Project Management 3rd Edition-Full-Material
Project Management 3rd Edition-Full-Material
Ministry of Manpower
Colleges of Technology COURSE
MATERIAL
ITDB3111
PROJECT MANAGEMENT
Contents
About this Course Material 5
How this Course Material is structured. ........................................................................... 5
Course Overview 8
Welcome to ITDB3111-Project Management .................................................................. 8
ITDB3111-Project Management—is this course for you? ............................................... 8
Course Objectives ............................................................................................................. 8
Course Outcomes .............................................................................................................. 9
Timeframe ........................................................................................................................ 9
Study Skills ..................................................................................................................... 10
Need Help? ..................................................................................................................... 11
Assignments ................................................................................................................... 11
Assessments .................................................................................................................... 12
Getting around this Course Material 13
Margin icons ................................................................................................................... 13
Chapter 1-INTRODUCTION TO PROJECT MANAGEMENT 14
1.1. Introduction .......................................................................................................... 14
1.2. Basic Concepts ...................................................................................................... 15
1.3. Stakeholders ......................................................................................................... 17
1.4. The Project Management Process ...................................................................... 19
1.5. Chapter Summary ............................................................................................... 23
1.6. Assignment............................................................................................................ 24
1.7. Case Study ............................................................................................................ 24
1.8. Reference Used ..................................................................................................... 25
Chapter 2-INTRODUCTION TO MICROSOFT PROJECT 27
2.1. Introduction .......................................................................................................... 27
2.2. Mapping The Project Management Software Usage To The Project
Management Process Group .......................................................................... 28
2.3. Importance of using Project Management Software ........................................ 29
2.4. Getting Started With Microsoft Project ............................................................ 31
2.5. Setting-Up The Microsoft Project Environment ............................................... 31
2.6. Chapter Summary ............................................................................................... 31
ITDB3111- Project Management, Third Edition
5
ITDB3111- Project Management, Third Edition
Resources
1. A Guide to Project Management Body of Knowledge (PMBOK
Guide) 4th Edition, 2008 Edition by PMI, Project Management
Institute
2. Business plan as a decision making tool for projects, Visitask,
http://www.visitask.com/Business-plan-decison-making-tool.asp
3. Business Plan Guidelines, Merlot,
http://www.merlot.org/merlot/viewMaterial.htm?id=301883
4. Business Project - IT ADVISERS BUSINESS PLAN SAMPLE,
iPlanner, http://www.iplanner.net/business-
financial/bizplan/bizplan.aspx?eq=_Kv8WPlpGI9X5pqTzaYF-Q
5. Examples of a Business Case, Bright Hub PM,
http://www.brighthubpm.com/project-planning/103223-
examples-of-a-business-case/?cid=parsely_rec
6. Feasibility Study Template, Bright Hub PM,
http://images.brighthub.com/media/6C54CD_feasibility-study-
template-from-kibs.doc
7. Guide to the Project Initiation Process Group, Bright Hub
PM,http://www.brighthubpm.com/project-planning/124432-
guide-to-the-project-initiation-process-group/?cid=parsely_rec
8. How to write an effective business plan, ABC Consulting,
http://www.businessconsultingabc.com/Writing_An_Effective_B
usiness_Plan.html
9. http://www.cvr-
it.com/Samples/XProject_Charter_Form_Template.pdf
10. Introduction to Project Management by Team Works taken from
http://www.merlot.org/merlot/viewMaterial.htm?id=90038Date
Modified in MERLOT:September 05, 2011
11. Introduction to Project Management by Larry Cooperman taken
from http://www.merlot.org/merlot/viewMaterial.htm?id=388951
Date Modified in MERLOT: April 15, 2011
12. Microsoft Project 2010 In Dept, 2011 by Quantum PM and Scott
Daley, Que
13. Microsoft Project 2010 Project Management, 2010 by Robert
Happy, PMP, MCT, Sybex
14. Microsoft® Project 2010 Inside Out, 2011 by Teresa S. Stover,
Microsoft Press
15. Oracle Primavera P6 Version 8: Project and Portfolio
Management, 2012 by Daniel L. Williams, PhD and Elaine Britt
Krazer, PMP, Packt Publishing
16. Project Management 101 by Linh Huong et. al. taken from
http://cnx.org/content/col11352/1.1/Last edited by Linh Luong on
Aug 19, 2011 3:48 pm GMT-5.
17. Project Management Book by Michael Harding Roberts HRA
Consulting taken from
http://www.merlot.org/merlot/viewMaterial.htm?id=562817 Date
Modified in MERLOT: June 28, 2011
18. Project Management by Merrie Barron and Andrew R. Barron
taken from http://cnx.org:8888/content/col11120/1.6/ Last edited
by Andrew R. Barron on Apr 5, 2013 10:47 am GMT-5.
6
ITDB3111- Project Management, Third Edition
19. Project Management for Dummies 3rd Edition, 2010 by Stanley
Portny, PMP, Wiley Publishing
20. Project Management Getting It Done by Teresa Hill et. al. taken
from http://cnx.org/content/col11374/1.1/ Last edited by Teresa
Hill on Nov 6, 2011 9:18 pm US/Central.
21. Project Management Made Easy by Sid Kemp taken from
http://www.merlot.org/merlot/viewMaterial.htm?id=562830Date
Modified in MERLOT: June 28, 2011
22. Project Management using Microsoft Project by Microsoft taken
from
http://www.merlot.org/merlot/viewMaterial.htm?id=78286Date
Modified in MERLOT:February 02, 2010
23. Project Manager Street Smarts, 2011 by Linda Kretz Zaval, PMP
and Terri Wagner, PMP, Wiley & Sons.
24. Sample Feasibility Study, Bright Hub PM,
http://images.brighthub.com/media/3D2FF6_feasibility-study-
sample.doc
25. Step by Step Guide to Project Management by PM@UTS taken
from
http://www.merlot.org/merlot/viewMaterial.htm?id=562845Date
Modified in MERLOT: June 28, 2011
26. Successful Project Management Applying Best Practices and
Real-World Techniques with Microsoft® Project, 2011 by
Bonnie Biafore, Microsoft Press
27. What is a Terms of Reference?, Project Management Tips,
http://pmtips.net/terms-reference/
Your Comments
After completing ITDB3111-Project Management, we would
appreciate it if you would take a few moments to give us your
feedback on any aspect of this course. Your feedback might include
comments on:
Course content and structure.
Course reading materials and resources.
Course assignments.
Course assessments.
Course duration.
Course support (assigned tutors, technical help, etc.)
7
ITDB3111- Project Management, Third Edition
Course Overview
Welcome to ITDB3111-Project Management
This course covers the project management skills, Processes and
Knowledge Areas with a strong emphasis on issues and problems
associated with delivering successful IT Project.
ITDB3111-Project Management—is this course for you?
This course is intended for students who are in Advanced Diploma
and are required to take a Major Elective course.
No prerequisite courses are required in taking this course.
Course Objectives
The objectives of this course are:
Course Outcomes
Upon completion of ITDB3111-Project Management you
Outcomes will be able to:
8
ITDB3111- Project Management, Third Edition
Timeframe
Study Skills
Your most significant considerations will be time and space i.e. the time
you dedicate to your learning and the environment in which you engage in
that learning.
http://www.how-to-study.com/
The “How to study” web site is dedicated to study skills resources. You
will find links to study preparation (a list of nine essentials for a good
study place), taking notes, strategies for reading text books, using
reference sources, test anxiety.
9
ITDB3111- Project Management, Third Edition
http://www.ucc.vt.edu/stdysk/stdyhlp.html
This is the web site of the Virginia Tech, Division of Student Affairs.
You will find links to time scheduling (including a “where does time
go?” link), a study skill checklist, basic concentration techniques,
control of the study environment, note taking, how to read essays for
analysis, memory skills (“remembering”).
http://www.howtostudy.org/resources.php
Another “How to study” web site with useful links to time
management, efficient reading, questioning/listening/observing skills,
getting the most out of doing (“hands-on” learning), memory building,
tips for staying motivated, developing a learning plan.
The above links are our suggestions to start you on your way. At the time
of writing these web links were active. If you want to look for more go to
www.google.com and type “self-study basics”, “self-study tips”, “self-
study skills” or similar.
Need Help?
10
ITDB3111- Project Management, Third Edition
Assignments
The learner is required to accomplish and submit assignments and/or
project that will be required by the Course Lecturer.
The required number of assignments and the corresponding marks
will be based on the approved Course Delivery Plan for the semester.
The assignments and/or project will be submitted to the Course
Assignments Lecturer as per the designated submission dates, methods and other
requirements.
The assignments will be given as specified in the Course Delivery
Plan.
Assessments
The learner is required to undergo and pass the required assessments
as specified in the College By-Laws and as per the Assessment
Pattern approved by the Department.
These assessments includes but are not limited to:
Assessments
Quizzes
Assignments
Laboratory Works
Presentations
Mid-Semester Examination
Final Examination
The corresponding marks will be set in the Course Delivery Plan.
11
ITDB3111- Project Management, Third Edition
While working through this Course Material you will notice the frequent use of margin icons.
These icons serve to “signpost” a particular piece of text, a new task or change in activity; they
have been included to help you to find your way around this Course Material.
A complete icon set is shown below. We suggest that you familiarize yourself with the icons and
their meaning before starting your study.
Computer-Based
Audio Video Feedback
Learning
Answers to
Objectives Basic Competence
Assessments
12
ITDB3111- Project Management, Third Edition
1.1. INTRODUCTION
This chapter provides the essential introductory concepts of Project Management. It
discusses the processes, life cycles, skills and knowledge areas. It also covers the
concepts behind the organizational aspects of Project Management such as
stakeholders, teams and work environment.
1.1.1. Objectives
The objectives of this Chapter are:
Explain what a project is, various attributes and constraints.
Identify the different stakeholders and their functions.
Describe the project management process and its areas.
1.1.2. Outcomes
Upon completion of this chapter, the student will be able to:
Explain the concepts of Project Management and Knowledge Areas.
Analyze organization structures.
1.1.3. Terminologies
Project-a temporary endeavor undertaken to create a unique product,
service or result.
Life Cycle-refers to the process used to build the deliverables
produced by the project.
Project Management-the application of knowledge, skills, tools and
techniques to project activities to meet project requirements.
Milestone-a significant point or event in the project.
Project Stakeholders-individuals or organizations who are
connected to the project in one way or another and can influence the
project’s outcome.
13
ITDB3111- Project Management, Third Edition
14
ITDB3111- Project Management, Third Edition
15
ITDB3111- Project Management, Third Edition
1.3. STAKEHOLDERS
Project stakeholders are individuals or organizations who are connected to the project
in one way or another and can influence the project’s outcome. The project manager
needs to work with different types of stakeholders in various ways. A stakeholder can
do the following [4]:
o Be actively involved in the work of the project.
o Exert influence over the project and its outcome (also known as managing
stakeholders).
o Have a vested interest in the outcome of a project.
The following are examples of Project Stakeholders [1]:
o Customers/users - The persons or organizations that will use the project’s
product or service or result. Customers/users may be internal and/or external to
the performing organization.
o Sponsor - A person or group that provides the financial resources, in cash or in
kind, for the project. The sponsor leads the project through the engagement or
selection process until formally authorized, and plays a significant role in the
development of the initial scope and charter.
o Portfolio managers/portfolio review board - Portfolio managers are
responsible for the high-level governance of a collection of projects or
programs, which may or may not be interdependent.
o Program managers - Program managers are responsible for managing related
projects in a coordinated way to obtain benefits and control not available from
managing them individually.
o Project management office - A project management office (PMO) is an
organizational body or entity assigned various responsibilities related to the
centralized and coordinated management of those projects under its domain.
o Project managers - Project managers are assigned by the performing
organization to achieve the project objectives. As the person responsible for
the success of the project, a project manager is in charge of all aspects of the
project including, but not limited to:
16
ITDB3111- Project Management, Third Edition
17
ITDB3111- Project Management, Third Edition
18
ITDB3111- Project Management, Third Edition
19
ITDB3111- Project Management, Third Edition
20
ITDB3111- Project Management, Third Edition
Project Management Process Groups
Knowledge
Monitoring
Areas Initiating Planning Executing Closing
&Controlling
Develop Develop Project Direct and Monitor and Close Project
Project Management Plan Manage Control Project or Phase
Project Charter Project Work
Integration Execution Perform
Management Integrated
Change
Control
Collect Verify Scope
Project Scope Requirements Control Scope
Management Define Scope
Create WBS
Define Activities Control
Sequence Schedule
Activities
Estimate Activity
Project Time
Resources
Management
Estimate Activity
Durations
Develop
Schedule
Estimate Costs Control Costs
Project Cost
Determine
Management
Budget
Plan Quality Perform Perform
Project Quality Quality Quality
Management Assurance Control
21
ITDB3111- Project Management, Third Edition
Project Management Process Groups
Knowledge
Monitoring
Areas Initiating Planning Executing Closing
&Controlling
Manage
Project Team
Identify Plan Distribute Report
Project Stakeholder Communications Information Performance
Communications Manage
Management Stakeholder
Expectations
Plan Risk Monitor and
Management Control Risks
Identify Risks
Perform
Qualitative Risk
Project Risk
Analysis
Management
Perform
Quantitative Risk
Analysis
Plan Risk
Responses
Project Plan Conduct Administer Close
Procurement Procurements Procurement Procurement Procurements
Management s
22
ITDB3111- Project Management, Third Edition
essential activities and achieving the required milestones and deliverables in the
different processes.
1.6. ASSIGNMENT
You are required to perform the following, either individually or in a group:
Assignment 1.6.1
1. Select a particular organization in which you or any members of the group have
sufficient knowledge.
2. Investigate on the selected organization’s structure and come up with a drawing
of its organizational chart.
3. Obtain information on an ongoing project in this organization and identify the
stakeholders of this project.
4. You or your members should reflect on the following:
How the organization you have selected is structured in relation to the
products and/or services they offer.
How the organization’s structure changes in relation to the project they are
currently undertaking.
Why is the project being undertaken? What are its perceived contributions
to the organization’s overall goal?
5. Submit a report containing your findings to the Course Lecturer and present this
in the class.
23
ITDB3111- Project Management, Third Edition
24
ITDB3111- Project Management, Third Edition
25
ITDB3111- Project Management, Third Edition
2.1. INTRODUCTION
One of the features of this course is the usage of a Project Management software tool
for managing key project activities. Microsoft Project and Primavera Project Planner
are examples of such software tool. Although these software tools are used in the hands-
on activities of this material, the software are only used to provide students with the
basic ideas on the usage of Project Management software on some key project
management activities. Furthermore, the students are encouraged to explore and use
other software with similar features or capabilities.
In this chapter, you’ll learn about the features, key settings and tools that are unique to
MS Project and Primavera Project Planner that help you get up and running fast—and
in the right way. Understanding some important option settings before you start
planning will go a long way toward helping you use Project Management software
more effectively.
2.1.1 Objectives
The objectives of this Chapter are:
Identify the different deliverables or activity of the project plan.
Identify the scheduling scheme of the project plan.
Use a software tool in creating project plan.
Determine the time frame, constraints, costs, and resources of the project
plan.
2.1.2. Outcomes
Upon completion of this chapter, the student will be able to:
Explain the concepts of Project Management and Knowledge
Areas.
Analyze a plan using methods and tools including Establish WBS,
time & effort estimates, resource allocation and scheduling.
Use tool for project management.
26
ITDB3111- Project Management, Third Edition
2.1.3. Terminologies
Calendar - the settings that define the working days and time for
a project, resources, and tasks.
Duration - the span of working time that you expect it will take
to complete a task.
o Initiating
o Planning
o Executing
o Monitoring and controlling
o Closing
Organizations have varying degrees of maturity and depth with regard to project
management processes and a clear understanding of how a tool like Project can help in
each of the project management process groups is essential. The following tables show
the different project management process groups and the processes included in each
with relation to their usage level of Microsoft Project.
Project
Microsoft Project
Management Comments
Usage Level
Stage
27
ITDB3111- Project Management, Third Edition
Executing Med-High Provides the roadmap and clear path to the final deliverable
or result.
Table 2.2.1 - Mapping out where Project 2010 will be the most help in managing
individual projects [2]
2.3.1. Scheduling
Scheduling is one of the most critical tools required to manage a project to its
conclusion. By making use of this feature in ‘Microsoft Project’ you can schedule a
project from the information you input about the overall project, the individual tasks
required to see the project through to completion, and the resources (people, equipment,
materials) necessary to complete those tasks. If there are changes that occur to the tasks
28
ITDB3111- Project Management, Third Edition
or resources after the schedule has been created, you can update these and MS Project
will update the schedule.
By assigning resources you create the association between specific tasks and the
resources (one or more) required to complete them. These resources include the work
resources (people and equipment required to conclude a task) and material resources
(materials or supplies).
Quality management is the set of activities planned at the beginning of the project that
help achieve quality in the project being executed, and which are defined on the basis
of the quality standards set by the project manager and the company delivering the
product.
For the project to finish on schedule the path of series of tasks must be completed on
schedule. This critical path completion will dictate the project’s finish date. Microsoft
Project defines the critical path by determining the critical tasks and the tasks having
‘slack’, meaning which tasks will be finished early or late according to start date and
scheduled duration.
By knowing and tracking the critical path of the project, as well as resources assigned
to critical tasks, the finish date of the project can be determined. Keeping track of the
completion and status of critical tasks is essential to keeping the project on course to
being completed on time.
29
ITDB3111- Project Management, Third Edition
stakeholders about the status and progress of the project. Various types of reports in
variety of forms can be generated by using project management software such as
“Status report, progress report, variance report, trend report, Forecasting reports, etc.”
These reports also help stakeholders to take proactive decisions to enhance
opportunities and decrease threats about the project deliverables.
30
ITDB3111- Project Management, Third Edition
31
ITDB3111- Project Management, Third Edition
3.1. INTRODUCTION
This chapter introduces the processes performed to define a new project or a new phase
of an existing project by obtaining authorization to start the project or phase. It shows
how initial scope is defined, financial resources are committed and internal and external
stakeholders and those who will interact and influence the overall outcome of the
project are identified. All this information is captured in the project charter.
3.1.1. Objectives
The objectives of this Chapter are:
Identify feasible project.
Develop and explain project charter.
Identify the roles and responsibility of a project team.
Describe the structure of a project team.
3.1.2. Outcomes
Upon completion of this chapter, the student will be able to:
3.1.3. Terminologies
Project Stakeholders-individuals or organizations who are
connected to the project in one way or another and can influence the
project’s outcome.
Project Statement of Work- a narrative description of products or
services to be delivered by the project.
32
ITDB3111- Project Management, Third Edition
33
ITDB3111- Project Management, Third Edition
34
ITDB3111- Project Management, Third Edition
35
ITDB3111- Project Management, Third Edition
Legal Feasibility
Operational Feasibility
36
ITDB3111- Project Management, Third Edition
Economic Feasibility
37
ITDB3111- Project Management, Third Edition
Technical Feasibility
Schedule Feasibility
3.3.1.3. Contract
A contract is an input if the project is being done for an external
customer.
38
ITDB3111- Project Management, Third Edition
39
ITDB3111- Project Management, Third Edition
o High-level requirements,
o High-level project description,
o High-level risks,
o Summary milestone schedule,
o Summary budget,
o Project approval requirements (what constitutes project
success, who decides the project is successful, and who
signs off on the project),
o Assigned project manager, responsibility, and authority
level, and
o Name and authority of the sponsor or other person(s)
authorizing the project charter.
40
ITDB3111- Project Management, Third Edition
http://www.projectmanagementdocs.com/project-initiation-
templates/feasibility-study.html
http://www.projectmanagementdocs.com/project-initiation-
templates/project-statement-of-work.html
41
ITDB3111- Project Management, Third Edition
http://www.projectmanagementdocs.com/project-initiation-
templates/stakeholder-management-strategy.html
o http://www.projectmanagementdocs.com/project-initiation-
templates/project-charter.html
o http://www.cvr-
it.com/Samples/XProject_Charter_Form_Template.pdf
o http://innovativeprojectguide.com/sample-project-plans/14-
sample-plans/160-sample-project-charter.html
o http://www.pmi.org/pmief/learningzone/KCMA_Curricula_Doc
uments/Project_Charter_for_School_Store.pdf
o http://www.brighthubpm.com/project-planning/5159-project-
charter-example-for-every-project-manager/
42
ITDB3111- Project Management, Third Edition
o http://www.projectmanagementdocs.com/initiating-process-
group/project-charter-long.html
43
ITDB3111- Project Management, Third Edition
44
ITDB3111- Project Management, Third Edition
45
ITDB3111- Project Management, Third Edition
46
ITDB3111- Project Management, Third Edition
47
ITDB3111- Project Management, Third Edition
Organizational process assets include any or all process related assets, such
as formal and informal plans, policies, procedures, and guidelines as well as the
organization’s knowledge bases such as lessons learned and historical
information.
48
ITDB3111- Project Management, Third Edition
49
ITDB3111- Project Management, Third Edition
Defining and sharing team roles and responsibilities upfront can help improve
performance and identify and head off potential difficulties during a project.
One way to display team roles and responsibilities is in a Responsibility
Assignment Matrix (RAM). The RAM is a table that depicts each project
members’ role in the performance of different project activities. The elements
and format of a RAM (Figure 3.5.3) is as follows:
Project deliverables are in the left-hand column.
Project audiences are in the top row.
The role each audience will play in performing the work to produce
each deliverable is in the intersections of the rows and columns.
50
ITDB3111- Project Management, Third Edition
51
ITDB3111- Project Management, Third Edition
Project Utilities or
Environmental Traffic Office
Deliverable: Manager Cindy
Coordinator Tammi Bailey
Mark Cross Santos
Enviro. Permits A R
Traffic Report A R
Utility Locates I I R
Intersection
A C R C
Design
Enviro. Permits A S
Traffic Report A R A R
Utility Locates I R R A
Intersection
A R S R
Design
There are many possible variations to this coding structure; the project team may
create unique codes that are more meaningful to the project such as:
Verifies - the person who ensures the work meets quality standards.
Final Authority - the person who puts the final stamp on the completed
work.
52
ITDB3111- Project Management, Third Edition
3.7. ASSIGNMENT
You are required to perform the following, either individually or in a group:
Assignment 3.7.1
An organization that specializes in providing telecommunication services is
contemplating on a project involving network security services in anticipation for the
implementation of 4G LTE network connectivity. Based on the knowledge you have
gained from the assignments in Chapter 1, this chapter’s contents and using the
provided templates and samples accomplish the following requirements:
1. Download the sample Project Charter from http://www.cvr-
it.com/Samples/XProject_Charter_Form_Template.pdf
2. Fill-up the Sections 1, 2, 4 & 5.
3. Identify your team members and their roles and responsibilities, and then create
an initial Responsibility Assignment Matrix.
4. Submit a report containing your findings to the Course Lecturer and present this
in the class.
53
ITDB3111- Project Management, Third Edition
Team members will consist of the following: Ms. Manal will be the assigned Tester.
Her monthly salary is 625Ro and she will do the work for March and April only. Mr.
Talib will be the Software Engineer with monthly salary of 890RO, who will worked
together with the project manager.
Ms. Mariam with a monthly salary of 875RO will be the Database Administrator who
will work during January, February and April only, Mr. Issa will be the Network
Engineer who will receive a monthly salary of 1050RO. He will work during February,
March and April only together with Mr. John with 980RO monthly salary who will be
in charge on the security of the system. Mr. Ruel with a monthly salary of 1000RO will
manage the information system of the project from January to April.
There are just a few major deliverables: User registration module, modules for
application for appeal for resit and make-up exams, and appeal against exam result,
data warehouse for the system, 24-hour network connectivity, secured information, and
secured database with back up facility, test results, and posting of approved results.
Prepare a Budget (Cost) Plan for manpower services.
54
ITDB3111- Project Management, Third Edition
4.1. INTRODUCTION
55
ITDB3111- Project Management, Third Edition
This chapter deals with the processes needed to create the Project Plan. The Planning
Process Group consists of those processes performed to establish the total scope of the
effort, define and refine the objectives, and develop the course of action required to
attain those objectives. The planning processes develop the project management plan
and the project documents that will be used to carry out the project. The usage of
Microsoft Project will be introduced particularly in the creation of the project’s
schedule.
4.1.1. Objectives
The objectives of this Chapter are:
Determine the project deliverables and its characteristics.
Construct work breakdown structure of the project.
Identify the schedule, costs and resources of the project.
Describe different kind of management plan.
4.1.2. Outcomes
Upon completion of this chapter, the student will be able to:
Analyze a plan using methods and tools including Establish WBS, time &
effort estimates, resource allocation and scheduling.
4.1.3. Terminologies
Deliverables - the products we hope to achieve when the project is
completed.
Work Breakdown Structure (WBS) - a deliverable-oriented
hierarchical decomposition of the work to be executed by the project
team to accomplish the project objectives and create the required
56
ITDB3111- Project Management, Third Edition
57
ITDB3111- Project Management, Third Edition
58
ITDB3111- Project Management, Third Edition
59
ITDB3111- Project Management, Third Edition
60
ITDB3111- Project Management, Third Edition
61
ITDB3111- Project Management, Third Edition
62
ITDB3111- Project Management, Third Edition
63
ITDB3111- Project Management, Third Edition
64
ITDB3111- Project Management, Third Edition
65
ITDB3111- Project Management, Third Edition
66
ITDB3111- Project Management, Third Edition
3. Estimate resources.
Your resource plan helped you determine the resources you need, but
now you have to estimate what these resources will cost. The project
manager works with the resources assigned to do the work to first
estimate the time needed for activities. Table 4.5.1.3.1 lists factors that
help bring reality to the estimate.
67
ITDB3111- Project Management, Third Edition
68
ITDB3111- Project Management, Third Edition
69
ITDB3111- Project Management, Third Edition
70
ITDB3111- Project Management, Third Edition
71
ITDB3111- Project Management, Third Edition
72
ITDB3111- Project Management, Third Edition
73
ITDB3111- Project Management, Third Edition
Most of the time, a project manager doesn’t get to choose their team members.
You use those people who are assigned by others. You will want to know if the
resources are:
Expert
Highly competent
Competent
Novice
3. Create a resource calendar. A resource calendar lets you know how many
resources you need as well as when you need them.
4. Determine resource assumptions.
5. Determine resource risks and mitigation strategies.
74
ITDB3111- Project Management, Third Edition
75
ITDB3111- Project Management, Third Edition
76
ITDB3111- Project Management, Third Edition
77
ITDB3111- Project Management, Third Edition
The following is a template that includes the elements of a resource and staffing
management plan:
Section 1: Human Resources
Quantity
Cost assumptions
Dates needed
Date released
Special needs
Special skills
Training needs
Office and material requirements
78
ITDB3111- Project Management, Third Edition
Type of resource
Quantity of resources needed for tasks
Skills
Experience level:
Expert
Highly competent
Competent
Novice
Section 4: Resource Calendar
Insert your resource calendar in this section.
Section 5: Resource Assumptions
Insert your documented assumptions in this section.
Section 6: Resource and Staffing Risks
Resource
Risk
Mitigation strategy
4.7. DEVELOPING THE COMMUNICATIONS PLAN
4.7.1. Why create a communications plan?
When there is an extensive undertaking, communication of information and
coordination of efforts across teams are critical success factors. The objective
is to ensure accurate, consistent, and timely communication of information to
the business teams, project teams, and management.
The project manager will be engaged in many types of project communications
modalities including, but not limited to, the following:
Project plans (such as schedules, budgets, risk and resource plans)
Project meetings
Status reporting
Organizational charts
Requirements
Contracts
Presentations
79
ITDB3111- Project Management, Third Edition
Decision memoranda
Policies and procedures
Historical records
To be able to do all of this effectively, you must create a communications plan.
The project manager should be the focal point for the flow of communications
in a project environment. Let’s take a look at three common scenarios:
Between the Project Manager and the Customer – The project
manager receives the project goals from the customer.
Between the Project Manager and the Sponsor – The project
manager receives the project priority from the sponsor. The project
manager sends performance information such as budget and schedule
results to the sponsor.
Between the Project Manager and the Project Team – The project
manager provides the project standards to the project team and receives
performance results from the project team.
To be successful with these communications, you need to determine the
communication needs of stakeholders.
80
ITDB3111- Project Management, Third Edition
Table 4.7.2.1 identifies some of the key stakeholders and the type of
information they may require.
81
ITDB3111- Project Management, Third Edition
82
ITDB3111- Project Management, Third Edition
83
ITDB3111- Project Management, Third Edition
84
ITDB3111- Project Management, Third Edition
85
ITDB3111- Project Management, Third Edition
86
ITDB3111- Project Management, Third Edition
Once it has been determined that you will outsource your work item(s), it is
time to prepare the statements(s) of work to enable the procurement process to
begin. A good CSOW helps you do that. The elements of a CSOW include but
are not limited to the following:
Clear roles and responsibilities
Location of work
Security issues if necessary, such as access to proprietary information,
key codes, building access codes
Milestones and deliverables with acceptance criteria
Clear description of quantities, technical specifications, and quality
expectations
Progress reports
Payments
Change control
4.8.5. Procurement Plan Template
The following represents a template that can be used to create your project
procurement plan:
Section 1: Specifications
Design specifications
Performance specifications
Functional specifications
Section 2: Source Selection Package
Bid documents (usually standardized)
List of qualified vendors (expected to bid)
Proposal evaluation criteria
Bidder conferences and schedules
How change requests will be managed
Supplier payment plan
Section 3: Procurement Actions
What procurement actions the project team is authorized to execute
on its own without reference to the procurement department
87
ITDB3111- Project Management, Third Edition
What status reports the project team will require from the
procurement department on outsourced items
How multiple providers will be managed
How procurement will be coordinated with other aspects of the
project
Purchasing decisions (including authority to commit)
Make-or-buy decisions with supporting data
Section 4: Procurement Documents
Requests for quotes
Requests for information (RFIs)
Requests for proposals (RFPs)
Section 5: Types of Contracts
Firm fixed price (FFP)
Fixed-price incentive (FPI)
Cost plus fixed fee (CPFF)
Cost plus incentive fee (CPIF)
Cost plus percentage of cost (CPPC)
Cost plus award fee (CPAF)
Time and materials (T&M)
Section 6: Contract Administration
Change management
Specification interpretation
Adherence to quality
Warranties
Subcontractor management
Production surveillance
Waivers
Contract breach
88
ITDB3111- Project Management, Third Edition
89
ITDB3111- Project Management, Third Edition
90
ITDB3111- Project Management, Third Edition
91
ITDB3111- Project Management, Third Edition
92
ITDB3111- Project Management, Third Edition
Measurement devices
Any other relevant information from the scope statement or other
project documents to get started
4.9.3. Establish Valid Requirements
Indicators help you determine whether your processes are capable of meeting
your customer’s needs. An indicator is defined as a measure of meeting valid
requirements. Indicators are used to monitor both the effectiveness or condition
of a part of the work process (process indicators) and the quality of the output
or outcome of the process (quality indicators).
No matter what type, all indicators should have the following characteristics:
Measurable - They can be expressed quantitatively (in time,
dollars, customer specifications, and so forth).
Verifiable - Multiple, independent observers of the process should
be able to agree on the results obtained from measuring the process.
Accurate records should be kept so the measurements can be tracked
over time.
Cost-effective - Indicators must be chosen with economy of time
and cost in mind. Ideally, data for indicators will be available from
existing sources and/or management information systems.
4.9.4. The Quality Management Plan
The quality management plan describes how the project management team will
execute the project while complying with policies, standards, or legal
requirements. The following represents a quality plan template that you may
find useful:
Section 1: Quality Control Activities - Describe the planned
approach for verifying that the required quality has been obtained.
Section 2: Project Management Quality Activities - Describe
activities such as compliance reviews, templates, and checklists.
Section 3: Quality Assurance Checkpoints - Describe points in the
project when checks will be made to verify that the quality control
93
ITDB3111- Project Management, Third Edition
94
ITDB3111- Project Management, Third Edition
95
ITDB3111- Project Management, Third Edition
96
ITDB3111- Project Management, Third Edition
97
ITDB3111- Project Management, Third Edition
Change is inevitable. Just when you think the project plan is cast in stone, a change
pops up. You want to be able to do the following:
Manage each request for change, in order to ensure that any new scope, cost,
and/or schedule of the project remains under control and has full traceability
Make sure each request for change is assessed by all affected functional areas
Make sure each assessed change request has a decision made (accepted,
rejected, or deferred) by the appropriate authority
The project manager drives the decision-making process and ensures that all the
stakeholders who might be impacted by the change are fully involved.
The change management process includes sub-processes to:
Briefly assess each proposed change
Analyze the potential impact of the proposed change on the project as a whole
Decide how to proceed with a change request (CR) after its impact has been
analyzed
Monitor the progress of approved changes until they are complete
Additionally, a change review board (CRB) or change control board (CCB) should be
engaged if the changes affect the project scope, the original schedule, and/or costs
beyond the authority level delegated to the project manager.
98
ITDB3111- Project Management, Third Edition
99
ITDB3111- Project Management, Third Edition
100
ITDB3111- Project Management, Third Edition
o Organizational risks include cost, time, and scope objectives that are
internally inconsistent, lack of prioritization of projects, insecure funding,
and resource competition.
o External risks could include a shifting legal or regulatory environment;
labor issues; country risk; weather; unavailability of raw materials;
permitting difficulties; postulated events such as vandalism, terrorism, or
sabotage; or social and environmental issues.
o Other risks include the following:
Personnel
Human resource management
Financial
Operational
Natural and man-made disasters
Political
Economic cycle/marketing
Contractual/legal
Requirements changes
Design changes
Task omissions
Estimating and scheduling errors
Technical errors
Staff turnover, illness or death, unplanned vacations and leaves of
absence
Late delivery of external deliverables
Priority changes that result in loss of resources, including support
work
Late approvals and acceptances
Extended learning curves
Unavailable or unreliable tools and methods
Assumptions that turn out not to be true
4.11.3. Perform Qualitative Risk Assessment
101
ITDB3111- Project Management, Third Edition
After you have identified the risks, the next process for risk management is
qualitative analysis. In this process, you want to determine the likelihood of
occurrence and the impact of the risk if it does occur.
Sizing the Probabilities of Risk Likelihood
Project stakeholders must agree on the break points between
severity descriptors and percentages associated with them in order
to be consistent in their assessment regarding the likelihood that a
risk event will occur:
Very low may indicate a 5% likelihood of occurrence or that
the risk event hasn’t happened within the past five years.
Low may indicate a 20% likelihood of occurrence or that the
risk event has happened within the past five years.
Medium may indicate a 40% likelihood of occurrence or that
the risk event has happened once or twice within the past 24
months.
High may indicate a 60% likelihood of occurrence or that the
risk event has happened once within the past 12 months.
Very high may indicate an 80% likelihood of occurrence or
that the risk event has happened on a regular basis over the
past 24 months.
Sizing the Impact of Risk Events or the Amount at Stake
Impacts, or consequences associated with risk, are examined to
assess the consequences to project objectives. The following are
examples of using severity descriptors:
Very low may mean having insignificant impact on the
project objectives (for example, 5–10% slippage on the
schedule and/or budget).
Low may mean having minor outcomes that are unlikely to
have a permanent or significant effect on the project
objectives (for example, a 20% chance that materials won’t
arrive when planned).
102
ITDB3111- Project Management, Third Edition
103
ITDB3111- Project Management, Third Edition
104
ITDB3111- Project Management, Third Edition
105
ITDB3111- Project Management, Third Edition
106
ITDB3111- Project Management, Third Edition
This chapter presented the essential processes within the Planning Processes Group
which focuses on the development of the overall Project Management Plan. The usage
of Project Management software, in this case Microsoft Project was also given
particularly in the development of the WBS and the project’s schedule.
Planning a project can be as simple or elaborate as you make it but no matter what,
proper planning will decide the fate of a project.
4.13. ASSIGNMENT
You are required to perform the following, either individually or in a group:
Assignment 4.13.1
You have just determined the following major activities required for the
implementation of a new telephone system:
A: Conduct station reviews (3): Predecessor none
B: Obtain network requirements (2): Predecessor none
C: Create station designs (2): Predecessor A
D: Create network cable design (4): Predecessor B
E: Build out switch room (8): Predecessor B
F: Install patch panel in switch room (2): Predecessor E
G: Install hardware (3): Predecessor E
H: Install cable (2): Predecessors D, E
I: Tie down cable to patch panel (3): Predecessors F, H
J: Install, program, and test stations (2): Predecessors C, G, I
K: Conduct continuity tests (4): Predecessor J
L: Test software (1): Predecessor K
1. Using the precedence diagramming technique, draw the network diagram for
this project and calculate the ES, EF, LS, and LF of each of its activities.
2. Determine the critical path.
3. Show all float
Assignment 4.13.2
107
ITDB3111- Project Management, Third Edition
Answer the given questions based on the given table below. Conduct further research
for your solutions in the PERT exercise.
108
ITDB3111- Project Management, Third Edition
Design Selection with 5 days for each task. The Designer (D) is the one in
charge of this task together with the System Analyst using laptops and
printer.
M5. After Market Research is Product Development that will be done by the
Product Developer (PD) together with the Designer within 20 days. Part of
this task is Prototyping. They will use desktop, scanner, printer and plotter.
M7. After Market Research, Product Design and Product Development, next is
Production Planning that should be done by you together with the
Designer and System Analyst. It will take 25 days for this task. Part of the
this task is Production Design that will take for 15 days and Production
testing that will take for 10 days. They need laptop, projector, printer and
scanner.
M9. After Product Development and Production Planning, the next is
Marketing will take 15 days to be done by the Account Executive (AE). In
this task includes Marketing strategy (3 days), Marketing Plan (5 days) and
Marketing Collateral (7 days doing brochures, advertising and
commercials)
M11. Project Management is next after Product Development, Production
Planning and Marketing and it should be your main task and will take 30
days using laptop, printer and scanner.
A. Defining the Project schedule.
B. Creating the calendar, setting workdays and holidays.
C. Assign Finish to start relationship between activities in the PERT View.
D. Creating e a resource table and assigning the resources to the Project activities.
E. Organize the Work Break Structure.
F. Draw the PERT diagram indicating start to end activities.
G. Identify the critical path from the PERT diagram.
H. Compute the total float/slack for each activity.
I. Compute for the total project float.
4.15. HANDS-ON
You are required to perform the following, either individually or in a group:
109
ITDB3111- Project Management, Third Edition
If you are using Microsoft Project, see the Microsoft Project Laboratory Manual and
perform the following:
4.14.1 Laboratory Work : Outlining (Creating the WBS)
4.14.2 Laboratory Work : Estimating Duration
4.14.3 Laboratory Work: Using WBS Codes
If you are using Primavera Project Planner, see the Primavera Project Planner
Laboratory Manual and perform the following:
1.2 Laboratory Work: Estimating Duration
1.7 Laboratory Work: Entering the WBS and Using WBS Codes
110
ITDB3111- Project Management, Third Edition
5.1. INTRODUCTION
This chapter deals with the processes needed to create the Project Plan. The Executing
Process Group consists of those processes performed to complete the work defined in
the project management plan to satisfy the project specifications. This Process Group
involves coordinating people and resources, as well as integrating and performing the
activities of the project in accordance with the project management plan
5.1.1. Objectives
The objectives of this Chapter are:
Describe how to manage and directing project plan.
Apply quality management plan and assessment to the project.
Determine and perform managerial process and skills in holding
project team.
5.1.2. Outcomes
Upon completion of this chapter, the student will be able to:
Explain the concepts of Project Management and Knowledge Areas.
Analyze organization structures.
Analyze concepts of Quality Management, Assurance and Control.
Analyze risks and manage them.
Analyze project execution and manage it.
Evaluate set-targets, deliverables and conflict resolution documents.
Analyze team management.
5.1.3. Terminologies
Seller - A provider or supplier of products, services, or results to an
organization.
Risk - An uncertain event or condition that, if it occurs, has a positive
or negative effect on a project’s objectives.
111
ITDB3111- Project Management, Third Edition
112
ITDB3111- Project Management, Third Edition
113
ITDB3111- Project Management, Third Edition
114
ITDB3111- Project Management, Third Edition
115
ITDB3111- Project Management, Third Edition
116
ITDB3111- Project Management, Third Edition
117
ITDB3111- Project Management, Third Edition
118
ITDB3111- Project Management, Third Edition
Milestones achieved
Milestones planned but not achieved
Deliverables completed
Work packages planned but not completed
Accomplishments planned for the next period
Milestones to be achieved
Deliverables to be completed
Summary of issues
Risks
Changes
Action items
o Progress Reporting
Progress reporting describes what the project team has
accomplished since the project began. These are elements of
a progress report:
Progress of deliverables identified in the work
statement
Comparisons of expenses to the expected budget to
date
Effectiveness of the project to date
Current challenges in completing the project
Quality assessment
Risks
119
ITDB3111- Project Management, Third Edition
120
ITDB3111- Project Management, Third Edition
Implementing the quality plan begins with quality assurance, which is a proactive
process that helps execute the project and delights the customer. Quality assurance
begins when you begin the work on the project. The Quality Assurance Plan should be
multifunctional (so the plan can be repeated elsewhere in the organization) and
prevention oriented.
5.5.1. Details
Quality assurance is preplanned. It is an integral part of your Project Quality
Management Plan; with predetermined check steps that you have placed within
your project to ensure that the project fulfills its goals.
121
ITDB3111- Project Management, Third Edition
Cost of quality refers to the total cost of all efforts to achieve product or service
quality, such as reworking.
5.5.4. Cost of Conformance
Prevention and appraisal activities are considered a cost of conformance to
quality. Design reviews, training, and quality planning are also associated with
the costs of prevention activities.
5.5.5. Cost of Nonconformance
Joseph Juran, a noted quality expert, spoke often of the cost of not conforming
to quality, referring to the impacts of internal and external failure. Internal
failures are those that occur before leaving the organization and include
scrapping, reworking, repairing, and evaluating defects.
5.5.6. Quality Audits
One of the quality assurance tools is a project audit. A project audit can be
performed randomly or at specified times within each phase of the project. The
intended outcome of the audit is to confirm the following:
The planned project quality requirements are met.
The products are safe and fit for the customers’ use.
All laws and regulations have been followed.
Data systems to track, measure, and report quality attributes and quality
characteristics are accurate and adequate.
Any variances identified during quality checks are addressed by
appropriate corrective action.
Any opportunities for continuous improvement are noted for future
action.
122
ITDB3111- Project Management, Third Edition
The results of your qualitative analysis determined which risks you’ll use in this
process. Normally you would work on risks that were qualified as high impact
and high probability of occurrence. Any risk that is high probability and high
impact should be treated with a sense of urgency.
5.6.2. Interviewing
Follow these steps to conduct a successful data collection interview:
1. Interview project stakeholders and subject matter experts in order to
quantify the probability and consequences of risk on the project
objectives.
2. The project manager must then define the benefits and boundaries
of the project and document the rationale of the risk ranges
discovered during the risk qualification process.
3. The project manager must prepare for the risk interview by
performing triage on key risk elements in order to establish risk
ranking.
4. Set up a meeting with the subject matter experts and those who
planned and who will manage the work.
5. Conduct the interview. Everyone’s views are valuable but do
challenge the ranges they may give you.
6. If the relationship between risk and probability is uncertain, then
you as the project manager may choose to perform three-point
estimating as you did while using the Program Evaluation and
Review Technique (PERT) in Phase 2 for project tasks.
5.6.3. Sensitivity Analysis
Sensitivity analysis is a simple tool that investigates how estimated
performance varies with changes in the pre-identified key assumptions that are
based on the project objectives. Generally, five steps are involved in creating a
sensitivity analysis:
1. Design the experiment.
2. Assign ranges of variation to input factors.
3. Generate the input vectors through the design.
123
ITDB3111- Project Management, Third Edition
Advertising
Advertising or publishing a request for information (RFI) in trade
journals, newspapers, or other industry publications expands exposure
to potential bidders.
Internet Search
Many commodities can be obtained over the Internet for a firm fixed
price. However, if the commodities are highly complex or are associated
with high risk, you should not use the Internet because of the costs
involved.
5.7.2. Select the Seller
The process of selecting the seller involves determining the best-value
contractors by considering price, schedule, technical issues, and other factors.
The project manager works closely with the procurement officer (buyer) to
124
ITDB3111- Project Management, Third Edition
125
ITDB3111- Project Management, Third Edition
1. Develop objectives. If you are the buyer, what is the maximum you are
willing to pay? If you are the seller, what is the minimum you are willing
to accept?
2. Assess your opponent to see what motivates them. Is your opponent
interested in profitability, keeping people employed, developing a new
technology, or wanting to use your name for future reference?
3. Describe your strategy and tactics. Know before you begin what
techniques you’ll use to swing your opponent to your point of view.
4. Assemble your facts. Do your financial and other homework! Your
opponents are doing their homework about you and your business, and
will use these facts to their favor.
5. Conduct a complete price/cost analysis. That way, you know what
the contract items should cost before committing to a fee or type of
contract.
6. Arrange the details of the negotiations. Specify where the
negotiations will occur, the type of table to be used (round or square),
who will face the windows, and so on.
126
ITDB3111- Project Management, Third Edition
127
ITDB3111- Project Management, Third Edition
128
ITDB3111- Project Management, Third Edition
Be sure that team members perceive that the recognition and rewards
are fair.
Some of the most career-enhancing rewards are nonfinancial in nature.
Whatever choice is made, recognize and reward good performance.
5.8.4. Conflict Resolution
Conflict is a natural occurrence in the project management experience.
Resolving conflicts doesn’t come naturally to most people. You’ll perform
conflict resolution many times in your project, and there are several approaches
to conflict:
Forcing or dictating a solution pushes one viewpoint at the expense of
others and offers only win/lose solutions. Hard feelings may come back
in other ways.
When you avoid conflict, you withdraw or retreat from the actual or
potential conflict situation. It does not solve the problem.
When you accommodate conflict, you attempt to smooth over the
situation. You emphasize areas of agreement rather than areas of
difference, but this provides only short-term solutions.
When you compromise your position, you are looking for bargains for
solutions that bring a degree of satisfaction to all parties. This provides
a definitive resolution.
You can collaborate and reach consensus by incorporating multiple
viewpoints and insights. This leads to consensus and commitment and
provides long-term resolution.
Confronting the situation treats conflict as a problem to be solved by
examining alternatives and requires give-and-take and open dialogue.
Confrontation provides the ultimate resolution.
5.9. CHAPTER SUMMARY
This chapter has covered the important processes that make up the Executing Process
Group. The execution of project activities to achieve the deliverables must be
performed based on the plans outlined in the planning stage in accordance with the
129
ITDB3111- Project Management, Third Edition
guidelines presented in this chapter. As execution of the project goes on, certain
changes and adjustments are made and quality, risks and team harmony must be taken
into account.
5.10. ASSIGNMENT
You are required to perform the following, either individually or in a group and present
your findings in a report to be submitted to the Course Lecturer:
Answer the following questions:
What are the challenges associated with acquiring resources?
What could happen if a new team member is not oriented to the project
As a project manager, what should you do when you are assigned to a project but
feel you don’t have the expertise to do the work?
What should a team member do when it is clear the assigned project manager
simply doesn’t have the skills needed to manage the project (for example, the
project is behind schedule, meetings have become finger-pointing sessions, or the
project manager doesn’t return calls and sits in the office all day with the door
shut)?
List at least five expectations a project sponsor may have of you (the project
manager) and five commitments a sponsor will make to you (the project manager).
Describe items that are considered a cost of quality and items that are considered a
cost of nonconformance.
What is the purpose of a quality audit?
Why is a bidder’s conference important?
When should a bidder’s conference take place?
Who should conduct the bidder’s conference and why?
5.11. CASE STUDY
Higher College of Technology would launch the IT Open Day on 6th of March 2015.
They assigned you as the Project Manager of this event. The project charter and
contract had been signed. The following are the activities to be undertaken in
preparation for the launching of IT Open Day:
130
ITDB3111- Project Management, Third Edition
a. The first task is collecting inputs for Project charter (5 days). Part of this task is
Project Statement of Work. You are the person responsible for this task.
b. Identify the stakeholders will start at the same time with collecting inputs for
Project charter that will take 10 days and should be done by Portfolio Manager.
c. After collecting inputs for project charter and identifying the stakeholders, the
next task is assessing the tools and techniques. This task should be done by
Project Sponsor and Project Manager. It will take 10 days to finish the task. Part
of this task is to provide expert judgment.
d. After assessing tools and techniques, the next tasks are: creating charter
template (5 days), at the same time with creating charter template is project
justification (3 days) and also project approval requirements (5 days). The
person responsible is the Project Manager, Project Sponsor and the customer.
e. After creating charter template, project justification and project approval, the
next task is setting up the project management office. Part of this task is to
locate for venue which will take 15 days and should be done by the portfolio
manager.
f. Defining roles and responsibilities should be the next task after identifying the
stakeholders, and setting up the project management office. It should be done
within 20 days and the person in charge is the Project Manager and Project
Sponsor.
In one of your team meetings, it has been reported that there’s a lot of issues and it is
found that many of the issues could have been prevented had a simple review checklist
been used. You prepare a code review checklist and ensure the code is reviewed as per
the checklist. With the project done you decide to communicate the completion details
and closure of contracts.
1. What type of communication (Incident, Formal or informal) are you going to use
to communicate the completion details and closure of contracts?
2. Analyze the above scenario and categorize if your action is preventive or
corrective. Justify your answer.
5.12. HANDS-ON
131
ITDB3111- Project Management, Third Edition
132
ITDB3111- Project Management, Third Edition
6.1. INTRODUCTION
The Monitoring and Controlling process group involves taking measurements and
performing inspections to find out whether there are variances in the plan. If you
discover variances, you need to take corrective action to get the project back on track
and repeat the affected project Planning processes to make adjustments to the plan as a
result of resolving the variances.
6.1.1. Objectives
The objectives of this Chapter are:
Explain how to manage and control the project.
Determine and identify the suitable management direction at the project
execution.
Determine how to control possible risk during the execution of the
project.
6.1.2. Outcomes
Upon completion of this chapter, the student will be able to:
Explain the concepts of Project Management and Knowledge Areas.
Analyze a plan using methods and tools including Establish WBS, time &
effort estimates, resource allocation and scheduling.
Analyze concepts of Quality Management, Assurance and Control.
Analyze risks and manage them.
Analyze project execution and manage it.
Evaluate set-targets, deliverables and conflict resolution documents.
Use case studies for project management.
6.1.3. Terminologies
Acceptance Criteria. Those criteria, including performance
requirements and essential conditions, which must be met before
project deliverables are accepted.
Control. Comparing actual performance with planned performance,
analyzing variances, assessing trends to effect process improvements,
133
ITDB3111- Project Management, Third Edition
134
ITDB3111- Project Management, Third Edition
135
ITDB3111- Project Management, Third Edition
136
ITDB3111- Project Management, Third Edition
o Collecting Metrics
One of the outputs of the plan quality process is quality metrics. You define
what you want to measure to analyze performance. The following is a list
of metrics that could be collected on your project. This list is not exhaustive
but may help provide additional ideas for your project:
Cost
Schedule
Productivity
Quality of deliverables
Quality of project
o Quality Control
Quality control in project management requires that the project manager use
appropriate tools at predetermined intervals in order to meet project goals.
These tools include the following:
Cost/benefit analysis
Control charts
Benchmarking
Design of experiments
Statistical sampling
Flowcharting
Cause and effect diagrams
137
ITDB3111- Project Management, Third Edition
Histograms
Pareto charts
Run charts
Scatter diagrams
Inspections
138
ITDB3111- Project Management, Third Edition
6.5. ASSIGNMENT
You are required to perform the following, either individually or in a group and submit
your answers to the Course Lecturer:
Assignment 6.5
You can answer the following questions through the use of the Internet or other Project
Management books. Present a scenario or use diagrams to support your answers.
1. What information can a fishbone diagram give you?
139
ITDB3111- Project Management, Third Edition
140
ITDB3111- Project Management, Third Edition
6.7. HANDS-ON
You are required to perform the following, either individually or in a group:
If you are using Microsoft Project, see the Microsoft Project Laboratory Manual and
perform the following:
6.6.1. Laboratory Work: Setting Baseline in Tracking Gantt View
6.6.2. Laboratory Work: Resetting the Baseline
If you are using Primavera Project Planner, see the Primavera Project Planner
Laboratory Manual and perform the following:
5.1 Laboratory Work: Setting Baselines in Tracking Gantt View
5.2 Laboratory Work: Resetting the Baseline
7.1. INTRODUCTION
141
ITDB3111- Project Management, Third Edition
This chapter deals with the basic tasks needed to perform project closure. It provides
learners with the proper methods on how to perform formal acceptance of project
deliverables, how to transfer the deliverables into operation, process information from
lessons learned in project activities and how to assess the performance of the project
team.
7.1.1. Objectives
The objectives of this Chapter are:
Determine the process in accepting or rejecting projects.
Identify the necessary measures and documents in finalizing the
project.
7.1.2. Outcomes
Upon completion of this chapter, the student will be able to:
Explain the concepts of Project Management and Knowledge Areas.
Analyze organization structures.
Analyze a plan using methods and tools including Establish WBS, time &
effort estimates, resource allocation and scheduling.
Analyze concepts of Quality Management, Assurance and Control.
Evaluate set-targets, deliverables and conflict resolution documents.
Use case studies for project management.
7.1.3. Terminologies
Close Procurements - The process of completing each project’s
procurement.
Close Project or Phase - The process of finalizing all activities across
all of the Project Management Process Groups to formally complete the
project or phase.
Contract - a mutually binding agreement that obligates the seller to
provide the specified product or service or result and obligates the buyer
to pay for it.
142
ITDB3111- Project Management, Third Edition
143
ITDB3111- Project Management, Third Edition
144
ITDB3111- Project Management, Third Edition
145
ITDB3111- Project Management, Third Edition
146
ITDB3111- Project Management, Third Edition
147
ITDB3111- Project Management, Third Edition
148
ITDB3111- Project Management, Third Edition
149
ITDB3111- Project Management, Third Edition
150
ITDB3111- Project Management, Third Edition
151
ITDB3111- Project Management, Third Edition
152
ITDB3111- Project Management, Third Edition
1. What should the project manager do if the final outcome of the project is not
accepted?
2. Does formal project acceptance release you, the project manager, from further
obligations?
3. What do you do if the customer says he will sign the document but wants
additional concessions from you?
4. Why should the project manager write a performance review of team members
when feedback has been provided to the team members since the project
began?
5. What should you do if you are uncomfortable providing less-than-satisfactory
feedback?
6. Is it appropriate to ask your team members to write their own performance
reports?
153
ITDB3111- Project Management, Third Edition
154