Weekly Progress Plan Vs Actual - Template

This weekly update provides the status of the construction project to build an operations building for the Air Force in Jubail, Saudi Arabia. To date, no work has been completed and the project is 0% finished, with a remaining budget of over $2.3 million. The project involves substructure, superstructure, masonry works, and other construction elements. A chart shows that planned and actual weekly and cumulative progress are both at 0% complete, with the project remaining on budget and schedule.

Uploaded by

ton
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
856 views

Weekly Progress Plan Vs Actual - Template

This weekly update provides the status of the construction project to build an operations building for the Air Force in Jubail, Saudi Arabia. To date, no work has been completed and the project is 0% finished, with a remaining budget of over $2.3 million. The project involves substructure, superstructure, masonry works, and other construction elements. A chart shows that planned and actual weekly and cumulative progress are both at 0% complete, with the project remaining on budget and schedule.

Uploaded by

ton
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 14.0 15.0 16.0 17.0 18.

3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 14.0 15.0 16.0 17.0 18.0 19.0

PROJECT : CONSTRUCTION OF OPERATION BUILDING FOR AIR FORCE, JUBAIL


SUBJECT : WEEKLY UPDATE
TODATE 15 April 2019
COST  ACTUAL ACCOMPLISHMENT TO DATE BALANCE TO COMPLETE
Actual % 
Previous  This Week  To date %  % Weight  
Activity ID Activity Name Unit Qty Unit Rate Amount WT % Earned Value Cost % Progress Weight QTY Cost To Complete
%Comp. % Comp. Complete Balance
CONSTRUCTION OF OPERATION BUILDING FOR AIR FORCE, JUBAIL             2,396,621.15 100.00%                                     ‐ 0.00% 0.00%               2,396,621.15 100.00%
  Construction             2,379,306.65 99.28%                                     ‐ 0.00% 0.00%                2,379,306.65 99.28%
    Substructure                 247,174.67 10.31%                                     ‐ 0.00% 0.00%                   247,174.67 10.31%
    Superstructure                 576,572.85 24.06%                                     ‐ 0.00% 0.00%                   576,572.85 24.06%
    Masonry Works                   21,144.06 0.88%                                     ‐ 0.00% 0.00%                     21,144.06 0.88%
    Waterproofing Works                 120,567.48 5.03%                                     ‐ 0.00% 0.00%                   120,567.48 5.03%
    Finishes                 287,660.56 12.00%                                     ‐ 0.00% 0.00%                   287,660.56 12.00%
    Doors and Windows                   90,520.21 3.78%                                     ‐ 0.00% 0.00%                     90,520.21 3.78%
    Metal Works                     3,564.75 0.15%                                     ‐ 0.00% 0.00%                        3,564.75 0.15%
    Specialties                   43,077.46 1.80%                                     ‐ 0.00% 0.00%                     43,077.46 1.80%
    Electrical Works                 397,428.89 16.58%                                     ‐ 0.00% 0.00%                   397,428.89 16.58%
    Fire Fighting and Fire Alarm System                   24,851.40 1.04%                                     ‐ 0.00% 0.00%                     24,851.40 1.04%
    Plumbing Works                 235,629.98 9.83%                                     ‐ 0.00% 0.00%                   235,629.98 9.83%
    HVAC Works                 172,635.75 7.20%                                     ‐ 0.00% 0.00%                   172,635.75 7.20%
    Telecom and Data System                 158,478.60 6.61%                                     ‐ 0.00% 0.00%                   158,478.60 6.61%
  Testing and Commissioning                   17,314.50 0.72%                                     ‐ 0.00% 0.00%                     17,314.50 0.72%
    General Items                   17,314.50 0.72%                                     ‐ 0.00% 0.00%                     17,314.50 0.72%

20.00% 110.00%
Weekly Construction Progress Update (Plan vs Actual)
18.00%

90.00%
16.00%

14.00%
70.00%
Planned Weekly Actual Weekly
12.00%

Planned Cum Actual Cum
10.00% 50.00%

8.00%

30.00%
6.00%

4.00%
10.00%

2.00%

0.00% ‐10.00%
22‐Mar‐ 29‐Mar‐ 05‐Apr‐ 12‐Apr‐ 19‐Apr‐ 26‐Apr‐ 03‐ 10‐ 17‐ 24‐ 31‐ 07‐Jun‐ 14‐Jun‐ 21‐Jun‐ 28‐Jun‐ 05‐Jul‐ 12‐Jul‐ 19‐Jul‐ 26‐Jul‐ 02‐Aug‐ 09‐Aug‐ 16‐Aug‐ 23‐Aug‐ 30‐Aug‐ 06‐Sep‐ 13‐Sep‐ 20‐Sep‐ 27‐Sep‐ 04‐Oct‐ 11‐Oct‐ 14‐Oct‐
19 19 19 19 19 19 May‐19 May‐19 May‐19 May‐19 May‐19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19
Planned Weekly 0.00% 0.00% 0.00% 0.00% 0.14% 1.08% 2.59% 1.23% 0.88% 1.10% 0.52% 0.04% 0.87% 0.97% 2.80% 5.72% 5.72% 4.84% 4.40% 2.43% 3.58% 9.15% 2.48% 6.71% 17.74% 17.83% 3.35% 1.68% 2.15% 0.00% 0.00%
Actual Weekly
Planned Cum 0.00% 0.00% 0.00% 0.00% 0.14% 1.23% 3.82% 5.05% 5.93% 7.03% 7.55% 7.59% 8.46% 9.43% 12.22% 17.94% 23.67% 28.50% 32.90% 35.33% 38.91% 48.06% 50.54% 57.24% 74.99% 92.82% 96.17% 97.85% 100.00%100.00%100.00%
Actual Cum