7K-L, Second & Third Floor, Jalan Ban Hock, 93100, Kuching, Sarawak. Tel: +6082 7877 123 Fax: +6082 7877 234 Method Statement
7K-L, Second & Third Floor, Jalan Ban Hock, 93100, Kuching, Sarawak. Tel: +6082 7877 123 Fax: +6082 7877 234 Method Statement
1. Installing 150 Install the reinforcement bar as per 2 semi- Bar cutter 8hrs/day 10 days Rebar
reinforcemen approved drawing. skilled Bar bender @15set/d Tie wire
t bar labours ay
Hammer
Measuring
tape
2. Installing 150 Before erecting the shutters, box 2 semi- Hammer 8hrs/day 10 days Nail
formwork out and cast in items will be skilled Measuring @15 Plywood
installed. Formwork are installed to labours tape set/day
its dimension correctly. The shutters
will be braced and anchorages
properly as per the drawing. For
proper alignment, tie rods shall be
used.
7K-L, Second & Third Floor,
Jalan Ban Hock,
93100, Kuching, Sarawak.
[email protected]
Tel: +6082 7877 123
Fax: +6082 7877 234
METHOD STATEMENT
4. Removal of 150 The formwork is removed when the 2 General 8hrs/day 10 days
formwork concrete has gain sufficient Labour @15pcs/d
strength ays
7K-L, Second & Third Floor,
Jalan Ban Hock,
93100, Kuching, Sarawak.
[email protected]
Tel: +6082 7877 123
Fax: +6082 7877 234
METHOD STATEMENT
1. Installing 301 The reinforcement bar will be cut 4 semi- Bar cutter 8hrs/day 10 days Rebar
reinforcement and bended as per the bar skilled Bar bender @30set/d Tie Wire
bar schedule. labours Hammer ay
Measuring
tape
2. Installing 301 The chamfers shall be provided at 4 semi- Hammer 8hrs/day 10 days Nail
formwork all exposed edges and the shutters skilled Measuring @30set/d Plywood
will be installed and fixed. Erect labours tape ay
formwork to the dimension and
ensures that lines and levels within
the tolerances. Steel bars are used
as side support for the shutter to
maintain the proper alignment.
Allowance must be made for height
adjustment of the props.
7K-L, Second & Third Floor,
Jalan Ban Hock,
93100, Kuching, Sarawak.
[email protected]
Tel: +6082 7877 123
Fax: +6082 7877 234
METHOD STATEMENT
4. Removal of 301 The formwork is removed when the 2 semi- Excavator 8hrs/day 10 days
formwork concrete has gain sufficient skilled Hammer @20pcs/d
strength, labour ays