MPMKVVCL (Mpseb) PDF
MPMKVVCL (Mpseb) PDF
MPEB to-MPSEB
MPESB to –COMPANIES
MPSEB (Govt.of
to COMPANIES (GOVT. OF MPMP undertaking)
UNDERTAKING)
POWER MANAGEMENT
Percentage of electrification as per old
10 98.17% 98.17% 98.17% 98.17% 98.20% 98.20%
policy %
Percentage of electrification as per New
12 33.84% 35.79% 42.97% 61.65% 64.61% 75.57%
policy %
13 Pump Work completed
1 INPUT MU 17710.9
2 SALE MU 13349.61
33 KV LINES OVER HEAD
11 KV LINES OVER HEAD
LT NETWORK OVER HEAD WITH NAKED
CONDUCTOR/A.B.CABLE
LT NETWORK IN MODERN UNDER GROUND
COLONIES
DISTRIBUTION XMERS POLE MOUNTED
2 6
Advantages of over head
Electric system
2 7
Why do we need change ?
Uninterrupted power supply is needed in modern days.
Less space available for overhead line erection.
To avoid outages during high wind thunderstorms or heavy
snow or ice storms
Clearance form buildings in narrow streets.
Obstruction to transportation.
Shifting needed during Road widening/Bridge construction/
Building construction.
Ground clearance becomes lesser when road height up comes.
2 8
Advantages of Under Ground Electric system-
2 9
Underground Cable and Jointing
kit
3 0
CSS used in underground electric
system-
3 1
Disadvantages of Underground electric system-
1. Undergrounding is more expensive parallel
standby arrangement is required.
2. High cost of maintenance.
3. Difficult breakdown maintenance finding and
repairing overhead wire breaks can be
accomplished in hours, underground repairs can
take days or weeks
Underground cable locations are not always
obvious, which can lead to unwary diggers
damaging cables or being electrocuted.
4. Dry weather required for cable jointing.
ENERGYMETER (INTERNAL
ASSEMBLY)
LV1 Domestic
Tariff Order 1718
Sub Category Fixed Cost Charge Energy Cost
Charge
LV1.1 Rs/KW/Month Rs/Unit
030 units NIL 3.10
LV1.2 (i) For Metered connections
Up to 50 units 50/35* per connection 3.85
51100 units 90/65* per connection 4.70
101300 units 100/85* for each 0.5 kW 6.00
Above 300 units 110/105* for each 0.5 kW 6.30
Minimum Charges: Rs. 60 per connection per month as minimum charges towards energy charges are applicable for
above categories.
Temporary connection for construction of own 390/350* for each one KW of sanctioned or
8.30
house (max. up to one year). connected or recorded load whichever is highest.
Temporary connection for social marriage and 70/55* for each one KW of sanctioned or
8.30
religious functions connected or recorded load whichever is highest
for each 24 hrs duration & part thereof.
Supply through DTR meter for clusters of
Jhuggi/Jhopadi till individual meters are Nil 3.30
provided.
Minimum Charges: Rs. 1000/ per connection per month is applicable towards energy charges for temporary connection
and no minimum charges are applicable for supply through DTR meter for clusters of Jhuggi/Jhopadi.
3 4
LV4 (Industrial)
Tariff Order 1718
Categ Fixed Cost Charge Energy Cost Charge
SubCategory
ory (Urban/Rural)
Rs/KW/Month Rs/Unit
4.1 NonSeasonal Consumer
A Demand based tariff (C.D. upto 150 HP/112 Kw) 285/180* per kW or 228/144* 6.30
per KVA of billing demand
B Temporary connection 1.3 times of the applicable
tariff
In case of consumers having contract demand up to 20 HP, the energy charges and fixed charges shall be billed at a rate
30% less than the charges shown in above table for tariff category 4.1a.
4.2 Seasonal Consumers (period of season shall not exceed 180 days continuously). If the declared season or offseason
spreads over two tariff periods, then the tariff for the respective period shall be applicable.
A During season Normal tariff as for Non Normal tariff as for Non
seasonal consumers seasonal consumers
B During offseason Normal tariff as for Non Normal tariff as for Non
seasonal consumers on 10 % of seasonal consumers on 10
contract demand or actual % of contract demand or
recorded demand, whichever is actual recorded demand,
more whichever is more
3 5
We Can Classify the Accidents as given below
so far as work on lines is concerned
• Accidents that occur due to falling of poles while
stringing of conductor, during erection of poles in
non-aligned condition.
• Due to non use of proper stay or due to lack of
proper earthing, the charging of line may lead to
accident to persons or animals.
• Due to lack of provision of guarding at Road-crossing
points and crossing of H.T./ L.T. lines may result in
accident.
• The line coming to AB Switch or D.O. fuse is not
connected at proper place and in a proper way.
• Accident may occur when service connection is not
provided properly as per standard practice.
WAY OF AVOIDING
ACCIDENTS
General Responsibilities of Supervisory
• staff
Danger signs or barriers as may be necessary may
be displayed to warn the public and others of the
danger zones and to prevent them from entering the
same, before taking the work in hand.