P1Ch1AS7AndASI29 PDF
P1Ch1AS7AndASI29 PDF
EXAMPLES
“Construction of a Single Asset “ :
Construction Construction
Laying Rails Etc
Of Bridge Of Dam
TYPES OF CONTRCTS
4
Construction
Contracts
Segmenting
Contracts
Combining
Contracts
Combining & Segmenting
Construction Contracts
7
• Identify costs incurred and cost estimates for the unfinished contract works.
2.
• Check if outcome of the contract can be reliably measured on basis of contract revenue &
3. cost estimates.
• Check disclosures.
6.
Contract Revenue
10
COMPRISED OF 4 COMPONENTS :
Contract Revenue
Initial
Agreed Variations Claims Incentives
Upon Price
CHANGES IN
SPECIFICATION OR DESIGN
DELAYS CAUSED BY
CUSTOMERS
CHANGE IN QUALITY OF
INPUTS
CLAIMS
14
1. Probability of customer’s
acceptance.
AND
2. Reliability in
measurement of amount of
claim
Incentives
15
Contract
Costs
Directly Allocated
Specific
Attributable Contract
Costs
Costs Overhead
16
Direct Costs
1. • Site labour cost.
2. • Materials.
3. • Transport charge.
4. • Cost of design.
17
Direct Costs II
• Cost of rectification and guarantee work, including warranty costs
8.
18
Cost Attributable Costs - Excluded
19
General and administrative costs for which the reimbursement is not specified in the
contract
If such “pre-contract” costs are reliably measurable and it is probable that the
contract will be secured, then such costs are included as part of the overall contract
cost.
Once such “pre-contract” costs have been expensed, they cannot be reinstated
once the contract is secured.
Allocated Contract Overhead
21
It includes :
1. • Insurance.
When it is likely that contract costs will exceed contract revenue, then the entire loss must
be
recognized in the income statement immediately, regardless of the stage of completion.
Measurement of Outcome
23
• It is probable that the economic benefit of the contract will flow to the entity;
AND
• Both the costs to complete the contract and the stage of completion can be reliably
estimated:
AND
• The costs attributable to the contract can be clearly identified and measured.
Measurement of Outcome
24
COST-PLUS CONTRACT:
• It is probable that the economic benefit of the contract will flow to the entity;
AND
OR
Stage of completion
Future Costs ?
29
No profit , No Loss.
No Loss
Profit Loss
No Profit
b) Advance received.
PARTICULARS AMOUNT
( CU’000 )
Costs to date 48
Costs to complete 32
Profit (CU100,000 – 12
CU80,000)
36
Illustration
The following information relates to a cost plus contract by a
business with a 30 June year end.
2007 2008
CU’000 CU’000
Cumulative costs incurred 100 150
on work to date
2007
Costs CU100,000
2008
Costs CU150,000 to date, less CU100,000
recognized in 2007 = CU50,000
39
Illustration
A business is not able to measure reliably the outcome
of a contract, but estimates that all costs incurred are
recoverable from the customer. The following details are
available :
CU’000
40
Illustration
The amounts to be recognized in the statement of
comprehensive income are :
CU’000
Revenue 30
41
Illustration
The following details relate to a contract expected to be loss making :
CU’000
Estimated contract revenue 100
Costs to date 72
Costs to complete 48
Total estimated costs 120
42
Illustration
The amounts to be recognized in the statement of
comprehensive income are :
CU’000
Revenue (60% of CU100,000) 60
Cost of sales 72
Loss 12
Provision for full contract 8
1. Lazy Builders Inc. has incurred the following contract costs in the
first year on a two-year fixed price contract for $4.0 million to
construct a bridge:
• Material cost =………………………………………………….. $2
million
• Other contract costs (including site labor costs) = $1 million
• Cost to complete = ……………………………………………..$2
million
How much profit or loss should Lazy Inc. recognize in the first year of
the three-year construction contract?
(a) Loss of $0.5 million prorated over two years.
(b) Loss of $1.0 million (expensed immediately).
(c) No profit or loss in the first year and deferring it to second year.
(d) Since 60% is the percentage of completion, recognize 60% of loss
(i.e., $0.6 million).
MCQ - 2
2. Brilliant Inc. is constructing a skyscraper in the heart of town and has signed a
fixed price two-year contract for $21.0 million with the local authorities. It has
incurred the following cost relating to the contract by the end of first year:
• Material cost =……………………………………………………………… $5 million
• Labor cost =………………………………………………………………….. $2 million
• Construction overhead =………………………………………………. $2 million
• Marketing costs = ………………………………………………………..$0.5 million
• Depreciation of idle plant and equipment = …………………$0.5 million.
At the end of the first year, it has estimated cost to
complete the contract =………………………………………………….. $9 million.
What profit or loss from the contract should Brilliant Inc. recognize at the end
of the first year?
(a) $1.5 million (9/18× 3.0)
(b) $1.0 million (9/18 × 2.0)
(c) $1.05 million (10/19 × 2.0)
(d) $1.28 million (9.5/18.5 × 2.5)
46
MCQ - 3
3. Mediocre Inc. has entered into a very profitable fixed price contract for
constructing a high-rise building over a period of three years. It incurs the
following costs relating to the contract during the first year:
• Cost of material =……………………………………………………………….. $2.5 million
• Site labor costs = ………………………………………………………………….$2.0 million
• Agreed administrative costs as per contract to
be reimbursed by the customer =………………………………………... $1 million
• Depreciation of the plant used for the construction = …………$0.5 million
• Marketing costs for selling apartments when they are ready $1.0 million
Total estimated cost of the project =……………………………………. $18 million
48
MCQ - 5
• 5. A construction company signed a contract to build a theater
over a period of two years, and with this contract also signed
a maintenance contract for five years. Both the contracts are
negotiated as a single package and are closely interrelated to
each other. The two contracts should be
(a) Combined and treated as a single contract.
(b) Segmented and considered two separate contracts.
(c) Recognized under the completed contracted method.
(d) Treated differently—the building contract under the
completed contract method and maintenance contract under
the percentage of completion method.
49
Thank
You.
50