Burj Khalifa WBS

This document outlines a work breakdown structure dictionary for a construction project. It lists 15 main work packages with over 50 sub-tasks and provides estimates for cost and responsibilities. Some key risks are also identified such as working at heights, wind pressure, scaffolding failure, and transporting materials to high levels. The total estimated cost is over $350 million with the largest shares going to concrete work, lifts, glass work, and wood work. Various contractors and consulting firms are assigned responsibility for the different tasks.

Uploaded by

Asif Mahmood
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (6 votes)
3K views3 pages

Burj Khalifa WBS

This document outlines a work breakdown structure dictionary for a construction project. It lists 15 main work packages with over 50 sub-tasks and provides estimates for cost and responsibilities. Some key risks are also identified such as working at heights, wind pressure, scaffolding failure, and transporting materials to high levels. The total estimated cost is over $350 million with the largest shares going to concrete work, lifts, glass work, and wood work. Various contractors and consulting firms are assigned responsibility for the different tasks.

Uploaded by

Asif Mahmood
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

WORK BREAKDOWN STRUCTURE DICTIONARY

CONTROL ACCOUNT CODE ACTIVITY COST RESPONSIBLE RISKS


1.1 STEEL WORK $15 Million
Samsung Engineering Risk of height, wind pressure
1.2 BRAND SELECTION
1.3 Y SHAPE SOM, Chicago Change in design effect on cost, time
1.4 WELDING $6 Million
Risk of height, sun heat
1.5 DRILLING $7 Million Samsung Engineering
GREY STRUCTURE
1.6 CONCRETE WORK $20 Million
1.7 FOUNDATION $7 Million Brookfield multiplex
1.8 EXCAVATION $5 Million Baier and ME foundation Materials & their durability
1.9 LEVELLING $6 Million
Besix and Arbatec
1 10 CONCRETE PLACEMENT $15 Million
2.1 POWER WORK $18 Million
2.2 CONDUIT PIPING $10 Million
Change in design effect on cost, time
2.3 WIRES INSTALLATION $12 Million
2.4 SOCKETS, SWITCHES, A.C $30 Million
ELEVATORS Otis
2.5 LIFT DESIGN $20 Million Effect of gravity on tall buildings
2.6 LIFT CAPACITY $5 Million
2.7 LIFT SPEED $3 Million
2.8 INTERIOR $10 Million
3.1 WIND PRESSURE TESTING $0.5 Million
wind pressure, working at height
3.2 PANEL SELECTION
GLASS WORK 3.3 ALUMINUM/ UPVC $35 Million Al Ghurair Group Scaffolding failure
3.4 PANEL SELECTION Risk of collapse
3.5 GLASS INSTALLATION $17 Million Workers exposed to sun radiation at height
4.1 DESIGN
4.2 MATERIAL $20 Million Transport of material to such heights
4.3 SELECT WOOD
WOOD WORK Dorma
4.4 SELECT COLOR Workers working at height
ROOM HARDWARE,
4.5 $40 Million Objects falling from height
CUPBOARDS, CABINETS
5.1 CABLE TESTING $5 Million
Internal travel/transport within building

NETWORK INFRASTRUCTURE Hyder Consulting


Internal travel/transport within building
5.2 CABLE BRAND
5.3 CONDUIT PIPING $15 Million
Workers working at height
NETWORK INFRASTRUCTURE 5.4 WIRES INSTALLATION $10 Million Hyder Consulting
5.5 SURVEY $5 Million Escape route from height
5.6 CABLE NETWORK $16 Million Transport of material to such heights
5.7 DESIGN $5 Million Danger of site machinery
on at height