Method Statement Roof Platform
Method Statement Roof Platform
0 19-07-2018 IFI AF IW SG
REVISION SHEET
CONTENTS
1. Purpose..................................................................................................................... 4
2. Scope ........................................................................................................................ 4
6. Housekeeping........................................................................................................... 7
METHOD STATEMENT OF
ROOF PLATFORM INSTALLATION
T-301
1. Purpose 1. Tujuan
This method statement is made for Method statement ini dibuat bertujuan untuk
Engineering, Procurement & Construction pelaksanaan pekerjaan pada proyek Pekerjaan
(EPC) Projects Construction of Terminals Engineering, Procurement & Construction (EPC)
LPG Refrigerated by following of safe and Proyek Pembangunan Terminal LPG
secure working steps on the work of Roof Refrigerated dengan mengikuti langkah-langkah
Platform Installation. kerja yang aman dan selamat pada pekerjaan
2. Scope Roof Platform Installation.
This method statement is cover all scope 2. Ruang Lingkup
of work directly or indirectly performed on Method statement ini mencakup pada semua
the Roof Platform Installation. lingkup pekerjaan yang dilakukan pada proses
3. Terms of implementation pekerjaan Roof Platform Installation. Baik
Requirements to be fulfilled for the pekerjaan yang berhubungan secara langsung
execution of the work in this method maupun tidak langsung yang dilakukan
statement are : dipekerjaan Roof Platform Installation.
a. Permission to work 3. Syarat-syarat Pelaksanaan
Before starting this work, first must Syarat-syarat yang harus dipenuhi untuk
obtain a work permit from Personnel pelaksanaan pekerjaan yang ada pada Prosedur
from Operation Construction (EPC) Operasi Standar ini adalah:
Refrigerated LPG Terminal a. Ijin untuk pekerjaan
Construction Project, such as: Sebelum memulai pekerjaan ini terlebih dahulu
General work permit harus mendapatkan ijin kerja dari Personnel
Job safety analysis dari Operation Construction (EPC) Proyek
Meetings to discuss of the work to Pembangunan Terminal LPG Refrigerated,
be done and the impact of safety in seperti :
the workplace. General Work Permit (GWP).
b. Tools & Equipment JSA (Job Safety Analysis).
Kinds of equipment that used to Mengadakan Pertemuan / Meeting untuk
support the work of Roof Platform membahas pekerjaan yang akan dilakukan
Installation are: dan dampak keselamatan pada pekerjaan
Crawler Crane 100T. tersebut.
Shackle. b. Peralatan kerja
Webing Sling / Wire Sling. Jenis-jenis peralatan yang digunakan untuk
METHOD STATEMENT OF
ROOF PLATFORM INSTALLATION
T-301