Modified Bitumen
Modified Bitumen
TG1
Third Edition
July 2015
Published by
Southern African Bitumen Association (Sabita)
Postnet Suite 56, Private Bag X21
Howard Place, 7450, South Africa
Tel: +27 21 531 2718
Fax: +27 21 531 2606
Email: [email protected]
DISCLAIMER
Considerable effort has been made to ensure the accuracy and reliability of the information contained in this publication. However,
neither Sabita nor any of its members can accept liability for any loss, damage or injury whatsoever resulting from the use of this
information. The content of this publication does not necessarily represent the views of any members of Sabita.
Copyright notice: This document and the contents of these pages are the Southern African Bitumen Association (Sabita). This
document is made available to Members of Sabita as a service and is intended for the sole use of such Members, who may reproduce
this document in whole or in part for the purpose of implementation of the systems described herein. All other rights are reserved.
Any other use requires the prior written permission of Sabita.
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Technical Guideline:
Published by Sabita
Postnet Suite 56
Private Bag X21
Howard Place 7450
South Africa
ISBN 978-1-874968-67-2
3
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
* These manuals have been withdrawn and their contents have been incorporated in a manual
entitled: The use of modified binders in road construction published as Technical Guideline 1.
** This manual has been withdrawn and its software programme incorporated in TRH12: Flexible
pavement rehabilitation investigation and design.
*** These manuals have been withdrawn and their contents have been consolidated with the second edition
of Manual 10.
TECHNICAL GUIDELINES
TG1 The use of Modified Bituminous Binder in Road Construction
TG2 Bitumen stabilised materials
TG3 Asphalt reinforcement for road construction
4
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
5
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
PREFACE
The publication of the first edition of Technical Guideline No. 1 (TG1): The use of Modified Bituminous Binders in Road
Construction in 2001 was a major step towards achieving a unified approach to the specification and use of modified binders
in South Africa. The classification of modified binders into various generic classes which are, to some extent, “polymer blind”, is
now firmly entrenched in the industry.
Since that time the modification of bituminous binders has become an increasingly more dynamic field. In addition, new
modifiers, including rejuvenators and warm-mix technology, have been introduced into the road construction sector and are
being specified on a more regular basis. As a result, in 2005 the Road Pavements Forum (RPF) reconstituted a task group with
a mandate to review the current edition of TG1, and to revise the document to reflect the improved knowledge obtained in
promoting current industry best-practice. The activities of this task group culminated in a revised publication in 2007 as well
as this 3rd Edition (2015).
Notwithstanding advances continuously being made internationally and locally with respect to an improved understanding
and prediction of the behaviour of modified products, the ultimate goal of specifying performance-driven properties has not
yet been fully realised.
As a result, the product property requirements together with their associated limits recommended in this document, are still
largely empirically based. Nevertheless, the sections covering aspects such as HSE, handling and storage, selection criteria,
design influences as well as specific construction constraints have been updated to assist practitioners in optimising their use.
While the requirements and/or limitations as recommended in this document should serve the purpose in the majority of
applications of these products, it is accepted that specifying agencies with adequate experience may prescribe other limits
based on their own specific circumstances, environment and experience.
6
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
ACKNOWLEDGMENTS
On behalf of the road construction industry represented by the RPF, Sabita acknowledges, with thanks, the time and effort
given by the following members of the Task Group responsible for compiling this important guideline document for the
industry:
Dennis Rossmann SANRAL (Chair)
Riaan Burger SANRAL
Simon Coe Chevron SA (Pty) Ltd
Some of the aspects incorporated into the original document were based on guidelines developed by Austroads and the
Australian Asphalt Paving Association (AAPA). Their permission to do so is gratefully acknowledged.
7
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
SCOPE
This technical guideline covers the requirements for generic classes of homogeneous (thermoplastic polymers) and non-
homogeneous (bitumen-rubber) modified binders for use in asphalt, surface seals and crack sealing applications. It includes
recommendations related to the appropriate selection criteria, product property requirements, HSE, manufacture, storage,
handling and quality control measures for the procurement and application of modified binders.
Methods for the sampling, preparation and common test procedures of these products have been included as an Appendix to
the document. The intention is that most of these tests will be incorporated into the South African National Standards (SANS)
standard test methods for compliance with South African National Accreditation Systems (SANAS) requirements. This process
is already well under way.
It should be noted that aggregate selection, mix design and final product composition are not addressed here. It is
recommended that practitioners refer to the relevant manuals/guidelines, or appropriate research, covering these aspects.
However, the scope of this document has been extended to include requirements for special applications related to fuel
resistance, bond coats and microsurfacing. These were not previously covered under the generic specification framework.
Furthermore a protocol for conducting a field evaluation for introducing new modified binder products is also provided as
a guideline in the appendices. While the scope of this document is, as stated above, confined to generic classes of modified
binders, the existence of proprietary products, offering enhanced performance characteristics, is acknowledged. It is expected
that the manufacturers or marketers of such products would follow a certification process such as Agrèment South Africa,
which could include the provision of appropriate performance guarantees.
8
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
CONTENTS
PREFACE 6
ACKNOWLEDGMENTS 7
SCOPE 8
1. INTRODUCTION 13
Surface Seals 13
Hot-Mix Asphalt 13
Tack Coat 13
Crack Sealing 14
Rejuvenators 14
Warm Mix Technology 14
9
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
4. MANUFACTURE 33
4.1 General 33
4.2 Homogenous binders 34
4.2.1 SBR modified bitumen 34
4.2.2 SBS modified bitumen 34
4.2.3 RET 34
4.2.4 EVA 34
4.2.5 Hydrocarbon modified binders and high molecular weight waxes 35
4.3 Non-homogenous polymer modified binder 35
4.3.1 The wet method 35
4.3.4 The dry method 36
4.4 General items 36
4.4.1 Combining agents 36
4.4.2 Pre-blending 36
4.4.3 Mixing 36
4.4.4 High shear mixers 37
6. PRODUCT REQUIREMENTS 40
6.1 Special Applications 44
6.1.1 Modified emulsions for microsurfacings 44
6.1.2 Hydrocarbon modified bitumen for high modulus asphalt 45
6.1.3 Modified binders for fuel resistant surfacings 45
6.1.4 Modified bitumen emulsion for tack coat 46
6.1.5 Modified emulsions for geotextile application 46
7. SELECTION CRITERIA 47
7.1 Spray Seal Applications 48
7.1.1 Environmental influences during application 48
7.1.2 Aggregate influences 49
7.1.3 Substrate influences 50
7.1.4 Project location and programming influences 50
7.1.5 Traffic influences 51
7.1.6 Design influences 52
7.1.7 Selection guide 52
7.2 Asphalt 52
7.2.1 Hot mix asphalt 52
7.2.2 Warm mix asphalt 53
8. CONSTRUCTION 58
8.1 Introduction 58
8.2 Construction procedures 58
8.2.1 Mixing of polymers 58
8.2.2 Storage and handling 58
8.2.3 Quality control 58
8.2.4 Re-constitution 58
8.2.5 Contamination 58
10
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
11
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
METHOD MB-14: Particle size distribution and loose fibre content of rubber crumbs 105
METHOD MB-17: Softening point of modified bitumen by ring and ball method 107
12
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
CHAPTER 1 : INTRODUCTION
1. INTRODUCTION
Modified binders have the ability to offer improved performance over conventional binders, but do not offer a universal
solution for all situations.
Benefits that may be derived from binder modification include :
• Improved consistency;
• Reduced temperature susceptibility;
• Improved stiffness and cohesion;
• Improved flexibility, resilience and toughness;
• Improved binder-aggregate adhesion;
• Improved resistance to in-service ageing.
However, irrespective of the improvement in binder characteristics, the fundamental rules of design of asphalt or surfacing
seals (including aggregate quality, layer stiffness/flexibility and workability) should not be ignored.
Modified binders are generally more expensive than conventional binders; hence, their correct application does not lie in the
simple substitution of conventional binders, but requires appropriate design of the final product in order to maximise the
cost-effectiveness relevant to a specific situation. Very often performance requirements for routine situations can be met with
the use of appropriate conventional binders. There are, however, particular situations where modified binders could offer cost-
effective solutions.
Typical conditions where such binders should be considered are given below.
Surface Seals
• In areas of high stress such as heavy traffic, steep inclines, intersections (modified tack coat for Cape Seals)
and sharp curves;
• In areas experiencing large daily/seasonal temperature fluctuations or high ambient temperatures for long periods;
• As a Stress Absorbing Membrane Interlayer (SAMI);
• For sealing over active cracks of up to 3 mm without pre-treatment (Stress Absorbing Membrane, SAM);
• In slurry seals for heavy duty applications (e.g. rut filling);
• In remote areas where improved durability is required.
Hot-Mix Asphalt
• On relatively highly flexible pavements;
• In areas of high stress such as heavy traffic, steep inclines, intersections and sharp curves;
• In asphalt bases which are subjected to high loading under slow moving traffic;
• In areas experiencing large daily/seasonal temperature fluctuations or high ambient temperatures for long periods;
• In areas that are subjected to fuel spillages;
• In open graded mixes requiring a high binder film thickness;
• In areas where thin layer overlays are required.
Tack Coat
As a tack coat under very thin asphalt surfacings to improve layer adhesion (thereby reducing the risk of de-lamination) and
preventing pick-up by construction vehicles.
13
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
CHAPTER 1 : INTRODUCTION
Crack Sealing
• For cracks wider than 3 mm;
• For highly active cracks.
Rejuvenators
With the current international trend towards more sustainable practice, recycling of non-renewable materials is becoming
the norm. While these products modify bituminous product properties and could, in a sense, be categorised as “bitumen
modifiers”, they have not been included in this document. The majority of these products are currently “proprietary” in nature
and, as such, fall outside of the scope of this guideline at present.
14
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
The general HSE hazards and effects associated with bitumen and bituminous binders are well documented in various
Sabita publications. In this section the most critical HSE hazards and effects specific to modified binders are highlighted and
discussed in some detail.
Reactive bitumen foaming may also result in ‘boil over’ in a tank or vehicle compartment leading to spillage of hot bitumen.
15
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
• Test and ensure that cutter oils, solvents and other bitumen additives are not contaminated with water;
• Ensure that water does not enter into tanks or vessels containing bitumen at elevated temperatures, particularly
during firefighting or emergency tank cooling procedures.
“Vapour” usually refers to the gaseous state of a liquid (usually a volatile liquid) that evolves when “vaporisation” takes place
on the surface of a liquid. Vapour consists of very fine sub-microscopic droplets diffused or suspended in the air and vapour
could be odourless or have very distinct odour. Vapour can sometimes be seen as a vapour cloud, but normally the vapour is
“invisible” to the naked eye.
“Fumes” are formed when vapour from “volatilised” bitumen condenses in cool air. Fumes contain microscopic solid particles
and are usually quite visible in the form of smoke or a “mist” suspended in the atmosphere.
Considering the above definitions and for purposes of this discussion, “bitumen fumes” can best be described as “vapour
containing suspended solid particles that could be harmful to humans if inhaled”.
However, numerous studies in the USA and Europe have been conducted on the health effects of occupational exposure
to ‘conventional’ bitumen and ‘modified bitumen’ including polymer modified bitumen, and the overall consensus of these
studies can be summarised as follows:
Eye, nose, and throat irritations are the most common effects of exposure to bitumen fumes, including those emanating from
modified bitumen.
Although no definitive results have yet been obtained, the trends are suggestive that exposure to polymer modified bitumen
are potentially more hazardous.
Research into the longer term effects of exposure to bitumen fumes is ongoing, and is in particular focussed on the potential
of the incidence of cancer in workers exposed to bitumen fumes. Results have thus far been inconclusive; however researchers
remain cautious and currently classify bitumen fumes as ‘possibly carcinogenic to humans’.
2.2.3 Increased likelihood of exposure to harmful fumes during handling and application of
modified bitumen
According to an EAPA publication Safe handling advice when working with polymer modified bitumen, comparative studies of
emissions from standard paving grades and SBS-modified bitumen confirmed that under correct working conditions there
was no significant increase or differences in fume formation. However, studies also acknowledge that:
• Modified bitumens contain additives that are potentially more hazardous. For example, some extender oils contain
high concentrations of harmful Polycyclic Aromatic Hydrocarbons (PAHs) and every precaution must be taken to
reduce the exposure of workers to fumes. Manufacturers’ recommendations for each product should be followed;
• Modified bitumen is produced, stored and applied at higher temperatures compared to conventional binders and
therefore, if strict temperature control is not exercised, the potential for emission of toxic fumes is increased.
16
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
17
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
2.4 Literature
With this revision of TG1 the following publications were consulted to ensure current knowledge and information is included
in the revision:
i. Hazard Review: Health Effects of Occupational Exposures to Asphalt, National Institute for Occupational Safety and Health ,
U.S. Department Of Health And Human Services;
ii. Crumb-Rubber Modified Asphalt Paving: Occupational Exposures and Acute Health Effects, Niosh Health Hazard Evaluation
Report: Heta #2001-0536-2864;
iii. Health, Safety & Environmental Aspects of Bituminous Materials, Australian Asphalt Pavement Association, 2010;
iv. Occupational exposures to bitumen and their emissions: WHO/International Agency for Research on Cancer,
October 18, 2011;
v. Life Cycle Inventory: Bitumen, 2nd Edition July 2012, Published by the European Bitumen Association;
vi. The Asphalt Paving Industry - A Global Perspective: Production, Use, Properties, and Occupational Exposure Reduction
Technologies and Trends, Second Edition, Global Series 101, Produced February 2011.
18
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Similar to conventional binders, the physical properties of modified binders are largely controlled by the fundamental
properties related to temperature, viscosity and phase transition. Modified bitumen provides the technology to produce
a bituminous binder with improved viscoelastic properties which remain in balance over a wider temperature range and
loading conditions.
There are four distinct modes of interaction between bitumen and modifiers:
• The modifier is present as a separate phase within the bitumen;
• The bitumen is present as a separate phase in the modifier and the product will display the properties of the modifier
rather than the bitumen;
• The modifier will form an interface with the bitumen, giving greater elasticity due to changes in the mechanical
structure of the material;
• The modifier will form a molecular bond with the bitumen giving greater elasticity and stiffness to the material.
They can also be considered in two distinct application modes; those which are hot applied and those which are cold applied
either by emulsifying and/or cutting back.
Cold applied products in the form of bitumen emulsion or cutback bitumen are also available for use in the road building
industry. Only bitumen emulsions are normally modified to improve the residual bitumen’s viscoelastic properties. Cutters
are sometimes added to hot binders to reduce their viscosity and improve their ability to wet the stone aggregates during
surfacing seal applications in cooler weather conditions.
The homogeneous polymer modifiers typically used in bitumen modification are thermoplastic polymers such as:
• Styrene-butadiene-styrene (SBS) block copolymers (Elastomeric);
• Blend of SBS, WMA additive and cross-linking agent (Elastomeric);
• Synthetic styrene-butadiene-rubber (SBR) latex (Elastomeric);
• Styrene isoprene rubber (SIR) (Elastomeric);
• Natural rubber latex (Elastomeric);
• Ethylene-vinyl-acetate (EVA) block copolymers (Plastomeric);
• RET (Reactive Elastomeric Terpolymer).
The non-homogenous bitumen-rubber utilises crumbed rubber from recycled tyres.
1
Blends with rejuvenators are excluded
19
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
For cold applied products, the rheological properties of bitumen in the emulsion can either be modified by the pre-
modification of bitumen, or by the post-modification of the bitumen emulsion. In South Africa, the post-modification of the
bitumen emulsion is the most popular practice. Natural rubber or synthetic rubber latex such as SBR or SIR can be used to
improve the properties of bitumen in the various applications.
Each of the different types of modified bitumens will be discussed separately in order to describe the benefits and sensitivity
to application of each of the various modifiers.
Styrene-Butadiene-Styrene (SBS) The latex emulsion breaks first, forms a skin and
SBS is a block copolymer and can be classified as either linear or radial. prevents the bitumen emulsion from breaking. This
A radial blocked copolymer results in much higher viscosity and causes the rubber to lie on top of the road surface,
softening point for the same addition of polymer making it more difficult where it is picked up by traffic.
to mix with bitumen, compared with the linear block copolymers.
SBS can be considered as a thermoplastic rubber and is characterised by its glass transition point (Tg). Coherent cross-linking
points provide high stiffness below the glass transition point. The process is reversed by melting (100°C) the copolymer which
causes it to dissociate, become soft and start to flow. On cooling the copolymer regains strength and elasticity.
Styrene and butadiene are mutually incompatible and attempt to separate in the modified binder mix. However, as the
copolymers are chemically linked, styrene end blocks agglomerate and form three dimensional cross-linked polystyrene
domains which give the polymer mechanical properties comparable to cross-linked rubber (vulcanisation). Since the cross-
linking is physical rather than chemical, the process is reversible.
At elevated temperatures above the glass transition point of the polystyrene domains, the physical cross-links dissociate. On
cooling, the domains reform and the physical cross-links with long continuous elastic networks reform and are restored within
the bitumen.
SBS absorbs the maltenes in the bitumen, swells and, at higher dosage levels, forms a continuous molecular network in the
bitumen phase which makes up a major fraction of the bitumen by volume. At lower concentrations (3 - 4%) the SBS will
only form a fragmented molecular network. At higher concentrations (4 - 6%) a continuous network forms which results in
a dramatic increase in the softening point. The molecular networks increase the elastic component of bitumen which assists
with recovery after deformation. As the SBS content is increased, the elastic recovery also increases.
The effect that an increase in the amount of SBS polymer will have on the softening point of base bitumen with varying
asphaltene contents is shown in Figure 2. The rate of increase in the softening point and thus the shape of the curve is
dependent mainly on the asphaltene content of the base bitumen, the type and grade of the SBS polymer and the percentage
thereof. Typically, the curve assumes an S-shape as the SBS structure changes from a fragmented form to a continuous
network in the modified binder.
Figure 2 - Typical effect of SBS on the softening point of bitumen with different asphaltene contents
20
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
An apparent correlation exists between elastic recovery and deformation resistance in that an increase in elastic recovery
provides for better deformation performance. Cohesive strength also increases with the increased elastic recovery. SBS hot
modified binders are generally preferred to SBR due to their higher softening points and higher elastic recovery properties,
which in turn can be applied at lower temperatures as a result of their lower relative viscosities.
At low temperatures, the addition of SBS improves the flexibility of the bitumen which inhibits cracking and improves the
resistance of the binder to crack reflection.
Styrene-Butadiene-Rubber (SBR)
SBR latex consists of styrene butadiene polymer, emulsified with a solids content generally greater than 50% depending on
the grade. The SBR latex is manufactured through the copolymerisation of the hard styrene monomer and the soft butadiene
monomer. The butadiene contributes to the elasticity and makes the binder more flexible whereas the styrene gives stiffness
and strength to the material.
The mechanical bonding mechanisms and chemistry of SBRs are very similar to those of SBS, with the exception that during
the copolymerisation of the butadiene, single-unit monomers are randomly linked to form long, multiple units.
SBR latex is used in both hot and cold modified binders. However, the emulsifier type becomes very important when selecting
the SBR-latex for the modification of bitumen emulsions. Anionic latex emulsifiers are used with anionic emulsion and,
similarly, cationic latex emulsions are used with cationic bitumen emulsion grade.
SBR modified binders are predominantly used in cold applied binders for seals, bond coats, crack sealants and
microsurfacings. Hot modification of bitumen with SBR is still commonly used for seals and, to a lesser extent, in asphalt. With
the modification of hot bitumen the amount of SBR latex that can be added is limited by:
• the rapid increase in the binders viscosity which is in turn restricted by the spray temperature; and
• the evaporation of the water content of the latex when blending with the hot bitumen.
SBR polymers improve adhesion of the binder with the aggregate in sealing applications, which results in better chip
retention. They also provide improved elasticity and flexibility to the binder, seal cracks and prevent water ingress into the
pavement. In asphalt applications they increase the deformation resistance, enhance fatigue properties and retard
crack reflection.
21
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
EVA (Ethylene-Vinyl-Acetate)
EVA is a polymeric plastomer which consists of two monomers ethylene and vinyl-acetate (VA). The two monomers form long
crystalline molecular strings which dissociate when the temperature is increased above the material’s glass transition point.
The morphology of EVA is semi-crystalline and interconnected by polyethylene crystalline molecules and vinyl-acetate
molecules which form amorphous chains contributing to the flexibility.
The polyethylene provides the stiffness to the material with cohesion provided by the crystallinity and chain length. The
copolymers are polar and, together with the maltenes of the bitumen, will dictate the compatibility and adhesive properties
of the binder. The following main parameters control the properties of EVA:
• Vinyl Acetate (VA) content: The more the VA content increases, the higher the proportion of rubbery regions
(i.e. an increase in flexibility) and the lower the proportion of crystalline regions (i.e. a decrease in stiffness).
• Molecular weight: Standard practice for EVA’s is to measure melt flow index (MFI); the higher the MFI the lower
the molecular weight and viscosity.
EVA modified bitumens have the ability to provide improved resistance to rutting in hot-mix asphalt compared to
conventional bitumen along with improved compatibility, safer handling and better workability compared to SBS and SBR
modifiers. Some grades of EVA also increase the resistance to damage caused by fuel spillages and pose no problems with
future recycling of the material. However, it should be noted that the properties of EVA vary for different grades depending on
the chain length and molecular weight of the polymer, the vinyl acetate (VA) monomer content and the crystallinity. In terms
of the EVA modifiers, the VA content and melt flow rate (MFR) are as important as the styrene content and linear or radial
structure in SBSs when determining specific properties.
EVA modified bitumen is also more heat stable and does not deteriorate as fast as SBR and SBS modified bitumen products
at elevated temperatures during storage. Storage stability will therefore be better than that of SBS and SBR.
The compatibility of bitumen and EVA may vary, depending on the composition of the bitumen and the type or grade of
the modifier.
RET consist of three polymers (and also goes under the name of ENBAGMA).
• Ethylene
- being a hydrocarbon it is compatible with bitumen;
- provides stiffness and viscous properties to prevent rutting.
• n-Butyl Acrylate
- provides elastomeric properties to prevent cracking and rutting;
- improves adhesion to aggregates.
• Glycidyl Methacrylate
- reacts with bitumen to provide a homogeneous, storage stable modified binder.
Bitumen-rubber
Bitumen-rubber binders combine rubber crumbs (with a specific, grading, morphology and composition) with bitumen at
high temperatures to achieve a complex two phase product which has both the elasticity and stiffness of tyre rubber, and the
flow characteristics of bitumen.
Rubber is obtained by processing and recycling rubber tyres, and it is important to note that the type of tyre rubber varies
depending on the sources and make of the tyre. The natural rubber and synthetic rubber content will also vary depending
on the source. The morphology of the rubber particles significantly influences the composition of crumbed rubber after
mechanical grinding. Table 1 shows typical requirements for rubber crumbs for modified bitumen.
22
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
When the bitumen rubber blend cools down the course rubber particles form a rubber network which is filled with bitumen
and it is the rubber network that contributes to the improved cohesion, elasticity, flexibility, re-healing capabilities and
strength of the material. Bitumen rubber has been used successfully in both surfacing seal and asphalt applications due to
its improved elasticity and stiffness and can be used as a stress absorbing membrane interlayer (SAMI). The stone retention
properties, resistance to bleeding and resistance to deformation are also enhanced.
The typical composition of bitumen rubber is shown in Table 2. However, the ratio of components varies depending on
the bitumen source, the climatic conditions and the application. With the addition of extender oil the maltenes in bitumen
remains virtually unaffected and improves the fatigue and durability characteristics of the binder. The requirements of the
extender oil are such that it should have a flash point of greater than 180°C and a percentage by mass of aromatic unsaturated
hydrocarbons greater than 55.
Note:
Rubber crumbs also contain other components that may have a beneficial
effect on the properties of the binder. For example, the crumbs contain Extender oils and high boiling point
in excess of 30% carbon black which has been shown to add reinforcing fluxing agents are different in nature
properties to bitumen and antioxidants in the rubber contribute to the and have different properties and purposes.
durability of bitumen rubber.
23
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
North American Asphaltum is a natural, resinous hydrocarbon found in Utah, USA, soluble in aromatic and aliphatic solvents
and is frequently used to harden petroleum products. The black, shiny, free-flowing, granular substance is brittle and easily
crushed into a dark brown powder that is fully compatible with bitumen. It has a high asphaltene (71%) and nitrogen (3%)
content and is essentially sulphur-free (0.3%). It is 99% pure in its natural state, is low in toxicity and is non-carcinogenic.
South American Asphaltum originates from Argentina and is a natural bitumen of high purity, composed of hydrocarbons,
asphaltenes and aromatics of high molecular weight. Table 3 shows a comparison of the composition of Asphaltum and a
typical bitumen.
Asphaltenes 71 >80% 8 - 18
Saturates 2 - 4 - 10
Asphaltum can provide increased mix stability, helps to reduce rutting and shoving because it increases the load bearing
capability, reduces tempera- ture susceptibility of asphalt and imparts improved aggregate adhesion and resistance to water
stripping. It is fully compatible with bitumen allowing for good stability in storage.
The F-T waxes act as “flow improvers” and have the ability to reduce the viscosity of the modified bitumen during mixing
and compaction of hot-mix asphalt, thereby allowing lower temperatures during these processes, as is the case with
warm-mix asphalt.
F-T waxes increase the softening point and decrease the penetration value of the binder. As a result handling of the modified
binder at elevated temperatures is facilitated, while at service temperatures the deformation resistance of asphalt
is enhanced.
Figure 3 shows the effect of F-T wax modification of a binder on its viscosity over the in-service and application temperatures
zones as compared to conventional bitumen.
24
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
The F-T wax modified bitumen has good aggregate adhesion, provides satisfactory stiffness at the higher operating
temperatures and resistance to cracking at low operating temperatures.
The F-T waxes are completely compatible with bitumen and are stable in storage. They can also be used as a co-modifier
with polymer modified bitumen to produce hybrid products that may be tailored for specific engineering requirements for
improved long-term performance of asphalt layers. It is recommended that the manufacturer’s guidelines on blending and
construction practice be followed to derive maximum benefit from the use of this modifier.
1. In the first method, rubber latex, which is a stable dispersion (emulsion) of rubber particles in water, is incorporated in the
aqueous phase before co-emulsification with the bitumen in the colloid mill. The manufacturing conditions are similar
to the conditions employed for producing conventional bitumen emulsions. This type of emulsion is called a three phase
emulsion, as it consists of bitumen and rubber droplets dispersed in the water phase. Typically, Styrene Butadiene Rubber
(SBR) latex would be used for the modification of bitumen emulsions.
2. The second method involves pre-dissolving the solid polymer – typically SBS – in the bitumen before emulsification.
The final emulsion thus consists of two phases i.e. polymer modified bitumen droplets dispersed in the aqueous phase.
As the polymer modified binder has a considerably higher viscosity than conventional penetration grade bitumen, it is
necessary to heat the modified binder to an elevated temperature to ensure proper emulsification in the colloid mill. Due
to the higher temperatures employed, the emulsion exit temperature from the colloid mill will exceed the boiling point
of water. To prevent the polymer modified emulsion from boiling upon exiting the colloid mill, it is necessary to cool the
emulsion to below its boiling point, by passing it through a heat exchanger. SBS modified emulsions are currently not
commonly available in South Africa.
SBR modified spray grade bitumen emulsions are characteristically slower breaking than conventional rapid-set bitumen
emulsions, after application. Consequently, during surfacing seal operations with latex modified emulsions, sufficient time
should be allowed for the water component to evaporate, before allowing traffic on to the surface.
25
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
The rheology of modified binders is complex, and, although the results from conventional tests may indicate a significant
alteration in properties, the in-service performance of these binders is not easily categorised. The typical influence of type, as
well as amount of modifier on viscosity and softening point properties is shown in Figures 4 and 5, respectively.
26
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Selection of polymer type and grade, as well as the amount, will be dictated largely by the need to satisfy the minimum
softening point requirement as well as achieving the specified application viscosity within the recommended maximum
temperature limits, to prevent degradation of the product. This certainly is the case with SBR modified binders, as can be seen
in in Figures 4 and 5, and users must be cautioned that by increasing the amount of polymer to meet the minimum softening
point requirement will lead to a dramatic increase in the viscosity rendering the final product difficult to apply.
Experience has shown that there is a general tendency for the softening point values of polymer modified binders to decrease
in storage over time. Where long haul distances or lengthy delays are expected, it may be necessary to slightly increase the
percentage of modifier added. When assessing the acceptability of this product property (as with any other properties)
cognisance should always be taken of the inherent uncertainty applicable to the test method.
Unlike conventional bitumen which displays Newtonian behaviour above its softening point temperature, modified binders
tend to display shear thinning behaviour thus rendering dynamic viscosity measurements at normal shear rates of limited
usefulness, particularly below application temperatures.
Thus the use of the standard procedure of the Brookfield viscosity test at one shear rate to determine asphalt mixing and
compaction temperatures for modified binders is not appropriate. Using the viscosity limits commonly used for conventional
binders, based on a single shear rate, lead to excessively high temperatures when compared to field experience and
producers’ recommendations. There is a prospect for using the Dynamic Shear Rheometer for estimating appropriate mixing
and compaction temperatures for modified binders.
In most instances, the addition of a polymer results in the binder having lower moduli at low temperatures, and is therefore
more flexible. At high temperatures, however, the binder exhibits an improved stiffness and elasticity when compared to the
unmodified bitumen. The most common way of measuring rheological properties is through the use of the Dynamic Shear
Rheometer (DSR), which applies a range of shear stresses at various frequencies (loading time) and temperatures.
3.2.2 Elasticity
Elastic behaviour indicates that the binder recovers most or all of its initial shape when the load that caused the deformation
is removed. The elastic recovery of a binder is commonly used to measure the fatigue resistance of a binder or its ability to
absorb large stresses without necessarily cracking or deforming.
Particular modifiers have unique elastic recovery characteristics depending on the morphology of the modifier/binder system.
For example, SBS forms a three-dimensional network of highly elastic, butadiene chains connecting stiff styrene domains,
resulting in very high elastic recoveries. SBR has random styrene/butadiene molecules, resulting in relatively lower elastic
recovery. EVA forms a rigid three-dimensional network, imparting no elastic recovery properties to the base binder but
provides a high stiffness.
The elastic property of a binder is generally influenced by the type of modifier as well as the degree of modification, and is
determined by measuring the recovery of a sample which has been extended in a low temperature ductilometer. In cases
where modifiers enhance elasticity, there is a direct relationship between elastic recovery and the degree of modification.
3.2.3 Cohesion
Cohesion is a measure of the tensile stress required to break the bond between molecules of the bituminous binder. The
inherent strength, tenacity and toughness of the bituminous binders are improved by modification with thermoplastic
polymers and rubber crumbs. Hence, a greater tensile stress is required to break the molecular bonds of modified binders and
cause failure compared with a lower tensile stress required to break the bonds of conventional binders.
Although no longer a requirement in this document, the results of a force-ductility test illustrate the nature of the cohesive
strength of modified binders. The test involves the elongation of a sample with the force measured at very small elongation
intervals. Figure 5 shows the typical profiles of various modified binder types obtained during the test.
27
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
As shown in Figure 6, the maximum force is reached early in the elongation process. The elastic phase is represented by the
area before the initial peak and the total area under the curve can be used to calculate the energy required to extend the
binder, which is a good indication of the binder’s toughness or resistance to cracking.
The energy required to elongate elastomeric modified binders is generally significantly more than that for conventional
binder. Plastomeric modified binders will impart stiffness to the bituminous binders but not necessarily improve its cohesive
nature. Such modified binders may well perform in a brittle manner in tension.
The cohesive properties of modified binders provide guidance to how soon after construction a seal could be opened to
traffic, as well as providing an assessment of the ability of the binder to withstand shear stresses imparted by heavy traffic.
3.2.4 Adhesion
Adhesion is a measure of the strength of the bond between the bituminous binder and mineral aggregate.
It is largely dependent on the physical and chemical nature of the bituminous binder and aggregate type when combined
for application.
By increasing the film thickness of the binder layer the adhesion is improved. The film thickness of the binder layer can be
increased by:
• Reducing the time-lag between the binder application and the stone application in surfacing seals;
• Using pre-coated stone;
• Using emulsion cover (fog) sprays to increase or correct the final binder application rate;
• Pre-blending an adhesive agent with the modified binder prior to spraying.
Temporary reduction of the viscosity by the addition of cutters during colder weather conditions also improves the adhesion
properties. However, care should be taken in areas with hot humid climates and/or heavy traffic conditions.
It should also be noted that different types of aggregates exhibit different adhesion behaviour depending on the chemical
nature of the parent rock in terms of its hydrophilic (water-attractive) or oleophobic (oil-repelling) nature. Depending on
the chemistry of the parent rock, the nature of the aggregate could vary. However, bitumen is oleophilic (oil-attracting) or
hydrophobic (water-repelling). Therefore, based on the inherent character of the aggregate, it may or may not react (form
chemical, charge-related bonds) with water, but the presence of water will have a negative influence on the adhesion
properties and it will repel the bitumen.
Acidic aggregates are more hydrophilic than basic aggregates. Acidic aggregates will therefore have poor adhesion properties
in the presence of water. Cationic spray grade emulsion overcomes this tendency when the free electrons on the aggregate
form physical/electrical bonds with the positively charged bitumen and SBR latex droplets as shown in Figure 7.
Similarly and, especially in high risk applications and under difficult construction conditions, surface active chemicals in
commercially approved adhesion promoters and pre-coating fluids have been used effectively to improve the adhesion
properties. However, if these substances are used in conjunction with bitumen emulsions in the construction of a surfacing
seal, they are known to retard the breaking characteristics of the emulsion.
28
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
In-service ageing describes the hardening (increase in stiffness and reduction of elastic properties) of a binder during its life
on the road due to oxidation, loss of volatiles, physical hardening and exudation.
Degeneration and adverse changes in the properties of modified binders are also observed when bituminous products are
stored at high temperatures. Durability of bituminous binders therefore relates to the ability of a particular binder in a specific
application to resist the negative influence of ageing.
Temperature susceptibility
All bitumens display thermoplastic properties, i.e. they become softer (more liquid) when heated and harden when cooled.
The degree of variation in consistency (or viscosity) is referred to as temperature susceptibility.
Conventionally it is characterised by Softening Point at elevated temperatures and Fraass Brittle Point at lower temperatures.
This is characterised by the variation in consistency (stability) of the bitumen related to temperature and is governed by the
softening point at high temperatures and, typically, the Fraass Brittle Point at lower temperatures. The window between the
two extremes is called the service temperature of the bitumen with the two extremes being dependent on the crude source
and bitumen grade. Should the binder be exposed to temperatures above the softening point bleeding/rutting could occur
and below the brittle point, cracking may be observed (see Figure 8).
29
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
By adding polymers to bitumen the in-service temperature range is widened. The increased stiffness compared to
conventional bitumen enhances the performance characteristics of the modified bitumen and provides better protection
against increased traffic loads and adverse climate conditions. In addition, thinner asphalt layers could be considered during
design and construction/rehabilitation to reduce the cost of the pavement.
Certain modified binders, e.g. bitumen rubber, SBS and SBR materials are generally susceptible to thermal degradation.
SBS and SBR are also susceptible to oxidation, making it important to monitor temperatures carefully during all stages –
production, storage, mixing and application – of these modified materials.
In a modified bitumen there is competition between the modifying agent (rubber crumbs, SBS, SBR or RET) and the naturally
occurring asphaltenes for the available maltene portion (resins and aromatics) of the bitumen. This competition varies with
the type and source of both the bitumen and the polymer, and this will affect the compatibility of the final product. Therefore
any changes in the crude type and refining process used during the manufacture of the base bitumen could affect the
compatibility of the polymer bitumen system.
The stability or homogeneity test as described in MB-6 is used to determine the compatibility of the base bitumen and the
polymer in question and to assess the hot storage stability of a material.
As the application of mechanical stirring will inhibit segregation of the different components during storage, the stability test
should be used by manufacturers as an indicator of whether stirring of their product is required or not. Also, whenever there is
any reason to believe that the chemistry of the base bitumen has changed, the test should be repeated.
Polymer modified binders are normally produced with 70/100 penetration grade bitumen. During lower temperature
conditions it is necessary to soften the binder by utilising an appropriate hydrocarbon cutter, such as illuminating kerosene, to
prevent stone loss by improving the adhesion properties of the binder and promoting the early formation of a stable mosaic
of aggregate.
From a safety perspective, the practice of cutting back hot binders is a hazardous operation as the blending temperature
of the binder is well in excess of the cutter’s flash point. Ideally, this operation should only be undertaken under controlled
conditions such as in a blending plant.
However, if the blending of the cutter has to be undertaken on site, the binder supplier must produce a written method
statement of his blending procedures for cutting back modified bitumen. The reader is referred to the Sabita publication:
Guide for the control of HSE hazards associated with the field production of medium curing cutback bitumen.
It should also be noted that there is always the real risk that the use of a cutter can lead to bleeding of the newly constructed
seal with the onset of warmer weather conditions under heavy traffic. Thus special care must be taken of all the factors that
could affect the performance of the new seal if the modified binder is cut back.
30
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
o
• The expected maximum road temperature does not exceed 30 C for several hours during the application period.
o
Sealing should only commence when the road surface temperature reaches 25 C and continues to rise
o
above 30 C; or
o
• The expected minimum air temperature in the following 48 hours is expected to drop below 10 C. To this end the
weather forecast for the ensuing week should be obtained to ensure that the minimum temperatures are not
expected to fall below this value.
Shady areas
Where the road will be in shade during the day it is likely that the maximum road temperature in the shaded area would be
o0
below 25 C. In such locations cutting back should be considered, provided that such areas are large enough. However, these
areas are often isolated in comparison to the overall project e.g. areas under bridge decks and thus the following options are
recommended in place of cutting back:
• Increase the binder application rate by up to 20% for large areas. Alternatively, split the binder application by
reducing the application rate of the tack spray and spraying a diluted emulsion as a cover spray;
• Start the application in the shaded areas and ensure that the distance between the sprayer and chip spreader is kept
to a minimum;
• Where a significant length of the project is expected to be in shade, consider using an emulsion for the project and
covering the seal with no-fines grit after the emulsion has broken. In addition, keep the shaded areas of the road
closed to traffic for 48 hours. Care must be taken when using modified emulsions in cooler locations, because the
latex in the emulsion forms a skin which inhibits the breaking process.
As some areas in South Africa experience night temperatures below 10°C in March, it is recommended that the minimum
temperatures from the closest weather station for the preceding 10 year period be obtained prior to making any decisions as
to whether to cutback or not.
Type of surfacing
The type of surfacing will also influence whether or not a cutter can be used. Cutters should not be used in the spray
applications for:
• Cape seals, tack sprays for double seals, geofabric seals and SAMIs as they will be covered by a slurry, binder or
asphalt which would lead to the entrapment of the volatiles.
• Seals to be placed over fresh asphalt or slurry surfaces (excluding texture slurries of less than 2 mm) as it could lead
to premature embedment of the new seal. A ball penetration test should be done to determine the hardness of
a new asphalt or slurry surface before resealing with a cutback modified binder.
Spray grades of modified emulsions usually contain 2 - 4% m/m of cutter (flux), which is varied seasonally to enhance the
breaking and adhesion characteristics. The presence of cutter in the emulsion may cause bleeding in Cape seals carrying very
heavy traffic, as well as instability in geofabric seals during warmer weather.
As a general guide, the use of cutters should be restricted to roads carrying less than 5 000 elv/day, and the amount of
heavies should be less than 15% of the traffic volume. Furthermore their use in high stress areas like climbing lanes and busy
intersections should be avoided. The application of modified binders incorporating a cutter on residential streets during
cooler temperatures as experienced in the winter months generally presents a low risk of bleeding.
Modified binder seals incorporating up to 3% cutter have been successfully applied on roads carrying relatively high traffic. A
reduction in the amount of cutter which would normally be added, as well as a possible reduction in binder application rate,
must be made to accommodate the effects of heavier and higher traffic volumes over and above 5 000 elv/day.
31
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Amount of cutter
In the absence of a proven test method to determine the equivalent low temperature adhesion properties of modified binders
with cutters, it is recommended that the binder supplier be approached for guidelines on the amount and type of cutter to be
used for the respective modified binder in accordance with the expected road temperature.
Construction constraints
The cutting back of modified binders does not negate the need to follow good construction practices. Specific guidelines
based on local experience are given in Chapter 8: Construction.
32
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
CHAPTER 4 : MANUFACTURE
4. MANUFACTURE
4.1 General
The processes being used to manufacture polymer modified bitumens are proprietary, and different manufacturing
configurations and processes are used by the various suppliers. Some aspects are, however, common to all manufacturing
processes and the basic requirements for a blending plant for homogenous polymer modified bitumen are:
• Mixing vessels should ideally be heated with hot oil coils, instead of direct flame heating, to minimize the
degradation of the polymer at the manufacturing plant. Once on site, flame heating is the norm;
• The heating mechanism should be capable of raising the temperature of the contents of the tank by 5 - 10°C per hour;
• The manufacturing vessels should be fitted with:
- Calibrated thermometers and temperature controllers;
- A mixing system which is capable of effectively mixing the polymer into the bitumen;
- A mechanism for feeding the polymer into the bitumen;
- A calibrated dipstick.
A general flow diagram for the process of polymer modified bitumen manufacture using a high shear mill is shown in Figure 9.
The most important steps in the polymer modified binder manufacturing process are dispersion and reaction. These steps
determine the structure (i.e. morphology) of the final binder and hence its properties. Polymer, typically in either: crumb,
pellet or powder form, is added to hot bitumen into which the polymer particles disperse. The hot bitumen and additive
mixture causes the polymer particles to swell and flow. A number of factors that influence the efficiency of the dispersion
process are:
• The polymer particle size - smaller particles present a larger surface area to the bitumen, allowing faster penetration;
• The temperature of the process - bitumen will penetrate the poly-mer more rapidly at higher temperatures;
• The polymer incorporation system - must be capable of rapidly wetting the polymer and uniformly dispersing it
throughout the contents of the vessel;
• The dispersion system – typically a high shear mixer which is required to disperse and dissolve the polymer;
• The type and brand of polymer.
A general overview of the manufacture of the various types of polymer modified binders is given overleaf:
33
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
CHAPTER 4 : MANUFACTURE
The residual SBR component is dissolved in the bitumen by agitation and pump circulation. The agitation/circulation time and
manufacturing temperature required is a function of the polymer/bitumen compatibility, with extended mixing times and
higher mixing temperatures being required for less compatible systems.
If the heated product has to be stored in the manufacturing vessel for any reason, it is advisable to agitate or circulate the final
product during storage, to prevent possible polymer segregation.
It is important that the water be completely expelled in the manufacturing vessel before discharge. Residual water can cause
further foaming during heating in binder distributors and haulier tanks, with the possibility of boil-over.
The rate of addition of the polymer to the manufacturing vessel should be carefully controlled. If the addition rate is too high,
polymer conglomerates could form on the surface, resulting in lumps, which could be problematic during application of
the binder.
Similar to SBR modified bitumen, it is advisable to have some means of circulation in the vessel to prevent possible polymer
segregation during storage of the heated binder.
A schematic of a typical mixing process of SBS modified bitumen is given in Figure 10.
4.2.3 RET
Although this type of polymer is in pellet form, high speed shear mills are not required, and only agitation is necessary to
blend the polymer with the bitumen. After the reaction has taken place, the modified binder is ready for use or shipping
to site.
4.2.4 EVA
EVA polymer is incorporated into bitumen by adding the polymer pellets while stirring or circulating the contents of the
mixing vessel. The polymer melts in the bitumen and a short period is required for the polymer to dissolve completely. As
with SBR and SBS modified bitumen, the compatibility of EVA with the base bitumen should be assessed.
A schematic of a typical mixing process of EVA modified bitumen is given in Figure 10.
34
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
CHAPTER 4 : MANUFACTURE
Special manufacturing equipment is required to manufacture this highly viscous material. The product has a limited useable
life of 4 - 6 hours, and therefore manufacture usually takes place on site or very close to it.
When bitumen-rubber binder is used for surfacing seal applications, it is applied with binder distributors specially designed
to handle this highly viscous binder. In these applications, the bitumen-rubber binder is manufactured using the “wet-
blend method”, whereby the rubber is added to and digested by the hot bitumen. Two processes can be employed for the
manufacture of bitumen-rubber asphalt: the “wet-blend method” as well as the “dry-blend” method whereby the rubber is
added to the aggregate in the same way as filler. The wet-blend method is used in the majority of cases.
The extender oil could either be added to the penetration grade bitumen before delivery, or to the bitumen on site. The
bitumen is pumped into the small blending tank at a temperature of not more than 220°C for short periods before the
introduction of rubber in proportion to the bitumen flow rate. The blending unit consists of a small tank equipped with a
high speed stirring device which ensures proper “wetting” of the rubber, and prevents the formation of rubber lumps in the
final product. During the addition of the rubber component, the blend cools down considerably and has to be re-heated to
a temperature of 190 - 200°C to ensure proper digestion of the rubber. From the blending tank the product is transferred to
a digestion tank which could also be a specialised binder distributor. During the digestion period the product is continually
agitated while being heated to the final temperature.
35
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
CHAPTER 4 : MANUFACTURE
On completion of the digestion period, a hand-held Haake viscometer is used to perform a viscosity test on the product to
confirm that sufficient digestion has taken place. If approved, the product is ready for application.
High speed
Bitumen Mixing Chamber
Secondary rubber-crumb hopper
Rubber-crumb
inlet
Auger feeder
High speed
Mixing Chamber
Primary rubber-crumb hopper
Super-heated
bitumen inlet
High speed
Blended bitumen rubber
mixer
To reaction vessel
Sufficient mixing time should be allowed to ensure acceptable distribution of the bitumen throughout the aggregate/rubber
blend. The bitumen temperature should be 145 – 165°C and the asphalt leaving the pugmill should be at a temperature
ranging from 190 – 210°C. The mix is then transferred to the hot-storage bins where it is left for at least an hour to allow for the
digestion of the rubber by the bitumen. The asphalt is drawn from the bins and transported to site as required.
Practitioners tend to be sceptical of the dry blend method, because of the inability to determine the properties of the
bitumen-rubber binder in the mix. Hence the use of this method is generally only justified if small quantities of bitumen-
rubber asphalt are required for emergency repairs. The wet blend method usually involves substantial establishment costs of
the blending unit, which are only justified for larger projects.
4.4.2 Pre-blending
Where raw materials are required to be pre-blended, procedures should be established and documented for proportioning,
mixing and storing the blended material.
4.4.3 Mixing
Component materials should be thoroughly mixed to ensure production of a homogeneous modified binder. The design
of mixing equipment varies considerably depending on the type of binder being manufactured. They can vary from high
shear mills used to blend SBS pellets, to low shear agitators for blending rubber crumbs. However, critical elements that are
common to all processes are procedures for proportioning of materials, temperature control, mixing time and conditions, and
maintenance and cleanliness of equipment.
36
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
CHAPTER 4 : MANUFACTURE
37
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
For this purpose a generic system has been developed for classifying modified binders according to four main criteria based
on application type and temperature, type of polymer used, and a numerical value. The following codes are used to designate
the different classes of modified binders:
• Type of application:
- Spray seal (S);
- Asphalt (A);
- Crack sealant (C).
• Type of binder system:
- Emulsion – If the product is an emulsion then the letter C would follow directly after the letter indicating
the type of application;
- Hot applied – No letter is used after the letter indicating the type of application.
• Predominant type of modifier used:
- Elastomer (E) e.g. A-E1;
- Plastomer (P) e.g. A-P1;
- Rubber (R) e.g. S-R1;
- Hydrocarbon (H) e.g. A-H1.
• Level of modification:
This is indicated by a numerical value. The higher the number the higher the softening point value of the binder, but
this does not necessarily imply improved overall performance properties. The intention is to provide for higher order
modification in the future, should the need arise, by increasing the numerical value.
An additional code can also be used for classification purposes to indicate whether or not the use of a fluxing agent or cutter
is permitted. Should the binder application not permit the use of flux or cutter the letter “t” should be shown in brackets after
the classification.
Table 4 summarises the different classes of generic modified binders according to their end application.
38
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Notes
1
These emulsions have the option of being made with or without cutters depending on their application.
2
Some of the modifiers in these classification classes are also capable of imparting fuel resistant properties.
More details pertaining to the selection and properties of these modified binders and their specialist application are covered
in Chapter 7.
39
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
6. PRODUCT REQUIREMENTS
In developing the product requirements for each generic class of binder an attempt has been made, where possible, to use
the same testing regimen with appropriate compliance limits. However, this is not the case for polymer modified binders
compared to bitumen-rubber due to the distinct nature of the composition and behaviour of these two binder types.
The tests prescribed in the specification framework have been selected to ensure that:
• The consistency of binders is controlled at the various in-service temperature ranges:
- Low temperature to limit fatigue cracking (Elastic Recovery @ 15°C)
- Elevated temperature to limit rutting and bleeding (Ring & Ball Softening Point)
• Modified binders used in road surfacings can be expected to perform over a range of climatic and traffic conditions.
The specification framework has been based on a wide range of softening point values to accommodate South Africa’s
typically hot climate.
• The binder is pumpable (Viscosity @ 165°C), safe (Flash point) and stable (Storage Stability @180°C) during normal
handling and storage conditions.
• The performance is within acceptable limits after ageing when subjected to the rolling thin film oven test (RTFOT).
The test limits prescribed are empirically based on observed in-service performance over several years, and reflect current
production trends in South Africa. While the ultimate goal is to formulate performance related specifications, the industry
is currently not in a position to prescribe tests and associated limits which would render this possible. However, for a given
project, it may be necessary to perform additional tests to rank the properties of the various binders in order to reduce risk.
The properties for the various modified binders and their respective applications are given in Tables 5 - 10.
Table 5: Properties of hot applied polymer modified binders for surfacing seals
Notes
1
The softening point values obtained for bitumen modified with SBS will tend to fluctuate over time and on reheating.
Road surfaces could become too rigid at low overnight temperatures with resultant poor adhesion properties.
2
Certain base bitumens, when used in the production of modified binders, are prone to cause segregation of the
modified binder. The Storage Stability test result should be interpreted as an indicator of the compatibility of the base
bitumen and the modifier used. In cases where compliance limits are not met, proposals of site agitation procedures
of the binder to prevent segregation shall be submitted to the client for consideration. In all cases whenever there
is any reason to believe that the composition of the base bitumen has changed, the test shall be repeated to ensure
compliance or to determine the need for measures to prevent segregation
3
Mass loss gives an indication of the presence of volatiles in the binder.
40
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Class
Property Unit Test Method
SC-E1 SC-E2
1
Binder content (m/m) 65-68 70-73 65-68 70-73
% MB–22
Notes
1 For steep inclines, severe cross fall and higher application rates it is advisable to use the higher binder content
emulsion to reduce runoff.
2 Pour the emulsion through the larger sieve to remove the skin and larger particles before passing the emulsion
through the finer sieve.
3 Either the rotary vacuum or the simple evaporation method can be used. For on-site testing the simple method is
more practical and is thus recommended. The simple method retains most of the fluxing oils whereas these are
removed in the rotary vacuum method. The latter method renders a better indication of the binder properties after
in-service curing.
41
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Note
1
Certain base bitumens, when used in the production of modified binders, are prone to cause segregation of the modified binder. The
Storage Stability test result should be interpreted as an indicator of the compatibility of the base bitumen and the modifier used. In
cases where compliance limits are not met, proposals of site agitation procedures of the binder to prevent segregation shall be
submitted to the client for consideration. In all cases, whenever there is any reason to believe that the composition of the base
bitumen has changed, the test shall be repeated to ensure compliance or to determine the need for measures to prevent segregation.
Care should be taken when changing suppliers of A-E1 and A-E2 modified binders, as the influence of warm mix technology
could have a significant influence on the compaction temperature, depending on the source of base bitumen used. It is
recommended that a new compaction temperature be established in such cases by compacting at different temperatures.
The compaction temperature that matches the void content of the original mix design should then be used. The suppliers of
modified binders must inform their clients of the presence of warm mix technology products in their binder.
42
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Test Class
Property Unit Method S-R1 A-R1
Softening Point °C MB-17 55-65 55-65
dPa.s
Dynamic Viscosity @ 190°C MB-13 20-40 20-50
5
minutes > 70 > 80
Compression recovery 1 hour
> 70 > 70
% MB-11
24
hours > 40 n/a
Resilience @ 25°C % MB-10 13-35 13-40
Flow mm MB-12 15-70 10-50
Note
Certain base bitumens, when used in the production of modified binders, are prone to cause segregation of the modified binder.
1
The Storage Stability test result should be interpreted as an indicator of the compatibility of the base bitumen and the modifier used.
In cases where compliance limits are not met, proposals of site agitation procedures of the binder to prevent segregation shall be
submitted to the client for consideration. In all cases whenever there is any reason to believe that the composition of the base bitumen
has changed, the test shall be repeated to ensure compliance or to determine the need for measures to prevent segregation.
43
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Test Class
Property Unit Method C-E1 CC-E1
1
C-R1
2
Softening point °C MB-17 ≥80 ≥70 55-65
2
Elastic recovery @ 15°C % MB-4 ≥80 ≥50 -
Dynamic viscosity @ 190°C dPa.s MB-13 - - 20-40
Dynamic viscosity @ 165°C Pa.s MB–18 ≤0,65 - -
Dynamic viscosity @ 25°C Pa.s MB–18 - ≤0.8 -
Resilience @ 25°C % MB-10 - - 13-40
Flow mm MB-12 - - 15-70
Binder content (m/m) % MB-22 - ≥55 -
Notes
1
CC-E1 is suitable for 2 - 4 mm cracks. For wider cracks use C-E1 or C-R1.
2
Value to be determined on the residue after recovery of the binder by evaporation method MB-20.
Emulsions used in conventional slurries are manufactured from 70/100 bitumen, which has a minimum softening point of
only 42°C. The addition of an elastomer improves the adhesion of the binder to the aggregate, thus reducing the loss of
aggregate, especially in the early life of the seal. In the case of rut-filling, the elastomer, in conjunction with a harder grade of
base bitumen, will increase the consistency of the binder at high in-service temperatures and thus increase the rut resistance
of the mix. It must be noted that the elastomer component in the mixture is not sufficient to prevent reflective cracking in the
new surface.
The recommended limits given in Table 11 are for a quickset cationic bitumen emulsion modified with an elastomer which is
used with a continuously graded crusher dust and applied by a continuously mixing machine. The emulsion must be specially
formulated to allow for a period of between 90 and 120 seconds when mixed with the selected aggregate, to ensure sufficient
setting time of the mix during placing.
44
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Table 11: Properties of polymer modified emulsions for machine- applied microsurfacing
Class
AC-E2
Test Method AC-E1
Property Unit (Rut
(Overlay)
filling)
Binder content (m/m) % MB–22 62-65 62-65
710µm
Residue on sieve ≤0,1 ≤0,1
1
sieving
(/100 ml) 150µm G MB-23
sieve ≤0,5 ≤0,5
Notes
1
Pour the emulsion through the larger sieve to remove the skin and larger particles before passing the emulsion through
the finer sieve.
2
Either the rotary vacuum or the simple evaporation method can be used. For on-site testing the simple method is more practical and is thus
recommended. The simple method retains the fluxing oils whereas these are removed in the rotary vacuum method. The latter method
renders a better indication of the binder properties after in-service curing.
Additionally, the raised softening point and viscosity at elevated service temperature of hydrocarbon modified binders
will improve the deformation resistance of asphalt mixes compared to those manufactured with conventional penetration
grade bitumen. The use of hydrocarbon modified binders should be considered as a cost effective way to improve the rut
resistance of asphalt bases and wearing courses in hot climates. The use of hydrocarbon modified mixes is not recommended
in pavements with high deflections.
The properties recommended for hydrocarbon modified binders for use in high modulus asphalt are shown in Table 9.
45
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Tests have been developed for measuring the fuel resistant properties of asphalt mixes. Two standards are in use in Europe,
one being EN 12697-43 and the other the French standard NF P 98-251-1. The EN standard involves soaking the asphalt
briquette in fuel for a period followed by brushing in a Hobart mixer. The material loss of the briquette is a measure of the
resistance of the asphalt to fuel. The French method is based on the Duriez test and involves soaking an asphalt briquette in
kerosene for 7 days and comparing the dry strength to the soaked strength similarly to the immersion index for adhesion.
When requesting a fuel resistant binder for asphalt wearing course, it is recommended that the supplier quantifies the fuel
resistant properties of the binder in accordance with these two standards in terms of percentage mass loss or loss of strength.
This will provide a tool to rank the fuel resistance of the different binders along with the other performance parameters being
considered for the project.
In cases where pick-up of the tack coat may occur, e.g. by trucks or asphalt pavers, it would be necessary to use a special
polymer modified emulsion, known as “trackless tack”. These emulsions are characterised by having rapid setting
characteristics, and the residue deposited on the road surface is less tacky that the residue obtained from conventional tack
coat emulsions.
The emulsion must be formulated to enable it to be applied through a spray bar positioned on the asphalt paver, immediately
preceding the placing of the asphalt. The properties of the residual binder are enhanced by the elastomer, while the viscosity
of the emulsion should be low enough to allow the product to be easily sprayed. The enhanced binder consistency must be
such as to minimise the migration of the binder into the new thin layer to prevent flushing and the subsequent closing up of
the surface texture under traffic. The elastomer also helps improve the adhesion of the new thin layer to the existing substrate
under severe traffic action.
The properties of a modified emulsion used as a tack coat for UTFCs are similar to those for SC-E1 (65-68% binder content)
shown in Table 6, which outlines the properties for polymer modified emulsions for surfacing seals.
It must, however, be noted that the following requirements should be taken into consideration:
• No cutter may be used in the formulation of the emulsion, as this will lead to solvent entrapment in the new surface,
increasing the risk of bleeding;
• The viscosity requirements are lower (i.e. 21-100 SFs @ 50°C) given the need for the emulsion to be sprayed at lower
application rates and to be able to flow more readily on application.
46
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
7. SELECTION CRITERIA
Modified binders are more expensive than conventional binders. The decision to utilise a modified binder should therefore
always be made on the basis of “value engineering” and not “fashion”. However, the cost premium of utilising these binders
can frequently be justified by improved performance and/or extended service life of the constructed layer. Table 12 provides
a guideline to the advantages and disadvantages of modified binders compared with conventional binders to assist in the
selection process.
Table 12: Advantages and disadvantages of modified binders compared with conventional binders
47
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
The characteristics and behaviour of modified bitumen can differ significantly from that of conventional bitumen. As
discussed in Chapter 3, they are generally more viscous, cohesive and resilient, which can influence, to a greater or lesser
degree, aspects such as surfacing seal and/or asphalt design procedures, handling and storage of the binder, climatic
condition limitations during construction, as well as construction techniques and limitations.
Experience has shown that modified binders are very sensitive to poor aggregate/binder adhesion immediately after
construction, and if extreme climatic conditions are expected, the use of such products must be selected with caution. Thus,
the simple substitution of conventional bitumen with a modified product, without taking aspects such as the above into
account, will probably result in sub-optimal performance and possibly premature failure.
The selection of modified binders should thus always be based on specific needs and particular constraints and should never
be regarded as a substitute for good design and construction practice.
Modified binders have been classified according to the application in which they are expected to perform. Some
recommendations on the most appropriate product for a given primary in-service requirement, substrate condition and/or
component availability are given below. Also highlighted are some constraints related to the use of these products.
When the field conditions or demands are such that none of the selection criteria necessarily apply, specialist advice needs to
be obtained.
With the exception of SAM or SAMI layers, it could be argued that the use of conventional bitumen would be appropriate
in the majority of surfacing seal applications in South Africa. However, the sustained increase in traffic volumes, as well as
loading spectrum on some routes, results in many instances where the historically proven performance range of conventional
binders is being exceeded. Thus, in many instances the use of modified binders could extend the range with respect to the
appropriateness of surfacing seal applications as a result of:
• Increased binder application rate (for early aggregate retention);
• Increased binder application rate (to improve impermeability);
• Improved shear strength for high stress situations e.g. turning traffic;
• Reduced risk of bleeding (increased binder cohesion) under high in-service temperature conditions (>60°C);
• Reduced sensitivity to daily fluctuations of in-service temperatures;
• Limiting, or delaying, reflective or thermal cracking;
• Increased durability (increased binder film thickness).
It should however be noted that the binder is only one element of a surfacing seal system, and that all aspects such as climate,
aggregate, design and construction must be considered prior to selecting the most appropriate binder.
The risk of early, and sometimes catastrophic, aggregate loss can be reduced by considering some of the following measures:
• Seal type: single seals are the most vulnerable, especially those with larger ALD aggregates (i.e. 19 mm versus 6.7
mm). The use of double seals significantly reduces the risk of aggregate loss by improving the aggregate interlock;
• Cover sprays: the application of a diluted/undiluted cationic spray grade emulsion can reduce the risk even further
48
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
as the binder helps glue the aggregates together. The use of conventional binder for the second spray of the double
seal could also be considered;
• Delay in trafficking: local experience has shown that a significant reduction in early aggregate loss can be achieved
if traffic is kept off the newly constructed seal for 24 - 48 hours. Continuous rolling and brooming, especially during
the warmer period of the following day or two, is however necessary to achieve this reduction in aggregate loss;
• Adhesion agent: it is becoming standard practice to add an adhesion agent to the binder to improve its aggregate
wetting and/or adhesion properties. Unless the stability (and thus effectiveness) of the product has been adequately
proven, the adhesion agent should only be added immediately prior to spraying (up to 30 minutes), typically at a rate
of 0.3 - 0.5% v/v) and circulated in the spray tanker;
• Road surface temperature: the minimum surface temperatures for surfacing sealing with the respective modified
binders are given in Table 13 as a guideline;
• Cutting back: while the addition of a cutter may solve, or reduce, a potential adhesion problem in the short term,
problems have been experienced with respect to bleeding/flushing of the surface during subsequent hot periods,
especially in heavy duty applications. This practice should only be considered when spraying at the end of the
summer season before the onset of winter. The use of cut-back modified binders (winter-grades) has, however, been
successful in relatively light duty applications, such as residential streets. Refer to Chapter 3 for information covering
the procedures and performance risks associated with this practice.
S-E1; S-E2 25
SC-E1; SC-E2 10
S-R1 25
Note
1
The supplier’s method statement should also be noted.
CHAPTER 7
1 : SELECTION CRITERIA
SC-E1 or SC-E2 binders is specified in areas of steep inclines and/or high superelevation. The required application rates
may be such that significant run-off of the binder could occur prior to the application of the aggregate.
In some instances, however, there may be insufficient funding to implement the most appropriate, though costly, intervention
strategy for a long term solution. In such cases the use of modified binders in seals constructed as a temporary holding action
is an option that may be utilised to reduce the rate of deterioration of the pavement and/or its functional properties.
• Retained moisture: where the surface to be sealed is cracked or open textured, and there is a likelihood of excess
moisture within the layer, the use of a highly modified binder in any resealing application should be viewed with
extreme caution. Due to their high cohesion properties, highly modified binders do not permit the escape of any
moisture entrapped below the seal, resulting in fairly rapid stripping of the binder from the aggregate in the
underlying layer – the so called “pressure cooker effect”. This is especially prevalent where the substrate consists of an
asphalt layer. Stripping of the binder has also been observed where the substrate is a surface seal overlying a granular
base, but it would appear that the rate of stripping occurs at a slower rate, probably as a result of the thicker binder
film prevalent in seals. In such circumstances it would be preferable to apply the seal only after a prolonged dry
period. If this is not possible consideration should be given to utilising an unmodified binder which permits the
release of moisture and then has the ability to “self-heal” during the warmer periods once the pressure of the water
vapour has dissipated.
Therefore, the selection of the most appropriate modified binder type should always take into account the following:
• Distance from blending plant;
50
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Where any of the above situations are pertinent, consideration should be given to the utilisation of an appropriate modified
emulsion binder class.
TRH3: Design and construction of surfacing seals provides guidance for the selection of the most appropriate binders for given
traffic and climatic conditions. Table 14 provides additional guidelines for the selection of the most appropriate binder for a
given stress condition.
51
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Steep gradients ✓ ✓ ✓
Entrapped moisture ✓2 ✓2
Notes
1
Suitable for new construction or reseal projects where traffic accommodation is not a problem.
2
Where there is a high risk of moisture entrapment (especially in underlying asphalt layers) the use of an unmodified binder should be
considered.
3
A number of cases have been reported where early cracking or crack reflection has been attributed to the sensitivity of S-E2 to cold
temperatures.
4
Where other factors responsible for possible degradation of the heated product could occur such as long haul distances from the
blending plant, disruptions to construction or small areas to be sealed over consecutive days, unmodified binder should also be
considered.
7.2 Asphalt
7.2.1 Hot mix asphalt
Not all bituminous binders for hot-mix asphalt (HMA) require modification. The addition of modifiers and other additives is
dictated by technical objectives that need to be met. These could include:
52
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
The decision whether to incorporate a modifier or additive in an HMA mixture, and if so, what class, should always be based
expert analysis of service conditions and/or fundamental engineering requirements such as:
• Predicted spectrum of traffic loading;
• Predicted in-service pavement temperatures that will influence the risk for rutting or low temperature fracture;
• Stiffness or resilience of the substrate;
• Degree and extent of existing distresses prior to rehabilitation;
• Generic type of mix selected e.g. stone or sand skeleton.
The incorporation of modifiers or additives into HMA may improve the performance characteristics of the layer and
enhance the durability of the mix, which ultimately may result in an extended service life and reduced maintenance. It is,
however, important to recognise that the incorporation of a modifier or additive is only part of the process of improving the
performance of HMA; the aggregate packing configuration is another.
Although each modifier or additive may offer certain benefits over conventional binders, there are no universal solutions to
the challenges posed. Sometimes, one property of HMA is improved, but at the expense of another. At any time one should
ensure that proper practice is followed in pavement/mix design and construction procedures. Then, and only then, should
one consider how engineering of the binder will address the design objectives.
53
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Table 15 lists some common binder modifiers and additives used in HMA and the general purpose of their use:
54
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
The improvement to rut resistant properties of an HMA mix resulting from the incorporation of a modified binder is well
documented and widely accepted. This is especially true for sand-skeletal mixes. However, notwithstanding the above, the
need to comply fully with all the other fundamental mix design criteria, especially the volumetric properties, cannot be
over emphasised.
As implied by the binder classification, binders conforming to the A-P class requirements have been formulated specifically
to enhance the rut resistance properties of asphalt. The use of this class of binder should however be restricted to layers
constructed on a relatively stiff support as their fatigue properties are generally limited (with the possible exception of EVA).
Class A-E binders have to date been the predominant binders used in HMA modification. Notwithstanding the fact that they
are classed as “elastomers” their increased stiffness at elevated temperatures can contribute to the rut resistant properties of
the mix. In addition, their use is more appropriate on support structures that are more flexible than those preferred for
the A-P Class.
Class A-R binders also contribute to deformation resistance and have the added benefit of significantly improving fatigue
properties. However, their use is generally restricted to open or semi-open graded mix types, which may not be appropriate
on substrate layers that are permeable or aged and sensitive to the ingress of moisture, unless the mix, in the case of a semi-
open grading, can be rendered virtually impermeable by the use of a fairly high percentage of A-R binder.
7.2.1.2 Cracking
Fatigue cracking occurs due the cumulative effect of repeated traffic loading, particularly when the stiffness of substrates is
low or has been reduced. Modified binders can be effective in increasing the fatigue resistance of HMA for a given strain level.
However, if the strain levels are too high it is doubtful whether any binder class would be effective. In such cases, a surface
dressing manufactured with a modified binder (typically an A-R class) could be considered as a holding action.
Shrinkage cracking as a result of seasonal moisture changes and/or cementitious stabilisation can vary greatly with respect
to the degree of strain and activity. The use of A-E and A-P class binders in dense graded mixes has proven to be generally
ineffective in reducing reflection cracking. Mix types that permit relatively high quantities of modified binder such as SMA
and semi-open graded mixes have been used successfully in certain instances. In low volume applications the use of mixes
incorporating softer standard bitumen, as well as higher bitumen contents, would also reduce reflection cracking, but
resistance to permanent deformation could, as a consequence, be significantly compromised particularly in sand
skeleton mixes.
55
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Environmental cracking (top down) occurs as a result of binder ageing and/or temperature changes such as freeze-thaw.
The use of modified binders generally permits higher binder film thickness in the mix with a resultant reduction in the risk of
premature ageing. Where an existing asphalt surface exhibits signs of ageing it may be necessary to pre-treat the surface (e.g.
fog spray) to ensure an adequate bond with the new modified HMA overlay.
For certain mix types such as SMA and open-grade mixes, the use of a modified binder may be appropriate for purposes other
than improvement to rutting or fatigue resistance properties. For example, they could be used to prevent drain down of the
binder during transportation and placing. The use of these binders may replace, or be used together with, other products,
such a cellulose fibre.
The design of asphalt mixes incorporating modified binders should follow the standard procedures currently in use. Due to
the non-Newtonian behaviour of modified binders, selection of appropriate mixing and compaction temperatures requires
careful consideration. Incorrect selection of these criteria will result in erroneous determination of the volumetric properties
of the mix which are critical quality control elements. Due to the reduced workability resulting from the addition of certain
types of modifiers, for a given binder content, modified binders may cause an increase of the voids in mix of between 0.2 and
0.4% above that obtained for standard bitumen.
All modified binders have a limited shelf life. This has traditionally been true for the A-R class of binder maintained at
application temperatures. Recent developments in this technology have, however, enabled the periods of stability of the
mix to be extended. Such products are, however, still currently “proprietary” in nature, and as such, are not covered in
this publication.
The logistic issues surrounding the use of modified binders, (e.g. blending and storing) should always be taken into account
prior to their selection. Where only small quantities of HMA are required, or where daily production requirements are relatively
low, the appropriateness of their use from a cost premium perspective should be carefully considered. In such instances,
modified binders with a high storage stability or modifiers that can be incorporated directly into the mixer’s pugmill or
bitumen feed pipe (i.e. do not require pre-blending with the bitumen) should be considered.
Below is a summary of this method of producing and laying asphalt with specific reference to modified binders. For more
details the reader should consult Sabita Manual 32: Best practice guideline for warm mix asphalt.
There are numerous advantages to WMA, some of the important ones being:
• Environmental Benefits:
- Reduced consumption of non-renewable fossil fuels and greenhouse gas emissions;
- Reuse of by-products which would otherwise require disposal;
- Increased potential for recycling reclaimed asphalt.
• Health benefits:
- Improved conditions for workers and neighbouring communities.
• Engineering and economic benefits:
- Improved workability which aids compaction and facilitates hand work;
- Flatter thermal gradings – yielding extended compaction windows and enabling night work and accommodating
longer haul distance;
- Reduced binder ageing.
While a number of technologies that facilitate the manufacture and laying of WMA do not always involve bitumen additives as
such, some technologies may alter the consistency or rheological properties of the asphalt binder during the manufacturing/
construction process and are listed below for information.
56
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Water technologies
Chemical additives
These technologies are based on additives that have little effect on the binder’s rheological properties and act mainly by
reducing the internal friction of the mix, enabling it to be compacted at the lower temperatures. Some additives also improve
adhesion of binder to aggregate and resistance to moisture damage.
Rheological modifiers
This broad category includes products that modify the rheological properties of the binder, by reducing its viscosity at mixing
and paving temperatures thereby improving aggregate coating and compaction. At in-service road temperatures the binder
stiffens, improving resistance to rutting.
Hybrid polymer modification is considered a sub-class of rheology modifier where the principle of co-modification
technologies is being used. Such technologies typically employ the combination of an elastomer and a plastomer, sometimes
enhanced with the introduction of a chemical crosslinking agent to facilitate a more homogenous modified binder with
improved elastic recovery characteristics.
These modifiers differ from the others in this class in that they typically decrease the viscosity of the binder in the liquid state
when compared to virgin bitumen. The viscosity of the bitumen, however, is increased upon cooling of the asphalt after
construction, resulting in improved asphalt stability and rut resistance.
57
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
CHAPTER 8 : CONSTRUCTION
8. CONSTRUCTION
8.1 Introduction
The use of modified binders in both asphalt and surface seals is currently common practice in South Africa. The fluid
characteristics (viscosity) of modified binders are very different from those of conventional bitumen binders. An increase
in viscosity and binder cohesion (internal strength) as a result of modification of the bitumen is usually accompanied by a
decrease in the initial wetting ability (adhesion) of the binder and therefore a reduction in the initial adhesion of the binder
to the aggregate particle. This reduction in initial adhesion can have a significantly detrimental effect on the performance
characteristics of both modified asphalt layers and modified seals.
Consequently modified binders require more attention to detail and special considerations of the construction procedures to
ensure satisfactory adhesion between the binder and the aggregate in both asphalt and seals.
8.2.4 Re-constitution
It is generally not possible to reconstitute some of the modified binders if they have lost their required modified properties.
A SBS modified binder can, for instance, not be reconstituted while bitumen-rubber and SBR latex modified binders can,
in some instances, be reconstituted without any major problems. Reconstituted binders must, however, still meet the
specifications that apply to the project.
8.2.5 Contamination
Different classes or types of polymer modified binders must not be mixed, as they may be incompatible and result in a non-
useable product or a product with unknown properties. However if a small quantity (< 10%) of polymer modified binder is left
in a sprayer or tanker, it may be acceptable to top up the load with conventional bitumen for future works as this will not have
any adverse effect on the performance of the bitumen.
Although all the guidelines and best practices applicable to conventional binder asphalt and seals should always be adhered
to when modified binders are used, the following aspects should receive special attention.
Weather conditions
Modified binders (even if cut back) should not be sprayed if there is a likelihood of rain or windy conditions. Wind chill causes
the rapid formation of a skin on the modified binder, which will delay or even prevent adequate wetting and adhesion to
58
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
CHAPTER 8 : CONSTRUCTION
the aggregates. This is especially so for modified emulsions, and spraying should be postponed until conditions are more
favourable. Hot modified binders should not be sprayed in the cold months, from May to the end of August unless a special
formulation is prepared by the supplier.
The ambient temperature is an important factor when sealing with modified binders. For most modified binder applications,
the pavement and air temperatures need to be above 20°C, and higher still where wind chill is expected. Wind chill will cause
the binder to ‘skin’ more quickly and this will delay, or prevent, wetting and adhesion. Warm and dry weather conditions
before and after application of the modified binder seal are desirable. Subsequent cold and/or wet weather may result in the
aggregate stripping if the adhesive bond is not adequate.
Pre coating
Only pre-coated aggregate should be used with modified binders. The pre-coated aggregate stockpiles should be protected
against rain and dust. If heavy rain is experienced on an unprotected pre-coated aggregate stockpile, especially soon after
pre-coating, the pre-coating material will wash off.
Only dry pre-coated aggregate (i.e. “hand dry”) should be used. A sample should be taken from the pre-coated stockpile and
the material should be dry to the touch. Excessively wet pre-coating will influence the bonding time between binder and
stone significantly. If the pre-coating practice is inadequate the constructed seal might perform satisfactorily in dry and warm
weather, but will lose a considerable portion of the aggregate during the first wet and/or cold weather spell thereafter.
Presence of moisture
The presence of moisture on the surface or within the pavement layer to be sealed should be avoided. The substrate should
be totally dry prior to commencement of sealing. Where there is a risk of afternoon showers, consideration should be given
to postponing the sealing operations, especially if the road is to be opened to traffic the same day. The glass plate method
should be used to determine if any moisture is present in the layer prior to sealing. This method involves a glass plate placed
on the layer to be sealed and if no moisture vapour is present on the underside of the glass plate after approximately 15
minutes, the layer can be sealed.
Spray lengths
Due to the decrease in adhesion characteristics of modified binders, it is essential that the aggregate spreading and rolling
operations be carried out as soon as possible after application of the binder. Hence, it may be necessary to reduce the length
of spray runs substantially from those normally acceptable for conventional binders to ensure that the time delay between
binder and aggregate application and rolling is kept to the minimum.
Shady areas
Where sealing is to be done under overhead bridge structures or in localised shady areas, it is considered good practice to
commence the spray run at these areas, thereby reducing the time delay of aggregate application and rolling to the minimum.
In addition, the binder application rates could be increased by up to 20% in these areas (if approved by the designer).
Production rates
Ideally the pavement and ambient temperatures should be at least 25°C and rising prior to application of the modified binder.
It may therefore be prudent to limit the production rates by sealing only in the middle part of the day in order to reduce the
risk of aggregate loss.
Spray nozzles
The quality of the spray nozzles is of the utmost importance when spraying modified binders. The required application of
binder must be sprayed through suitably sized spray nozzles to ensure that the bitumen binder is spread uniformly on the
road surface. The nozzles should be medium size for spraying hot polymer modified binders and large size to spray more
viscous modified binders such as bitumen-rubber. All nozzles must be clean, open and function properly, and should be
regularly checked for blockages. Hot modified binders are normally sprayed with a uniform triple– or even quadruple overlap.
59
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
CHAPTER 8 : CONSTRUCTION
Cutting back of modified binders is not general practice in South Africa. The primary purpose of cutting back bituminous
binders is to soften the binder temporarily to enable it to achieve adhesion between the binder and the aggregate, and
to keep the binder soft enough to allow traffic to fully embed the aggregate into the binder. In most cases conventional
cutter oils (e.g. illuminating kerosene or aviation jet fuel) are successfully used, although some polymer modified binders
may require a particular type of cutter oil for compatibility. It must be noted that cutting back hot bituminous binders is a
hazardous operation.
The cutting back practice of modified binders is based on the same principles that apply to conventional binders, with the
amount of cutter oil added related to the class of polymer modified binder, prevailing weather conditions, traffic, aggregate
size, and type and condition of pre coating.
It is critically important to assess the applicable pavement surface temperature correctly to determine the appropriate
concentration of cutter oil. The quantity of cutter oil added should be based on the likely temperature of the shaded areas on
the pavement. The expected prevailing weather conditions for the following few weeks should also be considered. If in doubt,
the cutter oil requirement should be based on the worst of the expected conditions. Where a cutter has been added to the
modified binder the following should be noted:
• No spraying of cutback modified binder should take place after 14h00, however rolling should continue until later in
the afternoon;
• The road should ideally be kept closed to traffic overnight, especially in higher traffic situations, and rolling should
continue the next morning;
• The road should only be opened to traffic when the road temperature has risen above 15°C;
• The cutting back of a modified binder will result in a lowering of its viscosity and density, hence the application rate
and spraying temperature should be adjusted accordingly.
Contingency plan
Even if all best practice guidelines have been followed with respect to design and construction of the modified binder
seal, the unpredictability of weather or other influences, such as plant breakdowns and unforeseen delays, could result in
unexpected but significant early aggregate loss. It is therefore considered good practice always to have a contingency plan in
place should such situations occur. Such plans should include provision for:
• Emergency closure of the lane at any time (day or night) with appropriate traffic accommodation measures in place;
• Longer term lane closures with additional rolling during the warmer part of the day;
• Application of a fog spray as soon as possible.
Binder-aggregate adhesion
To ensure adequate adhesion a field check should be made by lifting an aggregate particle from the modified binder about
one minute after spreading or by dropping it into freshly sprayed binder. The aggregate should retain a coating of binder as it
is removed from the sprayed binder. Little or no adhering binder can indicate a need to cease work or to vary procedures (e.g.
extended rolling) to ensure adequate adhesion between the binder and the aggregate.
The section of surfacing seal should not be opened to traffic unless there is reasonable confidence that early aggregate loss
will not occur.
Adhesion agent
The addition of an adhesion agent to promote bonding of the modified binder with the aggregate particles is common
practice. In most instances, double the amount of adhesion agent is used in relation to conventional bitumen. The adhesion
agent selected must be compatible with the type of modified binder and the aggregate.
Most commonly used adhesion agents are not heat stable and should not be added to a tanker or other storage tanks long
before use. The adhesion agent should ideally be added to the sprayer about half an hour prior to spraying and the binder
must be thoroughly circulated.
Repeated dosage of adhesion agents to compensate for loss of effective-ness in storage can have an adverse effect on the
adhesion. The stability of adhesion agents is dependent on storage temperature as well as type of adhesion agent, and should
be verified by the supplier.
60
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
CHAPTER 8 : CONSTRUCTION
8.2.7 Asphalt
The following matters should be taken into consideration during the construction of asphalt layers with modified binders:
Asphalt mixes incorporating modified binders are generally constructed in a way similar to that of conventional mixes, with
the exception that the compaction temperature required can generally be higher depending on the type and percentage
of modifier used. The rule of thumb is that the temperature should be increased by 2.5°C for every 1% modifier added to the
base binder. This is not applicable to FT wax and EVA – see notes below.
It is recommended that information on the temperature-viscosity relationship relevant to the modified bitumen in use
be obtained from the binder supplier on a regular basis to ensure that appropriate temperatures are adopted for various
operations.
Trial section
A trial section is of utmost importance if modified binder asphalt is to be constructed. At least 100t of asphalt mix should be
used in this section to facilitate a thorough investigation of the plant mix properties and all equipment and rolling techniques
and patterns.
Haulage
The trucks transporting modified asphalt from the production plant to the site should be insulated and equipped with
suitable tarpaulins to ensure a minimum loss in temperature of the mix between the production plant and the site. The
haulage limit should be about 4 hours and not more than 2 hours should lapse between arrival of the mix on site and
completion of compaction.
Weather conditions
Weather conditions play an important role in the time available for compaction of the asphalt mix because of their effect on
the rate of cooling of the modified asphalt.
Thick asphalt layers (>40 mm) can be paved at near freezing temperature conditions. Thinner asphalt layers cool more quickly
and the minimum air temperature should be about 10°C higher than for thick asphalt layers. Rain and especially wind can
have a marked effect on the cooling of asphalt layers. On a windy day it may be found that the modified asphalt layer cools
down to below the minimum compaction temperature too quickly to obtain the required density.
Paving of the modified asphalt layer should not continue if rain is likely to occur before compaction of the layer to the
required density can be achieved.
Construction requirements
The higher temperature requirement for modified asphalt mixes dictates that particular care must be exercised to ensure that:
• There is adequate compaction plant available to ensure that compaction of the layer is completed within the
compaction temperature window;
• Appropriate rolling patterns are determined during the construction of the trial section and employed to expedite
the achievement of the required compaction;
• The elapsed time between mixing and placement of the modified asphalt is minimised to avoid excessive cooling of
the mix;
• There is a continuous supply of mix to the paver to limit the number of joints as hand work on modified asphalt is
difficult. A material transfer vehicle should be given serious consideration when paving modified asphalt;
• The water sprayed on the roller tyres should contain a release agent to prevent pick-up of the compacted mat during
the compaction of the asphalt;
• Environmental, health and safety obligations are not compromised.
When EVA modified asphalt is used as a binder in asphalt it is important to ensure that the necessary crystalline structure has
formed in the binder. This can be observed with the mat moving during the compaction process when the temperature of the
mix is too high.
61
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
CHAPTER 8 : CONSTRUCTION
An exception to the above is when the binder is modified with an F-T wax, which has significantly lower viscosity compared
to conventional modified binders at equivalent mixing/compaction temperatures. The appropriate compaction temperatures
must be adjusted accordingly otherwise there is a high probability that the paved layer will:
• Exhibit excessive movement under the rollers;
• Develop permanent fine shear cracks allowing ingress of moisture;
• Become over-compacted with associated premature flushing/bleeding of the surface.
Pre coating
Aggregate to be pre-coated for use on asphalt layers should be coated using bitumen that is not softer than 50/70
penetration grade. The reason for this is that a thick film of bitumen is needed on the aggregate to ensure a good adhesion
between the pre-coated aggregate and the asphalt mat in which the aggregate has a thin film thickness.
62
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
On-site heating of modified binders is done with flame tubes that protrude into the tank space. Diesel burners are mainly
used and these types of burners are also rapidly replacing LPG burners as a means of heating on road and spray tankers. The
temperature on the outside of the tube which comes into contact with the binder is in excess of 300°C. By nature, bitumen is
a poor conductor of heat and heat transfer takes place through convection when the bitumen is in a fluid state. Therefore, it is
imperative that during the heating of a hot-applied modified binder that the following steps are taken to counteract localised
overheating of the binder in the vicinity of the flue pipes and possible degradation of the polymer:
• The tank should be designed with a circulation system to ensure that there is a constant movement of binder over the
flues during heating;
3
• It is recommended that tanks which have a volume in excess of 20 m be equipped with double flue pipes;
• In the event of having to superheat the binder above 180°C it is essential that tanks are fitted with augers or stirrers to
prevent localised overheating;
• The binder should be stored at the minimum pumping temperature, not at the application temperature, and should
only be heated to the application temperature just prior to use to limit degradation of the polymer;
• The binder should not be allowed to solidify in the storage tank as reheating will result in localised overheating
around the flues. It should rather be heated intermittently over an extended period to maintain a constant storage
temperature;
• Rapid heating of the binder should be avoided. As a rule-of-thumb the rate of heating should not exceed 15°C per
hour unless the tank is fitted with an agitation mechanism;
• Radiation losses can be minimised by adequate insulation, which will also reduce heating time;
• All tanks are to be fitted with calibrated temperature gauges. In the case of a sprayer a temperature gauge should be
fitted on the spray bar as well as the tank to ensure that the binder is sprayed at the correct application temperature;
63
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
• All established modified binder storage facilities should strive to install temperature recording devices with automatic
temperature controls for heating;
• A method statement on the correct handling and storage temperatures for the modified binder should be obtained
from the supplier;
• A distinction should be made between heating of modified binder during transport and static storage;
• Transporters should collect the product at the required temperature and maintain an appropriate temperature
during transport;
• Temperature reductions at a rate of approximately 3 – 5°C/hour in hauler tankers, depending on ambient temperature
and regaining of the desired storage temperature, should not exceed 15°C/hour.
• Bitumen/polymer deposits will inevitably build up on flame tubes, reducing the heating efficiency and clogging
screens and filters. Removal of these deposits should form part of the periodic maintenance programmes. Switching
to oil heating should also be considered.
• Methods of heating generally used are:
- Gas;
- Diesel;
- Kerosene;
- Waste oil;
- Electricity;
- Thermal heating – hot oil;
- Heat exchange – gas/oil;
- LFO;
- Coal/steam.
The handling criteria will vary depending on the type of modified binder. This will be discussed in more detail later in this
section, but in the absence of any additional information from the supplier, Tables 16, 17 and 18 provide guidelines for the
handling of the various classes and types of modified binders.
Polymer modified binders should not be kept at their application temperatures for longer than necessary and Table 16 should
be used as a guideline. If the heated binder is not used at the end of the work shift, the temperature should be reduced
and only super-heated again prior to reuse. Generally the heating of a polymer modified binder above 180°C will result in a
reduction of its storage life. If there is any doubt about the suitability of a product after heating and storage, a sample should
be taken and the softening point should be checked against the specification.
Table 16 provides a guideline for heating polymer modified binders for normal storage and application purposes. The
suppliers of these binders must be consulted to ascertain the appropriate temperatures relevant to their specific type of
modified binder. If the recommended time period has been exceeded, samples of the binder should be taken and retested to
ensure that the properties of the binder have not degraded.
64
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Notes
1
When storing product for 48 – 240 hours it is recommended that the tank has agitation circulation.
2
If the recommended maximum holding time has been exceeded the binder should be resampled and tested to ensure compliance
with the specification.
3
S-E1 and S-E2 (SBS) can be sprayed at a maximum temperature of 195°C, but at the risk of thermal degradation.
4
A-E2 temperatures to be confirmed by practitioners and historical data.
5
C-E1 Crack sealer is stored cold.
To prevent such bitumen/polymer deposits being formed, heating of SBR modified bitumen emulsions should be very gentle,
and accompanied by mild pump circulation. Some modern sprayers are equipped with agitators which are very effective in
reducing localised over-heating on the burner flues.
No polymer degradation should occur with modified emulsions during the normal temperature range encountered in
handling and storage and shown in Table 17. Unlike their hot-applied counterparts, emulsions should not be heated during
storage but only prior to application. If polymer modified emulsions are kept in storage for any length of time it is advisable
that the binder be agitated gently from time to time.
Polymer modified emulsions are shear sensitive, so pumping must be limited and should preferably be carried out by vane
pumps or under compressed air. Where the product is transferred with positive displacement gear pumps, very high shear
forces are generated between the gears of the pumps, resulting in shearing of the emulsion. Hence, in such cases, pumping of
cold emulsion should be minimised to prevent an increase in the residue on sieving value.
As SBR droplets generally have a lower density than that of penetration grade bitumen, they will have a tendency to migrate
to the surface of the emulsion. This is reflected as a white milky layer. The separated latex, can, however, be easily re-dispersed
into the emulsion, by simple agitation.
65
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Due to the difference in density between the dispersed bitumen droplets and the continuous phase, there will be a natural
tendency for the bitumen droplets to gradually settle at the bottom of the storage tank. Storage tanks containing latex, and
modified bitumen emulsions should thus be agitated at least once per week. This can be effected by pump circulation (see
below) or by blowing air into the bottom of the tank by means of an air “spider”.
The viscosity and residue on sieving results of polymer modified emulsions generally deteriorate fairly rapidly after
manufacture of the emulsion. These emulsions should, therefore, be tested within seven days of manufacture to ensure that
realistic results are obtained for these parameters.
Polymer modified emulsions should be passed through a strainer when loading and discharging from a tank or sprayer to
remove the lumps which form due to skinning. During storage, a skin forms on the surface of the product due to evaporation
of the water phase, and pieces of skin may break off over time causing blockages in the nozzles on the sprayers. It is important
that the strainers be checked and cleaned regularly to prevent a build-up of material.
Notes
1
This applies to modified emulsions with a binder content of approximately 65% m/m.
2
This applies to modified emulsions with a binder content of approximately 70% m/m.
3
The modified emulsion should be gently circulated or stirred at regular intervals to avoid sedimentation over time.
4
If the recommended maximum holding time has been exceeded, the binder should be resampled and tested to ensure compliance
to the specification.
5
Freshly manufactured product that is transported direct to site may exceed short term handling and transportation maximum
temperatures.
66
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Figure 13 - Typical changes in viscosity values for bitumen rubber at different temperatures over time
A dual set of heating flues is required in the storage and spray tanks to heat the bitumen-rubber to the required elevated
temperature. An auger or stirring mechanism must also be installed in the vicinity of the heating flues to prevent localised
overheating and carbonisation of the binder. A positive displacement gear pump capable of pumping a liquid with a viscosity
of up to 5000 cP is required to transfer and spray the bitumen rubber binder. Only sufficient quantities of bitumen rubber
should be blended at any time in accordance with what can be sprayed or mixed within the application viscosity window of
the product. Allowance must be made for changing weather conditions and construction delays.
Proper planning and close cooperation between the supplier and contractor is essential to limit the over-production of
bitumen-rubber, which may result in unnecessary degradation of the binder over prolonged periods of heating. The product
must not be super-heated if it is not going to be used. This will enable the product to be reheated at a later stage for reuse if
it is still within specification. If it is out of specification, up to 25% can be blended with new bitumen and rubber crumbs for
spray application. In asphalt applications the use of higher proportions of degraded binder can be considered, but will in all
likelihood require additional rubber crumb to meet the specification requirements. The reader is referred to Sabita Manual 19:
Guidelines for the design, manufacture and construction of bitumen-rubber asphalt wearing courses.
67
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Table 18 shows the recommended temperatures and time limits for the short-term handling, storing, spraying, mixing and
application binders modified with bitumen rubber.
1 Refer
S-R1 170 24 150 240 210 195
to time/
1 2 viscosity
A-R1 170 24 150 240 210 190 curve
-
C-R1 165 24 - - 190 180
Notes
1
If the recommended time period has been exceeded the binder should be resampled and tested to ensure that the properties of the
binder have not degraded.
2
Minimum temperatures for asphalt manufacturing are viscosity-dependent.
9.2 Contamination
Contamination of modified binders with other bituminous binders or petroleum products can adversely affect their
performance properties. The largest risk of contamination occurs during the transporting and storage of the product. Prior to
loading by a haulier, or transferring product into site storage tanks or a sprayer, it is essential that the tank be clean, and that
it contains no other product, unless it is a dedicated tank. In that case it is essential to ensure that the product in the tank still
complies with the relevant specification. Some modified binders (e.g. bitumen-rubber and hot modified SBR binders) have
limited storage lives and are more prone to degradation during prolonged heating. Should this material be mixed with new
product, the final product could be out of specification.
When changing products, proper flushing procedures must be followed to avoid any possibility of contamination between
incompatible products that could adversely affect the product quality or possibly result in a boil-over in the case of an
emulsion. More details are provided in section 3.8 in Sabita Manual 25: Code of Practice: Transportation, off-loading and storage
of bitumen and bituminous products related to the changing of product and flushing procedures.
To ensure that the properties of the applied modified binder have not changed significantly from that of the original product
dispatched from the blending plant, the following quality control measures are recommended:
• The supplier must conduct the necessary tests on the product to ensure that it meets the specification requirements
before dispatching the product. The supplier must keep retention samples for each batch for a period of 12 months
following the completion of the project. In the case of modified emulsions this period can be reduced to 3 months
from date of manufacture;
68
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
• The supplier should supply a laboratory certificate for each batch stating the binder properties. This might not include
all the test requirements but should contain the indicative tests like softening point. The batch certificate should be
transmitted to the site electronically or delivered by the haulier driver;
• Samples should be taken from the haulier while the product is being discharged on-site, and these should be retained
for further testing in the case of a dispute. This is the responsibility of the receiving party;
• Samples should be taken from the site storage tank on a daily basis and tested prior to application. In the case of a
sprayer, samples should be taken for every load sprayed;
• Product not applied can be returned to storage and retested for compliance prior to further use;
• All samples must be clearly labelled on the side of the container and NOT on the lid, with all relevant details for ease
of identification and traceability;
• To limit the potential for a dispute arising from test results of the manufacturer and the site laboratory, it is
recommended that correlation testing be carried out between the laboratories prior to the supply of binder to
identify any discrepancies.
On commencement of a contract, the full spectrum of tests should be conducted on the first batch of the product
manufactured or delivered on site, to demonstrate the supplier’s ability to comply with the specification. Thereafter, the
respective tests should be conducted at an agreed frequency unless there is a change in the source of raw material (base
bitumen or polymer).
In the case of bitumen-rubber, the supplier must also provide a set of curves showing the changes in the flow, softening point
and viscosity with time at various temperatures relevant to the technology stated in the company’s method statement.
Tables 19, 20 and 21 provide an indication of the frequency level for all the tests required at the different stages.
Site
Property Manufacturer Haulier Sprayer
storage
Before ageing
Softening point Every batch Every load Every day Every load
Elastic recovery
Every batch Every 5th load
@ 15°C
Dynamic viscosity
Every batch Every 5th load
@ 165°C
Storage stability
Every 10th batch
@ 180°C¹
Once, at start
Flash Point
of project
After ageing (RTFOT)
Every 10th
Mass change Every 10th batch
load
Difference in Every 10th
Every 10th batch
Softening Point load
Elastic recovery Every 10th
Every 10th batch
@ 15°C load
Note
1
This test should be performed on a frequency basis or whenever there is a change in the source of base bitumen or bitumen
crude type.
69
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Site
Property Manufacturer Haulier storage Sprayer
Sample
Binder content (m/m) Every batch Every day Every load
only
Saybolt Furol viscosity
Every batch
@ 50°C
Residue on sieving
Every batch
(/100 ml)
Sedimentation after
Every 5th batch
60 rotations
Recovered binder residue
Elastic recovery
Every batch
@ 15°C
1 At the start of
Dynamic viscosity At the start of every load
every batch
Compression recovery:
5 minutes Every 5th batch Every 5th batch
1 hour
Notes:
1
Dynamic viscosity is an indicator of the product quality. Attempts should be made for viscosity to be measured at 190°C.
If the viscosity is not measured at 190°C on site its value can be determined at 190°C using the relevant temperature-viscosity graph.
70
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
The above items should be recorded in writing and form part of the quality management plan for compliance by all parties.
71
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
10.1 Sampling
All modified binders should be sampled in accordance with the procedures provided in Method MB-1: Sampling of modified
binders. MB-1 covers sampling from bulk storage, during loading, and from sprayers and drums. It is also important that the
samples are representative of the batch being tested. Hence, it is imperative that the binder be thoroughly mixed in the tank
before sampling to ensure that the binder is homogenous.
All storage tanks and spray tankers should be fitted with sampling valves and the use of a thief sampling device should
be avoided. If the spray-bar has nozzles which can be opened individually, a sample may be taken from a spray nozzle. At
no stage may an open tin can be used to take a sample from the top of a tank. The sampling valve should be located on a
circulation line with a permanent support on which to rest the container during filling. Road tankers (haulers) should not be
fitted with sampling valves as they have no means of circulating the product. Therefore, samples must be taken in-line at the
binder plant when loading, or when the product is offloaded at the site storage tank.
Appropriate sample containers must be used which are new, clean and can be properly sealed. See 10.1.2 below. All sampling
should be carried out by properly trained personnel. It should be noted that a correct sampling procedure is an essential
prerequisite for obtaining accurate and precise test results.
Containers for emulsified bituminous materials should be wide-mouth plastic-lined cans with lined screw caps of plastic-lined
triple-seal friction-top cans.
Containers for crushed or powdered bituminous materials should be triple-seal friction-top cans or plastic sacks placed in
other containers suitable for handling.
The size of the container should correspond to the required amount of sample.
72
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
The manufacturer must take a sample from the finished product tank (1) and test the product against the specification
requirements prior to releasing the product. The reason for taking subsequent samples at the various points in the supply
chain (2, 3 and 4) is for quality assurance purposes. It is important to ensure that the quantity of the sample is sufficient to
conduct the necessary tests. The samples taken prior to sampling point (4) should be split into three containers for reference
purposes in the case of a dispute in the test results or for further testing. These samples must be properly labelled with all the
relevant information pertaining to the sample taken to provide for adequate traceability in the event of a dispute. The testing
frequency must be agreed in the quality management plan. In the absence of such a plan, Tables 19, 20 and 21 in Chapter 9
can be used as guidelines.
Storing the samples in metal shipping containers or outdoors in direct sunlight should be avoided. Any deviation from
the above can affect the properties of the sample. In the case of a modified emulsion, the quality of the emulsion will start
deteriorating after 3 months, thus limiting the duration to a maximum period of 6 months before sedimentation takes place.
A convection oven must be used to reheat samples from room temperature until the binder is liquid enough to handle. The
use of a hot plate for this purpose is not acceptable as the source of heat cannot be accurately controlled and measured, and
will increase the risk of localised over-heating. Once the sample is liquid, a low-shear mechanical stirrer with variable speed
should be used to ensure a homogeneous sample which is representative of the original binder.
To ensure that the test results are repeatable and reproducible between laboratories, the supplier and engineer should agree
on a procedure for reheating samples in the site laboratory. This should include standardisation in terms of method MB-2 on:
• Type of equipment used to heat the sample;
• Rate and period of heating;
• Type of stirring mechanism to be used.
73
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
It is important that split samples of the modified binder are sent to all the participating laboratories (e.g. supplier, site and
control laboratories) and tested before commencement of a project to ensure that the results are within the reproducible
limits as prescribed by the test methods.
The recommended approach is to conduct the asphalt mix design using conventional bitumen to determine the volumetric
properties of the mix. Once the design target values have been achieved, it is recommended that the conventional bitumen
be substituted with the modified binder, that briquettes be compacted at different temperatures, and that the resultant air
voids of the mix be measured. The temperature which equates to the design air voids is then used as the
compaction temperature.
The changes in the theoretical mix relative densities must also be taken into account. The mixing temperature of the modified
asphalt should be approximately 15 to 20°C higher than that of conventional bitumen. As a rule of thumb, in cases where SBS
modification is used, the compaction temperature should be increased by 2 to 3°C per % of SBS modifier used.
However, the supplier of the modified binder should be consulted to provide guidelines on mixing and compaction
temperatures for this purpose. For the design of asphalt with bitumen-rubber, the reader is referred to Sabita Manual 19:
Guidelines for the design, manufacture and construction of bitumen rubber asphalt wearing courses.
74
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
To date the most commonly utilised modifiers have been SBR, SBS, crumb rubber and, to a lesser degree, EVA. A performance
history of these modifiers has been accumulated over the last number of decades and correlated with the regimen of
tests prescribed in this document leading to the limits specified for the purpose of controlling quality, and consistency of
manufacture. Due to the current lack of true performance-based properties and specifications, the recommendations do not
necessarily guarantee the binder’s fitness-for-purpose for all the various applications and environmental conditions likely to
be encountered during its service life.
A modified binder is but one component material within a layer system, and factors such as, inter alia; aggregate properties/
packing, construction techniques, traffic, temperature as well as mix/seal design methodology will have an influence on the
long term performance of such a system. The purpose of this section is to develop a protocol for introducing new modified
binders in order to encourage innovation in a controlled and responsible manner. This is best achieved through a combination
of conducting laboratory tests on the binder (with and without aggregates) and evaluating the binder’s performance during
field trials.
- UV resistance/ageing;
- Compatibility with available base bitumens - Storage stability (changes in properties over time).
Comparative adhesion tests may also be conducted, while bearing in mind that adhesion of the binder to the aggregate is
largely influenced by construction practice. Tests such as the Vialit adhesion test, can be selected for this purpose, subject to
agreement of the parties involved.
1
The specific test adopted for a particular performance characteristic would depend on the level of sophistication adopted in relation
to the class of road and prevailing traffic and environmental conditions.
75
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
- Section identification;
- Date and time of construction;
- Weather conditions;
- Air and pavement temperatures;
- Substrate condition;
- Vertical and horizontal alignment of pavement;
- Drainage conditions;
- Traffic conditions;
• Material and construction details:
- Surfacing texture;
- Aggregate loss;
- Binder appearance and condition;
- Crack extent and activity;
- Any signs of surfacing distress.
76
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
The trial sections should be monitored over a period of time to allow for a proper evaluation. However, experience has shown
that if problems are likely to be encountered with the performance of a newly launched binder, they will generally become
manifest, or give an indication of potential problems, after the first summer and winter cycle.
If justifiable, use should be made of accelerated pavement testing (APT) on the test sections to assess long term performance
of the candidate materials.
It is always desirable to have any performance assessments of “new product” trial sections carried out by knowledgeable and
independent practitioners. Information gained from the laboratory tests and field trials must be recorded and made available
to road authorities/specifiers, so that they will be in a position to make meaningful assessments as to the suitability of the new
binder for the required application.
77
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Note:
78
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Definition
The object of sampling to prescribed protocols is to ensure that correct sampling procedures are followed and that results
provide the required information on a composite sample that is representative of the whole.
2. Apparatus
2.1 One-litre open top metal tins fitted with a triple-seal-friction lid for the storing of binders;
3. Method
3.1 Sampling from bulk storage
Samples should be taken from a bulk tank by means of a sampling “thief” or via a sampling valve. The sample valve may be
attached to the side of the tank or built into the discharge line. The sample should be drawn when at least one third and not
more than two thirds of the contents of the tank have been discharged.
3.1.1 The contents of the bulk tank should be thoroughly mixed by pump circulation or stirring for at least
30 minutes;
3.1.2 Withdraw approximately 4 litres from the sampling valve and discard by returning to the bulk product in the
tank. Draw four one-litre samples for testing purposes. Seal containers immediately after sampling.
3.2.2 The sample can be taken from the spray bar, a sampling valve or through the manhole of the tank, using a
sampling thief.
3.3.2 Mix the contents of the drums to be sampled thoroughly by rolling, turning end over end and stirring
if necessary;
3.3.3 If emulsion is being sampled, place a suitable rod through the bung and establish whether excessive sediment
and/or separation are present at the bottom of the drum. As the rod is withdrawn, examine closely for signs of
lumps or extraneous matter;
3.3.4 Pour four one-litre samples for testing purposes. Seal containers immediately after sampling.
79
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
3.4 Labelling
Ensure that samples are securely packed for transport to the testing laboratory. The sample must be clearly identified by
marking on the lid and the container. The following information should appear on the label:
• Client;
• Project number;
• Type of material;
• Batch number;
• Date and time;
• Sampling temperature.
4. Notes
4.1 Safety Precautions
Strict precautions must be taken at all times to avoid injury or the risk of fire, when handling hot polymer modified binders.
The following are some of the precautions to be taken in the handling of these binders:
4.1.2 Heat resistant gloves, with close fitting cuffs and other suitable protective clothing should be worn
during sampling;
4.1.3 Sample containers should be held with tongs or supported on a suitable tray while the sample is being taken;
4.1.5 Sampling personnel should stand away from the sampling valve and on the windward side;
4.1.6 The sample valve should be opened very slowly to prevent a sudden outflow of hot material;
4.1.7 See also Sabita Manual 8: Guidelines for the safe and responsible handling of bituminous products.
Seal the sample tightly immediately after sampling. Wipe any spilled material on the outside of the tin with a clean dry cloth
immediately after sampling. Do not use solvent soaked cloths.
Reference:
Austroads Modified Binder Test MBT 01.200.
80
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
2. Apparatus
2.1 An oven capable of temperatures of 200°C for heating bituminous materials with an accuracy of ±5°C;
3. Method
Sample reduction from bulk (samples larger than 2 litres). This method is not applicable to modified bitumen emulsions. The
procedure shall be as follows:
i. Heat the bulk sample to the required temperature, allowing sufficient time to reach this temperature;
ii. Remove the sample from the oven and thoroughly stir it for 30 seconds with a spatula without entraining air;
iii. Divide the bulk sample into sub-samples using smaller containers of 1 litre capacity.
3.2 Bitumen-rubber
3.2.1 It is assumed that the samples are cold when received;
3.2.2 Two one litre samples are required. One sample for the viscosity test and the second sample for the remainder
of the tests;
3.2.3 Open the sample containers. If unable to remove the lids, make a small hole in the lids to allow for air
to escape.
3.2.5 After two hours in the oven, the samples should be sufficiently fluid. Do not keep in the oven for longer
than 3 hours;
3.2.6 Remove the sample required for the viscosity test from the oven. Heat to the final test temperature of 190°C
over a suitable heat source, while stirring continuously with a spatula, before performing the viscosity test;
3.2.7 Homogenise the second sample by stirring for approximately 5 minutes with a spatula after removal from the
oven. Gentle heating over a controllable heat source will be required to maintain the temperature at
approximately 160–170°C;
Note:
81
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
3.3 Polymer modified binders of the type A-P1, A-H1 & A-H2
It is assumed that the sample is cold when received.
3.3.1 Open the sample container. If unable to remove the lid, make a small hole in the lid to allow for air to escape.
Place the sample in an oven maintained at a temperature of 180 ± 5°C;
3.3.2 After two hours the samples should be sufficiently fluid. Do not keep in the oven for longer than 3 hours;
3.3.3 Homogenise the sample by stirring for approximately 5 minutes with a spatula while heating over a
controllable heat source. Do not heat to a temperature higher than 180°C;
Note:
3.4 Polymer modified binders of the type S-E1, A-E1, S-E2 and A-E2
3.4.1 It is assumed that the sample is cold when received.
3.4.2 Open the sample container. If unable to remove the lid, make a small hole in the lid to allow for air to escape;
3.4.4 After two hours the sample should be sufficiently fluid to pour. Do not keep in the oven for longer than
3 hours;
3.4.5 Homogenise the sample by stirring for 30 minutes with a variable speed electric stirrer fitted with a paddle
mixer, while controlling the temperature at 170 to 180°C. The speed of the stirrer should be carefully controlled
to minimise the risk of entraining air into the sample;
Note:
4. General
4.1 Polymer modified binders are complex mixtures of polymers, bitumen and other petroleum additives. Due to the
higher than normal handling temperatures, the risk of burning with polymer-modified bitumen is higher than with
standard bitumen. Notices describing the action to be taken in case of burns should be prominently displayed in the
laboratory. The safety precautions mentioned under Method MB-1: Sampling polymer modified binders should be taken;
4.2 As the properties of polymer modified binders are affected by the handling of the sample in the preparation of test
specimens, it is necessary to strictly adhere to the preparation procedures described above;
4.3 Polymer modified bitumen is characterised by the formation of a structure on cooling after blending of the constituents.
The sample must thus be heated to a temperature at which this structure will be broken down before testing and
moulding test specimens. The rate of cooling influences the structure formation and, therefore, conditions under which
specimens are cooled prior to testing must be controlled;
4.4 Polymer modified binders are heat sensitive materials and may undergo significant changes in their properties if
exposed to high temperatures for extended periods. Improper heating can therefore, result in sample test results that
may not truly represent the characteristics of the material.
82
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Definition
The test simulates the effect of the manufacturing process where bitumen is hot mixed with aggregate for asphalt production.
The oxidation effects at mixing temperatures (typically in the range of 150°C to 170°C) on the thin binder films that occur
during asphalt manufacture, transportation and placement are simulated by the RTFO test conducted at an oven temperature
of 163°C over a period of 90 minutes. This test therefore indicates approximate change in the properties of bitumen, which
is indicated by viscosity measurements, softening point, penetration and elastic recovery testing undertaken on the binder
residue that remains after the RTFO test is completed.
The test is also used to determine the mass change after RTFOT.
2. Apparatus
The following apparatus is required in addition to that listed in ASTM: D2872 (see note 5.1)
2.2 Metal treatment bottles and rollers in accordance with the description in Figure 1.
3. Method
3.1 Sample preparation
Polymer modified bitumen samples for testing shall be prepared in accordance with method MB-1 and method MB-2.
Heat the sample in its container with a loosely fitted cover in an oven not exceeding the treatment temperature for the
minimum time necessary to ensure that the sample is completely fluid. Manually stir the sample but avoid incorporating air
bubbles. Select the required number of sample bottles to produce sufficient material for characterising tests, which are to be
performed on the residue. Allow the treatment bottles (with rollers) to cool to approximately room temperature (18 – 25°C).
Add 40g of sample to each bottle.
Leave the samples for 30 minutes without rotating the carriage or any air flowing.
Start the rotation of the carriage and the air flow with the flow meter indicating 4± 0.5 l/min.
Maintain the samples in the oven for 60 min (± 10s), and then switch off the carriage and airflow.
Taking out one bottle at a time, pour the contents from each bottle into a suitable container for testing. Drain each bottle until
the treated material stops running freely (just dripping).
Stir the material in the container briefly to ensure that the contents from all bottles are mixed to yield a representative sample.
83
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
4. Report
A comment on the sample behaviour during the test, in terms of its flow characteristics.
If sample flow is restricted at any stage during the test, oxidation of the binder, or loss of volatiles will be reduced and the test
will not truly reflect the real effects of asphalt plant mixing and transportation.
5. Notes
When testing binders with the roller method a wire hook (paper clip) can be used to support the roller over the open
treatment bottle. This encourages complete drainage of the binder back into the bottle.
5.1 The preparation of the oven shall be in accordance with ASTM: D2872 but adapted using the apparatus shown
in Figure 1.
5.2 When the quantitative value of the loss or gain in mass is required use two separate treatment bottles for the
determination. Cool the containers for the test to room temperature and weigh each treatment separately to
the nearest 0,001g. Proceed as per 3.2. At the conclusion of the testing period remove the treatment bottles
from the oven. Cool the treatment bottles to room temperature in a desiccator. Weigh to the nearest 0,001g
and calculate the loss on the basis of the binder in the bottle. Discard the residue.
References:
ASTM: D2072
Austroads MBT 03
84
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
A
Brass cap threaded to suit bottle
tube thread
B C C1
D
E
85
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Duplicate samples are extended under pre-determined conditions for a distance of 200 mm and the elongated thread is cut.
After a recovery period of one hour the extent of the recovery of the thread is determined.
2. Apparatus
2.1 Specimen composite moulds
Two composite moulds as specified in Figure 1 shall be used to form the specimens. The moulds consists of a base plate made
of a non-corrosive metal, fitted with a clamping device, and of four frame pieces made of a copper-zinc alloy (brass), as shown
in Figure 2. The four frame pieces consist of two side-pieces and of two end-pieces, known as clips, in each of which a hole is
bored for attachment to the stay bolt plates of the testing machine. The boreholes in the clips shall be so designed that they
fit easily, but without play, onto the stay bolts.
2.2 Ductilometer
The Ductilometer consists of a trough as specified in sub-clause 2.2.1 in conjunction with a testing machine as specified in
sub-clause 2.2.2, and a measuring instrument as specified in sub-clause 2.2.3. The ductilometer shall be designed so as to
ensure vibration-free testing.
2.2.1 Trough
The trough shall permit an elongation of the briquette specimens to a length of at least 100 cm. Its dimensions shall be
such that at least two specimens may be tested side by side. The clearance between the moulds containing the briquette
specimens and the sidewalls of the trough shall be not less than 10 mm. When the trough is two-thirds full, the bath liquid
shall cover the moulds, attached to the testing machine, both above and below by at least 25 mm. An opal glass sheet shall be
placed over the bottom of the trough.
Maintenance of the temperature limits specified in sub-clause 3.3 shall be ensured by circulating the bath liquid through the
connected thermostat (see sub clause 2.3), and if necessary by the provision of additional insulation.
While the specimens are being pulled apart, the circulation of the bath shall not be switched off, but its rate of flow shall be
reduced to such an extent that the threads are not visibly affected by the flow of the liquid. When a moving deflector is fitted
at the water inlet point, experience has shown that a rate of water circulation of up to 1.5 litres per minute may be permitted.
The testing machine shall be capable of pulling apart two specimens simultaneously. The specimens shall be held by two
plates made of non-corrosive metal fitted with stay bolts (see Figure 3). At least one of these plates shall be movable in the
direction of pull. The diameter of the stay bolts shall be 8 ± 0,1 mm. The drive of the testing machine shall be so designed that
the stay bolts may be pulled apart at a uniform speed of 50 mm/min ± 2,5 mm/min throughout the test. The specified speed
shall, in particular, be maintained, even when high deformation resistance has to be overcome at the start of the test. Periodic
checks shall be made, under load, to establish whether the testing machine can maintain the specified pulling speed.
Note:
A stop shall be provided to ensure that in the initial position of the testing machine the distance between the boreholes in the
clips exactly corresponds to that between the stay bolts.
86
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
The scale interval of the measuring instrument for determining the distance of elongation shall not be greater than 5 mm.
2.3 Thermostat
The thermostat controlling the temperature in the trough of the ductilometer and in the water bath (see sub-clause 2.5) must
be capable of keeping temperatures constant within ± 0,2°C.
2.4 Thermometer
DIN 12775 – E 0,1/0/50 thermometer.
2.6 Knife
The knife shall have a straight cutting edge of at least 40 mm in length, or a plaining blade.
If differences between the specific gravity of the water and the density of the specimen material disturbs the formation of
the thread, causing it either to rise to the surface or sink to the bottom of the bath, then the specific gravity of the bath liquid
in the trough shall be adjusted to the density of the specimen material by the addition of either methyl alcohol or sodium
chloride.
87
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
The moulds containing the briquette specimens shall first be kept for 30 minutes in the water bath. Then the excess binder
shall be cut off level with the mould frame with the aid of a warmed knife. The moulds shall then be returned immediately to
the water bath, maintained at the test temperature, and kept there for a further 85 - 95 minutes.
Between filling the moulds and starting the elongation operation in the ductilometer, 150 ± 10 minutes shall have elapsed.
4. Test procedure
After the specified heat treatment, the briquette specimens shall be lifted off the base plate and transferred to the
ductilometer trough, where the clips shall be mounted on the stay bolts of the testing machine which has been brought into
the initial position for the test. The scale of the testing machine shall previously have been adjusted to the zero setting. Then
the sidepieces shall be carefully removed. Circulation of the bath liquid shall now be reduced, being set either at or below the
maximum permissible rate of flow specified. Throughout the test, the temperature shall not vary from the initial temperature
by more than 0,3°C.
The testing machine specified in sub-clause 2.2.2 shall now be actuated. The threads formed by the two briquette specimens,
as they are pulled apart, shall be observed and the appearance of clumps (pearling) shall be reported.
Threads shall be suspended at a level about halfway between the surface of the liquid and the bottom of the trough. If the
threads rise to the surface to sink to the bottom, the specific gravity of the bath liquid shall be corrected as described in sub-
clause 2.8, and the test repeated.
The samples shall be elongated to a distance of 200 mm. After the elongation distance of 200 mm has been reached, stop the
ductilometer and hold the sample in its elongated position for five minutes. After five minutes, clip the sample approximately
in half by means of scissors or other suitable cutting device. Let the sample remain undisturbed in the ductilometer for a one-
hour recovery period. At the end of this time, retract the half sample specimen until the two broken ends touch. At this point
note the elongation in mm.
% Recovery = (200-E)
200
Where
Report the percent recovery to the nearest whole percentage point. Repeat the test if the duplicate test results differ by more
than two percentage points.
88
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
89
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Figure 3 - Stay bolt plates of the testing machine, with two briquette specimens, in the initial position
90
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Definition
Stability is the resistance to segregation between the modifying agent and the base bitumen when the modified binder is
stored hot.
2. Apparatus
2.1 An open ended 300 mm long glass tube with a diameter of 12,5 mm;
2.2 Silicon rubber stoppers (capable of withstanding temperatures of 185°C) to seal a 12,5 mm diameter tube;
2.4 A stand with a clamp that will hold the glass tube vertically in the oven;
3. Method
3.1 Preparation of test sample
Refer to MB-2 for preparation of the sample before testing.1
Pour the melted sample into the pre-heated glass tube (after corking the base) to about 10 mm from the top. Cork the top of
the glass tube. Ensure that the cork has a v-notch cut along its length to act as a breather. Place the glass tube in the oven (set
at 180°C ± 2°C) in a vertical position (using the standard clamp). The sample must remain in the oven for three days at 180°C
± 2°C. After three days remove the glass tube and allow it to cool to room temperature. The sample must then be cooled to
about 0°C. At this temperature cut the tube with a glass cutter transversely into three equal sections.
Prepare the top and bottom sections in accordance with method ASTM D36 (ring & ball) to determine the softening points of
the top and bottom respectively.
4. Calculations
Calculate the difference in softening point between the top and bottom sections and record in °C.
Note
1
It is important that the specified 180°C is used in order for dissociation to take place – if not the two networks have not been
broken down.
91
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
APPENDIX 1 : METHOD MB-8 : PULL OUT TEST METHOD FOR SURFACING AGGREGATE
Definition
The pull out load test is the load required to dislodge a stone chip from a bituminous seal on the road to assess when the
surface treatment can be opened to traffic.
2. Apparatus
2.1 A spring balance with a capacity of 1000g and graduated every 10g;
2.2 Crocodile clips or small spring loaded battery clamps with attached nylon or string approximately 0,6 m long;
3. Preparation of apparatus
Attach crocodile clips to each end of a suitable length of nylon line. Attach one end to the spring balance. The length of line
should be such that the zero point of the scale is at eye level. Place an average sized stone into the crocodile clip and zero
spring balance. Complete this test method as per Section 4.
4. Test method
Select an area of the road surface in either the left or right wheel path of the surfacing. Measure and record the surface
temperature to the nearest 0,5°C using the contact thermometer. The thermometer should be placed against several stones in
the vicinity of the test and an average taken.
Record the start times of the test and temperatures. Select a stone and attach the crocodile clip to the stone. Slowly raise
the upper portion of the scale and apply a pull out rate of 20g per second. Monitor the scale carefully and continue the load
increments until the stone becomes detached.
Record the maximum reading on the pull-out test data sheet (Figure 1). Remove the stone from the clip and repeat the test
a further nine times at this position. If the stone twists during the test and results in a significantly reduced pull out force, the
result should be ignored.
92
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
APPENDIX 1 : METHOD MB-8 : PULL OUT TEST METHOD FOR SURFACING AGGREGATE
5. Calculations
Apply a temperature correction factor to the data to give pull out loads at 40°C or such other temperature in the range of 15°C
to 50°C as may be expected on the road. The following formula and preliminary constants for various binders should
be used:
m
f2 = f1.10 x (T2 – T1)
Where:
At temperatures below 15°C the binder becomes more brittle and the above corrections no longer apply.
Calculate the mean and standard deviation of the temperature corrected data. The mean value of 1 standard deviation
approximates the 10th percentile value. Depending on the traffic volumes and speeds, and the consequences of stripping, the
15th percentile value or 10th percentile value should be used to assess whether the road could be opened to traffic.
93
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
APPENDIX 1 : METHOD MB-8 : PULL OUT TEST METHOD FOR SURFACING AGGREGATE
Location: Date:
Binder type:
Test number
End
10
Average
Standard deviation
94
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
APPENDIX 1 : METHOD MB-8 : PULL OUT TEST METHOD FOR SURFACING AGGREGATE
6. Criteria
Preliminary criteria for opening to traffic are tabulated in the table below.
95
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Definition
The penetration of bitumen is defined as the distance in tenths of a millimetre that a standard needle will penetrate into the
bitumen under fixed conditions of loading, time and temperature. This test measures the relative hardness or consistency of
bitumen rubber blends.
2. Apparatus
2.1 A standard bitumen penetrometer with a plunger assembly which can be tared to weigh 75g ± 0,01 when the
ball penetration tool is attached;
2.2 A ball penetration tool with a ball of 17 ± 0,1 mm in diameter attached to a shaft, which fits into the
penetrometer. The tool should weigh 27,5g (± 0,1g) (see Figure 1);
2.3 Glass beakers, diameter of approximately 70 mm and at least 70 mm deep or flat bottom metal tins with the
same dimensions;
2.5 A penetration transfer dish of glass or heavy plastic with a diameter of at least 130 mm and at least
120 mm high.
3. Method
3.1 Preparation of test specimen
Take samples of bitumen rubber (MB-1) and prepare them as described in method MB-2. Fill the test container in paragraph
2.3 to a height of approximately 60 mm with the bitumen rubber.
Leave the sample to stand under laboratory atmospheric conditions (24°C ± 4°C) for 24hrs ± 2 hrs. Then place the sample in a
water bath at 25°C ± 2°C for at least two hours before testing.
3.2 Testing
Coat the penetration ball, fitted to the penetrometer, very lightly with silicone grease. Place the container with sample in the
transfer dish filled with water from the water bath to cover the surface of the sample to a depth of at least 20 mm.
Place the ball in contact with the surface of the material to be tested, not less than 10 mm from the side of the container. Set
the indicator dial of the penetrometer to zero. Release the penetration assembly and allow it to penetrate the specimen for
five seconds. Record the reading as ball penetration “P” in tenths of a mm.
Without returning the dial pointer to zero, press the ball down an additional 100 units at a rate of 10 units per second.
Re-engage the clutch to hold the tool down for an additional five seconds. During this time set the dial pointer on zero for
non-spring load spindles. Release the clutch, allow the specimens to recover for 20 seconds, engage the clutch and record the
reading as F (see point 4).
Determine the penetration and resilience, if possible, at three points equally spaced from one other, and at least 10 mm
away from the side of the container. Between each test, determine the temperature of the water in the transfer dish. If the
temperature has dropped by more than 1°C, replace the water from the water bath.
96
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
4. Calculations
Calculate the resilience for each test to the nearest one percent as follows:
Where:
Report the average ball penetration value and average resilience for the conditioned and unconditioned samples to the
nearest one percent.
5. Notes
5.1 If the mass of the ball penetration tool is 27,5g, it should only be necessary to remove the 50g weight from the
penetration shaft used for the normal bitumen penetration test in order for the assembly to have a total mass of 75g.
5.2 Where metal tins are used as sample containers, the rims of the tins should not be much above the level of the sample
for the material at the start of the test. If the container is seamed around its bottom rim, a suitable spacer should be
placed under it to ensure a solid base. A plaster of Paris spacer, made as follows, has been found to work well. Mix plaster
of Paris to a pasty consistency. Flatten the paste with a straight edge to approximately 5 mm thick. Coat the bottom of
a metal container lightly with silicone grease and press it slowly into the plaster of Paris (to assist in the removal of air
under the tin.) Cut the excess plaster of Paris at the sides of the tin, and leave the plaster of Paris at the sides of the tin to
form a neat base. Leave the plaster of Paris to set and remove the tin. This base can remain in the transfer dish. Tins are
placed on it for testing.
5.3 The clutch of the penetrometer may slip slightly during the rest period when testing material with a fairly high resilience.
Holding the measuring plunger down and monitoring any slippage on the dial may prevent this. Slippage can be
corrected or prevented by slight downward pressure on the plunger.
References:
SABITA method BR2T
EN1426
97
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
NOTE:
ONLY THE FOLLOWING
DIMENSIONS ARE CRITICAL:
Top diameter of shaft: 3,2 ± 3,1 mm
Diameter of ball: 17 ± 0.1 mm
Mass of tool: 27,5 ± 0,1g
98
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Definition
Compression recovery of bitumen-rubber blends indicates a measure of the contribution made by the rubber crumbs.
2. Apparatus
2.1 A compression frame capable of reducing the height of the bitumen- rubber specimen from 25,4 mm to
12,7mm (fixed). The frame shall have a removable metal base plate on which the specimen(s) can be formed
(see Figure 1);
2.2 Moulds of silicone rubber or other suitable material capable of withstanding a temperature of 175°C with
inside dimensions: height 25,4 mm; diameter 19,0 mm. The moulds should be made in such a way that they
can be easily removed (see 4.1);
2.3 A water bath or air cabinet capable of maintaining a temperature of 25°C ± 0,2°C;
2.4 Releasing agent such as a 1:1 mixture of glycerine and dextrin or silicone grease;
2.5 A height-measuring device such as a T gauge to measure to an accuracy of at least 0,5 mm;
3. Method
3.1 Preparation of test cylinders
Prepare the bitumen-rubber as described in Method MB-2. Place two cylindrical moulds on the clean base plate, each
approximately halfway between the centre of the base plate and the guide holes. If moulds other than silicone rubber are
used they should be treated with the releasing agent. Fill the moulds to excess with the bitumen-rubber. Allow cooling to
room temperature and remove the excess material with a hot spatula.
3.2 Testing
Immerse the test specimens together with the base plate in the water bath or air cabinet at 25°C ± 2°C for at least one hour.
Remove it from the water bath or air cabinet and carefully remove the moulds from the cylinders. It is important not to pull
the sample off. Place the base plate in the test rig.
Place a round of paper on top of each bitumen-rubber cylinder. Place the compression plate on top and, by means of the
lever, compress the bitumen-rubber cylinders with a smooth quick action until the spacer rings touch the compression plate,
while keeping the compression plate as level as possible.
Immediately remove the compression plate and the releasing paper rounds and note the time accurate to five seconds.
If a stopwatch or other timing device is used, set it in operation.
Measure the height of each of the cylinders after the following time intervals: 5 minutes ± 5 seconds, 1 hour ± five minutes,
and 24 hours ± 30 minutes recovery. During this time samples should be left where they cannot be damaged, and will be free
from vibrations and shock.
99
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
4. Calculations
Calculate and report the percentage recovery as a percentage of the original height to the nearest one percent after five
minutes, 1 hour, 4 hours and 4 days recovery:
% Recovery = h x 100
25,4
Report the results accurate to 0,1% for five minutes, one hour, four hours and four days recovery.
Notes
Silicone rubber moulds may be made using a self-curing or two-part sili- cone rubber compound or similar material. Metal moulds can
be used to make the silicone rubber moulds. The silicone rubber mould is cut vertically on one side to facilitate removal of the bitumen-
rubber cylinder. It is held together with an elastic band when in use.
The backing paper used for self-stick labels or film has been found to work well.
If an air cabinet is not available the samples may be kept in a room where the temperature is controlled at 25°C ± 2°C. This fact should be
mentioned in the test report.
Reference:
Sabita Method BR3T
100
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
2. Apparatus
2.1 Moulds consisting of a brass or copper plate 3,2 mm tick with a cut out rectangle 20 x 60 mm. Multiple
specimen moulds can also be used with the cut-outs not less than 20 mm apart;
2.2 Smooth, flat, tinned oven trays or similar stiff metal plates at least 200 x 200 mm (see 5.1);
2.3 A force draft drying oven capable of maintain a temperature of 60°C ± 1°C, free from vibration (see 5.2);
2.4 A water bath or air cabinet capable of maintaining a temperature of 25°C ±1°C, and big enough to
accommodate the tray in 2.2;
o o
2.5 A firm frame or support to keep the tray (2.2) at an angle of 35 ± 2 in the oven;
2.8 Water-soluble releasing agent such as a 1.1 mixture of dextrin and glycerine or silicone grease.
3. Method
3.1 Preparation of test specimen
Prepare the bitumen rubber as described in method MB-2. Prepare at least two moulds for each sample to be tested by
coating it thoroughly with the releasing agent. Place the moulds not less than 20 mm apart with one short side approximately
10 mm from one side of the tray. (Multiple specimen moulds can also be used – see 2.1). This will be the topside of the
specimens. Fill the moulds with an excess of bitumen rubber.
When cool, after 30 minutes, trim the top surface level with the sides of the moulds using a hot spatula. Holding the flat side
of the blade of the spatula at an angle to the specimen, level off the excess material. It should not be scraped off with the
sharp edge of the blade. The slight bulge that is formed behind the spatula is acceptable.
Remove the moulds carefully from the specimens after cooling and wash clean the test specimens and plate clean of releasing
agent. Make a mark opposite and in line with the bottom end of each of the specimens on the bottom of the tray with an
indelible heat resistant pen or soft pencil. Place the tray with specimens in a water bath or air cabinet at 25°C ± 1°C for 30 ±
five minutes prior to testing.
3.2 Testing
Remove the tray from the water bath or air cabinet and dry it and the specimens with an absorbent cloth or paper towel. Place
the tray in the oven at 60°C ± 1°C at an angle of 35° ± two degrees with the topside facing up. The oven should not vibrate
as this may influence the results. Leave the specimens in the oven for four hours ± five minutes, remove and allow cooling
to room temperature. Make a mark opposite the lower end of the specimen below the previous mark. Measure the distance
between the two marks as the flow distance accurately to 1 mm.
101
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
4. Calculations
Report the flow distance in mm accurately to 1 mm for the average of the two samples. Also indicate in the report if any
separation of bitumen from the bitumen-rubber is noticed.
5. Notes
5.1 Research indicates that the metal from which the tray is made does not influence the results. The only
important prerequisite is that the surface should be smooth and free from scratches, and it is thus important
that the tray is not scratched during cleaning;
5.2 It may be impossible to find a force draft oven without any internal vibration. Every effort should be made to
reduce and minimise vibration in the oven as far as possible, since this may influence the results.
Reference:
Sabita Method BR 5 T
102
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
2. Apparatus
2.1 A hand-held rotary viscometer with a rotor-cup to measure dynamic viscosity in the range of 0,5 to 10 Pa.s. For
laboratory use the instrument should be mountable on a stand (see also 5.2);
2.2 A purpose-made stand or retort stand and clamps to hold the viscometer rigidly for viscosity determinations in
the laboratory;
2.3 An oven thermostatically controlled and capable of maintaining temperatures of 150°C to 300°C
accurate to ± 5°C;
2.6 A stirring rod or spatula capable of mixing and stirring of the viscous bitumen material;
2.7 Metal tins or glass beakers with capacities of approximately one litre and with a diameter of at least 100 mm,
allowing a sample depth of at least 80 mm. If the tins are also used as sample containers, they should have
tightly fitting lids.
3. Method
3.1 In the field
Take a representative sample of bitumen-rubber blend as described in Method MB-2, using the sample containers in 2.7
above. Directly after taking the sample, stir it well with a suitable stirring rod. Measure and record the temperature (see 5.1).
Attach the correct viscosity cup-rotor to the viscometer such that viscosity measurements will be between 0,5 and 10 Pa.s
(see 5.2). Ensure that the vent hole on top of the rotor is open. Place the sampling tin or beaker on a firm non-heat absorbing
base and immerse the viscometer rotor in the centre of the sample up to the depth mark on the stem. After approximately 30
seconds start the rotation of the rotor while holding the instrument absolutely horizontal (see 5.3). If possible, a stand should
be used. Take and record the viscosity reading to an accuracy of 0,1 Pa.s approximately ten seconds after the rotor is set in
motion. Remove and clean the rotor (see 5.6).
Heat the sample as quickly as possible in an oven to the recommended spray temperature (see 5.5). If the sample is in a
container as specified in 2.7 above, the viscosity can be determined directly. Otherwise, transfer the sample to a container as
specified in 2.7. Stir the sample with a suitable stirrer while the temperature is monitored. When the required test temperature
is reached (see 5.4), remove the stirrer and thermometer and determine the viscosity as described in 3.1. The viscometer
should be fixed onto a stand to hold it firm and horizontal. Remove and clean the rotor (see 5.6).
103
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
4. Calculations
The viscosity readings should be taken and recorded accurately to 0,1 Pa.s. Report the results to the same accuracy together
with the date, time, sampling and binder temperature (see 5.6).
5. Notes
5.1 In seal work it is necessary to measure the viscosity of the bitumen-rubber blend before, during and after spraying to
determine its spray ability. To make the results meaningful the viscosity and temperature should be determined as soon
as possible after sampling to prevent heat loss;
5.2 The metric standard for expressing dynamic viscosity is Pa.s. Most viscometers are, however, calibrated in either
centipoise (cP) or dPa.s with 1 cP = 1 dPa.s x 10-2 = 1 Pa.s x 10-3.
Thus, 1,5 Pa.s = 15 dPa.s = 1500 cP;
5.3 To prevent damage to the instrument some manufacturers stipulate that the viscometer be set in motion before the cup
is immersed. To comply with these requirements, while still allowing for the cup to heat up to the temperature of the
bitumen-rubber, it is suggested that the cup be immersed for 30 seconds, pulled more than halfway out of the binder, the
motion started and the cup immersed to the mark. The viscosity reading should then be taken approximately 10 seconds
after this second immersion;
5.5 The bitumen-rubber sample should be heated and tested in the shortest time possible, as the properties of the blend
may change considerably with prolonged heating. Material should be discarded if it has remained at this high
temperature for more than one hour, unless time dependent tests are required;
5.6 Clean the rotor-cup as soon as possible after the test, while it is still hot, by first wiping excess material off with a dry cloth
or paper and then cleaning it in a suitable organic solvent such as toluene.
Reference:
Sabita Method BR5T
104
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
APPENDIX 1 : METHOD MB-14 : PARTICLE SIZE DISTRIBUTION AND LOOSE FIBRE CONTENT OF RUBBER CRUMBS
2. Apparatus
2.1 The following test sieves, 200 mm diameter, complying with SANS 3310-1: 2 mm; 1 mm; 0,600 mm; 0,300 mm;
0,150 mm; 0,075 mm with a lid and receiver;
3. Method
Obtain a representative sample of approximately 500g of rubber crumbs, either from randomly selected individual bags as
delivered on site or from the rubber crumbs container at the blending or mixing plant, at random intervals.
Mix the sample thoroughly and break down any lumps that it may contain (see Notes 5.3). Scoop out duplicate test samples of
more or less 100g each and test each sample as follows:
• Nest the sieves on the receiver in descending order of size and transfer the sample to the top sieve. Place the lid
in position and hand sieve the sample for approximately two minutes by rocking and tapping the sieves. Mechanical
sieving can be used for this initial operation, especially when the presence of fibres is suspected, but the final sieving
should be done by hand;
• Remove the lid and gently rub the rubber crumbs in the uppermost sieve. Hand sieve the material until nothing more
passes that specific sieve. If fibre is present it can be clearly seen in the sample as short light coloured hairs, which will
form a ball during the sieving operation. Collect the fibre balls carefully and place them in a clean receptacle. Remove
the sieve and repeat the operation for each sieve in the series. For the 1,18 mm and other finer sieves, the fibres
collected on a specific sieve are placed back on the next coarser sieve and re-sieved to remove rubber particles
sticking to the fibres. The fibres are then carefully collected and placed in the fibre receptacle (see Notes 5.2);
• Weigh the material retained on each sieve accurately to 0,01 g. Also determine the mass of the fibres collected from
the sieves.
105
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
APPENDIX 1 : METHOD MB-14 : PARTICLE SIZE DISTRIBUTION AND LOOSE FIBRE CONTENT OF RUBBER CRUMBS
4. Calculations
Calculate the percentages passing the sieves as described in SANS 3001-AG1 and report the results to the nearest 0,1%.
Calculate the fibre content as a percentage of the total sample by mass and report together with the grading results. In the
report the following should be noted:
• The batch number and sampling date if available;
• The condition of the bags in which the rubber was stored;
• The height of the rubber bag stockpile;
• The presence of foreign materials in the rubber such as steel wire, string etc.;
• If the rubber crumbs are loose or lumpy;
• If fibre particles are visible or not.
5. Notes
5.1 Although the fibre particles in rubber crumbs are fairly short they tend to form a ball during the sieving operation. The
same happens during the blending and/or mixing operation and their presence creates construction problems and may
lead to an unacceptable end product;
It is impossible to separate or collect all the fibres in the crumbs, but usually the specifications state that no fibre or a very
small percentage is allowable. This method will therefore be sufficient in most instances where fibre could be a problem.
5.2 The sieving operation and collection of fibres is a tedious process and care should be taken that the operator does not
hurry the test;
5.3 Rubber crumbs should be dry when sampled. If damp, they should be dried in a force drying oven at 60°C for one hour
prior to testing. Higher temperatures and prolonged heating may change the charac- teristics of the rubber and should
be avoided.
Reference:
Sabita Method BR6T
106
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
APPENDIX 1 : METHOD MB-17 : SOFTENING POINT OF MODIFIED BITUMEN BY RING AND BALL METHOD
METHOD MB-18 : DYNAMIC (APPARENT) VISCOSITY OF POLYMER MODIFIED BINDERS
Reference:
ASTM D36 (using shouldered ring)
2. Definition
The co-efficient of viscosity is the ratio between applied shear stress and rate of shear. This co-efficient, stated in Pa.s,
measures the resistance to flow of a liquid, and is commonly termed viscosity.
Reference:
ASTM D4402
107
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
b. The recovery of modified bitumen residue from emulsion using a Bunsen burner (Method B).
1. Scope
This method describes the recovery of modified bitumen residue from a modified bitumen emulsion containing some fluxing
oil. The residue recovered represents the modified binder on the road after a period in which the fluxing oils are allowed
to evaporate.
METHOD A
2. Apparatus
2.1 A rotary evaporator, including holding and receiving flasks, designed to be subjected to at least one
atmosphere of vacuum (about 63 cm Hg), according to DIN 1996 (Buchi or similar);
3. Sample preparation
Polymer modified binder samples for testing shall be prepared in accordance with method MB 1 and method MB 2.
3.1 Add 300g ±1g modified emulsion to the one litre holding flask of the rotary evaporator (500g ±2g in two litre
flask). Attach firmly to the apparatus and lower the flask into the oil bath at 60°C ±5°C. (See Figure 1). The oil
should come up to the level of emulsion in the flask. Start rotation of the flask at 50 rpm and subject to a
vacuum of 30 cm Hg ±5 cm. Start the flow of cold water through the condenser of the apparatus. Leave for
60 minutes ±5 minutes. Raise the temperature gradually to 150°C, ensuring that the emulsion does not boil
over onto the condenser (vacuum as before). This may take up to 30 minutes. Leave at 150°C ±5°C for 60
minutes ±5 minutes.
While the vacuum is maintained during recovery, a small flow of air should be introduced into the holding flask
(via the valve at the top of the condenser) to assist in driving off the volatiles (water and flux).
Remove the holding flask containing recovered modified bitumen and pour out for further testing.
METHOD B
4. Apparatus
4.1 A Bunsen burner;
108
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Air Valve
109
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
Reference:
SANS 4001 BT4 which refers to ASTM: D244
Reference:
ASTM: D244
110
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
2. Method
SANS 4001 BT4, which refers to I.P 91, with the following amendments:
• The two test sieves should be a 0,150 mm sieve, 50 mm high and approximately 80 mm in diameter as well as a 0.710
mm sieve, 50 mm high and approximately 80 mm in diameter;
• The reagent (soap solution) shall be a 0,1N hydrochloric acid solution containing 1% cetyltrimethyl- ammonium
bromide (centrimide).
References:
Cationic: SANS 4001 BT4, which refers to IP 91
Anionic: SANS 4001 BT3, which refers to IP 91
2. Method
• The ASTM D 244 method is followed with the following amendment;
• The thickness of the electrode shall be 0,71 mm.
Reference:
SANS 4001 BT4 which refers to ASTM D 244
111
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
NOTES:
112
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
NOTES:
113
Technical Guideline : Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction The Use Of Modified Bituminous Binder In Road Construction
NOTES:
114
Technical Guideline :
The Use Of Modified Bituminous Binder In Road Construction
NOTES:
115
NOTES:
WWW.SABITA.CO.ZA