BCD4-000-43-SPC-4-091-00 - rev0-REC Painting & Galvanizing
BCD4-000-43-SPC-4-091-00 - rev0-REC Painting & Galvanizing
Specification
Painting and Galvanizing
Table of Contents
Section Title Page
1.0 PURPOSE
The purpose of this specification is to define the minimum technical requirements for
the surface preparation, painting, galvanising and coating system to be used for plant
equipment, piping and steel structures located onshore and offshore for Betara
Complex Development Project Phase 4 (BCD4) Project of PetroChina International
Jabung Ltd (PCI) in Jambi, Indonesia.
Indonesian Law
Statutory Regulations
3.0 DESIGN
This specification covers both shop and site and defines minimum requirements for
surface preparation, coating systems, coating system application and inspection for
equipment, piping and structures.
Where the paint manufacture’s surface preparation specification is less stringent than
this specification, the paint manufacturer’s recommendation take precedence, but
only with written approval from Company
Substitutions or modifications of any item, material or detail shall be made only upon
written approval of Company.
The material supplied shall be of a standard model or series in regular production at
Manufacture’s facilities.
Company has the right to stop blasting and painting operations when, in Company’s
opinion, weather conditions are not deemed suitable for such operations.
Copper slag may be reused a maximum of two times and only if it meets the other
requirements of this Specification, and if a representative grit sample of 200 gms is
sieved and meets grit size G-14.
Extreme care shall be exercised to prevent damage when blasting near flange faces,
valve stems, coated bolts and nuts, control panel, instrument valves, nameplates,
machined surfaces and factory coated items. These surfaces shall be protected
during blasting and coating operations.
3.2 Application
The protective coatings shall be thoroughly mixed applied in strict accordance with
SSPC and the Paint Manufacturer’s instructions over clean, properly prepared
surfaces.
All carbon steel surfaces shall be primed and finish painted in accordance with this
specification and the paint manufacturer’s written instructions.
Joints may be primed prior to leak testing unless sensitive leak test describe in ASME
B31.3 is required.
A minimum of 12 mm around the edge of blasted areas shall be left uncoated unless
adjoining a newly coated surface. Blasting shall continue to a minimum of 1” into
adjoining coated surfaces.
Structural members designed in such a manner as to contain a field splice by welding
shall not be coated in the splice area prior to splicing for a distance of 4”. This area
shall be included in the blasting operation but shall be properly masked-off prior to
application of coating. Masking shall remain on members to protect the splice area
from rust and other contamination until the field splice is made. After the weld is
made and cleaned, coating shall be applied in accordance with this Specification.
Surface imperfections such as slag, arc strikes, weld splatter, porosity, sharp edges,
pits, laminations, slivers or crevices shall be removed or repaired prior to coating.
Any areas where grinding is required after blasting shall be blast cleaned by
CONTRACTOR to obtain the required surface pattern.
In areas inaccessible to blasting and painting, seal plates 1/8” thick shall be added
and seal welded all around. These plates shall receive the full coating system. Areas
that cannot be boxed in shall, subject to approval by Company, be filled with epoxy
mastic, caulking compound or other suitable filler to prevent retention of dirt and
moisture. These areas include deck penetrations.
All landing surfaces for gratings shall be completely coated to the finish coat prior to
fixing. All landing surfaces of equipment, pipe-spools, support brackets, flange faces,
bolt holes and areas under “U” bolts are to be coated with the applicable paint system
before installation.
Inorganic zinc primers exposed for prolonged periods shall have white stains and
zinc corrosion products removed by using manufacture recommended procedure
prior to applying top coating. Following such washing, surfaces should be completely
dry prior to applying the top coat.
In all cases where the second or third coats were applied more than three days
previously and have to be over-coated, the surfaces shall be lightly abraded or
solvent wiped to ensure good inter-coat adhesion between these coatings. Method of
preparing a coated surface include light whip blasting or power disc sanding and
washing with solvent recommended by the Manufacturer.
Only experienced industrial painters shall be used.
3.5 Repairs
The edges of undamaged coating shall be feathered to a minimum of 2 inches from
the damaged area.
All exposed bare steel surfaces shall be prepared in accordance with Section 3.1 of
this Specification.
Immediately after completion of surface preparation, the repair area shall be primed
in accordance with one of the repair systems in Attachment 4.
The repair coating primer shall overlap the adjacent undamaged coating by a
minimum of 2 inches
Damaged areas requiring repair of intermediate and finish coats shall be cleaned per
Section 3.1 of this specification. Undamaged coating edges around the damaged
area shall be feathered to a smooth finish.
Touch-up painting shall be conducted at least weekly. Any item remaining uncoated
in the structure or piping system shall be removed and coated at CONTRACTOR’s
expense.
Yellow (Non-skid)
Yellow
White*
* Note : Underwater installation aids shall be painted white per a paint system
approved by Company.
3.14 Documentation
For each different coating system, prior to any surface preparation and coating
operation commencement, a complete surface preparation and painting procedure
shall be prepared for submission to and acceptance from PCI
Colour chart shall be included with the procedure.
4.0 MATERIAL
All coating system materials shall be as nominated in attachment 2 and 3, except
offshore steel structure that should follow attachment 5.
5.0 MANUFACTURING
Any specific additional requirements shall be stated on the attachments.
Two, 1 inch x 1 inch U.S. Standard gage 10 panels abrasive blasted to the degree
specified and sealed between Plexiglas shall be prepared for Company’s
acceptance.
The blast profile depth shall be checked using either a calibrated Elcometer
roughness gauge or a Keane -Tator profile comparator.
The sand blasted surface, primer coat, intermediate coat, and final coat shall be
examined for dirt and dust prior to application of additional coats.
After each coat has been applied and cured, the coating adhesion shall be tested in
accordance with ASTM D-3363. Where the coating adhesion does not meet the
specification, the entire surface shall be re-blasted, and coated again.
After all the repairs have been made, the cured coating shall be tested and the film
thickness measured, with a dry film thickness gauge, in accordance with SSPC-PA-2.
The readings shall be taken at the rate of one thickness reading, minimum, for every
10 square feet of surface shall be taken randomly. The reading and the reading
location shall be recorded in a log. The finished cured coating shall be free or dust or
dirt at the time the reading is made. A clean rag should be used to clean coating
prior to thickness reading. A reading shall also be recorded on the final finished
cured coating DFT. The final coating system total DFT record shall be in chalk and
shall be written at the reading location. Where the actual coating thickness is more
than 3 mills below the specified DFT, the coating will be rejected and shall be
repaired.
After the coating application has been completed, the entire assembly shall be
visually inspected. Where any of the following defects are discovered, they shall be
repaired or replaced:
• Gauge glasses, instruments, machined surfaces, flange faces, nameplates, etc.
shall be examined for damage caused by metal surface cleaning or coating
application
• Tightly spaced and cramped areas shall be examined for improper coating
thickness and coverage
• The entire assembly shall be examined for damaged areas in coating caused by
shop handling of the assembly.
As a minimum, following quality control tools shall be maintained.
• Wet film thickness gauges – shall be carried by all painters
• Dry film thickness gauge
• Keane -Tator Comparator
The dry film thickness of each individual coat and the total system shall be checked
by magnetic thickness gauge. This shall be calibrated as a minimum twice daily,
using foils in the thickness range being measured and a steel plate with a surface
representative of that being achieved in practice.
All records of inspection and testing of material supplied by CONTRACTOR and all
manufacturer material certificates shall be submitted to PCI.
PCI shall be permitted to test the coating and any repairs subsequently made to it, in
compliance with this Specification. CONTRACTOR shall repair such tests and other
defects in the coating at no extra compensation.
CONTRACTOR shall perform all testing required to ensure compliance with this
Specification at its cost.
CONTRACTOR shall have adequate inspection tools available on site for inspection
purposes. These tools shall include:
• Visual Standard
• Dry Paint Thickness Gauges
1. Elcometer Pull Off Gauge
2. Elcometer Thickness Gauges
• Surface Profile
1. Gauge No. 123 (Elcometer)
2. Keane Tator Gauges
3. Testing Press on film tape
• Abrasives
Set of sieves to ASTM E11
8.0 ATTACHMENT
ATTACHMENT-1: RECOMMENDED PAINTING SYSTEMS FOR ONSHORE
FACILITIES
ATTACHMENT-2: GUIDE FOR SELECTION OF PAINT SYSTEMS
ATTACHMENT-3: RECOMMENDED PAINTS BRANDS
ATTACHMENTS
ATTACHMENT 1 – RECOMMENDED PAINTING SYSTEMS FOR ONSHORE FACILITIES
PAINT SERVICE SURFACE SURFACE COATING DESIGNATION TOTAL PAINT
TEMPERATURE PREPARARION (REFERENCE TABLE 2) DRY FILM SYSTEM
RANGE (SEE NOTE 3) THICKNESS
PRIMER FIRST COAT FINISH COAT
All exterior carbon steel surfaces including vessels, piping, valves, exchangers, all ‐25oF to 200oF Abrasive Blast PA T1 T2 10 Mils 1
structural steel, base plates, skid bases, platforms, ladders, hand rails and exterior to SSPC‐SP‐10
surfaces of all carbon steel tanks.
All exterior carbon steel surfaces including vessels, piping, valves, exchangers, 201oF to 750oF Abrasive Blast to PB ‐‐‐‐ T3 5 mils 2
SSPC‐SP‐10 (2 coats)
o o
All exterior carbon steel surfaces for Rotating Equipment 200 F to 375 F Abrasive Blast to PB ‐‐‐‐ T3A 5 mils 2A
SSPC‐SP‐10 (2 coats)
All exterior high temperature carbon steel surfaces. 751oF to 1,000oF Abrasive Blast to PC ‐‐‐‐ ‐‐‐‐ 2 Mils 3
SSPC‐SP‐10 (2 coats)
All insulated carbon steel surfaces ‐45oF to 750oF Abrasive Blast to PB ‐‐‐‐ ‐‐‐‐ 3 Mils 4
SSPC‐SP‐10
All insulated carbon steel surfaces 751oF to 1,000oF Abrasive Blast PC ‐‐‐‐ ‐‐‐‐ 2 Mils 5
to (2 coats)
SSPC‐SP‐10
Control panels located inside buildings 20oF to 120oF Abrasive Blast PF T2 T2 6 Mils 6
SSPC‐SP‐10
o o
Field Control Panels ‐25 F to 200 F Abrasive Blast to PA T1 T2 12 Mils 7
SSPC‐SP‐10 (2 coats)
Carbon steel surfaces immersed in fresh, salt or brakish water ‐25oF to 140oF Abrasive Blast to T‐5 ‐‐‐‐‐‐‐….. ‐….. 16 Mils 8
Interior of all carbon steel surfaces i.e. including roofs of tanks in fresh, salt and SSPC‐SP‐10 (2 coats)
brackish water surface, in case of no gas blanket system.
Interior of steel fuel tanks ‐25oF to 180oF Abrasive Blast All Interior Tank bottom and 400 MM up interior walls and Sides, above 9
to Surfaces fittings 400 mm 3 Mils
SSPC‐SP‐10 PI Bottom ‐ 9 Mils
Document – BCD4-000-43-SPC-4-091-00
Revision 0
PetroChina International Jabung Ltd. Specification
Painting and Galvanizing
Tank Bottom and 2 meters up interior Walls and Fittings
Abrasive Blast to
‐25oF to 180oF 11
Interior of steel crude, condensate tanks (See Note 1) SSPC‐SP‐10 PG ‐‐‐‐ T6 12 Mils
(2 coats)
2. The Company paint systems defined in Table 1 may be changed only if specifically recommended by the coating manufacturer in writing and only after Company approval of the coating manufacturer's
recommended alternative.
3. The surface preparation specified covers mechanical cleaning only. Regardless of what surface preparation is specified, all surface must first be solvent cleaned per SSPC‐SP‐1 and then washed with a water
miscible cleaning agent.
Document – BCD4-000-43-SPC-091-00
Revision 0
PetroChina International Jabung Ltd. Specification
Painting and Galvanizing
ATTACHMENT 2 – GUIDE FOR SELECTION OF PAINT SYSTEMS*
o o
PC Silicone aluminum 751 F to 1000 F Unpainted steel and iron surfaces 2 1.0 Mils Must Cure
2 Hours at 400oF
o o
PF Inhibitive epoxy primer ‐25 F to 200 F Unpainted steel and iron surfaces for interior used 1 2.0 Mils 8 Hours
o o
PG Non‐inhibitive epoxy primer ‐25 F to 200 F Tank interiors 1 2.0 Mils 8 Hours
o o
PH Catalyzed polyester resin primer ‐25 F to 180 F Tank interiors 1 2.0 Mils 8 Hours
o o
PI Water based, air cured, inorganic zinc silicate primer ‐25 F to 180 F Tank interiors 1 3.0 Mils 24 Hours
o o
PJ Heat resistant, zinc pigmented, silicon primer 200 F to 750 F Repair/maintenance primer for high surface 1 2.0 Mils 4 Hours
temperatures
Use only when specified
o o
T1 High build epoxy ‐25 F to 200 F Intermediate coat over inorganic zinc silicate 1 5 Mils 24 Hours
o o
T2 Aliphatic polyurethane ‐25 F to 200 F Top coat over high build epoxy 1 2 Mils 8 Hours
o o
T3 Silicone aluminum 201 F to 750 F Top coat over inorganic zinc silicate 2 1 Mil 12 Hours
Document – BCD4-000-43-SPC-091-00
Revision 0
PetroChina International Jabung Ltd. Specification
Painting and Galvanizing
o o
T8 High solids, amine cured epoxy ‐25 F to 200 F Interior of steel crude oil and condensate tanks 2 12 Mils 16 Hours
o o
T9 High solids, self priming epoxy 0 F to 200 F Maintenance and coating repair 1 6 Mils 8 Hours
o o
T10 Epoxy aluminum mastic 0 F to 200 F Maintenance and coating repair (piping and 1 5 Mils 8 Hours
flowlines)
Document – BCD4-000-43-SPC-091-00
Revision 0
PetroChina International Jabung Ltd. Specification
Painting and Galvanizing
ATTACHMENT 3 – RECOMMENDED PAINTS BRANDS
PAINTING
GENERIC ICI DIMET HEMPELS CEILCOTE DNT CHUGOKU SIGMAKALON CARBOLINE
DESCRIPTION
DESIGNATION
PA Inorganic zinc silicate Zinc Galv 6 Dimetcote 9 FT Galvosil 15780 Polyzinc 200 Zettar OL‐HB Galbon S‐HB 7558 Sigma Tornusil MC 58 Carbozinc 12
PB Inorganic zinc silicate Zinc Galv 6 Dimetcote 9 FT Galvosil 15700 Polyzinc 200 Zettar OL‐HB Galbon S‐HB 7558 Sigma Tornusil MC 58 Carbozinc 12
PC Silicone aluminum Hi‐Heat Silicone Amercoat 878 Silicone Aluminum 56910 Ceilcote 870 Pyrosin B #1000 Silicon #400 Silver 7567 Sigmatherm Super Thermaline 4631
Thermovit
PD Zinc rich organic epoxy Zinc Rich Epoxy Amercoat 68 A Zinc Primer 15360 Polyzinc 100 Zettar EP 2 HB Epicon Zinc HB‐2 7702 Sigmacover HS Zinc Carbozinc 658
Primer
PE Universal primer ‐‐‐‐ Amercoat 185 Hempels Primer 15300 Ceilcote 934 ‐‐‐‐ ‐‐‐‐ 7413 Sigmacover Primer Carbomastic 15
PF Inhibitive epoxy primer Epoxy Metal Primer‐Two Pack Amercoat 71 Hempadur 15300 Ceilcote 671 Eponic #90 U/C ‐‐‐‐ 7413 Sigmacover Primer Carboguard 893SG
PI Water based, air cured, ‐‐‐‐ Dimetco 4 Galvosil 15700 ‐‐‐‐ ‐‐‐‐ Galbon L 7551 Sigma Silguard MC Phenoline 1205
inorganic zinc silicate
primer
PJ Heat resistant, zinc ‐‐‐‐ ‐‐‐‐ Silicone zinc 16900 ‐‐‐‐ Pyrosin LL #600 ‐‐‐‐ 7566 Sigmatherm Super Thermaline 4631
pigmented silicone Thermovit Primer
primer
PTC Epoxy tie coat Epoxy Tie‐Coat‐Two Pack Amercoat 182 Shopprimer E15280 Ceilcote 671 Eponic #35 ‐‐‐‐ 7420 Sigmarite Sealer Carboguard 190HB
T1 High build epoxy Epoxy Bildcote Amercoat 383 HS Hempadur Hi‐build Ceilcote 650 HB Eponic #20 Epicon arine 6821 Sigmacover EP Carboguard 190HB
45230 Undercoat HB Primer/Built Coat
7456 Sigmacover CM
Coating
T2 Aliphatic polyurethane Polyurethane Acrylic Amercoat 450 GL Hemphethane 55210 Ceilcote 480 V Top H ‐‐‐‐ 7528 Sigmadur Gloss Carbothane 134
T3 Silicon aluminum Hi‐Heat Silicone Amercoat 878 Silicone Aluminum 56910 Ceilcote 870 Pyrosin B 1000 ‐‐‐‐ 7563 Sigmatherm Siloxane Thermaline 4631
T3A Silicon resin ‐‐‐‐ ‐‐‐‐ ‐‐‐‐ ‐‐‐‐ Pyrosin B#850C ‐‐‐‐ ‐‐‐‐ Thermaline 4674
Document – BCD4-000-43-SPC-091-00
Revision 0
PetroChina International Jabung Ltd. Specification
Painting and Galvanizing
PAINTING
GENERIC ICI DIMET HEMPELS CEILCOTE DNT CHUGOKU SIGMAKALON CARBOLINE
DESCRIPTION
DESIGNATION
T5 Coal tar epoxy Coal Tar Epoxy‐Two Pack Amercoat 78 HB Hempadur 151305 Ceilcote 660 SDC Coat 402T Biscom HB 7472 Sigma TCN 300 Bitumastic 300M
T6 High build epoxy tank Hi‐Build Tank Coating System Amercoat 66 Hempadur 15400 Ceilcote 650 HB Eponic #35 T/C Epicon T‐500 7433 Sigmaguard EHB Phenoline 1205
lining Two Pack Undercoat
T7 Polyester glass flake ‐‐‐‐ ‐‐‐‐ Polyester GF 35920 Ceilcote 251/252 ML‐3000 ‐‐‐‐ 7447 Sigmacover TCP Carboguard 1209
tank lining Glassflake
T8 High solids, amine cured ‐‐‐‐ Amercoat 395 Hempadur 1540 ‐‐‐‐ Eponic #35 T/C ‐‐‐‐ 7433 Sigmaguard EHB Phenoline 1205
epoxy
T9 High solids, self priming ‐‐‐‐ Amerlock 400 Hempadur Mastic ‐‐‐‐ Eponic #35 U/C ‐‐‐‐ 7430 Sigma Multimastic Carboguard 190HB
epoxy 455880
T10 Epoxy Aluminum mastic ‐‐‐‐ Amercoat 390 Hempadur Mastic ‐‐‐‐ Eponics Al ‐‐‐‐ 7430 Sigma Multimastic Carbomastic 15
455880
Document – BCD4-000-43-SPC-091-00
Revision 0
PetroChina International Jabung Ltd. Specification
Painting and Galvanizing
ATTACHMENT 4 ‐ MAINTENANCE PAINTING SYSTEMS
Document – BCD4-000-43-SPC-091-00
Revision 0
PetroChina International Jabung Ltd. Specification
Painting and Galvanizing
Document – BCD4-000-43-SPC-091-00
Revision 0