Pgcil Final Report 1
Pgcil Final Report 1
04.06.2019 to 04.07.2019
ON
765/400KV SUBSTATION, LUCKNOW
POWER GRID CORPORATION OF INDIA LIMITED
SUBMITTED BY
ABHISHEK CHAURASIA
ELECTRICAL ENGINEERING (4th sem)
ROLL NO- 2K17/EE/008,
DELHI TECHNOLOGICAL UNIVERSITY,
DELHI.
ABHISHEK CHAURASIA
ELECTRICAL ENGINEERING
(4thsem)
ROLL NO -
2K17/EE/008
DELHI TECHNOLOGICAL UNIVERSITY,
DELHI.
INDEX
Abstract
About PWERGRID
765KV /400KV Remote operated Sub –Station
765 kV Major Equipmentsand Switchyard diagrams
SCADA System ( Supervisory Control And Data Aquisition/ SAS(Substation
Automation System)
Protection Relays
Single Line Diagram of 765/400kV
Power Line Carrier Communication PLCC
Auxiliary Supplies
Sub –Station Equipment
Current Transformer (CT)
Capacitive Voltage Transformer (CVT)
Inter Connecting Transformer (ICT)
Circuit Breaker
Isolator
Lightening Arrester (LA)
Wave Trap
Shunt Reactor
Conclusion
ABSTRACT
The 765/400 kV new substation is full automatic Remote Operated substation which is being
operate from 400/220 kV Lucknow substation Control Room.
In this substation total 9 Bays of 765 kV side and these are like 765kV Lucknow-Balia Line-
(Connected bay nos 701 & 702), second is 765 kV Lucknow-Bareilly Line connected to bay
nos 707 & 708.
In 765kV side there are two single phase 3x80=240 MVAR line reactor connected to
Lucknow-Balia & Lucknow Bareilly Lines , one is single phase 3x80 MVAR bus reactor
which is connected to 765 kV Main Bus-II in bay no 709. There are two ICT of (single phase)
1500 MW each capacity and one is spare transformer single phase of 500 MVA capacity. In
this substation 400 kV side total 12 bays .
1- 400 kV Lucknow-Lucknow Line -1
2- 400 kV Lucknow-Lucknow Line -2
3- 400 kV Lucknow-Kanpur Line -1
4- 400 kV Lucknow-Kanpur Line -2
In this side also a 125 MVAR bus reactor which is connected to bay no 407.
VISION World Class, Integrated, Global Transmission Company with Dominant Leadership in
Emerging Power Markets Ensuring Reliability, Safety and Economy.
MISSION We will become a Global Transmission Company with Dominant Leadership in Emerging
Power Markets with World Class Capabilities by:
World Class: Setting superior standards in capital project management and operations for the
industry and ourselves
Global: Leveraging capabilities to consistently generate maximum value for all stakeholders in India
and in emerging and growing economies.
Inspiring, nurturing and empowering the next generation of professionals.
Achieving continuous improvements through innovation and state of the art technology.
Committing to highest standards in health, safety, security and environment
OBJECTIVES: The Corporation has set following objectives in line with its mission and its status
central Transmission Utility to:
This was the first 765kV Line energized on 28.02.2012in the Northern Region
and second line in POWERGRID.
TRANSMISSION LINES
ASSOCIATED WITH 765/400kV LUCKNOW SUBSTATION
S. Line Length
Name of the Transmission Line
No. (in Kms)
1 765kV S/C Ballia-Lucknow Line 319
The GPS time synchronising signal for the synchronization of the entire system BCUs and IEDs
REMOTE MODE: Control authority in this mode is given to a higher level (Remote Control
Centre) and the operation can be controlled only remotely. Control operation from lower levels shall
not be possible in this operating mode.
BCUFunctions: BCU is capable of acquiring analog input values like, Active power, Reactive Power,
Current, Voltage and frequency, power factor, KWh , kvarh( having output as 4-20 mA, 0-10 mA, 0-+10
mA using analog input modules.Acquiring analogy values from the status inputs of devices from the
substation, processing and transmitting to substation control centre and remote end control centre. Receiving
and processing digital commands from the .control centreTheoperation of BCU (Bay Control Unit) high-
voltage apparatus within the station is possible from different places:
Only one operator at a time can operate the BCU. In EMERGENCY Operation It is be possible to close or
open the selected Circuit Breaker with ON or OFF push buttons even during the outage of bay IED(BCU) .
Bay protection functions The protection functions are independent of bay control function. The
protectionis provided by separate protection IEDs numerical relays and other protection devices Relay &
ProtectionIEDs All IEDs . connected to the communication infrastructure for data sharing and meet the real-
time communication requirements for automatic functions. The data presentation and the configuration of the
various IEDs are compatible with the overall system communication and data exchange requirements
The position of each switchgear, e.g. circuit breaker, isolator, earthing switch, transformer tap changer etc.,
ssupervise continuously. Every detected change of position immediately displayed in the single-line diagram
on the station HMI screen, recorded in the event list and Alarms initiated in the case of spontaneous position
changes.
Remote Control Centre (SCADA)
IEC 60870-5-101
PACiS OI Client
PACiS OI Server
BCU
SBUS IEDs
SYSTEM ISA : set of devices with specific functions that interact one to/with other with common rules.
System is COMMUNICATION & CONFIGURATION
SBUS Station BUS (system federal network)
In the above digram different IEDs are connected in FO Cable ring. OI Server collect information from IEDs
and provide to OI Client for display/view to operator workstation
PROTECTION RELAYS:
D-BusBar Protection
1.LBB Protection.
2.Bus bar Pprotection
NOTE: DEF-Directional Earth Fault, REF-Rectricted Earth Fault, SOTF-Switch On To Fault. LBB-Local Breaker
Backup
It is clear that three circuit breakers are used in one dia between the two busbars, Bus 1 and Bus 2 for two circuits
emerging out of it. Two such dia are shown in the figure. Following advantages are associated with this type of bus bar
arrangement
1- The supply is not interrupted in the event of fault on a bus as either of the bus can be used to maintain supply
and keep the feeders (or transmission lines) charged.
2- The supply is not interrupted in the event of any fault on a circuit breaker.
3- Possibility of addition of circuits is always there.
Main SLD of 765/400 kV: Upper portion of SLD is 765 kV side. Total Bays are 9 from 701 to 709. 701(Main) &
702(TIE) Bays are of Lucknow-Balia Line, 707(Main) & 708(TIE) Bays are of Lucknow-Bareilly Line and 704(Main)
& 705(TIE) Bays are for future line.Total TIE Bays are 702, 705 & 708
Lower portion of the SLD is of 400 kV side. Total Bays are 12 from 401 to 412. Bay no. 402(TIE) & 403(Main) of
Lucknow-Lucknow line-2, Bay no. 405(TIE) & 406(Main) of Lucknow-Lucknow Line-1, Bay nos 408(TIE),
409(Main) for Lucknow Kanpur Line-1 & 411(TIE), 412(Main) for Lucknow Kanpur Line -2
line. Total TIE Bays are 402, 405, 408 & 411.
System Architecture of 765/400 kV provide the information of connected relays in the whole substation.
Green Relays/BCU indicate healthy position of its. Red indication of its means Relay/BCU is not
communicating with SCADA. Upper portion of this architecture is of 765kV and divided in three parts/kiosk
and lower portion of its is of 400kV and divided in four parts means four kiosk system. All kiosks are
connected to each other with Fibre Optical (FO) cable ring.
FO Cable start from 765kV Control Room to 765 kiosk-1 to 765kV kiosk-2 to 765kV kiosk-3 to 400kV
kiosk-1 to 400kV kiosk-2 to 400kV kiosk-3 to 400kV kiosk-4 to 765kV Control Room. In the kiosks FO
cable is connected with the help of LIU (Line Interface Unit). LIU communicate with EFS (Ethernet Fibre
Switch).
In 765/400kV S/S, 400kV Lucknow-Lucknow Line-2: Bay no 403 is main Bay and 402 is TIE Bay. Bay
no 401 is for future bus reactor.
In 765/400kV S/S, 400kV Lucknow-Lucknow Line-1: Bay nos 406 is main Bay and 405 is TIE Bay. Here
404 is main Bay of ICT-1
Power Line Carrier Communication PLCC
The power line carrier communication equipment required is to provide primarily efficient,
secure and reliable information link for carrier aided distance protection and direct tripping of
remote-end breaker and also for speech communication between 220/400/765 kV sub-stations.
It includes carrier terminals of multipurpose type for speech and protection. All carrier
terminals including those for protection, suitable for point to point speech communication also.
PLCC use Amplitude Modulation and has single side band transmission mode.
Mode of transmission Amplitude Modulation single side band with suppressed carrier
or reduced carrier frequency 40to 500kHz range.
Nominal carrier frequency 4.0 kHz band in either direction of transmission
Supply voltage48 V DC +15%, -10% Positive pole earthed
SPEECH COMMUNICATIONPLC equipment provide telephone communication
between the
stations where the transmission lines are terminating. It is possible for subscriber at any
of the stations to contact the subscriber at all other stations connected in the system by
dialing his call number.
A) High Frequency Cable: High frequency cable connects to the PLC terminal installed
indoorto the coupling device which installed in the switchyard.
B) Line trap/ wave trap
Cconform to latest IEC 60353 fulfilling all the technical requirements.
The rated short time current for 1Second should be 63/50/40/31.5 kA as per
requirement.
The mH. Rating should be 1.0/0.5/0.25mH depending on frequency plan.
The Line Trap shouldbe suitable for outdoor pedestal or suspension mounting
andshould be mechanically strong enough to withstand the stresses due to
maximum wind pressure of 260kg/square meter
For pedestal mounting, each line trap mounted on a tripod structure formed by
three insulator stacks arranged in a triangular form. All the accessories and
hardware, mounting stool including bolts for fixing the line trap on
insulatorsshould be of non-magnetic material.
C) Lime Matching Unit(LMU)The modular coupling device MCD80, it is mounted in
switchyard near CVT together with the coupling capacitor and line trap basically fulfill
the following functions:
Insertion and extraction of PLC signals on high voltage overhead lines and cables.
Through connection and distribution of PLC signals in intermediate stations.
Impedance matching between transmission path and PLC equipment.
Potential separation of high voltage equipment and PLC equipment.
In addition to reliable protection of personnel and communication equipment,
maximum emphasis was also placed on low insertion loss for the coupling of the
PLC signals on the transmission line.
Reliable
AUXILIARY SUPPLIES
AC SOURCE :
Source-1 (33kv /415v) from UPPCL Lucknow
Source -2 ( 33 kv /415v) from ICT-2 as a T-3
In case of loss of auxiliary supply, the emergency power backup system, which is a diesel-generator set,
starts automatically. This generator can provide power continuously for 5 hours.
DC SOURCE:
Each DC Source charged by separate chargerby 220V and 48 volt separate chargerrespectively.
In the Battery room Battery Banks are installed which provide D.C. supply for the sub-station DC.
Equipment operation D.C. Supply is required for the operation of the relay in the control panel and
for the operation of PLCC. There are four battery banks, two for 220 V supply (one primary and
other backup) and for 48 V supply. Each 220 V Lead - Acid battery bank comprises 110 cell of 2.2
V each. Capacity of the battery banks is 600AH. Float or trickle charging is used for the batteries
i.e. batteries are charged under no load at a ratio equal to their self-discharge rate. Any battery
or cell is allowed to discharge to value 80% of the full charge , i.e., the cell is allowed to
discharge only of 20% of its maximum voltage.
Aux Power Supply SLD
Current Transformer
CT provide 1 Ampere at secondry with respect to primary of 3000A or 2000A or 1000A
The CVT is also useful in communication systems. CVTs in combination with wave traps are
used for filtering high frequency communication signals from power frequency. This forms a
carrier communication network throughout the transmission network.
Interconnecting Transformer (ICT)
In 765/400 kV Lucknow substation, there are two ICTs and both are single phase of
500 MVA each auto transforfer and capacity of each ICTs 1500 MVA.
A transformer is a device that transfers electrical energy from one circuit to another through
inductively coupled electrical conductors. A changing current in the first circuit creates a
changing magnetic field; in turn, this magnetic field induces a changing voltage in the second
circuit. By adding a load to the secondary circuit, one can make current flow in the transformer,
The secondary induced voltage VS, of an ideal transformer, is scaled from the primary VP by a
factor equal to the ratio of the number of turns of wire in their respective windings. By
appropriate selection of the numbers of turns, a transformer thus allows an alternating voltage
Interconnecting transfomers are used to connect two EHV line at different voltages . The
interconnecting transformer are auto transformer which can step up & step down the voltages
for synchronization of two grid voltages.
Generation of Electrical Power in low voltage level is very much cost effective. Hence
Electrical Power are generated in low voltage level. Theoretically, this low voltage leveled
power can be transmitted to the receiving end. But if the voltage level of a power is
increased, the electric current of the power is reduced which causes reduction in ohmic or I 2R
losses in the system, reduction in cross sectional area of the conductor i.e. reduction in
capital cost of the system and it also improves the voltage regulation of the system. Because
of these, low leveled power must be stepped up for efficient electrical power transmission.
This is done by step up transformer at the sending side of the power system network. As this
high voltage power may not be distributed to the consumers directly, this must be stepped
down to the desired level at the receiving end with help of step down transformer. These are
the use of electrical power transformer in the Electrical Power System.
The oil cools the transformer, and provides part of the electrical insulation between internal
live parts. It has to be stable at high temperatures so that a small short or arc will not cause a
breakdown or fire. To improve cooling of large power transformers, the oil-filled tank may
have radiators through which the oil circulates by natural convection. Very large or high-
power transformers (with capacities of millions of watts) may have cooling fans, oil pumps.
Oil transformers are equipped with Buchholz relays.
.
CIRCUIT BREAKER
A circuit breaker is an automatically operated electrical switch designed to protect an
electrical circuit from damage caused by overload or short circuit. Its basic function is to detect
a fault condition and, by interrupting continuity, to immediately discontinue electrical flow.
Unlike a fuse, which operates once and then has to be replaced, a circuit breaker can be reset
(either manually or automatically) to resume normal operation. Circuit breakers are made in
varying sizes, from small devices that protect an individual household appliance up to large
switchgear designed to protect high voltage circuits feeding an entire city.
The circuit breaker must detect a fault condition; in low-voltage circuit breakers this is usually
done within the breaker enclosure. Circuit breakers for large currents or high voltages are
usually arranged with pilot devices to sense a fault current and to operate the trip opening
mechanism. The trip solenoid that releases the latch is usually energized by a separate battery,
although some high-voltage circuit breakers are self-contained with current transformers,
protection relays, and an internal control power source. Once a fault is detected, contacts within
the circuit breaker must open to interrupt the circuit; some mechanically-stored energy (using
something such as springs or compressed air) contained within the breaker is used to separate
the contacts, although some of the energy required may be obtained from the fault current
itself. Small circuit breakers may be manually operated; larger units have solenoids to trip the
mechanism, and electric motors to restore energy to the springs.
The circuit breaker contacts must carry the load current without excessive heating, and must
also withstand the heat of the arc produced when interrupting (opening) the circuit. Contacts
are made of copper or copper alloys, silver alloys, and other highly conductive materials.
Service life of the contacts is limited by the erosion of contact material due to arcing while
interrupting the current. Miniature and molded case circuit breakers are usually discarded when
the contacts have worn, but power circuit breakers and high-voltage circuit breakers have
replaceable contacts. When a current is interrupted, an arc is generated. This arc must be
contained, cooled, and extinguished in a controlled way, so that the gap between the contacts
can again withstand the voltage in the circuit. Different circuit breakers use vacuum, air,
insulating gas, or oil as the medium in which the arc forms.
Bulk oil
Air blast
Vacuum
SF6
In 765/400 sub-station of PGCIL, the circuit breakers used are of SF6 type only, due to
the nature of high rating lines
SF6 has excellent insulating strength because of its affinity for electrons (electro negativity)
i.e. whenever a free electron collides with the neutral gas molecule to form negative ion, the
electron is absorbed by the neutral gas molecule. Sulfur Hexafluoride (SF6) is an excellent
gaseous dielectric for high voltage power applications. It has been used extensively in high
voltage circuit breakers and other switchgears employed by the power industry. Applications
for SF6 include gas insulated transmission lines and'gas insulated power distributions. The
combined electrical, physical, chemical and thermal properties offer many advantages when
1. The current chopping tendency is minimized by using the gas sf6 at low pressure
2. The closed circuit gas cycle and low velocity operation eliminates the moisture
3. Because of the outstanding arc quenching properties of sf6, the arcing time is small,
6. Electrical clearances are drastically reduced due to high dielectric strength of SF6.
An isolator switch is part of an electrical circuit and the switch isolates circuits that are
continually powered or is a key element which enables an electrical engineer to safely work
In some designs the isolator switch has the additional ability to earth the isolated circuit
thereby providing additional safety. Such an arrangement would apply to circuits which inter-
connect power distribution systems where both end of the circuit need to be isolated.The major
difference between an isolator and a circuit breaker is that an isolator is an off-load device,
Lightning has been a source of wonder to mankind for thousands of years. Some of the
accepted facts about thunder cloud and lightning phenomenon:
1. The height of the cloud base above the surrounding ground level may vary from 500
to 30000 ft. the charged centers which are responsible for lightning are in the range of
1000 to 5000 ft.
2. The maximum charge on a cloud is of the order of 10 coulombs which is built up
exponentially over a period of perhaps many second or even minutes.
3. The maximum potential of a cloud lies approximately within the range of 10 MV to
100 MV.
4. The energy in the lightning stroke may be of the order of 250 KWHR.
The current in the streamer is of the order of 100 ampere and the sped of the streamer is
0.5ft./microsecond. This streamer is known as pilot streamer because this leads to the lightning
phenomenon. Depending upon the state of ionization of the air surrounding the streamer, it is
branched up to several paths and this is known as a stepped leader. The leader steps are of the
order of 50 m in length and are accomplished in about a microsecond. The charge is brought
from the cloud through the already ionized paths to these pauses. The air surrounding these
pauses is again ionized and the leader in this way reaches the earth.
(i) Under normal operation, the lightning arrester is off the line i.e. it conducts no current to
earth or the gap is non-conducting
(ii) On the occurrence of over voltage, the air insulation across the gap breaks down and an arc
is formed providing a low resistance path for the surge to the ground. In this way, the excess
charge on the line due to the surge is harmlessly conducted through the arrester to the ground
instead of being sent back over the line.
WAVE TRAP
It is connected in series with the power (transmission) line. It blocks the high frequency carrier
waves (24 KHz to 500 KHz) and let power waves (50Hz - 60Hz) to pass through. It is basically
an inductor of rating in millihenry.
It is used for trapping the high frequency communication signals sent on the line from the
remote substation and diverting them to the telecom/teleprotection panel in the substation
control room (through coupling capacitor and LMU).
This is relevant in Power Line Carrier Communication (PLCC) systems for communication
among various substations without dependence on the telecom company network. The signals
are primarily teleprotection signals and in addition, voice and data communication signals.
Line trap also is known as Wave trap. What it does is trapping the high frequency
communication signals sent on the line from the remote substation and diverting them to the
telecom/teleprotection panel in the substation control room (through coupling capacitor and
LMU). This is relevant in Power Line Carrier Communication (PLCC) systems for
communication among various substations without dependence on the telecom company
network. The signals are primarily teleprotection signals and in addition, voice and data
communication signals.
The Line trap offers high impedance to the high frequency communication signals thus
obstructs the flow of these signals in to the substation busbars.
SHUNT REACTOR
The need for large shunt reactors appeared when long power transmission lines for system
voltage 220 kV & higher were built. The characteristic parameters of a line are the series
inductance (due to the magnetic field around the conductors) & the shunt capacitance (due to
the electrostatic field to earth). Both the inductance & the capacitance are distributed along
the length of the line. So are the series resistance and the admittance to earth. When the line
is loaded, there is a voltage drop along the line due to the series inductance and the series
resistance. When the line is energized but not loaded or only loaded with a small current,
there is a voltage rise along the line (the Ferranti-effect).In this situation, the capacitance to
earth draws a current through the line, which may be capacitive. When a capacitive current
flows through the line inductance there will be a voltage rise along the line.
To stabilize the line voltage the line inductance can be compensated by means of series
capacitors and the line capacitance to earth by shunt reactors. Series capacitors are placed at
different places along the line while shunt reactors are often installed in the stations at the
ends of line. In this way, the voltage difference between the ends of the line is reduced both
in amplitude and in phase angle.
FIGURE - REACTOR
Shunt reactors may also be connected to the power system at junctures where several
lines meet or to tertiary windings of transformers. Shunt reactors contain the same
components as power transformers, like windings, core, tank, bushings and insulating
oil and are suitable for manufacturing in transformer factories. The main difference is
the reactor core limbs, which have non-magnetic gaps inserted between packets of core
steel
CONCLUSION
Transmission systems have a force multiplier effect on the electricity sector. Apart from
increasing reliability of the electricity grids, they help in harnessing the diversity available
over the vast interconnection on account of weather, festivals, culture, lifestyle, growth
disparities etc. This diversity helps in economy exchanges of electricity leading to very low
payback periods (less than three years) on investment as well as a high benefit-cost ratio even
would further help in reaping the benefit of this diversity. Further the enlargement of the grid
also increases the interdependence between regions and calls for building of institutions,
***********
*******
***