QAQC Forms
QAQC Forms
Note:
This checklist is provided as part of the evaluation and review process for Quality Assurance & Quality Control Plan.
The checklist assists designated reviewers in determining whether specifications meet criteria established in the condition of contract.
The objective of the evaluation is to determine whether the document complies with the contract specifications & methodology requirements.
Attached to this document is the DOCUMENT REVIEW CHECKLIST. Its purpose is to assure that documents achieve the highest standards relative
to format, consistency, completeness, quality, and presentation.
Submissions must include the following three documents, and must be presented in the following order: (First) Document Review Checklist,
(Second) the Construction Quality Assurance and Quality Control Plan Checklist, and (Third) the Construction Quality Assurance and Quality Control Plan.
Organisation: …………………………………………………………………………………………………………………………………………………..
…………………………………………………………………………………………………………………………………………………..
Question YES NO
General
i. Is CQACP signed by the QA/QC manager who prepared the plan?
ii. Is CQACP signed by the senior QA/QC official?
iii. Is CQACP signed by the senior management official(s)?
iv. Does CQACP provide a list of abbreviations used?
v. Does CQACP format comply with Contract Specification?
1
Question (continue) YES NO
Planning
i. Does the CQACP contain an adequate process for planning construction
operations?
ii. Does the CQACP contain an adequate process for providing technical
expertise in sampling, statistics, analytical services and QA/QC?
iii. Does the CQACP contain an adequate process for management to
assess the QA/QC planning process?
iv. Does the CQACP contain an adequate process for preparing, reviewing,
and approving QA/QC project plans?
2
Question (continue) YES NO
Quality Improvements
i. Does the CQACP contain an adequate process for corrective actions
in the organisation?
ii. Does the CQACP identify who confirms the effectiveness of
corrective actions?
3
APPENDIX - 2
Stop Work Authorization Letter
Project Name: ___________________________________________________________________
This Letter of Authorization outlines your responsibility as our Project Quality Assurance & Quality Control
Manager (PQACM) for the project referenced above. As the PQACM, you report directly to the Project
Manager. You review the specifications, addendums and plans in their entirety and implement the Quality
Management Plan. The Project Quality Assurance and Quality Control Plan encompasses three phases of
inspection: Preparatory Meetings and Initial and Follow-Up Inspections. You and/or your staffs (Quality
Assurance & Quality Control Officer - QACO) are responsible for reviewing specifications, submittals, as-builts,
plans and shop drawings for compliance to the contractual requirements.
You and/or your staffs conduct daily audits to ensure that the workmanship and materials used in the
construction of the project are in compliance with the plans, drawings and specifications.
You are authorized to stop work that does not comply with the plans and specifications. You and your staff
must document all non-conforming conditions, items and/or workmanship noted and constantly monitor and
alert Safety personnel to safety violations. If, at any time, you require assistance with the implementation of
the Project Quality Assurance and Quality Control Plan, contact the Project Manager.
________________________________________
Project Director
Shwe Taung Group
Acknowledgements
________________________________________
Project Director
Shwe Taung Development (Junction City Project)
________________________________________
Project Manager
HTCT (Junction Square Extension Project)
4
APPENDIX - 3.1
Non-Conformance Report
Project Name: NCR No.:
Non-Conforming Condition:
Cause of Nonconformity:
Dispositioned by (Site QAQC team - within 7 days of receipt of the NCR): Date:
5
APPENDIX – 3.2
Completed by Accepted by
Item
Description Construction Quality Control
No.
(Sign/Date) (Sign/Date)
6
APPENDIX - 3.3
Contractor: Weather:
4 – Activities in process:
Response:
5 – General comments:
Response:
7 – Prep/Initial Dates (Preparatory and initial dates held and advance notice)
Response:
7
Report Number: Page 2 of 2
CONTRACTOR’S QUALITY CONTROL REPORT (CQCR)
WEEKLY LOG OF CONSTRUCTION Date:
Activity Start/Finish:
QC Requirements:
Contractors/Visitors on Site:
On behalf of the contractor, I certify that this report is complete and correct and all
Contractor
equipment and material used and work performed during this reporting period are in
Certification compliance with the contract, plans and specifications, to the best of my knowledge,
except as noted above.
8
APPENDIX – 3.4
EMPLOYER: CONTRACTOR: ENGINEER/PM:
Project Title: -
MAR. No.
Material Approval Request Revision No. 0
Material Description: Date: 00/00/0000
Package
Material Trade Name: Manufacturer / Supplier:
Attachments :-
1. Samples submitted Yes N/A
2. Original Brochure Yes N/A
3. Other supporting Documents attached Yes N/A
CONSULTANT Comments:
________________________________________________________________________________________________________________
_______________________________________________________________________________________________________________
_______________________________________________________________________________________________________________
_______________________________________________________________________________________________________________
_______________________________________________________________________________________________________________
___________________________________________________________________________________________________________________
Signature:
Name:
Designation: Date:
9
APPENDIX – 3.5
10
Contractor Take Delivery Form
Project Name: Contractor:
Item:
BL No.:
Performa invoice:
Item:
BL No.:
Performa invoice:
Item:
BL No.:
Performa invoice:
Item:
BL No.:
Performa invoice:
Item:
BL No.:
Performa invoice:
Item:
BL No.:
Performa invoice:
Item:
BL No.:
Performa invoice:
Item:
BL No.:
Performa invoice:
Item:
BL No.:
Performa invoice:
Item:
BL No.:
Performa invoice:
Item:
BL No.:
Performa invoice:
Item:
BL No.:
Performa invoice:
11
APPENDIX – 3.6
12
APPENDIX – 3.7
EMPLOYER: CONTRCTOR: ENGINEER/PM:
Date:
Location:
This instruction is hereby confirmed in writing and unless contradicted in writing forthwith shall be
deemed to be an order in writing by the Engineer pursuant to conditions of contract.
Singed for
Date
Engineer/PM:
13
APPENDIX – 3.8 Document Transmittal Form
PROJECT TITLE
Transmittal
Client: Date:
Recipient:
Attention:
SAMPLES
REPORT/TEST RESULTS
1 IR-0000
REMARKS
14