel 40x 40 x 650 1
4. Screw ½”, Full Threaded 3
5. PVC Tape Green Colour 1
6. Labels Transparent Tape 1 Packet
7. Cable Tie I/D, 6” 1 Packet
78
Fig 7.4 TRSM Rack Grounding
Procedure:
1. First of all remove the insulation of wire by knife or cutter and then add lugs
in it.
2. Properly use PVC tape to cover the connection of lugs with cable.
3. Now put the cable in the grounding bar of TRSM rack and route it through
TRSM rack side and hold it properly with cable ties.
4. Now making a 100 mm. loop and put the cable of PVC Channel.
5. After routing with PVC channel the cable reached at cable tray and it should
be properly hold by cable ties.
6. After that the cable should be terminated with IGB by 100 mm. loop and lugs
should be properly attached.
79
S.No. Particulars Status Punch Points Remarks
1. Proper use of cable tie No 1. Cable ties are
should be done at different
distances
2. Lugs should be No 1. A part of
properly crimped cable is using
out from
lugs.
2. Lugs are
loose
3. These should be 100 No No loop is formed
mm loop before before IGB.
termination with IGB
4. Distance of Cable tie No No pattern is
should be equal followed for
throughout the cable distance.
tray
4. DDF Grounding:
Requirements:
80
3. PVC Tape Green Colour 1
4. Labels Transparent Tape 1 Packet
5. Cable Tie 6” Indoor 1 Packet
Procedure:
81
6. Route the cable through PVC Channel.
7. After that route the cable through cable tray and it should be properly tie with
cable tie.
8. After that cable should be terminated to IGB and before termination these
should be a 100 mm. loop.
82
5. Battery Bank and Power Plant Grounding:
Requirements:
Procedure:
83
1. First of all remove outer insulation of cable by knife or cutters and then add
lugs on it.
84
6. PIU Grounding:
Requirements:
Procedure:
85
1. First of all remove the outer insulation of cable and fit the lugs and properly
hex crimped.
2. Now cable should be routed through the equipment and tie with PVC channel
and these should be of 100 mm PVC channel.
4. After that cable tray cable should be routed to IGB and before IGB these
should be 100 mm. loop.
86
5. These should be a 100 No. No loop is used.
mm loop before IGB
Procedure:
87
3. From bottom portion of surge arrester the cable should be joined and properly
fit and terminate to IGB.
4. These should be a 100 m loop before IGB and after surge arrester.
8. IGB to EGB:
Requirements:
88
2. Lugs Cu Ring Type 2
3. PVC Tape Green 1
4. Labels Transparent Tape 1 Packet
5. Cable Tie 6” I/D 1 Packet
Procedure:
1. First of all remove insulation of cable by cutter or knife.
2. Adjust lugs with it of 35 sq. mm and properly hex crimped.
3. After that the lugs should be properly tighten with IGB and make a loop of
about 1 meter through Roxtec and terminate with EGB.
89
Chapter-8 Site Analyzer
1. Dummy Load
2. ½” F – 7/8” F – Adapter
3. ½” M - 7/8” F Adapter
4. ½” F – 7/8”M Adapter
5. Site analyzer software
6. Data cable (D-9 RS 232 serial straight cable)
7. Calibration Kit
8. Element 50W, 5W
90
Procedure to Operate:
1. Put ‘ON’ the site analyzer by pressing the ‘ON’ button. The display will be
on.
2. After few second the display goes to any one mode in which it previously
operated
3. To change mode press mode button and screen changes to made, here three
modes:
4. To measure VSWR just set the measurement with selection button of its front
side.
5. After that screen changes to measure match
6. Now press the configuration button and select change frequency by selection
button after that screen will change.
7. After that process arrow to fill upper limit of frequency it should be 960
MHZ.
8. Press escape button and screen changes to measure match.
9. Now we see at the bottom of the display the calibration is OFF. We have to
calibrate to get the reading is a proper manner.
10. Now we press calibration button from the functions and screen changes to it
11. Now we connect open calibration kit and from selection open it after few
second it shows that open calibration done.
12. Now we connect short calibration kit and select it from the selection key,
after few second it also calibrated.
13. Now we connect dummy load on RF Port and press load after few second it
shows that calibration is done.
91
14. We see that now calibration is full.
15. Now we press configuration button and select scale.
16. After select scale for VSWR readings.
17. Now we can take VSWR readings.
18. To take VSWR readings press marker button from the function and press
enter.
19. Press marker-1 and On it from selection keys after that we see the readings of
VSWR.
Fault Localization
92
Chapter -9 Conclusion
Now a days telecom is a growing field as everywhere the project of 4G installation
and 3G installation is coming and work of installation and commissioning is in the
full swing. Whenever a company install a site at any place they required engineers
who can work their and should know the basics of telecom engineering and should
know how to work on the equipment. After undergo training for the telecom field I
would be aware of the field and the things related to it. That was a platform where I
learn that how to commission and integrate the equipment and learn many things and
co-ordination with team. Really it was very helpful, After undergo training I would
be able to installation of RF equipment with commissioning and alignment of
microwave equipment and integration and testing of cell site.
Future Scope:
If we talk about future scope of telecom field ,it relly have great opportunities and
now days every things is depend on internet. In every business we are using mobile
phone and at evry aspect of life we require a source of communication for that
communication we need cell sie so installation is in full swing. If we talk about the
scenario of india in telecom. Installation of 4G just stared and the engineer who is
able to work at the 3G can easily work on 4G .
Recently in Delhi Reliacnce Jio stared their project of 4G and they require about
6000 engineer in delhi location.
93
REFERENCES
Book Code Title Year Author
STRATEGIES FOR
SUCCESS IN THE
ISBN1580531423 NEW 2000 KAREN STROUSE
TELECOMMUNICATI
ONS MARKET
THE
ISBN0849385733 COMMUNICATIONS 1996 GIBSON.E.
HANDBOOK
OPTICAL FIBER
ISBN0123951690 TELECOMMUNICATI 1997 KAMINOW I.P.
ONS III
GSM SYSTEM
ISBN0890068607 1997 A. MEHRORTA
ENGINEERING,
GLOBAL
CONNECTIONS:INT'L
ISBN0442023626 1997 R.VAN NOSTRA
TELECOM &
INFRASTR.
NETIZENS: ON THE
ISBN0818677066 HISTORY AND 1997 HAUBEN
IMPACT OF USENE
INTERCONNECTION
ISBN0818678003 NETWORKS: AN 1997 DUATO
ENGINEERING APP
PHYSICAL LEVEL
ISBN0818656972 INTERFACES AND 1995 BLACK
PROTOCOLS 2D ED
PRACTICAL
CRYPTOGRAPHY FOR
ISBN0818671408 1996 STALLING
DATA
INTERNETWORKS
TELECOMM
NETWORK
ISBN0780310136 1995 AIDAROUS
MANAGEMENT INTO
THE 21ST CEN
NETWORK AND
ISBN0780311078 INTERNETWORK 1995 STALLINGS
SECURITY
ENGINEERING
NETWORKS FOR
ISBN0780311582 1997 BHATNAGER
SYNCHRONIZATION,
CCS
94
95