DPR
DPR
Grant: PMGSY
శధర శరర
9440557273
PRADHAN MANTRI GRAM SADAK YOJANA ( P M G S Y )
(Ministry of Rural Development ,Govt,of India)
Kadapa
namgaripalli to Ahobilapuram of Pulivendula (M) in YSR Kadapa
District
Page No.
PRADHAN MANTRY GRAM SADAK YOJANA (PMGSY)
Package summarry Proforma : B
Total
Estimated Average cost
cost per Km
Rs Rs
468.74 67.15
Yes No
Whether road deteriorated due non maintenance
Dondlavagu 1005
Balapanur 2444
Nakkalapalli 255
Total population 3704
Total weight
c) Utility value = Total weight/ Length of road
d) Does the Proposed Road lead up to the growth centre /hub or the road is
being made partially? Yes
i) Carriageway -
ii) Roadway 5.00
iii) Road Land Width 7.50
R&B Road
RG Road-
Road
slope 1:2
G.L
Item T
GSB
WMM
WMM
BT with SDBC
9
Light commercial
Trucks Agricultrual Tractors/ Trailers Buses
vehcicles
Motorised
Days
Cars, two wheelers
Jeeps, L UL L UL OL L UL OL L UL
Vans,
Three
wheelers
Day1 5 15 8 10 5 2 0 17 15 0 0 0
Day2 5 24 16 10 5 2 0 16 16 0 0 0
Day3 5 32 14 10 5 3 0 15 14 0 0 0
Total 15 71 38 30 15 7 0 48 45 0 0 0
Avg. 5 24 13 10 5 2 0 16 15 0 0 0
a ADT in the year of Traffic Count= 148
A= Intitial traffic in the year of completion of construction in terms of the number of commericial
vehicles per day
D= Lane distribution factor 1
F= Vehicle damage factor
n= Design life in years 10
r= growth rate adopted % 6%
N= The cumulative number of standard axles to be catered for the design in terms of msa
CVPD 151
10 Sub-grade CBR
Chainage 0/4-0/6 1/2-1/4 2/4-2/6 3/2-3/4 4/4-4/5 5/5-5/7 6/2-6/4
Design CBR (%) 3.80 3.90 3.80 3.90 3.90 3.8 3.90
11 Cost Details
A. Pavement components
10
Thick
Description of the Layer ness Qty. Cost (Rs
(mm)
GSB
WBM
Dense lean concrete
Quantity of Concrete Pavement
Pavement Quality Concrete(M30) 555.00 29
B). CD Works :
Location - Chainage ( Similar Type of CD's may be grouped together) Type of CD & their Nos Total Length of Culv
C. Protection works
Chainage
11
From To Length( m)
I 6.98
II 6.98
III 6.98
IV 6.98
V 6.98
Total Maintenance Cost
13 Whether the road has geometric as per rural roads manual (RRM) / Latest circulars of
NRRDA
12
14 Whether CD Works / Protetion Works Provided as per RRM / Latest circulars of NRRDA
/ Respective Codes
15.Does the Estimation Conform to Standard Rate Analysis and SSR generated for the current Phase
SSR 2018-19
21 In case, sub grade CBR is less than 5; has Soil Stabilisation etc. been proposed
22 Is the design of the following elements as per Rural Roads Manul / Circulars of NRRDA:
Is the design of flexible Pavement as per IRC 37 2001 and design of Rigid Pavement as per IRC SP:58- 1998.
Certified that the Design and Estimation for the Proposed Road work are based on the data and SSR pro
Engineers . The Proposal after final Correction is entered on the OMMS.The Propasal may be considered
14
Certified that the Design and Estimation for the Proposed Road work are based on the data and SSR pro
Engineers . The Proposal after final Correction is entered on the OMMS.The Propasal may be considered
Name Signature
Date Name
Date
15
KM
Year of completion
50.87
209.56
13.10
273.53
L 0 6 0
Overall
Weightage
No
NH
16
No
YES / NO
In the Built Up Area (m) In the Open Area
(m)
- -
5.00 6.00
7.50 10.00
Thickness
mponent layers
slope 1:2
G.L
Thickness
150
75
75
25
18
Animal Drawn
Buses
Cycle Rickshaws
Vehicles
Total
Cycles
Num Tyred
OL SWC
0 30 0 30 0 137
0 29 0 29 0 152
0 27 0 28 0 153
0 86 0 87 0 442
0 29 0 29 0 148
184.49 Nos.
170,353
10
6%
151
177.82 25.476
42.69 6.116
10.73 1.537
0.89 0.128
56.99 8.164
10.84 1.553
2.44 0.350
45.54 6.524
0.000
0.00 0.000
347.94
0
0
0
29.34 209.555
59.19
11.63
20.64
91.46
20
0.00
0.00 0.00
0.00 0.00
Average
Cost in Rs
cost / m
Cost in Rs Average
cost / km
0.00
14688.00
15226.00
18761.00
6155.00
62728.00
1001052.00
22548.00
455672.00
1596830.00 2.288
Err:509
Err:509 Err:509
KM Cost /Km
6.98 0.465
6.98 2.327
6.98 2.327
6.98 4.188
6.98 4.653
13.96
6667.00 46536.00
33333.00 232664.00
33333.00 232664.00
60000.00 418800.00
66667.00 465336.00
1396000.00
YES
21
YES
Vetted at
NRRDA Year
Yes No
√ ~ 2018-19
Chennai 325.00
Chennai 325.00
AT SITE 0.00
Scrutinized by
chnical Agency
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YSR Kad
[2] Name of the Members of the STA involved in the Technical scrutiny
[3] Whether Pre-DPR meeting was held with SRRDA and DPIUs
[4] Summary of the Project Proposals scrutinized indicating district wise road wise detailes of length and c
includes the No. of packages and total value
[5] Whether schedule for scrutiny was fixed in advance ( give detailes) and difficulty in adhering to schedule
[6] Actual scrutiny process and time taken for scrutiny ( Please indicate the dates)
[7] Interaction of the Engineers fo the Executing Agencies with the STAs
[9] Reliability of data obtained through investigations and used in the design/estimation
[10] Compliance of the provisions / instructions given in the guidelines / circulars / operations manula / IRC
prepareation of DPRs including Environmental / RR / Road safety aspects etc.,
[11] Levels of repsonse from the Senior Engineers of the Executing Agencies for the suggestions
[12] If DPRs outourced, Perceived level of competence of outsourced consultants and suggestions
[13] Overall comments and impression of the STAs. If any on the process of the preparation of DPRs
scrutiny
Name of th
TRI GRAM SADAK YOJANA ( P M G S Y )
of Rural Development ,Govt,of India)
YSR Kadapa
Year: 2018-19
d indicating district wise road wise detailes of length and cost. The summary
ith details
iven in the guidelines / circulars / operations manula / IRC codes etc., in the
al / RR / Road safety aspects etc.,
TAs. If any on the process of the preparation of DPRs and their technical
Signature and
Name of the Co ordinator STA
PRADHAN MANTRI GRAM SADAK YOJANA
(Ministry of Rural Development, Govt.of India)
FORMAT - F1
SUMMARY SHEET
ANNEXURE-7
DISTRICT : YSR Kadapa Block : Simhadripuram Package No :
Unconnected Habitations
Name of the Block Total No.of Habitations
>1000 500-1000 250-500 <250
1 2 3 4 5 6
Simhadripuram 3 2 0 1 0
1 2 3 4 5 6 7 8 9
Upgradation 1 6.98 16 469.79 50.21 520.00 3
New Connectivity
other upgradation
Total 1 6.98 16 469.79 50.21 520.00 3.00
ANNEXURE-7.A
PRADHAN MANTRI GRAM SADAK YO
( Ministry of Rural Development, Govt. of
Facility
Road Existing
S.No.
accessed
Name of Block Length Surface
Use
(Km) Type Clearing
A/B/C/D
Details and Earthwork
Grubbing
From To N A U
1 2 3 4 5A 5B 5C 6 7 8 9 10 11
Thickness
1 Simhadripuram Dondlavagu Balapanur N D 6.98 Earthen Rising
(mm)
Other
unforese Total cost
WBM Gr.III
WBM Gr.II
B.O.E.
Sub-Grade en of
WMM
Sub Base Edging
preparatio CC Road items/ Pavement(
GSB Gr.III (shoulde
n GSB Gr.I Prime Tack Seal Road sum of 10
rs) PC
coat Coat coat furniture to 22)
& BM
12 13 14 15 15A 16 17 18 19 20 21 22 23
150 0 0 150 25
0.00 42.69 56.99 10.73 29.34 10.84 2.44 45.54 92.51 469.79
DY.Executive Engineer Asst Executive Engineer
PIU SubDivision PIU SubDivision
Mydukur Mydukur
PRADHAN MANTRI GRAM SADAK YOJANA
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
to
Balapanur
16
19 20
469.79 520.00
Block : Simhadripuram
District:
1 2 3 4 5 6 7 8 9 10 11 12 13
to .
Balapanur
YSR Kadapa
ad Details
Bituminous Layer
14 15 16
Block : Simhadripuram
District:
Sl.N Package No. Primary net work Associated PCI Age Whether proposed Other non Whether includes
o. through for Upgradation confirmance in package Y/N
Route (ATR) subsidary to
No. Habitation served (with the ATR
population)
1 2 3 4 5 6 7 8 9 10
1 PMGSY 3 3704 Yes
Dondlavagu 1005
Balapanur 2444
Nakkalapalli 255
YSR Kadapa
11
3704
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YSR Kadapa District
[1] (a) Certified that the land width for the roads is availabe and that no additional land is required
(b) Certified that the land width for the roads is likely tobe available as certified by the Panchyats
[2] (a) Certified that no forest land is involved along the entire road way
[OR]
(b) Certified that the case for permission under Forest conservation Act has been moved to the
Forest Department on ( Date )
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YSR Kadapa District
2 Dy.E.E.
3 E.E.
4 S.E.
Head of PIU
Executive Engineer
PIU Division Kadapa
Table 5.1 Average Daily Traffic at {Insert location} (both ways) {The table will be repeated for the number of
locations surveyed. This must include counts taken on the similar road.}
Average
5
14
24
0
7
31
0
29
0
29
0
138
81
58
Table 5.2 Average Annual Daily Traffic at {Insert location} (both ways) {This table will be repeated for each homogeneous
Sl. No. Type of Vehicle ADT AADT
2 Auto Rickshaw 14 17
3 Scooters/Motorbikes 24 30
4 Bus / Minibus 0 0
5 Trucks 7 9
8 Cycles 29 36
11 Pedestrian 0 0
0.06
0.06
0.06
0.06
0.06
0.06
0.06
0.06
0.06
0.06
0.06
0.06
0.06
0.06
SUMMARY OF 3 - DAY COUNT
Cycles 30 29
Laden 5 5
Trucks
Unladen 2 2
Laden 0 0
Buses
Unladen 0 0
Laden 17 16
Agricultural
Tractors / Trailers
Unladen 15 16
Medium Laden 8 16
commercial
vehicles
Unladen 10 10
Cars, Jeeps,
Vans, Three 5 5
wheelers
148 +
148 +
AADT = 184.49
184.49
207.30
No. of Vehicles 5 2 29
Proportion of
projected AADT / 1.401 1.401 1.401
ADT
No. of Vehicles
Based on daily 7 3 41
count
VDF
20.03 0.87 13.81
Conslidated
ESAL / DAY
4811 35.41
ESAL 170353
Pavement Thickness Design
Design data
28 87 29
27 86 29
32 71 24
5 15 5
3 7 2
0 0 0
0 0 0
15 48 16
14 45 15
14 38 13
10 30 10
5 15 5
365
2 X 148 X 0.6 X 75
365
13320
365
36.49
ADT X (1.06)2
eration)
MCV Unladen
25
1.401
35
0.02
0.70
35.41
Nos / day
mm / annum
300 mm
To 9AM Hrs
To 12NOON Hrs
To 3PM Hrs
To 6PM Hrs
Day Total 5 15 8 10 5 2 17 15 0 30 0 30
Record traffic volume by tally marks (four vertical strokes followed by a diagonal stroke for the 5th vehicle ( IIII IIII II )
Remarks
Season: Post
Harvest/ Monsoon,
Weather
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YSR Kadapa District
To 9AM Hrs
To 12NOON Hrs
To 3PM Hrs
To 6PM Hrs
Dry Total 5 24 16 10 5 2 16 16 0 29 0 29
Record traffic volume by tally marks (four vertical strokes followed by a diagonal stroke for the 5th vehicle ( IIII IIII II )
Remarks
Season: Post
Harvest/ Monsoon,
Weather
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YSR Kadapa District
To 9AM Hrs
To 12NOON Hrs
To 3PM Hrs
To 6PM Hrs
Day Total 5 32 14 10 5 3 15 14 0 27 0 28
Record traffic volume by tally marks (four vertical strokes followed by a diagonal stroke for the 5th vehicle ( IIII IIII II )
Remarks
Season: Post
Harvest/ Monsoon,
Weather
PART-B (MAINTENANCE)
Block : Simhadripuram
District:
Sl. Effective Length in
Description Rate / KM
No. KM
1 2 3 4
Maintence cost for the defective Liability
1
Period for BT roads
TOTAL
PART-B (MAINTENANCE)
PMGSY
YSR Kadapa
Amount
46536.00
232664.00
232664.00
418800.00
465336.00
1396000.00
DETAILED ESTIMATE
Date of : 13-08-2018
Inspection
The work " Providing BT to the Road from Kadapa-Kurnool Road @ Bhumayapalli to Santhinagaram via
Muthalurupadu,Krishnampalli in Khajipet (M) in YSR Kadapa District",which was administratively sanctioned for Rs
under Panchayat Raj Assets Grant vide Go.Rt.No 952 ,dt:27.07.2018 of PR&RD (Progs.II) Dept.It is Single connective
villages Bhumayapalli,Muthalurupadu,Moolavaripalli and Krishnampalli .The total lengthof the road is 5.300 km .Th
road surface is km 0/0-3/650 Badly damaged BT Surface with PCI value 1 & in Km 3/650-5/300 earthen surface ., In
road along the above staff and instructed to prepare detailed estimate with the following items which are necessar
conditions.
1 As there is stream ,for crossing it is instructed to provide 1Vx2.00Mt Slab culvert in Km 0/2-0/4
As there are stream ,for crossing it is instructed to provide 1000mm Dia Pipe culvert in Km 0/4-0/6
2 2/0,3/8-4/0 (3No).
As there are field channels ,for crossing it is instructed to provide 600mm Dia Pipe culvert in Km 2/
3 3/2,3/6-3/8,3/8-4/0 (4Nos).
4 As there is existing damaged culvert in Km 0/8-1/0,it is instructed to provide repairs to the existing
It is instructed to Provide Prime coat, Tack coat, SDBC 25 mm thick in to a compacted thickness of 25 mm in
10 0/300,0/600-1/800,2/850-3/650, 4/350 - 5/300.
It is instructed to provide CC Pavement of M30 Grade to a compacted thickness of 170 mm in KM 0/300-0/
11 2/220,2/700-2/850 and 3/650-4/350 .
12
It is instructed to provide Selected earth shoulders of 1.125 Mtr width & 150 mm compacted thick in KM 0/
The Executive Engineer , PIU Division ,Kadapa and Deputy Executive Engineer, PIU S
Mydukur are instructed to prepare the detailed estimate duly providing the above provisions.
SUPERINTNEDING ENGINEE
P.R.CIRCLE, KADAPA.
Y.S.R.DISTRICT.
To
The Executive Engineer, PIU division, Kadapa,
Copy to the Dy.Executive Engineer, PIU subdivision, Mydukur.
Copy submitted to the Chief Engineer , PR , Vijayawada for favour of information.
ENDING ENGINEER, P.R.CIRCLE, KADAPA.
bba Reddy, M.TECH.,
eer, PRI,Jammalamadugu
ation canal.
with carted earth in km 4/350-5/300 and Widen the road with
SUPERINTNEDING ENGINEER,
P.R.CIRCLE, KADAPA.
Y.S.R.DISTRICT.
favour of information.
KEY MAP
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YSR Kadapa District
0/740
0/0
Krishnamgaripalli
SUPERINTENDING ENGINEER, EXECUTIVE ENGINEER, DY.EXE.ENGINEER, ASST. EXE ENGINEER,
PANCHAYATIRAJ, KADAPA PIU DIVISION, KADAPA PRI SUB DIV Pulivendula PRI SUB DIV Pulivendula
dapa District
EXE ENGINEER,
UB DIV Pulivendula
STRIP MAP
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of
Pulivendula (M) in YSR Kadapa District
MUTHALURUPADU-SANTHINAGARAM
5/300
2/850
Proposed 600mm Dia PC
2.700
Existing CC road
2.200
1.800
0.600
Proposed 1000mm Dia PC
0/0
KADAPA-KURNOOL ROAD
This road connecting Dondlavagu, Balapanur & Nakkalapalli villages . This road is Multi connectivety to this
villages .The total length of the road is 6.980 km .The existing road surface is km 0/0-6/980 earthen surface ., It is proposed to
strengthen the road up to BT standards to with stand future traffic.
Provisions of Estimate:
1 Providing clearing and grubbing road land at km 0/0-7/050
5 Providing Prime coat, Tack coat, SDBC 25 mm thick in to a compacted thickness of25 mm in KM 0/820-7/050
6 Providing Selected earth shoulders of 1.875 Mtr width & 150 mm compacted thick in KM 0/0-7/050
Construction of 1000 mm dia pipe culvert in Km 0/000, 0/620, 1/115, 1/360, 1/507, 1/900, 3/300, 3/380, 3/500, 3/840,
9 4/030, 4/320, 4/465, 4/630, 4/800, 4/940, 6/350, 6/385, 6/730, 6/820, 7/043 -Total 21 Nos
d thick in KM 0/0-7/050
per APDSS
ASST.Exe. ENGINEER
PRI SD PULIVENDULA
EXECUTIVE ENGINEER,
PR DIVISION Jammalamadugu
GENERAL ABSTRACT
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of
Pulivendula (M) in YSR Kadapa District
Total
4 Add GST @ 12 %
9 Unforeseen items
Lakhs
Amount
37727678
1596830
5918808
1163251
2064186
48470753
5816490
242354
48471
105750
2574408
741774
58000000
EXECUTIVE ENGINEER
PR DIVISION Jammalamadugu
COST ESTIMATE FOR ROAD CONSTRUCTION
KM 0/0- 7/050
1 X 2 7050.00 2.00 28200.00
28200.00
deduct Voids 40%
-11280.00
45120.00 1.98
sqm
2 Construction of embankment with Selected earth obtained from borrow pits with all
lifts, transporting to site, spreading, grading to required slope and compacting with
vibratory roller 80-100 KN to meet requirement of Tables 300.1 and 300.2 with a lead
upto 1000 m as per Technical Specification Clause 301.5 MORD including contractors
profit & Over head charges but excluding , Seigonarage charges & GST
47911.72 371.14
Cum
3 Construction of granular sub-base by providing well graded material(Table 400.1)
with Grading III Material(HBG M/C +Stone dust) CBR Value not less than 20 and PI
Value less than 6 spreading in uniform layers with Tractor grader on prepared
surface, mixing by mix in place method with rotavator at OMC, and compacting with
Vibratory Roller to achieve the desired density, complete as per Technical
Specification Clause 401 MORD .including contractors profit & Over head charges but
excluding , Seigonarage charges & GST
Page 86 of 296
S.No Description No Measurments Quantity Rate / per
L B D
Deduct for BT ROAD CROSSING
in km 6/360-6/380 1 X 1 20.00 4.00 0.15 -12.00
4209.00 1014.31
cum
4 Providing, laying, spreading and compacting graded stone aggregate to wet mix
macadam specification including premixing the material with water at OMC in
mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in
uniform layers in sub-base/base course on a well prepared sub-base and compacting
with smooth wheel roller of 80 to 100kN / Vibratory Roller 80-100 kN weight to
achieve the desired density including lighting, barricading and maintenance of
diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406
MORD/ MORTH,including overhead charges & Contractor profit, But excluding GST
3484.69 1635.31
cum
5 Providing and applying Prime coat with bitumen emulsion (SS-1) on prepared surface
of granular base including cleaning of road surface and spraying primer at the rate of
0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502
MORD (for use on Wet mix macadam & WBM) ,including overhead charges &
Contractors profit etc., Complete but Excluding GST for Prime Coat
23231.25 46.66
sqm
Page 87 of 296
S.No Description No Measurments Quantity Rate / per
L B D
6 Providing and applying Tack coat with Bitumen emulsion (RS-1) using emulsion
distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces
treated with primer & cleaned with Hydraulic broom as per Technical Specification
Clause 503 MORD,including overhead charges & Contractors profit etc., Complete
but Excluding GST for Tack Coat
23231.25 10.51
sqm
7 Providing and laying Semi dense bitumious concrete with 40-60 TPH batch type HMP
producing a average output of 37.5 tonnes per hour using chrushed aggreates of
specified grading,premixed wetbituminous binder &4.5 to 5 percent of mix and
filter,tranporting the hot mix to work site,layingwith a hydrostatic paver finisher with
sensor control to the required grade,level and alighment,rolling with smooth
wheeled, vibratiry and tandem rollers to achieve the desirod compaction as per
MORT Specification clause NO,508, Complete in all respects , including overhead
charges & Contractors profits but execluding GST,seignarage charges
580.77 7840.70
Cum
8 Construction of Improved sub-grade/Shoulders by providing selected earth having
MDD not less than 1.85 g/cc with LL & PI not more than 40% and 20 respectively and
spreading in uniform layers with tractor grader on prepared surface and compacted
at OMC with vibratory roller 80-100 kN to achieve the desired density complete as
per IRC Technical Specification Clause 303 MORD by using machinery including all
overheads and contractor's profit but excluding GST and Seigniorage charges.
Page 88 of 296
S.No Description No Measurments Quantity Rate / per
L B D
3965.63 270.59
cum
Page 89 of 296
S.No Description No Measurments Quantity Rate / per
L B D
9 Construction of un-reinforced, dowel jointed at expansion and construction joint
only, plain cement concrete pavement, thickness as per design, over a prepared sub
base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade),
coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of
not less than 0.2 cum capacity and appropeiate weigh batcher using approved mix
design, laid in approved fixed side formwork (steel channel, laying and fixing of 125
mictron thick polythene film, wedges, steel plates including levelling the formwork as
per drawing), spreading the concrete with sholvels, rakes, compacted using needle,
scareed and plate vibrators and finished in continuous operation including provision
of contraction and expansion, construction joints, applying debonding strips, primer,
sealant, dowel bars, near approaches to bridge / culvert and construction joints,
admixtures as approved, curing of concrete slabs for 14- days, curing compound
(where specified) and water finishing to lines and grade as per drawing and Technical
Specification Clause 1501 MORD.including overhead charges & Contractors profit but
excluding GST and seinorage
Page 90 of 296
ATE FOR ROAD CONSTRUCTION
89338
17781956
Page 91 of 296
Amount
4269231
5698548
1083970
Page 92 of 296
Amount
244160
4553643
Page 93 of 296
Amount
1073058
Page 94 of 296
Amount
2933774
37727678
Page 95 of 296
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YSR Kadapa Distric
for abutments
1 st step 1x 2 8.70 1.700 0.40 11.83
2 nd step 1x 2 8.30 1.500 0.40 9.96
3 rd step 1x 2 7.90 1.300 0.40 8.22
For Wing walls
1 st step 1x 4 2.00 1.600 0.40 5.12
2 nd step 1x 4 2.00 1.400 0.40 4.48
3 rd step 1x 4 2.00 1.200 0.40 3.84
Cu.m 43.45 3784.50
Plain cement concrete M 15 grade using 40,20 & 10mm metal
mechanically mixed in substructure complete as per drawings and
4 technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204
MORD and 1500, 1700 & 2200 MORTH ,including overhead charges &
Contractors profit but excluding GST.
for abutments
Body Wall (1.0+0.7)/2 1x 2 7.50 0.850 1.00 12.75
For Wing walls
Body Wall (0.90+0.40)/2 1x 4 2.00 0.650 1.40 7.28
Cu.m 20.03 4002.90
Providing and laying reinforced cement concrete M25 grade (Design Mix)
using 20 & 10mm metal mechanically mixed in substructure as per
5 drawing and technical specifications Clauses 800, 1205.4 and 1205.5
MORD / Sections 1500, 1600 & 1700 MORTH ,including overhead charges
& Contractors profit but excluding VAT upto 5m height.
Providing and laying reinforced cement concrete M25 grade (Design Mix)
using 20 & 10mm metal mechanically mixed in superstructure as per
6 drawing and technical specifications Clauses 800, 1205.4 and 1205.5
MORD / Sections 1500, 1600 & 1700 MORTH ,including overhead charges
& Contractors profit but excluding GST upto 5m height.
Amount
10678
62724
164437
80178
19242
35342
9896
6735
4014
21188
34017
448451
T.EXE. ENGINEER
DIVISION, MYDUKUR
CUTIVE ENGINEER
DIVISION , KADAPA
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in Y
V.C.C. M 15
340
Parapet
40
24
20 70
2.00
144
100
G.L. 10 100 20
130
40 0
40 150 20
150 40 20
170
190
30
620
620
460
Note: All dimensions without units are in Cms. CROSS SECTION C.C. -M10
70
130
150
170
225
gineer, Asst. Exe Engineer,
vision , P.I.U. Sub Division,
Mydukur
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of
Pulivendula (M) in YSR Kadapa District
Construction of 2-00 m Span - Slab Culvert
20
20
20
40
16
0
50
2
0
0
Name of the sub Work : Construction of 1m span RCC slab culvert (5 Nos) at km 0/3, 2/6, 3/2, 3/220, 4/2
Measurments
S.No Description No Quantity Rate Amount
L B D
1 Earthwork in excavation for structures as per drawing and technical
specifications Clause 305.1 including setting out, construction of shoring and
bracing, removal of stumps and other deleterious material and disposal upto a
lead of 50 m, dressing of sides and bottom and backfilling in trenches with
excavated suitable material as per Technical Specification 305 MORD / 304
MORTH ,including overhead charges & Contractors profit but excluding VAT and
seigniorage charges - For Foundations
Levelling course
Footings
For Abutments
1 st step 1 x 2 8.10 1.70 0.30 8.26
2 nd step 1 x 2 7.80 1.50 0.30 7.02
3 rd step 1 x 2 7.50 1.30 0.30 5.85
Wing walls '1st footing 1 x 4 2.45 1.325 0.90 11.69
(1.5+1.15)/2 32.82 3784.50 124202
Cum
Abutments
Abutments 1 x 2 7.50 0.85 1.00 12.75
(1.0+0.7)/2 = 0.85
Wing walls 1 x 4 2.45 0.700 1.00 6.86
(1.0+0.4)/2 = 0.70
Bed blocks
Bed blocks 1 x 2 7.50 0.70 0.20 2.10
Dirt walls 1 x 2 7.50 0.40 0.21 1.26
3.36 5435.70 18264
Cum
6 Providing and laying reinforced cement concrete M25 grade (Design Mix) using
20 & 10mm metal mechanically mixed in superstructure as per drawing and
technical specifications Clauses 800, 1205.4 and 1205.5 MORD / Sections 1500,
1600 & 1700 MORTH ,including overhead charges & Contractors profit but
excluding VAT and seigniorage chargesupto 5m height. - For Super Structure
(Deck slab)
3 x 7 1.00 21.00
21.00 841.90 17680
Rmt
9 Cost, supply and fixing of Bituminous Mastic pad 12.7 mm including cost and
conveyance and all labour charges etc., complete
Sub estimate is technically approved for Rs.3,54,140/- (Rupees Three lakhsfifty four thousand one hundered and
forty only)
O/c
So4 PA SE, PR, KDP
1 2 3 4 5 6 7 8 9
1 Earthwork excavation for foundation of structures upto 3 m
depth as per drawing and technical specification Clause
1104 including setting out,Construction of shoring and
bracing,removal of stumps and other deleterious matter
,dressing of sides and bottom and backfilling in trenches
with excavated suitable material as per MORD
specification 300 & 1100
Deduct for Pipe portion 0.8 x 1 -6.20 0.75 0.75 Cu.m -2.79
wing walls
1.00 x 2 4.00 0.80 2.00 Cu.m 12.80
(1.2+0.40)/2
parapet 1.00 x 2 4.00 0.30 0.30 Cu.m 0.72
Deduct for Pipe portion 0.80 x 2 -0.80 0.75 0.75 Cu.m -0.72
Total
SUPERINTENDING
EXECUTIVE ENGINEER
ENGINEER
rt at km 2/6-2/8,3/0-3/2,3/6-3/8,3/8-4/0 (4Nos)
Amount
(Rs.)
10
2236
14175
64639
25706
106756
427023
ASST.EXE. ENGINEER
PIU,SUB DIVISION, MYDUKUR
EXECUTIVE ENGINEER
2 Providing & fixing of typical PMGSY informatory sign board as per MORD
secifications and drawing. Three MS plates of 1.6mm thick, top and middle plate
duly welded with MS flat iron 25mmx5mm size on black on edges. The lower plate
will be welded with MS angle iron frame of lower most plate and flate iron frame of
middle plate will be welded to 2 nos 75mmx75mm of 12 SWG sheet tubes posts duly
embedded in CC M15 grade blocks of 450mmx450mmx600mm, 600mm below
ground level. The top most diamond plate will be welded to middle plate by
47mmx47mm of 12 SWG sheet plate tube. All MS will be stove enmeled on both
sides. Lettering and paining of superior quality in required shede and colour. All
sections of framed posts and sheet tube will be painted with primer and two coats of
epoxy paint as per drawing clause 1701 and annexure 1700.1 if MORD excluding
GST & seineorage charges
At Speed breakers
triangular portion prime
coat+tack coat 8 3.75 1.25 37.50
At Speed breakers
triangular portion SDBC
25 mm thick layer 8 3.75 1.25 0.01 0.49
Amount
14688
15226
18761
6155
62728
996840
4212
7048
4288
11212
455672
1596830
CUTIVE ENGINEER,
SION Jammalamadugu
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YS
Kadapa District
1 2 3 4 5 6 7 8 9
2 Filling in foundation trenches for Pipe bedding with Sand as per drawing and
technical specification Clause 305.3.9 MORD & 304 MORTH ,including overhead
charges & Contractors profit but excluding GST and seigniorage charges.
5 Providing and laying reinforced cement concrete M25 grade (Design Mix)
using 20 & 10mm metal mechanically mixed in Substructure as per
drawing and technical specifications Clauses 800, 1205.4 and 1205.5
MORD / Sections 1500, 1600 & 1700 MORTH ,including overhead charges
& Contractors profit but excluding GST upto 5m height.
5 Providing and laying reinforced cement concrete M25 grade (Design Mix)
using 20 & 10mm metal mechanically mixed in superstructure as per
drawing and technical specifications Clauses 800, 1205.4 and 1205.5
MORD / Sections 1500, 1600 & 1700 MORTH ,including overhead charges
& Contractors profit but excluding GST upto 5m height.
TOTAL:
10
30827
20346
133754
389463
31615
160743
21863
60617
8027
27165
278831
1163251
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YS
Kadapa District
1 2 3 4 5 6 7 8 9
3 Plain cement concrete M 15 grade using 40,20 & 10mm metal mechanically
mixed in substructure complete as per drawings and technical specification
Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200
MORTH ,including overhead charges & Contractors profit but excluding GST.
4 Providing and laying reinforced cement concrete M25 grade (Design Mix)
using 20 & 10mm metal mechanically mixed in Substructure as per
drawing and technical specifications Clauses 800, 1205.4 and 1205.5
MORD / Sections 1500, 1600 & 1700 MORTH ,including overhead charges
& Contractors profit but excluding VAT upto 5m height.
5 Providing and laying reinforced cement concrete M25 grade (Design Mix)
using 20 & 10mm metal mechanically mixed in superstructure as per
drawing and technical specifications Clauses 800, 1205.4 and 1205.5
MORD / Sections 1500, 1600 & 1700 MORTH ,including overhead charges
& Contractors profit but excluding VAT upto 5m height.
TOTAL:
10
20188
54308
120044
880158
23156
160530
21553
60617
8027
27165
167298
1543044
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS
for apron toe wall U/S 1 x 1 40.00 0.60 0.15 Cu.m 3.60
for apron toe wall D/S 1 x 1 40.00 0.60 0.15 Cu.m 3.60
for apron toe wall D/S 1 x 1 40.00 0.40 0.60 Cu.m 9.60
237.24 3784.50
TOTAL:
SUPERINTENDING
EXECUTIVE ENGINEER
ENGINEER
27626
375659
10
897835
113738
312251
10
317165
19912
2064186
2064186
ASST.EXE. ENGINEER
PRI SD PULIVENDULA
EXECUTIVE ENGINEER
PR DIVISION Jammalamadugu
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS
Construction of 1000 mm dia pipe culvert in Km 0/000, 0/620, 1/115, 1/360, 1/507, 1/900, 3
3/380, 3/500, 3/840, 4/030, 4/320, 4/465, 4/630, 4/800, 4/940, 6/350, 6/385, 6/730, 6/820, 7
-Total 21 Nos
Sl.N Description of Number L B D Unit Quantity Rate
o. items (Rs.)
1 2 3 4 5 6 7 8 9
47.02 3784.50
1 2 3 4 5 6 7 8 9
TOTAL:
SUPERINTENDING
EXECUTIVE ENGINEER
ENGINEER
Amount
(Rs.)
10
6997
30472
177947
10
62450
3982
281848
281848
ASST.EXE. ENGINEER
PRI SD PULIVENDULA
EXECUTIVE ENGINEER
PR DIVISION Jammalamadugu
HYDRAULIC PARTICULARS
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M
in YSR Kadapa District
Superintending Engineer,
PR Circle : YSR Kadapa
m of Pulivendula (M)
Acres
Sqm
Sq.Km.
Cumecs.
Mtrs/Sec.
Sqm.
Sqm.
Exe Engineer,
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in Y
V.C.C. M 15
740
Parapet
40
48
20 70
6.00
238
170
G.L. 10 130 20
160
45 0
45 180 20
165 45 20
200
190
30
620
620
910
Note: All dimensions without units are in Cms. CROSS SECTION C.C. -M10
70
160
180
200
225
gineer, Asst. Exe Engineer,
endula PRI SD Pulivendula
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivend
in YSR Kadapa District
Construction of 6-00 m Span - Slab Culvert
Parapet
600
91
0
75
0
Parapet
70
PLAN OF 6.00 M SPAN SLAB CULVERT 160
180
200
910
910
79
0
870
gineer,
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of
Pulivendula (M) in YSR Kadapa District
Construction of 6-00 m Span - Slab Culvert
20
20
20
40
18
0
80
1
0
0
0
WINGS PLAN OF 6.00 M SPAN SLAB CULVERT
for Protection
Wall
1 x 1 15.00 1.30 1.00 Cu.m 19.50
Cu.m 19.50 94.90
2 PCC M10 (1:3:6 nominal mix) in levelling course below open
foundation of Head walls as per drawings & Technical
Specification 802,803,1202 & 1203 and MORDClause 1109
for Protection
Wall
Amount
(Rs.)
9
1851
20029
154975
176855
E. ENGINEER
ISION, MYDUKUR
VE ENGINEER
SION , KADAPA
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M)
in YSR Kadapa District
4.77 3784.50
TOTAL:
Amount
3520
18052
21572
E. ENGINEER
ISION, MYDUKUR
VE ENGINEER
ION , KADAPA
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M)
YSR Kadapa District
Amount
157803
157803
E. ENGINEER
ISION, MYDUKUR
VE ENGINEER
ION , KADAPA
Seigniorage Charges
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YSR Ka
District
S No Description of Work Quantity Unit Description of Total Quantity Seignorage
(Finished item ) Material of Material Charges / Cum
Collected
1 2 3 4 5 6 7
Construction of 1000 mm dia pipe culvert in Nos 21
Km 0/000, 0/620, 1/115, 1/360, 1/507, 1/900,
3/300, 3/380, 3/500, 3/840, 4/030, 4/320,
4/465, 4/630, 4/800, 4/940, 6/350, 6/385,
6/730, 6/820, 7/043 -Total 21 Nos
Road Furniture
1 HM stones 28 No Earth 38.92 30.00
Metal 35.392 75.00
Sand 21.2352 50.00
2 Ordinary Km stone 8 No Earth 22.16 30.00
Metal 24.128 75.00
Sand 14.4768 50.00
32955.30
9043.50
3014.50
38984.25
15594.00
9745.20
2637.00
879.00
6174.75
1975.92
2227.50
742.50
285.00
95.00
8733.30
7406.25
2468.50
14234.25
4554.96
1620.00
540.00
4050.00
1350.00
1437351.60
378810.00
118968.90
347598.00
1167.60
2654.40
1061.76
664.80
1809.60
723.84
15.12
30.24
12.10
151.20
302.40
120.96
11.34
22.68
9.07
2574407.79
2574408.00
2 Sand at kummarampalli
SUPERINTENDING ENGINEER
PANCHAYATIRAJ CIRCLE , KADAPA
LEAD CHART (2019-20)
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YSR Kadapa District
1 2 3 4 5 6 7 8 9 10 11 12
FOR ROAD WORKS
1 Selected Earth Local 10.00 55.00 131.80 15.79 116.01 0.00 0.00
2 60-63mm HBG metal Rayalapuram 10.00 399.05 131.80 15.79 116.01 70.00 0.00
IRC, MORTH & MORD
3 50 -55mm HBG Metal Rayalapuram 10.00 434.30 131.80 15.79 116.01 70.00 0.00
IRC, MORTH & MORD
4 40-45mm HBG M/c Metal Rayalapuram 10.00 560.00 131.80 15.79 116.01 70.00 140.00
IRC, MORTH & MORD
5 40-45mm HBG hand broken Metal Rayalapuram 10.00 560.00 131.80 15.79 116.01 70.00 0.00
IRC, MORTH & MORD
6 25-27mm M/c HBG Metal Rayalapuram 10.00 899.05 131.80 15.79 116.01 70.00 224.76
IRC, MORTH & MORD
7 19 - 22mm HBG M/c metal Rayalapuram 10.00 937.15 131.80 15.79 116.01 70.00 234.29
IRC, MORTH & MORD
8 19 - 22mm HBG Hand broken Rayalapuram 10.00 937.15 131.80 15.79 116.01 70.00 0.00
metal
IRC, MORTH & MORD
9 12-14 mm HBG M/c Metal Rayalapuram 10.00 742.85 131.80 15.79 116.01 70.00 185.71
IRC, MORTH & MORD
10 9.5-11.2 mm HBG M/c Metal Rayalapuram 10.00 624.75 131.80 15.79 116.01 70.00 156.19
IRC, MORTH & MORD
12 2.36 - 5 mmHBG M/c Metal Rayalapuram 10.00 293.35 131.80 15.79 116.01 70.00 73.34
IRC, MORTH & MORD
13 BT Emulsion SS 1 (Chennai) dt. Chennai 325.00 45970.00 1072.50
01.12.2018
14 BT Emulsion RS (Chennai) dt. Chennai 325.00 27510.00 1072.50
01.12.2018
15 BT (60/70 grade) (CHENNAI) dt. Chennai 325.00 35050.00 1072.50
01.12.2018
FOR CD WORKS
16 Sand for filling Local 5.00 375.00 75.30 9.02 66.28 0.00 0.00 0.00
17 Sand for Concrete Kummarampalli 39.00 510.00 442.40 53.01 389.39 0.00 0.00
18 Sand for mortar/ plastering Kummarampalli 39.00 510.00 442.40 53.01 389.39 0.00 0.00
19 40 mmHBG M/c Metal-SS5 Rayalapuram 10.00 608.00 131.80 15.79 116.01 70.00 152.00
20 20 mm HBG M/c Metal-SS5 Rayalapuram 10.00 1016.00 131.80 15.79 116.01 70.00 254.00
21 12 mm HBG M/c Metal-SS5 Rayalapuram 10.00 808.00 131.80 15.79 116.01 70.00 202.00
22 10 mm HBG M/c Metal-SS5 Rayalapuram 10.00 680.00 131.80 15.79 116.01 70.00 170.00
23 2.36 mm Below HBG chips (crusher Rayalapuram 10.00 333.00 131.80 15.79 116.01 0.00 0.00
stone dust)
24 1000mm Dia NP3 Class Allagadda 134.00 5227.00 1719.28 Price 32.98
variation=
25 1000mm Dia Collar Allagadda 134.00 961.00 44.40
26 900mm Dia NP3 Class Allagadda 134.00 4284.00 1678.71 Price 25.43
variation=
27 900mm Dia Collar Allagadda 134.00 770.00 32.98
28 600mm Dia NP3 Class Allagadda 134.00 2068.00 788.80 Price 6.50
variation=
29 600mm Dia Collar Allagadda 134.00 385.00 25.43
3) Certified that the work lies within (a) Municipal limits (or) (b) Agency limits & up to 16 km from all weather road (Yes/ No). no % allowed =
4) Certified that the leads are true and nearer to the site to the best of my Knowledge.
5) Water is to be procured from private source (Y/N) Y
SUPERINTENDING ENGINEER, EXECUTIVE ENGINEER, DY. EXECUTIVE ENGINEER ASSISTANT EXE ENGINEER
PANCHAYATI RAJ, KADAPA PR Division Jammalamadugu PRI SD Pulivendula PRI SD Pulivendula
Total Amount
13
171.01
585.06
620.31
886.01
746.01
1309.82
1357.45
1123.16
1114.57
966.95
552.70
47042.50
28582.50
36122.50
441.28
899.39
899.39
946.01
1456.01
1196.01
1036.01
449.01
6979.26
1005.40
5988.14
802.98
2863.30
410.43
3409.94
3900.00
42000.00
43000.00
42000.00
% allowed =
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YSR Kadapa D
S. Index Description of item Unit Qty Rate
No. Code
1 Clearing and Grubbing Road Land
RBR-STCL- Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and t
2 girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materia
stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disp
top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201 MORD . in
contractors profit & Over head charges but excluding , Seigonarage charges & GST
By Machanical Means
In area of non Throny Jungle (Light Jungle)
Unit =10 Sqm
Out put = 1 Hectare
a) Labour
Mate day
Mazdoor (un-skilled) day 4.16 420.00
Add Municipal/ Agency Allowance 0%
b) Machinery
Dozer D-50 with attachment or suitable machinery for hour 10.00 1546.80
removal of trees & stumps
Tractor with trolley 3t hour 1.00 413.60
Total
c) Over heads & Contractor's profit 12.500%
Rate for hectare
Rate per 1 Sqm = (a+b+c)/10000
2 RBR-EECD- Construction of Embankment with Selected earth Obtained from Borrow pits by Machinery
4
Construction of embankment with Selected earth obtained from borrow pits with all lifts, transporting to sit
spreading, grading to required slope and compacting with vibratory roller 80-100 KN to meet requirement o
Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 MORD includin
contractors profit & Over head charges but excluding , Seigonarage charges & GST
Unit = cum
Taking output = 100 cum
a) Labour
Mazdoor (Unskilled) day 1.04 420.00
Add Municipal/ Agency Allowance 0%
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum per Cum 1.67 2791.60
hour
Tipper 5.5cum with 10T capacity hour 4.50 950.30
Dozer D50 for spreading @ 200 cum per hour hour 0.50 1,546.80
172 / 296
Tractor with Grader @ 25 cum per hour hour 4.00 423.60
Water tanker 6 KL capacity hour 2.00 655.20
Vibratory roller 80-100 KN capacity @ 100 cum per hour hour 1.00 2736.20
c) Material
Selected earth cum 100.00 171.01
Water kl 12.00 0.00
Add seignorage charges Cum 100.00 0.00
Basic rate of formation of road with borrow soils per Cum
OR
Vibratory roller 80-100 kN hour 6.00 2736.20
Tractor with Rotavator 25 cum per hour hour 12.00 423.60
Water tanker 6 kl capacity hour 3.00 655.20
c) Material
Well graded/ Close Graded granular sub-base material as
per Table 400.1
9.5 mm to 4.75 mm @ 66per cent(metal) 237.60 768.55
2.36 mm below @ 34 per cent (stone dust) 122.40 449.01
Water kl 18.00 0.00
Total
Over heads & Contractor's profit 12.500%
Cost for 300cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/300
173 / 296
4 RBR-EECD- Selected Earth Shoulders
15
Construction of Improved sub-grade/Shoulders by providing selected earth having MDD not less than 1.8
with LL & PI not more than 40% and 20 respectively and spreading in uniform layers with tractor gra
prepared surface and compacted at OMC with vibratory roller 80-100 kN to achieve the desired density co
as per IRC Technical Specification Clause 303 MORD by using machinery including all overheads and contr
profit but excluding GST and Seigniorage charges.
c) Material
Selected earth cum 100.00 171.01
Water Kl 30.00 0.00
Basic rate of Selected earth shoulders for 100 cum
a) Basic rate of Selected earth shoulders cum
c) Over heads & Contractor's profit 12.500%
Aggregates 22.4 mm to 2.36 mm using M/C metal @ 40% cum 53.20 955.54
(Average of 19-22mm, 12-14mm, 9.5-11.20 mm, 5-7mm &
2.36-5 mm metal)
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 1.040 420.00
Add Municipal/ Agency Allowance 0%
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.400 381.80
Air compressor 210 cfm hour 1.400 556.50
Bitumen emulsion pressure distributor @ 1750 sqm/hour hour 1.000 875.60
Water tanker 6 kl capacity 1 trip per hour hour 0.500 655.20
c) Material
Bitumen emulsion (SS-1) @ 0.85 kg per sqm t 1.480 47042.50
Water kl 3.000 0.00
Unit = sqm
Taking output = 1750 sqm
a) Labour
175 / 296
Mate day -
Mazdoor (Unskilled) day 1.040 420.00
Add Municipal/ Agency Allowance 0%
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.400 381.80
Air compressor 210 cfm hour 1.400 556.50
Emulsion pressure distributor @1750 sqm per hour hour 1.000 875.60
c) Material
Bitumen emulsion (RS-1) @ 0.275 kg per sqm t 0.480 28582.50
Cost of 1750 sqm = (a+b+c+d+e)
Rate per sqm = a+b+c+d+e/1750
(e) Over heads & Contractor's profit 12.500%
Rate per Sqm
Unit = Cum
Taking output = 195 cum (450 tonnes.)
a) Labour
Mate day
day 12.00 420.00
Mazdoor working with HMP, Mechanical broom,
paver,roller,asphalt cutter and assistance for setting
outlines,levels and layout of construction.
Skilled mazdoor for checking line & levels day 5.84 420.00
Add Municipal/ Agency Allowance 0%
b) Machinery
hour 11.00 24636.00
Hot Mix Plant 100 - 120 TPH
ii) Electric Generator Set 250 KVA hour 6.00 2162.60
iii) Front end loader 1 cum bucket capacity hour 6.00 1594.70
Smooth wheeled roller 8-10 tonne for initial break down hour 3.90 1329.90
rolling (6 x 0.65)
Vibratory roler 8 tonne for intermediate rolling Hour 3.9 2736.20
hour 6.00
Hydrostatic Paver finisher with sensor control @ 75 Cum 3115.20
per hour
hour 3.90 1856.50
Finish rolling with 6-8 tonne smooth wheeled tandem
roller.
c) Material
(I) Bitumen 60/70 gr. @ 5% by weight of mix t 22.50 36122.50
Total Weight of mix = 450 tones
Weigth of Bitumen = 22.5 tones
Weigth of Aggregate = 450-22.5= 427.50 tones
176 / 296
Taking density of aggregate = 1.50ton/cum
Volume of aggregate = 285.0 cum
9.5-11.2 mm HBG M/c chips Cum 81.225 966.95
5-7mm HBG M/c Chips Cum 81.225 786.01
177 / 296
2.36 mm-5mm HBG M/c Chips Cum 58.425 552.70
Below 2.36 mm Cum 58.425 449.01
Unit = cum
Taking output = 360 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 2.080 420.00
b) Machinery
Excavator 0.90 cum bucket capacity @ 100 cum per hour hour 3.60 2791.60
Tipper 5.5 cum capacity, 4 trips per hour hour 15.00 413.60
c&d) Overheads & Contractors Profit 12.500%
Cost for 360 cum = a+b+c+d
Rate per cum = (a+b+c+d)/360
Unit = cum
(100x3.75 x 0.200)
a) Labour
Amount
1,747.20
0.00
15,468.00
413.60
17,628.80
2,203.60
19,832.40
1.98
achinery
436.80
0.00
4,661.97
4,276.35
773.40
179 / 296
1,694.40
1,310.40
2,736.20
17,101.00
0.00
0.00
32,990.52
4,123.82
37,114.34
371.14
1008.00
3360.00
0.00
5083.20
16,417.20
5083.20
1965.60
182607.48
54958.82
0.00
270483.50
33810.44
304293.94
1014.31
180 / 296
MDD not less than 1.85 g/cc
layers with tractor grader on
the desired density complete
all overheads and contractor's
0.00
436.80
0.00
1694.40
2,736.20
773.40
1310.40
17101.00
0.00
24,052.20
240.52
30.07
270.59
270.59
3,360.00
1,008.00
0.00
6,378.80
6,718.80
4,751.50
1,694.40
4,569.45
871.42
181 / 296
47,258.62
50,834.52
17,915.50
0.00
145,361.01
1,453.61
181.70
1,635.31
436.80
0.00
534.52
779.10
875.60
327.60
69,622.90
0.00
72,576.52
9,072.07
81,648.59
46.66
182 / 296
436.80
0.00
534.52
779.10
875.60
13,719.60
16,345.62
9.34
1.17
10.51
5040.00
2452.80
0.00
270996.00
12975.60
9568.20
5186.61
10671.18
18691.20
7240.35
812756.25
183 / 296
78540.51
63843.66
184 / 296
32291.50
26233.41
2559.36
1359046.63
169,880.83
1528927.46
7840.70
873.60
10049.76
6204.00
2140.92
19268.28
53.52
2,500.00
2,300.00
2,520.00
RATE ANALYSIS (CD - WORKS) - SSR2019-20
186 / 296
2 RBR- Filling in foundation trenches for Pipe bedding with Sand as per drawing and techn
FNDN-2 specification Clause 305.3.9 MORD & 304 MORTH ,including overhead charges & Contrac
profit but excluding GST and seigniorage charges.
Sand filling
Unit = 6cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.31 420.00
Add Municipal/ Agency Allowance 0%
b) Material
Sand cum 6.00 441.28
187 / 296
4 RBR- Plain cement concrete M 15 grade using 40,20 & 10mm metal mechanically mixe
SBST-5 foundation complete as per drawings and technical specification Clauses 802, 804, 805,
I 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH ,including overhead charge
Contractors profit but excluding GST and seigniorage charges below GL
Unit = cum
(a) Material
Cement t 0.275 3900.00
Coarse sand cum 0.480 899.39
40 mm aggregate cum 0.480 946.01
188 / 296
5 RBR- Plain cement concrete M 15 grade using 40,20 & 10mm metal mechanically mixe
SBST-5 foundation complete as per drawings and technical specification Clauses 802, 804, 805,
I 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH ,including overhead charge
Contractors profit but excluding GST and seigniorage charges - above GL
Unit = cum
(a) Material
Cement t 0.275 3900.00
Coarse sand cum 0.480 899.39
40 mm aggregate cum 0.480 946.01
189 / 296
6 RBR- Plain cement concrete M 20 grade (Design mix) using 40,20 & 10mm metal (H
SBST-5 mechanically mixed in foundations complete as per drawings and technical specifica
III Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MO
,including contractors profit & Over head charges, GST and Seigneorage etc., complete-
190 / 296
For height upto 5 m
Unit = cum
P.C.C grade M 15
Nominal mix (1:2.5:5) using CC Mixer (MORD)
Unit = cum
(a) Material
Cement t 0.343 3900.00
Coarse sand cum 0.450 899.39
40 mm aggregate cum 0.360 946.01
20 mm aggregate cum 0.360 1456.01
10 mm aggregate cum 0.180 1036.01
Water kl 1.200 0.00
(b) Labour
Mate day -
Mason (1st Class) day 0.100 500.00
Mazdoor (Unskilled) day 1.390 420.00
Add Municipal/ Agency Allowance 0%
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.400 525.50
Generator 33 kVA hour 0.400 1032.00
Unit = t
(a) Material
HYSD bars including 5 per cent for overlaps and t 1.05 42000.00
wastage
Binding wire kg 6.00 55.00
(b) Labour for cutting, bending, shifting to site,
tying and placing in position
Mate day -
Blacksmith day 2.00 495.00
Mazdoor (Unskilled) day 6.40 420.00
Add Municipal/ Agency Allowance 0%
191 / 296
Unit = t
(a) Material
HYSD bars including 5 per cent overlaps and t 1.05 42000.00
wastage
Binding wire kg 6.00 55.00
(b) Labour for cutting, bending, shifting to site,
tying, and placing in position
192 / 296
Mate day -
Blacksmith day 2.00 495.00
Mazdoor (Unskilled) day 6.84 420.00
Add Municipal/ Agency Allowance 0%
10 RBR- Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as
SPST-2 drawing and technical specifications Clauses 1002, 1010 and 1202 MORD / 1600 MORTH
Bars below 36 mm dia including over laps and wastage, where they are not welded ,inclu
overhead charges & Contractors profit but excluding GST and seigniorage charges -
Super Structures
Unit = t
(a) Material
HYSD bars including 5 per cent for laps and t 1.05 42000.00
wastage
Binding wire kg 8.00 55.00
(b) Labour for cutting, bending, tying and placing
in position
Blacksmith/ Rod Binder day 3.00 495.00
Mazdoor (Unskilled) day 8.44 420.00
Add Municipal/ Agency Allowance 0%
193 / 296
(d) Formwork @ 10% on (a+b+c) 10.00%
194 / 296
12 RBR- Providing and laying reinforced cement concrete M25 grade (Design Mix) using 20 & 10m
SPST-1- metal mechanically mixed in superstructure as per drawing and technical specifications
II(A) Clauses 800, 1205.4 and 1205.5 MORD / Sections 1500, 1600 & 1700 MORTH ,including
overhead charges & Contractors profit but excluding GST and seigniorage chargesupto 5m
height. - For Super Structure (Deck slab)
R.C.C M 25 Grade (Design Mix)
Unit =cum
(i) Height upto 5m
Case I : Using Concrete Mixer.
(a) Material
Cement t 0.40 3900.00
Coarse sand cum 0.45 899.39
20 mm aggregate cum 0.54 1456.01
10 mm aggregate cum 0.36 1036.01
Water kl 1.200 0.00
(b) Labour
Mason (1st Class) day 0.10 500.00
Mazdoor (Unskilled) day 1.39 420.00
Add Municipal/ Agency Allowance 0%
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour/cum 0.40 525.50
Generator 33 KVA hour 0.40 1032.00
Unit = cum
(a) Material
Cement t 0.407 3900.00
Sand cum 0.45 899.39
20 mm aggregate cum 0.54 1456.01
10 mm aggregate cum 0.36 1036.01
(b) Labour
Mason (1st Class) day 0.10 500.00
Mazdoor (Unskilled) day 1.39 420.00
Mazdoor (Unskilled) for cleaning deck slab day 0.15 420.00
concrete surface
Add Municipal/ Agency Allowance 0%
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 525.50
Generator 33 KVA. hour 0.40 1032.00
Amount
3,494.40
0.00
16,749.60
20,244.00
2,530.50
22,774.50
22,774.50
94.90
2184
3339
5523
690.375
6213.375
621.34
196 / 296
ches for Pipe bedding with Sand as per drawing and technical
9 MORD & 304 MORTH ,including overhead charges & Contractors
d seigniorage charges.
130.20
0.00
2,647.68
2,777.88
347.24
3,125.12
520.90
concrete M 10 grade in open foundations using 40 mm nominal
gregate, mechanically mixed, placed in foundation and compacted
g for 14 days complete as per drawings and technical specifications
1203 MORD and 1500, 1700 & 2100 MORTH ,including overhead
t but excluding GST and seigniorage charges For levelling course
858.00
404.73
851.41
0.00
50.00
583.80
0.00
210.20
85.18
3,043.32
0.00
3,043.32
380.42
3,423.74
3,423.80
197 / 296
15 grade using 40,20 & 10mm metal mechanically mixed in
r drawings and technical specification Clauses 802, 804, 805, 806,
D and 1500, 1700 & 2200 MORTH ,including overhead charges &
ding GST and seigniorage charges below GL
1,072.50
431.71
454.08
349.44
82.88
0.00
50.00
583.80
0.00
210.20
3,234.61
129.38
3,363.99
420.50
3,784.49
3,784.50
198 / 296
15 grade using 40,20 & 10mm metal mechanically mixed in
r drawings and technical specification Clauses 802, 804, 805, 806,
D and 1500, 1700 & 2200 MORTH ,including overhead charges &
ding GST and seigniorage charges - above GL
1,072.50
431.71
454.08
349.44
82.88
0.00
50.00
583.80
0.00
210.20
3,234.61
323.46
3,558.07
444.76
4,002.83
4,002.90
199 / 296
20 grade (Design mix) using 40,20 & 10mm metal (HBG)
undations complete as per drawings and technical specification
06, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH
& Over head charges, GST and Seigneorage etc., complete-
1,337.70
404.73
340.56
524.16
186.48
0.00
50.00
583.80
0.00
210.20
412.80
4,050.43
162.02
4,212.45
526.56
4,739.01
4,739.10
20 grade (Design mix) using 40,20 & 10mm metal (HBG)
b structure complete as per drawings and technical specification
06, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH
& Over head charges, GST and Seigneorage etc., complete-
200 / 296
1,337.70
404.73
340.56
524.16
186.48
0.00
50.00
583.80
0.00
210.20
412.80
4,050.43
405.04
4,455.47
556.93
5,012.40
5,012.40
cing HYSD bar reinforcement in foundation complete as per
cifications Clauses 1000 and 1202 MORD & 1100, 1600 MORTH for
uding over laps and wastage, where they are not welded ,including
ead charges, GST etc., complete - For Foundation
44,100.00
330.00
990.00
2,688.00
0.00
48,108.00
6,013.50
54,121.50
54,121.50
ng HYSD bar reinforcement (Fe 415) in substructure complete as
specification Clauses 1002, 1005, 1010 & 1202 MORD / Sections
rs below 36 mm dia including over laps and wastage, where they
verhead charges & Contractors profit but excluding GST and
Sub Structures
201 / 296
44,100.00
330.00
202 / 296
990.00
2,872.80
0.00
48,292.80
6,036.60
54,329.40
54,329.40
44,100.00
440.00
1,485.00
3,544.80
0.00
49,569.80
6,196.23
55,766.03
55,766.10
e M25 grade (Design Mix) using 20 & 10mm metal mechanically
mplete as per drawings and technical specification Clauses 802,
nd 1204 MORD and 1500, 1700 & 2200 MORTH ,including overhead
t but excluding GST and seigniorage charges (upto 5m height)
1,571.70
404.73
786.25
372.96
0.00
50.00
583.80
0.00
210.20
412.80
203 / 296
4,392.44
439.24
4,831.68
603.96
5,435.64
5,435.70
204 / 296
ced cement concrete M25 grade (Design Mix) using 20 & 10mm
n superstructure as per drawing and technical specifications
205.5 MORD / Sections 1500, 1600 & 1700 MORTH ,including
ctors profit but excluding GST and seigniorage chargesupto 5m
ure (Deck slab)
1,560.00
404.73
786.25
372.96
0.00
50.00
583.80
0.00
210.20
412.80
4,380.74
876.15
5,256.89
657.11
5,914.00
5,914.00
t concrete wearing course M 30 (Design Mix) grade using 20 &
mixed excluding reinforcement complete as per drawing and
uses 800 and 1206.3 MORD and 2702 MORTH ,including overhead
t but excluding GST and seigniorage charges -
1,587.30
404.73
786.25
372.96
50.00
583.80
63.00
0.00
210.20
412.80
4,471.04
134.13
4,605.17
575.65
5,180.90
ituminous Mastic pad 25.4 mm including cost and conveyance and
ding contractors profit & Over head charges, GST etc., complete
205 / 296
991.00
RBR-TSRA
Unit = t
(a) Material
HYSD bars including 5 per cent for overlaps and t 1.05 42000.00
wastage
Binding wire kg 6.00 55.00
(b) Labour for cutting, bending, shifting to site,
tying and placing in position
Mate day -
Blacksmith day 2.00 495.00
Mazdoor (Unskilled) day 6.40 420.00
Add Municipal/ Agency Allowance 0.00%
Unit = cum
P.C.C grade M 15
Nominal mix (1:2.5:5) using CC Mixer (MORD)
Unit = cum
(a) Material
Cement t 0.275 3900.00
Coarse sand cum 0.480 899.39
40 mm aggregate cum 0.480 946.01
20 mm aggregate cum 0.240 1456.01
10 mm aggregate cum 0.080 1036.01
Water kl 1.200 0.00
(b) Labour
Mate day -
Mason (1st Class) day 0.100 500.00
Mazdoor (Unskilled) day 1.390 420.00
Add Municipal/ Agency Allowance 0.00%
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.400 525.50
(d) Formwork @ 4% on cost of material, labour and 4.00%
machinery (a+b+c)
Rate per cum = a+b+c+d+e+f
RBR- d Providing concrete for plain concrete M 10 grade in open foundations using 40 mm
FNDN-4 nominal size Graded hard stone aggregate, mechanically mixed, placed in
foundation and compacted by vibration including curing for 14 days complete as per
drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD and
1500, 1700 & 2100 MORTH ,including overhead charges & Contractors profit but
excluding GST.
P.C.C grade M 10
Nominal mix 1:3:6
Unit = cum
(a) Material
Cement t 0.22 3900.00
Coarse sand cum 0.45 899.39
40 mm aggregate cum 0.90 946.01
Water kl 1.20 0.00
(b) Labour
Mate day -
Mason (1st Class) day 0.10 500.00
Mazdoor (Unskilled) day 1.39 420.00
Add Municipal/ Agency Allowance 0.00%
(c) Machinery
Mechanical concrete mixer 0.4/0.28 cum capacity hour 0.40 525.50
fitted with water measuring device and preferably
also with load cell.
Water tanker 6 kl capacity hour 0.13 655.20
RBR-TSRA
Unit = Each
Taking output = one traffic sign
(i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.126 152.88
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11 cum 0.126 3363.99
(iii) Painting two coats including prime coat on concrete
surface with Epoxy Paint as per specifications
(III) 1.5 mm thick M.S. Sheet duly painted with stove enameled
paint including lettering, signs, border, message with reflective
tape of engineering grade required size, shade and colour as
per Technical Specifications
2. The rate for excavation, cement concrete M-15, and painting may be taken from respective Chapters.
3. The depth of foundation and quantity of cement in the foundation are indicative. These may be incre
having higher wind velocities like in coastal area. This is applicable to all road signs and direction boards.
RBR-TSRA
Unit = each
Take Output = 0.9 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.126 152.88
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11 cum 0.126 3363.99
(iii) Painting on M.S. tube post with primer and two coat of
epoxy paint as per specifications
(c) Machinery
Tractor with trolley hour 0.08 413.60
Over heads & Contractor's Profit 12.50%
Cost for 0.9 sqm = (i+ii+iii+a+b+c+d+e)
Rate per 0.9 sqm board 1 No.
Note : Rate for excavation, cement concrete M15 and painting may be taken from respective Chapters.
RBR-TSRA
Providing & fixing of typical informatory sign board as per MORD secifications and drawing. Three MS
plates of 1.6mm thick, top and middle plate duly welded with MS flat iron 25mmx5mm size on black on
edges. The lower plate will be welded with MS angle iron frame of lower most plate and flate iron frame
of middle plate will be welded to 2 nos 75mmx75mm of 12 SWG sheet tubes posts duly embedded in CC
M15 grade blocks of 450mmx450mmx600mm, 600mm below ground level. The top most diamond
plate will be welded to middle plate by 47mmx47mm of 12 SWG sheet plate tube. All MS will be stove
enmeled on both sides. Lettering and paining of superior quality in required shede and colour. All
sections of framed posts and sheet tube will be painted with primer and two coats of epoxy paint as per
drawing clause 1701 and annexure 1700.1 if MORD excluding GST & seineorage charges
Unit = Each
Taking out put = one typical board
i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.252 152.88
(ii) Cement Concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11 cum 0.252 3363.99
(iii) Painting on MS Steel tubes with primer and two coats of
epoxy paint
2x2.05x.30 = 1.23
1x1.10x188 = 0.21
As per item no. 9 of Chapter 10 sqm 1.80 104.78
(iv) Printing new letters and figures of any shade with
synthetic enamel paint black or any other approved colour to
give an even shade.
Logo Border 60x4x5 = 1200 per cm height per letter
c) Machinery
Tractor with trolley hour 0.24 413.60
Over heads & Contractor's Profit 12.50%
Cost for one Board= (i+ii+iii+iv+a+b+c+d+e)
Printing and lettering for blank spaces on the lower plate will be written as required and paid separately.
Rate per kL
44100.00
330.00
990.00
2688.00
0.00
48108.00
1528.80
0.00
1528.80
152.88
RBR-TSRA
1072.50
431.71
454.08
349.44
82.88
0.00
50.00
583.80
0.00
210.20
129.38
3363.99
858.00
404.73
851.41
0.00
50.00
583.8
0.00
210.20
85.18
3043.32
RBR-TSRA
3043.32
1740.00
924.00
0.00
540.00
1332.00
4536.00
113.40
348.00
273.00
0.00
72.60
350.00
4.23
1047.83
104.78
725.00
RBR-TSRA
239.40
0.00
111.00
1075.40
0.67
RBR-TSRA
19.26
423.86
48.20
109.20
0.00
520.80
44.52
16.96
178.04
33.09
174.24
1568.20
eet given at (i) to (viii) may be adopted as per site requirement and in accordance with
RBR-TSRA
19.26
423.86
61.82
109.20
0.00
520.80
44.52
593.46
17.80
33.09
227.98
2051.79
2051.80
t concrete M15 and painting may be taken from respective Chapters.
RBR-TSRA
38.53
847.73
188.60
3036.78
327.60
0.00
2652.30
187.74
89.04
RBR-TSRA
759.78
110.67
99.26
1042.25
9380.30
aces on the lower plate will be written as required and paid separately.
7905.39
1062.22
256.84
1116.99
1206.00
300.00
2629.20
0.00
2481.60
2119.78
3179.70
12682.26
1266.20
423.48
RBR-TSRA
1293.89
1125.60
500.00
3074.40
0.00
2481.60
2855.93
25703.36
1836.00
5315.11
3175.13
212.50
711.02
221.10
750.00
3082.80
0.00
2481.60
1993.66
17942.92
543.80
n, cement concrete, steel reinforcement, painting and lettering may be taken from
d in place of precast RCC stones, then rate of cement concrete and steel reinforcement
RBR-TSRA
TRAFFIC VOLUME
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YSR Kadapa District
Date of Survey :
Total
Animal
Motor
Drawn Motorised
Cycles/Sc Pedestiran
Sl.No Duration Buses Trucks Cars Vans Jeeps Bicycles Carts Except Non
ooters/Tw s
(Bullock Two Motorised
o wheelers
carts) Wheelers
1 2 3 4 6 7 8 9 10 11 12 13 14
1 5.00 to 6.00A,M 0 1 0 0 0 0 4 0 0 1 4
Date of Survey :
Total
Animal
Motor
Drawn Motorised
Cycles/Sc Pedestiran
Sl.No Duration Buses Trucks Cars Vans Jeeps Bicycles Carts Except Non
ooters/Tw s
(Bullock Two Motorised
o wheelers
carts) Wheelers
1 2 3 4 6 7 8 9 10 11 12 13 14
1 5.00 to 6.00A,M 0 0 0 0 0 0 0 0 0 0 0
Date of Survey :
Total
Animal
Motor
Drawn Motorised
Cycles/Sc Pedestiran
Sl.No Duration Buses Trucks Cars Vans Jeeps Bicycles Carts Except Non
ooters/Tw s
(Bullock Two Motorised
o wheelers
carts) Wheelers
1 2 3 4 6 7 8 9 10 11 12 13 14
1 5.00 to 6.00A,M 0 0 0 0 0 0 0 0 0 0 0
Technical Assistant
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YSR
Kadapa District
Over Laden
0.34
2.86
Badly
1 km 0/0-0/300 Damaged BT 200 300 WMM 100mm thick.
surface
Badly
2 km 0/300-0/600 Damaged BT 175 345 CC 170 mm thick
surface
Badly
3 km 0/600 -1/800 Damaged BT 200 300 WMM 100mm thick.
surface
Badly
4 km 1/800 -2/220 Damaged BT 175 345 CC 170 mm thick
surface
Existing CC in
5 Km 2/220-2/700 Village 300 0
Portion
Badly
7 km 2/850 -3/650 Damaged BT 200 300 WMM 100mm thick.
surface
km 4/350 - Earthen
9 0 300 GSB 150 mm , WMM 150 mm
5/300 Surface
RESULTS FOR ONLY WHEEL LOAD CONSIDERATION RESULTS FOR WHEEL LOAD AND TEMPARATURE STRESS
Case 1 Case 2
Radius of relative stiffness, l m 711.6123582572 temparature stress at edge, Mpa 0.4922035546
Stress developed, σ, Mpa Wheel load Stresses at edge, Mpa 3.4974019168
Design is Total stresses, σ, Mpa 3.9896054714
Design is Safe
3
4.2157783872
0.00001
0.5242393896
20
0.06
10
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YSR Kadapa
District
Design of CC pavement
Design parameters
Flexural strength of concrete Fr = 46 Kg/cm2
Design wheel load P= 4100 Kg
Tyre pressure q= 8 Kg/cm2
Poission' Ratio u= 0.15
/
centegrad
Coefficcient of Theramal expansion x= 0.00001 e
Elastic modulus of concrete E= 300000 Kg/cm2
Traffic growth rate r= 0.06
Spacing of contraction joints L= 375 Cm
width of pavement B= 375 Cm
Spacing of expansion joint = 50 M
Subgrade CBR value = 4.0%
Sub base course = Compacted GSB 15.0cm thick
Design life n = 20 Years
Present Traffic = 60 CPVD
Design steps
Modulus of subgrade rection 'k' for given CBR value = 3.5 Kg/cm2/cm
Effect 'k' vale = 4.2 Kg/cm2/cm
Assume thickness, h = 20 cm
Radius of relative stiffness, l = [Eh^3/12k(1-u^2)]^1/4
= 83.54 Cm
PI)(P/0.5227q)^0.5]^0.5
4log10b-0.4048]
5m
HYDRAULIC PARTICULARS
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula
(M) in YSR Kadapa District
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YSR Kadapa District
Proposed C
Exisiting WBM
Exisiting GSB
Exisiting CC Pavement
Proposed CC Pavement
TYPICAL CROSS SECTION
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YSR Kadapa District
7.50m
Proposed WMM
Proposed BT.
SST.EXE ENGINEER,
PRI SD Pulivendula
2.2 Preliminary alignment investigation
STRIP MAP
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M)
in YSR Kadapa District
Block : Pulivendula District : Kadapa State : Andhra Pradesh
1000
900
Agricultural lands on both sides
C3 740-820
Proposed Vented Causeway
Local stream crossing
700
Name of work: Providing BT road from Krishnamgaripalli to Ahobilapuram of Pulivendula (M) in YSR Kadapa
District
Block : Pulivendula District : Kadapa State : Andhra Pradesh
2000
1600
1300
1200
1000
dula (M) in YSR Kadapa
Andhra Pradesh
3000
2900
C8 2880
Proposed 1 V 6m span Slab Culvert
Agricultural lands on both sides
2800
2700
2600
2500
2400
2300
2200
2100
2000
apuram of Pulivendula
Andhra Pradesh
4000
3900
3800
3700
3600
3400
3200
3100
3000
apuram of Pulivendula
Andhra Pradesh
5000
4900
4700
4500
4400
4200
4100
Andhra Pradesh
illage portion
illage portion
illage portion
illage portion
illage portion
6000
5900
5800
5700
5600
5500
5400
5300
5200
5100
Andhra Pradesh
7000
6900
6700
6600
6500
6400
Proposed 1000mm Dia PC C20 6385
6300
6200
6100
6000
apuram of Pulivendula
Andhra Pradesh
Village portion
Village portion
Village portion
ots on both sides
7050
Proposed 1000mm Dia PC C23 7050
7000
`
apuram of Pulivendula
Andhra Pradesh
Village portion
Lead charges of 2019-20
Metal Earth, Gravel & Sand pipes 1000 pipes 900 pipes 600
lead Rate lead lead Rate lead Rate Rate
11.30 11.30 extra from 6 to 30 km 11.48 11.48 5.24
9.40 9.40 extra above 30 km
0.5 0.00 0.5 0.00 0.5 238.36 0.5 197.79 0.5 112.84
1 28.30 1 27.40 1 238.36 1 197.79 1 112.84
2 39.50 2 38.40 2 238.36 2 197.79 2 112.84
3 52.70 3 52.70 3 238.36 3 197.79 3 112.84
4 64.00 4 64.00 4 238.36 4 197.79 4 112.84
5 75.30 5 75.30 5 238.36 5 197.79 5 112.84
6 86.60 6 86.60 6 249.84 6 209.27 6 118.08
7 97.90 7 97.90 7 261.32 7 220.75 7 123.32
8 109.20 8 109.20 8 272.80 8 232.23 8 128.56
9 120.50 9 120.50 9 284.28 9 243.71 9 133.80
10 131.80 10 131.80 10 295.76 10 255.19 10 139.04
11 143.10 11 143.10 11 307.24 11 266.67 11 144.28
12 154.40 12 154.40 12 318.72 12 278.15 12 149.52
13 165.70 13 165.70 13 330.20 13 289.63 13 154.76
14 177.00 14 177.00 14 341.68 14 301.11 14 160.00
15 188.30 15 188.30 15 353.16 15 312.59 15 165.24
16 199.60 16 199.60 16 364.64 16 324.07 16 170.48
17 210.90 17 210.90 17 376.12 17 335.55 17 175.72
18 222.20 18 222.20 18 387.60 18 347.03 18 180.96
19 233.50 19 233.50 19 399.08 19 358.51 19 186.20
20 244.80 20 244.80 20 410.56 20 369.99 20 191.44
21 256.10 21 256.10 21 422.04 21 381.47 21 196.68
22 267.40 22 267.40 22 433.52 22 392.95 22 201.92
23 278.70 23 278.70 23 445.00 23 404.43 23 207.16
24 290.00 24 290.00 24 456.48 24 415.91 24 212.40
25 301.30 25 301.30 25 467.96 25 427.39 25 217.64
26 312.60 26 312.60 26 479.44 26 438.87 26 222.88
27 323.90 27 323.90 27 490.92 27 450.35 27 228.12
28 335.20 28 335.20 28 502.40 28 461.83 28 233.36
29 346.50 29 346.50 29 513.88 29 473.31 29 238.60
30 357.80 30 357.80 30 525.36 30 484.79 30 243.84
31 367.20 31 367.20 31 536.84 31 496.27 31 249.08
32 376.60 32 376.60 32 548.32 32 507.75 32 254.32
33 386.00 33 386.00 33 559.80 33 519.23 33 259.56
34 395.40 34 395.40 34 571.28 34 530.71 34 264.80
35 404.80 35 404.80 35 582.76 35 542.19 35 270.04
36 414.20 36 414.20 36 594.24 36 553.67 36 275.28
37 423.60 37 423.60 37 605.72 37 565.15 37 280.52
38 433.00 38 433.00 38 617.20 38 576.63 38 285.76
39 442.40 39 442.40 39 628.68 39 588.11 39 291.00
40 451.80 40 451.80 40 640.16 40 599.59 40 296.24
41 461.20 41 461.20 41 651.64 41 611.07 41 301.48
42 470.60 42 470.60 42 663.12 42 622.55 42 306.72
43 480.00 43 480.00 43 674.60 43 634.03 43 311.96
44 489.40 44 489.40 44 686.08 44 645.51 44 317.20
45 498.80 45 498.80 45 697.56 45 656.99 45 322.44
46 508.20 46 508.20 46 709.04 46 668.47 46 327.68
47 517.60 47 517.60 47 720.52 47 679.95 47 332.92
48 527.00 48 527.00 48 732.00 48 691.43 48 338.16
49 536.40 49 536.40 49 743.48 49 702.91 49 343.40
50 545.80 50 545.80 50 754.96 50 714.39 50 348.64
51 555.20 51 555.20 51 766.44 51 725.87 51 353.88
52 564.60 52 564.60 52 777.92 52 737.35 52 359.12
53 574.00 53 574.00 53 789.40 53 748.83 53 364.36
54 583.40 54 583.40 54 800.88 54 760.31 54 369.60
55 592.80 55 592.80 55 812.36 55 771.79 55 374.84
56 602.20 56 602.20 56 823.84 56 783.27 56 380.08
57 611.60 57 611.60 57 835.32 57 794.75 57 385.32
58 621.00 58 621.00 58 846.80 58 806.23 58 390.56
59 630.40 59 630.40 59 858.28 59 817.71 59 395.80
60 639.80 60 639.80 60 869.76 60 829.19 60 401.04
61 649.20 61 649.20 61 881.24 61 840.67 61 406.28
62 658.60 62 658.60 62 892.72 62 852.15 62 411.52
63 668.00 63 668.00 63 904.20 63 863.63 63 416.76
64 677.40 64 677.40 64 915.68 64 875.11 64 422.00
65 686.80 65 686.80 65 927.16 65 886.59 65 427.24
66 696.20 66 696.20 66 938.64 66 898.07 66 432.48
67 705.60 67 705.60 67 950.12 67 909.55 67 437.72
68 715.00 68 715.00 68 961.60 68 921.03 68 442.96
69 724.40 69 724.40 69 973.08 69 932.51 69 448.20
70 733.80 70 733.80 70 984.56 70 943.99 70 453.44
71 743.20 71 743.20 71 996.04 71 955.47 71 458.68
72 752.60 72 752.60 72 1007.52 72 966.95 72 463.92
73 762.00 73 762.00 73 1019.00 73 978.43 73 469.16
74 771.40 74 771.40 74 1030.48 74 989.91 74 474.40
75 780.80 75 780.80 75 1041.96 75 1001.39 75 479.64
76 790.20 76 790.20 76 1053.44 76 1012.87 76 484.88
77 799.60 77 799.60 77 1064.92 77 1024.35 77 490.12
78 809.00 78 809.00 78 1076.40 78 1035.83 78 495.36
79 818.40 79 818.40 79 1087.88 79 1047.31 79 500.60
80 827.80 80 827.80 80 1099.36 80 1058.79 80 505.84
81 837.20 81 837.20 81 1110.84 81 1070.27 81 511.08
82 846.60 82 846.60 82 1122.32 82 1081.75 82 516.32
83 856.00 83 856.00 83 1133.80 83 1093.23 83 521.56
84 865.40 84 865.40 84 1145.28 84 1104.71 84 526.80
85 874.80 85 874.80 85 1156.76 85 1116.19 85 532.04
86 884.20 86 884.20 86 1168.24 86 1127.67 86 537.28
87 893.60 87 893.60 87 1179.72 87 1139.15 87 542.52
88 903.00 88 903.00 88 1191.20 88 1150.63 88 547.76
89 912.40 89 912.40 89 1202.68 89 1162.11 89 553.00
90 921.80 90 921.80 90 1214.16 90 1173.59 90 558.24
91 931.20 91 931.20 91 1225.64 91 1185.07 91 563.48
92 940.60 92 940.60 92 1237.12 92 1196.55 92 568.72
93 950.00 93 950.00 93 1248.60 93 1208.03 93 573.96
94 959.40 94 959.40 94 1260.08 94 1219.51 94 579.20
95 968.80 95 968.80 95 1271.56 95 1230.99 95 584.44
96 978.20 96 978.20 96 1283.04 96 1242.47 96 589.68
97 987.60 97 987.60 97 1294.52 97 1253.95 97 594.92
98 997.00 98 997.00 98 1306.00 98 1265.43 98 600.16
99 1006.40 99 1006.40 99 1317.48 99 1276.91 99 605.40
100 1015.80 100 1015.80 100 1328.96 100 1288.39 100 610.64
101 1025.20 101 1025.20 101 1340.44 101 1299.87 101 615.88
102 1034.60 102 1034.60 102 1351.92 102 1311.35 102 621.12
103 1044.00 103 1044.00 103 1363.40 103 1322.83 103 626.36
104 1053.40 104 1053.40 104 1374.88 104 1334.31 104 631.60
105 1062.80 105 1062.80 105 1386.36 105 1345.79 105 636.84
106 1072.20 106 1072.20 106 1397.84 106 1357.27 106 642.08
107 1081.60 107 1081.60 107 1409.32 107 1368.75 107 647.32
108 1091.00 108 1091.00 108 1420.80 108 1380.23 108 652.56
109 1100.40 109 1100.40 109 1432.28 109 1391.71 109 657.80
110 1109.80 110 1109.80 110 1443.76 110 1403.19 110 663.04
111 1119.20 111 1119.20 111 1455.24 111 1414.67 111 668.28
112 1128.60 112 1128.60 112 1466.72 112 1426.15 112 673.52
113 1138.00 113 1138.00 113 1478.20 113 1437.63 113 678.76
114 1147.40 114 1147.40 114 1489.68 114 1449.11 114 684.00
115 1156.80 115 1156.80 115 1501.16 115 1460.59 115 689.24
116 1166.20 116 1166.20 116 1512.64 116 1472.07 116 694.48
117 1175.60 117 1175.60 117 1524.12 117 1483.55 117 699.72
118 1185.00 118 1185.00 118 1535.60 118 1495.03 118 704.96
119 1194.40 119 1194.40 119 1547.08 119 1506.51 119 710.20
120 1203.80 120 1203.80 120 1558.56 120 1517.99 120 715.44
121 1213.20 121 1213.20 121 1570.04 121 1529.47 121 720.68
122 1222.60 122 1222.60 122 1581.52 122 1540.95 122 725.92
123 1232.00 123 1232.00 123 1593.00 123 1552.43 123 731.16
124 1241.40 124 1241.40 124 1604.48 124 1563.91 124 736.40
125 1250.80 125 1250.80 125 1615.96 125 1575.39 125 741.64
126 1260.20 126 1260.20 126 1627.44 126 1586.87 126 746.88
127 1269.60 127 1269.60 127 1638.92 127 1598.35 127 752.12
128 1279.00 128 1279.00 128 1650.40 128 1609.83 128 757.36
129 1288.40 129 1288.40 129 1661.88 129 1621.31 129 762.60
130 1297.80 130 1297.80 130 1673.36 130 1632.79 130 767.84
131 1307.20 131 1307.20 131 1684.84 131 1644.27 131 773.08
132 1316.60 132 1316.60 132 1696.32 132 1655.75 132 778.32
133 1326.00 133 1326.00 133 1707.80 133 1667.23 133 783.56
134 1335.40 134 1335.40 134 1719.28 134 1678.71 134 788.80
135 1344.80 135 1344.80 135 1730.76 135 1690.19 135 794.04
136 1354.20 136 1354.20 136 1742.24 136 1701.67 136 799.28
137 1363.60 137 1363.60 137 1753.72 137 1713.15 137 804.52
138 1373.00 138 1373.00 138 1765.20 138 1724.63 138 809.76
139 1382.40 139 1382.40 139 1776.68 139 1736.11 139 815.00
140 1391.80 140 1391.80 140 1788.16 140 1747.59 140 820.24
141 1401.20 141 1401.20 141 1799.64 141 1759.07 141 825.48
142 1410.60 142 1410.60 142 1811.12 142 1770.55 142 830.72
143 1420.00 143 1420.00 143 1822.60 143 1782.03 143 835.96
144 1429.40 144 1429.40 144 1834.08 144 1793.51 144 841.20
145 1438.80 145 1438.80 145 1845.56 145 1804.99 145 846.44
146 1448.20 146 1448.20 146 1857.04 146 1816.47 146 851.68
147 1457.60 147 1457.60 147 1868.52 147 1827.95 147 856.92
148 1467.00 148 1467.00 148 1880.00 148 1839.43 148 862.16
149 1476.40 149 1476.40 149 1891.48 149 1850.91 149 867.40
150 1485.80 150 1485.80 150 1902.96 150 1862.39 150 872.64
151 1495.20 151 1495.20 151 1914.44 151 1873.87 151 877.88
152 1504.60 152 1504.60 152 1925.92 152 1885.35 152 883.12
153 1514.00 153 1514.00 153 1937.40 153 1896.83 153 888.36
154 1523.40 154 1523.40 154 1948.88 154 1908.31 154 893.60
155 1532.80 155 1532.80 155 1960.36 155 1919.79 155 898.84
156 1542.20 156 1542.20 156 1971.84 156 1931.27 156 904.08
157 1551.60 157 1551.60 157 1983.32 157 1942.75 157 909.32
158 1561.00 158 1561.00 158 1994.80 158 1954.23 158 914.56
159 1570.40 159 1570.40 159 2006.28 159 1965.71 159 919.80
160 1579.80 160 1579.80 160 2017.76 160 1977.19 160 925.04
161 1589.20 161 1589.20 161 2029.24 161 1988.67 161 930.28
162 1598.60 162 1598.60 162 2040.72 162 2000.15 162 935.52
163 1608.00 163 1608.00 163 2052.20 163 2011.63 163 940.76
164 1617.40 164 1617.40 164 2063.68 164 2023.11 164 946.00
165 1626.80 165 1626.80 165 2075.16 165 2034.59 165 951.24
166 1636.20 166 1636.20 166 2086.64 166 2046.07 166 956.48
167 1645.60 167 1645.60 167 2098.12 167 2057.55 167 961.72
168 1655.00 168 1655.00 168 2109.60 168 2069.03 168 966.96
169 1664.40 169 1664.40 169 2121.08 169 2080.51 169 972.20
170 1673.80 170 1673.80 170 2132.56 170 2091.99 170 977.44
171 1683.20 171 1683.20 171 2144.04 171 2103.47 171 982.68
172 1692.60 172 1692.60 172 2155.52 172 2114.95 172 987.92
173 1702.00 173 1702.00 173 2167.00 173 2126.43 173 993.16
174 1711.40 174 1711.40 174 2178.48 174 2137.91 174 998.40
175 1720.80 175 1720.80 175 2189.96 175 2149.39 175 1003.64
176 1730.20 176 1730.20 176 2201.44 176 2160.87 176 1008.88
177 1739.60 177 1739.60 177 2212.92 177 2172.35 177 1014.12
178 1749.00 178 1749.00 178 2224.40 178 2183.83 178 1019.36
179 1758.40 179 1758.40 179 2235.88 179 2195.31 179 1024.60
180 1767.80 180 1767.80 180 2247.36 180 2206.79 180 1029.84
181 1777.20 181 1777.20 181 2258.84 181 2218.27 181 1035.08
182 1786.60 182 1786.60 182 2270.32 182 2229.75 182 1040.32
183 1796.00 183 1796.00 183 2281.80 183 2241.23 183 1045.56
184 1805.40 184 1805.40 184 2293.28 184 2252.71 184 1050.80
185 1814.80 185 1814.80 185 2304.76 185 2264.19 185 1056.04
186 1824.20 186 1824.20 186 2316.24 186 2275.67 186 1061.28
187 1833.60 187 1833.60 187 2327.72 187 2287.15 187 1066.52
188 1843.00 188 1843.00 188 2339.20 188 2298.63 188 1071.76
189 1852.40 189 1852.40 189 2350.68 189 2310.11 189 1077.00
190 1861.80 190 1861.80 190 2362.16 190 2321.59 190 1082.24
191 1871.20 191 1871.20 191 2373.64 191 2333.07 191 1087.48
192 1880.60 192 1880.60 192 2385.12 192 2344.55 192 1092.72
193 1890.00 193 1890.00 193 2396.60 193 2356.03 193 1097.96
194 1899.40 194 1899.40 194 2408.08 194 2367.51 194 1103.20
195 1908.80 195 1908.80 195 2419.56 195 2378.99 195 1108.44
196 1918.20 196 1918.20 196 2431.04 196 2390.47 196 1113.68
197 1927.60 197 1927.60 197 2442.52 197 2401.95 197 1118.92
198 1937.00 198 1937.00 198 2454.00 198 2413.43 198 1124.16
199 1946.40 199 1946.40 199 2465.48 199 2424.91 199 1129.40
200 1955.80 200 1955.80 200 2476.96 200 2436.39 200 1134.64
201 1965.20
202 1974.60
203 1984.00
204 1993.40
205 2002.80
206 2012.20
207 2021.60
208 2031.00
209 2040.40
210 2049.80
211 2059.20
212 2068.60
213 2078.00
214 2087.40
215 2096.80
216 2106.20
217 2115.60
218 2125.00
219 2134.40
220 2143.80
221 2153.20
222 2162.60
223 2172.00
224 2181.40
225 2190.80
226 2200.20
227 2209.60
extra for every km beyond 5 km
SSR- 2019 -20 Initial Rates
Labour per Rate 1 60-63 mm size HBG metal (IRC and MORTH)
Mate day (Road SSR) 471.00 W.I with I.T.I day 580.00 2 50 - 55 mm size HBG metal (IRC and MORTH)
Mazdoor day 420.00 painter 2nd Class * day 460.00 3 40-45 mm size HBG metal (IRC and MORTH)
Mason(1st class) day 500.00 painter 1st Class * day 580.00 4 25-27 mm size HBG metal (IRC and MORTH)
Mason(2nd class) day 460.00 Surveyor day 750.00 5 40-45 mm size HG M/C metal (IRC and MORTH)
Blacksmith day 2nd cl 495.00 Asphalt/ Bitumen Sprayer day 460.00 6 19-22 mm size HG M/C metal (IRC and MORTH)
(Road SSR)
7 12-14 mm size HG M/C metal (IRC and MORTH)
Blasting charges 70.00 9 5-7 mm size HG M/c metal (IRC and MORTH)
Loading and Unloading for metal & Stone 138.50 69.25 207.75 19 Rough stone 300 mm thick (Granite) Revetment
Loading and Unloading for earth,Sand and gravel 117.00 42.50 159.50 20 Jeddy stone 450-600mm
21 Soling stone 150 mm granite
22 Sand for Concrete
23 Sand for mortar/ plastering
24 Quarry Rubbish
25 1000mm Dia NP3 Class Plain end
26 1000mm Dia Collar
27 900mm Dia NP3 Class Plain end
28 900mm Dia Collar
29 600mm Dia NP3 Class Plain end
30 600mm Dia Collar
31 Binding wire
32 Cement primer exterior grade kg
33 red oxide(lt)
34 Epoxy paint(lt)
35 Synthetic enamel paint- 1st
36 RR masonry stone OTG
37 Water
38 Selected earth
39 Filter media
40 25.4 mm mastic pad
41 12.7 mm mastic pad
42 100mm AC pipe Basic rate
43 Fevicol Adhesive
44 Unitek Fine grade (25 Kg)
45 RR masonry stone (Granite)
46 CR Masonry Stone (Granite)
47 CR masonry stone OTG
48 Bond stones ( 600 x 200 x 200 mm )
49 110mm PVC 6Kgf/cm2 pipe Basic rate
50 Joint filler board 20mm thick as per IS:1838 -
BMT U02
51 Super plasticizer
52 De bonding strip
53 Selent
54 Poly sheet 125 micron
55 Jute rope
399.05
434.30
560.00
899.05
560.00
937.15
742.85
624.75
480.00
293.35
333.00
113.00
510.00
608.00
1016.00
808.00
680.00
156.00
163.80
196.20
90.50
510.00
510.00
84.75
5227.00 Cost of Cement - 3882.00/MT
961.00 Cost of MS Steel - 41500.00/MT
4284.00
770.00
2068.00
385.00
55.00
180.00 building SSR 2018-19 sno 327
121.00SR BMT-J.03
280.00 I&CAD Gates & Hoists
222.00 building SSR 2017-2018 sno 354
171.45
77.00 M 189(b)
55.00 M 163 excluding seinorage
332.00 M012 including blasting & M/c
839.00 Bldg SSR 2016-2017 sno 845
481.00 Bldg SSR 2016-2017 sno 846
253.00
*
240 70 Blasting
274.3 82 Blasting
207
47.60
701.00
735.00
43 1 Kg
8.55 1 mts
53.95 1 Lts
15.25 1 Sqm
8.35 1 mts
Hire/ Usage charges for plant and machinery as per 2018-2019
Barrel
Dia thickness Steel CC qty steel qty Dia
Longi spiral
300 50 0.78 1.53 0.05497787 2.4936 300
Caulking
space thickness length Steel CC qty steel qty
Longi spiral
16 30 150 0.11 0.22 0.00653137 0.3564
Certified that the proposed road passes inbetween patta lands and side earth is slushy soils in KM 0/0-
5/3 which is not suitable for widening and rising of road. Hence Selected earth is Proposed in these
reaches.
SUPERINTENDING ENGINEER
PR CIRCLE, KADAPA