Technical Specification - Conveyor System
Technical Specification - Conveyor System
TECHNICAL SPECIFICATION
FOR
BELT CONVEYOR
CONTENT
1.0 GENERAL
4.1 General
4.2 Proprietary Equipment
4.3 Tests Prior to Delivery
4.4 Tests and Commissioning on Site
4.5 Commissioning
1.0. General
1.1. Scope of Specification
This Specification covers the design, manufactures, construction, inspection, and commissioning
of Belt Conveyor.
The work shall be carried out strictly accordance with:
i) The conditions, requirement, Schedules and drawings contained in the Contract
ii) Any variation and/or modification agreed to by the Principal and the BAMA.
1.2. Specification
The minimum technical requirement for quality and workmanship for design, Materials,
Supply, Manufacture, Assembly, Inspection, Testing, Preparation for Shipment, Erection,
Testing and Commissioning of the Belt Conveyor shall be as set out in the following Standard
Specifications. While the Specification is arranged in sections and clauses, with titles and
headings, the Specification shall be read as a whole and such arrangement, titles, and heading
shall not affect the intention and construction of the Specification. Although some cross-
references have been included to facilitate reading, such cross-references or lack there of shall
not be construed as limiting the application of the Specification as a whole.
are obviously required and necessary for the safe, efficient operation of the plant, then they shall
be deemed to be included as part of the Contract.
All material and or Equipment supplied under the contract, except for installation equipments,
shall be:
• New equipment /material, in good condition and manufactured/fabricated within one
year before the beginning of the contract award.
• Good quality, manufactured/fabricated based on recognized standard, suitable for coal
mining industry application, tropical whether and dust laden condition.
• Approval from the Principal is required prior to fabrication/manufacture of the
equipment/material.
3.2.3. Foundations
Generally all structures shall be supported on isolated, strip or spread footings. Strip
footings shall be used for conveyor trestles.
Isolated footings shall be used for conveyor modules. Isolated or spread footings should
be used for transfer towers, motor control center and control rooms. Piled footings shall
be used where appropriate.
All footing shall be designed to adequately resist all imposed static and dynamic loading
including earthquake loads and provide resistance against overturning. All foundation to
be designed and constructed by the Principals, except anchor bolts and grouting. The
BAMA shall supply and delivered all anchor bolts to site within duration of 90 (ninety
days) from signing of contract
3.2.5. Painting
All structural steelwork, plant, equipment, pipework and platework including walkway
checker plate shall be painted otherwise protected against corrosion in accordance with
this Specification unless exempted herein to approved in writing by the Principal. All
fabricated structural steel. pipework and platework including checker plater shall be
abrasive blast cleaned to Class 2 ½ finish and primed within four hours and before any
surface tarnishing occurs. Any surfaces tarnished shall be reblasted before priming.
Cleaned surface shall be kept free of contamination and not be touched by bare hand.
Any oils, grease or other surface contamination of bare steel or previous coatings shall
be solvent cleaned before applying the next coat. All sheet steel used for electrical
cubicles and panels shall be acid de-scaled and phosphate passivated prior to fabrication.
After surface preparation the following appropriate coating system-1 shall be applied :
Primer coat : inorganic zinc silicate, DFT 50 micron.
Intermediate coat : high build epoxy, DFT 100 micron.
Finish coat : gloss 2 pack recoatable acylic top coat, DFT 50 micron.
Interior surfaces of chutes are to be primed only as for fabricated steelwork. External
surfaces shall be fully coated as for other fabricated steelwork. Refer to company’s
standard specication.
3.3.2. Conveyors
Conveyor belt speed shall be calculated using the following criteria:
• Minimum material bulk density.
• Nominal capacity shall not exceed 90% of the CEMA cross sectional area.
• Surchage angle of 20o.
• If the loading angle is less than or equal to 5° the surcharge angle shall not be
reduced.
• If the loading angle is greater than 5° and less than or equal to 10° the
surcharge angle shall be reduced by 5°.
• Plant conveyors shall not exceed a belt speed of 5 m/s. Conveyor demand
powers shall be calculated using the following criteria:
• Design capacity shall be 110% of the nominal conveyor capacity.
• Power utilisation shall not exceed 97% of the installed motor power at the
design capacity.
Conveyor power and tension requirement shall be calculated based on the
following standard:
• ISO 5048 : Continuous mechanica handling equipment or
• CEMA : Belt Conveyor for BulkMaterial or
• DIN 22101
All conveyor components shall be selected to minimize spare parts requirements and
shall be rationalized for maximum interchangeability. The Principal will require
standardization of pulleys and idlers with components on other plants. All conveyors,
except the portion in the reclaim tunnel, shall be provided with wind hoops over the top
of the conveyor. Rain/wind covers are not required.
a. Belting
The belt width of all conveyors shall be 1800 mm . Type of belt shall be rationalized for
maximum interchangability. Only two type of belt allowed for all conveyor. Belt shall
have 6 x 3 mm grade M covers. Conveyor Belt troughing angles shall be a minimum of
35°. Maximum design tension in any conveyor belt shall be that tension to convey the
maximum design tonnage. Belt tensions at start up or stop shall not exceed 140% of
allowable working tension of the belt. If excessive belt lengthening occurs during the
warranty period, the BAMA shall shorten and replace the belt at its own expense.
b. Idler
Troughing idlers shall be 3 roll type, 152 mm diameter, 6307 ZZ bearing with a
troughing angle of 35° and rigid frame. Graduated adjustable transition idlers shall be
used sufficient to avoid distortion stresses in belt edges and center but in general shall
not less than three idler spaces. Tail transitions shall have the belt line with the pulley.
Spacing of troughing idlers shall be maximum 1500 mm. Under loading skirts, spacing
shall not exceed 750 mm in areas where impact idlers are not installed. Rubber disc
impact idlers shall be used over the length of discharging chutes at loading point at a
maximum spacing of 300 mm. Impact idler frame shall be retractable type for easy
maintenance. Impact idler shall be 3 roll type, 152 mm diameter, 6307 ZZ bearing with
a troughing angle of 35o.
Return idlers shall be 2 roll type, 152 mm diameter, 6307 ZZ bearing with a troughing
angle of 10°. Spacing of return idlers shall be maximum 3000 mm. Idler roller bracket
and base frames shall be hot dip galvanized and shall be slotted to accommodate drop-in
dead shaft type rollers. All bracket slots shall be neat fitting to prevent rattling of
components during operation.
Bearing Type.
Unless specified otherwise, all bearings shall be deep grooved ball bearings with C3
clearances. Both bearings of each roller shall be positively locked to the shaft. Dead
shaft type idler bearings shall be lubricated and sealed for life. Unmodified L10 life of
80,000 hours under design load conditions and full speed.
Sealing Mechanisms
Bearings seals shall shed water and be rain and hose proof. Sealing mechanisms shall
be shielded grease filled bearing inside a dry labyrinth seal, with an external dust seal.
Shafts
Shafts shall be machined from carbon steel to AS 1442 or AS 1443. Shaftdeflection at
the bearings shall not exceed the bearing manufacturer's recommendations under
flooded belt and impact conditions.
Idler manufacture
Idler roller shells and tubes shall be from precision finished Electric Resistance Welded
type to AS 1450 Grade 200 or better. Surface roughness of outside of idler roller shall
not exceed Ra = 12.5 μm. Welds between end discs and shells shall be continuous and
smooth with a minimum corner radius of 3 mm.
Plain steel rollers (excluding weigh idlers) shall be concentric with the shaft to within:
Idler diameter 152 mm TIR < 0.3. Impact idlers rubber covers TIR < 1.0 mm.
Rollers fitted with rubber or plastic discs shall be concentric with the shaft to within 1.0
mm Total Indicated Runout (TIR). Rollers and tubes shall be straight to within 1/1,000.
Idler Static Balance:
• Steel rollers 0.055 N.m or conform to ISO 1740 G 40
• Weigh rollers 0.015 N.m or conform to ISO 1740 G 6.3
c. Pulley
Each pulley assembly shall be heavy duty design supplied complete with shaft, hub
connection, lagging, plummer blocks and bearings located on their respective bearing
housing center and ready for field installation.
Pulleys shall be live shaft type designed for both belt life and pulley life consideration.
Pulley face shall be belt wide + 200 mm and pulley diameters shall be not less than the
published minimum diameter recommended by the belting. Pulley assemblies shall be
designed for unprotected outdoor operation under all weather conditions. Bearing shall
be designed for 60.000 hours life. Pulley bearings shall be double row spherical roller
self aligning type mounted on adaptor sleeve.
All plummer block housings shall be cast iron with split construction and shall be either
SSN 500 or SD series of the four bolt slotted hole type for all shaft diameters. All
bearing housings shall be fitted with a rubbing seal and grease purged labyrinth
(taconite) type seals. Grease nipples shall be fitted for regreasing of the labyrinth seals
only:
Shafts shall be connected to the shell/end discs using Ringfeeder or equivalent locking
assemblies. The oiled condition Ringfeeder assembly rated transmissible torque shall be
not less than 2.0 times the specified peak torque generated by the belt tensions during
starting or braking. Drive pulleys shall be lagged with 12 mm ceramic lagging. Non
drive pulleys shall be lagged with 10 mm diamond grooved rubber lagging. Rubber
lagging shall have a Shore Hardness between 50 and 60. All pulleys shall be live shaft.
Normal internal clearance bearings shall be used.
Bearings shall be fitted such that initial and final clearances are in accordance with the
bearing manufacturer's instructions. Records of bearing installation clearances shall be
maintained and submitted.
Minimum L10 service life of 60,000 hours to AS 2729 under normal full load/full speed
running conditions. Bearings shall be provided with seals which effectively exclude all
dirt, foreign matter, water due to rain or high pressure water hoses and prevent loss of
bearing lubricant. Open ends of housings shall be fitted with synthetic rubber wiper
seals with the lip position such that it prevents entry of grease or injurious material to
the bearing chamber. This wiper seal shall be protected by a multi-labyrinth seal.
The labyrinth shall be positioned to give a grease cavity between the wiper seal and the
labyrinth, i.e. Taconite. Unless otherwise specified 6 mm NPT tapped holes shall be
provided for purging of the labyrinth seals. 8 mm NPT tapped holes shall be provided
for bearing re-greasing but shall be fitted with blank plugs. 'V' ring seals shall not be
used without external sealing to the atmosphere.
Replaceable wear sleeves or plates shall be provided where practical. All seals shall be
Viton type. Bearings less than 25 mm internal diameter may be sealed-for-life type
d. Scraper
All conveyors shall be Conservatively designed to provide an appropriateservice life and
shall incorporate dual scrapers at the discharge (primary and secondary scraper) and V-
ploughs along the return strand of the conveyor prior to tail pulley and vertical gravity
take up.
Primary scraper shall be Belle Banne Flexco H type primary scraper with tungsteen
carbide tip or Martin Heavy Duty (HD type) pre-cleaner with urethane blade. Secondary
scraper shall be Belle Banne Flexco U type secondary scraper with urethane blade or
Martin Secondary Cleaner (DT2S type) with tungsteen
carbide tip. V-plow shall be self adjusting V-plow type. Belle Banne V-Plow or Martin
VPlow with polyurethane blade.
e. Safety guard
Adequate safety guarding shall be provided at all potential danger points as follow:
a) Tail pulley
b) Gravity take ups
c) Rotating part such as fluid coupling and V-belt
In the design of all guards consideration shall be given to the method of attachment to
enable easy and quick removal and replacement for maintenance or other purposes.
f. Take up
Take up shall be automatic gravity type take up except for conveyor less than 40 m, a
screw take up can be used. Screw take-ups shall be of heavy duty, self cleaning type
complete with a rigid welded steel 4 holes base frame, spherical roller bearings housed
in plummer blocks and a protected manually adjustable
positioning concentric screw.
g. Protection Devices
As the minimum requirement, the conveyor shall be equipped with the following
protection devices:
• Underspeed switches
• Belt drift/Belt missalignment switches
• Block chut switches
• Pull wire/rip cord switches
• Take up limit swicthes (upper & lower)
• Belt rip detection switches
• Starting sirens
• Emergency stop buttons near drives
• Brake limit switches
• Fluid coupling thermal detection switch
i. Drive unit
General
Conveyor drive units shall be designed for continuous operation, 24 hours per day. 330
days per year with at least 95 % availability with down time only for schedule
maintenance. All equipment will be required to operate in extremely dirty conditions.
All enclosures shall be capable of withstanding heavy and abrasive dust loads. And
humid, hot and wet ambient conditions.
Drives shall be suitable for a minimum of 6 equally spaced full load starts or stops per
hour. In addition drives shall be designed for 2 consecutive starts under full load
conditions,without damage to the equipment.
Electric motor
Electric motor for less than and including 200kW shall be squirrel cage induction type,
TEFC enclosure, IP 55 enclosure protection, Class F insulation, 1500 rpm and 380 V/50
Hz /3 Phase.
Electric motor for above 200kW shall be squirrel cage induction type, TEFC enclosure,
IP 55 enclosure protection, Class F insulation, 1500 rpm and 3300 V/50 Hz /3 Phase.
Method of starting shall be soft starter for motor above and include 30 kW.
Gear box
Worm reducers are not acceptable. Gearbox bearings shall be ball or roller antifriction
type having a minimum L 10 Life of 60,000 hours based on full load power demand.For
gearboxes fitted .with holdbacks, extended shafts shall be provided to suit the holdback
on both ends of the intermediate shaft. All gearboxes of a similar size to those having
holdbacks shall have extended shafts for interchangeability.
Fluid coupling
Fluid couplings shall be provided on all conveyor drives Incorporating motors of 37kW
and above. Fluid couplings on conveyors shall incorporate a delay chamber and
annularchamber to give a Smooth progressive build up of torque during starting and
Flexible coupling
Flexible couplings may be provided on the gearbox input shaft on all drives less than or
equal to 30kW in size.
Coupling sizes shall be selected such that the power rating required by theoupling is
determined on the same basis as that used for the gear unit with which it is to operate.
Where couplings are fitted with seal, these shall suitablefor a mildly abrasive dust laden
atmosphere. All coupling shall be fitted with guards. Non lubricated coupling are
preferred.
Brake
Brakes shall be provided on conveyors where excessive drifts are acountered or where
conveyors have different stopping times during emergency shutdown and there is the
possibility of material build up at the transfer station.
All brakes shall be fail safe type with sufficient energy dissipating and shall be installed
on the reducer high speed shaft or directly onto the pulley shaft. Brakes shall be electro-
hydraulic thruster release. Brake pads shall be asbestos free and brake disc shall be
stainless and dynamically balanced.
Holdback
Holdbacks shall be used to prevent roll back of conveyors. Holdbacks shall be installed
when the force required to lift the material on the conveyor (based on maximum design
capacity as shown on the flowsheet) is greater than the friction force required to move
the belt and material horizontally. The friction force shall be calculated friction factor of
0.012.
carriage. The weigh zone (which includes both the scale and lead in/out machined
idlers) shall be located at least 15 m from the loading
point of the conveyor and at least 15 m from the tangent point of any vertical
curve in the conveyor or as recomended by the manufacturer.
3.3.8. Skirt
Skirt plates shall be provided as an extension of the sides of the loading trough and
extend parallel to one another for at least 1.2 m for 1.0 m/s belt speed and minimum
three (3) meters past the discharge point. Sealing strips shall not be used with the
standard chute/trough arrangement.
In the situation .where loading troughs cannot be adopted, skirt plates shall incorporate a
sealing arrangement of the hand operated clamp type with skirt rubbers easily adjustable
to compensate for wear without the use of tools. Skirt rubbers shall be adjustable and
renewable from the outside of the chute and
shall be FRAS neoprene without fabric or fiber reinforcement. Rubber seals shall be
12mm thick (minimum) and 250 mm wide with a shore durometer hardness between 45
and 55. The minimum skirt plate thickness shall be 6 mm. The skirt boards shall be
covered, and not more than two-thirds the belt width apart. The height shall be
determined by the burden cross section but shall be not less dm 450 mm. Skirt boards
shall be fully enclosed to contain dust.
3.4.2. General
The BAMA shall be responsible for the complete design, supply,installation, and
commissioning of the electrical and control system for coal handling facility, including
design, supply, install and commission the power supply for the plant from the generator
set house. This Specification defines the specific requirements of that system. All
materials and equipment supplied under this Contract shall be new and of the highest
quality. All materials and equipment, the electrical design and the installation shall be in
accordance with the relevant codes and standards and the project specifications as listed
in this Specification.
3.4.3. Transformer
Hermetically sealed transformer tanks shall have flexible corrugated or folded walls and
a completely welded construction. The tank, cover and cooling system assembly shall
have the mechanical strength to withstand without any permanent distortion, the internal
pressures caused by the contraction or expansion of the oil/liquid and gas volumes under
the specified service conditions.
The tank material shall be made as far as possible of Hot Dip Galvanised steel - or, for
large size transformers, coated with a Zinc-ethyl-silicate primer - with a coating adapted
to the environment (salt laden marine environment, corrosive environment, etc.).
For special offshore application-Stainless steel 316 L can be used for tank material, but
it will require prior the Principal approval. The tank shall be mounted on a base frame.
The tank cover shall be designed to prevent the water accumulation. The tank, cover,
valves and all accessories shall be hermetically sealed against air, water and insulating
oil.
3.4.7. Earthing
Earthing grid shall be supplied and installed by the BAMA. A combined earthing system
shall be used. The BAMA shall connect this earthing to the MCC earth. The earth grid
shall have a resistance not exceeding 2 ohm which refer to AI-E01.
Electrical design shall take this into account, particularly with respect to the limitation of
step and touch potentials. Adequate bonding earths shall be installed to meet these
requirements.
• the MCC shall be fixed type, compartementalized design, dust and vermin
proof type with IP-54 enclosure protection. It shall be free standing floor
mounted type made of 14/16 SWG steel sheet with epoxy and polyester powder
polymerized painted at high temperature.
• Internal wiring shall be done with 1.5 mm2 PVC insulated wire up to terminal
block.
• Refer to AI-E04
fuel tank, etc. shall be provided with adequate lighting. The complete plant must be
adequately lit so safe operation is possible
around the clock.
3.4.18. PLC
3.4.18.1. PLC Networking Cables
The PLC network cables shall be classified as instrumentation cables. The
cables shall be installed separate to power and control cables, i.e. Separated by a
barrier and installed with other instrumentation cables.
The network cables shall be installed to the BAMA design requirements. Space
shall be allowed in all cable ladder and trenches for the installation of these
cables. Prior to installation of cable ladder covers
or backfilling of trenches, inspection by the Principal shall be requested. Cable
tests may be carried out by the BAMA, prior to backfilling of trenches or
installation of cable ladder covers. Where installed in cable ladder, these cables
shall be bundled together and cable tied at the upper edge of the cable ladder. A
barrier shall be
BELT CONVEYOR SPECIFICATION
May 2012 Page 27 of 38
installed to separate these and other instrumentation cables from power/control
cables. The Principal accepts that these cables may need to be installed
underground for some of the cable route. Where installed underground these
cables shall be installed collectively in a 100 mm PVC conduit. The conduit
shall provide complete protection to the cables and shall be equipped with a
draw wire for future installation.
c. Hardware
The PLC hardware supplied by the BAMA shall be in accordance with the
following specification. The BAMA shall supply and install the PLC in an IP52
free standing cubicle. The PLC input/output
General
The PLC hardware shall embrace the latest available technology, be robustly
constructed, simple to assemble and wire, expendable and accessible for
maintenance and fault finding. The requirement for
component redundancy shall redundancy as specified in the scope of work
Central Processor
Each PLC shall have its own central processor. The shall communicate with the
network via an interface and with each PLC module. The Following minimum
functions are required:
- solving logical statement and ladder rungs.
- processing integer and floating point maths;
- timers, counters and shift registers;
- P.I.D. computations;
- Boolean logic.
- 1/0 can be forced.
- RS 232 interface;
- facility for connection of portable programming unit;
- on line programme changes;
- programming and monitoring access security system using keylock or
passwords;
- scan time not to exceed 50 milliseconds;
- non-volatile RAM memory for programme.
- processor self diagnostics and diagnostics for I/0 modules:
- the detection of internal faults or loss of C.P.U. power shall cause all
outputs to go to 'fail safe' normally (de-energized mode) and, will
alarm condition.
The latest revision of firm ware shall be provided up to the end of the contract
Period. Where remote Input/Out put are used, the facility to plug in a portable
programming terminal shall be provided at the
remote Input / Output location. This shall allow monitoring and programming
PLC of the processor from this location.
Input/Output Modules
Input and output modules shall be of the plug in type, easily removable for
Replacement. They shall be optically isolated to a minimum of 3000 volts.
L.E.D. status indicators shall be provided for each input and output. If internal
fusing is provided in the modules then blown fuse indicators are also required.
The modules shall be keyed, to prevent modules of differing voltages or
functions being accidentally interchanged. The modules shall be replaceable
without de-energizing the equipment.
The maximum loop length of circuits capable of being connected to each type
of module shall be stated at the time of tender. Minimum cabling requirements
shall also be specified. Input modules shall have the following features and
ranges:
• 12 – 24V DC
• 5V D.C.
BELT CONVEYOR SPECIFICATION
May 2012 Page 26 of 34
• 4 - 20mA, 0 - 20mA
• 1 - 5V DC, 0 – 10V DC
• BCD inputs
• Thumb wheel inputs
• Pulse input modules.
Output modules shall have the following features and ranges:
• 12 - 24V DC
• 5V DC TTL
• 4 - 20mA , 0 - 20mA
• 1 – 5V DC, 0 - 10V DC
Digital outputs shall be rated at 2A for resistive loads and IA for inductive
loads, at full module loading.
Standard analogue input/output signals shall be 4-20mA. All new control
system shall incorporate 110V AC control voltage and 24V DC for low level
PLC input/output signals and instrumentation signals.
All outputs shall be direct connected, i.e. two wire. The use of interposing
relays shall only be acceptable where the substation or field load exceeds the
module output current rating.
Input Output
Control circuits and the associated input/output connections shall be designed to
take into account the specifications of the PLC hardware and PLC software
capabilities.The completed design and a PLC hardware list (with signal voltages
and levels) shall be forwarded to the Principal, who will review and
approve the selection
Wiring
The BAMA shall provide the PLC and associated terminal strips complete,
installed in a cubicle. The cubicle shall be complete with entries for connection of inter
panel wiring to the marshalling panel. The BAMA will cable and connect
between the PLC input/output modules and the PLC terminal strips. These cores
will be ferruled in accordance with the BAMA connection schedule or
termination
drawings. It shall be the BAMA responsibility to connect the panel wiring
between the substation marshalling panels and the PLC terminal strips. These
cores shall be correctly ferruled.
Field or MCC analogue input/output shall be directly connected to the
respective PLC input/output module. These cables shall not go through the
marshalling panels.
b. Software Functionality
Mechanical, electrical and process equipment software shall be designed to
ensure correct plant operation in accordance with this Specification. To ensure
correct plant operation, the PLC software controlling sequential, process, alarm,
and supervisory logic must be correct. The BAMA shall develop the
requirements and methodology of the plant operation. This "plant operational
description" shall be in a combination of written text and block diagram or logic
diagram format. It shall include an alarm list and a list of the input/outputs and
data, requiring transfer to the operator interface system. This description shall
be given to the Principal for review and comment.
The BAMA shall develop a functional specification which shall define:
• a functional description of the plant operations
• sequence diagrams - auto start up, auto shut-down and fault trip shut-
down
• a breakup of the proposed programme structure into blocks
• description of each programme block
• alarm list and input/output list.
This functional specification shall be reviewed and approved by the Principal
prior to the commencement of the software development. Areas of the
functional specification may be altered upon reviewing and any changes shall
be clearly documented. If the changes are excessive it may be necessary for the
BAMA to forward the revised functional specification for re-approval. The PLC
software
functionality and input/output list shall be deemed final at this stage, and the
BAMA shall begin development of the software.
c. Software Development
Development of the PLC software shall be completed by the BAMA.
3.4.18.4. Operator Interface System
a. General
The PLC network shall be monitored: and controlled via control panelsin the
control room. The control panels shall be supplied and installedby the BAMA.
The following minimum components in control panel are required:
• mimic panels
• pushbuttons and switches
• gauges
• potentiometers
• enunciator lights
• acknowledge and reset pushbuttons
• enunciator buzzer.
The control panels shall be directly connected to the PLC only The control
panel shall be designed and manufactured to control and monitor all equipment
as specified in the Scope of Work or the Principal Requirement, or as directed
by the Principal. In addition to the emergency stops required in the field, one
emergency stop shall be provided in each control room. This shall be mounted
on the control panel. The emergency stop shall be hardwired to the appropriate
control circuit(s). The emergency stop shall be fitted with a clear hinged lid to
prevent accidental operation.
In control room the following displays/indication shall be provided for the
operator:
Operator Controls
• drive stop/start
• drive group stop/start
• selection switches
Drive Status
• running/stopped
• motor current
• drive or drive group ready
• magnet status
Alarms
• motor thermal overload trip
• motor thermistor trip
• pullwire switches
• belt alignment switches
• underspeed switches
• position limit switches
• blocked chute
• pressure/temperature/flow alarms
Analogue Variable
• motor current
• pressure/temperature/flow
b. Functionality
a. General
All devices shall be of a heavy duty type, of proven design, suitable for
theapplication. The device housing shall be metallic construction.
c. Underspeed switch
Proximity type underspeed switches shall be used. The remote evaluation unit
shall be installed in the associated drive M.C.C. cubicle or a general control
marshalling cubicle. Alternatively, the evaluation shall be performed in the
P.C.L.
e. Warning Devices
All warning devices shall be weatherproof. Sirens shall be used as start up
warning devices for conveyors. All other warning devices shall be horns. A
warning device with switch adjustable modes and tones shall be supplied.
h. Local Isolators
Unless otherwise stated, all motors shall be fitted with a lockable local
isolator.The isolator shall be of the full-load current break type, fitted with early
breakand late make auxiliary contacts. This should form part of the local control
station.
i. Solenoid Valves
Unless otherwise specified, solenoid valves shall be brass body, soft seating
general purpose type with epoxy resin encapsulated 110V AC, 50 Hz, coil, in a
weatherproof enclosure.
representative, who shall then present the proposed commissioning procedure for implementation
by the BAMA.
The BAMA shall integrate the testing and commissioning of the equipment items with the
overall plant commissioning program and shall be responsible for carrying out all the
recommended procedures as directed by the manufacturer of the equipment. The BAMA shall
arrange for a representative of the manufacturer to be on-site during commissioning to direct the
BAMA staff through the appropriate procedures and make any necessary
adjustments/modifications to ensure the equipment operates
satisfactorily.
Allowance shall be made for the appropriate staff to be made available to carry out such
adjustments/modifications as deemed necessary. Any carnage or materials necessary to adjust or
modify the equipment during commissioning will be supplied by the BAMA as part of this
Contract.
prepared by the manufacturer and accepted by the Principal. Those procedures will be the basis
for commissioning and testing of the equipment and the BAMA shall support those procedures
on site.
The BAMA shall carry out tests as specified to show correct assembly and erection of the plant.
Adequate notice shall be given to the Principal that each piece of plant is ready for testing,
including the adjusting and setting of all limit switches, indicating lights, signals and other
protective devices.
Testing specifically required by the manufacturer in installation instructions shall be performed
after the inspection and approval of the installation by the manufacturer's engineering
representative. During conveyor belt tracking, if idlers are moved from right angles to the
conveyor center line, they shall be clearly marked and shall be returned to their right angle
alignment before testing of belt tracking is completed.
Each feeder and conveyor shall be tested under local control and all necessary adjustments made
to ensure it is in a safe operating condition. Conveyors shall be run empty for a period of not less
than four hours after alignment of components and training of the belt.
Feeders shall be run empty for a period of not less than four hours. Starting time, stopping time,
noise levels, bearing temperatures, and motor amp reading shall be recorded as applicable.
After all equipment has been run individually to the satisfaction of the Principal, it shall then be
operated continuously in groups as directed by the Principal under no load conditions, and
normal operating sequence control from the control centers appropriate to the operating sections
of the plant. 2 x 12 hours of continuous and uninterrupted operation of each complete section
shall be attained.
The operation is deemed uninterrupted operation if:
a. Number of interruption is less than 6 time over the 12 hours operation with single
interruption time less than 5 minutes and
b. Total interruption time over the 12 hours operation is less than 30 minutes.
During this period, all motions and all devices shall be tested in the presence of and to the
satisfaction of the Principal or its representative. If any equipment or device in any section
proves unsatisfactory in the opinion the Principal, the BAMA shall effect rectification of each
fault or faults, and a further uninterrupted trouble free period of 2 x 12 hours operation of such
section shall be attained before commissioning may
proceed.
4.5. Commissioning
The BAMA shall demonstrate the correct operation of all items of plant up to the design
maximum and shall make such adjustments as required to ensure operation of the plant,
according to this Specification and the satisfaction of the Principal. During such commissioning,
the BAMA shall demonstrate that the required rates are as specified in this Specification. If such
requirements are not attained, then the BAMA shall make such adjustments as are necessary, and
the entire operation shall be repeated until the specified rates is attained in three complete and
uninterrupted twelve hour periods of operation. After completion of such throughput tests, all
equipment shall be washed down and otherwise cleaned of coal, and all faults shall be rectified.
The entire equipment shall then be operated under no load for an uninterrupted period of four
hours.
The BAMA shall keep proper records of the commissioning of each section of the Plant,
including the load currents of every motor. Where load or speed variations occur, recordings
shall cover the complete variations. A Practical Completion Certificate for the plant will only be
issued following successful completion of all commissioning procedures and acceptance by the
Principal.
The operation is deemed uninterrupted operation if:
a. Number of interruption is less than 6 time over the 12 hours operation with single
interruption time less than 5 minutes and
b. Total interruption time over the twenty-four hours operation is less than 30 minutes.
c. The plant has reach nominal capacity as specified.