1. The document provides a method statement for installing a roof platform at a refrigerated LPG terminal construction project. 2. It outlines the scope, terms of implementation including permitting and PPE requirements, and preparation steps for the roof platform installation. 3. The method statement details the requirements and safety procedures to be followed, such as using fall protection equipment, barricades and signage, when lifting and installing the roof platform.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
67% found this document useful (3 votes)
698 views

Method Statement Roof Platform

1. The document provides a method statement for installing a roof platform at a refrigerated LPG terminal construction project. 2. It outlines the scope, terms of implementation including permitting and PPE requirements, and preparation steps for the roof platform installation. 3. The method statement details the requirements and safety procedures to be followed, such as using fall protection equipment, barricades and signage, when lifting and installing the roof platform.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

METHOD STATEMENT OF

ROOF PLATFORM INSTALLATION


T-301

Document No Pekerjaan Engineering, Procurement & Rev : 0


Construction (EPC) Proyek Pembangunan Sheet No
LREF-00-PR-20-0252S-A4 Terminal LPG Refrigerated 1 of 6

CLIENT : WIKA – PEN CONSORTIUM


CONTRACTOR : PT. BANGUN BEJANA BAJA
PROJECT TITLE : Pekerjaan Engineering, Procurement &
Construction (EPC) Proyek Pembangunan
Terminal LPG Refrigerated
LOCATION : Tanjung Sekong di Merak Mas – Banten
CONTRACT NO. : PEN-150099001

0 19-07-2018 IFI AF IW SG

PRE CHK APP CHK CHK APP


REV DATE DESCRIPTION PT. BANGUN BEJANA
WIKA-PEN PTM
BAJA
METHOD STATEMENT OF
ROOF PLATFORM INSTALLATION
T-301

Document No Pekerjaan Engineering, Procurement & Rev : 0


Construction (EPC) Proyek Pembangunan Sheet No
LREF-00-PR-20-0252S-A4 Terminal LPG Refrigerated 2 of 6

REVISION SHEET

No Rev Page Subject Description of Change

Issued For Information


1 0
METHOD STATEMENT OF
ROOF PLATFORM INSTALLATION
T-301

Document No Pekerjaan Engineering, Procurement & Rev : 0


Construction (EPC) Proyek Pembangunan Sheet No
LREF-00-PR-20-0252S-A4 Terminal LPG Refrigerated 3 of 6

CONTENTS

1. Purpose..................................................................................................................... 4

2. Scope ........................................................................................................................ 4

3. Terms of implementation ......................................................................................... 4

4. Preparation of Roof Platform Installation ............................................................... 5

5. Method statement of Roof Platform Installation .................................................... 6

6. Housekeeping........................................................................................................... 7
METHOD STATEMENT OF
ROOF PLATFORM INSTALLATION
T-301

Document No Pekerjaan Engineering, Procurement & Rev : 0


Construction (EPC) Proyek Pembangunan Sheet No
LREF-00-PR-20-0252S-A4 Terminal LPG Refrigerated 4 of 6

1. Purpose 1. Tujuan
This method statement is made for Method statement ini dibuat bertujuan untuk
Engineering, Procurement & Construction pelaksanaan pekerjaan pada proyek Pekerjaan
(EPC) Projects Construction of Terminals Engineering, Procurement & Construction (EPC)
LPG Refrigerated by following of safe and Proyek Pembangunan Terminal LPG
secure working steps on the work of Roof Refrigerated dengan mengikuti langkah-langkah
Platform Installation. kerja yang aman dan selamat pada pekerjaan
2. Scope Roof Platform Installation.
This method statement is cover all scope 2. Ruang Lingkup
of work directly or indirectly performed on Method statement ini mencakup pada semua
the Roof Platform Installation. lingkup pekerjaan yang dilakukan pada proses
3. Terms of implementation pekerjaan Roof Platform Installation. Baik
Requirements to be fulfilled for the pekerjaan yang berhubungan secara langsung
execution of the work in this method maupun tidak langsung yang dilakukan
statement are : dipekerjaan Roof Platform Installation.
a. Permission to work 3. Syarat-syarat Pelaksanaan
Before starting this work, first must Syarat-syarat yang harus dipenuhi untuk
obtain a work permit from Personnel pelaksanaan pekerjaan yang ada pada Prosedur
from Operation Construction (EPC) Operasi Standar ini adalah:
Refrigerated LPG Terminal a. Ijin untuk pekerjaan
Construction Project, such as: Sebelum memulai pekerjaan ini terlebih dahulu
 General work permit harus mendapatkan ijin kerja dari Personnel
 Job safety analysis dari Operation Construction (EPC) Proyek
 Meetings to discuss of the work to Pembangunan Terminal LPG Refrigerated,
be done and the impact of safety in seperti :
the workplace.  General Work Permit (GWP).
b. Tools & Equipment  JSA (Job Safety Analysis).
Kinds of equipment that used to  Mengadakan Pertemuan / Meeting untuk
support the work of Roof Platform membahas pekerjaan yang akan dilakukan
Installation are: dan dampak keselamatan pada pekerjaan
 Crawler Crane 100T. tersebut.
 Shackle. b. Peralatan kerja
 Webing Sling / Wire Sling. Jenis-jenis peralatan yang digunakan untuk
METHOD STATEMENT OF
ROOF PLATFORM INSTALLATION
T-301

Document No Pekerjaan Engineering, Procurement & Rev : 0


Construction (EPC) Proyek Pembangunan Sheet No
LREF-00-PR-20-0252S-A4 Terminal LPG Refrigerated 5 of 6

 Palu. mendukung pekrjaan Roof Platform


 Linggis. Installation adalah:
 Welding Machine  Crawler Crane 100T.
 Aluminium ladder  Shackle.
c. Use of PPE  Webing Sling / Wire Sling.
While start to work and entering the  Palu.
Tank Site location, all employees  Linggis.
obligate to use Personal Protective  Mesin Las
Equipment (APD) according to with  Tanggal Almunium
Safety Standards, such as: c. Penggunaan PPE
 Helmet. Pada saat akan melakukan pekerjaan dan
 Safety Glass. memasuki daerah lokasi tangki, semua
 Safety Shoes. karyawan yang terlibat harus/Wajib
 Hand Gloves. menggunakan Alat Pelindung Diri (APD) yang
 Full Body Harness. sesuai dengan standar keselamatan kerja,
4. Preparation of Roof Platform seperti :
Installation.  Helmet.
Preparation of roof platform installation  Welding Tools.
can be do by following these steps:  Kacamata safety.
a. Prepare all materials of roof platform  Sepatu safety.
that will installed on lifted location.  Sarung tangan.
b. Prepare all tools and equipment to be  Full Body Harness.
used for roof platform installation. 4. Proses persiapan untuk Roof Platform
c. Install barricade and sign board at Installation.
location of lifting and installation. Persiapan untuk pekerjaan Roof Platform. dapat
d. Make sure the area is safe to do the dilakukan dengan mengikuti langkah-langkah
job. berikut:
5. Method statement for Roof Platform. a. Persiapkan material roof platform yang akan di
If all preparations complete, Roof instal di lokasi pengangkatan.
Platform Installation can be started by b. Persiapkan semua tools & equipments yang
following the steps as follows: akan digunakan untuk aktivitas roof platform
a. Ground assembly part of roof platform installation.
to be installed with support facing up c. Pasang barikade dan rambu rambu di area
METHOD STATEMENT OF
ROOF PLATFORM INSTALLATION
T-301

Document No Pekerjaan Engineering, Procurement & Rev : 0


Construction (EPC) Proyek Pembangunan Sheet No
LREF-00-PR-20-0252S-A4 Terminal LPG Refrigerated 6 of 6

(above roof platform fame) to minimize pengangkatan dan Installation.


fit up activity at high. d. Pastikan alokasi sudah aman untuk melakukan
b. After ground assembly complete, aktivitas pekerjaan.
reverse the part of roof platform before 5. Langkah pekerjaan Roof Platform Installation.
lifted with support of roof platform Jika semua persiapan sudah selesai maka
facing down (below of roof platform pekerjaan Roof Platform dapat dimulai dengan
frame). mengikuti langkah-langkah seperti berikut :
c. Install lifting tools to the part of roof a. Ground assembly bagian roof platform yang
platform according to lifting plan. akan di install dengan posisi support
d. Lift and installed the part of roof menghadap ke atas.
platform to the position according to b. Setelah ground assembly selesai, balikkan
drawing. roof platform dengan posisi support
e. Tack weld the support of roof platform menghadap ke bawah.
while already on position, add more c. Pasangkan lifting tools pada bagian roof
temporary support if necessary. platform yang akan diinstal sesuai dengan
f. After inspected and approved by QC, lifting plan.
roof platform can be full weld. d. Angkat dan pasang bagian roof platform ke
6. Housekeeping posisi sesuai gambar.
If the roof platform installation work is e. Tack weld support roof platform ketika sdh di
completed, all work locations must be posisi yang tepat, tambahkan support
cleaned from the waste. All waste should sementara apabila diperlukan.
be disposed of in its place and adjusted to f. Setelah dicek dan disetujui oleh QC, bisa
the type of waste. Arrange and organize dilakukan full weld pada roof platform.
all materials and equipment in its place. 6. Housekeeping
Jika pekerjaan roof platform installation
selesai, maka semua lokasi pekerjaan harus
dibersihkan dari sampah dan semua sampah
harus dibuang pada tempatnya serta disesuaikan
dengan jenis sampahnya. Tata dan atur semua
material dan peralatan pada tempatnya.
METHOD STATEMENT OF
ROOF PLATFORM INSTALLATION
T-301

Document No Pekerjaan Engineering, Procurement & Rev : 0


Construction (EPC) Proyek Pembangunan Sheet No
LREF-00-PR-20-0252S-A4 Terminal LPG Refrigerated 7 of 6