Flow Chart EHV Transformer Installation PDF
Flow Chart EHV Transformer Installation PDF
Yadav
Flow Chart for EHV Transformer
Erection, Testing & Commissioning
Initial Checking: Internal Inspection Checkpoints:
1) Check Core Isolation
1) Packing & Despatch: Check Main tank & acces despatched from 2) No foreign material
works (Dry Air / N 2 with positive pressure. 3) Barrier board & shunt should be intact
2) Receipt Checking: Inspect for transit damage / Internal shifting 4) Check main lead of HV/IV/LV/Tap windings has no
3) Check Core Isolation: Check Core - Frame is intact damage
5) Check internal shipping damage or manufacturing defects
4) Dry Air / N 2Gas Filled Transformer: Check Dry Air / N2 Gas in
6) Check OLTC Contacts
pressure gauge to be positive & Tank valve is in open condition.
7) Check Dust, Insulation, internal connection of FOS
Also check Cylinder is open, Moisture dew point & report to mfg.
8) Bushing lead clearance,
5) Oil Filled Transformer: Check Oil Level as per Mfgr Guideline & 9) Check HV,LV, HVN& other CT internal / secondary
oil BDV, PPM
6) Check Impact Recorder values and analyse with manufacturer Erection: Without opening of blanking
7) Insurance Coverage: Transit & Shifting Damage, Damages during 11) Erection of A Frames, Radiators, Conservators, buchholz
ETC, if noticed. Report to Mfr to cover in Insurance Claim pipeline, breathers
12) Check A Frames & Radiator position
13) Erection of OLTC DM & Bevel Gear Shaft Alignment
Site Preparation: 14) Erection of turrets along with CTs & bushings- HV, LV &
1) Arrangement of tools & tackles, cranes, Neutral
2) Oil Filtration Machine, Selection of Vacuum Pump depending of 15) Checking of Lead Entry after bushing erection
voltage class of transformer, 16) Assembly of Coolers (Radiators / Heat Exchangers),
3) Testing Equipment for preliminary & final testing Conservators & other accessories