Substation Inspection and Maintenance
Substation Inspection and Maintenance
What is a Substation?
Connected Asset Lifecycle Management
ABB’s Workforce Management System
Challenges
Inspection
Maintenance
Repair
Target Customer Profile
Glossary
Substation automation protection and Advanced system and equipment supervision for
control system with IEC 61850 station bus efficient asset management Non-conventional instrument
transformers increase safety and
reduce footprint
– Transmission Substation
• > 170 kV – Convert Substation
– Sub-transmission Substation • Convert currents: AC to DC or DC to AC
• 60 – 170 kV • Rare
• US: 138 kV / 230 kV / 356 kV / 500 kV – Switching Substation (Switchyard)
• Canada: 110 kV / 220 kV / 400 kV • Substation without transformers operating only at a single voltage level
• Different voltages have different safety considerations • Used to switch lines or parallelizing circuits
– Distribution Substation – Railways
• < 60 kV • Electrified railways also use substations
• End users are consumers • Often distribution substations
– Collector Substation
• Substation that collects from generation projects like a wind farm
What is a Substation?
Connected Asset Lifecycle Management
ABB’s Workforce Management System
Challenges
Inspection
Maintenance
Repair
Target Customer Profile
Glossary
– Sensors (Grid Sentry) collects asset information • Work Order released to WFM • Crew updates readings / repair information
– Assessment Analytics (Asset Health Center) – WFM (Hancock) • Crew updates Labour / Equipment information
• Identify problems using a variety of methods • Work Order is sent to a Crew • Crew identifies repair required and sends a
(trending, thresholds, rate of change, statistical • Crew arrives at the Substation Work Request to the EAM
correlation and probabilistic theory) • Crew completes the Work Order
• Crew views a Substation Hazard Report WFM-
• Provide recommendations for corrective action >AHC • Work Order status is sent to Ellipse
/ preventative maintenance (Including
Timeframe) • Crew views all Substation issues WFM->AHC – Ellipse
• Sends Work Requests to Ellipse • Crew views current asset information WFM- • Updates the status of the Work Order
>AHC – Asset Health Center
– EAM (Ellipse)
• Crew views asset maintenance steps WFM- • Data points sent to AHC
• Creates a Work Order associated with the asset >EAM
• Requisitions materials, resources and • Crew views schematic from LinkOne WFM-
equipment >EAM
What is a Substation?
Connected Asset Lifecycle Management
ABB’s Workforce Management System
Challenges
Inspection
Maintenance
Repair
Target Customer Profile
Glossary
– Clearances
• Tagout/lockout procedures. Access to equipment isolation, work status, – Switching
and schedule information required. • Critical systems have parallel breakers
• To perform maintenance, a certain bay is re-routed and then shut down
– Inspection
• Collecting and storing information. – Utilities don’t always inspect substations as a whole
• Coordinate multiple feeders
– Personnel Qualifications • Certain breakers, group inspections / maintenance in to one work order
• Due to the various substation requirements, qualifications need to be • Switches and transformers do not have much change
considered.
– Equipment
• Equipment required should be identified.
Substations: http://electrical-engineering-portal.com/download-center/books-and-guides/power-substations
Under ABB PGGI Service, there are 3 types of work performed on Substations Maintenance Contract
• Service Calls (Warranty Calls) • Calls are first forwarded to Raleigh, NC
• Maintenance Calls • Work order is then manually assigned to the nearest Service Tech
• Testing and commissioning (Inspection)
Testing and commissioning
Service Calls • Equipment Tested (example):
• Equipment under warranty • Static VAR compensators
• 24 / 7 maintenance contract • Capacitor Stations (300 kV / 500 kV)
• Calls are first forwarded to Montreal • Schedule depends on customers
• Work Order is then manually assigned to whoever is free and nearest to • 2 – 3 months per station
the call • 10 hrs / 6 days a week
Testing and Commissioning – Note: Cell phone restrictions. Some older sites are not allowed
1. Work Order sent to the Tech via email
2. Tech downloads from ABB’s server the Inspection and Test Plan (ITP) (like
Switch Order)
3. Tech arranges a conference call to sign off on the ITP
4. Each separate apparatus is inspected
– Must be within certain parameters
• w/in parameter – passes
• Trouble shooting and repairs may be required (done on the spot)
• If Union, the trouble shooting request sent to union for repairs
– Inspection performed with a crew
– Currently using paper forms
• Industrial clients usually have their own maintenance programs (2 – 3 year • Manufactures have recommendations for new installations
inspections • SCADA monitors oil results
• Assessment performed first • Oil condition is an indicator on the health of the transformer
• Oil Sample • Normal Maint schedule 2 – 3 years
• Visual • Oil sample taking every 3 months if transformer is bad
• Electrical and Mechanical Recommendation • While inspecting the transformer
• If in bad shape and will fail w/in 6months • Change / replace bushings
• Usually have 1 spare on site because can take up to 1 year to replace a • Information for the inspector
transformer
• Details
• Inspection cycle
• Location
• Usually have customer guys do regular checkups
• Designation
• Procedures followed:
• History
• IEEE or other testing standards followed
What is a Substation?
Connected Asset Lifecycle Management
ABB’s Workforce Management System
Challenges
Inspection
Maintenance
Repair
Target Customer Profile
Glossary
What is a Substation?
Connected Asset Lifecycle Management
ABB’s Workforce Management System
Challenges
Inspection
Maintenance
Repair
Target Customer Profile
Glossary