LTBD1 With FSA Drive Manual PDF
LTBD1 With FSA Drive Manual PDF
1HSB429954-10en 2009-03-09
LTB 72.5-145D1/B
2-column support
Operating mechanism FSA 1
3-pole operation
The information contained in this document may be subject to change without prior warning and should not be
considered as binding on ABB AB's behalf. ABB AB accepts no liability for any errors that may appear in this
document. ABB AB is not liable for any damage resulting from the incorrect interpretation of this document. This
document, or parts thereof, may not be reproduced or copied without ABB AB's consent. It must not be distributed
to others, or used by unauthorized parties. Any breaches to the above will be penalized with the support of applicable
laws.
3 Safety 23
3.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
3.2 General safety information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
3.2.1 Levels of safety risks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
3.2.2 Hazardous working situations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
3.2.3 Safety during maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
3.3 Safety related instructions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
3.3.1 Warning - risk of crushing in the operating mechanism and link system . . . . . . . . . . . . . . . . . . 27
3.3.2 Release the spring charge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
4 Reference information 29
4.1 Oil types . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
4.2 Types of grease . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
4.3 Locking fluid. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
4.4 Tightening torque. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
4.5 Requisite equipment, installation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
4.6 Requisite equipment, maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
4.7 Requisite equipment, overhaul. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
4.8 Operating values . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
5 Delivery 39
5.1 Delivery inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
5.2 Storage prior to assembly. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
5.3 Lifting the circuit-breaker poles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
5.4 Lifting the operating mechanism . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
1HSB429954-10en 2009-03-09 3
6 Installation 47
6.1 Installation in short steps . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
6.2 Foundations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
6.3 Assembly of support on the foundation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
6.4 Assembly of pole beam on the support . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
6.5 Fitting of operating mechanism on pole beam . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
6.6 Assembly of circuit-breaker poles. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
6.7 Electrical connections. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
6.7.1 Connecting the circuit-breaker's operating mechanism . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
6.7.2 Fitting the rails or lines. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70
6.8 Assembly of gas monitoring system . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71
6.9 Pressurizing of circuit-breaker poles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 78
6.9.1 Preparations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 78
6.9.2 Gas filling with SF6-gas . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80
6.9.3 Filling of mixed gas. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
6.10 Inspection prior to commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87
6.10.1 Density check . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87
6.11 Inspection of screw joints. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88
7 Commissioning 89
7.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89
7.2 Pre-commissioning check list . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90
8 Maintenance 93
8.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 93
8.2 The maintenance schedule for operating mechanism and circuit-breaker . . . . . . . . . . . . . . . . . . 94
8.3 The service life of the circuit-breaker . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 96
8.4 The service life of the arcing contacts in the event of short circuit breaking . . . . . . . . . . . . . . . . 97
8.5 Activities after 1-2 years . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98
8.5.1 Ocular inspection and density check . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98
8.5.2 Cleaning and lubrication of circuit-breakers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99
8.6 Activities after 3-6 years or 2,000 Close and Open operations . . . . . . . . . . . . . . . . . . . . . . . . . . . 100
8.6.1 Preventive maintenance of operating mechanism and circuit-breaker. . . . . . . . . . . . . . . . . . . 100
8.6.2 Overhaul of breaking unit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103
8.7 Activities after 15 years or 5,000 Close and Open operations . . . . . . . . . . . . . . . . . . . . . . . . . . . 104
8.7.1 Overhaul of the whole circuit-breaker and operating mechanism . . . . . . . . . . . . . . . . . . . . . . 104
8.7.2 Cleaning, lubrication and rust protection of operating mechanism. . . . . . . . . . . . . . . . . . . . . . 110
8.7.3 Inspection of latch devices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 112
8.7.4 Inspection of drive unit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 114
8.7.5 Check of oil level in damper . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 115
8.7.6 Inspection of heating element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 116
4 2009-03-09 1HSB429954-10en
9 Overhaul 117
9.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 117
9.2 Preparations for overhaul . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 118
9.3 Removing of SF6-gas . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120
9.4 Cleaning and waste management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 122
9.5 Removal of circuit-breaker pole for transport. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 123
9.6 Overhaul of circuit-breaker pole. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126
9.6.1 Dismantling of breaking unit from the post insulator. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126
9.6.2 Removal of post insulator . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 129
9.6.3 Overhaul of mechanism . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 132
9.7 Assembly of circuit-breaker pole . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 135
9.7.1 Treatment of contact surfaces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 135
9.7.2 Treatment of sealing surfaces and seals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 137
9.7.3 Assembly of post insulator . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 138
9.7.4 Assembly of breaking unit on the post insulator . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141
9.7.5 Filling the gas before transport . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 144
9.8 Replacement of breaking unit. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 145
9.8.1 Dismantling of breaking unit for transport . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 145
9.8.2 Assembly of breaking unit on site following overhaul . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 149
9.9 Assembling the circuit-breaker poles and commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 153
10 Repairs 155
10.1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 155
10.2 Operating mechanism . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 156
10.2.1 Removal and assembly of casing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 156
10.2.2 Replacement of coil . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 161
10.2.3 Replacement of tripping latch assembly . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 163
10.2.4 Replacement of closing latch assembly . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 166
10.2.5 Replacement of tripping and closing latch device assembly . . . . . . . . . . . . . . . . . . . . . . . . . . 172
10.2.6 Replacement of limit stop roller on the closing lever . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 180
10.2.7 Replacement of damper . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 182
10.2.8 Replacement of auxiliary contact . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 184
10.2.9 Replacement of gear housing and motor in the drive unit . . . . . . . . . . . . . . . . . . . . . . . . . . . . 187
10.2.10Replacement of limit switch . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 191
10.2.11Replacement of eye bolt and bellows . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 194
1HSB429954-10en 2009-03-09 5
12 Spares 203
12.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 203
12.2 Circuit-breaker pole. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 205
12.2.1 Circuit-breaker pole . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 205
12.2.2 Breaking unit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 206
12.2.3 Post insulator and insulating pull-rod . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 207
12.2.4 Mechanism . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 208
12.2.5 Accessories . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 209
12.3 Operating mechanism . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211
12.3.1 Damper. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211
12.3.2 Latch device . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 212
12.3.3 Heating element . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 213
12.3.4 Open and closing latch device assembly . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 214
12.3.5 Eye bolt and bellows for transmission rod . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 215
12.3.6 Drive unit with motor and gear housing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 216
12.3.7 Limit switch. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 217
6 2009-03-09 1HSB429954-10en
1 Product description, circuit-breaker
1.1 Description
Structure
1HSB429954-10en 2009-03-09 7
1 Product description, circuit-breaker
1.1 Description
8 2009-03-09 1HSB429954-10en
1 Product description, circuit-breaker
1.2 Breaking principle
Auto-Puffer principle
The breaking unit functions in accordance with the Auto-PufferTM principle with a
puffer cylinder that is divided into two chambers: an Auto-PufferTM section and a
compression section.
When normal rating currents are interrupted, the SF6 gas is compressed in the
compression section to an overpressure. When the arcing contacts separate, the gas
in the compression section flows out and extinguishes the arc at a current zero
passage.
When short-circuit currents are interrupted, the requisite extinguishing pressure is
built up in the Auto-PufferTM section by heat from the arc. The pressure increase is
achieved with energy from the arc and no extra energy is required from the operating
mechanism.
On closing, the puffer cylinder slides upwards, the contacts engage and the puffer
cylinder is refilled with gas.
1 Puffer cylinder
2 Auto-PufferΤΜ chamber
3 Compression section
1HSB429954-10en 2009-03-09 9
1 Product description, circuit-breaker
1.3 Functional overview and standards
Standards, IEC
The circuit-breakers comply with the requirements in the IEC 62271-100 standard
and are restrike free when breaking capacitive loads.
10 2009-03-09 1HSB429954-10en
1 Product description, circuit-breaker
1.4 Gas system and density monitor
Density monitor
The circuit-breaker is fitted with a density monitor for checking the density of the
gas. All density monitors are fitted with a set of contacts that are to be connected to
give an alarm in the event of abnormal leakage. There are two levels for the alarm,
these are:
• Level 1, alarm
• Level 2, blocking
NOTE!
A new or overhauled circuit-breaker must be checked for leakage by reading the
density monitor after about one month. Following the initial check, it should be
checked at 1-2 year intervals in conjunction with routine visual inspections.
1HSB429954-10en 2009-03-09 11
1 Product description, circuit-breaker
1.5 Description, SF6-gas
Gas stability
Sulfur hexafluoride SF6is a synthetic gas, which is colorless, odorless and non-
combustible.
The gas is chemically very stable and at room temperature, it does not react with any
other substance.
The stability of the gas is the basis for it being used in electrical devices as it provides
very high electrical insulation and can effectively extinguish arcs. These SF6
properties enable the construction of devices and equipment with small footprints,
using little material, that are safe and have long service lives. In an electrical context,
the SF6 gas is only used in closed and sealed systems, e.g. as insulation gas in
substations and insulation and extinguishing medium in circuit-breakers for high and
medium voltage.
1 Air
2 Oil
3 Vacuum
4 SF6, 0.1 MPa
5 SF6, 0.5 MPa
12 2009-03-09 1HSB429954-10en
2 Product description, Operating Mechanism
2.1 Structure and function
General
The motor-charged spring operating mechanism is designed for operating the circuit-
breakers.
Structure
Functional description
The closing spring is charged by a motor, via a worm gear, which generates power
and thereby the possibility of a closing operation. A closing latch device keeps the
closing spring charged and ready to close the circuit-breaker. In the event of closing,
power is transferred to charge and lock the trip spring, and the closing spring is
charged again by the motor. A tripping latch then keeps the trip spring charged and
thereby also keeps the circuit-breaker in closed position. When the signal for opening
occurs, the trip spring discharges and the circuit-breaker opens.
1HSB429954-10en 2009-03-09 13
2 Product description, Operating Mechanism
2.1 Structure and function
14 2009-03-09 1HSB429954-10en
2 Product description, Operating Mechanism
2.2 Closing and opening operations and charging of the closing spring
2.2 Closing and opening operations and charging of the closing spring
When the signal indicates that the circuit breaker will close, the closing latch is
released from the main shaft and the closing spring trips. This means that the cam
disc rotates via the closing lever. The switching shaft is put in motion and the circuit-
breaker closes, at the same time as the trip spring in turn is charged and locked. The
motor then charges the closing spring following each closing operation, via the main
shaft and worm gear. When the spring is then charged, the circuit is broken by the
limit switch.
When the signal indicates that the circuit breaker will open, the tripping latch device
releases from the switching shaft and the trip spring trips, and thereby opens the
circuit-breaker.
Affected parts
1 Main shaft
2 Closing spring
3 Cam disc
4 Closing lever
5 Switching shaft
6 Trip spring
7 Motor
1HSB429954-10en 2009-03-09 15
2 Product description, Operating Mechanism
2.3.1 Drive unit
Motor
1 Motor
2 Gear housing
16 2009-03-09 1HSB429954-10en
2 Product description, Operating Mechanism
2.3.2 Latch device with coils
General
The operating mechanism has one closing coil and two trip coils as standard, but can
on request be fitted with double closing coils.
Coil voltage:
- 110 V DC or 220 V DC
The standard rated output of the coils is 500 W.
1HSB429954-10en 2009-03-09 17
2 Product description, Operating Mechanism
2.3.3 Damper
2.3.3 Damper
The operating mechanism is fitted with a damper to dampen the final phase of the
opening travel.
18 2009-03-09 1HSB429954-10en
2 Product description, Operating Mechanism
2.3.4 Auxiliary contact
General
1HSB429954-10en 2009-03-09 19
2 Product description, Operating Mechanism
2.3.5 Heating element
General
The operating mechanism is fitted with a heating element that prevents condensation.
The heating element must always be connected.
Technical data
The 70 W heating element is always connected, while the 140 W heating element is
thermostat controlled. Check the resistance where necessary.
Voltage Resistance Power
220 V 691 ohm 70 W
110 V 173 ohm 70 W
220 V 346 ohm 140 W
110 V 86 ohm 140 W
20 2009-03-09 1HSB429954-10en
2 Product description, Operating Mechanism
2.4.1 Preconditions for different operations
Control panel
Remote/Local operation
Open operation
An opening operation for a closed circuit-breaker can be performed when the "Local/
Remote/Disconnected" switch is in the "Local" position, the gas density is greater
than the blocking level and the "Close/Open" control switch is set to "Close".
Closing operation
A closing operation using the "Close/Open" control switch or electric remote impulse
can only be done if:
• The "Local/Remote/Disconnected" switch is in the "Remote" or "Local"
setting.
• The closing spring is charged.
• The circuit-breaker is in open position.
• The gas density is larger than the blocking level.
1HSB429954-10en 2009-03-09 21
2 Product description, Operating Mechanism
2.4.2 Auto-reclosing
2.4.2 Auto-reclosing
Preconditions
22 2009-03-09 1HSB429954-10en
3 Safety
3.1 Introduction
3 Safety
3.1 Introduction
General
1HSB429954-10en 2009-03-09 23
3 Safety
3.2.1 Levels of safety risks
Description
Throughout the manual, various types of safety risks are indicated. These are divided
into five different levels, depending on the degree of danger. The most serious level
on this scale provides a warning about serious personal injury or possible death, or
major damage to a product, if the instructions are not observed. The least serious is
simply a comment on important facts and conditions. The levels are indicated using
symbols; see below.
Descriptions of the symbols that appear in the manual are provided here, along with
their meanings.
Symbols Designation Implication
DANGER! The yellow, filled warning triangle warns that an accident
can occur if the instructions are not complied with, resulting
in serious injury or death and/or major damage to the
product.
It is used, for example, to warn such of dangers as: contact
with high voltage, explosion or fire risk, risk for toxic gases,
risk of crushing, impacts, falls from high places, etc.
WARNING! The red, unfilled warning triangle warns that an accident can
occur if the instructions are not complied with, resulting in
serious injury or death and/or major damage to the product.
It is used, for example, to warn of such dangers as: contact
with high voltage, explosion or fire risk, risk for toxic gases,
risk of crushing, impacts, falls from high places, etc.
ELECTRIC The symbol for electric shocks warns of electrical dangers
SHOCK! that could cause serious injury or death.
24 2009-03-09 1HSB429954-10en
3 Safety
3.2.2 Hazardous working situations
General
For all work on high-voltage circuit-breakers, the risks below must be observed and
corresponding measures taken.
Risk Action
Working close to high voltage. Disconnect and earth around the workplace. If work
must be carried out next to live plant components, the
safety distance must satisfy the applicable safety
regulations.
Working on ladders and platforms Work must be executed in accordance with applicable
safety regulations. Avoid climbing ladders and
platforms in poor weather conditions.
Working with low voltage Disconnect the control power and as necessary, the
Both AC and DC can be connected to heater power.
the operating mechanism.
Working next to pressurized Working close to the circuit-breaker's insulators
insulators. where there could be a risk of damage to the insulator
Normal working pressure is up to 0.8 may not be carried out before the gas has been
MPa. Damage to the porcelain evacuated to a maximum pressure of 0.125 MPa
insulator can cause it to splinter. (abs).
1HSB429954-10en 2009-03-09 25
3 Safety
3.2.3 Safety during maintenance
General
For all work on high-voltage circuit-breakers, the risks below must be observed and
the corresponding measures taken.
The standard operating cycle is O - 0.3 s - CO - 3 min - CO. When testing circuit-
breakers and relay systems that include more than three closing operations, the time
between the operations should not be less than 1 minute.
Safety instructions
WARNING!
Damage to the insulator porcelain may cause it to explode with the subsequent risk
of splintering. When damage has been identified, the insulator must be replaced.
WARNING!
Mechanical damage to the insulator may cause it to explode with the subsequent risk
of splintering. Work on the circuit-breaker where there is a risk of mechanical
damage to the insulators is to be executed at reduced gas pressure, 0.125 MPa (abs).
WARNING!
Do not operate the operating mechanism without a load. The operating
mechanism may not be switched on, operated, or have a charged tripp and/or closing
spring until all circuit-breaker installation and adjustment tasks have been
completed.
26 2009-03-09 1HSB429954-10en
3 Safety
3.3.1 Warning - risk of crushing in the operating mechanism and link system
3.3.1 Warning - risk of crushing in the operating mechanism and link system
Description
Energy is stored in both the closing and trip springs. The operating mechanism may
be tripped by heavy vibrations or by unintentional contact of the mechanical
interlocking components, which could result in crushing injury.
Action
Action Note
1. Put the circuit-breaker in open
position.
2. Release the spring charge by During transport and when the operating
disconnecting the motor power and mechanism is under assembly or stored, the
carrying out a closing and opening closing and trip springs must be discharged for
operation. safety reasons.
3. Disconnect and earth the high-voltage
side.
1HSB429954-10en 2009-03-09 27
3 Safety
3.3.2 Release the spring charge
General
1 Motor protection
2 Switch, Local/Remote/Disconnected
3 Spring charge indicator
4 Control switch, Close/Open
The item numbers in the text correspond to the item numbers in the illustration.
Action Note
1. Cut the motor current by switching off the motor protection (1).
2. Set the Local/Remote/Disconnected switch (2) on the control panel to the
Local position.
3. Execute an Open-Close-Open operation.
4. Check that the spring is discharged. The spring charge indicator (3)
shows discharged spring.
5. The circuit-breaker is in Open position.
6. Following completion of work the motor protection (1)must be reset.
28 2009-03-09 1HSB429954-10en
4 Reference information
4.1 Oil types
4 Reference information
4.1 Oil types
General
This section deals with the applications, type names and suppliers of oil.
CAUTION!
All lubricant and oil spills must be covered using absorbent material and be handled
as chemical waste in accordance with locally applicable regulations.
CAUTION!
When handling oil and lubricants, long-sleeved overalls protective gloves and
protective goggles must be worn at all times.
Oil A
1HSB429954-10en 2009-03-09 29
4 Reference information
4.1 Oil types
Oil D
NOTE!
Dampers with the letter “S” punched on the cover are to be filled with oil “S”.
Property Value
Viscosity 20 °C 6.0 cSt
Oil S
Silicone oil designed for dampers in heavy operating mechanisms, like BLG and
BLK models.
Supplier Designation Spare part number
ABB 1173 7011-106 1HSB875318-C
SHELL DC 200 Fluid 200 CS -
30 2009-03-09 1HSB429954-10en
4 Reference information
4.2 Types of grease
General
This section deals with the applications, type names and suppliers of grease.
Grease G
Low temperature grease for all types of bearings, gear drives and worm gears as well
as valves in air-blast circuit-breakers. Also used for greasing O-rings and as crevice
corrosion protection for circuit-breakers, and for moving contacts (opening contacts)
in disconnectors.
Supplier Designation Spare part number
ABB 1171 4014-407 5316 381-A
GULF 718EP Synthetic grease -
MOBIL Mobil grease 28 -
SHELL Aero Shell Grease 223 -
Grease K
Molycote grease for lubricating pins in link gears and in seismic dampers.
Supplier Designation Spare part number
ABB 1263 0011-102 5316 381-M
Dow Corning G-rapid plus -
Grease L
Grease M
Low temperature grease for long-term and permanent lubrication of worm gears,
gear drives and other machine elements. Counteracts wear and corrosion.
Also reduces electrical resistance at the lubrication point, therefore making it suitable
for electrical connections and for lubrication of contacts in disconnectors and
earthing switches.
Supplier Designation Spare part number
ABB 1171 4016-612 5316 381-J
Klüber Isoflex Topas NB 52 -
1HSB429954-10en 2009-03-09 31
4 Reference information
4.2 Types of grease
Grease N
For lubrication of moving contacts and puffer cylinders in SF6 circuit-breakers. The
grease is to be rubbed on in a very thin layer on the sliding surfaces of the contacts.
Supplier Designation Spare part number
ABB 1171 4016-607 5316 381-L
Montefluos S.p.A Fomblin OT20 -
Grease P
Vaseline for treatment of contact surfaces in fixed joints internally in the breaking
unit.
Supplier Designation Spare part number
ABB 1171 5011-102 5316 381-N
SHELL Shell Vaseline 8401 -
Grease "S"
Grease SV
32 2009-03-09 1HSB429954-10en
4 Reference information
4.3 Locking fluid
General
This section deals with the applications, names and suppliers of locking fluid.
The surfaces must be free from oil, grease, wax, paint and anti-rust agent.
Locking fluid B
Medium strong locking fluid used for locking threads and for interlocking screw and
nut joints. Removable.
Supplier Designation Spare part number
ABB 1269 0014-429 -
LOCTITE Ltd. Loctite 243 -
Locking fluid C
Strong locking fluid for locking and interlocking of bolts. Difficult to remove.
Supplier Designation Spare part number
ABB 1269 0014-408 -
LOCTITE Ltd. Loctite 270 -
Locking fluid D
A thin fluid that penetrates quickly. Used for locking brackets following assembly or
adjustment. The fluid can also impregnate porous welded joints, castings and
sintered material. The interlocking has a high resistance against pressure, solvents
and chemicals.
Fluid can only be used on clean and dry surfaces. Oily goods must be washed with
industrial spirit.
Spray the fluid on the surface in question or apply with a brush.
Supplier Designation Spare part number
ABB 1269 0014-409 -
LOCTITE Ltd. Loctite 290 -
Locking fluid F
Extra strong locking fluid for cylindrical attachment. Recommended for joints with
sliding or forced fit. Must be heated in order to be removed (temperature resistance
175º C).
Supplier Designation Spare part number
ABB 1234 0011-126 -
LOCTITE Ltd. Loctite 648 -
1HSB429954-10en 2009-03-09 33
4 Reference information
4.4 Tightening torque
General
34 2009-03-09 1HSB429954-10en
4 Reference information
4.5 Requisite equipment, installation
General
This section specifies the equipment needed for installing the circuit-breaker.
Requisite tools
Lubricant
Other documentation
1HSB429954-10en 2009-03-09 35
4 Reference information
4.6 Requisite equipment, maintenance
General
This section specifies the equipment needed for maintenance of the operating
mechanism.
Tool
Cleaning equipment
Lubricant
36 2009-03-09 1HSB429954-10en
4 Reference information
4.7 Requisite equipment, overhaul
General
This section specifies the equipment needed for overhauling the circuit-breaker.
Tool
Lubricant
Spares
1HSB429954-10en 2009-03-09 37
4 Reference information
4.8 Operating values
Times
Events Times
Close time coil I (and II) Max. 75 ms
Open time coil I Max. 45 ms
Open time coil II Max. 45 ms
1
Close-Open time Max. 65 ms
1. Close-Open time refers to the time the arcing contacts are closed during a
closing operation when the trip impulse is connected at the same time via the
auxiliary contact.
Events Values
Charging time for motor Max. 15 s
Control voltage tripping coil I V (according to rating plate)
Control voltage tripping coil II V (according to rating plate)
Control voltage closing coil I (and II) V (according to rating plate)
Resistance
Main circuit resistance per pole:
Pole Resistance
LTB 72.5D1/B <40µΩ
LTB 145D1/B <40µΩ
Stroke
38 2009-03-09 1HSB429954-10en
5 Delivery
5.1 Delivery inspection
5 Delivery
5.1 Delivery inspection
General
The material is packed in boxes and on pallets. The boxes are marked with package
numbers and gross weights. Other information is printed on a plate/label attached to
two sides of the boxes.
All packaging material is recyclable.
Damaged goods
Check on arrival that the delivery matches the order and delivery documents and that
no transportation damage has occurred. If damage is found or suspected, the boxes
must be opened and the damage photographed and documented.
In the event of missing material or if transportation damage has occurred, this must
be immediately reported to ABB AB.
1HSB429954-10en 2009-03-09 39
5 Delivery
5.2 Storage prior to assembly
Circuit-breaker
The circuit-breakers must be stored in their original packaging where they are
protected from damage. The units must not stand in water and must primarily be kept
in a horizontal position indoors and above ground level, so as to avoid cracking or
water damage.
The circuit-breakers may also be stored outdoors, but then in an area protected from
rain on a dry, well-drained surface. If a tarpaulin is used, it must not be wrapped too
tightly; air circulation to the zinc-plated surfaces must not be hindered. Any
condensation must be easy to drain off.
The lowest permitted temperature limit for storage is -30ºC.
Operating mechanism
Storage conditions
All components must be held in an easy to access store and in an environment that
meets the following.
The storage area must have:
a roof
solid ground
air humidity below 50%
a temperature of 20°C (±10°C).
Dust, smoke, abrasive or flammable gas, steam or salt may not be present in close
proximity to the circuit-breaker. If this is the case, the equipment must be cleaned
prior to assembly.
40 2009-03-09 1HSB429954-10en
5 Delivery
5.2 Storage prior to assembly
Packaging boxes of different sizes must never be stacked on top of each other (the
pressure could damage the lids of the lower boxes). If different sized boxes need
stacking, a frame must be used between the boxes to distribute the pressure.
WARNING!
Never stack more than three boxes on top of each other. Due to instability and the risk
of collapse the boxes need to be secured.
Spares
1HSB429954-10en 2009-03-09 41
5 Delivery
5.3 Lifting the circuit-breaker poles
General
Safety
WARNING!
In order that the correct lifting tackle is used it is extremely important to check the
weight of the circuit-breaker pole. The weight of the circuit-breaker pole is specified
on the dimension print applicable to the order.
CAUTION!
Please note the positioning of the lifting sling! With respect to polymeric insulators,
the lifting sling is to be placed as close as possible to the flange and not on the rubber
surface.
NOTE!
The circuit-breaker pole/poles are to be stored in transport boxes until immediately
before assembly.
Requisite equipment
Lifting illustration
1 Screw joint
42 2009-03-09 1HSB429954-10en
5 Delivery
5.3 Lifting the circuit-breaker poles
Lifting instructions
NOTE!
If it does not hiss, the circuit-breaker pole has a
leak that must be fixed before assembly.
2.
DANGER!
The lifting tackle used to lift the circuit-
breaker pole must be dimensioned for
the weight.
• The polymer circuit-breaker
pole weighs about 130 kg.
• The porcelain circuit-breaker
pole weighs about 300 kg.
See dimensional drawing for exact
weights.
3. Place a lifting sling around the top of See Lifting illustration on page 42.
the circuit-breaker pole as shown in
the previous figure.
CAUTION!
Please note the positioning of the lifting sling!
With respect to polymeric insulators, the lifting
sling is to be placed as close as possible to the
flange and not on the rubber surface.
1HSB429954-10en 2009-03-09 43
5 Delivery
5.3 Lifting the circuit-breaker poles
Action Note/Illustration
4. Check that the bolts (1), have the See Lifting illustration on page 42.
correct tightening torque.
Torque!
79 Nm.
5. Lift the circuit-breaker pole from its
horizontal position in the transport
packaging.
Start with pole B1.
44 2009-03-09 1HSB429954-10en
5 Delivery
5.4 Lifting the operating mechanism
Requisite equipment
Lifting illustration
Lifting instructions
NOTE!
The lifting slings must not be placed around the cabinet when lifting.
3.
DANGER!
The operating mechanism weighs 150 kg! Use lifting tackle that is
dimensioned for the weight.
4. Lifting the operating mechanism.
1HSB429954-10en 2009-03-09 45
5 Delivery
5.4 Lifting the operating mechanism
46 2009-03-09 1HSB429954-10en
6 Installation
6.1 Installation in short steps
6 Installation
6.1 Installation in short steps
General
This section provides a summary of the installation procedure, that is the steps
required for installing the complete circuit-breaker with support and operating
mechanism.
Illustration
1 Circuit-breaker pole
2 Pole beam
3 Support
4 Operating mechanism
1HSB429954-10en 2009-03-09 47
6 Installation
6.1 Installation in short steps
The instructions below give a brief summary of the installation. Follow the link for
each step for more detailed information on how the actions in question are executed.
Action Read more in section:
1. Check the delivery. Delivery inspection on page 39.
2. Check that all the necessary tools are Requisite equipment, installation on page 35.
on hand.
3. Check that the foundations meet all the Foundations on page 49.
requirements for the installation.
4. Fit the support legs on the foundations. Assembly of support on the foundation on page
50.
5. Fit the pole beam to the support legs. Assembly of pole beam on the support on page
52.
6. Fit the operating mechanism on the Fitting of operating mechanism on pole beam
pole beam. on page 54.
7. Fit all circuit-breaker poles. Assembly of circuit-breaker poles. on page 56.
8. Fit the gas monitoring system. Assembly of gas monitoring system on page
71.
9. Install all electrical connections: Electrical connections on page 68.
• Connect the operating
mechanism.
• Fit the rails or lines.
• Charge the closing spring.
10. Pressurize the circuit-breaker poles. Pressurizing of circuit-breaker poles on page
78.
11. Prepare for commissioning.
• Perform a density check. Density check on page 87.
• Check the screw joints. Inspection of screw joints on page 88.
48 2009-03-09 1HSB429954-10en
6 Installation
6.2 Foundations
6.2 Foundations
General
The foundation for the circuit-breaker must be flat and horizontal. The figure below
shows the permitted tolerances in mm for the position of the foundation bolts and for
the phase spacing.
Any deviations are to be corrected using spacers, see section Assembly of support on
the foundation on page 50. The nominal dimensions, as well as the dimensions for
the foundation bolts and nuts are specified in the dimension print that is applicable to
the order.
Tolerances
1HSB429954-10en 2009-03-09 49
6 Installation
6.3 Assembly of support on the foundation
General
Structure
NOTE!
Foundation bolt, nuts and spacers are not included in the delivery.
Requisite equipment
50 2009-03-09 1HSB429954-10en
6 Installation
6.3 Assembly of support on the foundation
Assembly
The following instructions describe the assembly of the support on the foundation.
The item numbers in brackets refer to the previous figure.
Action Note
1.
DANGER!
The support legs are heavy! Use lifting
tackle that is dimensioned for the
weight. See dimension print for
applicable order.
2. Check that the supports are vertical.
3. Adjust the supports to the same level
using the nuts (2).
4. Fill the space between the lower nut
and the foundation using spacers.
NOTE!
The space should be as small as
possible.
5. Tighten the lower nut (2) to the spacers
(4).
Torque!
300-350 Nm
6.
NOTE!
Make the final tightening of the
supports after the adjustment and
assembly of the pole beam.
1HSB429954-10en 2009-03-09 51
6 Installation
6.4 Assembly of pole beam on the support
General
Structure
The figure below shows the pole beam's retaining bolts and nuts.
1 Pole beam
2 Support
3 Bolt M20x60 (8 pcs), Washer (16 pcs), Nut M20 (8 pcs)
Requisite equipment
52 2009-03-09 1HSB429954-10en
6 Installation
6.4 Assembly of pole beam on the support
Assembly instructions
The following instructions describe the assembly of the pole beam on the support.
Action Note/Illustration
1. Lift the pole beam (1)
2. Carefully lower the pole beam (1) onto
the support legs (2).
Torque!
300 Nm.
4. Make the final tightening of the support
in the foundation.
Torque!
300-350 Nm.
1HSB429954-10en 2009-03-09 53
6 Installation
6.5 Fitting of operating mechanism on pole beam
General
The operating mechanism is already adjusted on delivery, and is supplied with the
closing spring correctly set.
Structure
1 Operating mechanism
2 Lifting brackets (4 pcs)
3 Pole beam
4 Washer 17x30x3 (4 pcs), Spring washer 17x27.4x3.5 (4 pcs), Nut M16 (4 pcs)
54 2009-03-09 1HSB429954-10en
6 Installation
6.5 Fitting of operating mechanism on pole beam
Safety
WARNING!
The operating mechanism must not be switched on, operated or have a charged
closing spring before all assembly and adjustments have been completed to the
circuit-breaker.
CAUTION!
The operating mechanism may only be lifted by the assigned lifting brackets
Requisite equipment
Torque!
190 Nm.
1HSB429954-10en 2009-03-09 55
6 Installation
6.6 Assembly of circuit-breaker poles.
General
This section describes the assembly of the circuit-breaker poles and torsion tubes.
The circuit-breaker poles are fitted in the order B1, A1 and finally C1, see the
illustration below.
Structure
The figure below shows the order of assembly of the circuit-breaker poles.
1 Circuit-breaker pole B1
2 Circuit-breaker pole A1
3 Circuit-breaker pole C1
56 2009-03-09 1HSB429954-10en
6 Installation
6.6 Assembly of circuit-breaker poles.
Requisite equipment
Assembly instructions
The following instructions describe the assembly of the circuit-breaker poles on the
pole beam and the fitting of the torsion tubes. Lifting the circuit-breaker pole is
described in Lifting the circuit-breaker poles section on page 48.
Action Note/Illustration
1. Check that the circuit-breaker pole is
tight prior to fitting to the support.
• Remove the sealing cap (3).
• Press the non return valve cone
(2) inwards using a screwdriver.
1. Mark
2. Non return valve
3. Sealing cap
NOTE!
A hissing noise should then be clearly heard
from the pole. If it does not hiss, the circuit-
breaker pole has a leak that must be fixed
before assembly.
2. Refit the sealing cap.
1HSB429954-10en 2009-03-09 57
6 Installation
6.6 Assembly of circuit-breaker poles.
Action Note/Illustration
3. Lift the circuit-breaker pole B1 in place
and fit it on the pole beam.
1. Circuit-breaker pole
2. Bolt M16x60 (4 pcs), washer 17x30x3
(8 pcs), nut M16 (4 pcs).
3. Pole beam
NOTE!
Check that the outer lever is positioned on the
same side as the transmission rod.
NOTE!
Lifting the circuit-breaker pole is described in
Lifting the circuit-breaker poles on page 42.
58 2009-03-09 1HSB429954-10en
6 Installation
6.6 Assembly of circuit-breaker poles.
Action Note/Illustration
4. Fit the bolts, washers and nuts (1) and
tighten finger tight.
NOTE!
Final tightening is executed when all the circuit-
breaker poles have been fitted.
5. Remove the transport plate (1) from
the operating lever (2).
1. Transport plate
2. Operating lever
NOTE!
Make sure the outer lever is fitted as per the
illustration.
1HSB429954-10en 2009-03-09 59
6 Installation
6.6 Assembly of circuit-breaker poles.
Action Note/Illustration
6. Lubricate the shaft end (2) and spline
in the torsion tube using Grease "G".
Fit the short torsion tube (1) between
B1 and A1 on the free shaft end (2).
NOTE!
A blind tooth is to be fitted into the spline. Never
use force when assembling.
60 2009-03-09 1HSB429954-10en
6 Installation
6.6 Assembly of circuit-breaker poles.
Action Note/Illustration
7. Fit the circuit-breaker pole A1 on the
pole beam.
• Lower the circuit-breaker pole
to the correct height. The
mechanism housing flange
should be slightly touching the
top of the pole beam.
• Lubricate the shaft end and
spline in the torsion tube using
Grease "G".
• Move circuit-breaker pole A1
towards B1 and guide the
operating shaft (2) into the
torsion tube (1).
Use a torque tool if the position of the
operating shaft needs adjusting. Fit the
free shaft end on circuit-breaker pole
A1.
NOTE!
A blind tooth is to be fitted into the spline. Never
use force when assembling.
1HSB429954-10en 2009-03-09 61
6 Installation
6.6 Assembly of circuit-breaker poles.
Action Note/Illustration
8. Fit the bolts, washers and nuts (1) and
tighten finger tight.
NOTE!
Final tightening is executed when all the circuit-
breaker poles have been fitted.
62 2009-03-09 1HSB429954-10en
6 Installation
6.6 Assembly of circuit-breaker poles.
Action Note/Illustration
9. Fit the remaining circuit-breaker pole
C1.
• Lubricate the shaft end and
spline in the torsion tube using
Grease "G", applies to both B1
and C1.
• Fit the torsion tube (1) on the
free shaft end on circuit-
breaker pole B1.
• Lower the circuit-breaker pole
to the correct height. The
mechanism housing flange
should be slightly touching the
top of the pole beam.
• Move the circuit-breaker
towards the circuit-breaker pole
already fitted and guide the
operating shaft (2) into the
torsion tube (1).
Use a torque tool if the position of the
operating shaft needs adjusting. Fit the
free shaft end on circuit-breaker pole
C1.
NOTE!
A blind tooth is to be fitted into the spline. Never
use force when assembling.
1HSB429954-10en 2009-03-09 63
6 Installation
6.6 Assembly of circuit-breaker poles.
Action Note/Illustration
10. Fit the bolts, washers and nuts (1) and
tighten finger tight.
NOTE!
Final tightening is executed when all the circuit-
breaker poles have been fitted.
11. Fix the poles by tightening all bolts (1)
between the poles and pole beam.
Torque!
190Nm.
64 2009-03-09 1HSB429954-10en
6 Installation
6.6 Assembly of circuit-breaker poles.
Action Note/Illustration
12. Put the circuit-breaker in open
position.
• Fit the torque tool on the circuit-
breaker's free shaft end (1) to
enable movement of the circuit-
breaker.
• Turn the shaft to ensure that the
hole in the outer lever (2) and
the hole in the mechanism
housing (3) are aligned. Verify
with the control pin (4).
• Remove the torque tool.
2. Outer lever
3. Control hole
4. Control pin
13. Check that the hole on the
transmission rod's eye bolt is aligned
with the hole in the outer lever when
the circuit-breaker is open.
If this is the case, continue to point 15.
1HSB429954-10en 2009-03-09 65
6 Installation
6.6 Assembly of circuit-breaker poles.
Action Note/Illustration
14. • Unscrew the lock nuts (1).
• Adjust the length of the
transmission rod by turning the
rod (2) to ensure that the hole
on the transmission rod and the
outer lever are aligned.
NOTE!
This action is only taken if the length of
the transmission rod needs adjusting.
1. Lock nuts
2. Adjusting rod
15. Fit the pin and lock washer (2)
between the eye bolt on the operating
mechanism's transmission rod and the
outer lever on circuit-breaker pole B1.
• Lubricate the pin (2) using
Grease "M".
1. Outer lever
2. Pin D=17, lock washer SL 12.
66 2009-03-09 1HSB429954-10en
6 Installation
6.6 Assembly of circuit-breaker poles.
Action Note/Illustration
16. Tighten the lock nuts on the
transmission rod.
Torque!
M20: 140 Nm.
M16: 79 Nm.
NOTE!
This action is only taken if the length of
the transmission rod is adjusted.
17. Verify with a control pin that the hole in
the outer lever and the hole in the
mechanism housing are aligned.
1HSB429954-10en 2009-03-09 67
6 Installation
6.7.1 Connecting the circuit-breaker's operating mechanism
General
Safety
WARNING!
Incorrectly connected motor cables may cause personal injury and serious
mechanical damage.
Connection
Action Note/Illustration
1. Run the cables for the operating and
signal lines through the cable inlets (1)
at the bottom of the cabinet.
1. Cable inlets
NOTE!
The cables must be run to ensure they do not
prevent manual charging of the closing spring
with a hand crank.
2. Fit the flange with an appropriate seal
for the cable in question.
68 2009-03-09 1HSB429954-10en
6 Installation
6.7.1 Connecting the circuit-breaker's operating mechanism
Action Note/Illustration
3. Connect the cables to the coupling
terminals as per the applicable
connection diagram.
NOTE!
The blocks are of the plug-in type and available
in through design with a connection of max 4
mm2 multicore conductor area, and as
disconnectable design with a connection of
max. 6 mm2 multicore conductor area designed
for motor, AC and supply circuits.
4. Connect the earth cable to the earth
terminal (1) on the side of the cabinet.
1. Earthing terminal
1HSB429954-10en 2009-03-09 69
6 Installation
6.7.2 Fitting the rails or lines.
General
Safety
WARNING!
Work may not be performed on pressurized circuit-breakers.
NOTE!
Bimetal washers are positioned so that their aluminum sides face the aluminum
surfaces. The copper sides are turned towards the copper- or silver-plated surfaces.
NOTE!
Contact paste may only be used on fixed joints. It must not be used inside the
breaking units.
Remember!
High voltage lines, which consist of aluminum rails or aluminum attachments for
lines, can be connected directly to the breaking units' adapter plates, which are made
of aluminum, following treatment with contact paste.
However, if copper rails or copper attachments are used for lines, grease must be used
and a bimetal washer fitted to the joint. Bimetal washers can be supplied from ABB
on request.
Connect all supports to the existing grounded net
Requisite equipment
Action Note
1. Clean the contact surfaces of grease or old paste.
2. Polish the surfaces with a cleaning cloth, e.g. Scotch Brite no.
7447 or using an emery cloth.
3. Apply grease to the aluminum and copper surfaces
immediately after polishing.
4. Assemble the joint
5. Wipe off any unnecessary grease.
70 2009-03-09 1HSB429954-10en
6 Installation
6.8 Assembly of gas monitoring system
General
This section describes the assembly of the gas monitoring system. The gas tubes are
fitted to the pole beam on delivery, but are not connected. Connection is described in
this section.
The density monitor can be an indicating or non-indicating model.
NOTE!
If the circuit-breaker is to be filled with mixed gas, the gas monitoring system has to
be fitted after filling with gas!
Structure
1 Density monitor
2 Connection cable
3 Cable ties
4 Roxtec cable seal
1HSB429954-10en 2009-03-09 71
6 Installation
6.8 Assembly of gas monitoring system
Requisite equipment
Assembly
The gas tubes are fitted on delivery, but are not connected.
If the circuit-breaker is filled with mixed gas, the gas tubes are fitted after the gas has
been filled; see section Filling of mixed gas on page 83.
The operating mechanism is delivered with a seal fitted in the hole for the density
monitor's cable seal. This seal is removed when fitting the gas monitoring system.
Action Note
1.
NOTE!
When fitting the gas monitoring
system, the greatest possible
cleanliness must be observed.
2.
NOTE!
Ensure that the gas tubes do not come
into contact with the pole beam. Risk of
galvanic corrosion.
72 2009-03-09 1HSB429954-10en
6 Installation
6.8 Assembly of gas monitoring system
Action Note
3. Connect the gas tubes to the circuit-
breaker poles.
Lubricate the O rings using “G” grease
prior to assembly.
1. Clamp nut
2. Non return valve
3. O-ring
NOTE!
Only thread on the clamp nut (1) to the slot in
the non-return valve (2) ensuring the
connection is tight, but the non-return valve has
not opened.
4. When all circuit-breaker poles are
connected in this way: tighten the
clamp nut (1).
Torque!
10 Nm
1HSB429954-10en 2009-03-09 73
6 Installation
6.8 Assembly of gas monitoring system
Action Note
5. Connect the density monitor (1) to the
gas block.
Lubricate the O rings (3) using grease
"G" prior to assembly.
• 1. Density monitor
• 2. Cabling
• 3. O rings
6. Tighten the density monitor (1) when
the gas has been filled.
7. Remove the seal (1) from the top of the
operating mechanism.
74 2009-03-09 1HSB429954-10en
6 Installation
6.8 Assembly of gas monitoring system
Action Note
8. Fit the Roxtec seal in the hole. Make
sure the rubber seal (1) is in place.
1. Rubber seal
2. Seal
3. Nut
9. Tighten the nut (3) on the bottom. Use Loctite 270
Torque!
10 Nm
10. Guide the density monitor's cable (1)
into the operating mechanism through
the Roxtec seal.
1HSB429954-10en 2009-03-09 75
6 Installation
6.8 Assembly of gas monitoring system
Action Note
11. Adjust the size of the two seal halves
by removing layers of rubber. Place the
halves around the cable (1) and check
that the measurement agrees with the
figure to the right.
1. Cable
12. Thoroughly lubricate the inside of the The Roxtec grease is packed in the bag for the
seal halves using Roxtec grease. seal.
Lubricate the outside sparingly.
13. Fit the seal halves around the cable
and press them into the cable entry.
76 2009-03-09 1HSB429954-10en
6 Installation
6.8 Assembly of gas monitoring system
Action Note
14. Tighten the tensioning screws (1)
crosswise.
NOTE!
Make sure the cable runs straight
through the cable entry when
tightening.
Torque!
1 Nm
15. Use a cable tie to attach the cable to
the component plate inside the
operating mechanism.
16. Connect the cable from the operating
mechanism to the density monitor and
attach the cable in the holes on the
pole beam (1) using cable ties.
1HSB429954-10en 2009-03-09 77
6 Installation
6.9.1 Preparations
6.9.1 Preparations
General
The circuit-breaker poles are delivered vacuum processed and filled with SF6 gas to
a pressure of 0.12- 0.13 MPa abs at 20°C.
Safety
WARNING!
Any transport damage to the porcelain entails risk to safety when filling the gas. To
avoid personal injury when filling, installation personnel must exercise caution,
staying in a protected and safe area away from the circuit-breaker as there is a risk of
splintering. The gas cylinder is placed at the same location as the filling device.
WARNING!
When commissioning, the SF6 gas or mixed gas must be topped off to the pressure
specified on the rating plate. Different gas pressures may occur depending on the
different requirements with respect to the lowest ambient temperature.
Preparations
Action Note
1. Connect the cables to the operating
mechanism's connection blocks for
closing and opening operations.
• The cables are run to the
control room or a place
protected from the circuit-
breaker.
2. Connect the cables to a suitable push
button switch.
3. Set the operating mechanism's "Local/
Remote/Disconnected" switch to
"Remote" position.
4. Close the motor circuit-breaker to
charge the closing spring.
5. Open the terminal blocks to the density
monitor's cables that are connected
and break the circuit to the interlocking
relays.
6. Connect the performance testing
device with variable control voltage
and time measurement.
78 2009-03-09 1HSB429954-10en
6 Installation
6.9.1 Preparations
The illustration below shows all the component parts in the gas filling equipment.
1HSB429954-10en 2009-03-09 79
6 Installation
6.9.2 Gas filling with SF6-gas
General
This section describes how the circuit-breaker is filled with SF6 gas. For instructions
on filling mixed gas, see page Filling of mixed gas on page 83.
Requisite equipment
NOTE!
When reading the pressure gauge, the filling pressure must be corrected depending
on the temperature as per the table below.
Table for filling pressure
80 2009-03-09 1HSB429954-10en
6 Installation
6.9.2 Gas filling with SF6-gas
The instructions below describe filling of SF6 gas. The item numbers in parenthesis
refer to figureGas filling components on page 79.
Action Note
1.
NOTE!
Do not use any sharp tools!
2. Put the gas bottle (3) in a protected
place.
3. Check the filling pressure on the
circuit-breaker's rating plate
4. Fit the regulator (11) to the gas cylinder
(3). Set the correct filling pressure,
temperature compensated, as
specified in table Filling pressure (SF6
gas) on page 80, on the regulator (11).
5. Carefully remove the sealing rings
from the density monitor (1, 2),
lubricate liberally using grease "G" and
refit.
6. Connect a density monitor (1, 2)/ Precision pressure gauges are not included in
precision pressure gauge to the the delivery.
coupling (6) or cross-connection (10).
7. Open the valve (4) or alternatively
valve (9).
• If the pressure gauge is
connected to the coupling link
(6) the valve (9) must be
closed.
• If the pressure gauge is
connected to the cross
connection (10) the valve (4)
must be closed.
8. Connect the coupling link (6) to the
circuit-breaker's gas block.
9. Connect the gas filled hose (8) to the
coupling link (6).
10. Connect the gas filled hose (8) to the
gas bottle (3) via the regulator (11).
WARNING!
Move away from the circuit-breaker to a
protected place and let the gas flow until the
regulator is shut down.
11. Wait until the gas temperature has
reached the circuit-breaker's
temperature level and then read the
pressure on the density monitor (1, 2).
1HSB429954-10en 2009-03-09 81
6 Installation
6.9.2 Gas filling with SF6-gas
Action Note
12. Adjust the pressure where necessary.
NOTE!
When reading the pressure gauge, the filling
pressure must be corrected depending on the
temperature specified in table Filling pressure
(SF6 gas) on page 80.
13. Remove the hose (8) from the coupling
link (6) located on the gas block.
14. Shut off the tap (4).
15. Remove the coupling link from the gas
block.
16. Relieve the pressure at the pressure
gauge by opening valve (4) or valve
(9).
17. Remove the density monitor or the
precision pressure gauge from the
coupling link and fit it to the circuit-
breaker.
18. Shut off the tap to the gas bottle when
all poles have been filled.
19. Disconnect the hose from the gas
bottle and relieve the regulator by
pressing in the non return valve.
20. Relieve the regulator's adjustment
pressure by turning the adjuster tap
ensuring the pressure is correct for the
next circuit-breaker to be fitted.
21. When the density monitor (1 ) or (2)
has been properly fitted; tighten the
clamp nut.
Torque!
10 Nm
22. Switch the circuit-breaker to Close and
Open three times from a protected
location.
23. Connect the cables to the density
monitors.
24. Reset the circuits to the blocking
relays.
25. Perform a density check See section Density check on page 87.
NOTE!
A new or overhauled circuit-breaker should be
checked for density by reading the density
monitor after about 1 month and then as
specified in the maintenance schedule.
82 2009-03-09 1HSB429954-10en
6 Installation
6.9.3 Filling of mixed gas
General
The circuit-breaker is to be filled with mixed gas (SF6 and N2 or CF4 gas) at low
temperatures in order to avoid condensation of the SF6 gas. See the rating plate if this
is to be done or not.
Follow the information on the rating plate for the gas mixture proportions. Example.
For a circuit-breaker with filling pressure 0.70 MPa abs (+20°C), start by filling with
0.52 x 0.7 = 0.36 MPa abs (+20°C)SF6 gas and then N2 or CF4 gas to 0.70 MPa abs
(+20°C).
Remember!
NOTE!
When filling mixed gas, the SF6 gas must always be filled first.
NOTE!
When reading the precision measuring instrument, the filling pressure must be
corrected depending on the temperature as per the table below.
1HSB429954-10en 2009-03-09 83
6 Installation
6.9.3 Filling of mixed gas
Requisite equipment
Gas filling
The instructions below describe how the circuit-breaker is filled with mixed gas.
Note that the poles are filled separately and one at a time. The item numbers in
parenthesis refer to figure Gas filling components on page 79.
Action Note
1.
NOTE!
Do not use any sharp tools!
2. Put the gas bottle (3) in a protected
place.
3. Check the filling pressure on the
circuit-breaker's rating plate
4. Fit the regulator (11) to the gas bottle.
Set the correct filling pressure on the
regulator, temperature compensated,
as specified in table Filling pressure WARNING!
(mixed gas) on page 83. When filling mixed gas, the SF6 gas must
always be filled first.
5. Connect a precision pressure gauge to Precision pressure gauges are not included in
the coupling link (6) or cross the delivery.
connection (10).
6. Open the valve (4) or alternatively
valve (9).
• If the pressure gauge is
connected to the coupling link
(6) the valve (9) must be
closed.
• If the pressure gauge is
connected to the cross
connection (10) the valve (4)
must be closed.
7. Connect the coupling link (6) to one of
the circuit-breaker poles' gas valves
(12).
WARNING!
When filling mixed gas, the poles must be filled
one at a time.
8. Connect the gas filled hose (8) to the
coupling link (6).
84 2009-03-09 1HSB429954-10en
6 Installation
6.9.3 Filling of mixed gas
Action Note
9. Connect the gas filled hose (8) to the
gas bottle (3) via the regulator (11).
WARNING!
Move away from the circuit-breaker to a
protected place and let the gas flow until the
regulator is shut down.
10. Wait until the gas temperature has
reached the circuit-breaker's
temperature level and then read the
pressure on the density monitor.
11. Adjust the pressure where necessary.
NOTE!
When reading the pressure gauge, the filling
pressure must be corrected depending on the
temperature specified in table Filling pressure
(mixed gas) on page 83.
12. Close the valve (4) and remove the
coupling link from the filled pole.
13. Connect the coupling link to the next
pole.
14. Open valve (4) again and repeat the
filling of the other two poles as per
items 9 and 10.
15. Remove the hose (8) from the coupling
link (6) located on the last pole filled.
16. Shut off the tap to the pressure gauge.
17. Remove the coupling link from the
circuit-breaker.
18. Relieve the pressure at the pressure
gauge by opening valve (4) or valve
(9).
19. Remove the pressure gauge from the
coupling link.
20. Shut off the tap to the gas bottle.
21. Disconnect the hose from the gas
bottle and relieve the regulator by
pressing in the non return valve.
22. Relieve the regulator's adjustment
pressure by turning the adjuster tap
ensuring the pressure is correct for the
next circuit-breaker to be fitted.
23. Install the gas monitoring system when See section Assembly of gas monitoring
all poles are filled with gas. system on page 71.
NOTE!
The circuit-breaker must not be operated until
the gas monitoring system has been installed!
1HSB429954-10en 2009-03-09 85
6 Installation
6.9.3 Filling of mixed gas
Action Note
24. When the density monitor (1 ) or (2)
has been properly fitted; tighten the
clamp nut.
Torque!
Tightening torque 10 Nm
25. Switch the circuit-breaker to close and
open three times from a protected
place.
26. Connect the cables to the density
monitors.
27. Reset the circuits to the blocking
relays.
28. Perform a density check See Density check on page 87.
NOTE!
A new or overhauled circuit-breaker should be
checked for density by reading the density
monitor after about 1 month and then as
specified in the maintenance schedule.
86 2009-03-09 1HSB429954-10en
6 Installation
6.10.1 Density check
General
This section describes how you make a density check with a leak detector around the
gas block and the gas tube connections.
Requisite equipment
Instructions
Action Note
1. Apply leak spray around the
connections.
2. If the connections are not tight:
• disconnect the connections
• check the O rings and contact
surfaces
• replace the seals where
necessary.
3. Perform a new tightness check.
1HSB429954-10en 2009-03-09 87
6 Installation
6.11 Inspection of screw joints
General
Inspection
• Use the control pin to check that the operating lever's control hole is aligned
with the pre-drilled hole in the mechanism housing. The control pin is placed
inside the operating mechanism's cabinet. The part number is given in section
Requisite equipment, installation on page 35.
• Check that all screw joints are tightened at the right torque, see section
Tightening torque on page 34.
88 2009-03-09 1HSB429954-10en
7 Commissioning
7.1 Introduction
7 Commissioning
7.1 Introduction
General
Before the circuit-breaker is put into service, all inspections as detailed in Pre-
commissioning check list on page 90 for installation and commissioning must have
been carried out and the operating values for the installation completed.
Reset all connection circuits as per the applicable circuit diagram and check-tighten
the affected connection blocks. Put the help tools in their holders in the operating
cabinet.
1HSB429954-10en 2009-03-09 89
7 Commissioning
7.2 Pre-commissioning check list
General
Identification
Date:
Installation:
Action Note
1. Check that the circuit-breaker and the
operating mechanism have been
assembled as per the installation
instructions.
2. Check-tighten all screw joints with the See Tightening torque on page 34.
correct tightening torque.
Action Note
1. Make a visual inspection to check if the
damper has leaked oil into the
operating mechanism.
2. Check tighten the bolts in the
connection blocks that have been
affected by the assembly.
3. Check the functionality of the heating
element.
4. Check that the thermostat, if any, is set Other settings may occur in accordance with
to 10° C. customer specifications.
90 2009-03-09 1HSB429954-10en
7 Commissioning
7.2 Pre-commissioning check list
Action Note
1. Check the gas filling and test run as See Gas filling with SF6-gas on page 80 or
per instructions Filling of mixed gas on page 83.
Check the operating values for the circuit-breaker against data applicable to the
circuit-breaker in Operating values on page 38 and note the measured values in the
table below.
(2)
Filling pressure is as specified on the rating plate.
CAUTION!
The circuit-breaker may not be operated from Open to Close without an intermediate
delay of 300 ms!
Signing
1HSB429954-10en 2009-03-09 91
7 Commissioning
7.2 Pre-commissioning check list
92 2009-03-09 1HSB429954-10en
8 Maintenance
8.1 Introduction
8 Maintenance
8.1 Introduction
Chapter structure
This chapter contains information for the necessary maintenance activities. The
chapter is structured as follows:
• The maintenance schedule that contains intervals and competence levels for
the various maintenance activities.
• Information on the circuit-breaker's service life.
• Activities at 1-2 year intervals.
• Activities at 3-6 years or 2,000 Close and Open operation intervals.
• Activities at 15 years or 5,000 Close and Open operation intervals.
There are also activities to be carried out after 30 years or 10,000 Close and Open
operations.
These are detailed in chapter Maintenance on page 93.
NOTE!
In corrosive or polluted air and in climates with high humidity, it may be necessary
to half the inspection period.
The specified inspection intervals are to be regarded as recommended guidelines that
can either be extended or shortened depending on local conditions.
1HSB429954-10en 2009-03-09 93
8 Maintenance
8.2 The maintenance schedule for operating mechanism and circuit-breaker
The activities in each interval are to be planned separately, i.e. they do not appear in
the instructions for later intervals. For example, if activities executed at 1-2 year
intervals are to be conducted regularly and it is up to the customer to plan the time so
that, by way of suggestion, activity no 2 coincides with the activities to be carried out
at 3-6 year intervals, etc.
Maintenance schedule
Compe-
Interval tence Maintenance activity Instructions
level
1-2 years A Visual inspection Ocular inspection and density
check on page 98.
3-6 years or B Preventive maintenance of Preventive maintenance of
2,000 Close and operating mechanism and operating mechanism and
Open operations circuit-breaker circuit-breaker on page 100.
C Overhaul of breaking
chamber at the
unsynchronized capacitor
bank, reactor and filter circuit-
breaker
15 years or 5,000 B Overhaul of circuit-breaker Overhaul of the whole circuit-
Close and Open and operating mechanism breaker and operating
operations mechanism on page 104.
C Overhaul of breaking
chamber at the synchronized
capacitor bank, reactor and
filter circuit-breaker
30 years or C General overhaul of complete If the circuit-breaker and the
10,000 Close circuit-breaker and operating operating mechanism are
and Open mechanism: overhauled for a further
operations 10,000 operations, all moving
• dismantling of circuit-
parts must be replaced.
breaker pole and link
gear If the circuit-breaker and the
operating mechanism are
• assembly of new overhauled for a further 2,000
contact set operations, certain worn parts
must be replaced.
• replacement of other
worn components. See chapter Overhaul on
page 117.
ΣnxI2=20,000 C Overhaul of breaking
chamber at the line and
transformer circuit-breaker
94 2009-03-09 1HSB429954-10en
8 Maintenance
8.2 The maintenance schedule for operating mechanism and circuit-breaker
Competence levels
The different maintenance activities require different competence levels for the
personnel carrying out the work. The significance of the different levels is:
• A: substation personnel without special training.
• B: personnel authorized by ABB to carry out assembly, commissioning and
maintenance work.
• C: personnel authorized by ABB to carry out assembly, commissioning and
maintenance work. In some cases support may be necessary from ABB.
1HSB429954-10en 2009-03-09 95
8 Maintenance
8.3 The service life of the circuit-breaker
General
Assuming that the recommended inspection intervals and actions have been
observed, the circuit-breaker will have a service life greater than 30 years or 10,000
mechanical operations.
Maintenance points
In general, there are only two reasons for replacing the breaking units:
Reasons
1 If the number of short-circuits x short-circuit current (kA) approaches the curve, see
figure No of operations on page 97.
2 If the number of operations at the line, reactor, or capacitor connection, as well as the
switching of load current1), has reached the number under the heading "Interval" in The
maintenance schedule for operating mechanism and circuit-breaker on page 94.
1)
The load currents from normal Close and Open operations are not calculated in the
formula. These are only calculated when counting the total number of mechanical
Close and Open operations.
Another reason for replacing the breaking units is limited to mechanical faults/faulty
adjustment of the drive system, which could damage the components inside the
breaking units.
NOTE!
Opening the breaking unit calls for special instructions and may only be carried out
by qualified and authorized personnel.
Calculations
The graph that shows the restriction to the number of permitted short circuits can be
given roughly as:
Formula Explanation
2
Σn x I = 20,000 n = number of short circuits
I = short-circuit current kA (RMS)
96 2009-03-09 1HSB429954-10en
8 Maintenance
8.4 The service life of the arcing contacts in the event of short circuit breaking
8.4 The service life of the arcing contacts in the event of short circuit breaking
General
The diagram shows the number of breaks as a function of the breaking current that
the contacts in a circuit-breaker can handle before burn-off is so great that they must
be replaced.
No of operations
n No of operations
kA Short-circuit current
1HSB429954-10en 2009-03-09 97
8 Maintenance
8.5.1 Ocular inspection and density check
General
This section specifies the maintenance activities that must be carried out on the
circuit-breaker and the operating mechanism after 1-2 years.
Competence level
Personnel who carry out maintenance work are to have competence level A: they
must be substation personnel but do not need to have any special training.
Condition of circuit-breaker
98 2009-03-09 1HSB429954-10en
8 Maintenance
8.5.2 Cleaning and lubrication of circuit-breakers
The circuit-breaker's porcelain insulators are to be cleaned of salt and dirt deposits in
connection with cleaning of other insulators in the substation. The time interval for
this cleaning depends on local conditions, i.e. the degree of air pollution.
Wash and dry the insulators using rinsing equipment and drying cloths.
WARNING!
Mechanical damage to the insulator may cause it to explode with the subsequent risk
of splintering. Work on the circuit-breaker where there is a risk of mechanical
damage to the insulators is to be executed at reduced gas pressure, 0.125 MPa (abs).
NOTE!
Composite insulators must NOT be cleaned.
Lubricant
Only use the lubricant recommended in section Types of grease on page 31. This is
particularly important at temperatures below -25°C.
Lubrication of circuit-breakers
The circuit-breaker bearings are lubricated with grease on delivery and do not
normally need to be lubricated other than for larger overhauls.
See Treatment of sealing surfaces and seals on page 137.
1HSB429954-10en 2009-03-09 99
8 Maintenance
8.6.1 Preventive maintenance of operating mechanism and circuit-breaker
8.6 Activities after 3-6 years or 2,000 Close and Open operations
General
This section specifies all the maintenance activities that must be carried out on the
operating mechanism after 3-6 years or 2,000 Close and Open operations.
DANGER!
Before working on the operating mechanism:
• the motor current must be cut.
• the circuit-breaker must be open, disconnected and earthed.
• the closing and trip springs must be discharged; see section Release the spring
charge on page 28.
• the circuit-breaker (control switch) must be in DISCONNECTED position
Competence level
Personnel who carry out maintenance work are to have competence level B:
personnel must be authorized by ABB to carry out assembly, commissioning and
maintenance work.
Condition of circuit-breaker
Requisite equipment
The table below specifies all the actions that need to be taken for preventive
maintenance of the circuit-breaker.
Component Action More information
Complete circuit- Heat measurement: check the Heat measurement is carried out
breaker temperature increase in the at full load prior to disconnection
outer parts of the circuit-breaker. of the circuit-breaker.
The highest permitted
temperature difference between
the phases is 5°C.
Use a thermal camera.
Consideration must be taken to
the load current during
measurement, both to the larger
variations of the load current 3-4
hours prior to measurement. See
the manual for the thermal
camera.
Complete circuit- Look for corrosion. External ocular inspection. Treat
breaker with anti-rust agent where
necessary.
Complete circuit- Simple operational tests. Execute a simple operational test,
breaker if possible in combination with the
measurement of operational times
(including Close-Open times).
The table below specifies all the actions that need to be taken for preventive
maintenance for the operating mechanism.
Component Action More information
Worm gear (worm and Clean and lubricate with grease Does not need to be
gear wheel) “G”. removed.
Rating plate on each Check and note the serial number.
cabinet
Operation counter Check and note the number of
operations.
Structure
General
This section contains information on overhauling the breaking units. The interval is
2,000, 5,000 Close and Open operations or Σn x I2=20,000, depending on the type of
circuit-breaker; see The maintenance schedule for operating mechanism and circuit-
breaker on page 94.
Competence level
Personnel who carry out maintenance work are to have competence level C:
personnel authorized by ABB to carry out assembly, commissioning and
maintenance work. In some cases support may be necessary from ABB.
Condition of circuit-breaker
The closing and trip springs are to be discharged, the circuit-breaker is to be in open
position, disconnected and earthed. The entire circuit-breaker pole, with breaking
unit, is to be removed and transported to the workshop.
Requisite equipment
NOTE!
Use personal protective equipment:
• long-sleeved overalls
• protective gloves of plastic or
rubber
• tight fitting facemask for dust
protection
2. Remove the circuit-breaker pole and See section Removal of circuit-breaker pole for
transport to the workshop. transport on page 123.
3. Lift off the breaking unit. See section Dismantling of breaking unit from
the post insulator on page 126.
General
This section specifies the maintenance activities that must be carried out on the
circuit-breaker and the operating mechanism after 15 years or 5,000 mechanical
Close and Open operations.
Note that the activities for the circuit-breaker and the operating mechanism are
described in two separate tables. However, the list of equipment is common to all
activities.
Competence level
Personnel who carry out maintenance work are to have competence level B:
personnel authorized by ABB to carry out assembly, commissioning and
maintenance work.
Condition of circuit-breaker
The closing and trip springs are to be discharged, the circuit-breaker is to be in open
position, disconnected and earthed.
Requisite equipment
Below is a list of the tools necessary for an overhaul of the circuit-breaker and
operating mechanism. In addition to these tools, other equipment and expendable
supplies that may be specified in cross-referenced sections could also be necessary.
Equipment Part number Note
Rinsing equipment for cleaning
insulators
Electronic timing for the circuit-
breaker's function times
Gas filling equipment Where there is the need of gas filling
Dew point meter
Torque wrenches
Measurement equipment for
resistance
Measurement equipment for
voltage
Control pin 1HSB539782-1
Anti-rust agent Where there is the need of anti-rust
treatment.
Torque tool 1HSB426883-3 Packed in accessories box.
The table below specifies all the components that need to be checked for the overhaul
of the circuit-breaker. Any tools and expendable material is detailed in the table and
is also listed in the previous table.
Instructions/more informa-
Component Check...
tion
Porcelain insulators tightening torque for nuts and Use torque wrenches. The correct
bolts. tightening torque is specified in
Tightening torque on page 34.
Composite insulators insulator, with reference to
damage.
Circuit-breaker, • Opening time Measuring with electronic timing.
function times Nominal control voltage
• Closing time
For times, see Operating values on
• Close-Open time page 38.
• Deviations between Maximum time deviation between
phases the phases, 5 ms at closing and 3
ms at opening.
• Backup switch
• Coupling times
• Contact damping
SF6 gas gas pressure, by reading the Correct pressure specifications for
density monitor. different temperatures are on the
rating plates.
Fill with gas, if necessary, using
gas filling equipment, see Gas
filling with SF6-gas on page 80.
SF6 gas dew point, for normal gas Use a dew point meter.
pressure in the circuit-breaker. Dew point max. -5°C at specified
filling pressure and +20°C.
Density monitoring the density monitor's pressure Remove the density monitor from
(SF6 gas) indicator and signal and break the circuit-breaker to check the
contacts. function.
NOTE!
The test must take place in normal
air conditions, +20 °C and 101.3
kPa (1,013 mbar).
Minimum permitted voltage
when checking: 30 V.
Instructions/more informa-
Component Check...
tion
Main circuit resistance through Resistance values as specified in
measurement. section Operating values on page
(200 A DC) 38.
Higher values are permitted for
frequent operation with small
currents (≤ 400 A).
Calculation of permitted resistance:
• R = permitted raised
resistance
• Rn = max. resistance as per
Operating values on page
38
• In = rated current as per
rating plate
• I = the current that the
maximum resistance is
calculated for
Link gear open-position, by checking that Verify with control pin
the reference hole in the
operating lever is aligned with
the hole in the link gear's
mechanism housing.
The table below specifies all the components that need to be checked for the overhaul
of the operating mechanism. Any tools and expendable material are detailed in the
table and are also listed in Requisite equipment on page 104.
Component Check... Instructions/more information
Operating external condition, with External ocular inspection.
mechanism regard to cleanliness Clean and lubricate where necessary.
and any corrosion. Treat with anti-rust agent where necessary.
See Cleaning, lubrication and rust
protection of operating mechanism on page
110.
Retaining bolts and that they are in position. No tools needed.
nuts
Damper that the damper has no If there is an oil leak, the whole damper
oil leaks. must be replaced!
See section Replacement of damper on
page 182 for instructions and spare part
numbers.
NOTE!
The performance test is to be carried out
when the circuit-breaker is out of service.
Control voltage availability (minimum Measure the minimum control voltage.
control voltage). Closing time coil: < 85% of nominal value.
Opening time coil: < 70% of nominal value.
Variable DC-voltage unit.
Anti-pumping relay availability (relay's An Open-Close operation at the rated
lowest control voltage). voltage with a closing impulse that lasts for
30 seconds must be possible without
"pumping" of the circuit-breaker, i.e., when
the circuit-breaker executes repeated
Close-Open operations.
The relay's lowest control voltage is
measured.
Motor motor current. The motor current must be measured
towards the end of the charging process.
See Operating values on page 38.
Max. charging time: 15 seconds.
The motor must be able to charge the spring
at 85% of nominal voltage (IEC).
See Inspection of drive unit on page 114.
Latch device Settings, visually. For setting the gap in the latch device, see
Lubricate the shafts. Inspection of latch devices on page 112.
Surfaces on shafts and interlocks are
lubricated using Grease "L". See section
Types of grease on page 31.
Coils coil resistance and The coil resistance and current is allowed to
current. vary ±10 % of the measurement values
received during routine tests.
Limit switch function. In the final phase of the charging process of
the closing spring, the closing circuit must
be closed before cutting the motor current.
Heating element in resistance and signal for See Inspection of heating element on page
the operating voltage drop. 116.
cabinet
Heating element in resistance. 140 W, 110 V R= 86 Ohm ±10 %
central cabinet (if 140 W, 220 V R=346 Ohm ±10 %
applicable)
Thermostat (if that the thermostat is See Pre-commissioning check list on page
applicable) adjusted as per the set 90.
value.
The following components are to be cleaned and lubricated when they are fitted in
the operating mechanism. The components are highlighted in the illustration that
follows after the table.
Clean and
Item Component lubricate More information
with...
1 Limit stop roller on the operating Grease "G"
mechanism's closing lever
2/3 Rollers on the closing and tripping Grease "L"
latch assembly levers
4 Contact surface for interlock, closing Grease "G" Clean and lubricate the work
surfaces.
5 Contact surface for interlock, Grease "G" Clean and lubricate the work
opening surfaces.
6 Pins for spring locking (3 pcs) Grease "G" Lubricate the worn surfaces.
7 Pin for the closing spring's lever Grease "G" Lubricate the worn surfaces.
8 Eye bolt for transmission rod Grease "G" Note: The eye bolt must be
removed before cleaning and
lubrication! Removal is described
in section Replacement of eye
bolt and bellows on page 194.
Safety
WARNING!
Work on the operating mechanism with the circuit-breaker in closed position and
charged closing spring always represents a risk.
It is therefore important to observe the safety instructions before commencing work.
See Hazardous working situations on page 25.
Lubricant
The table below shows the greases and oils that are needed for this maintenance. For
suppliers and trade names of oils and greases, see sections Oil types on page 29 and
Types of grease on page 31.
Lubricant Spare part number Note
Grease "G" 5316 381-A
Oil "S" 1HSB875318-C
Cleaning
Clean the operating mechanism where necessary through vacuuming. The time
interval for this cleaning depends on local conditions, i.e. the degree of air pollution.
Check that the filters in the valves are clean. Replace them if they are overly dirty.
Lubrication
The operating mechanism's ball, roller and needle bearings, and shafts are lubricated
with grease for each function as specified in Types of grease on page 31 and under
normal conditions, require no maintenance. The worm gear and worm screw (worm
transmission) are to be lubricated as specified in the maintenance schedule; see
section Preventive maintenance of operating mechanism and circuit-breaker on page
100.
The dampers are filled with "S" oil on delivery.
Rust protection
Certain steel mechanical components in the operating mechanism are surface treated
through manganese phosphating agent and protected by being dipped in oil. This
applies primarily to levers, interlocks, gear wheel, components in the link system and
brackets for the cam discs. Other components, such as the chassis, are painted as a
means of rust protection. The closing and trip springs are anti-rust protected with
two-component paint.
On delivery, the operating mechanism is treated with desiccant as transport
protection against moisture.
Despite good anti-rust treatment, minor rust attacks may occur after a few years,
particularly if the circuit-breaker is installed in a highly corrosive environment. Rust
spots must be polished off and new anti-rust agent applied by brush or spray. Grease
“G” or Tectyl 506 is recommended as a rust inhibitor; see section Types of grease on
page 31.
NOTE!
Tectyl 506 forms a wax-like protective coat after drying and must not be applied to
bearings and interlock mechanisms or to gear wheels.
Spares
Spare parts must be stored indoors in an approved storage area1) and in original
packaging. This applies especially to rubber components (seals etc.) that must also
be protected against sunlight to prevent drying out. Gaskets can only be stored for a
limited period, so avoid stocking them. Supports can be stored outdoors.
1) Approved storage areas: Roof, solid ground, air humidity below 50%, temperature
oC (±10oC).
+20
General
The operating mechanism has one closing coil and two trip coils fitted as standard,
but can on request be fitted with double closing coils.
Latch device
Requisite equipment
Check of play
Action Note/Illustration
1. Check and clean the shafts in the latch
devices.
2. Lubricate these with grease “L”.
3. Check that the voltage to the coils does See the operating mechanism's delivery
not fall below the min. level. document.
4. Check the play between the coil arm
and auxiliary latch. The permitted play
is given in the figure to the right.
NOTE!
If the play is outside the specified dimensions,
the whole latch device must be replaced.
This is described in sections Replacement of
closing latch assembly on page 166
andReplacement of tripping latch assembly on
page 163.
General
Requisite equipment
Action Note
1. Measure the motor current at the end See section Operating values on page 38.
of the charging process.
NOTE!
The motor must be able to charge the springs
at 85 % of nominal voltage (IEC).
If this is not the case, replace the motor as per
section Replacement of gear housing and
motor in the drive unit on page 187.
General
This section describes how to check the oil level in the damper.
Requisite equipment
Structure
Instructions
Action Note
1. If the oil level is to be checked using Damper removal is described in section
ultrasound equipment, the damper can Replacement of damper on page 182.
remain in place. Otherwise it must be
removed.
2. Check the oil level
Where necessary, top up with oil "S".
General
The operating cabinet is fitted with a heating element to prevent condensation and
must always be connected.
Illustration
Instructions
Action Note
1. Measure the element's resistance In order to ensure the element is intact
2. Measure the power supply to the
element
Data
9 Overhaul
9.1 Introduction
General
Scope
If the overhaul is made for a further 10,000 operations, all moving parts must be
replaced.
If the overhaul is made for a further 2,000 operations, certain worn parts must be
replaced.
Competence level
Personnel who carry out maintenance work as per this chapter are to have
competence level C: they must be authorized by ABB to carry out assembly,
commissioning and maintenance work. In some cases support may be necessary from
ABB.
General
This section describes the preparations that are necessary prior to an overhaul of the
circuit-breaker.
The overhaul can be carried out according to two methods:
• The recommended method is to remove the entire circuit-breaker pole for
transport to the service workshop where it can be fully dismantled for the
overhaul; see sections Removal of circuit-breaker pole for transport on page
123.
• The alternative method is to only dismantle the breaking unit; see sections
Replacement of breaking unit on page 145.
The latter method does not require as much work, but may only be applied in clement
weather that resembles indoor working conditions.
WARNING!
The following points must be observed before beginning the overhaul.
• The springs must be discharged; see below under preparations.
• The gas must be evacuated; see Removing of SF6-gas on page 120.
NOTE!
Under no circumstances may the breaking unit be opened during rainy or unstable
weather, or when the humidity is 80% or higher.
Requisite equipment
Preparations
Action Note/Illustration
1. Before dismantling the circuit-breaker,
and during the course of the work, the
instructions in Safety on page 23 must
be read and followed.
2. Check and note the circuit-breaker's
operating values prior to dismantling.
• Deviations from the
recommended values indicate
that something needs to be
checked with extra care for the
overhaul.
3. Put the circuit-breaker in open
position.
4. Cut the control voltage and where
necessary the heater voltage as well.
5. Switch the circuit-breaker Close-Open
so that the springs are discharged.
6. Disconnect and earth.
General
Safety
CAUTION!
Work on the circuit-breaker's insulators or live parts, as well as transport and
dismantling of all circuit-breaker poles from the support, may not be executed until
the gas has been evacuated to a maximum pressure of 0.125 MPa abs.
WARNING!
If nitrogen is to be discharged into the open air, in cases where nitrogen is used for
internal cleaning of circuit-breakers, this must be conducted through a dust and
absorption filter. Evacuation is to take place outdoors and at ground level.
WARNING!
Unused SF6 gas is non-toxic, odorless and colorless. It is heavier than air and in the
event of heavy discharges, it easily collects in low-lying areas, such as cable
trenches, tanks, etc.
For large volumes of SF6 gas in such areas, the risk of suffocation could therefore
arise due to lack of oxygen.
Requisite equipment
NOTE!
Mixed gas, SF6 mixed with N2 or CF4,
may not be reused unless the mixing
ratio is controlled.
4. After vacuum pumping, the circuit-
breaker is filled with dry nitrogen at
atmospheric pressure. It is then
vacuum pumped once again.
5. Finally the circuit-breaker is again filled
with dry nitrogen at atmospheric
pressure.
6. The circuit-breaker is now ready for
dismantling
General
Safety
CAUTION!
Certain crevice products formed in the breaking unit, in combination with moisture,
are corrosive and can irritate the skin, eyes and mucous membranes.
NOTE!
All dust and old absorbent agents are to be collected in a sealed vessel and treated as
chemical waste in accordance with local regulations.
NOTE!
Drying cloths, protective gloves and vacuum cleaner bags are to be thoroughly rinsed
using plenty of water.
Requisite equipment
Equipment Note
Vacuum cleaner With fine dust filter and plastic nozzle
Drying cloths Of non-lint material
Sealed storage vessels For waste products and used absorption filters
Steel brush For aluminum contact surfaces
Cleaning cloth E.g. Scotch-Brite, for contact copper surfaces
Industrial spirit 95% (vol) C2H5OH, for cleaning internal surfaces
Thick plastic foil and plastic For prevention of moisture penetration and to protect
bags cleaned parts prior to installation.
Cleaning
• For internal cleaning of the circuit-breaker, protective gloves of plastic or
rubber, long-sleeved overalls and a close-fitting facemask with filtration to
counteract fine dust and acidic gases must be worn.
• The dust (crevice products) formed in the circuit-breaker is to be removed with
a vacuum cleaner fitted with a fine dust filter and wiped off using drying cloths
moistened in industrial spirit.
General
Preconditions
NOTE!
This type of work may only be executed by personnel trained by ABB.
Requisite equipment
Dismantling
The following instructions describe the removal of the circuit-breaker pole for
transport.
Action Note/Illustration
1. Loosen the poles' gas connections by
unscrewing all three nuts to the mark
(1) on the non-return valve (2).
1. Mark
2. Non return valve
3. Sealing cap
2. Now remove all nuts
3. Fit the sealing caps (3).
Action Note/Illustration
4.
DANGER!
The lifting tackle used to lift the circuit-
breaker pole must be dimensioned for
the weight.
• The polymer circuit-breaker
pole weighs about 130 kg.
• The porcelain circuit-breaker
pole weighs about 300 kg.
See dimensional drawing for exact
weights.
5. Put a lifting sling under the breaking
unit's upper flange and secure with a
lifting crane.
NOTE!
For composite insulators: Place the lifting sling
as close as possible to the flange. Do not place
it on the rubber surface.
6. Remove the transmission rod's eye
bolt from the circuit-breaker's outer
lever by removing the shaft end (1)
after you have removed the lock
washer at the rear.
Action Note/Illustration
7. Loosen the circuit-breaker pole at the
four bolts (1) in the pole beam.
General
This section describes the removal of a breaking unit, after the circuit-breaker pole
has been dismantled and transported to a workshop.
NOTE!
The circuit-breaker pole is fitted vertically on a suitable support, e.g. a circuit-
breaker support or a frame of the floor of the workshop.
Structure
1 Operating shaft
2 Bolt M12x80 (4 pcs), washer 13x28x3 (8 pcs), nut M12 (4 pcs)
3 Post insulator
4 Breaking unit
5 Lock washer SL12
6 Pin D=12
7 Insulating pull-rod
Requisite equipment
Instructions
The instructions below describe the removal of a breaking unit from a circuit-breaker
pole. The item numbers in the text correspond to the item numbers in the previous
illustration.
Action Note
1. Turn the operating shaft (1) anti-
clockwise to the contacts' closed
position.
NOTE!
Use the torque tool.
2.
DANGER!
The lifting tackle used to lift the circuit-
breaker pole must be dimensioned for
the weight.
• The polymer circuit-breaker
pole weighs about 130 kg.
• The porcelain circuit-breaker
pole weighs about 300 kg.
See dimensional drawing for exact
weights.
3. Fit the lifting devices from the top of the
breaking unit to the hoist or overhead
crane.
NOTE!
Stretch the lifting device moderately.
For composite insulators: Place the lifting sling
as close as possible to the end flange and not
on the rubber surface.
4. Remove the bolts (2) between post
insulator (3) and breaking unit (4)
5. Lift the breaking unit 75 - 100 mm.
NOTE!
The breaking unit must not be lifted more than
100 mm to avoid damage to the inside of the
circuit-breaker.
Action Note
6. Remove the lock washer (5) and the
pin (6).
NOTE!
Ensure that no lock rings or washers fall down
in the post insulator when dismantling.
Cover the opening by e.g. a cloth rag.
7. Lift off the breaking unit completely and
place it vertically on an appropriate
surface, e.g. on two cross bars to
ensure it does not tip over.
General
This section describes the removal of post insulators, after the breaking unit has been
removed from a dismantled circuit-breaker pole.
To prevent moisture in the air coming into long-term contact with dust in the post and
insulating pull-rods, the work on removal and cleaning must be planned to ensure it
can be executed quickly and without long breaks.
Structure
1 Post insulator
2 Bolt M 16x50, washer 17x30x3
3 Mechanism housing
4 Lock washer SL1 6
5 Pin D=20
6 Insulating pull-rod
7 Lower lock nut
8 Turnbuckle screw
9 Upper lock nut
Safety
NOTE!
Use personal protective equipment:
• long-sleeved overalls
• protective gloves of plastic or rubber
• tight fitting facemask for dust protection
Requisite equipment
Instructions
The instructions below describe the removal of post insulators. The item numbers in
the instruction text refer to the previous illustration.
Action Note
1.
DANGER!
Use lifting tackle dimensioned for the
post insulator. See dimensional
drawing for exact weights.
2. Fit the lifting devices from the top of the
post insulator to the hoist or overhead
crane.
3. Remove the post insulator bolts (2)
from the mechanism housing (3).
Action Note
4. If the insulating pull-rod is to be
dismantled, the x distance must be
measured on the old bar:
Lift the post insulator sufficiently so
that the internal turnbuckle screw (8) is
accessible for measurement and
measure the x dimension. Save the
note for the assembly.
General
This section describes the overhaul of the complete mechanism (shown in the figure
below).
Structure
1 Mechanism housing
2 Inner operating lever
3 Operating shaft
4 Radial seal
5 Lock ring
6 Ball bearings
7 Bushing
8 O-ring 49.2 x 5.7 (located outside bushing pos. 7)
9 X-ring 49.2 x 5.7 (located inside bushing pos. 7)
10 Pin D = 20 mm
11 Linkage joint
12 Lock washer SL1 6
Remember!
NOTE!
Clean the mechanism through vacuuming and drying. Check the bearings and replace
all sealing rings.
Requisite equipment
Instructions
The item numbers in the instructions below correspond to the item numbers in
Structure on page 132.
Action Note
1. Remove the radial seals (4).
2. Remove the lock rings (5).
3. Knock/pull out the operating shaft (3). The ball bearings and the bushing on one side
follow when you knock/pull out the operating
shaft.
4. Knock/pull out the other ball bearings
and the other bushing.
5. Inspect the ball bearings (6). Replace the ball bearings where damage is
identified!
• Do not lubricate these.
6. Inspect the bushings (7) that keep the Replace the bushings if damage is discovered.
sealing rings in place.
7. Replace the sealing rings (8, 9) in the
bushings (7) and lubricate with grease
"S".
• Fill the space between the
sealing rings with grease.
8. Press in the bushing (7) and ball
bearings (6) on one side. Fit the circlip
(5).
NOTE!
Turn the bearings' sealing rings toward the
circlip and place the bushing against the gas
space.
Press in the bearings and bushing together to
avoid creating an air pocket.
9. Refit the operating shaft (3) through The shaft (3) and the inner operating lever (2)
the inner operating lever (2). each have a blind tooth and these must be
aligned. Be sure to rotate the shaft (3) correctly
in order to guide it through the inner operating
lever (2).
Action Note
10. Press in the bushing (7) and ball
bearings (6) on the other side. Fit the
circlip (5).
NOTE!
Turn the bearings' sealing rings toward the
circlip and place the bushing against the gas
space.
Press in the bearings and bushing together to
avoid creating an air pocket.
11. Apply grease "G" to the circlips (5).
12. Fit the new radial seals (4).
General
Before the breaking unit is refitted, the contact surfaces are to be treated as follows.
Requisite equipment
General
In conjunction with installation, all sealing surfaces are to be cleaned, degreased and
checked.
Remember:
NOTE!
The sealing grooves and other sealing surfaces may not have transverse scratches.
Any minor scratches on the sealing surfaces can be removed using a fine cleaning
cloth, such as Scotch-Brite. Polish along the sealing line and never across it.
Requisite equipment
Instructions
Action Note
1. Replace all seals with new ones when
reassembling the circuit-breaker.
2. Sparingly lubricate the sealing Surfaces and seals are lubricated to facilitate
surfaces and seals. the seal's fitting to the surface and as corrosion
protection.
Excess grease that could be pressed out of the
flanges inside the gas space may not occur.
3. Coat the flange surfaces outside the
external seals with a thin, fully covering
layer of corrosion protective agent
adapted to suit the pertinent flange
material (grease "G").
General
Structure
1 Post insulator
2 Bolt M16x50 (4 pcs) Washer 17x30x3 (8 pcs)
3 Mechanism housing
4 Insulating pull-rod
5 Sealing ring 169.5x5.6
6 Lower lock nut
7 Turnbuckle screw
8 Upper lock nut
9 The insulating pull-rod's key handle
Requisite equipment
Instructions
The item numbers in the instructions’ text refer to the illustration in Structure on page
138.
Action Note/Illustration
1.
NOTE!
Be careful not to damage the insulating
pull-rod.
2. If the insulating pull-rod has been
removed, the x distance is adjusted in
accordance with the dimension of the
old pull-rod:
Adjust the x dimension so that it
matches the notation made when the
post insulator was removed.
NOTE!
The turnbuckle screw (7) must be
screwed in the same amount in the
linkage joint and the insulating pull-rod.
Torque!
100 Nm.
4. Lubricate and place the sealing ring (5)
on the mechanism housing (3).
Action Note/Illustration
5.
DANGER!
The lifting tackle used to lift the circuit-
breaker pole must be dimensioned for
the weight.
• The polymer circuit-breaker
pole weighs about 130 kg.
• The porcelain circuit-breaker
pole weighs about 300 kg.
See dimensional drawing for exact
weights.
6. Lift the post insulator (1).
NOTE!
Hold the insulating pull-rod during assembly so
that it does not scratch the post insulator.
7. Fit bolts with washers (2) and tighten.
Torque!
79 Nm
General
This section describes how the breaking unit is refitted to the post insulator.
Structure
1 Puffer pull-rod
2 O-ring 169.5x5.6
3 Post insulator
4 Lower adapter plate
5 Pin D=12
6 Lock washer SL12
7 Bolt M12x80 (4 pcs), washer 13x28x3 (8 pcs), nut M12 (4 pcs)
8 Insulating pull-rod
9 Upper adapter plate
10 Sealing ring 194.6x5.6
11 Container for absorbent
12 Cover
13 Bolt M10x30, washer 10.5x20x2
14 Breaking unit
Requisite equipment
Instructions
The instructions below describe how the breaking unit is refitted to the post insulator.
The item numbers (in brackets) in the text correspond to the item numbers in the
previous illustration.
Action Note
1.
DANGER!
Use lifting tackle that is dimensioned
for the weight of the circuit-breaker.
See dimension print for the exact
weights.
2. For assembly of replacement unit:
Reduce the nitrogen pressure in the
breaking unit (14) to atmospheric
pressure and remove the protective
cover.
3. Suspend the breaking unit in the lifting
device and pull down the puffer pull-
rod (1) to fully extended position
making it accessible for assembly. NOTE!
For composite insulators: Place the lifting sling
as close as possible to the end flange and not
on the rubber surface.
4. Clean the sealing surface on the
sealing ring (2) on the post insulator (3)
carefully.
5. Also clean the lower flange and
adapter plate (4) and lubricate
generously with grease “G” to ensure
the sealing ring is kept in place during
assembly.
6. Place the sealing ring (2) in its slot.
7. Slowly lower the breaking unit (14) so
that it comes into position for fitting the
pin (5), around 75-100 mm above the
post insulator (3).
Action Note
8. Connect the puffer's pull-rod (1) to the
insulating pull-rod (8) with the pin (5)
and lock using a lock washer (6).
9. When the pin is fitted, lower the
breaking unit carefully down towards
the post insulator and centre.
10. Secure the breaking unit with bolts,
washers and nuts (7).
Torque!
79 Nm.
11. Remove the bolts (13 ) and the cover
(12) and lift out the container for the
absorbent (11).
12. Clean the sealing surface on the upper
flange and adapter plate (9) and
lubricate with grease “G”.
13. Place the sealing ring (10) on top of the
upper flange.
14. Open the packaging to new absorbent
and apply this in the container (11).
15. Fit the container (11) and cover (12).
16. Tighten the bolts (13).
Torque!
45 Nm.
General
Before the circuit-breaker pole can be moved it must be treated with gas as per this
section.
Instructions
Action Note/Illustration
1. Vacuum pump down to a pressure of
100 Pa and let the vacuum pumping
continue for at least one hour after this
pressure has been reached.
2. Stop the vacuum pumping and fill the
circuit-breaker with dry and clean
nitrogen to atmospheric pressure. Let
it stand a couple of hours or overnight.
3. Vacuum pump back down to a The filling hoses are to be stored to ensure that
pressure of 100 Pa and fill with clean they are not exposed to moisture and
SF6-gas to 0.125 MPa (abs). contamination. They must not be used for
anything other than their intended purpose.
4. The circuit-breaker pole is now ready
for transport.
General
This section describes the dismantling of the breaking unit for transport. Dismantling
the breaking unit on site is an alternative to the recommendation (removing the whole
circuit-breaker, and then dismantling the breaking unit in a workshop) and is only to
be applied in stable weather which gives indoor-like working conditions.
The circuit-breaker must be removed from service before the breaking unit is
dismantled, see Preparations for overhaul on page 118, the gas evacuated, see
Removing of SF6-gas on page 120, and filled to atmospheric pressure with nitrogen.
Preconditions
NOTE!
Under no circumstances may the breaking unit be dismantled or opened during rainy
or unstable weather.
NOTE!
This type of work may only be executed by personnel trained by ABB.
NOTE!
If the post insulator or breaking unit is left for a long period without being refitted,
the post insulator, or breaking unit, is to be vacuum pumped and filled with nitrogen.
Structure
1 Operating lever
2 Bolt M12x80 (4 pcs), washer 13x28x3 (8 pcs), nut M12 (4 pcs)
3 Post insulator
4 Breaking unit
5 Lock washer SL12
6 Pin D=12
7 Insulating pull-rod
Requisite equipment
Instructions
The instructions below describe the dismantling of a breaking unit for transport.
Unless otherwise stated, the position numbers in brackets refer to the previous
illustration.
Action Note
1. Before removing the breaking unit the Se Preparations for overhaul on page 118 and
circuit-breaker is to be taken out of Removing of SF6-gas on page 120.
service.
2. Fill the circuit-breaker with nitrogen to
atmospheric pressure.
3. Remove the transmission rod eye bolt
from the circuit-breaker's outer
operating lever by removing the shaft
end (1) after you have removed the SL
lock washer, see the figure to the right.
DANGER!
The lifting tackle used to lift the circuit-
breaker pole must be dimensioned for
the weight.
• The polymer circuit-breaker
pole weighs about 130 kg.
• The porcelain circuit-breaker
pole weighs about 300 kg.
See dimensional drawing for exact
weights.
6. Fit the lifting devices from the top of the
breaking unit to the hoist or overhead
crane.
NOTE!
Stretch the lifting device moderately.
For composite insulators: Place the lifting sling
as close as possible to the end flange and not
on the rubber surface.
Action Note
7. Remove the bolts (2) between post
insulator (3) and breaking unit (4)
8. Lift the breaking unit 75-100 mm.
NOTE!
The breaking unit must not be lifted more than
100 mm to avoid damage to the inside of the
circuit-breaker.
9. Remove the lock washer (5) and the
pin (6).
NOTE!
Ensure that no lock rings or washers fall down
in the post insulator when dismantling.
Cover the opening by e.g. a cloth rag.
10. Lift off the breaking unit completely and
place it vertically on a suitable surface,
such as on two cross bars, to ensure it
does not tip over. NOTE!
If large amounts of moisture enter the post
insulator, this must be immediately sealed and
filled with nitrogen to be transported as soon as
possible to the workshop for dismantling and
careful cleaning.
11. Press the insulating pull-rod (7) down
into the post insulator (3) so that the
entire insulating pull-rod is below the
edge.
12. Fit the protective cover A with the The cover part number is specified in Requisite
sealing ring above the post insulator equipment on page 146.
(3).
NOTE!
When the protective cover has been fitted, the
nitrogen pressure in the post insulator is raised
to 0.125 MPa abs.
13. Push the puffer pull-rod into the
breaking unit (4).
14. Fit protective cover R with a sealing The cover part number is specified in Requisite
ring on the breaking unit. equipment on page 146.
15. The breaking unit is now ready for
transport.
NOTE!
If the post insulator or breaking unit is left in this
condition for a long period without the unit
being refitted, the post insulator, or breaking
unit, is to be vacuum pumped and filled with
nitrogen.
General
This section describes the assembly of the breaking unit following an overhaul, when
the breaking unit has been dismantled on site, i.e. not in the workshop.
Structure
1 Puffer pull-rod
2 O-ring 169.5x5.6
3 Post insulator
4 Lower adapter plate
5 Pin D=12
6 Lock washer SL12
7 Bolt M12x80 (4 pcs), washer 13x28x3 (8 pcs), nut M12 (4 pcs)
8 Insulating pull-rod
9 Upper adapter plate
10 Sealing ring 194.6x5.6
11 Container for absorbent
12 Cover
13 Bolt M10x30, washer 10.5x20x2
14 Breaking unit
15 Operating shaft
Requisite equipment
Instructions
The instructions below describe how the breaking unit is refitted to the post insulator.
The item numbers (in brackets) in the text correspond to the item numbers in the
previous illustration.
Action Note
1.
DANGER!
Use lifting tackle that is dimensioned
for the weight of the circuit-breaker.
See dimension print for the exact
weights.
2. Suspend the breaking unit in the lifting
device and remove the protective
cover.
NOTE!
For composite insulators: Place the lifting sling
as close as possible to the end flange and not
on the rubber surface.
3. Pull down the puffer pull-rod (1) to fully
extended position making it accessible
for assembly.
4. Reduce the nitrogen pressure in the The protective covers must be removed on all
post insulator (3) to atmospheric poles at the same time.
pressure and remove the protective
cover from the post insulator.
5. Turn the operating lever (15) anti-
clockwise to its closed position to
ensure that the breaking unit can be
fitted. NOTE!
Use the torque tool.
6. Clean the sealing surface on the
sealing ring (2) on the post insulator (3)
carefully.
Action Note
7. Also clean the lower flange and
adapter plate (4) and lubricate
generously with grease “G” to ensure
the sealing ring is kept in place during
assembly.
8. Place the sealing ring (2) in its slot.
9. Slowly lower the breaking unit (14) so
that it comes into position for fitting the
pin (5), around 75-100 mm above the
post insulator (3).
10. Connect the puffer's pull-rod (1) to the
insulating pull-rod (8) with the pin (5)
and lock using a lock washer (6).
11. When the pin is fitted, lower the
breaking unit carefully towards the
post insulator and centre.
12. Secure the breaking unit with bolts,
washers and nuts (7).
Torque!
79 Nm.
13. Remove the bolts (13 ) and the cover
(12) and lift out the container for the
absorbent (11).
14. Clean the sealing surface on the upper
flange and adapter plate (9) and
lubricate with grease “G”.
15. Place the sealing ring (10) on top of the
upper flange.
16. Open the packaging to new absorbent
and apply this in the container (11).
17. Fit the container (11) and cover (12).
18. Tighten the bolts (13).
Torque!
45 Nm.
Action Note
19. Attach the transmission rod's eye bolt
to the circuit-breaker pole's operating
lever with the shaft end (1) and lock
with a lock washer at the rear, see the
figure to the right.
20. Check the open position using the The part number of the guide pin is specified in
control pin that is to run through the Requisite equipment on page 150.
hole of the outer lever and the hole in
the mechanism housing.
21. Fill the circuit-breaker pole with gas.
1. Vacuum pump down to a
pressure of 100 Pa and let the
NOTE!
vacuum pumping continue for
at least one hour after this Store the filling hoses in a way that does
pressure has been reached. expose them to moisture and contamination.
They must not be used for anything other than
2. Stop the vacuum pumping and their intended purpose.
fill the circuit-breaker with dry
and clean nitrogen to
atmospheric pressure. Let it
stand a couple of hours or
overnight.
3. Vacuum pump back down to a
pressure of 100 Pa and fill with
clean SF6 gas to 0.125 MPa
(abs).
22. The circuit-breaker is now ready for See Gas filling with SF6-gas on page 80.
gas filling.
General
First overhaul
CAUTION!
The circuit-breaker may not be operated from Open to Close without an intermediate
delay of 300 ms!
(2)
Filling pressure is as specified on the rating plate.
Second overhaul
CAUTION!
The circuit-breaker may not be operated from Open to Close without an intermediate
delay of 300 ms!
10 Repairs
10.1 Overview
General
This chapter contains instructions on how you replace the operating mechanism's
spare parts, that feature in chapter Spares on page 203.
There is also information on each section on the equipment required to implement
the repairs in question, i.e. relevant spare part numbers, tools to be used, lubricant, etc
General
Structure
Requisite equipment
The instructions below describe how you remove the casing from the operating
mechanism.
Action Note/Illustration
1.
DANGER!
Before working on the operating
mechanism:
• the motor current must be cut.
• the circuit-breaker must be
open, disconnected and
earthed.
• the closing and trip springs
must be discharged; see
section Release the spring
charge on page 28.
• the circuit-breaker (control
switch) must be in
DISCONNECTED position
2. Remove the earth plate (1) inside the
cabinet.
1. Earth plate
Action Note/Illustration
3. Remove the cable plate under the
cabinet by unscrewing the retaining
bolts (1).
The instructions below describe how the casing is fitted to the operating mechanism.
Action Note
1. Move the casing up over the operating
mechanism and attach using the four
bolts (1) at the rear and the retaining
bolts (2) under the cabinet.
Torque!
M16: 100 Nm
M10: 45 Nm
2. Attach the cable plate using retaining
bolts (1) under the casing.
Torque!
M8: 22.5 Nm
Action Note
3. Refit the earth plate (1) inside the
cabinet.
General
This section contains information on replacing the closing coil Y3 and trip coils Y1
and Y2.
Structure
The figure below shows the position of the coils in the operating mechanism. The
figure shows the operating mechanism without casing, but the coils can be replaced
without removing the casing.
1 Closing coil Y3
2 Tripping coil Y1
3 Tripping coil Y2
Requisite equipment
Replacement of coil
The instructions below describe the removal and assembly of the coils. The same
instructions apply to all coils.
Action Note/Illustration
1.
DANGER!
Before working on the operating
mechanism:
• the motor current must be cut.
• the circuit-breaker must be
open, disconnected and
earthed.
• the closing and trip springs
must be discharged; see
section Release the spring
charge on page 28.
• the circuit-breaker (control
switch) must be in
DISCONNECTED position
2. Remove the cover (1) from the coil to
be replaced.
NOTE!
Check the voltage!
8. Fit the cover.
General
This section describes the replacement of the complete tripping latch assembly
including the coils.
Structure
The figure below shows the position of the tripping latch assembly in the operating
mechanism.
Requisite equipment
The instructions below describe how the tripping latch assembly is removed from the
operating cabinet.
Action Note
1.
DANGER!
Before working on the operating
mechanism:
• the motor current must be cut.
• the circuit-breaker must be
open, disconnected and
earthed.
• the closing and trip springs
must be discharged; see
section Release the spring
charge on page 28.
• the circuit-breaker (control
switch) must be in
DISCONNECTED position
2. Remove the casing from the operating
mechanism.
3. Remove the closing and trip springs to Follow the instructions Replacement of tripping
facilitate manual movement of the and closing latch device assembly on page 172
operating mechanism's opening lever. up until the point when the bolt is unscrewed
from the spring. Note that the spring does not
The lever is otherwise in the way when
need to be fully removed, but can be loosened
you need to remove the tripping latch
at one end.
device assembly.
NOTE!
Before removing the closing and trip
springs you must measure the A
dimension of the closing spring and the
B dimension of the trip spring!
Information on these dimensions is
given in section Replacement of
tripping and closing latch device
assembly on page 172.
4. Remove the covers from the trip coils
and remove their cables.
5. Remove the latch device from the
operating mechanism by removing the
retaining nuts on the outside.
The nuts are locked with Loctite and
may need to be heated carefully using
a LP-gas burner in order to be
removed.
Action Note
6. Rotate the operating lever's opening
lever to release the latch device and
remove the assembly from the
operating mechanism.
There is not a lot of space for this task
and the latch device may need to be
positioned at different angles in order
to pull it out.
The instructions below describe how the tripping latch assembly is fitted inside the
operating mechanism.
Action Note
1. Angle and push in the latch device
under the operating mechanism's
opening lever.
2. Attach the latch device using the three
retaining nuts on the outside of the
operating mechanism. Use locking
fluid. NOTE!
Locking fluid, Loctite 270
Torque!
40 Nm
3. Connect the cables to each coil and
refit the old covers.
4. Refit the closing and trip springs. Note Follow the instructions Replacement of tripping
the original A and B dimensions! and closing latch device assembly on page
172.
5. Refit the operating mechanism casing. Described in section Removal and assembly of
casing on page 156.
General
This section describes the replacement of the complete closing latch assembly
including the coils.
Structure
The figure below shows the position of the closing latch assembly in the operating
mechanism.
Requisite equipment
The instructions below describe how the closing latch assembly is removed from the
operating cabinet.
Action Note/Illustration
1.
DANGER!
Before working on the operating
mechanism:
• the motor current must be cut.
• the circuit-breaker must be
open, disconnected and
earthed.
• the closing and trip springs
must be discharged; see
section Release the spring
charge on page 28.
• the circuit-breaker (control
switch) must be in
DISCONNECTED position
2. Remove the casing from the operating
mechanism.
3. Remove the closing and trip springs to Follow the instructions Replacement of tripping
facilitate manual movement of the and closing latch device assembly on page 172
operating mechanism's closing lever. up until the point when the bolt is unscrewed
from the spring. Note that the spring does not
The lever is otherwise in the way when
need to be fully removed, but can be loosened
you need to remove the closing latch
at one end.
device assembly.
NOTE!
Before removing the closing and trip
springs you must measure the A
dimension of the closing spring and the
B dimension of the trip spring!
Information on these dimensions is
given in section Replacement of
tripping and closing latch device
assembly on page 172.
Action Note/Illustration
4. Remove the pin installed in between
as shown in the figure to the right, and
a small black pin further forward on the
latch device.
Action Note/Illustration
11. Remove the latch device from the
operating mechanism by removing the
retaining nuts on the outside.
The nuts are locked with Loctite and
may need to be heated carefully using
a LP-gas burner in order to be
removed.
12. Pull out the latch device from the
cabinet.
CAUTION!
The latch device's two plates are not
linked together which means they can
fall apart when the assembly is pulled
out!
There is not a lot of space for this task
and the latch device may need to be
positioned at different angles in order
to pull it out.
The instructions below describe how the closing latch assembly is fitted inside the
operating mechanism.
Action Note/Illustration
1. Angle and push in the latch device into
the operating mechanism.
NOTE: Ensure that the mechanical
interlock arm (1 ) on the latch device
runs against the head (2) on the main
shaft, see the figure to the right!
Action Note/Illustration
2. Attach the latch device using the two
retaining nuts on the outside of the
operating mechanism. Use locking
fluid. NOTE!
Locking fluid, Loctite 270
Torque!
40 Nm
3. Connect the cables to each coil and
refit the old covers.
4. Push the closing lever back to the
correct position on the main shaft and
attach it using the retaining bolt.
5. Refit the position indicator module.
6. Attach the damper.
7. Refit the pin to the spring bracket
(shown in the figure in the next step).
Action Note/Illustration
8. Refit the spring in the latch device. The
short hook on the spring (2) is to be
attached around the slot on the pin (1)
and the long hook on the spring (3) is
to be attached around the small black
pin on the latch device.
Note that the spring is to be turned to
ensure the opening on the hooks is
facing down!
General
This section describes the replacement of closing and trip springs that are delivered
as a complete assembly with the spring fitted to the attendant brackets.
Structure
The figure below shows the position of the closing and trip springs in the operating
mechanism.
1 Closing spring
2 Trip spring
Requisite equipment
The new closing spring must have the exact same pre tension as the old one when it
is fitted. Therefore, there must be a certain distance, known as A-dimension,
measured on the old spring before it is removed in order for the new spring to be
adjusted when fitting. The figure below shows the surfaces between which the A -
dimension is to be measured.
A The A dimension is the distance between the cast surface on the spring bracket and
the surface of the external diameter of the cylinder where the spring bolt runs
through.
The new trip spring must have the exact same pre tension as the old one when it is
fitted. Therefore, there must be a certain distance, known as B-dimension, measured
on the old spring before it is removed in order for the new spring to be adjusted when
fitting. The figure below shows the surfaces where the B-dimension is to be
measured.
B The B dimension is the distance between the cast surface on the spring bracket and
the top side of the brass washer.
The instructions below describe how the spring assembly is removed from the
operating mechanism. The instructions differ a little for the closing and trip springs,
which is also noted in the relevant steps in the instructions.
Action Note/Illustration
1.
DANGER!
Before working on the operating
mechanism:
• the motor current must be cut.
• the circuit-breaker must be
open, disconnected and
earthed.
• the closing and trip springs
must be discharged; see
section Release the spring
charge on page 28.
• the circuit-breaker (control
switch) must be in
DISCONNECTED position
2. Remove the casing from the operating Described in section Removal and assembly of
mechanism. casing on page 156.
3. Measure the A-dimension on the The dimensions are shown in the figures
closing spring or the B-dimension on Measurement of A-dimension of closing spring
the trip spring and save the notes until on page 173 and Measurement of B-dimension
assembling the new spring. of trip spring on page 174.
Action Note/Illustration
4. Loosen the two nuts (1) on the spring. Closing spring:
Trip spring:
Action Note/Illustration
5. Unscrew the bolt from the spring. Closing spring:
Trip spring:
The instructions below describe how the spring assembly is fitted inside the
operating mechanism. The instructions differ a little for the closing and trip springs,
which is also noted in the relevant steps in the instructions.
Action Note/Illustration
1. The spring must be turned the right Closing spring:
way in the operating mechanism, i.e.,
turned so that the the correct sides of
the spring are turned inward and
outward in the operating mechanism!
See detail figures to the right to
determine which side is to be facing
outwards.
Trip spring:
Action Note/Illustration
4. Tighten both nuts (1) on the closing Closing spring:
and trip springs.
Trip spring:
5. Refit the operating mechanism casing. Described in section Removal and assembly of
casing on page 156.
General
This section contains information on the replacement of the limit stop roller on the
closing lever.
Structure
The figure below shows the position of the limit stop roller in the operating
mechanism.
Requisite equipment
The instructions below describe how the limit stop roller on the operating
mechanism's closing lever is replaced.
Action Note/Illustration
1.
DANGER!
Before working on the operating
mechanism:
• the motor current must be cut.
• the circuit-breaker must be open,
disconnected and earthed.
• the closing and trip springs must be
discharged; see section Release
the spring charge on page 28.
• the circuit-breaker (control switch)
must be in DISCONNECTED
position
2.
NOTE!
The new limit stop roller must have the
same dimension as the old roller.
3. Remove the safety washer (1).
4. Push out the shaft (2) and pull out the roller
(3). Take care of the two spacers on each
side of the roller.
5. Lubricate the new needle bearing with
grease “G” and put it in the new roller.
6. Place a spacer at each end of the roller, put
the parts in place and push in the shaft
through the washers and the roller with the
bearing.
7. Refit the safety washer and attach with the
bolt.
General
Structure
The figure below shows the position of the damper in the operating mechanism as
seen from behind.
1 Damper
Requisite equipment
Replacement of damper
DANGER!
Before working on the operating mechanism:
• the motor current must be cut.
• the circuit-breaker must be open,
disconnected and earthed.
• the closing and trip springs must be
discharged; see section Release the
spring charge on page 28.
• the circuit-breaker (control switch)
must be in DISCONNECTED position
2. Remove the casing from the operating Described in section Removal and
mechanism. assembly of casing on page 156.
3. Remove the split pin at the damper's upper
bracket.
4. Remove one of the split pins at the damper's
lower bracket.
General
Structure
The figure below shows the position of the auxiliary contact in the operating
mechanism.
1 Auxiliary contact
Requisite equipment
DANGER!
Before working on the operating
mechanism:
• the motor current must be cut.
• the circuit-breaker must be
open, disconnected and
earthed.
• the closing and trip springs
must be discharged; see
section Release the spring
charge on page 28.
• the circuit-breaker (control
switch) must be in
DISCONNECTED position
2. Remove the casing from the operating Described in section Removal and assembly of
mechanism. casing on page 156.
3. Remove the damper's upper bracket in Removal of the damper is described in section
order to release the linkage. Replacement of damper on page 182.
4. Remove the linkage's lower bracket
and remove the whole linkage.
5. Dismantle all contacts from the
auxiliary contact.
6. Remove the four retaining bolts (1) and
remove the auxiliary contact.
Action Note/Illustration
9. Refit the linkage.
1. Tighten the bolt (1) in the lower
bracket.
2. Refit the linkage in its upper
bracket together with the
damper.
General
This section contains information on replacing the gear housing and motor in the
drive unit.
Structure
The figure below shows the position of the gear housing and motor in the operating
mechanism.
1 Gear housing
2 Motor
Requisite equipment
The instructions below describe how the complete drive unit with gears and motor is
removed from the operating mechanism.
Action Note/Illustration
1.
DANGER!
Before working on the operating
mechanism:
• the motor current must be cut.
• the circuit-breaker must be
open, disconnected and
earthed.
• the closing and trip springs
must be discharged; see
section Release the spring
charge on page 28.
• the circuit-breaker (control
switch) must be in
DISCONNECTED position
2. Remove the casing from the operating Described in section Removal and assembly of
mechanism. casing on page 156.
3. Remove the entire drive unit by
loosening the two retaining bolts (1)
from the side.
Action Note/Illustration
4. Lower the unit and remove the link
pipe that runs upwards.
The instructions below describe how the drive unit is dismantled, i.e., how the gear
housing and motor are replaced, following the removal of the entire drive unit for the
operating mechanism as per the previous instructions.
Action Note
1. Remove the four retaining bolts on the
motor.
2. Pull the motor out of the gear housing.
Ensure that the bushing remains in
place inside the gear housing when
fitting a new motor.
3. Replace the defect component and
refit the gear housing and motor.
Ensure the motor drive runs through
the bushing inside the gear housing.
4. Tighten the four retaining bolts on the
motor.
5. Fit the complete drive unit in the
operating mechanism again, as per the
following instructions.
The instructions below describe how the complete drive unit with gear housing and
motor is fitted in the operating mechanism.
Action Note/Illustration
1. Place the drive unit in the operating
mechanism together with the link pipe.
NOTE!
Loctite 270
Torque!
40 Nm
3. Refit the operating mechanism casing. Described in section Removal and assembly of
casing on page 156.
General
Structure
The figure below shows the position of the limit switch in the operating mechanism.
1 Limit switch
Requisite equipment
DANGER!
Before working on the operating
mechanism:
• the motor current must be cut.
• the circuit-breaker must be
open, disconnected and
earthed.
• the closing and trip springs
must be discharged; see
section Release the spring
charge on page 28.
• the circuit-breaker (control
switch) must be in
DISCONNECTED position
2. Remove the casing from the operating Described in section Removal and assembly of
mechanism. casing on page 156.
3. Remove the two retaining bolts (1) and
remove the spring pin (2). Remove the
limit switch.
Action Note/Illustration
4. Disconnect the cables from the limit
switch.
If there is only one of the contacts that
needs replacing, loosen the relevant
cables and replace the particular
contact.
t = 0.3 mm
8. Refit the casing on the operating Described in section Removal and assembly of
mechanism. casing on page 156.
General
This section contains information on replacing the transmission rod's eye bolt and
bellows
Structure
The figure below shows the position of the transmission rod, eye bolt and bellows
Requisite equipment
The instructions below describe how the transmission rod is removed from the
cabinet.
Action Note/Illustration
1.
DANGER!
Before working on the operating
mechanism:
• the motor current must be cut.
• the circuit-breaker must be
open, disconnected and
earthed.
• the closing and trip springs
must be discharged; see
section Release the spring
charge on page 28.
• the circuit-breaker (control
switch) must be in
DISCONNECTED position
2. Remove the casing from the operating Described in section Removal and assembly of
mechanism. casing on page 156.
3. Remove the pin (1) from the
transmission rod's upper bracket by
first removing the SL lock.
Action Note/Illustration
5. Loosen the support bolt (2) from the
opening lever at the transmission rod's
lower bracket.
The instructions below describe how the eye bolt is replaced on the transmission rod,
after the rod has been removed as per the previous instructions.
Action Note
1. Remove the retaining nut and unscrew
the eye bolt.
2. Lubricate the new eye bolt using "G"
grease.
3. Use the same washer, nut and bolt in
the new eye bolt.
Replacement of bellow
The instructions below describe how the bellows are replaced on the transmission
rod, after the rod has been removed as per the previous instructions.
Action Note/Illustration
1. Cut the strap on the bottom edge of the
bellows.
2. Fit new bellows and attach them with a
strap on the bottom edge.
The instructions below describe how the transmission rod is refitted in the operating
mechanism.
Action Note/Illustration
1. Thread the transmission rod through
the top of the cabinet and through the
bellows up on the roof.
NOTE!
Check that the C-C distance between the eye
bolts is 456 mm.
2. Attach the bellows on the rod using a
strap (1).
Action Note/Illustration
3. Fit the transmission rod to the lower
bracket and lock using the support
screw (2) to the opening lever.
5. Refit the operating mechanism casing. Described in section Removal and assembly of
casing on page 156.
General
ABB AB strives to minimize the product’s impact on the environment throughout its
entire life cycle. Technical and product development focuses on environmental
aspects. The ecocycle approach is strived for and consideration is taken to the
materials' environmental impact and recycling alternatives. The manufacturing
processes are selected to be as safe to the environment as possible.
The table below shows the circuit-breaker materials, its parts by weight and
examples of application areas.
Parts by weight in
Material percent Example of application areas
SF6 gas
The SF6 gas must be evacuated prior to scrapping of a circuit-breaker. All handling
of SF6 gas must be conducted with care and according to the applicable regulations
to ensure that there are no gas leaks. The gas can be handled in different ways,
depending on the circumstances:
• Regenerated onsite, and reused in other equipment
• Sent to the gas supplier for regeneration
• Sent for destruction at a special waste treatment plant
In cases where the circuit-breaker is filled with mixed gas, the SF6 gas is separated
from the mixture for further processing according to the above. Alternatively, the gas
mixture can be sent for destruction without being separated. ABB AB can help
process the gas when a circuit-breaker is to be scrapped.
Porcelain
After cleaning, the porcelain can be sent for disposal or used for other purposes, such
as for use as filling material.
Composites
Composites can be fractioned and or disposed of, or used for other purposes, such as
for use as filing material with other materials.
Electronics
Metals
Metals are to be sorted according to type and surface treatment and sent to an
approved recycling company. Following the removal of any paint or other surface
treatment, clean metal can as a rule, be melted down and used in new products. Many
metal components of iron, steel and aluminum are large and easy to identify, e.g.
supports and mechanism housings.
ABB AB strives to reduce the use of precious metals and emissions of
environmentally hazardous metals. Recycling of these is particularly important.
Precious metals such as copper and silver are expensive and are only present in small
amounts in the earth’s crust. Copper is primarily used in current paths, puffers,
contacts and cables. Silver plating of contacts may occur. Emissions from certain
metals may cause damage. This applies to copper, but also zinc and nickel, which are
used sparingly as surface treatments.
Plastics
Before disposal, oil, grease and similar products must be removed and sent to an
approved environmental waste treatment plant or recycling company. By utilizing
gravimetric forces, oil waste can be separated into oil, water and a range of
contaminants. In many cases, the oil can then be reused. Alternatively, the energy
content in oil can be recovered through combustion at a plant designed for the
purpose.
Oil occurs in dampers where grease is used as a lubricant.
Rubber
Rubber can be sent to an approved environmental waste treatment plant, either for
disposal or reused for various purposes.
Rubber is present in various seals.
Other materials
Other materials are sorted and sent to an approved environmental waste treatment
plant.
Gas handling
Electrical equipment with 6 has been used for many years with good results. In cases
where a device or switchgear needs to be opened, the SF6 gas is collected and reused.
ABB's policy is that no SF6 gas is to be released during installation, service or
disposal of equipment.
SF6 gas
Pure SF6 gas is non-toxic and is harmless to inhale if the oxygen content is at least
20%. SF6 is approximately five times heavier than air. This means that gas may
collect in, e.g. cable trenches or at the bottom of tanks.
Greenhouse effect
The SF6 molecule contributes to the greenhouse effect, but does not contain any
chlorine and thereby has no impact on the ozone layer. Since SF6 gas began to be
used 50 years ago, a small amount of gas has leaked into the atmosphere. There are
currently approximately 3 x 10-12 parts by volume of SF6 in the atmosphere. Due to
the low concentration, this share is less than a tenth of a percent of the total
greenhouse effect.
Decomposition
The SF6 gas partially decomposes in conjunction with discharges. This takes place
in the temperature range where arcing is extinguished, 1500-5000 K, and provides an
efficient cooling effect. Here both gaseous and solid crevice products are formed. All
crevice products are reactive, which means that they are quickly decomposed and
disappear.
During normal operation, the level of gaseous crevice products is kept low through
built-in absorbers. The solid crevice products are primarily metal fluorides in the
form of a powder. The powder can be easily processed as separate waste and
represents no long-term threat to the environment. For service and maintenance there
are special procedures as the large concentrations of crevice products are corrosive
and toxic.
12 Spares
12.1 Introduction
General
The replacement modules for the operating mechanism are delivered complete and
tested.
Spare parts that are recommended for storage are marked with R. Where there are
more than ten circuit-breakers in operation we also recommend the spares marked
with RR. RRR parts can be held in stock in order to be able to replace parts quickly
and avoid prolonged stoppages.
State the type designation and manufacturing number, for any enquiries and when
ordering parts or tools. Specify the order number also where possible.
Summary, circuit-breaker
1 Damper
2 Closing coil
3 Tripping coils (2 pcs)
4 Closing spring assembly
5 Trip spring assembly
6 Drive unit with motor
7 Limit stop roller on closing lever
8 Bracket for limit switch
Structure
Component parts
Illustration
Component parts
Structure
Component parts
12.2.4 Mechanism
Illustration
Component parts
12.2.5 Accessories
Absorbent container
Density monitor
Gasket set
Protective cover
12.3.1 Damper
Illustration
Component parts
Illustration
Component parts
Illustration
Component parts
Structure
Component parts
Structure
Component parts
Structure
Component parts
Structure
Component parts
ABB AB
Circuit-Breaker Unit
S-771 80 LUDVIKA
SWEDEN
Telephone: +46 (0) 240 782000
Telefax: +46 (0) 240 782320