ESTIMATES
ESTIMATES
LOCATION :
SUBJECT : Bill of Quantities
ITEM DESCRIPTION
I. EXCAVATION WORKS
B Labor
Construction Foreman
Skilled Laborer
Common Laborer
ITEM DESCRIPTION
A Materials
40kg Portland Cement
Sand
Crushed Gravel 3/4
12mm x 1.2m x 2.4m Ordinary Plywood
2x4 Coco Lumber
Assorted Common Wire Nail
6m−∅12mm DRSB
6m-∅10mm DRSB
#16 Tie Wire
B Labor
Construction Foreman
Skilled Laborer
Common Laborer
C Equipment
One Bagger Concrete Mixer
ITEM DESCRIPTION
B Labor
Construction Foreman
Skilled Laborer
Common Laborer
C Equipment
Portable Welding Machine
0.00
15233.28
0.00
15233.28
ECT COST
of Estimtated Direct Cost 2284.99
of Estimtated Direct Cost 1523.33
of D 3808.32
of (D + E) 952.08
4760.40
262.57
19993.68
1102.80
QUANTITY UNIT
17.99 cu.m.
QUANTITY UNIT UNIT COST AMOUNT
70305.00
34802.40
4128.00
109235.40
ECT COST
of Estimtated Direct Cost 10923.54
of Estimtated Direct Cost 10923.54
of D 21847.08
of (D + E) 131082.48
152929.56
8500.81
262164.96
14572.82
QUANTITY UNIT
137.00 cu.m.
QUANTITY UNIT UNIT COST AMOUNT
2.00 pcs 3944.68 7889.37
1.00 pcs 1600.00 1600.00
3.00 pcs 65.00 195.00
1.00 gals 65.00 65.00
1.00 gals 450.00 450.00
2.00 gals 350.00 700.00
1.00 pcs Material200.00
Cost 200.00
...........
11099.37
1972.72
5695.04
18767.13
ECT COST
of Estimtated Direct Cost 2815.07
of Estimtated Direct Cost 1876.71
of D 4691.78
of (D + E) 23458.91
28150.69
205.48
46917.82
342.47
BREAKDOWN OF ESTIMATED EXPENDITURE
SUB-TOTAL -
SUB-TOTAL
TOTAL PROJECT ESTIMATED COST 100.00% 329,076.46
SUB-TOTAL
SUB-TOTAL -
SUB-TOTAL 99.17%
TOTAL PROJECT ESTIMATED COST 1,200,000.00
35,212.27
600,000.00
Project Name : CONSTRUCTION OF ANOTHER WINDCONE POLE AT RUNWAY 36
Location : SIARGAO AIRPORT, SURIGAO DEL NORTE
SCOPE OF WORK
1.0 GENERAL
The works to be done accomplished by the successful bidder shall consist of furnishing,
supervision, labor, materials, and tools to complete the Construction of Another Windconce Pole At Runway 36.
A Materials
40kg Portland Cement
Sand
Crushed Gravel 3/4
12mm x 1.2m x 2.4m Ordinary Plywood
2x4 Coco Lumber
Assorted Common Wire Nail
B Labor
Construction Foreman
Skilled Laborer
Common Laborer
C Equipment
One Bagger Concrete Mixer
QUANTITY UNIT UNIT COST AMOUNT