BBT Method
BBT Method
DUCT INSTALLATION.
PROJECT BYTES
CONTRACTOR BYTES
MR PROJECT MANAGER
MR HSE MANAGER
3.Team involved
01 01 02
SITE SUPERVISOR SITE SUPERVISOR SITE SUPERVISOR
01 01 01
01 01 01
0 02 02
06 06 07
Kindly read the manual for Safe Installation and Energizing the MARINE ELECTRICAL INDIA PVT
LTD S.M.A.R.T Busduct System
PREFACE
This manual describes the installation and inspection procedure of MARINE ELECTRICAL INDIA PVT LTD
S.M.A.R.T. busduct systems. Refer the manual carefully before setting the installation and the maintenance
of the busduct system. It is giving the proper instructions for proper handling, installation, operation and
maintenance, and also helps in minimizing personal injury, equipment damage during the handling of
the busduct system, and to facilitate the movement of the busduct sections.
Special care on the handling of the busduct is essential; as the product is for the usage of power
distribution which itself is very costly.
However it is recommended that the installation is performed only by qualified person, who is familiar with
the installation, testing / commissioning and operations of the busduct.
1 General 3
2 Unpacking 3
3 Handling 3
4 Storage 4
5 Operation 5
6 Protection Against Ingress Of Dust And Water 7
7 Summary 7
8 Joint Assembly 7
9 Horizontal Hanger Installation 10
10 Vertical Fixed Hanger Installation 11
11 Vertical Spring Hanger Installation 13
12 Inspection Of Joint Bolt 14
13 Fixing Tap-Off-Box 15
14 Energizing 16
15 Care And maintenance 16
16 Process Flow Chart for Installation 18
17 Appendix: -
1. Pre-Installation Checklist. 19
3. Pre-Commissioning Checklist. 21
1. PURPOSE
To define the fixing & execution method statement for bus duct.
2. SYSTEM DESCRIPTION
The bus duct is intended to supply and distribute power from Transformer secondary to switchgear.
3. RELATED WORKS
All Civil Works related to the support structure in roof & floor need to be completed and
proper clear access for bringing in the bus duct should be available.
4. REFERENCE DRAWINGS
5. SAFETY
b) All personnel and operatives shall wear safety footwear at all times.
c) Work areas and access way are to be free from debris, materials and
all trippinghazard.
d) All hand tools and portable power tools shall be of good order And shall be
used for the purposeintended.
e) All work on Energized Systems shall be done with a Permit to
WorkSystem.Proper Earthing / cordoning off to be done prior to Commencement
of work, if working in energized environment.
a) Air blower
b) Torque wrench
c) Meggar
d) Earth tester
e) Multimeter
2.PROCEDURE
Examine the drawing of Bus duct erection layout withrespect To the general layout.
Shift the Bus duct from stores to location by means ofsuitable Truck/lifting arrangement.
Carryout physical verification or any possible damage.
Check for necessary lifting tools &tackles in relation withload To be lifted and ensure safe lifting.
Check for the level alignment of the foundation/ structure Before starting the erection.
Assemble Bus duct at site and provide completesupporting Structures as required.
Sections of bus duct installed out door shall be supportedfrom ground.
Indoor sections shall be supported from ceiling and/or wall With GI/MS, brackets /hangers.
Clean all Bus bar joints through with Carbon tetra chloride.
Seal off wall bushings shall be provided where the
busduct Enters a building from its outdoor run as well as fromTransformer cell to switch-gear room.
SCAFFOLDINGS:
Scaffoldings will be inspected before use. Observations prior to allowing work on Scaffoldings.
1.2. The successful operation and performance of busduct is dependent upon proper handling,
installation, operation and maintenance, as well as upon proper design and manufacture. Neglecting
certain fundamental installation and maintenance requirements may lead to personal injury and
damage to electrical equipment or other property.
1.3. Installation, operation and maintenance of busduct should be conducted only by qualified personal.
1.4. For purpose of these guidelines, a qualified person is one who is familiar with the installation,
construction, and operation of the equipment and the hazards involved. In addition, the person
should be:
1.4.1 Trained and authorized to test, energize, clear, ground, tag and lockout circuits and equipment
in accordance with established safety practices.
1.4.2 Trained in proper care and use of personal protective equipment such as rubber gloves, hard
hat, safety glasses or face shields, and flash resistant clothing in accordance with established
safety practices
INSTRUCTIONS.
2.2. Nail pullers should be used for unpacking wooden crates to avoid damage.
2.3. Remove any support blocks which may have been used for shipping.
2.4. DO NOT REMOVE THE PLASTIC WRAPPING ON THE BUSDUCT AT THE LOAD AND SUPPLY
ENDS TILL THE BUSDUCT IT TAKEN UP FOR INSTALLATION, AS DUST, MOISTURE AND
ANY OTHER CONTAMINATION CAN OCCUR WHICH MIGHT RESULT IN THE FAILURE OF THE
BUSDUCT AFTER INSTALLATION.
2.5. Check the material received as against the packing list of the package.
3. HANDLING
These guidelines are provided to help avoid personal injury, and equipment damage during handling and
to facilitate moving the busduct sections and fittings at the job site.
3.1. Handle busduct with care to avoid damage to internal components and the enclosure or its finish.
Avoid subjecting busduct to twisting, denting, and impact and in general, rough handling.
3.2. Do not use busduct ends for lifting busduct sections or fittings.
3.3. When the busduct is received, unpack it sufficiently to inspect it for concealed damage and to
determine that the shipment is complete and correct.
3.4. If busduct is to be stored prior to installation, restore the packing for protection during that period
(see section 4.). When conditions permit, leave the packing intact until the section or fittings are at
their final installation location.
3.5. Verify that the weights of any busduct sections or fittings are within the rated capacity of the handling
equipment to be used.
Fig. 1
Fig. 2
Fig 2.
4. STORAGE
4.1. Busduct sections and fittings which are not to be installed and energized immediately should be
stored in a heated building having adequate air circulation and protection from dirt, fumes, water, and
physical damage.
4.2. It is recommended that busduct should not be stored outdoors. Protect busduct from dust and water
by covering with the waterproof sheet.(Fig. 3)
Fig. 3
4.3. If it must be stored outdoors, cover it securely to provide protection from weather and dirt. Temporary
electrical heating should be installed beneath the cover to prevent condensation.
4.4. Outdoor busduct is not weather resistant until completely and properly installed and should
be treated exactly the same as indoor busduct until after it is installed.
4.5. Bus duct should always be placed on the floor horizontally and, wooden battens or forms are placed
underneath the busduct.(Fig. 3 & Fig. 4)
Wrong Method of Storing of the Busducts.
ASSEMBLY
Fig. 4
5. OPERATION
5.1. Provide sufficient horizontal and vertical clearance from walls and ceilings to provide easy access to
joints, both for the original installation and possible removal of a section when required.
Copper Busduct Aluminum Busduct
Busduct Weight kg/m Width Busduct Weight kg/m Width
Rating Height 3P 3P 3P 3P Rating Height 3P 3P 3P 3P
mm mm
In 400
Amps 115 3W
21 4W
25 3W 4W In 400
Amps 125 3W
18 4W
22 3W 4W
630 125 22 27 630 125 19 24
800 125 24 30 800 140 24 28
1000 140 30 36 1000 165 28 34
1250 165 35 43 1250 205 34 39
1600 205 43 51 1600 250 42 46
2000 240 45 58 2000 305 48 54
2500 305 58 78 2500 405 50 59
3200 405 76 94 3200 475 63 74
3600 475 86 107 3600 495 64 75
4000 495 99 125 4000 605 72 85
4500 605 118 145 4500 710 76 89
5000 710 134 166 105 125 105 125
6300 740 141 177 5000 905 85 100
Table 1
5.2. Table 1 shows the approximate weight of busduct. However, the weight of special busduct (e.g.
flanged end, expansion joint and etc.) should be considered during transporting the units as it is
heavier than the weight calculated.
5.3. Avoid subjecting busduct not only to twisting, denting, and impact and, in general, rough handling.
Especially busduct ends are not to be hit against the structures or equipment and also not allowed to
stand busduct against the wall or other structures.
5.4. Suitable and certified hoisting wire should be used to hoist the busduct for easy installation and also
to avoid damage to the housing.
5.5. Ensure that proper distribution of the busduct weight is applied and careful approach is a must to
avoid any damage to the housing that could pinch the busduct insulation and result in a failure.
5.6. No direct fixing of hoisting wire to the joint cover hole on the housing for of the busduct, but instead,
use lifting jig for both horizontal and vertical busduct installation. (Fig. 5)
5.7. The joint hole should not be used for hoisting as it cannot withstand the weight of the busduct, which
result break on the wielding parts or any damages.
5.8. Do not drag the busduct across the floor.
5.9. When installing vertical riser, it is easier to lower the busduct from the floor above where it will be
installed. Vertical sections are often stored on the floor above their final location to facilitate lowering
them into position.
5.10. While hoisting any feeder ensure that the opposite side of the feeder being hoisted should be rested
on a support in order to prevent any damage to the joint.
5.11. Hang one busduct unit with two hangers in principle.
5.12. Depending on the site condition, preferably flanged end, flange end box, cable feed box shall be
installed first, followed by the sub-sequent unit numbers.(Fig 6)
5.13. While installing the busduct each unit of the busduct to be individually checked for IR value.
5.14. Also the IR to be checked during the various stages of installation.
It is lowered after proper alignment
Using the lifting fixture the busduct is with the load and supply of the
Perfectly meshed busduct.
raised. corresponding busduct
Fig 5 Fig 6
6. PROTECTION AGAINST INGRESS OF DUST AND WATER
The ingress of dust and water into the busduct will decrease electrical and physical properties and
cause dielectric damage.
6.1.2. Floor level liquids – minimum curbs of four inches should be installed around all floor
openings for riser busduct to prevent floor level liquids (water / oil spills) from entering the
openings.
6.1.3. Leaking roof – protect indoor busduct with a temporary sheet metal shield or other
protective cover to prevent water from falling onto the busduct until the roof is repaired.
6.1.4. Pipes – protect indoor busduct with a temporary sheet metal shied or other protective cover
to prevent water from falling onto the busduct until the pipes are repaired. Where pipes
(especially cold water pipes) pass directly above indoor busduct, the busduct should be
protected from dripping condensate by insulating the pipe or permanently shielding the
busduct with sheet metal or plastic.
6.1.5. Sprinklers – protect indoor busduct from direct or indirect spray of sprinklers.
6.2. To prevent this, take precaution against the ingress of dust water during storage and installation.
6.2.1. Install busduct after the general construction works are completed.
6.2.2. Install busduct when possible leaking roof is sealed.
6.2.3. Install extra cover at the busduct end.
7. SUMMARY
7.1. Review erection drawing very carefully.
7.2. Check the bill of material.
7.3. Check description and identification of each piece before installation it.
7.8. Check for possible source of water that may fall on indoor busduct and take corrective action to
prevent this.
8. JOINT ASSEMBLY
The joint section is heart of the busduct during its operation, so proper tightening of
the joint bolt is important to ensure its continuous and satisfactory operation.
8.1. Ensure all contact surfaces are clean and free of contaminants by using dry cloth.
8.2. Align the bus duct ends of adjoining sections, verifying proper phase alignment,
a
n
d
s Fig. 7 (b) Inserting Rod
Fig. 7 (c)
l Fig. 7 (a)
and slide the sections together as illustrated in Fig. 7. It is done by inserting jointing tool inside the
joining holes.
8.3. For easier connection of “supply” and “load” and less impact on the download of the busduct weight, certain
interval has to be kept. Use joint cover by screwing bolt on the lower part of the joint cover then follow by the
upper part of the joint cover this would enable easy jointing and accurate jointing interval. (Fig. 8.1, 8.2)
Fig. 8.1
Fig. 8.2
8.4. Assembly
8.4.1. Ensure load and supply sides are aligned correctly by placing inserting tool.
8.4.2. Joint the two sections until the joint edge to edge distance is 300mm or to have adequate contact
surfaces of each phase to phase.
8.4.3. Insert joint bolt with the joint support through the joint hole and tighten it with plate spring and MF nut
with the tool.
8.4.4. For IP 65 and IP67, install side cover with gasket and then fix with bolts (M8x16) on both sides.
8.4.5. Install the joint cover with gasket on the top and bottom of the jointing section.
8.4.6. After side cover and joint cover are fixed, apply sealant around the covers to ensure its protection
against water and dust.
8.5. Ensure that all busduct installation is in straight alignment, either in horizontally or vertically in order to have
proper jointing system. Then only tighten the Maintenance Free nut to the required torque
9.4. Install the hanger clamp on both side of the busduct for fixture.
9.5. Additional horizontal hangers shall be placed on elbows, such as vertical / horizontal elbow, offset elbow,
combination elbow and etc.
9.6. Supporting interval of horizontal hanger shall not exceed 1.5 meters for straight length. However each elbows /
Nut
Clamps
Horizontal Support
Fig. 12
Dimensions for Horizontal Hanger (Fig. 12)
Screw Threading
Ampere Rating Steel Angle Size (mm) on Rod in mm Weight (kg/m)
10.1. Temporarily support the busduct section in place. Fit the C-Channel (customer’s scope) onto the Floor Flange.
Fix on the bolts (customers scope) onto the slab in order to hold the C-Channel firmly to the slab.
10.2. Drill the C-Chanel with opening hole of 14mm dia. To accommodate the fixed support rod. Locate the hole in
line with the centerline of the side of the busduct housing. The distance in between these two holes from center
is 65mm. Then, drill the busduct housing with opening hole of 12mm dia. With the height around 85mm from the
top of the C-Channel for installing the L-Channel Bracket by using M10 bolts supplied. The distance in between
these two holes from center to center is 60mm.
10.3. Fix the rod to the top of the C-Channel together with the nuts as show. Try to adjust the Top Nut on both sides
until the height from the top of the C-Channel to the base of the “L” Channel is around 50mm and it is aligned
with the opening hole of 12mm dia. On the busduct housing.
10.4. Then fix the “L” Channel together with the nuts as shown (Fig. 13).
The following instructions are for fitting of vertical fixed Hanger for Busduct systems.
Then, drill the busduct housing with opening hole of 12mm dia.
with the height around 190mm from the top of the C-Channel
for installing the L-Channel Bracket by using M10 bolts
Fig. 15
supplied. The distance in between these two holes from center
to center is 60mm.
11.3. Fix the rod to the top of the C – Channel together with the
nuts.
11.4. Try to adjust the top nut on both sides until the height from the
top of the C – Channel to the base of the L – Channel is
around 155mm, while the height from the bottom of L –
channel to the bracket of the vertical spring hanger is 100mm.
Then, fix the L – Channel together with the nuts as shown in
Fig. 15.
11.5. Unscrew the top nut, 15mm above the top of the L – channel.
12.1. Tighten the MF nut using either a ratchet wrench or, a torque wrench (set to 1400kg-cm / 14kg-m).
12.2. Ensure the tightness of the MF nut until the neck of the MF nut is broken. If the MF nut is not tightened properly,
an over-heating of the busduct may occur.
12.3. The torque values of tightening of the nuts are as shown below. Table 2
NUT SIZE M8 M10 M14
TORQUE VALUE (kg – cm) 90 – 110 180 – 230 1400 – 1500
TORQUE VALUE (kg – m) 0.9 – 1.10 1.80 – 2.30 14 –
159
Table 2
13. FIXING TAP-OFF-BOX
14.1. Recheck all joint connections for tightness by following on the recommended torque value given as section
13.3. Table 2. Ensure that outer head of MF nut is broken. If not, then retighten the nut until it is broken, before installing side cover.
14.2. Ensure that upper nuts are of the spring hangers are unscrewed 15mm above the upper part of spring hanger.
14.3. Isolate the busduct run by disconnecting all connections to transformers, switchboards, meters and so forth.
14.4. Conduct an insulation resistance test on the whole busduct connection after installation. The insulation resistance value cannot be specified due to the length of the route and the environmental
factors. In a dried atmosphere, it would give a value of approximately 100 MΩ, it has to be checked due to some factors that can reduce the insulation and the other factors can be as follows;
14.4.3. Whether the bolts for connecting the equipment are securely fastened.
14.4.6. Busduct kept idle without charging for a very long period of time in humid atmosphere / conditions.
After energizing
When the equipment is energized for the first time, competent and qualified electrical personal should be present. If short circuits and ground faults caused by damage or poor installation
practices have not been detected in the check-out procedure, serious damage can result when the power is turned on.
14.5. There should be no electrical load on the busduct when it is energized. Since busduct typically extends through several rooms and floor levels, care should be taken to see that all devices fed
from the busduct are in the “OFF” position.
14.6. The equipment should be energized in sequence by starting at the source end of the system and working towards the load end. In other words, energize the main devices, then the feeder
devices and then the branch- circuit devices. Turn the devices to the “ON” position with a firm positive motion.
14.7. After all over-current devices have been turned on, loads such as lighting circuits, contractors, heaters, and motors may be turned “ON”.
14.8. Busduct, when operating properly, will have a moderate hum. Excessive noise may be an indication of hardware that has not been tightened or of metal parts that have been improperly
assembled.
14.9. Occurrence of sparking at any point along the busduct is not a normal condition. The busduct must be de- energized immediately, and remain de-energized until the sparking condition has
been corrected.
15.1.1. Inspect busduct once each year or after any severe electrical short circuit or ground fault.
15.1.2. Perform an infra-red temperature scan on all electrical connections and busduct enclosure while busduct is energized and operating under maximum load conditions. A permanent
record should be kept. If readings change with time, deterioration may be taking place and must be corrected.
15.1.4. If there is appreciable accumulation of dust and dirt, clean it off by using a brush, vacuum cleaner, or clean lint-free rags. In order to avoid blowing dust into busduct joint, circuit
breakers, or other equipment, do not use a blower or compressed air. Ensure that all drain holes are operating properly.
15.1.5. Check the insulation resistance prior to re-energizing the busduct. A permanent record should be kept of resistance readings. If readings decrease appreciably with time, deterioration
is taking place and must be corrected (contact the manufacturer).
Busway Installation
Schneider Electric, Mumbai
1
Agenda
3
• Check the packing list against the equipment received to ensure the order and
shipment are complete with local Schneider engineer.
• Check for any damage that may have occurred in transit. If any problem be found,
notify local Schneider office immediately.
4
• Match No. of crates in the packing list with shipping mark .
5
• Self-protection with well packing (plastic wrap)
• Apply “rain coat” to protect unfinished run after installation each time
Self-protection Storage Environment Rain Coat
6
• Water/ dust will provide alternative path / heating point
• Damage insulation
9
• Open crates
Packing list
Brass drawing
Run No.
10
Bom list from Brass
• Assembly tools and accessories
11
• Insulation test
• Conduct an insulation test at 1000V on each device before installation. The megohm
reading should not be less than 10MΩ.
12
Installation- Horizontal application
13
Hanger
Elbow
Straight length
Flange end
L
14
Hanger
15
• Fix hanger according to specific base point. For horizontal application, the maximum distance
between two supporting poles is 3 meters for indoor, and 1.5 meters for outdoor.
16
• Two kinds of hanger for horizontal installation.
Drop rod
Horizontal flatwise hanger Horizontal edgewise hanger
Remark :drop rod should be provided by customer. Flatwise hanger requires 2 pcs rods while edgewise is 1 pcs.
Test alignment when installing.
17
Straight length
18
• Remove tie channel from busway before installation.
Tie channel
19
• Orient the busways straight lengths with “TOP” sides facing the same way.
• Be sure the busways are aligned properly before attempting to join them.
1. 20
• Hook the joint assembly tool in the surge clamp, insert the rod through the hole and wedge it
• Avoid the wrong connection between earth bar and phase bar.
Attention
21
• Pull to slide the busways together until distance between two holes is 340mm.
22
• Place the top cover plate on the top side of the joint.
• Tighten joint bolts until outer head breaks off, mount the bottom cover using the same
procedure used to install the top cover.
Remarks: CFD has no top & bottom plate. 23
• Tighten the rubber plug in the center hole of the bottom cover plate.
• Install tie channel, eight protruding pins are all need to be tighten.
24
Elbow
25
• Remove the protective paper from the sealants which appear on the duct sides on fitting only.
Protective paper
Attention
26
Attention
Washer 27
Flange end
28
• Same connection way as elbow Installation at joint pak.
32
Straight length
Spring hanger
Channel
33
• Make sure horizontal alignment.
Channel
34
• Built concrete curd around channel to prevent water ingress.
35
Spring hanger
36
• Pre-adjust the length of spring
Compress length
of spring hanger
Remark: for vertical application, it requires two nos/pairs of spring hanger if spacing is more than 4.8 meters. 37
.
• Tighten the top nuts to the proper spring compression dimension.
For example:CFD2516GM54
• Fasten the hanger clamps to the busway duct sides and tighten the nuts.
Hanger clamps
39
• Note
• At design stage, distance between bottom of spring hanger and center of connection is at least
530mm.
40
• Spring hanger installation
• Back off the top nuts to the top of the rod after complete run is installed.
Attention
41
• Spring hanger installation
42
Straight length
43
• Check vertical alignment
IF NOT
Attention
44
• Raise the busway to the final installation location to connect the existing busway, same procedure
as horizontal application.
1 2 3 4 5
45
• Keep N phase face left all the time.
Attention
46
N L3 L2 L1
Installation- Tap off unit
47
5. Installation - Tap off unit
• For above 630A (includes 630A), installation way is Bolt-on type. Especially for horizontal and
vertical, they have different mounting.
Plug-in type Bolt-on type
48
©2014 Schneider Electric. All Rights Reserved.
All trademarks are owned by Schneider Electric Industries SAS or its affiliated companies or their respective
owners.
15.2.1. Inspect busduct once each year or after any severe electrical short circuit or ground fault.
15.2.2. Perform an infra-red temperature scan on all electrical connections and busduct enclosure while
busduct is energized and operating under maximum load conditions. A permanent record should be
kept. If readings change with time, deterioration that may be taking place and must be corrected.
15.2.4. Look for any moisture or signs of previous wetness or dripping onto the busduct or onto connection
boxes from leaky roofs, pipes, sprinklers or other sources moisture. Look for any recent changes in
sprinklers or other plumbing that might now be a source of trouble to busduct.
15.2.5. Seal off any cracks or openings which have allowed moisture to enter the busduct or its connection
boxes. Eliminate source of any dripping onto the busduct and any other sources of moisture see
SECTION 6 or more details on preventing liquid from getting onto the busduct.
15.2.6. Replace or thoroughly dry and clean any insulating material which is damp or wet or shows
accumulation of deposited material from previous wettings.
15.2.7. If there is appreciable accumulation of dust, clean it off by using a brush, vacuum cleaner, or clean
lint-free rags. In order to avoid blowing dust in the busduct joints, circuit breakers, or other equipment,
do not use a blower or compressed air.
15.2.9. Visually check connections to be certain that they are clean and secure. Loose and/or contaminated
connections increase electrical resistance which can cause overheating. Such overheating is indicated
by discoloration or flaking of insulation and/or metal parts. Pitting or melting of connecting surfaces is
a sign of arcing due to a loose or otherwise poor connection. Parts which shows evidence of
overheating or looseness should be cleaned or replaced if damaged, contact manufacturer before
opening joint bolts.
15.2.10. Check the insulation resistance prior to re-energizing the busduct. A permanent record should be kept
of resistance readings. If readings decrease appreciably with time, deterioration is taking place and
For PTTA (Partially Type Tested Assemblies) which have not been subjected to a dielectric test according to
8.2.2 or 8.3.2 (clause numbers 8.2.2 page # 61 or 8.3.2 page# 71 of IEC 60439 – 1), an insulation measurement
using an insulation measuring device at a voltage of at least 500V shall be carried out.
In this case, the test is deemed satisfactory if the insulation resistance between circuits and exposed
conductive parts is at least 1000ષ/V per circuit referred to the nominal voltage to earth of these circuits.
By exception, items which, according to their specific requirements, are current‐consuming apparatus (e.g.
windings, measuring instruments) at the application of the test voltage or are not designed for the full test
voltage shall be disconnected as appropriate.
16. Process Flow Chart for Installation.
Check IR value of the connected busducts before the start and at the end of the shift during the installation process
on a daily basis. Also cover the end portion of the busduct to prevent any water or dust seepage or contamination.
Not OK
OK
2 Wet riser and sprinkler should not be in the same shaft. Ok Not Ok N. A.
Electrical Shaft Clearance for no Water seepage. Proper
plastering / white wash / tiling to avoid any seepage of
3 Paint / Cement on the busduct. Ok Not Ok N. A.
1 R Phase ‐ Neutral
2 Y Phase ‐ Neutral
3 B Phase ‐ Neutral
4 R Phase ‐ Earth
5 Y Phase ‐ Earth
6 B Phase ‐ Earth
7 Neutral ‐ Earth
8 R Phase ‐ Y Phase
9 R Phase ‐ B Phase
10 B Phase ‐ Y Phase
For Client For Commissioning
Instruction / Check list for Pre-Commissioning of the Busduct System
Sr.
Description Status
No.
Client's Competent Personnel should take training on the method of installation of the bus
1 duct / Rising main / lighting Trunking from MARINE ELECTRICAL INDIA PVT LTD before start Ok Not Ok N. A.
of
All installation.
the busduct lines are aligned in plumb in case of riser & at zero level in case of horizontal
2 run of busduct. Ok Not Ok N. A.
Check whether all the joint bolts are sheared @14-15 kg-m. and tightening of joint bolt is
3 Ok Not Ok N. A.
100% responsibility of installation contractor / Clients.
Take insulation resistance at 500V. Check the IR before and after Shearing of joint Bolts. As
per IEC 60439-1, clause 8.3.4 insulation resistance should be at least 1000 ષ/V i.e. 0.5 M ષ.
4 (To maintain stringent quality standards MARINE ELECTRICAL INDIA PVT LTD Ok Not Ok N. A.
recommends
Check whether1M allષthe
) spring Hangers top Nuts are loosen and spring should be loaded in
5 Ok Not Ok N. A.
case of Riser as per installation manual.
Check whether earthing run along with Bus duct is physically connected to both the ends of
6 the busduct flanged & equipment. Ok Not Ok N. A.
7 Check whether all the bolts at Flanged end are tightened. Ok Not Ok N. A.
Check tightening of all the bolts of flexible links to equipment side like Panel ,Transformer,
8 DG Ok Not Ok N. A.
Check whether all the supports to the risers and bus duct line are installed properly to carry
9 the required weight of Busduct Ok Not Ok N. A.
10 Check whether all the holding clips on the horizontal supports are tighten Ok Not Ok N. A.
11 Check whether all the holding clips on Tap off box are tighten Ok Not Ok N. A.
13 Check for chance of water seepage on Busduct / Rising Main from other utilities Ok Not Ok N. A.
Check whether the entire name plates on Tap Off Box & panels indicating outgoing location
15 of supply. Ok Not Ok N. A.
Check whether caution / danger stickers displayed on all the Tap Off Boxes and Electrical
16 Ok Not Ok N. A.
Panels.
17 Check whether earthing wire is connected to Tap Off Box door & bus duct housing. Ok Not Ok N. A.
Check Phase sequence of Rising Main (R, Y, B, and N) in line with Tap off box incoming and
18 outgoing. Ok Not Ok N. A.
Check Whether Outdoor Installation Bus duct is properly filled up with sealant/compound at
19 the joints in case of IP/65/68 Ok Not Ok N. A.
Bus Duct / Rising Mains should not be energized without checking of all above instructions
20 and installation Contractor / Client to ensure all above points Ok Not Ok N. A.