Notification Letter

The letter notifies the Department of Occupational Safety and Health that scaffolding works will take place from October 16, 2019 to January 20, 2021 as part of the Sibiyu 132/33 kV Substation Project. Details on the scaffolding design, construction method statement, inspector and erector certificates, and material catalog are attached. Pestech expresses appreciation for cooperation during the construction period.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
102 views

Notification Letter

The letter notifies the Department of Occupational Safety and Health that scaffolding works will take place from October 16, 2019 to January 20, 2021 as part of the Sibiyu 132/33 kV Substation Project. Details on the scaffolding design, construction method statement, inspector and erector certificates, and material catalog are attached. Pestech expresses appreciation for cooperation during the construction period.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

Our Ref : PES(PSC)/18/016/1-098

Date : 15 October 2019

The Director,
Department of Occupational Safety and Health,
Lot 464, Jln Law Gek Soon
Bintulu Town District
97000 Bintulu,
Sarawak, Malaysia

Dear Madam,

Notification Of Scaffolding Works At Sibiyu 132/33 kV Substation Project

Please note that scaffolding works will take place as part of the above proposed Sibiyu
132/33 kV Substation Project located at Lot 142, Block 32, Kemena Land District,
Bintulu. The scaffolding works is expected to commence on October 16, 2019 and
may continue until January 20, 2021.

Please refer to attached document as listed below for details of scaffolding works:

i. Design Drawing and Calculation (with P.E. stamp)


ii. Method of Statement for Scaffolding Work

iii. Copy of Scaffold Inspector and Erector Certificate

iv. Scaffold Material Catalog

Pestech wishes to express sincere appreciation in advance for your cooperation and
understanding during the construction period.

Thank You.

“Consistently Dependable and Value Add”

PESTECH Sdn Bhd

_________________
Julius Jong
Project Manager

                           
       
Our Ref : PES(PSC)/18/016/1-098
Date : 15 October 2019

                           
       