7K-L, Second & Third Floor, Jalan Ban Hock, 93100, Kuching, Sarawak. Tel: +6082 7877 123 Fax: +6082 7877 234 Method Statement

This document outlines the method statement for installing reinforcement bars, formwork, pouring concrete, and removing formwork for columns and beams. For columns, the work will be done in 4 steps over 15 days total using materials like rebar, tie wire, nails and plywood. Each step will utilize semi-skilled laborers and takes 8 hours a day to complete. For beams, the same 4 steps will be completed over 10 days total, utilizing more semi-skilled laborers due to the larger number of beams.

Uploaded by

madina
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
45 views

7K-L, Second & Third Floor, Jalan Ban Hock, 93100, Kuching, Sarawak. Tel: +6082 7877 123 Fax: +6082 7877 234 Method Statement

This document outlines the method statement for installing reinforcement bars, formwork, pouring concrete, and removing formwork for columns and beams. For columns, the work will be done in 4 steps over 15 days total using materials like rebar, tie wire, nails and plywood. Each step will utilize semi-skilled laborers and takes 8 hours a day to complete. For beams, the same 4 steps will be completed over 10 days total, utilizing more semi-skilled laborers due to the larger number of beams.

Uploaded by

madina
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

7K-L, Second & Third Floor,

Jalan Ban Hock,


93100, Kuching, Sarawak.
[email protected]
Tel: +6082 7877 123
Fax: +6082 7877 234
METHOD STATEMENT

NO. OPERATIO QT METHOD DIAGRAM MENPOW PLANT/M OUTPUT DURAT MATERIALS


N Y ER ACHINER ION/DA
IES YS
COLUMN

1. Installing 150 Install the reinforcement bar as per  2 semi- Bar cutter 8hrs/day 10 days Rebar
reinforcemen approved drawing. skilled Bar bender @15set/d Tie wire
t bar labours ay
Hammer
Measuring
tape

2. Installing 150 Before erecting the shutters, box  2 semi-  Hammer 8hrs/day 10 days Nail
formwork out and cast in items will be skilled  Measuring @15 Plywood
installed. Formwork are installed to labours tape set/day
its dimension correctly. The shutters
will be braced and anchorages
properly as per the drawing. For
proper alignment, tie rods shall be
used.
7K-L, Second & Third Floor,
Jalan Ban Hock,
93100, Kuching, Sarawak.
[email protected]
Tel: +6082 7877 123
Fax: +6082 7877 234
METHOD STATEMENT

NO. OPERATION QT METHOD DIAGRAM MENPOW PLANT/M OUTPUT DURAT MATERIALS


Y ER ACHINER ION/DA
IES YS
3. Pouring 150 The concrete shall be thoroughly 2 Semi Vibrator 8hrs/day 15 days  Ready Made
concrete and compacted during and immediately Skilled Mixer @10pcs/d Concrete
curing after depositing. For better Worker ays
performance while operating.
Vibrators for each pump operating
must be presented. Curing shall be
started immediately after initial set
of concrete and finishing.

4. Removal of 150 The formwork is removed when the 2 General 8hrs/day 10 days
formwork concrete has gain sufficient Labour @15pcs/d
strength ays
7K-L, Second & Third Floor,
Jalan Ban Hock,
93100, Kuching, Sarawak.
[email protected]
Tel: +6082 7877 123
Fax: +6082 7877 234
METHOD STATEMENT

NO. OPERATION QT METHOD DIAGRAM MENPOW PLANT/M OUTPUT DURAT MATERIAL


Y ER ACHINER ION/DA S
IES YS
BEAMS

1. Installing 301 The reinforcement bar will be cut 4 semi-  Bar cutter 8hrs/day 10 days Rebar
reinforcement and bended as per the bar skilled  Bar bender @30set/d Tie Wire
bar schedule. labours  Hammer ay
 Measuring
tape

2. Installing 301 The chamfers shall be provided at 4 semi-  Hammer 8hrs/day 10 days Nail
formwork all exposed edges and the shutters skilled  Measuring @30set/d Plywood
will be installed and fixed. Erect labours tape ay
formwork to the dimension and
ensures that lines and levels within
the tolerances. Steel bars are used
as side support for the shutter to
maintain the proper alignment.
Allowance must be made for height
adjustment of the props.
7K-L, Second & Third Floor,
Jalan Ban Hock,
93100, Kuching, Sarawak.
[email protected]
Tel: +6082 7877 123
Fax: +6082 7877 234
METHOD STATEMENT

NO. OPERATION QT METHOD DIAGRAM MENPOW PLANT/M OUTPUT DURAT MATERIALS


Y ER ACHINER ION/DA
IES YS
3. Pouring 301 The concrete shall be thoroughly 2 semi-  Vibrator 8hrs/day 15 days  Ready Made
concrete and compacted during and immediately skilled  mixer @20pcs/d Concrete
curing after depositing. For better labour ays
performance while operating.
Vibrators for each pump operating
must be presented. Curing shall be
started immediately after initial set
of concrete and finishing.

4. Removal of 301 The formwork is removed when the 2 semi- Excavator 8hrs/day 10 days
formwork concrete has gain sufficient skilled Hammer @20pcs/d
strength, labour ays