HW 3 Sol

This document provides solutions to homework problems involving critical path method (CPM) scheduling. It includes drawing a network diagram for a sample project and identifying the critical path. The critical path for the given project is activities A-C-D-E-G, lasting 26 weeks. To reduce the completion time of another sample project by three weeks, the document shows crashing activities D, G, and A in sequential steps for the lowest total cost of $6,000.

Uploaded by

avni1601
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
224 views3 pages

HW 3 Sol

This document provides solutions to homework problems involving critical path method (CPM) scheduling. It includes drawing a network diagram for a sample project and identifying the critical path. The critical path for the given project is activities A-C-D-E-G, lasting 26 weeks. To reduce the completion time of another sample project by three weeks, the document shows crashing activities D, G, and A in sequential steps for the lowest total cost of $6,000.

Uploaded by

avni1601
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Homework Solutions – Chapter 3

1. The following activities are part of a project to be scheduled using CPM:

Activity Immediate Predecessor Time (wks)


A - 6
B A 3
C A 7
D C 2
E B,D 4
F D 3
G E,F 7

a. Draw the network


b. What is the critical path?
c. How many weeks will it take to complete the project?
d. How much slack does activity B have?

Solution

a.

b. A-C-D-E-G, also shown in the network above as the bold path.


c. 26 weeks, 6+7+2+4+7.
d. 6 weeks, 15-9.
2. For the project with the following information,
a. Determine the critical path and the early completion time in weeks.
b. Reduce the project completion time by three weeks. Assume a linear cost per
week shortened, and show, step by step, how you arrived at your schedule.

Activity Imm. Pred. Normal time Normal cost Crash time Crash cost
A -- 5 7000 3 13000
B A 10 12000 7 18000
C A 8 5000 7 7000
D B 6 4000 5 5000
E C 7 3000 6 6000
F C 4 6000 3 7000
G D,E,F 4 7000 3 9000

Solution

a. A-B-D-G, 25 weeks, 5+10+6+4.


b.

Activity Normal Normal Cost Crash Time Crash Cost NT-CT Cost/week
Time (NT) (NC) (CT) (CC) to expedite
A 5 $7,000 3 $13,000 2 $3,000
B 10 12,000 7 18,000 3 2,000
C 8 5,000 7 7,000 1 2,000
D 6 4,000 5 5,000 1 1,000
E 7 3,000 6 6,000 1 3,000
F 4 6,000 3 7,000 1 1,000
G 4 7,000 3 9,000 1 2,000

First, reduce D (lowest cost activity on the critical path) by one week. This adds an additional
critical path with activities C and E in it. Second, crash activity G by one week. Critical paths
remain the same. Third, crash activity A by one week at a cost of $3,000, which is the least
expensive.

Summary of activities crashed:

Step Activity Cost to crash Weeks reduced


1 D $1,000 1
2 G 2,000 1
3 A 3,000 1
Total cost $6,000