GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES Materials Engineering Report No
GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES Materials Engineering Report No
1)
2)
3)
4)
5)
REPORT BASEED ON
A flow chart summarizing the processes involved in the site investigation is included in the Appendix A
of the guideline. This guideline document should be used as a guide and not approached or referred to
as a limiting or standard geotechnical investigation/design specification. MAIN 5 (five ) above ROADS
Western Meghalaya
INTRODUCTION.................................................................................................................
OBJECTIVES........................................................................................................................
Laboratory Testing
GEOTECHNICAL REPORTS..............................................................................................
REFERENCES................................................................................................................................
APPENDIX A: FLOW CHART ON GUIDELINES FOR GEOTECHNICAL INVESTIGATIONS FOR BRIDGE
STRUCTURES MAIN 5 (five )ROADS Western Meghalaya .
INTRODUCTION This guideline document has been prepared to assist in the planning, cost estimation,
conduct and reporting of geotechnical investigations at bridge sites. Henceforth for ease of reporting,
reference is made only to requirements at bridge sites however corresponding requirements at
waterway structures are implicit in this term.
2. OBJECTIVES The objectives for these guidelines are to: Describe processes or stages of work to be
followed for a bridge site investigation. Describe information required to design bridge foundations.
Indicate standards of skill, workmanship and reporting, which are to be applied.
A flow chart summarize the processes involved in a bridge site investigation is included in Appendix A.
3. STAGES OF INVESTIGATION
3.1 Field Reconnaissance Survey For most bridge investigations access and environmental constraints
have major influences on cost. It is therefore necessary for a field reconnaissance survey to be
conducted as the first stage of a geotechnical investigation. This may be undertaken by MITP or by a
consultant specifically engaged for this survey. Information on the following should result: Legal and
physical aspects of access to site and bridge alignment – both riverbed and adjoining properties.
Availability of any services or supplies of water, electricity, earthworks plant. Buried or overhead
services. Photographs of surface conditions. Traffic control requirements. MAIN 5 (five )ROADS Western
Meghalaya.
The possible effects of alternative investigation techniques on the environment (for example, ground
disturbance, vegetation removal, water discharge, noise etc). On-ground survey details. Tide, river level
or other natural constraints. Notes on any exposed geology, for example the presence of boulders,
bedrock exposure, swamps etc. The physical relationship of the proposed construction to the immediate
natural surroundings and any existing developments. The field reconnaissance survey must be diligently
prepared and conducted to allow for reliable cost estimates to be prepared. Experienced and suitably
qualified personnel should perform the survey. Further stages of the investigation should be held until
the field reconnaissance survey has been completed and reported to MITP. Cost estimates for the major
part of the investigation will be based partly on this reconnaissance survey.
3.2 Desk Top Study Every site investigation should commence with a desk study directed towards
collecting, collating and reviewing the following:
Design drawings from any previous structure at the site. Previous site investigation reports, borehole
logs, penetrometer results and construction experience e.g. piling records. Geological and Topographical
maps, survey data and records. Hydrological data. Aerial photographs. Regional seismicity data. Survey
records, local knowledge and resources. MAIN 5 ( Five) ROADS Western Meghalaya .
The collection and collation of the above information, where possible, could be undertaken during the
field reconnaissance survey stage. However, further work to fully explore the extent of information
available may be required. During the desk study stage, an overview of complexity and risks associated
with each geotechnical design should be clearly identified.
3.3 Sampling and Testing This stage of the Geotechnical Investigation is involved with the exploration
of subsurface conditions and retrieval of test data for generating geotechnical parameters and
geotechnical profiles. Central to the investigation and subsequent design stage an understanding of the
ultimate limit state design to be adopted for design is an essential. This should be done by a suitably
qualified and experienced geotechnical engineer and conveyed to the personnel conducting the
investigation prior to the commencement of site works. The selection of Characteristic Values of
geotechnical parameters (refer AS 5100), the modification of these values by using Geotechnical
Strength reduction factors and the use of these modified values in calculating ultimate limit state design
capacity must be fully understood. Communication between the bridge design engineer and the
geotechnical engineer to achieve an appropriate understanding is imperative. Where the geotechnical
investigation is limited to the investigation of mobile riverbeds prior discussion with the MITP
Waterways Section is necessary. The objective of this type of investigation is to identify the approximate
limits of clear water and live bed scours for the purposes of foundation design of bridges and floodways
and invert levels of culverts. The types of geotechnical field investigation are usually site specific and
require discussion with the structural and waterways engineers. Defining the scope of the investigation
(eg. number of test locations, type of test, frequency and depth) is not covered explicitly by these
guidelines. The number, location and depth of tests is to consider: expected sub-surface conditions
previous geotechnical information available MAIN 5 (five) ROADS Western Meghalaya of likely extent of
zones in ground influenced by loading need to achieve a reliable geotechnical model for analysis size
and importance of the structure requirement to minimize contractor and MITP risk of changes during
the construction programmed due to variations in the subsurface conditions from that reported during
the investigation stage. Allowance should be made for the anticipated level of variability in ground
conditions and possible changes to the design. An experienced geotechnical engineer must make these
decisions and discussion on the number, location and depth of the selected tests must be a part of the
geotechnical report. This discussion must enable the reader of the report to understand what factors
were used to assess these variables and provide a clear understanding of the deliverables. While the
above points should be covered by a well planned investigation there may be situations where during
the investigation stage it is considered by MITP or the geotechnical consultant that additional
investigation will be required to generate a more reliable model and minimize risk. This work shall be
undertaken at a schedule of rates agreed upon prior to the commencement of the investigation. The
following references contain supplementary comments, which should be read and implemented into
investigation and testing as relevant. IRC, ASTHO Australian Standard AS1726 “Geotechnical Site
Investigations” Australian Standard AS1170 “Structural Design Actions” Australian Standard AS2159
“Piling – Design and Installation” Australian Standard AS5100 “Bridge Design-Foundations and Soil
supporting structures” All in situ testing, for example Standard Penetration Test (SPT), Electric Friction-
Cone Penetration Test (EFCPT) etc, should be carried out in accordance with the relevant
Australian/Indian , American Standards and supervised accordingly. The purpose of in situ testing is to
determine the soil parameters necessary for the design of foundations. Groundwater must be
investigated to determine: MAIN 5 (five) ROADS Western Meghalaya , the maximum level of the
permanent water table at the time of the investigation occurrence of a perched water table condition
and its level estimated rates of inflow to excavations effects of de-watering on water table levels and on
adjacent structures the presence of sub-artesian conditions the potential aggressiveness of the soil and
groundwater, for example SO4, Cl, pH and Total Dissolved Solids (TDS) to buried concrete and steel. For
most cases it will be necessary to install standpipes in selected boreholes to enable sampling and
observations of water to be made. An allowance in cost estimates must be given to these installations.
4. GEOTECHNICAL REPORTS
The information contained in a geotechnical report would normally be used for design, tendering and
construction purposes. The report should be prepared in two parts:
Part 1 – (“Site Investigations Report”) details of all field and laboratory test data to be represented
Collating and presentation of the geotechnical data for each sub-surface formation. This presentation
should be in a form which would enable selection of characteristic values for design. Submission of
proposal(s) for further field and laboratory work, if deemed necessary, with comments justifying the
need for this extra work.
(b) Conclusions and Recommendations The conclusions and recommendations of a geotechnical report
will include, but not be limited to the following: Classification of the project according to geotechnical
complexity. Selection of suitable characteristic values for the requirements of the project (geotechnical
design parameters). Settlement and stability computations. Recommendations concerning problems
that may be encountered during excavations, pumping operations, construction of retaining structures
and ground anchors, placement of earth materials etc. Comment on likely interaction of work on nearby
structures. Recommendations on any other issues e.g. for surface drainage if required.
GUIDELINES FOR GEOTECHNICAL INVESTIGATIONS ---------
STANDARDS IN MEGHALAYA REGIEON GEOTECHNICAL SITE INVESTIGATION, AS1726, IRC 5, IRC 6 AND
IRC : 78. STANDARDS INDIAN STRUCTURAL DESIGN ACTIONS, AS1170 STANDARDS INDIAN PILING -
DESIGN AND INSTALLATION, -------. STANDARDS INDIAN BRIDGE DESIGN – PART 3: FOUNDATION AND
SOIL SUPPORTING STRUCTURES,
• Surface geology
• Physical relationship of the proposed construction to the surroundings Desk Top Study Review of:
• Hydrological data
• Aerial photographs
• Regional seismicity
• Drilling method to be a function of ground and site conditions as well as equipment available
• Samples to be collected, transported and stored in an appropriate manner to avoid damage for later
laboratory testing
• Measurement of tip and sleeve resistance only refused or termination reason stated
• Measurement of tip, sleeve and pore water pressure with position of filter noted
• Establishment of groundwater levels using piezometer installation after completion of probing and in
the case of testing with pore pressure measurement groundwater levels should be confirmed
• Density or strength estimates to be established using standard equipment such as Perth Sand
Penetrometer, Dynamic Cone Penetrometer
• Test locations and levels to be established by survey Review information prior to dernobilsation from
site to ensure all aspects of the proposed program have been achieved and that information such as
groundwater levels are consistent and well established. Laboratory Testing The scope of testing to be
such that
• Consistency or classification of each of the different characteristic layers identified during the field
program is established, for example Atterberg limits or Particle Size Distribution
• Field data to be cross referenced with laboratory test results to ensure continuity of classification
• Remaining field samples to be checked against field logs to ensure classification consistent with
sampled material and logs modified accordingly
• Field and laboratory information assembled into a logical order to enable reporting or review by
independent persons Reporting Site Investigation Information
• Purpose and scope of the geotechnical investigation, including a discussion on the extent and scope of
the Investigation; refer field reconnaissance study and desk top study findings.
• Brief description of the project for which the geotechnical report is being compiled giving information
about the location of the project its size and geometry, anticipated beds, structural elements, materials
of construction, etc., and also giving a statement of the anticipated geotechnical complexity and risk
associated with the project.
• Detailed description of methods used for field and laboratory work with reference to accepted
standards followed, and with discussion on rationale used to determine the spacing, frequency and
locations of all tests.
• Names of the persons responsible for geotechnical site investigations and report writing.
• Presentation of field observations which were made by the supervising field personnel during the
execution of the sub-surface explorations.
• Data on fluctuations of groundwater table with time in the boreholes during the performance of the
fieldwork and piezometers after completion of fieldwork.
• Compilation of boring logs penetrometer results etc with descriptions of sub-surface formations
based on field descriptions and on the results of laboratory test.
• Grouping and presentation of field and laboratory test results in appendices. Evaluations. Conclusions
and Recommendations (a) Evaluation of geotechnical information
• The evaluation of geotechnical information may include but not be limited to, the review of the field
and laboratory work by Geotechnical Engineer. In cases where there are limited or partial data, the
Geotechnical Engineer should state this. If in the Geotechnical Engineer’s opinion the data are defective,
irrelevant, insufficient or inaccurate, he should point this out and qualify its comments accordingly. Any
particularly adverse test results should be considered carefully in order to determine whether they are
misleading or represent a real phenomenon that must be accounted for in the design.
• Tabulation and graphical presentation of the results of the field and laboratory work in relation to the
requirements of the projects.
• Determination of the depth of the ground water table and the seasonal fluctuations.
• Sub-surface profile(s) in graphic form (geotechnical profile of model), showing the disposition of the
various sub-surface formations. Detailed description of all subsurface formations in relation to their
physical properties and their compressibility and strength characteristics. Comment on Irregularities
such as pockets, cavities, etc.
• Grouping and presentation of ranges of variation of the geotechnical data for each subsurface
formation. This presentation should be in comprehensive form, which would enable selection of the
most appropriate characteristic value for the design.
• Submission of proposal(s) for further field and laboratory work, if deemed necessary, with comments
justifying the need for these extra work. (b) Conclusion and Recommendation
• The conclusion and recommendations of the geotechnical report will include, but not be limited to the
following:
• Selection of suitable characteristics values for the requirements of the project (geotechnical design
parameters).