0% found this document useful (0 votes)
53 views

44 Bricks

This document provides a cost derivation for standard bricks used in a flood control project in Cambodia. It breaks down the materials, labor, and equipment costs to calculate a total cost per unit of 27.99 for bricks measuring 80mmx80mmx175mm. Materials such as bricks, cement, and aggregates make up the largest portion of the cost at 16.28 per unit. Labor for foremen, skilled laborers, and general laborers contributes 5.03 per unit. Equipment like a bagger mixer and tools amounts to 2.62 per unit cost. Overhead and contractor profits are also included in the final cost calculation.

Uploaded by

GreatHavok
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
53 views

44 Bricks

This document provides a cost derivation for standard bricks used in a flood control project in Cambodia. It breaks down the materials, labor, and equipment costs to calculate a total cost per unit of 27.99 for bricks measuring 80mmx80mmx175mm. Materials such as bricks, cement, and aggregates make up the largest portion of the cost at 16.28 per unit. Labor for foremen, skilled laborers, and general laborers contributes 5.03 per unit. Equipment like a bagger mixer and tools amounts to 2.62 per unit cost. Overhead and contractor profits are also included in the final cost calculation.

Uploaded by

GreatHavok
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

UNIT COST DERIVATION

Project: NEAK LOEUNG FLOOD CONTROL SUBPROJECT


Item No.: 4.1.1
Description: Standard Bricks, 80mmx80mmx175mm
Quantity for Calculation (QC): 1
Unit: sqm

Work Item Unit Quantity Unit Cost Total Cost


1 Materials
1.1 Standard Bricks pcs 177.00 0.06 10.62
1.2 Reinforcing Bars kg 3.00 0.75 2.25
1.3 Cement bags 0.40 4.97 1.98
1.4 Fine Aggregates cum 0.05 11.65 0.58
1.5 GA 16 Tie Wires kg 0.1 1.09 0.08
1.6 Wastage (5% of 1.1 to 1.5) ls 1.0 0.77 0.77
-

Sub-Total 16.28
2 Labor
2.1 Foreman m-day 0.05 12.38 0.61
2.2 Skilled Laborer m-day 0.25 10.20 2.55
2.3 Laborer m-day 0.25 7.50 1.87

Sub-Total 5.03
3 Equipment
3.1 Bagger Mixer e-hr 0.50 5.00 2.50
3.2 Miscellaneous Tools ls 1.00 0.12 0.12
3.3 -

Sub-Total 2.62
4 Estimated Direct Cost (1 + 2 + 3) 23.93
4.1 Overhead (9% of 4) 2.15
4.2 Contractors Profit (8% of 4) 1.91
5 Value Added Tax (10% of 4 + 4.1 + 4.2) -
6 Total Cost (4 + 4.1 + 4.2 + 5) 27.99
7 Material Cost per Unit 16.28
8 Labor Cost per unit 5.03
9 Equipment Cost per unit 2.62
10 EDC per unit 23.93
11 Cost per unit (Total Cost/QC or 6/QC) 27.99

You might also like