OEE CALCULATION
Production Data
Shift Length 54 Hours = 3240 Minutes
Meal Break + Setup 6 @ 60 Minutes Each = 360 Minutes Total
Breakdown 10 @ 10 Minutes Each = 100 Minutes Total
Unscheduled Downti 960 Minutes
Ideal Run Rate 1.041 PPM (Pieces Per Minute)
Total Pieces 1,626 Pieces
Reject Pieces 8 Pieces
World My OEE
OEE Factor Class %
Availability 90.00% 65.47%
Performance 95.00% 85.82%
Quality 99.90% 99.50%
Overall OEE 85.00% 55.90%
World Class Overall OEE for discrete manufacturing plants is generally considered to be 85% or
better. Studies indicate that the average Overall OEE score for discrete manufacturing plants is
approximately 60%.