3.1 Work Measurement - Time Study - W4 PDF
3.1 Work Measurement - Time Study - W4 PDF
WORK MEASUREMENT
TIME STUDY
(Direct Time Study & Activity Sampling)
7-2 Design of Work Systems
Work Measurement
TIME STUDY
• Standard time
• Stopwatch time study
• Historical times
• Predetermined data
• Work Sampling
7-3 Design of Work Systems
Historical Experience
• Relatively easy, convenient, and inexpensive
• Not objective, unknown accuracy
Not recommended
7-4 Design of Work Systems
Time Studies
Allowances
1 Take glass 8 9 8 10 8
Time study data using snap back stop watch. Time in seconds. Total allowance is
15% of the normal time. Workers rating is 110%.
Compute the total standard time.
Calculate the labor cost per product if the worker’s wage is RM 3 per-hour.
7-10 Design of Work Systems
2 10 12 10 11 12 11 12.1 14.235
3 25 25 25 25 25 25 25 25
Element 1:
Average time = (8+9+8+10+8)/5 = 8.6 sec
Normal time = Average time x Rating = 8.6 x 1.1 = 9.46 sec
Standard time = Normal time /(1-allowance) = 9.46 / (1-0.15) = 11.129 sec
Total Standard Time = 11.129+14.235+25+9.318 = 59.682 sec/product
7-11 Design of Work Systems
Calculate the labor cost for each product if the worker’s wage is RM
3 per-hour.
RM 3 / hr −4
Worker' s wage = = 8.33(10) RM / sec
3600 sec/ hr
- Example 2 -
Work Elements Cycle 1 Cycle 2 Cycle 3 Cycle 4
Data from snap back stop watch in minutes of a manual assembly process time
study. The worker is rated at 108%. The allowances are 5% for fatigue, 6% for delay,
and 6% for personal relief. The worker’s salary is RM1000 per month.
a) Compute the total assembly standard time for the assembly process.
b) If the demand is 100,000 unit per month, estimate the number of operators
required for the assembly process. The company is operating 24 days per month
and a single 8 hour shift per day.
c) If the company can only manage to employ 18 workers, compute the over time
cost per day for each worker for the production of 100,000 units per month.
Assume only 15 workers are available for over time and the over time pay rate is 1.5
times of the normal wage.
7-13 Design of Work Systems
Solved Problem
Element Cycle 1 Cycle 2 Cycle 3 Cycle 4 Average Normal Std
Time Time
1 0.22 0.26 0.25 0.23 0.24 0.259 0.312
2 0.15 0.18 0.15 0.16 0.16 0.173 0.208
3 0.90 1.10 1.04 1.00 1.01 1.091 1.314
4 0.72 0.80 0.76 0.68 0.74 0.799 0.963
(a) Element 1
0.22 + 0.26 + 0.25 + 0.23
Average Time = = 0.24 min
4
1 1
Standard Time = Normal Time x = 0.259 × = 0.312 min
1 - Allowance 1 − 0.17
Total Assembly Standard Time = 0.312 + 0.208 + 1.314 + 0.963 = 2.797 min/unit
7-14 Design of Work Systems
Solved Problem
b) If the demand is 100,000 unit per month, estimate the number of
operators required for the assembly process. The company is operating 24
days per month and a single 8 hour shift per day.
(b)
hr day min min
Working time of 1 operator = 1 × 8 × 24 × 60 = 11,520
day mth hr mth
min
11,520
Monthly quantity produced by 1 operator = mth = 4,118.70 unit
min mth
2.797
unit
unit
100,000
Monthly Demand mth = 24.28 ≈ 25
Number of operators required = =
Capacity per operator 4118.70 unit
mth
7-15 Design of Work Systems
Solved Problem
c) If the company can only manage to employ 18 workers, compute the over time
cost per day for each worker for the production of 100,000 units per month.
Assume only 15 workers are available for over time and the over time pay rate is 1.5
times of the normal wage.
(c)
unit
Monthly quantity produced by 18 operators = 4,118.70 × 18 = 74 ,137 units
mth
unit
Monthly quantity shortage = 100,000 - 74,137 = 25,863 (monthly shortage, need OT)
mth
unit
25,863
mth unit
Daily quantity shortage = = 1077 . 6
day day
24
mth
min hr
= 3 , 014 = 50 . 234
day day
7-16 Design of Work Systems
Solved Problem
Due to only 15 operators are available for over time work,
therefore over time hours for each operator per day
hr
50.234
day hr
= = 3.349
15 operator operator − day
RM
1,000
Normal wage = mth = 5.208 RM
day hr hr
24 ×8
mth day
RM RM
Over time wage = 1.5 x 5.208 = 7.812
hr hr
Work Sampling
Work Sampling
• Used for
• Ratio delay studies
• Setting labor standards
• Measuring worker performance
7-19 Design of Work Systems
The Five Step
Work Sampling Procedure
Productive IIIII IIIII IIIII IIIII IIIII IIIII IIIII IIIII I 41 41/45 = 91%
Productive IIIII IIIII IIIII IIIII IIIII IIIII IIIII IIIII I 41 41/45 = 91%
hr min
Total observation time = 8 × 60 × 6 day = 2880 min
day hr
Standard Time, ST
Total observation time 1
=[ × Productive % × Rating] ×
Total output 1 − allowance
2880 min 1
Standard Time, ST = × 0.91× 0.97 ×
3000 unit 1 − 0.15
min
= 0.997
unit
7-23 Design of Work Systems
Tutorial 1
Proses Description Average Time (min)
1 Manual 23
2 Manual 32
3 Automatic machine 9
4 Manual 8
Rating : 110%
Allowance: 20%
Tutorial 1
(a)
Proses Description Average Time Normal Std Time
(min) time
1 Manual
2 Manual
3 Automatic
machine
4 Manual
(b)
7-25 Design of Work Systems
Tutorial 2
Emirates Consultant conducted a work sampling studies for 5 consecutive days at an
assembly factory. A total of 48 observations were made during the 8 hour working
period for each day. The data collected during the 5 day studies is illustrated in Table
1. The whole assembly process is operating on 5 working days per week, 95% rating
and the company’s allowable allowances is 20%.
(i) Compute the standard time (min/unit) for the assembly process.
(ii) At peak demand period, the factory is normally required to produce 3,100 units per
week. If only 60% of the employee is willing to work over time, compute the average
overtime per day must be arranged in order to meet the peak demand.
Item Data
Total output over 5 days studies 2,500 unit
Assembly process at fast speed 35% of observations
Assembly process at moderate speed 45% of observations
Assembly process at slow speed 5% of observations
Production is stopped due to no operator 5% of observations
Production is stopped due to no material 10% of observations
7-26 Design of Work Systems
Tutorial 2
(i)
Total observation time =
Std Time =
(ii)
unit
Peak Demand =
wk
unit
Capacity during normal 8 hours =
day
7-27 Design of Work Systems
Tutorial 2
Capacity shortage = unit/day
If all employees are forced to do over time, the over time hours
min
=
day
END OF CLASS