Bill of Quantity
Bill of Quantity
Home
BoQ
Basic things you should know about Bill Of Quantity (BOQ)
Generally BOQ is in tabular form which contents description, unit, quantity, rate & amount in
different columns.
Sample BOQ Document, PDF
Description column provides a brief explanation of what to be done. For example, in the first
item, the 32mm diameter CPVC pipes should be laid for cold water services in 20 bar operating
pressure. Specification & drawings are other two important items to be analyzed in detail for
clear understanding. Here the term engineer means the consultant for the project.
THE IMPORTANCE OF BOQ
BOQ shall be used in every phase (pre-contract & post-contract) of the project but need of BOQ
differs based on different contract agreements & project. The major usages are listed below.
1. It provides basic idea of the project by giving the quantities to tenderers.
2. It defines the extent of the work. (But it should be identified in line with drawings &
specification as well).
3. It gives estimated or anticipated contract sum. (very important to client)
4. It provides a basis for valuation of variation. (Variation is to be discussed in detail).
THE MAJOR PARTS OF BOQ
Parts of BOQ can be varied according to the project size as well the practices. Generally it has
measured works, Preliminaries & Provisional sums. The contract sum would be addition of these
three items.
PRELIMINARIES
In construction industry, preliminaries is known as the indirect cost for execution of project but
these are the costs which is very much vital for the construction activities. The reason for these
cost mentioned separately is it is very difficult to distribute these cost amongst with measured
works. The examples for preliminaries listed below.
1. Charges for performance bond, advance payment guarantee & Workmen compensation
2. Maintenance of the site clean
3. Requirement of site office, site stores & staff accommodation.
4. Cost towards the project management staff (QS, Project Manager, Engineering professionals)
5. Charges for drawings & safety
From the above mentioned examples, it can be understood these costs cannot be distributed to
work item but without these expenses there will be no project.
MEASURED WORKS
It is the actual or estimated work will be carried out to complete the project. The works have
been measured in different units. They are liner meter, square meter, cubic meter, number, item
& etc. Value of measured works will be calculated by multiplication of quantities and rate.
PROVISIONAL SUMS
It is the sum which is allocated for the undersigned works at the tender time. It will be adjusted
after the execution of the project.
In summary BOQ is very much important for the commercial management purposes. It should be
understood by every construction professional to deliver a quality and expected product to client.
In other words to provide value for money.
FacebookTwitterPinterest
Share
Save
COMMENTS
comments
Save
Related Posts
12 Comments
1. Pingback: Important technical terms (Drawing Related) for a Quantity Surveyor - The
Architecture City MAY 1, 2017
Type of Equipment use in construction
Preparing Bar schedule manualy
Basic things you should know about Bill Of Quantity (BOQ)
Sieve Analysis – Particle size analysis procedure
What are the type of contracts?
Septic Tank - Types, Design Calculation
Use of excavator in construction
Procurement methods in Construction Industry
Types of Estimate – Types of estimates that prepared on various stages of a project.
Column and Beam system in construction
Basic Civil Engineering Copyright © 2019.
Theme by MyThemeShop
FacebookTwitterPinterestShare