Trial Memo
Trial Memo
and
PREFATORY STATEMENT
The injured party may choose between the fulfillment and the
rescission of the obligation, with the payment of damages in either
case. He may also seek rescission, even after he has chosen
fulfillment, if the latter should become impossible… xxx
Page 2 of 12
ISSUES
1. Whether or not there is basis for the Plaintiff’s cause of action for
sum of money.
1Asuncion v. Evangelista, 375 Phil. 328, 356 (1999), citing Tolentino, Arturo, Commentaries and
Jurisprudence on the Civil Code of the Phil., Vol. IV, 1985 edition, p. 175.
2Insular Life Assurance Co., Ltd. v. Toyota Bel-Air, Inc., 573 Phil. 222, 232 (2008)
Page 4 of 12
xxx
3Agustin vs. Court of Appeals, G.R. No. 84751, June 6, 1990, 186 SCRA 375; Boysaw, et al. vs.
Interphil Promoters, Inc., G.R. No. L-22590, March 20, 1987, 148 SCRA 635; Abaya vs. Standard
Vacuum Oil, 101 Phil. 1262.
4G.R. No. 117190, January 2, 1997, 77 SCAD 647.
Page 5 of 12
price but the respondent did not pay because the windmill
collapsed due to the defects in the construction:
In the case at bar, the Plaintiff’s claim does not satisfy the first
element for the existence of a cause of action. Under the parties’
agreement, the Plaintiff’s obligation is to install an operational solar
panel project producing electricity for the water pumps of
MERWASCO. Plaintiff conducted an ocular inspection in the area
where the solar panel was to be installed. Contrary to Plaintiff’s
uncorroborated claims, there was already an existing Two-Tilt system
of steel frames during the ocular inspection so it necessarily follows
that Plaintiff was made aware of such particular design as proven by
the Chronology of Event sent to and received by Plaintiff on March 5,
2017. Yet, Plaintiff did not exercise proper diligence by not repairing
the materials to be used. He insisted on using the materials which are
appropriate only for a One-Tilt system of steel frames. Plaintiff also
claims that he proceeded upon Defendants’ suggestion of using the
materials for One-Tilt system when in truth and in fact there was no
suggestion made by the Defendants since it is followed by the fact
that the structure was already using the Two-Tilt system. It is highly
logical that the Defendants did not make the suggestion since that
would only entail additional expenses and labor costs that would
only work a disadvantage to him. Nor was there any ratification from
the Defendants. The Defendants cannot be made liable to pay for the
costs of the reconstruction of the steel frames since it was part and
parcel of Plaintiff’s obligation absent any ratification by the
Defendants.
5Cathay Pacific Airways, Ltd. v. Vasquez, G.R. No. 150843, March 14, 2003, 399 SCRA 207, 220.
Page 7 of 12
Upon its failure to fulfill its end of the contract obliterated any
trace of right entitling Plaintiff to the remaining balance of
Php300,000.00. Hence, Plaintiff has no basis for his cause of action for
6Commissioner of Internal Revenue v. Benguet Corporation, G.R. Nos.134587 & 134588, 8 July
2005, 463 SCRA 28, 42.
7Contex Corporation v. Commissioner of Internal Revneue, G.R. No. 151135, 2 July 2004, 433
SCRA 376, 385, citing Deoferio, Jr. and Mamalateo, THE VALUE ADDED TAX IN THE
PHILIPPINES 35-36 (1st ed. 2000).
8Romero vs. Court of Appeals, G.R. No. 107207, November 23, 1995, 65 SCAD621, 250 SCRA
223.
Page 8 of 12
sum of money with damages against the Defendants and should not
be entitled to the rest of the payment.
The injured party may choose between the fulfillment and the
rescission of the obligation, with payment of damages in either
case. He may also seek rescission, even after he has chosen
fulfillment, if the latter should become impossible.
PRAYER
THE FIRM
|PALLUGNA | ALENTON |RADAZA|
| ABBU | ABBU | MACALOS|CASIÑO
Door 5, Borromeo Building. Tomas Saco – 14th Streets
Page 12 of 12
Copy furnished: