Constraints For Achieving Full Load
Constraints For Achieving Full Load
Full Load
_____________________________________________________________
Unit-1
2. Mill E taking high current 34A at coal flow 27TPH, Full load in 4 mill
operation is a problem.
_____________________________________________________________
ST-I OFFSITE
_____________________________________________________________
Unit-2
2. No margin in ID Fan due to air ingress in ESP, Flue gas ducts & Furnace.
Air Flow cannot be increased beyond 620 T/hr.
3. O2 Tx RHS deviation high limiting fuel feeding margin (O2 > 2.5% to be
maintained).
4. HRH temp L & R deviation high (7-10 deg C). HRH L maintaining Lower
than HRH R.
5. DFA
_____________________________________________________________
Unit-3
2. Full load not achieving with 04 ESP passes (after commissioning of ESP
pass-E).
_________________________________________________________________
ST-2 OFFSITE
6. ST-2 DFA line vacuum very poor while running in dry mode.
__________________________________________________________________
UNIT-4
8. Control fluid oil continuous foaming taking place and FRF tank level
showing erratic in UCB.
__________________________________________________________
Unit-5
2. Mill A and H fineness poor and developing clinker when raising load.
3. Mill J not avl. From long time. Under permit for GRS/BRS.
5. I.D fans getting overloaded with coal flow above 380 TPH for maintaining
design O2 .
__________________________________________________________
Unit-6
1. Less margin available with combination of ID fan A & B as compared to
ID-A & C
4. At higher load & Due to poor vacuum, BFP got over speed to maintain
drum level hence to avoid over speeding load reduced.
__________________________________________________________________
UNIT-7
__________________________________________________________________