0% found this document useful (0 votes)
1K views10 pages

Two-Storey Residential Building

The document provides a program of works for a two-storey residential house project in Barangay Bonifacio, Surigao City. It includes a project description, technical personnel required, scope of works divided into 17 activities, estimated expenditures breakdown, and sample cost estimates for some of the activities. The total estimated cost of the proposed work is Php 4,991,196.30 to be completed within 240 calendar days.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views10 pages

Two-Storey Residential Building

The document provides a program of works for a two-storey residential house project in Barangay Bonifacio, Surigao City. It includes a project description, technical personnel required, scope of works divided into 17 activities, estimated expenditures breakdown, and sample cost estimates for some of the activities. The total estimated cost of the proposed work is Php 4,991,196.30 to be completed within 240 calendar days.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 10

INDIVIDUAL PROJECT PROGRAM OF WORKS

NAME AND LOCATION OF PROJECT: SOURCE OF FUNDS: APPROPRIATION:


TWO (2) STOREY RESIDENTIAL HOUSE
PhP 4,991,196.30
C.D. TO COMPLETE:
Barangay Bonifacio, Surigao City
240 Calendar Days
PROJECT DESCRIPTION: IMPLEMENTATION
PROCEDURE:

TECHNICAL PERSONNEL REQUIRED: EQUIPMENT:


1 - Foreman
16 - Skilled Workers Labor Intensive
10 - Unskilled Workers

SCOPE OF WORKS %WT AMOUNT (P)


I. EXCAVATION/BACKFILLING AND GRAVEL BEDDING: 2.38 118,904.50
II. FORMWORKS AND SCAFFOLDINGS: 4.14 206,800.00
III. CONCRETE WORKS: 11.85 591,289.60
IV. EMBANKMENT: 0.49 24,677.75
13.82 689,591.80
VI. MASONRY WORKS: 19.24 960,300.00
VII. STEEL TRUSSES: 3.86 192,500.00
VIII. SUPPLY AND INSTULATION OF COLOROOF ROOFING: 2.53 126,500.00
IX. DOORS AND WINDOWS: 6.33 315,700.00
X. CEILING WORKS: 5.55 277,200.00
XI. TILE WORKS: 7.19 358,622.00
XII. PLUMBING WORKS: 5.59 278,929.45
XIII. ELECTRICAL WORKS: 4.19 209,000.00
XIV. PAINTING WORKS: 4.88 243,520.20
XV. KITCHEN COUNTER AND CABINETS: 4.40 219,373.00
XVI. SUPPLY AND INSTALLATION OF STAINLES STEEL RAILINGS: (BAL 1.81 90,288.00
XVII. SUPPLY AND INSTALLATION OF ARCHITECTURAL SUN BUFFERS: 1.76 88,000.00
TOTAL 100.00 4,991,196.30

BREAKDOWN OF ESTIMATED EXPENDITURES:

A.TOTAL ESTIMATED MATERIALS COST 3,149,893.50


B. TOTAL LABOR COST 1,233,057.60
C. EQUIPMENT 154,500.00
D. SUPERVISION
E. CONTINGENCIES / MISCELLANEOUS 453,745.20

TOTAL ESTIMATED COST OF THE PROPOSED WORK 4,991,196.30


BILL OF MATERIALS AND COST ESTIMATES

Name of Project: Two (2) Storey Residential Building


Location: Barangay San Juan, Surigao City

ACTIVITIES/MATERIALS DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST

I. EXCAVATION/BACKFILLING AND GRAVEL BEDDING:


QUANTITY: 164.19 cu. m.
● Crushed Gravel 26 cu. m. P 1,000.00 P 26,000.00
TOTAL MATERIALS COST P 26,000.00
LABOR COST P 82,095.00
SUB-TOTAL P 108,095.00
CONTINGENCIES / MISCELLANEOUS P 10,809.50
SUPERVISION P
TOTAL COST P 118,904.50

II. FORMWORKS AND SCAFFOLDINGS:


QUANTITY: 252.00 sq. m.
● Coco - Lumber 2" x 4" x 10' 400 pcs P 107.00 P 42,800.00
● Coco - Lumber 2" x 3" x 10' 600 pcs P 80.00 P 48,000.00
● Coco - Lumber 2" x 2" x 8' 250 pcs P 43.00 P 10,750.00
● Marine Plywood 1/4" Thk. x 4' x 8' 82 shts P 390.00 P 31,980.00
● Common Wire Nails # 4" 75 kgs P 60.00 P 4,500.00
● Common Wire Nails # 2 1/2" 25 kgs P 60.00 P 1,500.00
● Common Wire Nails # 1 3 kgs P 60.00 P 180.00
TOTAL MATERIALS COST P 139,710.00
LABOR COST P 48,290.00
SUB-TOTAL P 188,000.00
CONTINGENCIES / MISCELLANEOUS P 18,800.00
SUPERVISION P
TOTAL COST P 206,800.00

III. CONCRETE WORKS:


QUANTITY: 84.14 cu. m.
● Portland Cement, T-1 40 kgs./bag 842 bags P 220.00 P 185,240.00
● Washed Sand 43 cu. m. P 1,000.00 P 43,000.00
● Crushed Gravel 85 cu. m. P 1,000.00 P 85,000.00
TOTAL MATERIALS COST P 313,240.00
LABOR COST P 125,296.00
EQUIPMENT EXPENSES:
● 1 - Bagger Mixer 30 days P 1,000.00 P 30,000.00
● 1 - Porta Lift 30 days P 2,000.00 P 60,000.00
● 1 - Concrete Vibartor 30 days P 300.00 P 9,000.00
SUB-TOTAL P 537,536.00
CONTINGENCIES / MISCELLANEOUS P 53,753.60
SUPERVISION P
TOTAL COST P 591,289.60

IV. EMBANKMENT:
QUANTITY: 47.48 cu. m.
● Embankment Materials 47.48 lgths P 350.00 P 16,618.00
TOTAL MATERIALS COST P 16,618.00
LABOR COST P 5,816.30
SUB-TOTAL P 22,434.30
CONTINGENCIES / MISCELLANEOUS P 2,243.45
SUPERVISION P
TOTAL COST P 24,677.75

V. REINFORCING STEEL BARS:


QUANTITY: 8,740.61 kgs
● Deformed Bars 16 mm. Dia. x 6 m. Long 676 lgths P 390.00 P 263,640.00
● Deformed Bars 12 mm. Dia. x 6 m. Long 333 lgths P 243.00 P 80,919.00
● Deformed Bars 10 mm. Dia. x 6 m. Long 631 lgths P 135.00 P 85,185.00
● Tie Wire # 16 120 kgs P 70.00 P 8,400.00
TOTAL MATERIALS COST P 438,144.00
LABOR COST P 175,257.60
EQUIPMENT EXPENSES:
● 1 - Electric Metal Saw 15 days P 400.00 P 6,000.00
● 1 - Bar Bender 15 days P 500.00 P 7,500.00
SUB-TOTAL P 626,901.60
CONTINGENCIES / MISCELLANEOUS P 62,690.20
SUPERVISION P
TOTAL COST P 689,591.80

VI. MASONRY WORKS:


QUANTITY: 819.15 sq. m.
● Concrete Hollow Blocks 4" Thk. 5,085 pcs P 13.00 P 66,105.00
● Concrete Hollow Blocks 6" Thk. 5,155 pcs P 20.00 P 103,100.00
● Stone Bricks, 30 cm. x 30 cm. 122 pcs P 1,300.00 P 158,600.00
● Portland Cement, T-1 40 Kgs/Bag 770 bags P 220.00 P 169,400.00
● Washed Sand 66 cu. m. P 1,000.00 P 66,000.00
● Deformed Bars 10 mm. Dia. x 6 m. Long 420 lgths P 135.00 P 56,700.00
● Hacksaw Blade 10 pcs P 65.00 P 650.00
● Tie Wire # 16 40 kgs P 70.00 P 2,800.00
TOTAL MATERIALS COST P 623,355.00
LABOR COST P 249,645.00
SUB-TOTAL P 873,000.00
CONTINGENCIES / MISCELLANEOUS P 87,300.00
SUPERVISION P
TOTAL COST P 960,300.00

VII. STEEL TRUSSES:


QUANTITY: 171.65 sq. m.
● Angle Bar, 2" x 2" x 6 m. x 1/4" Thk. 28 lgths P 1,300.00 P 36,400.00
● Angle Bar, 1 1/2" x 1 1/2" x 6 m. x 1/4" Thk. 31 lgths P 990.00 P 30,690.00
● Channel Purlins, 1.5 mm. Thk. x 2" x 3" x 6 m. 46 lgths P 570.00 P 26,220.00
● Plain Round Bar, 10 mm. Dia. x 6.00 m. 12 lgths P 160.00 P 1,920.00
● Angle Bar, 1" x 1" x 6 m. x 1/8" Thk. 20 lgths P 320.00 P 6,400.00
● Welding Electrode, 1/8" Dia. 6012 40 kgs P 120.00 P 4,800.00
● Steel Brush 2 pcs P 48.00 P 96.00
● Metal Primer Paint, Red Oxide 8 gals P 500.00 P 4,000.00
● Paint Brush # 2 2 pcs P 45.00 P 90.00
TOTAL MATERIALS COST P 110,616.00
LABOR COST P 43,384.00
EQUIPMENT EXPENSES:
● 1 - Welding Machine 15 days P 1,000.00 P 15,000.00
● 1 - Electric Metal Cutting Saw 15 days P 400.00 P 6,000.00
SUB-TOTAL P 175,000.00
CONTINGENCIES / MISCELLANEOUS P 17,500.00
SUPERVISION P
TOTAL COST P 192,500.00

VIII. SUPPLY AND INSTULATION OF COLOROOF ROOFING:


QUANTITY: 171.65 sq. m.
● Pre-Painted Coloroof Rib Type Longspan Galvanized Roofing 171.65 sq. m. P 500.00 P 85,825.00
Complete with Wall Flashings, Metal Fascia, Texscrews
Roof Sealant and Others Accessories
TOTAL MATERIALS COST P 85,825.00
LABOR COST P 29,175.00
SUB-TOTAL P 115,000.00
CONTINGENCIES / MISCELLANEOUS P 11,500.00
SUPERVISION P
TOTAL COST P 126,500.00

IX. DOORS AND WINDOWS:


QUANTITY: 49.83 sq. m.
● Panel Door with Door Jamb, 0.90 m. x 2.10 m. 2 sets P 9,600.00 P 19,200.00
● Panel Door with Door Jamb, 0.80 m. x 2.10 m. 2 sets P 8,500.00 P 17,000.00
● Panel Door with Door Jamb, 0.80 m. x 2.10 m. 8 sets P 7,500.00 P 60,000.00
● PVC Door with Complete with Accessories 0.60 m. x 2.10 m. 8 sets P 3,000.00 P 24,000.00
● Loose Pin Hinges, 4" x 4" 24 pairs P 180.00 P 4,320.00
● Door Knob, Kwikset 20 sets P 1,100.00 P 22,000.00
● Glass Sliding Door Complete with Aluminum Jamb, Framing 1 set P 27,720.00 P 27,720.00
Lock and Other Accessories, 3.30 m. x 2.10 m.
● Glass Sliding Window Complete with Aluminum Jamb, Framin 4 sets P 6,720.00 P 26,880.00
Lock and Other Accessories, 1.40 m. x 1.20 m.
● Glass Sliding Window Complete with Aluminum Jamb, Framin 2 sets P 2,400.00 P 4,800.00
Lock and Other Accessories, 1.00 m. x 0.60 m.
● Glass Sliding Window Complete with Aluminum Jamb, Framin 2 sets P 4,800.00 P 9,600.00
Lock and Other Accessories, 1.00 m. x 1.20 m.
● Glass Sliding Window Complete with Aluminum Jamb, Framin 2 sets P 2,880.00 P 5,760.00
Lock and Other Accessories, 0.60 m. x 1.20 m.
● Glass Sliding Window Complete with Aluminum Jamb, Framin 6 sets P 1,440.00 P 8,640.00
Lock and Other Accessories, 0.60 m. x 0.60 m.
TOTAL MATERIALS COST P 229,920.00
LABOR COST P 57,080.00
SUB-TOTAL P 287,000.00
CONTINGENCIES / MISCELLANEOUS P 28,700.00
SUPERVISION P
TOTAL COST P 315,700.00

X. CEILING WORKS:
QUANTITY: 314.96 sq. m.
● Pre-Painted Coloroof Spandrel, 0.40 mm. Thk. 57.6 sq. m. P 400.00 P 23,040.00
● Hardiflex Board, 4.5 mm. Thk. x 4 ft. x 8 ft. (Lite) 80 shts P 380.00 P 30,400.00
● Carrying Channel, 0.8 mm. x 5.00 m. 218 pcs P 140.00 P 30,520.00
● Double Furring Channel, 0.4 mm. x 5.00 m. 218 pcs P 130.00 P 28,340.00
● Single Furring Channel, 0.5 mm. x 5.00 m. 218 pcs P 110.00 P 23,980.00
● Double Furring Clip 1,530 pcs P 6.00 P 9,180.00
● Hardflex Board Screw 18,897 pcs P 1.00 P 18,897.00
● Blind Rivets, 1/8" Dia. x 1/2" (1,000 Pcs/Pack) 8 packs P 380.00 P 3,040.00
● Screw with Tox 1093 pcs P 3.50 P 3,825.50
TOTAL MATERIALS COST P 171,222.50
LABOR COST P 68,777.50
EQUIPMENT EXPENSES:
● 1 - Electrical Drill 30 days P 300.00 P 9,000.00
● 1 - Electrical Grinder 10 days P 300.00 P 3,000.00
SUB-TOTAL P 252,000.00
CONTINGENCIES / MISCELLANEOUS P 25,200.00
SUPERVISION P
TOTAL COST P 277,200.00

XI. TILE WORKS:


QUANTITY: 406.22 sets
● Floor Tiles, 40 cm. x 40 cm. Granite 2,015 pcs P 70.00 P 141,050.00
● Wall Tiles, 40 cm. x 40 cm. Granite 519 pcs P 70.00 P 36,330.00
● Portland Cement, T-1 40 Kgs/Bag 122 bags P 220.00 P 26,840.00
● Washed Sand 10 cu. m. P 1,000.00 P 10,000.00
● Tile Grout Cement 2 Kgs/Bag 18 packs P 80.00 P 1,440.00
TOTAL MATERIALS COST P 215,660.00
LABOR COST P 101,360.00
EQUIPMENT EXPENSES:
● 1 - Electrical Grinder 30 days P 300.00 P 9,000.00
SUB-TOTAL P 326,020.00
CONTINGENCIES / MISCELLANEOUS P 32,602.00
SUPERVISION P
TOTAL COST P 358,622.00

XII. PLUMBING WORKS:


QUANTITY:
● Water Closet, Closed Coupled 6 Liters Tank Capacity 6 sets P 7,500.00 P 45,000.00
Complete with the following: Flexible Hose Angle Valve
and Other Accessories
● Stainless Steel Sink Complete with Goose Neck Faucet 2 sets P 6,500.00 P 13,000.00
and Other Accessories
● Lavatory Sink, Complete with the following: Lavatory Faucet 6 set P 6,500.00 P 39,000.00
Angle Valve, Flexible Hose, P-Trap and Sink Drain
Assy. and Other Accessories
● Brass Faucet 8 pcs P 250.00 P 2,000.00
● Stainless Floor Drain 6" x 6" 6 pcs P 580.00 P 3,480.00
● PVC Pipe, 4" Dia. x 10 ft. Long, Series 1,000 30 lgths P 700.00 P 21,000.00
● PVC Elbow 4" Dia. x 90 Deg., Series 1,000 14 pcs P 70.00 P 980.00
● PVC Wye, 4" x 4" Series 1,000 23 pcs P 130.00 P 2,990.00
● PVC Elbow 4" Dia. x 45 Deg., Series 1,000 23 pcs P 70.00 P 1,610.00
● PVC Tee-Wye, 4" x 4" Series 1,000 9 pcs P 130.00 P 1,170.00
● PVC Wye, 4" x 2" Series 1,000 5 pc P 130.00 P 650.00
● PVC Wye, 2" x 2" Series 1,000 5 pc P 40.00 P 200.00
● PVC Clean-out with Cap, 4" Dia. Series 1,000 14 pcs P 390.00 P 5,460.00
● PVC Solvent Cement, 500 CC/Can 45 cans P 160.00 P 7,200.00
● PVC Pipe, 2" Dia. x 10 ft. Long, Series 1,000 27 lgths P 350.00 P 9,450.00
● PVC P-Trap, 2" Dia. Series 1,000 9 pcs P 90.00 P 810.00
● PVC Elbow 2" Dia. x 90 Deg., Series 1,000 32 pcs P 40.00 P 1,280.00
● PVC Tee-Wye, 2" Dia. 14 pcs P 65.00 P 910.00
● PPR Pipe, 1/2" Dia. x 12 ft. Long 45 lgths P 380.00 P 17,100.00
● PPR Coupling, 1/2" Dia. 45 pcs P 18.00 P 810.00
● PPR Union, 1/2" Dia. 45 pcs P 56.00 P 2,520.00
● PPR Female Adapter 18 pcs P 96.00 P 1,728.00
● PPR Equal Tee, 1/2" Dia. 18 pcs P 25.00 P 450.00
● PPR Elbow, 90 Deg. 1/2" Dia. 45 pcs P 25.00 P 1,125.00
● PPR Stop Valve Socket End, 1/2" Dia. 3 pc P 400.00 P 1,200.00
TOTAL MATERIALS COST P 181,123.00
LABOR COST P 72,449.20
SUB-TOTAL P 253,572.20
CONTINGENCIES / MISCELLANEOUS P 25,357.25
SUPERVISION P
TOTAL COST P 278,929.45
XIII. ELECTRICAL WORKS:
QUANTITY: 379.93 sq. m.
● Circuit Breaker Panel Board 1 - Main and 6 - Branches 2 sets P 7,500.00 P 15,000.00
Complete with Plug-in Type Circuit Breakers
1 - 60A Main
1 - 15A Branches
1 - 20A Branches
4 - 30A Branches
● Stranded Wire, THW # 14 3 boxes P 2,900.00 P 8,700.00
● Stranded Wire, THW # 12 3 boxes P 3,200.00 P 9,600.00
● Stranded Wire, THW # 10 1 box P 3,800.00 P 3,800.00
● Stranded Wire, THW # 6 1 box P 6,000.00 P 6,000.00
● Luminaire 24" x 48" 2-18 Watts, LED Tube 18 sets P 1,950.00 P 35,100.00
● LED Pinlight, Downlight Type 18 sets P 450.00 P 8,100.00
● LED Emergency Light 6 sets P 1,900.00 P 11,400.00
● Switch 1-Gang Classic Series with LED Set, 10A/250V 6 sets P 320.00 P 1,920.00
● Switch 3-Gang Classic Series with LED Set, 10A/250V 9 sets P 350.00 P 3,150.00
● Switch 2-Gang Classic Series with LED Set, 10A/250V 3 set P 330.00 P 990.00
● Convenience Outlet 3-Gang Classic Series 10A/250V 21 sets P 200.00 P 4,200.00
● PVC Electrical Pipe, 1/2" Dia. x 3.00 m. 120 lgths P 140.00 P 16,800.00
● PVC Utility Box, 2" x 4" Orange 30 pcs P 48.00 P 1,440.00
● PVC Octagonal Junction Box 4" x 4" with Cover and Screws 60 pcs P 48.00 P 2,880.00
● PVC Electrical Pipe, 1" Dia. x 3.00 m. 6 lgths P 280.00 P 1,680.00
● Entrance Cap 1" 2 pc P 150.00 P 300.00
● Elecrical Tape 30 rolls P 65.00 P 1,950.00
● Convenience Outlet 3-Pin Flash Mounted for Aircon 6 pcs P 300.00 P 1,800.00
● Cable Tie 150 pcs P 5.00 P 750.00
● Tie Wire # 16 3 kgs P 80.00 P 240.00
TOTAL MATERIALS COST P 135,800.00
LABOR COST P 54,200.00
SUB-TOTAL P 190,000.00
CONTINGENCIES / MISCELLANEOUS P 19,000.00
SUPERVISION P
TOTAL COST P 209,000.00

XIV. PAINTING WORKS:


QUANTITY: 1,856.95 sq. m.
● Flat Latex Paint 48 gals P 650.00 P 31,200.00
● Gloss Latex Paint Top Coat 48 gals P 750.00 P 36,000.00
● Flat Wall Enamel Paint 3 gals P 650.00 P 1,950.00
● Quick Drying Enamel Paint 8 gals P 750.00 P 6,000.00
● Mortaflex Cement Modifier Paint, (Davies) 20 gals P 1,200.00 P 24,000.00
● Skim Coat Cement, 2- Kgs/Bag 40 bags P 498.00 P 19,920.00
● Masonry Putty 40 gals P 550.00 P 22,000.00
● Body Filler Time-Out 20 gals P 560.00 P 11,200.00
● Paint Roller 6" Cotton w/Tray 6 sets P 350.00 P 2,100.00
● Mini Paint Roller 4" Cotton 3 pcs P 75.00 P 225.00
● Paint Brush 2" 3 pcs P 45.00 P 135.00
● Sand Paper # 120 90 pcs P 20.00 P 1,800.00
● Paint Thinner 4 gals P 400.00 P 1,600.00
TOTAL MATERIALS COST P 158,130.00
LABOR COST P 63,252.00
SUB-TOTAL P 221,382.00
CONTINGENCIES / MISCELLANEOUS P 22,138.20
SUPERVISION P
TOTAL COST P 243,520.20

XV. KITCHEN COUNTER AND CABINETS:


QUANTITY: 10.60 linear meters
● Granite Counter Top, 0.60 m. x 2.00 m. 4 sets P 14,000.00 P 56,000.00
● Granite Counter Top, 0.6 m. x 1.30 m. 2 sets P 9,100.00 P 18,200.00
● Melamine Board, 18 mm. x 4 ft. x 8 ft. 6 shts P 3,000.00 P 18,000.00
● Plyboard, 3/4" Thk. x 4 ft. x 8 ft. 8 shts P 1,050.00 P 8,400.00
● Aluminum T-Moulding 12 lgths P 900.00 P 10,800.00
● Aluminum Moulding with Handle 4 lgths P 1,500.00 P 6,000.00
● Silicon Sealant 10 tubes P 185.00 P 1,850.00
● Swivel Type Counter High Chair (Steel) 8 pcs P 2,900.00 P 23,200.00
TOTAL MATERIALS COST P 142,450.00
LABOR COST P 56,980.00
SUB-TOTAL P 199,430.00
CONTINGENCIES / MISCELLANEOUS P 19,943.00
SUPERVISION P
TOTAL COST P 219,373.00

XVI. SUPPLY AND INSTALLATION OF STAINLES STEEL RAILINGS: (BALCONY AND STAIRS)
QUANTITY: 20.52 linear meters
● 2" Dia. Stainless Steel Tube, Top Rail and 3 - 1" Dia. 20.52 l.m. P 4,000.00 P 82,080.00
Stainless Steel Tube Center Rails with 1 1/2" Stainless
Steel Square Tube, Vertical Posts Spaced Equally
TOTAL MATERIALS COST P 82,080.00
LABOR COST P
SUB-TOTAL P 82,080.00
CONTINGENCIES / MISCELLANEOUS P 8,208.00
SUPERVISION P
TOTAL COST P 90,288.00

XVII. SUPPLY AND INSTALLATION OF ARCHITECTURAL SUN BUFFERS:


QUANTITY: 20.00 sq. m.
● Architectural Sun-Buffers Materials To Be Used 20 sq. m. P 4,000.00 P 80,000.00
˃ 2.5 mm. Thk. x 2" x 4" Rectangular Tubes
˃ 3/16" Thk. x 1" x 1" Angle Bars
˃ Welding Electrodes
˃ Metal Primer Paints
TOTAL MATERIALS COST P 80,000.00
LABOR COST P
SUB-TOTAL P 80,000.00
CONTINGENCIES / MISCELLANEOUS P 8,000.00
SUPERVISION P
TOTAL COST P 88,000.00

TOTAL MATERIALS COST P 3,149,893.50


LABOR COST P 1,233,057.60
CONTINGENCIES / MISCELLANEOUS P 453,745.20
EQUIPMENT P 154,500.00
TOTAL COST P 4,991,196.30

You might also like