Analytic Exercise - Product Design Project, Questions 1, 2, 3, 4, 5
Analytic Exercise - Product Design Project, Questions 1, 2, 3, 4, 5
Drawing of Project Networks that includes all the activities mentioned above is as follows:
2. - The start and finish time for all activities could be seen on every circle of activities as shown in the Project Networks above, with information as below:
ES EF Legend:
ES = Early Start
A (D) EF = Early Finish
LS LF LS = Late Start
LF = Late Finish
A = Activity
(D) = Duration of Activity
* All duration in this case is in WEEK
- The minimum number of weeks to complete the project activities as shown at the last activity (V2 : contract negotiation) is 40 Weeks
- The activities in the project that are critical path for completing the project in the shortest time (which the ES = LS or EF = LF) are:
P1; P2; P3; P4; S1; D2; D4; I1; I3; I4; V2. (From the Project Networks above, we can notice the critical activities those are in red circle).
3. Activities have slack (not on the project critical path; we mark in yellow circle), are:
- S2, slack = 22-16 = 28-22 = 6 week(s)
- D1, slack = 22-21 = 23-22 = 1 week(s)
- D3, slack = 22-21 = 23-22 = 1 week(s)
- V1, slack = 28-22 = 38-32 = 6 week(s)
- I2, slack = 26-23 = 30-27 = 3 week(s)
4. If we parallel the subproject, the CPM result will be