ABC Costing Exercise
ABC Costing Exercise
QUESTION 1 OUT OF 20
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of
Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is
considering implementing an activity-based costing (ABC) system that allocates all $684,000 of
its manufacturing overhead to four cost pools. The following additional information is available
for the company as a whole and for Products Y and Z:
Activity Cost Pool Activity Measure Estimated Overhead CostExpected Activity
Machining Machine-hours $ 200,000 10,000 MHs
Machine setups Number of setups $ 100,000 200 setups
Product design Number of products $ 84,000 2 products
General factory Direct labor-hours $ 300,000 12,000 DLHs
Required:
1. What is the company’s plantwide overhead rate?
Explanation
1.The plantwide overhead rate is computed as follows:
2. Using the plantwide overhead rate, how much manufacturing overhead cost is allocated to
Product Y and Product Z?
Explanation
2.The plantwide overhead rate is computed as follows:
3. What is the activity rate for the Machining activity cost pool?
Explanation
3.
(a)
Estimated (b) (a) ÷ (b)
Overhead Expected Activity
Cost Activity Rate
Machining activity cost pool $200,000 10,000 MH$20 per MH
QUESTION 4 OUT OF 20
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of
Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is
considering implementing an activity-based costing (ABC) system that allocates all $684,000 of
its manufacturing overhead to four cost pools. The following additional information is available
for the company as a whole and for Products Y and Z:
Activity Cost Pool Activity Measure Estimated Overhead CostExpected Activity
Machining Machine-hours $ 200,000 10,000 MHs
Machine setups Number of setups $ 100,000 200 setups
Product design Number of products $ 84,000 2 products
General factory Direct labor-hours $ 300,000 12,000 DLHs
4. What is the activity rate for the Machine Setups activity cost pool?
Explanation
4.
(a)
Estimated (b) (a) ÷ (b)
Overhead Expected Activity
Cost Activity Rate
Machine setups activity cost pool $100,000 200 setups$500 per setup
QUESTION 5 OUT OF 20
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of
Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is
considering implementing an activity-based costing (ABC) system that allocates all $684,000 of
its manufacturing overhead to four cost pools. The following additional information is available
for the company as a whole and for Products Y and Z:
Activity Cost Pool Activity Measure Estimated Overhead CostExpected Activity
Machining Machine-hours $ 200,000 10,000 MHs
Machine setups Number of setups $ 100,000 200 setups
Product design Number of products $ 84,000 2 products
General factory Direct labor-hours $ 300,000 12,000 DLHs
5. What is the activity rate for the Product Design activity cost pool?
Explanation
5.
(a)
Estimated (b) (a) ÷ (b)
Overhead Expected Activity
Cost Activity Rate
Product design activity cost pool $84,000 2 products$42,000 per product
QUESTION 6 OUT OF 20
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of
Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is
considering implementing an activity-based costing (ABC) system that allocates all $684,000 of
its manufacturing overhead to four cost pools. The following additional information is available
for the company as a whole and for Products Y and Z:
Activity Cost Pool Activity Measure Estimated Overhead CostExpected Activity
Machining Machine-hours $ 200,000 10,000 MHs
Machine setups Number of setups $ 100,000 200 setups
Product design Number of products $ 84,000 2 products
General factory Direct labor-hours $ 300,000 12,000 DLHs
6. What is the activity rate for the General Factory activity cost pool?
Explanation
6.
(a)
Estimated (b) (a) ÷ (b)
Overhead Expected Activity
Cost Activity Rate
General factory activity cost pool $300,000 12,000 DLHs$25 per DLH
QUESTION 7 OUT OF 20
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of
Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is
considering implementing an activity-based costing (ABC) system that allocates all $684,000 of
its manufacturing overhead to four cost pools. The following additional information is available
for the company as a whole and for Products Y and Z:
Activity Cost Pool Activity Measure Estimated Overhead CostExpected Activity
Machining Machine-hours $ 200,000 10,000 MHs
Machine setups Number of setups $ 100,000 200 setups
Product design Number of products $ 84,000 2 products
General factory Direct labor-hours $ 300,000 12,000 DLHs
9. Using the ABC system, how much total manufacturing overhead cost would be assigned to
Product Y?
Explanation
9.The activity rates are computed as follows:
(a)
Estimated (b)
Overhead Expected (a) ÷ (b)
Activity Cost Pool Cost Activity Activity Rate
Machining $200,000 10,000 MH $ 20 per MH
Machine setups $100,000 200 setups $ 500 per setup
Product design $ 84,000 2 products $42,000 per product
General factory $300,000 12,000 DLHs $ 25 per DLH
Using the ABC system, the total overhead assigned to Products Y is computed as follows:
Product Y
Expected
Activity Amount
Machining, at $20 per machine-hour 7,000 $140,000
Machine setups, at $500 per setup 50 25,000
Product design, at $42,000 per product 1 42,000
General factory, at $25 per direct
8,000 200,000
labor-hour
Total overhead costs assigned $407,000
QUESTION 10 OUT OF 20
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of
Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is
considering implementing an activity-based costing (ABC) system that allocates all $684,000 of
its manufacturing overhead to four cost pools. The following additional information is available
for the company as a whole and for Products Y and Z:
Activity Cost Pool Activity Measure Estimated Overhead CostExpected Activity
Machining Machine-hours $ 200,000 10,000 MHs
Machine setups Number of setups $ 100,000 200 setups
Product design Number of products $ 84,000 2 products
General factory Direct labor-hours $ 300,000 12,000 DLHs
10. Using the ABC system, how much total manufacturing overhead cost would be assigned to
Product Z?
Explanation
10.The activity rates are computed as follows:
(a)
Estimated (b)
Overhead Expected (a) ÷ (b)
Activity Cost Pool Cost Activity Activity Rate
Machining $200,000 10,000 MH $ 20 per MH
Machine setups $100,000 200 setups $ 500 per setup
Product design $ 84,000 2 products $42,000 per product
General factory $300,000 12,000 DLHs $ 25 per DLH
Using the ABC system, the total overhead assigned to Products Z is computed as follows:
Product Z
Expected Activity Amount
Machining, at $20 per machine-hour 3,000 $ 60,000
Machine setups, at $500 per setup 150 75,000
Product design, at $42,000 per product 1 42,000
General factory, at $25 per direct labor-hour 4,000 100,000
Total overhead costs assigned $277,000
QUESTION 11 OUT OF 20
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of
Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is
considering implementing an activity-based costing (ABC) system that allocates all $684,000 of
its manufacturing overhead to four cost pools. The following additional information is available
for the company as a whole and for Products Y and Z:
Activity Cost Pool Activity Measure Estimated Overhead CostExpected Activity
Machining Machine-hours $ 200,000 10,000 MHs
Machine setups Number of setups $ 100,000 200 setups
Product design Number of products $ 84,000 2 products
General factory Direct labor-hours $ 300,000 12,000 DLHs
11. Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to
Product Y and Product Z? (Round your "Percentage" answers to 1 decimal place.)
Explanation
11.The plantwide overhead rate is computed as follows:
Product Y Product Z
(a) (a) ÷ (c) (b) (b) ÷ (c) Total
Plantwide Approach Amount % Amount % (c) Amount
Manufacturing overhead$456,000 66.7% $228,000 33.3% $ 684,000
QUESTION 12 OUT OF 20
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of
Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is
considering implementing an activity-based costing (ABC) system that allocates all $684,000 of
its manufacturing overhead to four cost pools. The following additional information is available
for the company as a whole and for Products Y and Z:
Activity Cost Pool Activity Measure Estimated Overhead CostExpected Activity
Machining Machine-hours $ 200,000 10,000 MHs
Machine setups Number of setups $ 100,000 200 setups
Product design Number of products $ 84,000 2 products
General factory Direct labor-hours $ 300,000 12,000 DLHs
12. Using the ABC system, what percentage of the Machining costs is assigned to Product Y and
Product Z?
Explanation
12.
(a)
Estimated (b)
Overhead Expected (a) ÷ (b)
Cost Activity Activity Rate
Machining activity cost pool$200,000 10,000 MH $ 20 per MH
Product Y Product Z
Expected Activity Amount Expected ActivityAmount
Machining, at $20 per machine-hour 7,000 $140,000 3,000 $60,000
13. Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y and
Product Z?
Explanation
13.
(a)
Estimated (b)
Overhead Expected (a) ÷ (b)
Cost Activity Activity Rate
Machine setups activity cost pool$100,000 200 setups $500 per setup
Product Y Product Z
Expected ActivityAmountExpected ActivityAmount
Machine setups, at $500 per setup 50 $25,000 150 $75,000
14. Using the ABC system, what percentage of the Product Design cost is assigned to Product Y
and Product Z?
Explanation
14.
(a)
Estimated (b)
Overhead Expected (a) ÷ (b)
Cost Activity Activity Rate
Product design activity cost pool $ 84,000 2 products $42,000 per product
Product Y Product Z
Expected ActivityAmountExpected ActivityAmount
Product design, at $42,000 per product 1 $42,000 1 $42,000
Product Y Product Z
(a) (a) ÷ (c) (b) (b) ÷ (c) Total
Activity-Based Costing System Amount % Amount % (c) Amount
Product design $42,000 50% $42,000 50% $84,000
QUESTION 15 OUT OF 20
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of
Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is
considering implementing an activity-based costing (ABC) system that allocates all $684,000 of
its manufacturing overhead to four cost pools. The following additional information is available
for the company as a whole and for Products Y and Z:
Activity Cost Pool Activity Measure Estimated Overhead CostExpected Activity
Machining Machine-hours $ 200,000 10,000 MHs
Machine setups Number of setups $ 100,000 200 setups
Product design Number of products $ 84,000 2 products
General factory Direct labor-hours $ 300,000 12,000 DLHs
15. Using the ABC system, what percentage of the General Factory cost is assigned to Product Y
and Product Z? (Round your "Percentage" answers to 1 decimal place.)
Explanation
15.
(a)
Estimated (b)
Overhead Expected (a) ÷ (b)
Cost Activity Activity Rate
General factory activity cost pool$300,000 12,000 DLHs $25 per DLH
Product Y Product Z
Expected Expected
Activity Amount Activity Amount
General factory, at $25 per direct labor-
8,000 $200,000 4,000 $100,000
hour
Product Y Product Z
(a) (a) ÷ (c) (b) (b) ÷ (c) Total
Activity-Based Costing System Amount % Amount % (c) Amount
General factory $200,000 66.7% $100,000 33.3% $ 300,000
QUESTION 16 OUT OF 20
Green Thumb Gardening is a small gardening service that uses activity-based costing to estimate
costs for pricing and other purposes. The proprietor of the company believes that costs are driven
primarily by the size of customer lawns, the size of customer garden beds, the distance to travel
to customers, and the number of customers. In addition, the costs of maintaining garden beds
depends on whether the beds are low maintenance beds (mainly ordinary trees and shrubs) or
high maintenance beds (mainly flowers and exotic plants). Accordingly, the company uses the
five activity cost pools listed below:
Activity Cost Pool Activity Measure
Caring for lawn Square feet of lawn
Caring for garden beds–low maintenance Square feet of low maintenance beds
Caring for garden beds–high maintenance Square feet of high maintenance beds
Travel to jobs Miles
Customer billing and service Number of customers
The company already has completed its first stage allocations of costs and has summarized its
annual costs and activity as follows:
Estimated
Overhead
Activity Cost Pool Cost Expected Activity
Caring for lawn $ 72,000 150,000 square feet of lawn
Caring for garden beds–low maintenance $ 26,400 20,000 square feet of low maintenance beds
Caring for garden beds–high maintenance $ 41,400 15,000 square feet of high maintenance beds
Travel to jobs $ 3,250 12,500 miles
Customer billing and service $ 8,750 25 customers
Required:
Compute the activity rate for each of the activity cost pools. (Round your answers to 2 decimal
places except customer billing and service.)
Explanation
Estimated
Activity Cost Overhead
Pool Cost Expected Activity Activity Rate
Caring for per square ft.
lawn $ 72,000 150,000 square ft. of lawn $0.48 of lawn
Caring for $ 26,400 20,000 $1.32 per square ft.
garden beds- of low
low square ft. of low maintenance
maintenance maintenance beds beds
Caring for $ 41,400 15,000 $2.76 per square ft.
garden beds- of high
high square ft. of high maintenance
maintenance maintenance beds beds
Travel to jobs $ 3,250 12,500 miles $0.26 per mile
Customer
billing and $
service 8,750 25 customers $ 350 per customer
The activity rate for each activity cost pool is computed by dividing its estimated overhead cost
by its expected activity.
QUESTION 17 OUT OF 20
Klumper Corporation is a diversified manufacturer of industrial goods. The company’s activity-
based costing system contains the following six activity cost pools and activity rates:
Activity Cost Pool Activity Rates
Supporting direct labor$ 6 per direct labor-hour
Machine processing $ 4 per machine-hour
Machine setups $ 50 per setup
Production orders $ 90 per order
Shipments $ 14 per shipment
Product sustaining $840 per product
Activity data have been supplied for the following two products:
Total Expected Activity
K425 M67
Number of units produced per year 200 2,000
Direct labor-hours 80 500
Machine-hours 100 1,500
Machine setups 1 4
Production orders 1 4
Shipments 1 10
Product sustaining 1 1
Required:
How much total overhead cost would be assigned to K425 and M67 using the activity-based
costing system?
Explanation
Activity Cost Pool Activity Rate Activity ABC Cost
K425
per direct
Supporting direct labor $ 6 80 direct labor-hours $ 480
labor-hour
per
Machine processing $ 4 machine- 100 machine-hours 400
hour
Machine setups $ 50 per setup 1 setup 50
Production orders $ 90 per order 1 order 90
per
Shipments $ 14 1 shipment 14
shipment
Product sustaining $ 840 per product 1 product 840
Total overhead cost $ 1,874
M67
per direct
Supporting direct labor $ 6 500 direct labor-hours $ 3,000
labor-hour
per
Machine processing $ 4 machine- 1,500 machine-hours 6,000
hour
Machine setups $ 50 per setup 4 setups 200
Production orders $ 90 per order 4 orders 360
per
Shipments $ 14 10 shipments 140
shipment
Product sustaining $ 840 per product 1 product 840
Total overhead cost $ 10,540
QUESTION 18 OUT OF 20
Thermal Rising, Inc., makes paragliders for sale through specialty sporting goods stores. The
company has a standard paraglider model, but also makes custom-designed paragliders.
Management has designed an activity-based costing system with the following activity cost pools
and activity rates:
Activity Cost Pool Activity Rate
Supporting direct labor $ 26 per direct labor-hour
Order processing $284 per order
Custom design processing$186 per custom design
Customer service $379 per customer
Management would like an analysis of the profitability of a particular customer, Big Sky
Outfitters, which has ordered the following products over the last 12 months:
Standard Custom
Model Design
Number of gliders 20 3
Number of orders 1 3
Number of custom designs 0 3
Direct labor-hours per glider 26.35 28.00
Selling price per glider $ 1,850 $2,400
Direct materials cost per glider$ 564 $ 634
The above costs include all of the costs of the restaurant except for organization-sustaining costs
such as rent, property taxes, and top-management salaries.
Some costs, such as the cost of cleaning the linens that cover the restaurant's tables, vary with the
number of parties served. Other costs, such as washing plates and glasses, depend on the number
of diners served or the number of drinks served.
Prior to the activity-based costing study, the owner knew very little about the costs of the
restaurant. She knew that the total cost for the month (including organization-sustaining costs)
was $240,000 and that 15,000 diners had been served. Therefore, the average cost per diner was
$16.
Required:
1&2. According to the activity-based costing system, what is the total cost and average cost per
diner for serving each of the following parties of diners? (Round your intermediate
calculations to 2 decimal places. Round your Total Cost final answers to 2 decimal places
and your Average Cost final answers to 3 decimal places.)
Explanation
1&2.The first step is to determine the activity rates:
(a) (b) (a) ÷ (b)
Activity Cost Pool Total Cost Total Activity Activity Rate
Serving parties $ 33,000 6,000 parties$5.50 per party
Serving diners $138,000 15,000 diners $9.20 per diner
Serving drinks $ 24,000 10,000 drinks $2.40 per drink
According to the activity-based costing system, the cost of serving each of the parties can be
computed as follows:
a.Party of 4 persons who order a total of 3 drinks:
(a) (b) (a) × (b)
Activity Cost Pool Activity Rate ActivityABC Cost
Serving parties $5.50 per party 1 party $ 5.50
Serving diners $9.20 per diner 4 diners 36.80
Serving drinks $2.40 per drink3 drinks 7.20
Total $ 49.50
The average cost per diner for each party can be computed by dividing the total cost of the party
by the number of diners in the party as follows:
a. $49.50 ÷ 4 diners = $12.375 per diner
b. $23.90 ÷ 2 diners = $11.95 per diner
c. $19.50 ÷ 1 diner = $19.50 per diner
This is the last question in the assignment. To submit, use Alt + S. To access other questions,
proceed to the question map button.