This inspection checklist is used to inspect reinforced concrete structures during construction. It includes items to inspect such as formwork, reinforcement, concrete, and post-concreting work. The contractor and resident engineer must both inspect the items and indicate their findings. They then sign to confirm the work complies with construction drawings before further concreting is allowed. The checklist captures project details, inspection dates, locations, structure types, and comments on inspection items.

Uploaded by

khinwah88
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (5 votes)
2K views1 page

Reinforced Concrete Inspection Checklist 2015

This inspection checklist is used to inspect reinforced concrete structures during construction. It includes items to inspect such as formwork, reinforcement, concrete, and post-concreting work. The contractor and resident engineer must both inspect the items and indicate their findings. They then sign to confirm the work complies with construction drawings before further concreting is allowed. The checklist captures project details, inspection dates, locations, structure types, and comments on inspection items.

Uploaded by

khinwah88
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

S G TAN & ASSOCIATES SDN BHD

REINFORCED CONCRETE INSPECTION CHECKLIST

PROJECT TITLE : ____________________________________________________________________________________________

INSPECTION DATE : _____________________________________________ SERIAL NO. _________________________________

LOCATION (Block / Level / Floor / Grid Line ) : ______________________________________________________________________

STRUCTURE TYPE (Pilecap / Column / Beam / Slab / Staircase) :_______________________________________________________

CONSTRUCTION DRG NO. ______________________________________REV. NO._________DATE ISSUED : ________________

Item Description Contractor’s Inspection Resident Engineer’s Inspection


Date Date
Comments* Comments*
1 Formwork
Dimension
Verticality
Levels
Stability/Tightness/Cleanliness
Safe and proper inspection access
2 Reinforcement
Main bar number & sizes
Main bar cover & arrangement
Main bar lap length & location
Link sizes & spacing
Provision for starter bars
3 Concrete
Name of Supplier
Weather condition
Grade
Slump test result
Test cube sampling (3 sets minimum)
Proper vibration
5 Miscellaneous
Width and depth of excavation
Cut or fill ground
Ground / Hardcore compaction
R.W.D.P in structure
R.C. features starter bar
M & E openings (add. reinforcements)
Site difficulties
4 Post concreting
Proper curing
Date of striking formwork
Honey comb & void
Exposed reinforcement
Bulging
All defective work properly rectified

*Comments : C = Complied, F = No Good, N/A = Not Applicable, Y = Yes, N = No

We hereby confirm that the above works were inspected by us and found to have complied fully with the
construction drawings :

Contractor : Resident Engineer :

Signature : Signature :

Note : Checklist shall be properly filled up, signed, and submitted to the Engineer. Concreting can only be
permitted after full compliance with the Engineer’s requirements.

You might also like