Book of Forms
Book of Forms
BOOK OF FORMS
(Public Works Accounts)
2017
FINANCE DEPARTMENT
The forms referred to in the Kerala Account Code, Volume III ,Parts I and II
can be modified in matters of detail or changed to suit local requirements only in
consultation with the Accountant-General to the extent authorised, by him.
The forms should be standardized in the K.P.W. Series when they are
reprinted.
P. VELAYUDHAN NAIR,
Finance Secretary.
PREFACE TO THE SECOND EDITION
The Kerala Public Works Account Code has been revised. Accordingly the
Forms referred to in the revised Code have been brought out in this edition of the
‘Book of Forms’.
P. VELAYUDHAN NAIR,
Finance Secretary.
PREFACE TO THE THIRD EDITION
After the issuance of the second edition, certain amendments have been
issued to the Kerala Public Works Account Code. Consequently, certain additions
and deletions to the forms have been effected. The “Book of Forms” have been
revised accordingly.
Reference to
Page
Code
1 2 3 4 5 6 7
1 Cash Book .. 1 6.6.1.-6.6.8. 80
1A Register of cheques received and adjusted .. 8 6.3.2.
2 Imprest Cash Amount .. 9 6.6.9.-6.6.13. 86 and 88
i
3 Acknowledgement for Receipt of Money .. 14 6.3.1. and 6.3.4.
4 Treasury Remittance Book .. 15 6.5.1.
5 Cash Balance Report .. 16 6.6.7. 82
6 Stores Indent .. 18 7.2.9.-7.2.11.
TABLE OF CONTENTS
Reference to
Page
Code Vol.III Department Code
Remarks
Code
i
Part I - Articles in hand
Part II - Articles temporarily lent or
sent out
Part III - Shortages awaiting adjustment
TABLE OF CONTENTS
iii
28 Works abstract ‘B’ - For Minor Works .. 80 10.5.1.-10.5.3. and
10.5.13., 10.5.23. 133
29 Report of Verification of unused balances
of materials-at- site .. 82 10.3.15.-10.3.18 129
TABLE OF CONTENTS
30 Deleted .. ..
31 Register of Material-at-site Accounts .. 83 10.3.18. 129
31A Account of Materials issued to Contractors .. 84 10.3.6.
32 Deleted .. ..
33 Deleted .. ..
34 Register showing the clearance of the
suspense head “Materials” .. 85 10.3.19. 129
35 Deleted .. .. 12.3.2. 160
36 Out-turn statement of Manufacture .. 87 10.6.3. 142
37 Work Slip .. 88
TABLE OF CONTENTS - (Contd)
Reference to
Paragraph of the Paragraph of
Article of the the Kerala
Kerala Public
Description of Form Kerala Account Public Works
Works Account
Remarks
Page
iv
43 Completion statement of works and repairs 104 10.6.11. 148 199(a)
44 (1) Register of revenue realised 10.6.11.
(2) Register of refunds of revenue
TABLE OF CONTENTS
v
57 Register of Divisional Accountant’s
Objections .. 123 4.2.7.
58 Schedule docket .. 124 22.4.2. 209
59 Schedule docket for percentage recoveries .. 126 22.4.3. 212
TABLE OF CONTENTS
Page
Code
Code
1 2 3 4 5 6 7
62 Suspense/Deposit Register .. 132 13.2.5.,13.3.8. and 164
22.4.4. 15.5.1. and
22.4.4.
63 Deleted .. ..
64 Deleted .. ..
vi
65 Schedule of Miscellaneous P.W. Advances .. 133 22.4.15. and 22.4.16. 217
66 Deleted .. ..
67 Schedule of debits to stock .. 135 22.4.2. and 22.4.8. 216
68 Stock Account .. 137 22.4.9. 216
TABLE OF CONTENTS
vii
and article 228
77 Abstract Book .. 158 22.4.1. 208
78 Extract from Contractor’s Ledger .. 168 10.7.8.(c) 233
TABLE OF CONTENTS
Page
Code
Code
1 2 3 4 5 6 7
86 Detailed list of works abstract /A-for Major
works/B-for Minor works/Petty works
requisition and accounts .. 184 21.1.5. 205
87 Register of miscellaneous recoveries .. 185 22.2.10.
88 Memo of review of registers, etc. .. 186 22.4.32.
89 Register of destruction of records .. 187 23.3.1.
viii
90 Register of Tenders .. 136(b)
91 Pass Book .. 188 22.3.3.
92 Temporary receipt for money received by a
TABLE OF CONTENTS
FORMS
BOOK OF FORMS
FORM 1
CASH BOOK
Notes
3. The cash book contains two money columns, headed (1) “Cash” and (2)
“Bank or Treasury”, on the payment side to distinguish between payments
made by cheques from those made out of the cash in chest. When,
however, a cheque is drawn to replenish the chest, its number and amount
should be entered on the payment side in the “Bank or Treasury” column
Nos. 10 and 11, and the amount only on the receipt side as “Cash from
Treasury” in the single “Cash” column No. 4.
4. Every entry must be concise. The date, the number of voucher if any, the name
of the work, and such a brief narration as will indicate unmistakably the
1
BOOK OF FORMS
nature of the transaction must be entered against each item. The amount
debitable or creditable to each separate work, head of account, or contractor
or other person should be entered separately, and the amounts to be posted
by the Divisional Office into the Abstract Book or Schedules of account
under each prescribed head of account should be distinctly brought out
opposite the entries in columns 5 and 12, headed “Classification of Receipts”
and “Classification of Charges”. A deduction, made at the time of payment,
creditable to a work or head of account other than that to which the payment
itself is debitable should, however, be entered on the receipt side of the cash
book.
5. Transactions must be entered in the cash book as soon as they occur and
strictly in the order of occurrence. If, however, owing to the absence of the
disbursing officer on tour a cheque issued by him, whilst in camp, is entered
in the cash book maintained at his head quarters on a subsequent date, the
actual date of issue of the cheque should be noted in the cash book as the
denominator of a fraction the numerator of which will be the date on which
the transaction is incorporated in the book. A similar procedure should be
observed when the double transaction relating to the realisation of
miscellaneous cash receipts by the subordinate and their payment directly
into treasury is incorporated in the cash book of the superior disbursing
officer on receipt of the receipted chalan of the treasury from the subordinate,
as prescribed in paragraph 6.3.4. of the Code.
2
BOOK OF FORMS
column. A counter reference should be given in the cash book, against the
original to the second entry of the cheque. The issue of a new cheque in lieu
of a time-expired or lost cheque should be entered on the date of issue in red
ink in the cash book but not in the column for payment, a counter reference
being given in either case against the original entry in the cash book.
The procedure for dealing with time-expired, cancelled and lost cheque is
prescribed in paragraphs 6.2.6. to 6.2.20. of the Kerala Public Works Account
Code.
8. It is a serious irregularity to draw cheques and deposit them in the cash chest
at the close of the year for the purpose of showing the full amount of grant
as utilised or to keep the cash book open after the 31st of March and make
disbursements in April entering them in the cash book as having been made
in March.
9. When an imprest is first given the fact should be noted in red ink in the cash
book of the disbursing officer giving it, in the column “To whom paid”, but
the amount should not be entered as an actual payment, as it will still form a
portion of the cash book balance of the disbursing officer making the advance.
If, however, a cheque is drawn, its amount must be shown on both sides of
the cash book, vide Note 3. Any subsequent increases or decreases in the
amount should be noted similarly, the increases on the payment side and the
decreases on the receipt side.
11. Similarly, when a temporary advance is given the fact should be noted in red
ink in the cash book of the disbursing officer giving it in the column “To
whom paid” but the amount should not be entered as an actual payment as
3
BOOK OF FORMS
it will still form a portion of the cash balance of the disbursing officer making
the advance. If, however, a cheque is drawn, its amount must be shown on
both sides of the cash book. As in the case of imprest accounts the disbursing
officer should enter in his cash book only the total for each work or the head
of account as brought out in the abstract.
12. Before the end of the month the disbursing officer must draw a cheque in his
own favour for the amount of departmental receipts utilised towards
departmental expenditure and endorse it with the words “Received payment
by transfer credit to the Public Works Department”.
13. All payments must be debited at once to the work or service on account of
which they are made. Money advanced to a subordinate for disbursement to
labourers, etc., at a distance should be noted in the cash book in red ink as a
temporary advance, in the manner followed when regular imprests are first
made; and when the subordinate returns the duly certified muster rolls, etc.,
with the unpaid wages, if any, the amounts actually paid should be debited to
the works or services concerned, the amount unpaid being returned into the
cash balance. A similar procedure should be observed when the disbursing
officer removes cash from his chest and takes it with him on tour for
disbursement.
14. When an advance on transfer is made to a Government servant from the cash
in the hands of the disbursing officer pending recoupment when the bill is
encashed subsequently, the amount thus advanced should not be entered
as a final transaction in the cash book but recorded as a temporary advance
so that the amount may continue to form part of the cash balance for which
the disbursing officer is responsible.
15. If the disbursing officer draws on more than one District or Sub Treasury or
the Bank, the total amount of cheques drawn during the month on each
(excluding the amount of cancelled cheques), should be recorded in the
another note at the foot of the cash book.
4
BOOK OF FORMS
16. The cash balances at the end of the month should be detailed in a note at foot
of the cash book:
. P.
Cash in chest……………………………………………….
Total …
5
BOOK OF FORMS
6
FORM 1
CASH BOOK
Payments
Bank or Treasury
7
Cash No. of cheque
(with No. of Amount
cheque book)
Date of payment
Classification of receipts
To whom paid , etc.
Amount (Cash)
Date of receipt
BOOK OF FORMS
1 2 3 4 5 6 7 8 9 10 11 12
. P. . P. . P.
FORM IA
SUBSIDIARY REGISTER OF CHEQUES RECEIVED AND ADJUSTED
(Referred to in para 6.3.2.)
Notes to be printed on the fly-leaf
1. Cheques of private individuals received in payment of Government dues should initially be entered in this
register in accordance with the instructions in para 6.3.2.
2. This register is to be treated as a subsidiary Cash Book and for this reason the page of the register should be
machine-numbered.
3. Only daily totals of receipts and remittances should be entered in the Cash Book.
8
Amount
BOOK OF FORMS
Date of receipt
Remarks
Serial No
Total amount of
cheques
Due to Government
Commission
Charges if any
1 2 3 4 5A 5B 5C 6 7 8 9 10
. P. . P. . P.
BOOK OF FORMS
FORM 2
IMPREST CASH ACCOUNT
(This form should be printed in two foils and bound in book form)
2. The round sum with which an imprest cash account is opened should at once
be entered in red ink in column 4, “Received”. If this amount exceeds 500
the orders of Government sanctioning the amount should be noted in the
remarks column of the account. The date and manner of the remittance, and,
if recouped by cheque, the cheque and cheque book number should also be
entered, column 3 being utilised for the latter purpose. The date of
encashment of the cheque should be entered in remarks column 6. The
disbursements from this imprest should be entered daily as the transactions
occur, clearly and in full detail.
9
BOOK OF FORMS
3. The cash balance should be verified after each disbursement and the imprest
account should be closed as soon as a recoupment becomes necessary, not
later than a week before the balance on hand if likely to be spent out, or on
the closing date of the account for each month, the balance struck, and cash
verified and certified. The original copy should then be cut off and sent to
the Drawing Officer, the duplicate (carbon) copy being retained by the imprest
holder. The account should be supported by a voucher in proper form, for
each payment, tacked on so as to correspond with the order of the entries in
column 2, “Voucher No”. The sums received from time to time in recoupment
of the imprest should be entered in column 4, in red ink in the same way as
the fixed amount with which the account was first opened.
4. The account should contain no entries of receipts other than the opening
entry of the imprest, and the subsequent recoupments of expenditure nor any
entries of expenditure other than those paid directly by the imprest holder
himself from the amount of the particular imprest. Amounts received as
temporary advances for payment of specific bills or muster rolls should not
be mixed with imprests intended for petty payments made on the Section
Officer’s responsibility without pre-audit by the Sub-divisional Officer.
10
BOOK OF FORMS
11
BOOK OF FORMS
FORM 2 - (contd)
Account No………....……
voucher etc.
1 2 3 4 5 6
. P. . P.
12
13
and
Imprest
account
voucher
. P.
. P.
. P.
. P.
. P.
. P.
. P.
FORM 2 - (contd)
. P.
ABSTRACT OF CHARGES
FORM 3
ACKNOWLEDGMENT FOR RECEIPT OF MONEY
Date…………………....
Received from…………………………….Rupees………………………………..
…………………………………………………………….......................................
14
FORM 4
TREASURY REMITTANCE BOOK
(Referred to in para 6.5.1)
……………….Division
. P. . P.
15
BOOK OF FORMS
1. The Remittance Book should accompany the cash remitted by the Department.
2. Remittances made into treasuries or cheques paid in as Public Works Receipt should be entered in the Remittance Book but
in the place for the treasury receipt should be entered “By Bank Cheques” and even then the book should accompany the
cheque so that treasury may give a preliminary acknowledgment for the receipt of the cheque in the book
The book should be closed at the end of the month with a Consolidated Treasury Receipt for the whole of the remittances
made during that period and sent to the Treasury Officer who after verifying the entry by comparison of the Schedule of
Receipts will sign the book and the receipt and return them to the Officer.
Any difference between the Consolidated Treasury Receipt and the Schedule of Receipts should be explained in the former
by the treasury.
BOOK OF FORMS
FORM 5
CASH BALANCE REPORT
(Referred to in para 6.6.7.)
Part I
Statement of the actual balance of cash in the hands of……………...........…
.............................................on the………………………………… day of
…………..20……… and of imprest and temporary
advances with subordinates
Remarks and
Description No. Amount explanation of large
balances, etc.
1 2 3 4
Cheques received in favour of self but not . P.
remitted
Bank drafts not remitted
*Notes *as detailed below
Deposits at call receipts
Rupees
½ Rupee (Fifty Paise)
¼ Rupee (Twenty-five Paise)
20 Paise
10 ”
5 ”
3 ”
2 ”
1 Paisa
Revenue Stamps
** Total cash in chest ** in words
Add amount of imprest and advances
shown below:—
Ground total balance as per cash book
16
BOOK OF FORMS
Part II
. P.
Total . .
Date………20………. (Signature)…………………………..
(Rank)………………………………..
The Cash Balance Report of all disbursing officers including the Divisional
Officer should accompany the monthly account for March and the original
cash balance report of subordinate disbursing officers should be initialled
by the Divisional Officer before transmission to audit.
17
BOOK OF FORMS
FORM 6
STORES INDENT
Sub-division……………
Head of account………………………
Quantity Quantity
indented issued
Descrip- Code
In In In In Unit Rate Value
tion of No.
fig- words fig- words
Serial No.
article
Remarks
ures ures
18
BOOK OF FORMS
[Reverse of Form 6]
Received the articles as per column 5(b). Please deliver the articles to the
person whose specimen signature is given below:
Passed for issue (furnish details of the items and quantities not
passed as per column 4)
Signature of Divisional/
Sub-divisional Officer.
19
FORM 6A
REGISTER OF INDENTS
(Referred to in para 7.2.10)
Name of work/job(with
Indent Description Code Quantity Signature of Quantity Reference
name of Contractor or
Indented Indenting issued to stock
of stores No. from whom value is
No. Date account
Remarks
Officer
Serial No
recoverable)
1 2 3 4 5 6 7 8 9 10 11
FORM 7
BIN CARD
20
(Referred to in para 7.2.12)
Article……………........................ Maximum stock…………................
Code No…………......................... Bin Card No..…………............. Minimum stock…………................
BOOK OF FORMS
1 2 3A 3B 4 5 6
FORM 7A
GOODS RECEIVED SHEET
(Referred to in para 7.2.5.)
Division……………….
Sub-division……......… Name of the supplier……..…..............
Section…………..........
Purchase/Supply Quantity
Invoice / Description Stores Code
Order
R.R. No. of materials No. On check Rate
Received
Date
Amount
Unit
Incidental
charges
Serial No.
No. Date measurement
1 2 3 4 5 6 7A 7B 8 9 10 11
. P. . P. . P.
21
Reference to payment voucher or
Amount including Bin Card Stores Ledger Remarks including result of test
adjustment of debit
incidental charges No. Folio No. check by superior officers
No. Date.
BOOK OF FORMS
12 13 14 15A 15B 16
. P.
1 2 3 4 5
22
. P.
BOOK OF FORMS
Total
Note.- A separate summary should be prepared for each sub-head of stock and the value of all the sub-heads
abstracted on another sheet.
Divisional Accountant
FORM 9
SUMMARY OF INDENTS
(Referred to in para 7.2.28.)
Division…………......……………….Name of sub-head………………............………Month…………...........…………
Name of Division/work to
Serial No. Date Indent No. Value creditable to stock which the amount is
debitable
1 2 3 4 5
. P.
23
Total ..
Note. - A separate summary should be prepared for each sub-head of stock and the value of all the sub-heads
BOOK OF FORMS
Divisional Accountant
FORM 11
PRICED STORES LEDGER
(Referred to in para 7.2.30)
Division…………………..
Sub-division………………. Article…………………
Maximum………………
Minimum……………….
Ordering level…………..
Code No………………..
Unit…………………….
Issue………Date……....
From……….To………...
Receipts
From whom
received/to
No.
24
whom issued Rate Value Incidentals Total
Date
Serial No.
GRS/Indent
Quantity
1 2 3 4 5A 5B 5C 5D 5E
BOOK OF FORMS
. P. . P. . P. . P.
Reference to payment or
Issues Balance
adjustment of debit
poster
Value
Initials of
Initials of
Date
No.
Value
Divisional
Accountant
T.E.O.
Remarks in-
cluding refer-
ence to Sl.No.
of item No. of
item to which
excess /short
amount paid,
if any, relate
Voucher/
Quantity
Quantity
6A 6B 7A 7B 8A 8B 9 10 11
. P. . P.
FORM 11-A
REGISTER OF BOOKLETS OF GOODS RECEIVED SHEETS/ INDENTS
(Referred to in paras 7.2.8 and 7.2.10)
Division………………….. Sub-division……………….
Date of Serial No.of Name and designation of Signature of the Date of receipt
officer to whom Remarks
issue booklet the officer to whom issued in the Division
issued
1 2 3 4 5 6
25
FORM 11-B
REGISTER OF BIN CARDS
(Referred to in para 7.2.13)
BOOK OF FORMS
Division…………………....
Sub-division……………….
Name and Signature of
Date of Bin Card designation of Date of
Name of article Code No. the officer to Remarks
issue No. the officer to return
whom issued whom issued
1 2 3 4 5 6 7 8
FORM 12
TOOLS AND PLANT RECEIVED SHEET
(Referred to in para 7.3.4.)
Division………………….. Sub-division……………….
Purchase/Supply
Invoice / order or indent Source of * Name of
Date Quantity Unit Rate
R.R. No. receipt article
Serial No.
No. Date
1 2 3 4A 4B 5 6 7 8 9
. P.
26
Reference to payment ** Remarks
Incidental Amount including Tools and plant voucher or adjustment including results
BOOK OF FORMS
* The articles to be entered in column 6 should be grouped by the prescribed sub-head of classification, vide paragraph 7.3.7.
** The entries in respect of receipt back articles lent or sent out (vide paragraph 7.3.3.) should be distinguished from others
by quoting reference to the original entries in the tools and plant indent in column 15.
Sub-divisional/Divisional Officer
FORM 13
TOOLS AND PLANT INDENT
(Referred to in para 7.3.5)
Tools and Plant Indent on………………………..Division/Sub-division
No……………………
Date………………….
Division………………
Sub-division…………
Name of work/job with name Name of
Quantity of contractor from whom person to
value is recoverable whom the Signature of
Name of
articles are to Indenting
article* Dated signature Signature of be delivered Officer
of Indentor and authorised and his
27
Head of Account
Rate
** Remarks
Issued
Unit
Serial No.
Indented
Amount
his designation agent signature
1 2 3 4 5 6 7 8 9A 9B 10 11 12
Sub-divisional
BOOK OF FORMS
. P. . P. Name……….. Officer……….
Signature…….. Divisional
Officer……….
Division………
Issued on……………………… Received T. and P. Ledger Folio No……..........
Signature and Designation. ……………… ……………… …………….................
………………… Date …………….Signature. Ledger Keeper. Divisional Accountant
Supplying Officer
* The articles to be entered in column 2 should be grouped by the prescribed sub-heads of classification, vide paragraph 7.3.7.
** The entries in respect of articles lent or sent out (vide paragraph 7.3.3.) should be distinguished from others by a suitable
remark in column 12.
FORM 14
TOOLS AND PLANT LEDGER
(Referred to in paras 7.3.7 and 7.3.8)
Part I
Articles in hand
Name of article……………….
Permanent * Temporary
transactions transactions
Date
of value
adjustment
vouchers or
Reference to
Issues
6B
Issues
5B
Remarks
Receipts
6A
Total issues
(5B plus 6B)
Serial No.
Balance
Initials of Sub-
From whom
received/To
whom issued
Receipts
5A
Total receipts
(5A plus 6A)
divisional Clerk
T&P received
sheet No. and
date/T&P Indent,
etc. No. and date
1 2 3 4 5 6 7 8 9 10 11 12
28
* Represents articles temporarily lent or sent out for repairs.
BOOK OF FORMS
Part II
Articles temporarily lent or sent out for repairs
Issues Receipts
Name of person Name of
No. Date of No.
or division article Date of
receipt received
issued
Balance
issue
Remarks
Serial No.
Initials of Sub-
back
divisional Clerk
1 2 3 4A 4B 5A 5B 6 7 8
Part III
Shortages awaiting adjustment
Remarks, including
Number found Reference to action taken for the
Name of person or Name of article short recovery or write clearance of shortages
division
off outstanding for more
Serial No.
than three months
1 2 3 4 5 6
29
BOOK OF FORMS
BOOK OF FORMS
FORM 15
STATEMENT OF RECEIPTS, ISSUES AND BALANCES OF ROAD METAL
(Referred to in paras 7.4.1 and 7.4.2)
Division……………. Sub-division……………..……
Road from…….to……...... Length…………… Kilometers
Month……………..20………..
Actual check
by
No. of kilometers
Expended during
Opening balance
measurement
Received during
Closing balance
Nature of metal
Remarks*
Results
month
month
Total
Date
1 2 3 4 5 6 7 8 9 10
Total
* The action taken in respect of deficiencies should be indicated in the remark’s column.
Note .- 1. The statement should show Kilometer by Kilometer the receipt, disposal and
balances of road metal of each kind, e.g., Stone, Kunker, etc.
2. Balance of metal for each Kilometer should be shown whether there are any transactions
on it during the month or not.
3. At the end of the account for any road or section of a road an abstract should be worked
out to show the receipts and issues according to estimates for the purpose of check with
the works accounts.
4. Copies of loose sheets should be submitted monthly to the Divisional Officer within a
fortnight of the submission of the monthly account.
5. Unused balances of the road metal should be verified at least once a year in the manner
prescribed in the rules.
6. Metal found surplus should at once be shown as receipts and deficits should not be
removed from the quantity accounts until recovery of their value or receipt of sanction to
their write off, but a red remark should be recorded at once in the remarks column and
carried forward from month to month until the discrepancy is set right.
30
FORM 16
RATE TABLE SHOWING THE LOWEST RATES AT WHICH METAL CAN BE SUPPLIED TO
THE ROAD SIDE THROUGHOUT THE DIVISION
(Referred to in para 7.4.4)
………………………Division
Distance carried Rate per 100 cubic meter
31
clearing,
No. of kilometers
Name of road
Remarks
etc.
1 2 3 4 5 6 7 8 9 10 11
BOOK OF FORMS
. P. . P. . P. . P. . P.
The rates should be revised from time to time as old quarries are exhausted or new ones opened or other circumstances
affect the rates.
FORM 17
SURVEY REPORT OF STORES*
(Referred to in paras 7.2.39 and 7.3.19)
Report of the survey of stores which have become unserviceable
Division……………………..
Sub-division…………………
32
BOOK OF FORMS
In charge……….
* Authority to write off should be obtained in this form.
** If the book value is not known, the replacement value should be entered in this column.
No……….dated the…………20…… No……….dated the…………20……
Submitted to the…………Engineer for Returned to the……..for necessary
orders with reference to paragraph 307 action as per orders noted above.
of the K.P.W.D. Code.
Divisional Officer Chief Engineer
Superintending Engineer
FORM 18
SALE ACCOUNT
(Referred to in para 7.2.24 and 7.3.13)
…………………..Division
Authority for the sale………………. ……………. Sub-division
when sold
Unit
Number
To whom and
necessary adjustment
. P. . P. . P.
33
Total
BOOK OF FORMS
FORM 19
MUSTER ROLL
(Referred to in paras 10.2.4, 10.2.6 and 10.2.7)
Muster Roll No…………….of labour employed on…………….
……………………. (Here enter name of work)
From…………..To…………………..
Notes
1. The nominal muster roll is the initial record Kerala…………… Department
of the labour employed each day on a
work and must be written up daily by the
subordinate.
34
BOOK OF FORMS
35
BOOK OF FORMS
11. Part II of the form is an extract from the Closed and resubmitted to the
measurement books of the officer- in- measuring officer.
charge of the work and will be filled in
before submitting the roll to the Sub-
divisional Officer
36
BOOK OF FORMS
14. All nominal muster rolls should be Measured and submitted for audit
numbered serially for a year in each sub- and payment.
division under the initials of the Sub-
division Officer and entered in the register
kept for the purpose before they are
issued to the section officers for use in Section Officer or other measuring
the works and their eventual return after officer
use should be watched and noted in the
register.
37
Part I
Dates Deduction
1 2 3 so on 31
Name Rate Amount Balance
Cont. Misc. Total
P.F.
Remarks
Serial No. or
Ticket No.
Dated initials of the
Disbursing Officer
Description or Class
. P. . P. . P. . P. . P. . P.
Initials of the
officer marking the
attendance daily
Initials of the
Total
38
Inspecting Officer
Allocation of labour . P.
............................................... Deduct amount
BOOK OF FORMS
39
BOOK OF FORMS
Total
Amount as per Muster Roll
Dated………………20………….. Signature…………………….
Officer –in-charge…………..
Section/Sub-division…….....
FORM 19A
REGISTER OF UNPAID WAGES
[Referred to in para 10.2.6 (d)]
Name of work…………………….
Sl.No.
. P. . P.
40
1 2 3 4 5 6 7 8 9 10
BOOK OF FORMS
Note. – The name of the work should be mentioned at the top before recording the entries relating to that work.
FORM 20
CASUAL LABOUR ROLL
[Referred to in para 10.2.6 (h)]
Casual Labour Roll of labour employed on the………………………………….. (Here enter name of work)
From………………….. To …………………………
Rate Amount
Name and Address Period
age
Work to which
chargeable
Dated initials
of the Paying
Officer
Remarks
Nature and
quantity of
work done
Description
or class
Serial number
Signature or thumb
impression of the
labourer with date
. P. . P.
1 2 3 4 5 6 7 8 9 10 11 12
41
Total
BOOK OF FORMS
FORM 21
MEASUREMENT BOOK
(Referred to in paras 10.2.9 and 10.2.11)
Division/Circle…………………..
Sub-division/Section…………….
Notes
1. The measurement book is the basis of all accounts of quantities, whether for
work done by piece work or by contract, or of materials received for specific
works which have to be measured, and should be so kept that the transaction
may be readily traceable into the accounts.
(b) Erasures and over writings in the measurement books are strictly prohibited
and will be seriously noticed. If mistakes are made, they should be corrected
by neatly scoring off the incorrect entries and inserting the correct ones in
red ink between the lines. Dated initials of the recording officer shall be
insisted on, on each page of the measurement book in the case of original
entries and initials, in the case of each and every correction. In the case of
contract work the contractor’s signature should be taken in the measurement
book in token of the contractor’s acceptance of the measurements recorded
either at the time of measurement or in any case, before payment, to avoid
complaints of omissions, incorrectness, etc.
3. (a) No member of the executive staff below the rank of a Section Officer in
responsible charge of a work, is empowered to measure a work and make
42
BOOK OF FORMS
(b) Each measurement book issued to a particular officer is his own personal
record and he is responsible for its safe custody and correct maintenance
until it is finally returned to the office for record, after completion or transferred
in the meantime by official transfer, to his successor on relief. Except when
the book is sent officially to other offices for preparation, audit and payment
of bills, book must always be in the personal custody of the officer who
owns the book.
4. (a) For easy identification and check, the descriptions of the locality and items
must be lucid; and the measurements shall be recorded systematically item
by item of the sanctioned estimates nothing also the respective item numbers.
The total of the quantities under the different items as entered in the quantity
column of the measurement book should be in the case of each bill, an up-to-
date quantity and not a ‘Since Last’ quantity.
(b) For large works separate measurement books shall be kept by the measuring
officer for each individual work or contract, or if found necessary or
convenient, separate books may be set apart for different classes of works,
or sub-heads of works, in which himself and checking officer will have with
them at the time of any measurement or check-measurement all the previous
measurements in one and the same book for easy reference and guidance.
Promiscuous recording of the measurements of one and the same work
43
BOOK OF FORMS
5. In the case of extra items or extra rates, the orders sanctioning its execution
or provision should invariably be quoted in the measurement books and the
bills before the auditing section passes such claims for payment .The
measuring officer may however record extra items, if any, in the measurement
books, if he is satisfied that they are covered at least by the written orders of
the Inspecting Officers in the work spot order books though not at time of
measurement, regularised by formal sanction of competent authority. The
audit section will all the same differ passing of such items until, formal
sanction is secured. Such items, will however be included in the quantity
columns of the bills, but the rates and amounts will be noted therein only on
receipt of formal sanction of competent authority to such items. This
stipulation is precautionary, to ensure that, the measurement and check-
measurement of extra items which it may be difficult or impossible to measure
at a later stage of a work, should not be postponed till it is too late, and such
items may not be lost sight of, while closing or checking interim bills or at the
time of final payment.
6. The measuring officer shall be responsible for closing the bills in the
measurement books taking care to enter therein correctly, all references,
previous measurement and all receipts and issues of materials up-to-date
and effect all recoveries. This shall be observed as an orthodox rule, as
the measuring officer is primarily and wholly responsible for all entries
made by him in the measurement book, and for the bills as corrected and
finally passed on for audit on the basis of those measurements. In fact,
the bill will be simply an exact copy of the closing abstract as made out
by the measuring officer in the measurement book.
7. From the measurement book, all quantities should be clearly traceable into
the documents on which payments are made and reference to the voucher
44
BOOK OF FORMS
in which the quantities are entered for payment as well as the date of entry
should be given by endorsement upon the original entries in the measurement
book. No contract certificate or bills should be signed without crossing out
connected entry in the measurement books and the document on which
payment is made should invariably bear a reference to the number and page
of the book in which detailed measurements are recorded.
8. The measurement books are thus one of the most important initial records
relating to the execution and payment of works. They should be carefully
checked by the Divisional/Sub-division Officer to see that they are kept as
complete records of each kind of work done for which certificates have been
granted. The eventual return of all books to the Division Office for record
should be insisted upon.
45
Name of work………………... Date of measurement……………….
Name of Contractor…………. Agreement No……………………….
1 2 3 4 5 6 7 8 9
Reference
to estimate Deduct previous Since last
Measurement up-to-date
measurement measurement
Particulars Total
Rate value
No. L. B. D. Contents to date
Book Page
or area
Value at rate
in Col.6
Item No.
Quantity
Quantity
Clos.5-8
Remarks
Sub-head
46
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
. P. . P. . P.
BOOK OF FORMS
BOOK OF FORMS
FORM 22
GOVERNMENT OF KERALA………………DEPARTMENT
Division…………………..
Sub-division………………
Section……………………
Name of work ..
Reference to agreement ..
47
FORM 22 - (Contd.)
Part I
Description, quantities and value of work done or supplies made
As per Reference to
As per Value at
measurement
estimate agreement No. Description of agreement
book Quantity of
work done or rate of work
work done or
supplies made done or
supplies made
supplies
Page No.
Unit
made
Item No.
Number,
quantity
or weight
Remarks
Rate
Number,
quantity or
weight
Book No.
Rate
. P. . P. . P.
48
BOOK OF FORMS
49
B. Remarks by Check-measuring Officer
[Here enter the nature of the check-measurement taken or other examination of the work and the result of such
BOOK OF FORMS
examination.]
Check - measured
Sub - divisional Officer Divisional Officer.
C. Audit Section
Checked again the calculations and verified the rates against the contract schedule, quantities against estimate –
Provisions and receipts and issues against sanctioned data.
……………………………Accountant. ……………………………… Accountant
………………………………………….....
……………………………..Head Clerk. Divisional Accountant.
BOOK OF FORMS
FORM 22 - (Contd)
Part III – Memorandum of Payments
Figures 1. Total value of work done as per Part I, column 19(F) . P. . P.
for work 2. Details of payment made
abstract (a) By recovery of amounts creditable to the
work—
. P. (i) Value of departmental materials or stock
supplied and used up as per Col. 7 of Part IV
of this bill
(ii) Works done departmentally on account of
the contractor as per C.B.V. No.
G
*(b) By recovery of amounts creditable to other
works or heads of accounts.—
(i) Income tax
(ii) Sales Tax
(iii) Revenue/Receipts and recoveries
(c) By cheque
H
The total value of work is admitted and passed for Rupees (in words)…………
………………………………… ………………………………….... .………as
detailed in item (2) of the memorandum of payment.
Certified that the bill Officer authorising Dated Signature…………………
as passed above has payment Rank……………………………..
been ledgered.
Divisional Accountant.
Paid by Cheque No………………….dated……………….20
Divisional Officer.
Received (in words) ………………………………………………………………… on
account of this work as a final payment in settlement of all demands.
Dated: Left hand thumb impression.
Stamp
(in figures)…………………………………
Witness. Full Signature of Contractor
For use in Accountant General’s Office.
Audited. Reviewed.
Auditor. Superintendent. Gazetted Officer.
* Substitution G.O.(P) 103/77/Fin. dated 23-3-1977.
50
FORM 22 - (Concld)
Part IV
Materials Account
Description of
materials
This bill
Total in hand
Value at the rate in
Column 4
Divisional or
District Stores
Indent No. and
Cash Book
Vouchers No.
Issues as per this bill
Unit
Rate
With Contractor
Serial No.
Total
With Government
1 2 3 4 5 6 7 8 9 10
51
. P. . P.
BOOK OF FORMS
FORM 22A
GOVERNMENT OF KERALA ……………………..DEPARTMENT
Division………………….. Sub-division…………………
FINAL BILL
(To be used for ‘final payments’ to contractors on lump-sum contracts)
Cash Book Vouchers No…………………………….Dated………………………………
Name of contractor………………………………….
Name of work………………………………………..
Serial number of this bill…………………………….
No. and date of his previous bill for this work……………………….............................
Reference to agreement……………………………….
Date of written order to commence work………………………………………………...
Date of actual completion of work………………………………………………………..
Part I
Account of work executed
Remarks
Rate Unit
item of work Quantity Amount
1 2 3 4 5 6
. P. . P.
Lump-sum
for each
Add for additions and
alterations in work
Deduct
Total value of work
done to date
(F)
52
BOOK OF FORMS
Form 22A - (contd)
Part II - Certificate and Signature
1. Certify that the work has been completed in accordance with the prescribed drawings
and specification and after taking into account all the authorised additions and
alterations the value of work done up-to-date conformably with the terms of the
contractor’s agreement, is ………….
2. The detailed measurements of the authorised additions and alterations mentioned
above were made by……………………on………………..and are recorded at
page(s) of Measurement Book No………of 19……. and I am satisfied that they
are correct.
Dated signature of authorised
Engineer.
………………………………...
Rank……………………………
Part III - Memorandum of Payments
1. Total value of work done as per Part I (F) . P.
2. Deduct
(i) Up-to-date intermediate payment as per entry ‘K’ . P.
of Part I of the last running account bill No……
dated …………… (D)
(ii) Total secured advances outstanding as per entry ‘C’
of Part II of account bill No..........dated………….. (E)
3. Payments now to be made: —
(a) By recovery of amounts creditable to this
work (G)
(b) By recovery of amounts creditable to other
work of heads of account
* (i) Income tax
(ii) Other items (H)
(c) By cheque
G+H
(Col. 1-2)
Pay *** ( ………..) Rupees (in words)…………………………………………........
Checked with agreement; Dated signature…………………
checked the calculations
for additions and alterations Designation of the Officer
with the rates. authorising payment…………..
Divisional Accountant.
* Substitution G.O (P) 103/77/Fin. dated 23-3-1977.
** Here specify the amount as per column3(c).
53
BOOK OF FORMS
Stamp
Audited Reviewed.
Part V - Remarks
* The payees’ acknowledgement should be for the gross amount as per 3(a+b+c)
54
BOOK OF FORMS
FORM 23
GOVERNMENT OF KERALA …………………..DEPARTMENT
Division……………………
Sub-division……………….
Section…………………….
[For Contractor : -This form provides for (1) Secured advance and payment for
measured works]
Name of work
Reference to agreement ..
55
FORM 23 - (Contd.)
Part I
Account of work executed
Rate
Rate
Page No.
Remarks
Serial No.
Unit
Up-to-date
Since last bill
Number, quantity
or weight
Book No.
Up-to-date
Since last bill
Number, quantity
or weight
56
1 2 3 4 5 6 7 8 9
. P. . P. . P. . P.
BOOK OF FORMS
57
[Here enter the nature of the check-measurement taken or other examination of the work and the result of such
examination.]
BOOK OF FORMS
Check-measured
Sub-divisional Officer. Divisional Officer.
C. Audit Section
Checked again the calculations and verified the rates against the contract schedule, quantities against estimate
provision and receipts and issues against sanctioned data.
Accountant Accountant
Head Clerk…………………………. Divisional Accountant
BOOK OF FORMS
FORM 23 - (Contd.)
Part III - Memorandum of Payments
Figures for 1. Total value of work done as per Part I, Column II, Entry
. P. . P.
works (A)
abstract
. P. 2. Deduct amount withheld -
(a) from previous bill
(b) from this bill
3. Balance, i.e., up-to-date payment (Items1-2) K
4. Total amounts of payments already made as per entry (K) of
Last Running Accounts Bill No……………….forwarded with
accounts for
5. Payments now to be made as detailed below:
(a) By Recovery of amounts creditable to this work -
(i) Value of departmental materials or stock supplied and used
up as per column…………….of Part IV – material
accounts of this bill …P
Total of items 2(b) and 5(a)…………………………. (G)
*(b) By recovery of amounts creditable to other works, heads
of accounts, etc.
(i) Income tax
(ii) Sales tax
(iii) Revenue /Receipt and recoveries
(c) By cheque
Total 5(b) and (c)…………………………………… (H)
The total up-to-date value of work is admitted for Rupees……………………........................
…………………………………………….and after deducting the previous payments and including
the amount withheld, the bill is passed for Rupees…………………………….......................
………………………………………………………. [item5(c)]
Certified that the Officer authorising Dated Signature
bill as passed above payment
has been ledgered Rank:
Head Accountant. Divisional Officer
Paid by Cheque No………….dated ………………20……………….
Divisional Officer
Received Rupees (in words)…………………………………………………………………. ………………on
account of this work (as a final payment in settlement of all demands)
Dated Left hand thumb impression
Stamp
Witness Full signature of Contractor
For use in Accountant General’s Office
Audited Reviewed.
Auditor. Superintendent. Gazetted Officer.
*Substitution G.O. (P) 103/77/Fin. dated 23-3-1977.
58
FORM 23 - (Contd)
Part IV
Material Account
Balance
Since receipt as per Since issues
in hand
Divisional or District
Description store indent No. and
of materials cash book voucher
No…..
Total issues
With departmental
agencies
Rate as in agreement
This bill
Unit
Quantity in hand as per
last C.C
Store
indent
No.
Value as per rate in
Col.4
Serial No.
As per this bill
With Contractor
W.B.O
works as per W.B.O
Transferred to other
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
59
. P.
BOOK OF FORMS
is
of
of
(6)&(7)
60
Quantity
ac t u al l y
utilised on the
work up-to-
date excluding
wastage
Remarks
Quantity of
work executed
up-to-date
Description of
items of work
on which the
material
utilised
C o - ef fi c i e n t
(Material
required per
unit of work)
Theoretical
quantity
materials for the
quantity
work executed
(Col. 3x4)
Reference to
Sl.No. in agree-
ment (original or
suppl.)
Total of columns
Quantity if any
allowed as per-
missible wastage
1 2 3 4 5 6 7 8 9
BOOK OF FORMS
Total
Note: 1. (A) Should agree with the total as per Col. (8)
2. Difference between the total of Col. (5) and the total quantity as per Col. (6) may be explained in Col. (9)
3. Total of (c) + (d) + (e) should be equal to (b).
4. Where recovery has been effected either for short usage of materials resulting in substandard work or for excess usage
of materials, the fact may also be stated in the remarks column giving reference to the bills in which recoveries were
effected.
Checked
Asst. Ex. Engineer / Head Draughtsman/ Ex. Engineer.
* Substitution. G.O. (P) 799/81. Fin dated 25-11-1981
BOOK OF FORMS
FORM 23 A
ACCOUNT OF SECURED ADVANCE
(Referred to in para 10.2.18)
(To be annexed to form 23 where necessary)
Division ......................................
Sub - division .............................
Name of Contractor ...................
Name of work ............................. Cash Book Voucher No.............. dated ...............
Sl.No. of the Bill to which the
Accounts pertains ....................
Reference to Agreement ............
Account of secured advances allowed on the security
of materials brought to site
Full rates as assessed by the
** Up-to-date amount of
Description of materials
* Quantity outstanding
Reference to Divisional
authorising advance
Divisional Officer
advance is made
previous bill
previous bill
advance
Unit
1 2 3 4 5 6 7 8 9 10
61
BOOK OF FORMS
FORM 23 A - (Concld.)
* Certified (1) that the plus quantities of materials shown in column 3 of the
account above have actually been brought by the contractor to the site of
the work and the contractor has not previously received any advance on
their security,(2) that these materials are of an imperishable nature and are all
required by the contractor for use on the work in connection with items for
which rates for finished work have been agreed upon , and (3) that a formal
agreement in form 23 signed and executed by the contractor in accordance
with paragraph 10.2.16 (b) of the Kerala Public Works Account Code is
recorded in the Divisional Office.
† This signature is necessary only when officer who prepares the bill is not the
officer who authorises the payment. In such a case the two signatures are essential.
62
BOOK OF FORMS
FORM 23 B
GOVERNMENT OF KERALA …………………..DEPARTMENT
Division………....………… Sub-division……………….....
RUNNING ACCOUNT BILL
(To be used for “intermediate payment” to Contractors on lump sum contracts)
Cash Book Voucher No …………………….dated………………………..
Name of the Contractor……………………………………………………..
Name of work ……………………………………………………………....
Serial No. of the Bill …………………………………………………….....
No. and date of his previous bill for this work ……………………….....
Reference to agreement …………………………………………………...
Date of written order to commence work ……………………………......
Part I
Account of work executed
1. Approximate value of work done up-to-date excluding the measured . P.
up additions and alterations
2. Value of measured up additions and alterations
3. Deduct amount to be withheld
4. Balance i.e., ‘up-to-date’ intermediate payment (Items 1+ 2- 3) K
5. Deduct intermediate payment already made as per entry ‘K’ of
the last Running Account Bill
6. Intermediate payment now to be made (Items 4-5) D
7. Amount of ‘secured’ advances as per entry ‘E’ of Part II of Account
Bill
8. Total payments now to be made as detailed below*
. P.
(a) By recovery of amounts creditable to this work G
(b) By recovery of amounts creditable to other works
or heads of account
** (i) Income tax H
(ii) Other items
(c) By cheque
G+H
* The total figures against item 8 should be tested to see that it agrees with the total
of items 6 and 7.
** Substitution G.O.(P) 103/77/Fin. dated 23-3-1977.
63
BOOK OF FORMS
FORM 23 B - (Contd.)
Part –II
Account of “Secured” advances allowed on the
security of materials brought to site
* Quantity outstanding (including
*Deduct quantity utilised in work
advance
is made
Unit
1 2 3 4 5 6 7 8 9 10
. P.
64
BOOK OF FORMS
FORM 23 B - (Contd.)
Part III
Certificates and Signatures
Rank……………………………………
* Here specify the method employed for estimating the value of work.
† Here specify the amount as per column 8(c) of Part I.
65
BOOK OF FORMS
Stamp
Audited Reviewed.
Part V - Remarks
* The payee’s acknowledgement should be for the gross amount as per column 8
(a+b+c) of Part I.
66
BOOK OF FORMS
FORM 23 C
INDENTURE FOR SECURED ADVANCES
[Referred to in paras 10.2.31 and 10.2.33 (b)]
(For use in cases in which the contract is for finished work and the contractor
has entered into an agreement for the execution of certain specified quantity
of work in a given time)
67
BOOK OF FORMS
(2) That the materials detailed in the said account of secured advance
which have been offered to and accepted by the Government as
security are absolutely the Contractor’s own property and free from
encumbrances of any kind and the Contractor will not make any
application for or receive a further advance on the security of
materials which are not absolutely his own property and free from
encumbrances of any kind and the Contractor indemnifies the
Government against all claims to any materials in respect of which
an advance has been made to him as aforesaid.
(3) That the materials detailed in the said account of secured advances and
all other materials on the security of which any further advance or
advances may hereafter be made as aforesaid (hereinafter called the
said materials) shall be used by the Contractor solely in the execution of
the said works in accordance with the directions of the Divisional
Officer,……………. Division (hereinafter called the Divisional
Officer)and in the terms of the said agreement.
(4) That the Contractor shall make at his own cost all necessary and
adequate agreements for the proper watch, safe custody and
68
BOOK OF FORMS
protection against all risks of the said materials and that until used
in construction as aforesaid the said materials shall remain at the
site of said works in the Contractors custody and on his own
responsibility and shall at all times be open to inspection by the
Divisional Officer or any officer authorised by him. In the event of
the said materials or any part thereof being stolen, destroyed or
damaged or becoming deteriorated in a greater degree than is due
to reasonable use and wear thereof the Contractor will forthwith
replace the same with other materials of the like quality or repair
and make good the same as required by the Divisional Officer.
(5) That the said materials shall not on any account be removed from the
site of the said works except with the written permission of the Divisional
Officer or an officer authorised by him on that behalf.
(6) That the advances shall be repayable in full when on or before the
Contractor receives payment from the Government of the price payable
to him for the said works under the terms and provisions of the said
agreement. Provided that if any intermediate payments are made to the
Contractor on account of work done than on the occasion of each
such payment the Government will be at liberty to make a recovery
from the Contractor’s bill for such payment by deducting there from
the value of the said materials then actually used in the construction
and in respect of which recovery has not been made previously, the
value of this purpose being determined in respect of each description
of materials at the rates at which the amounts of the advances made
under these presents were calculated.
(7) That if the Contractor shall at any time make any default in the
performance or observance in any respect of any of the terms and
provisions of the said agreement of these presents the total amountof
the advance or advances that may still be owing to the Government
69
BOOK OF FORMS
(8) That the Contractor hereby charges all the said materials with the
repayment to the Government of the said sum of Rupees……………
and any further sum or sum advanced as aforesaid and all costs,
charges, damages and expenses payable under these presents
PROVIDED ALWAYS and it is hereby agreed and declared that
notwithstanding anything in the said agreement and without prejudice
to the powers contained therein if and whenever the covenant for
payment and repayment hereinbefore contained shall become
enforceable and the money owing shall not be paid in accordance
therewith the Government may at any time thereafter adopt all or any
of the following courses as he may deem best:-
(a) Seize and utilise the said materials or any part thereof in the
completion of the said works on behalf of the Contractor in
accordance with the provisions in that behalf contained in the
said agreement debiting the Contractor with the actual cost of
effecting such completion and the amount due in respect of
advances under these presents and crediting the contractor with
the value of work done as if he had carried it out in accordance
with the said agreement and at the rates thereby provided. If the
balance is against the Contractor he is to pay the same to the
Government on demand.
70
BOOK OF FORMS
(b) Remove and sell by public auction the seized materials or any part
thereof and out of the moneys arising from the sale retain all the
sums aforesaid repayable or payable to the Government under these
presents and pay over the surplus (if any) to the Contractor.
(c) Deduct all or any part of the moneys owing out of the security
deposit or any sum due to the Contractor under the agreement.
(9) That except in the event of such default on the part of the Contractor
as aforesaid interest on the said advance shall not be payable.
(10) That in the event of any conflict between the provisions of these
presents and the said agreement the provisions of these presents
shall prevail and in the event of any dispute or difference arising
over the construction or effects of these presents the settlement of
which has not been herein before expressly provided for the same
shall be referred to the Government Arbitrator whose decision shall
be final and the provision of the Indian Arbitration Act for the time
being in force shall apply to any such reference.
In witness whereof the said *…………………………………and
†……………………………….. by the order and under the direction of
the Governor have hereunto set their respective hands the day and
year first above written.
Signed, sealed and delivered by…………………………………
the said contractor in the presence of witnesses:
Signature………………………………………
(1) Name……………………………..…………….
Address……………...…………………………..
Signature………………………………………
(2) Name……………………………..…………….
Address…………..…….………………………..
71
BOOK OF FORMS
Signed by ………………………………………………………….
for and on behalf of the Governor in the presence of witnesses:
Signature………………………………………
(1) Name……………………………..…………….
Address…………..……………….……………..
Signature………………………………………
(2) Name………………..………………………….
Address………..…………….…………………..
* Contractor’s name.
† Name and designation.
72
BOOK OF FORMS
FORM 24
HAND RECEIPT
(Referred to in paras 10.2.16 and 10.2.21)
(To be used as a simple form of voucher for all miscellaneous payments and
advances for which none of the special Forms 22 and 23 are suitable)
Cash Book Voucher No………………………dated…………………………
(1) Pay by Cheque* Rupees …………………to……………………….
Cash
(2) Paid by me † ………………………………………………………………………
Received from the Sub-divisional Officer-in-charge of……………………….
the sum of ( ……..) Rupees……………………………………………………
Witness……………………………….
For use in Divisional Office For use in Accountant
Sub-divisional General’s Office
Checked Audited Reviewed
73
FORM 25
PAY BILL OF WORK CHARGED ESTABLISHMENT
Kerala……………………….Department……………………….Division
Name of section……………………………. Bill for the month of……………………
Period
Serial No.
Reference to
sanction and
name of work to
which chargeable
Deduction (Fines,
absence, short
out-turns, etc.)
Reference to
schedule docket
Dated initials of
the Officer making
payment
Dated
acknowledgement
of payee
1 2 3 4 5 6 7 8 9 10 11 12 13
. P. . P. . P. . P.
74
Total ..
BOOK OF FORMS
1. Certified that all persons for whom wages have been drawn in this bill were on duty during the periods shown against their
names, each man being employed on the work and on duties for which his appointment was sanctioned and his pay is charged.
No person is employed in offices doing purely clerical, drawing, tracing or similar work.
2. Certified also that the wages of every person actually employed during the month have been claimed in this bill.
Pay Rupees (……)………………………………………
Dated……………………………..Signature…………………………
Assistant Engineer
Certified that the amount claimed in this bill have been disbursed to the persons named in the Acquittance Roll in my presence
and their acquittance obtained.
Checked and entered…………………………… Signature and rank of disburser
Dated signature of the Divisional Accountant
Remarks: Executive Engineer
BOOK OF FORMS
FORM 26
PETTY WORKS REQUISITION AND ACCOUNT
[Referred to in paras 10.2.6 (h) and 10.5.2]
(To be used for works and repairs not likely to cost more than 2, 500).
Requisition on the Divisional Officer, ……………..........………………………
Division …………………………, for…………………. (H.E. name of work)
Part I - Requisition
The undersigned wishes to have the following petty works carried out with
as little delay as possible.
.................................................................................................................................
.................................................................................................................................
(Here state the necessity for the work).
Rough estimate of probable cost
. P. . P.
Total ..
75
BOOK OF FORMS
FORM 26 – (Contd.)
Major Head……………Minor Head………………Detailed Head………………
Date…….20………..
Signature and Designation.
Sanctioned.
Date……..20……….. Signature of Divisional Officer
Accepted.
Date…….20……….. Signature and Designation
of responsible Civil Officer.
Part III - Summary of charges
Total of Initials of
Suspense account*
Cash book voucher
or transfer entry
Brief particulars
Sub-divisional
book item No.
Final charges
Accountant
The month
Up-to-date
Divisional
Officer
Total
. P.
Grand total
76
FORM 27
WORKS ABSTRACT ‘A’ FOR MAJOR WORKS
(Referred to in paras 10.5.1 and 10.5.23)
Division……….…………..
Sub-division………………
Month………….………….
Name of work……..………
Detail of up-to-date progress*
77
progress is taken Running Account Bill
(quoting page and book or other voucher
No. of Measurement 1 2 3
BOOK OF FORMS
Total
* Only quantities which have been actually measured and paid for on bills included in the Accounts should be
taken into this statement.
FORM 27– (Contd.)
Name of Work………....…… To be used when outlay is
Authority………....………... recorded by sub-heads
Brief
Total cost
particulars
Purchases
Materials
Labourers
Secured advances
C. B. V. or T. E. item No.
Other transactions/
Advance Payments
78
. P. . P. . P. . P. . P. . P. . P. . P. . P. . P. . P. . P. . P. . P. . P.
BOOK OF FORMS
BOOK OF FORMS
FORM 27 – (Concld.)
DETAIL OF CONTRACTOR’S CLOSING BALANCE
Reference to last
Closing balance
* Explanation of non-
running account bill
Name of
contractor
transactions
Voucher No.
adjustment
advances
payments
Advance
Secured
Other
Date
. P.
Total
The closing balance under the Suspense heads “Purchases” “Labourers” as arrived
at within has been compared with the connected records of outstanding liabilities
and unpaid wages for this work and found correct.
The work is still in progress. †
(Dated initials of Sub-divisional Officer)
* As a rule, reasons for delay should be recorded if an item is not cleared within the
three months.
† If the work was completed during the month, the fact should be stated within a
explanation of the steps taken to close the accounts of the work.
Certificate by Divisional Accountant
This abstract and state of progress have been checked under my supervision. I have
personally compared all the items in the “Detail of Contractors” “Closing balances”
with the Contractor’s Ledger and the items in the suspense account “Purchases” with
those in the Register of outstanding liabilities and found them correct.
(Dated initials of Divisional Officer)
Remarks by Divisional Officer
(This Divisional Officer will note here whether he had examined the work, counted
materials or checked measurements and make any other remarks in respect of the
execution of the work or of state of account as he may consider necessary).
(Dated initials of Divisional Officer)
79
BOOK OF FORMS
FORM 28
WORKS ABSTRACT ‘B’ FOR MINOR WORKS
(Referred to in paras 10.5.1, 10.5.3, 10.5.13, and 10.5.23)
Division: Folio in register of works:
Sub-division: Item in schedule of expenditure
Name of work: Schedule of docket:
Authority:
Month:
From what source
Suspense head
posted
adjustment book
page, or Voucher
Brief particulars
tions/ advance
Voucher No. or
Other transac-
Final charges
Cash Book
Purchases
Labourers
Total cost
payments
advance
Secured
No.
Estimate
No. . .
Expenditure
to end of . .
Month’s
transactions. .
Total ..
Total to end
of ..
80
BOOK OF FORMS
FORM 28 – (Concld.)
REFERENCE TO MEASUREMENTS
(A reference to any recorded measurements should be entered here)
Details of Contractor’s closing balance
Reference to last
running account bill Closing balance
* Explanation of
non-adjustment
Name of
transactions/
Voucher No.
contractor
payments
advance
Secured
advance
Other
Date
1 2 3 4 5 6
Total ..
The closing balance under the Suspense heads “Purchases” “Labourers” as arrived at
overleaf has been compared with the connected record of outstanding liabilities and
unpaid wages for work and found correct.
† The work is still in progress.
(Dated initials of Sub-divisional Officer)
* As a rule, reasons for delay should be recorded if an item is not cleared within three
months.
† If the work was completed during the month, the fact should be stated with an
explanation of the steps taken to close the accounts of the work.
Certificate by Divisional Accountant
This abstract has been checked under my supervision. I have compared personally all
the items in the “Detail of Contractors” “Closing Balances” with the Contractor’s
Ledger and the items in the suspense account “Purchases” with those in the Register
of outstanding liabilities and found them correct.
(Dated initials of Divisional Accountant)
81
BOOK OF FORMS
FORM 29
REPORT OF VERIFICATION OF UNUSED BALANCES
OF MATERIALS-AT-SITE
(Referred to in paras 10.3.15 and 10.3.18)
Description of materials Cement Steel Etc.
1. Balance as per Col.14 of Form 31
2. Actual balance as verified
3. Difference (+) excess
(-) less
4. Explanation for the difference
5. Action taken for adjustment of the difference
as per line 3 and for the disposal of the balance
(if the work has been completed ) as per line 2
Certificate
1. Certified that the quantities of the actual balances recorded against line 7 are the results
of verification made by me on ……………………….
2. Certified that the balance of materials- at- site of this work were verified by me on
………………………. and that the necessary report in this form was submitted to the
Divisional Officer in this office No. ….. dated…….
3. The balances of unused materials were not verified at any time during the year
……………….. as the accounts of this work are expected to be closed within three
months.
4. The balances of unused materials were not verified at any time during the year
……………….. as work was not under construction prior to …………………of that
year.
5. All modifications of the original estimate involving changes in the estimated quantity of
the principal items used have been recorded and the requisite sanction quoted to the
change.
Note. — The certificates not applicable to the case should be scored out.
Checked
Divisional Accountant (Signature of the Sub-divisional Officer)
Date…………..…. Date……….....…….
Divisional Officer’s order on the above proposals.
(Signature of the Divisional Officer)
Date……….…...….
82
FORM 31
REGISTER OF MATERIALS AT-SITE ACCOUNTS
(Referred to in para 10.3.18)
1. Division……………………………….
2. Sub-division…………………………...
3. Section ………………………………..
4. Name of work…………………………
5. Month…………………………………
Estimated
requirements
83
Balance
(12-13)
Balances
Remarks
Total
receipts
Reference to measure-
ment book or other
record
Total
issues
Total issues
to end of
month (Col.
8+11)
Issues
Total receipts
to end of
month (Col.
7+10)
Receipts
Issue
BOOK OF FORMS
Item No.
Description of materials
Qty. Unit Qty. Qty. Qty. Qty. Qty. Qty. Qty. Qty.
rate
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
. P.
* Similar columns should be opened for each of the months May to March and March supplemental.
Checked Checked
Sub-divisional Clerk Sub-divisional Officer Divisional Accountant Executive Engineer
………….Sub-division ………….Sub-division …………. Division …………. Division
BOOK OF FORMS
FORM 31 (A)
ACCOUNT OF MATERIALS ISSUED TO CONTRACTORS
(Referred to in para 10.3.6)
Division…………………..
Sub-division………………
Name of work………………………
Dated initials of
token of check
Accountant in
Sub-divisional
Dated initials
of Divisional
Total issues to the work
Officer
Description
of materials
Unit
Estimated
requirements
(quantities)
1 2 3 4 5 6 7
Balance B/F
to end of
March
April 20………
Progressive
Sub-divisional Officer,
……..…........….Sub-division .
84
BOOK OF FORMS
FORM 34
REGISTER SHOWING THE CLEARANCE OF THE
SUSPENSE HEAD “MATERIALS”
(Referred to in para 10.3.19.)
Division……………… Name of work…………
Sub-division………….
I - Statement showing the quantities and value of
materials used in construction *
Name of the sub-
head of the work
Description
of materials
Total value
Quantity
executed
Cement
Steel
Unit Ton Ton
Rate
Quantity/
Value
Brick works
Pucca Masonry
* Total used in construction.
The quantity used in construction should be calculated on the basis of work executed,
such authorised formulae being adopted for the purpose as may be in use locally.
II - Statement showing the adjustment of surpluses/ deficits
1. Quantities issued as per column 13
of register of materials-at-site
account (Form 31)
2. Quantities used as per Part I of this register
3. Difference (+) Excess issue
(-) Less issue
4. Explanation of differences.
Certified that the quantities of the various items shown in the above statement have been
worked out as accurately as possible on the basis of the quantities of the work actually
done.
Sub-divisional Officer,
Executive Engineer,
…….…………. Division.
Order of the
Divisional Officer.
85
FORM 34 - (Concld.)
III. STATEMENT SHOWING THE DISPOSAL OF MATERIALS REMAINING UNUSED AS PER
MATERIALS-AT-SITE ACCOUNTS
86
Head of account to be debited
If debited to sub-head
of this work
Divisional Accountant’s
dated initials
BOOK OF FORMS
Transferred to S.D.O.
...... .......…….Sub-Dn.
Sold by auction
Loss debitable to
sub-head
Total
BOOK OF FORMS
FORM 36
OUT-TURN STATEMENT OF MANUFACTURE
(Referred to in para 12.3.2)
Name of manufacture….....…………Site………........………Season……….......……….
Authority…………………………….Name of work…………………………………........
Remarks
previous month* Total
and values)* month*
1 2 3 4 5 6
Total values
* The values should be entered in red ink just below the quantities.
This should be attached to the Work Abstract for the operations.
87
FORM 37
WORK SLIP
(Referred to in para 10.6.3)
Division………………………… Name of work…………………………
Month…………………………..
88
Rate Cost Rate Rate
to date cost
Explanations of deviations,
excess etc.
Approximate
quantity
Quantity
Quantity
BOOK OF FORMS
1 2 3 4 5 6 7 8 9 10 11
. P. . P. . P. . P. . P.
Total charges Probable further
Total of estimate .. against final expenditure - A
heads
Add—Suspense Accounts—
,, Materials .. .. ..
,, Purchase .. .. ..
,, Secured Advance .. .. ..
,, Contractors—Other
Transactions /
Advance Payments .. .. ..
89
,, Labourers .. .. ..
Total booked outlay to date ..
Probable further expenditure as in entry A above ..
BOOK OF FORMS
Total ..
Deduct –Suspense accounts recoverable ..
Work commenced in -
Present state of progress in general terms.
Divisional Accountant. Divisional Officer,
Date……………..20……….. Date………..……20……….
BOOK OF FORMS
FORM
REGISTER OF WORKS ‘A’
(Referred to in para
Name of work…............…………… Authority .....................................
Sub-heads
costing
................
Month and below
Quantity
Quantity
Quantity
Quantity
Quantity
Quantity
Quantity
Quantity
. P. . P. . P. . P. . P. . P. . P. . P.
..
Estimate No.of
Expenditure to end of . .
previous year brought
forward (if any)
April 20 ..
Total ..
Rate of cost ..
May 20 ..
Total ..
Rate of cost ..
June 20 ..
Total ..
Rate of cost ..
July 20 ..
Total ..
Rate of cost ..
August 20 ..
Total ..
Rate of cost ..
September 20 ..
Total ..
Rate of cost ..
October 20 ..
Total ..
90
BOOK OF FORMS
38
FOR MAJOR WORKS
10.6.1 to 10.6.11)
Appropriation for the year ...............................
Additional
Other transactions/
Dated initials of
advance payments
Petty charge for
Secured advances
the Executive
supervision and materials issued Engineer to
Contingencies to contractor transactions of
Purchases
Total cost
Materials
direct to works the month
Labour
Amt Amt Amt Amt Amt Amt Amt Amt
Quantity
Quantity
. P. . P. . P. . P. . P. . P. . P. . P.
91
BOOK OF FORMS
FORM 38
Sub-heads
costing
.................
Month and below
Quantity
Quantity
Quantity
Quantity
Quantity
Quantity
Quantity
Quantity
. P. . P. . P. . P. . P. . P. . P. . P.
Rate of cost ..
November 20 ..
Total ..
Rate of cost ..
..
December 20
Total ..
Rate of cost ..
January 20 ..
Total ..
Rate of cost ..
..
February 20
Total ..
Rate of cost ..
March 20 ..
Total ..
Rate of cost ..
March Supplementary . .
Total ..
Rate of cost ..
92
BOOK OF FORMS
- (Concld)
Other transactions/
Additional Dated initials of
advance payments
Petty charge for
Secured advances
the Executive
supervision and materials issued Engineer to
contingencies to contractor transactions of
Purchases
Total cost
Materials
direct to works the month
Labour
Amt Amt Amt Amt Amt Amt Amt Amt
Quantity
Quantity
. P. . P. . P. . P. . P. . P. . P. . P.
93
FORM 39
REGISTER OF WORKS ‘B’ FOR MINOR WORKS
(Referred to in paras 10.6.1. to 10.6.11.)
Estimate
Dated initials of
Suspense
94
Months, etc. Total value of Divisional Officer
accounts Total charges
work done to transaction of
the month
BOOK OF FORMS
`. P. `. P. `. P.
Expenditure of previous years
brought forward if any ..
April 20….. ..
Total ..
May 20….. ..
Total ..
FORM 39 - (Concld.)
June 20….. ..
Total ..
July 20….. ..
Total ..
August 20 ….. ..
Total ..
September 20 ….. ..
Total ..
October 20 ….. ..
Total ..
November 20….. ..
95
Total ..
December 20….. ..
Total ..
BOOK OF FORMS
January 20 ….. ..
Total ..
February 20….. ..
Total ..
March 20 ….. ..
Total ..
Supplementary Account ..
Total ..
BOOK OF FORMS
FORM
REGISTER OF
(Referred to in
Name of manufacture..............................
Site .........................................................
Season ....................................................
Authority ...............................................
Operation
Months, etc.
Quantity
Quantity
Quantity
Quantity
Quantity
Quantity
Quantity
Amt Amt Amt Amt Amt Amt Amt
Estimate No. `. P. `. P. `. P. `. P. `. P. `. P. `. P.
Brought forward
from previous year ..
April ..
Total ..
Rate ..
May ..
Total ..
Rate ..
June ..
Total ..
Rate ..
July ..
Total ..
Rate ..
August ..
Total ..
Rate ..
September ..
Total ..
Rate ..
96
BOOK OF FORMS
40
MANUFACTURE
para 12.1.3.)
Out-turn
Dated initials of
Balance at debit Divisional Officer
Quantity
Quantity
Quantity
`. P. `. P. `. P. `. P.
97
BOOK OF FORMS
FORM
Operation
Months, etc.
Quantity
Quantity
Quantity
Quantity
Quantity
Quantity
Quantity
Estimate No. `. P. `. P. `. P. `. P. `. P. `. P. `. P.
October ..
Total ..
Rate ..
November ..
Total ..
Rate ..
December ..
Total ..
Rate ..
January ..
Total ..
Rate ..
February ..
Total ..
Rate ..
March ..
Total ..
Rate ..
Supplementary
Account ..
Total ..
Rate ..
98
BOOK OF FORMS
40 - (Concld)
Out-turn
Dated initials of
Balance at debit Divisional Officer
Quantity
Quantity
Quantity
`. P. `. P. `. P. `. P.
99
FORM 41
CONTRACTORS’ LEDGER
(Referred to in paras 10.7.1 to 10.7.9)
Name of contractor…………………………..
† Name of work or
“Other Total value
Serial no. “Secured account (in red ink)
Transactions/ of work or
of a Advances” Advanced and particulars of
Debits Credits supplies
Date No. running
+ = Debits payments” transactions
account - = Credits + = Debits
100
bill E* - = Credits
Remarks
G* H* F* A*
BOOK OF FORMS
1 2 3 4 5 6 7 8 9 10
`. P. `. P. `. P. `. P. `. P.
* These letters indicate in respect of each Running Account Bill the corresponding entries in form 23.
† If these are several contracts in connection with a work or account, the transactions relating to each should be
distinguished preferably by quoting the number and date of agreement or work order.
BOOK OF FORMS
FORM 42
DETAILED COMPLETION REPORT
Division…………………….
Name of work…………………………………
Amount of estimate…………………………..
Expenditure…………………………………..
Difference…………………………………….
Percentage of excess…………………………
Date of commencement……………………..
Date of completion…………………………..
Forwarded to the………………………….....
Explanation of differences
Notes
1. This form should be submitted to the Divisional Officer after submission of
the accounts of the month in which the work is reported to be completed.
2. The entries in the completion report must accord with the closing entries in
the Register of Works, and the last schedule docket submitted to the
Divisional Officer.
3. In the case of contribution works proposals should be submitted as to
disposal of the unexpended balance, if any, of the deposit amount.
4. When the Divisional Officer considers that narrative report of the work would
be useful and interesting from any special feature, difficulty or failure during
the progress of the work, he should sent one with this form.
101
FORM 42 - (Contd.)
DETAILED COMPLETION REPORT
(Referred to in para 10.6.11)
Name of work………………………
Major Head…………………………
Minor Head………………………… Reference to last schedule docket submitted……………..
Detailed head of classification……… Authority……………………….....………………………….
Sub-heads
of estimate
102
Rate
Rate
Amount
Reference to paragraphs
overleaf explaining
differences (a)
Amount
Quantity
Quantity
Rate
Amount
Quantity
BOOK OF FORMS
1 2 3 4 5 6 7 8 9 10 11
`. P. `. P. `. P. `. P. `. P. `. P.
Total carried
over
FORM 42 - (Concld.)
Sub-heads
of estimate
Rate
Reference to paragraphs
overleaf explaining
differences (a)
Rate
Quantity
Rate
Quantity
Amount
Amount
Amount
Quantity
1 2 3 4 5 6 7 8 9 10 11
`. P. `. P. `. P. `. P. `. P. `. P.
103
BOOK OF FORMS
Total
Dated the
Divisional Officer
* Excess to be entered in red ink; savings in black ink.
(a) If the explanation can be made sufficiently short to be put in this column, it should be done. If not, a reference
letter or number should be given and the explanation with the same reference letter or figure given overleaf.
For petty differences no explanation is required.
FORM 43
COMPLETION STATEMENT OF WORKS AND REPAIRS
(Referred to in para 10.6.11)
Completion statement of works and repairs completed during the month of……………………..the outlay on which
has not been recorded by sub-heads and the actual expenditure on which is in excess of the sanctioned estimate by
the amount greater than that which the Divisional Officer is empowered to pass.
Sanction
Names of works
grouped under major, Amount of Percentage
estimate Expenditure Excess* of excess*
minor and detailed Authority No. Date
heads of classification
Item No.
Remarks
104
1 2 3 4 5 6 7 8 9 10
BOOK OF FORMS
`. P. `. P. `. P.
105
BOOK OF FORMS
FORM
REGISTER OF
(Referred to in paras 9.5.1,
Major Head........................................
Reference Item
to voucher No. Particulars † † † † † † † †
No.
1 2 3 4 5 6 7 8
`. P. `. P. `. P. `. P. `. P. `. P. `. P. `. P.
Amount
brought
forward from ..
last month
Transactions
of the month ..
Total for
the month ..
Total up-to-
date carried
over to the ..
following
month
* To be used only in respect of projects for which Capital and Revenue Accounts are kept.
† These columns are intended for the Minor Heads (and detailed heads, if any) subordinate to the
‡ The form is also used for maintaining the detailed accounts of (1) Refunds of Revenue and (2)
106
BOOK OF FORMS
44
REVENUE REALISED
9.5.3 and 22.4.4)
* Name of system ...............................................
Recoveries of expenditure
Miscella-
† ‡ Establish- Tools and neous
Total
ment Plant Other
recoveries recoveries recoveries
9 10 11 12 13 14 15
`. P. `. P. `. P. `. P. `. P. `. P. `. P.
Deduct
Net
refunds
`. P. `. P.
107
FORM 44A
SCHEDULE OF (I) REVENUE REALISED.
(II) REFUNDS OF REVENUE.
(III) RECEIPTS AND RECOVERIES ON CAPITAL ACCOUNT.
(Referred to in para 22.4.15)
Division…………………….............
Major Head………………………… Name of system………………………
Minor heads (and
detailed heads) Recoveries of expenditure
ment recoveries
Miscellaneous
108
`. P. `. P. `. P. `. P. `. P. `. P. `. P. `. P. `. P.
1. Amount brought
BOOK OF FORMS
Divisional Accountant.
BOOK OF FORMS
FORM 45
STATEMENT OF RENTS RECOVERABLE IN CASH OR BY
DEDUCTION FROM PAY BILLS
(Referred to in paras 9.3.4 to 9.3.7)
Name of Division……………………. Name of Canal, etc……………………..
Major head to be credited…………...........………….
emoluments shown in
other particulars of
Amount recovered
Divisional Officer
Name of building
during 20……..
column 3
20……
1 2 3 4 5 6
`. P. `. P.
109
BOOK OF FORMS
FORM
REGISTER OF RENTS OF
(Referred to in paras 9.3.7,
By whom occupied Standard rent April 20.....
Registered No. of building
*Realisations
Assessments
Authority
Balance
Rate
or land
`. `. P. `. P. `. P. `. P. `. P.
Total ..
Total ..
* The entry made in this column under each month should be made in black ink and underneath
........................ of Form ......................................................
If there be any items of minus realisation rule below paragraph 9.5.6 of the K.P.W.A. Code during
i.e. (1) Gross and (2) Deduct refunds, so as to facilitate the posting of the Register of Refunds of
110
BOOK OF FORMS
46
BUILDINGS AND LANDS
9.3.8, 9.5.3 and 9.5.6)
May 20..... March 20..... Supply
*Realisations
*Realisations
*Realisations
Assessments
Assessments
Assessments
Remarks
Balance
Balance
Balance
`. P. `. P. `. P. `. P. `. P. `. P. `. P. `. P. `. P.
5th May
Divisional Accountant .............................
Divisional Officer ...................................
TOTAL REALISATIONS
Other Rent of Other Rent of Other
Total Total Total
rents buildings rents buildings rents
it be noted, in ink of another colour, amount realised during the year up-to-date; see column
a month, the figures to be entered against, “C”, “A” and “T” should be divided into 2 items each,
Revenue (paragraph 9.5.1 of the K.P.W.A. Code).
111
BOOK OF FORMS
FORM 47
CONSOLIDATED TREASURY RECEIPT
………………………………….Treasury
` in figures…………….
Certified that the amount for which the C.T.R. is furnished agrees with the
amount credited in the Treasury Accounts except for the difference of
`………………which is explained below:
112
FORM 48
SCHEDULE OF MONTHLY SETTLEMENT WITH TREASURIES
(Referred to in para 22.3.3 and 22.3.4.)
Part I
Cash remitted and acknowledged
Treasury
Treasury
Treasury
Treasury
Treasury
Treasury
Treasury
Treasury
Total
Treasury
2 3 4 5 6 7 8 9 10 11
`. P. `. P. `. P. `. P. `. P. `. P. `. P. `. P. `. P. `. P.
1. Difference brought over
113
as per line 5 of last
month’s memo
2. Cash remitted during the
BOOK OF FORMS
Treasury
Treasury
Treasury
Treasury
Treasury
Treasury
Total
Treasury
Treasury
Treasury
2 3 4 5 6 7 8 9 10 11
`. P. `. P. `. P. `. P. `. P. `. P. `. P. `. P. `. P. `. P.
114
not taken in the Divisional
Accounts of the month
BOOK OF FORMS
*(1) Full details by chalan should be furnished either on the back of the Schedule or in the form of a separate
statement attached to the Schedule.
Treasury
Treasury
Treasury
Treasury
Treasury
Total
Treasury
Treasury
Treasury
Treasury
1 2 3 4 5 6 7 8 9 10 11
`. P. `. P. `. P. `. P. `. P. `. P. `. P. `. P. `. P. `. P.
115
previous month’s memo
2. Cheques issued during the
BOOK OF FORMS
3. Total ..
1 2 3 4
`. P. `. P.
Uncashed
cheques
116
Total of uncashed cheques. Deduct
BOOK OF FORMS
Net difference
* The difference relating to each Treasury should be detailed in the manner indicated. Action taken to renew
uncurrent cheques and cheques remaining uncashed for over one year should be specified.
Action taken to rectify differences due to misclassification should also be furnished.
Divisional Officer.
BOOK OF FORMS
FORM 49
CHEQUE
REGISTER OF RECEIPT BOOKS
(Referred to in paras 6.7.1. to 6.7.9.)
Division:
Sub-division:
Division Office
using it
of the books
Cash books
Cash books
1 2 3 4 5 6 7
1. Temporary Receipt Books should also be entered in this register, separate folios
being adopted for them.
2. Column 3 and 4 should be filled in by the Divisional Accountant whenever on
examining a cash book it is noticed that a cheque book or receipt book has
been brought into use for the first time.
3. The prompt submission of the counterfoils of used cheque and receipt books for
check in the Divisional Office should be watched through this register.
117
BOOK OF FORMS
FORM 50
TRANSFER ENTRY ORDER
(Referred to in para 8.1.2. to 8.1.7.)
No…………………… Dated………………20………
Adjusted in the accounts for……………………………..
Vide Transfer Entry book, Item No…………………….
Debits Credits
*Particulars of the
transaction with Name of Name of
reasons for the work or work or
Amount Amount
proposed adjustment head of head of
account account
1 2 3 4 5
`. P. `. P.
118
FORM 51
TRANSFER ENTRY BOOK FOR…………..20……….
(Referred to in para 8.1.6. and 8.1.7.)
Division………………
Sub-division………….
Debits Credits
Dated
Item initials of
Date (1) Particulars of Head of Head of
No. Divisional
each transaction Account (with Amount Account (with Amount
Accountant
name of work) name of work)
1 2 3 4 5 6 7 8
`. P. `. P.
119
BOOK OF FORMS
1. Authority should be quoted in all case, e.g., No. and date of Transfer Entry Order, or of advice and acceptance
of transfer. In cases falling under Note 1 below paragraph 8.1.2 of the K.P.W.A. Code, it will suffice if the
Divisional Officer initials the entry in this column.
2. The total of the debits and credits against each item should agree with one another.
Dated initials of the Divisional Accountant Dated initials of the Divisional Officer.
FORM 54
REGISTER OF TRANSFERS AWAITED
(Referred to in para 5.3.4.)
For the year 20……….
Division………………
Sub-division………….
Reference to adjustment
Particulars
Month in
Amount
which
adjusted
adjusted
Remarks
Probable date of
adjustment
Estimated amount*
Dated initials of
Divisional Accountant
Reference to
correspondence, etc.
Name of work or head
of account
Dated initials of
Divisional Accountant
120
1 2 3 4 5 6 7 8 9 10
BOOK OF FORMS
`. P. `. P.
Amount per
mensem
Reference
to Voucher
Reference to sanction
with period for which
the sanction has been
accorded
Reference to
Voucher (c)
Reference
to Voucher
Name of
appointment
No.
Rate
1 2 3 4 5 6 7 8 9 10 11 12
121
`. P. `. P. `. P.
BOOK OF FORMS
a. Each entry of sanction should be initialled and dated by the Divisional Accountant
b. Name of the month for which wages have been earned.
c. Entries should be made briefly, e.g. voucher 24 for July will be entered as 24 -7.
d. Amount paid should be entered in black ink, and unpaid amounts or fines in red ink, the entries for fine being
distinguished by the letter F. Subsequent payments of unpaid amounts should be entered underneath in black
ink, it being seen that they do not exceed the amounts available as entered in red ink. Claims for arrears not
included in the original claims for the month concerned should ordinarily not be admitted without full explanation
of the circumstances under which they were omitted.
One or more pages should be set apart for each work or account.
FORM 56
REGISTER OF MISCELLANEOUS SANCTIONS
(Referred to in para 22.2.7.)
Note of expenditure
incurred against each
sanction from time to time
No. , date and
authority
Substance of order
Remarks
Month
Amount
No. of voucher
Item No.
Dated initials of
Divisional Accountant
Dated initials of
Divisional Accountant
Amount of sanction
122
1 2 3 4 5 6 7 8 9 10
`. P. `. P.
BOOK OF FORMS
FORM 57
REGISTER OF DIVISIONAL ACCOUNTANT’S OBJECTIONS
(Referred to in para 4.2.7.)
Division: Sub-division:
Item No.
`. P.
123
BOOK OF FORMS
Notes. - 1. Objections relating to transactions and orders of subordinate officers which are within the powers of the
Divisional Officer to sanction or to confirm should not be entered in this register.
2. This register will remain in the personal custody of the Divisional Accountant except when submitted
to the Divisional Officer.
3. In the month of April each year an extract from this register should be submitted to the Finance
Department of Government for review and orders and the objections entered in this register should
not be considered to have been settled till orders of the Finance Department are received and
entered in the last column of the register.
BOOK OF FORMS
FORM 58
SCHEDULE DOCKET
(Referred to in para 22.4.2)
No………………………….. Month…….…….…....…….
Division………………..........……* Name of work or schedule…………............………
**Classification of charges……………….......................…………………………..........
cash voucher
cash voucher
Number of
Number of
Remarks
Remarks
Remarks
Amount
Amount
Amount
Particulars
`. P. `. P. Brought forward . . `. P.
Cash charges for which vouchers
are not required in audit ..
Stock ..
Transfer entry debits -
T.E. No. ..
T.E. No. ..
T.E. No. ..
Total ..
Deduct Refunds ..
‡Cash receipts -
§Transfer entry credits -
T.E. No. ..
T.E. No. ..
T.E. No. ..
Total refunds ..
Total
carried
forward
Net charges of the month ..
Divisional Accountant.
NOTE
*Full name of work as given in the estimate should be entered here in the case
of each work included in a Schedule of Works Expenditure, Form 60 or in the
124
BOOK OF FORMS
Schedule of Deposits Works or Debits to Stock, Form 61,62 and 67. In all other
cases, the name of the schedule should be given.
**Only such particulars need be entered as are necessary to avoid errors in the
posting of charges in Schedule Dockets.
†In the case of Transfer Entry Debits the supporting vouchers if exceeding
` 100 each should also be attached, their particulars being quoted below each
entry and the amount of petty vouchers being specified in the column for
remarks. In these cases reference to the Schedule Docket or Schedule in which
the corresponding credit appears should also be given in the same column.
125
BOOK OF FORMS
FORM 59
SCHEDULE DOCKET FOR PERCENTAGE RECOVERIES
(Referred to in para 22.4.3)
Month…………20……….
Percentage Recoveries
* Name of work (i.e. full name
as given in the estimate)
Works expenditure
Tools Accounts
Establish- and Total Remarks
and audit
ment Plant
Item No.
`. P. `. P. `. P. `. P.
Total
126
FORM 60
SCHEDULE OF WORK EXPENDITURE
(Referred to in para 22.4.2., 22.4.6. and 22.4.15.)
Division………………
Major Head, Remittance or other Account……………………………Name of month………..……………….20………
Remarks regarding action taken to
Name of works (i.e. Full
regularise the excess, and the
name as given in the
approximate amounts of liabilities in
estimate).
the accounts of works for which
Schedule N . B . – A d m i n i s t r a t i v e
Progressive
technical estimates are not yet
Docket No approval and financial
sanctioned. If this work is completed,
Sanctioned
Estimate
Allotment
sanction may be noted in
please indicate date of completion and
the red ink, when a work is
the month in which the expenditure
Total charges of
the year
Total charges of
the month
Serial No.
Excess Excess
Total
expenditure (Month in
which expenditure last
appeared)
last appeared.
1 2 3 4 5 6 7 8 9 10
`. P. `. P. `. P. `. P. `. P.
127
Notes. – 1. Normally only those works should be included on which expenditure has been incurred during the month, in the schedule
accompanying the Monthly Accounts for September and March (Supplementary), however all the works (including those
BOOK OF FORMS
relating to works where there are no fresh transactions during the months) should be included. The Schedule for
September and March (Supplementary) should continue to include even completed work so long as there is any want of
excess over allotments, sanctioned estimates, administrative approval or financial sanction which has yet to be regularized.
2. In respect of minor works and repairs/maintenance works for which there is a lump allotment, column 8 may be filled
in only in the comprehensive schedule accompanying the Monthly Accounts for September and March (Supplementary).
3. In columns 8 and 9 the reference to the communication intimating the amount of allotment/sanctioned estimate should
also be quoted in the first month in which the expenditure appears of a revised sanction is issued.
4. The works relating to a Particular Project should be included at one place with the name of the Project as the heading. The
individual works should also be grouped under the various sanctioned appendices of the project indicating at the beginning
under a separate caption the number and the name of the sanctioned appendix.
5. The Schedules for the months of June, September, December and March should include all works relating to National
Highways and Central Road Fund executed by the Division, irrespective of whether any expenditure has been incurred
during the particular month or not.
Divisional Accountant.
FORM 61
SCHEDULE OF DEPOSIT WORK
(Referred to in paras 16.2.2., 16.2.4., 22.4.4. and 22.4.6.)
PART I
Account of deposit works affected during the month of ………………….20……….
Division………………
Expenditure, if any
Deposits Expenditure charged to miscella-
neous P.W. Advances
128
Detailed classification
of estimate
Total charge of
the month
Remarks (If the work is
completed say so)
Serial No.
To end of
previous month
Schedule docket number
During the
month
Total up-to-date
Up-to-date
Total up-to-date
1 2 3 4 5 6 7 8 9 10 11 12
`. P. `. P. `. P. `. P. `. P. `. P. `. P.
Net charge-
able during
the month to
P.W. Deposits
Total for A*
accounts **C *D(B-C)
affected by
the months
transactions
B
Add total for
accounts not
affected by
the month’s F
transactions, G
as per Part II
Grand Total K Deduct ‘up-
H=(F-G) ‡ L(=K-H)
to-date’ total
of accounts
129
†E
closing during
the month as
per items….
BOOK OF FORMS
Net up-to-
date total of
accounts
remaining
open at the
J close of the
month
Col. 3 - When a work is included for the first time in the schedule, the sanction should be entered in red ink in this column.
*The amount as per entries as per A and D should be entered in column 5 and 8, i.e. “Credits during month” and “Debits during month”
of the Schedule of Deposits.
**The amount as per entry C should, by a transfer entry be charged in lump sum to Miscellaneous P.W. Advances.
†The amount as per entry E should agree with entry of last month’s schedule.
‡ The amount as per entry L should agree with the closing balance of Deposits for work to be done as per column 8 of the Schedule
of Deposits.
FORM 61-(Contd.)
PART II
Account of deposit works not affected during the month
Serial Number
Advances
1 2 3 4 5 6 7
130
`. P. `. P. `. P.
BOOK OF FORMS
Total transferred
to Part I
Divisional Accountant.
* FORM 61- A
(See Art. 230, Note 1, Kerala Account Code, Volume III and Note 1 under para 22.4.15.,
Kerala Public Works Account Code)
Statement showing the expenditure incurred by the Public Works Department
to the end of ……………………….20…… on Deposit Works
Expenditure in excess
Name of Amount of Amount Expenditure Expenditure Unspent
of deposit debited to
work estimate of deposit during……… to the end balance at
the end Miscellaneous public
of……..
Sl.No.
Remarks
`. P. `. P. `. P. `. P. `. P.
131
BOOK OF FORMS
Item No.
necessary) the year
132
Credits Debits necessary)
1 2 3 4 5 6 7 8 9
BOOK OF FORMS
`. P. `. P. `. P. `. P.
Total ..
Col 2.— To be indicated thus: — 12 for December 1967, 1 for January 1968 and so on.
67 68
Col 5.— Score out “Credits” in the case of Miscellaneous P.W. Advances and Stock, and “Debits” in the case of purchases and
P.W. Deposits.
Col 6.— Score out “Debits” in the case of Miscellaneous P.W. Advances and Stock, and “Credits” in the case of purchases and
P.W. Deposits.
Col 9.— To be indicated thus: — “A” Paid in cash/or recovered in cash, “B” Adjusted by transfer entry, “C” Converted into
interest-bearing security, and so on, additional letters being entered with explanation at foot.
133
1
dates
3
Authority
Reference to month in which the item
4
Opening balance
7
9
Credits during the month
`. P. `. P. `. P. `. P.
FORM 65
Closing balance
10
`. P.
(Columns 8-9)
(Referred to in para 22.4.15.. and 22.4.16.)
III. Losses,
11
errors, etc.
II. Expenditure
retrenchments,
How *adjusted
SCHEDULE OF MISCELLANEOUS PUBLIC WORKS ADVANCES
deposit received
works in excess of
incurred on deposit
Remarks with explanation as to step taken
to effect adjustment of outstanding items
(in respect of credits during the month
12
here enter reference to schedule docket in
which the corresponding debit appears or
if it was a cash receipt say so)
*Column ‘A’ received in cash ‘B’ adjusted by book transfer, the letter ‘A’ and ‘B’ should be entered in this column.
BOOK OF FORMS
FORM 65-(Concld.)
*PART II
Abstract Account of Debits, Credits and Balances
Class of miscellaneous Opening Debits during Total Credits during Closing balance
P.W. advances balance the month (Columns 2+3) the month (Column 4-5)
1 2 3 4 5 6
`. P. `. P. `. P. `. P. `. P.
I. Sales on Credit ..
II. Expenditure incurred
on deposit works in
134
excess of deposit
received ..
BOOK OF FORMS
Total ..
*Part II should give the figure covering both affected and unaffected items.
Divisional Accountant.
BOOK OF FORMS
FORM 67
SCHEDULE OF DEBITS TO STOCK
(Referred to in paras 22.4.2. and 22.4.8.)
Month …………………………………………20……….
Total transactions
Schedule docket
Total up-to-date
expenditure (as given in the estimate)
of the month
N.B. – Sanction to be noted in red ink
Item No.
1 2 3 4 5 6
Manufacture of ………………......…..(1) `. P. `. P.
Operation……………………….…..
Out-turn……………………..……...
Manufacture of …………………..…...
Operation……………………...……
Out-turn……………………..……...
Total Manufacture
Operation (b) ...... .....
Total Manufacture
Out-turn (a) ...... .....
Land, Kilns, etc. (2)
Total Land, Kilns, etc. ..
Other sub-heads (3)
Total of other sub-heads
**Advance Payment (4)
(i) Payments
(ii) Advance adjusted
Total (1+2+3+4) ..
Purchases (5)
Total Purchases ..
** Carriage and Storage (6)
Total carriage and storage
Grand Total ..
Divisional Accountant.
135
BOOK OF FORMS
*Only those works or items should be entered on which there has been any
transaction during the month, and the “operation” and “out-turn”
transactions of each manufacture should be shown in two separate lines. In
March, all items under the groups “Manufacture” and “Land, Kilns, etc.”
the account of which are still open, should invariably be shown.
Under (1) should be detailed all manufacture operation in progress; under (2)
all works in progress in connection with the acquisition, construction and
repairs to Land, Kilns etc. ; under (3) should be shown (i) individually all
items of expenditure on the carriage handling, etc. , of stock materials when
the cost of such processes is chargeable to the Sub-head of stock under
which the materials are classified (vide paragraphs 10.8.1 and 22.4.8 of the
K.P.W.A. Code), (ii) individually all items of acquisition of stock materials,
for which an estimate is required under rule , and (iii) collectively all items of
acquisition of stock materials under (4) should be shown all **advance
payments **[and subsequent adjustment of such advances – vide para 13.2.5.
(e) under (5) should be shown all payments for stock] made during the month
**[by operation of the sub-head “purchase”] but see sub para 2 of para
13.2.5 c (i) **and under(6) will be shown collectively all transactions under
the sub-head “Carriage” and Storage”.)
(b) This should agree with the amount shown against the Sub-head
‘Manufacture” in Part II of the Stock Account, Form 68.
**Substitution. G.O. (P) 522/80/Fin. dated 22nd August, 1980 and G.O. (P) 693/85/Fin.
dated 2nd November, 1985.
136
BOOK OF FORMS
FORM 68
Division……………………………………
Month………………………………………
STOCK ACCOUNT
137
FORM 68- (Contd.)
STOCK ACCOUNT
(Referred to in para 22.4.9)
Part I
Classified account of receipts, issues, and balances
Sanctioned
reserves
Item No.
`. P. `. P. `. P. `. P. `. P.
1 Manufacture ..
2 Land and Kilns, etc. ..
138
3 Other sub-heads ..
4 **Advance Payment ..
BOOK OF FORMS
(Payments)
5 **Purchases ..
6 ** Storage ..
7 Total ..
*Certified that entries in lines 1, 2 etc., of this account agree with the corresponding entries in the Suspense
Register (Stock).
**Substitution. G.O. (P) 522/80/Fin. dated 22nd August, 1980.
Divisional Accountant.
FORM 68- (Contd.)
Part II
Detailed accounts of issues
Reference to
Amount Amount Amount Particulars Amount
Schedule etc*
Schedule
Docket No.
Schedule
Docket No.
Schedule
Docket No.
`. P. `. P. `. P. `. P.
Manufacture ..
Credits for out-turn .. Form
Land kilns, etc. .. S.D. No
T.E. No………………………....
T.E No………………………….
Total ..
Other sub-heads ..
139
(+) purchases ..
Issues to woks, etc. .. Previous
Column
Cash credits to stock ..
BOOK OF FORMS
FORM 69
CLASSIFIED ABSTRACT OF EXPENDITURE
(Referred to in para 22.4.11)
Month ……………….20…………
`. P. `. P.
*When a minor head of account is split up into two or more primary units, the figures
for each of these should be entered in the inner column. The minor head “Suspense”
should be detailed to exhibit the total of the debits, the total of the credits and the net
debit. Refunds of revenue will not appear in the abstract of expenditure but receipts
and recoveries on capital account should be shown as deduction.
140
FORM 71
SCHEDULE OF DEBITS TO MISCELLANEOUS HEADS OFACCOUNT
CREDITS
(Referred to in paras 16.3.2, 22.4.4 and 22.4.5)
Month …………..........…….20………
1 2 3 4 5 6
`. P.
141
BOOK OF FORMS
Total ..
The use of this schedule should be restricted to those transactions which are classifiable under the heads specified
in paragraph 21.4.4 (e) of the Kerala Public Works Account Code, Col. 6—In the Schedule of credits, items representing
cash receipts should be so described in this column; and against all other items should be given a reference to the
schedule docket wherein the corresponding debit appears.
Divisional Accountant.
FORM 71-A
SCHEDULE OF TRANSACTIONS ADJUSTED UNDER THE HEAD “CASH
SETTLEMENT SUSPENSE ACCOUNT”
(Referred to in paras 22.4.10 and 22.4.15)
Division……………………….. Month……………………
Item No.
Remarks
1 2 3 4 5 6 7 8 9
142
`. P. `. P. `. P. `. P. `. P.
BOOK OF FORMS
Certified that the claims have been sent to the Divisions concerned.
Divisional Accountant.
…..…………….Division.
*FORM 71-B
MISCELLANEOUS RETURNS
(Referred to in paras 22.4.16 and 22.4.24)
Office of the Executive Engineer, Position for the half-year ending
Division, 30-9-20………….
31-3-20………….
No. of items and
amount involved in Action taken by the originating division
Break up of Column 3 to secure settlement. This should
Name of respect of items over 6
Sl. indicate the latest position in respect
responding months
No. of each item remaining outstanding
division
No. of Amount Month to Amount containing the brief particulars of
which objections/correspondence.
Remarks
143
item
`. P. relates `. P.
BOOK OF FORMS
* Particulars
Nature of
objection
quoting
reference to the
advice thereof
sent separately
Item No.
144
†Whether an Original (O) or a
Responding (R) item
No. and date of
authority or
acceptance of
transfer (if any)
Amount brought to account
Details of cheque
Designation of the Name of the
Serial Remarks
Officer making the District
No.
cheque Treasury No. Date Amount
1 2 3 4 5 6 7
`. P.
145
BOOK OF FORMS
Divisional Accountant.
BOOK OF FORMS
FORM 72-B
LIST OF REMITTANCES
(Referred to in para 22.4.15)
Name of Division……………………. Month of Account……………..
Part I
Remittances made during the month
Particulars of
Serial No.
Remarks
Designation of Name of
Amount
chalan
remitter treasury
No. Date
1 2 3 4 5 6 7
`. P.
Total ..
Part II
Remittances brought to account in previous months
Particulars
Serial No.
Month in which
Name of of chalan
brought to account Amount
treasury
and item No. No. Date
1 2 3 4 5 6
`. P.
Note . - (1) The total of Part I should tally with the total of the Schedule of Debits to
Remittances (Form 72).
(2) When remittances are made by cheque/bank draft the particulars of
cheque/bank draft should be indicated in Col.7 of Part I.
(3) Particulars of chalan, viz., number and date which were not given in
Part I during the previous month should be entered in Part II.
Divisional Accountant.
146
BOOK OF FORMS
FORM 73
SCHEDULE OF DEBITS/CREDITS TO “ADJUSTING ACCOUNT BETWEEN
CENTRAL AND STATE GOVERNMENTS”/ “ADJUSTING ACCOUNT
WITH RAILWAYS”, “ADJUSTING ACCOUNT WITH P &T”,
“ADJUSTING ACCOUNT WITH DEFENCE”,“INTER-STATE
SUSPENSE ACCOUNT”
(Referred to in paras 22.4.4 and 22.4.5)
Month ……………….20..…………
*Name of
Government/ Particulars Reference to
Item
† Remarks
Railway/P&T/ of debit/ authority or Amount
No. Defence Accounts credit No. and date of
Officer acceptances
1 2 3 4 5 6
`. P.
Divisional Accountant.
*The entries should be grouped by each Government or Railway, P&T or Defence
Accounts Officer as the case may be.
Items should be grouped in two classes, A- Items to be finally accounted for in
the Accounts Office (to whom the accounts are rendered) and B- Items to be
passed on to other accounts offices.
† In the schedule of credits items representing cash receipts should be so described
in this column and against all other items should be given a reference to the
schedule docket in which the corresponding debit appears.
147
BOOK OF FORMS
FORM 75
SCHEDULE OF DEPOSITS
(Referred to in paras 15.5.2)
Division……………………. Month …….…20…..
Part I
Abstract account of receipts, adjustments and
balances of deposits
1 2 3 4 5 6
`. P. `. P. `. P. `. P. `. P.
I. Cash deposits of
subordinates as
security*
II. Cash deposits of
contractors as
security
III. Deposits for work
to be done
IV. Sums due to
contractors on
closed accounts
V. Sums due to other
Governments on
Closed accounts
VI. Miscellaneous
deposits
Total ..
148
Part II
Detailed extract from Deposit Register, Form 62
Remarks (In respect of
each credits during the
month, here enter
reference to schedule
docket in which the
corresponding debit
appears, or if it was a
† Closing balance
(7-8)
**Particulars of items
(to be grouped by
classes of deposits)
with name of work in
the case of contractor
†Opening
balance
**Reference to month in
which the item was last
affected
1 2 3 4 5 6 7 8 9 10 11
`. P. `. P. `. P. `. P. `. P. `. P.
149
Certified that, with the exceptions noted below, all the interests bearing securities as per items…………………….or their
BOOK OF FORMS
acknowledgements by the authorised custodians, have been received and lodged in a chest in the custody of the Divisional Officer,
and similar securities as per items…………have been certified as received and kept in custody by the Sub-divisional Officers
concerned.
Exceptions (with reasons) Divisional Accountant.
*Column 2. – To be indicated thus—”New” for items appearing for the first time “12/67 for December, 1967” 1/68 for January
1968 and so on.
**Column 3. – No entry need be made in column 3 in the first month of the half year, nor in the second to sixth months in the case
of items which were not affected by any transactions in the previous month or months of the half year.
† Columns 5 to 9 should be totalled separately for each class of deposits in September and March. In other months columns 5, 7 and
9 should not be totalled, but columns 6 and 8 should be totalled separately for each class.
‡Column 10. – “A” repaid in cash, “B” adjusted by transfer entry, “C” converted into an interest-bearing security and entered in the
Register of Securities. The letters A, B, C, etc., should be entered in the column “How adjusted”. If necessary
additional letters D, E, etc., should be entered with explanation at foot.
FORM 76
MONTHLYACCOUNT
(Referred to in paras 22.4.12 and 22.4.13)
Name of Division……………………. Month of ……………20…….State/Central…………….
Receipt Disbursement
Name of Major Heads, Heads of Account, etc. Schedule
(CR) (DR)
Item No.
1 2 3 4 5
Revenue `. P. `. P.
1 XXXIV - Irrigation, Navigation, Embankment
150
and Drainage works (Commercial) .. K.P.W. 44A
2 XXXV - Irrigation, Navigation, Embankment
and Drainage works (Non-Commercial) ..
BOOK OF FORMS
,,
3 XXXVII - Public Works .. ,,
Expenditure
4 .. .. ..
5 43 - Irrigation, Navigation, Embankment and
Drainage works (Commercial) ..
K.P.W. 69
6 44 - Irrigation, Navigation, Embankment and
Drainage works (Non-Commercial) .. ,,
FORM 76 - (Contd.)
Receipt Disbursement
Name of Major Heads, Heads of Account, etc. Schedule (DR)
(CR)
Item No.
1 2 3 4 5
7 50 - Public Works .. `. P. `. P.
K.P.W. 69
8 52 - Capital Outlay on Public Works within
the Revenue Account .. ,,
9 64 - Famine Relief Works .. ,,
10 95 - Capital Outlay on Schemes of Agricultural
151
Improvement and Research .. ,,
11 99 - Capital Outlay on Irrigation, Navigation,
Embankment and Drainage Works (Commercial) .. ,,
BOOK OF FORMS
Receipt Disbursement
Name of Major Heads, Heads of Account, etc. Schedule (DR)
(CR)
Item No.
1 2 3 4 5
`. P. `. P.
Part II - Contingency Fund
.. .. K.P.W. 69
19
.. .. ,,
20
.. .. ,,
21
.. .. ,,
152
22
Other Heads of Accounts
23 Miscellaneous - Heads of Account .. K.P.W. 71
BOOK OF FORMS
Receipt Disbursement
Name of Major Heads, Heads of Account, etc. Schedule
(CR) (DR)
Item No.
1 2 3 4 5
`. P. `. P.
30 Transfers between P.W. Officers .. K.P.W. 72
31 Adjusting Account between Central and State ..
K.P.W. 73
Governments
32 Do. with P. & T. (Name…..........…..) .. ,,
33 Do. with Railway (Name……...…..) .. ,,
34 Do. with Defence (Name……..…..) .. ,,
153
35 Inter-state Suspense Account (Name………..) .. ,,
Diminished (CR)
Cash balance* Increased (DR)
BOOK OF FORMS
Total ..
Opening Balance……………………….......................…………
*Closing Balance………………......................…………………
†Difference
*If the closing cash balance is less than the opening balance the difference will appear in the receipt column; but if
the balance has increased during the month, the difference will fall in the disbursement column.
†The total of the columns for Receipts and Disbursement must agree and if there is any difference due to cash being
in transit between two disbursing officers its amount should be included in the closing balance and the certificate
of Cash Balance should be amplified so as to state the amount and the steps taken to adjust it.
FORM 76 - (Contd.)
MEMO OF MISCELLANEOUS CASH RECEIPTS PAID INTO TREASURIES
`. P.
Balance from last account ..
Total ..
154
Paid into treasuries ..
BOOK OF FORMS
`. P.
………………Treasury-vide Form 48 ..
……………….Do. do. ..
……………….Do. do. ..
155
`. P.
BOOK OF FORMS
1. The standard form is only a model. The number of vertical columns may be
varied according to requirements, the examples given being those suitable
for an ordinary division of the Civil Works Branch.
2. This book need only be written up ordinarily when the monthly account does
not balance and discrepancy cannot be detected readily. If however, the
Divisional Accountant considers it desirable he may maintain this book
regularly to facilitate the check of the complied accounts.
3. The book should be posted from the several Cash Books in respect of cash
transactions, from the Transfer Entry Book in respect of transfer entries and
from the summary of Stock Receipts and Indents in respect of stock
transactions.
4. The amount of cash cheque entered in cash book should be shown on the
charges side under the head to which the payment relates, and the total
amount of cheques drawn should be shown as a single entry on the receipts
side in the column for “Public Works Cheques”, or “III Other Remittances”,
according as the treasuries on which the cheques are drawn are within or
outside the account circle in which the division itself is.
5. In posting the stock transactions from the summary of Stock Receipts and
indents, debits and (credits) to stock which represent credits (and debits)
posted in the Abstracts from the Cash Book and the Transfer Entry Book,
and which are separately shown in the Abstracts - vide paragraph 7.2.28 of
the K.P.W.A. Code - should be excluded, as theses are posted in the Abstract
Book direct from the Cash Books and the Transfer Entry Book. In the Vertical
columns, headed “stock”, should be entered, on the receipts side, the total
of the stock issues corrected as above.
6. As the posting from each cash book or other document are completed it
should be seen that the total postings on the receipt side and that further,
156
BOOK OF FORMS
the totals of the columns headed “Cash from Treasury”, agree in respect of
cash book, and those of the columns, headed “Transfer within Division”, in
respect of the whole division, separately for Cash and Stock unless any
Cash or Stock be in transit - See paragraphs 12.2.5 and 21.4.12 of the K.P.W.A.
Code.
9. Finally, it should be seen that the totals of the vertical column agree with the
totals of the relevant schedules, registers etc., or of the corresponding figures
therein. Difference should be traced and set right.
157
FORM 77
ABSTRACT BOOK
(Referred to in para 22.4.1)
Receipts………………………. Month…………….……20……….
Suspense accounts
XXXVII
Sub-divisions, etc. Miscellaneous
Public Works
Stock P.W. advances
1 2 3 4
Cash
Divisional Officer ..
Total ..
A Sub-division ..
Total ..
158
B Sub-division ..
Total ..
C Sub-division ..
BOOK OF FORMS
Total ..
Transfer entries
Total ..
Stock
Total ..
Total cash, transfer entries and stock ..
Deduct - Refunds of revenue transferred from ..
charges side
Net
Reference to Schedule, Register, etc., Form No ..
FORM 77 - (Contd.)
Receipts………………………. Month…………….……20……….
Establishment Cash
Tools and Miscellaneous
deduct settlement Public works
Sub-division, etc. plant deduct heads of
percentage suspense deposits
recoveries account
recoveries account
1 2 3 4 5 6
Cash `. P. `. P. `. P. `. P. `. P.
Divisional Officer ..
Total ..
A Sub-division ..
Total ..
159
B Sub-division ..
Total ..
C Sub-division ..
BOOK OF FORMS
Total
Transfer entries
Total ..
Stock
Total ..
Total cash, transfer entries and stock ..
Deduct - Refunds of revenue ..
transferred from charges side
Net
Reference to Schedule, Register, etc.,
Form No ..
FORM 77 - (Contd.)
Receipts………………………. Month…………….……20……….
U. Remittances
Adjusting Adjusting
Adjusting
accounts Adjusting accounts P.W.
account Interstate
between Central accounts with with Post remittances
Sub-divisions, etc. with Suspense Account
and State Railways and
Defence
Governments Telegraph
160
A Sub-division ..
Total ..
B Sub-division ..
Total ..
BOOK OF FORMS
C Sub-division ..
Total ..
Transfer entries
Total ..
Stock
Total ..
Total cash, transfer entries and . .
stock
Deduct-Refunds of revenue ..
transferred from charges side
Net ..
Reference to Schedule,Register,
etc.,Form No ..
FORM 77 -(Contd.)
Receipts………………………. Month…………….……20….…….
1 2 3 4 5 6 7 8
Cash `. P. `. P. `. P. `. P. `. P. `. P. `. P.
Divisional Officer ..
Total ..
A Sub-division ..
Total ..
B Sub-division ..
161
Total ..
C Sub-division ..
Total ..
BOOK OF FORMS
Transfer entries
Total .. No entries
Stock
Total ..
Total cash, transfer entries and . .
stock
Deduct-Refunds of revenue ..
transferred from charges side
Net ..
Reference to Schedule,Register, Transferred to charges side
etc.,Form No ..
FORM 77 -(Contd.)
Receipts………………………. Month…………….…20………….
1 2 3 4 5
Cash `. P. `. P. `. P. `. P.
Divisional Officer ..
Total ..
A Sub-division ..
Total ..
B Sub-division ..
162
Total ..
C Sub-division ..
Total ..
BOOK OF FORMS
163
B Sub-division ..
Total ..
C Sub-division ..
BOOK OF FORMS
Total ..
Transfer entries
Total ..
Stock
Total ..
Total cash, transfer entries and stock ..
Deduct - Refunds transferred ..
from receipts side
Net
Reference to Schedule, etc.,
Form No ..
FORM 77 - (Contd.)
Charges……………..
50 - Public Works - (Contd)
Cash
Miscellaneous Public
Sub-divisions, etc. Suspense accounts settlement
heads of works
Miscellaneous suspense
Stock account deposits
P.W. Adv. account
1 2 3 4 5 6
Cash `. P. `. P. `. P. `. P. `. P.
Divisional Office ..
Total ..
A Sub-division ..
Total ..
164
B Sub-division ..
Total ..
C Sub-division ..
BOOK OF FORMS
Total ..
Transfer entries
Total ..
Stock
Total ..
Total cash, transfer entries and stock ..
Deduct refunds transferred from ..
receipt side
Net . . No entries
Reference to Schedule, etc.,
Form No ..
FORM 77 - (Contd.)
Charges……………..
U. Remittances
Adjusting accounts Adjusting accounts
Adjusting accounts
between Central and
with Railways with P. and T.
Sub-divisions, etc. State Governments
Railway
Government
of …………
1 2 3 4
Cash
`. P. `. P. `. P.
165
Divisional Office ..
Total ..
A Sub-division ..
BOOK OF FORMS
Total ..
B Sub-division ..
Total ..
C Sub-division ..
Total ..
Transfer entries
Total ..
Stock
Total ..
Total cash, transfer entries and stock ..
Deduct refunds transferred from receipts side ..
Net ..
Reference to Schedule, etc.,Form No ..
FORM 77 - (Contd.)
Charges……………..
Remittances - (Contd.) P.W. Remittances Refunds of
Revenue to be
Adjusting Inter-state transferred to
Sub-divisions, etc. suspense account P.W. Other receipts side
account with
Cheques Remittances XXXVII
defence State of…...….. Public Works
1 2 3 4 5 6
Cash `. P. `. P. `. P. `. P. `. P.
Divisional Office ..
Total ..
A Sub-division ..
Total ..
166
B Sub-division ..
Total ..
C Sub-division ..
BOOK OF FORMS
Total ..
Transfer entries
Total ..
Stock
Total .. No entries
Total cash, transfer entries and stock ..
Deduct refunds transferred from ..
receipts side
Net ..
No entries
Reference to Schedule, etc., Transferred to
Form No .. receipts side
FORM 77 - (Concld.)
Charges……………..
Cash
Divisional Officer ..
Total ..
A Sub-division ..
Total ..
B Sub-division ..
Total ..
C Sub-division ..
Total .. ` Total of last three columns
167
Transfer entries
Total transfer entries
Total ..
Stock
BOOK OF FORMS
Total
Total ..
Total cash, transfer entries and stock ..
Total transfers within Division-stock
Deduct refunds transferred from receipts side . .
Net ..
Reference to Schedule, etc., Form No ..
Totals agreed with the corresponding figures in relevant Schedules, Registers, etc.
Date………………………. Divisional Accountant.
BOOK OF FORMS
FORM 78
EXTRACT FROM CONTRACTORS’ LEDGER
[Referred to in para 10.7.8 (c)]
Part I
Accounts affected by the month’s transactions
(Same as Form 41)
Part II
Accounts not affected by the month’s transactions
Remarks*
account last Debits (i.e. Credits,
No contractors
appeared in dues from (i.e. due to
Part I contractor) contractor)
1 2 3 4 5 6
`. P. `. P.
*If any individual dues from a contractor under the heads “Other Transactions/
Advance Payments” have been outstanding for more than 3 months the number and
date of the last running account bill or other voucher relating to it should be quoted
in the column for “Remarks” with an explanation of the delay in its adjustment.
Divisional Accountant.
168
BOOK OF FORMS
FORM 79
LIST OF ACCOUNTS SUBMITTED TO
ACCOUNTANT GENERAL
(Referred to in paras 22.4.15 and 22.4.18)
Division………………..
Month……………20.....
*Form No. of
† Name of document docu- Remarks
No.
ment
K.P.W. 76 Monthly Account ..
,, 44A Revenue realised/
Refunds of revenue/
Schedule of Receipts and recoveries
on capital account ..
,, 69 Classified Abstract of Expenditure ..
,, 60 Schedules of Works Expenditure ..
,, 58 Schedule Docket (with necessary
vouchers , Transfer Entry Orders,
Survey Reports and Sale Accounts
attached to each) ..
,, 59 Schedule Docket of Percentage
Recoveries ..
,, 68 Stock Account (with Sale Accounts,
Form K.P.W. 18) ..
,, 67 Schedule of Debits to stock ..
,, 65 Schedule of Miscellaneous P.W.
Advances ..
(Local) Schedule of Workshop Suspense ..
,, 71 Schedule of Credits to Miscellaneous
Heads of Account ..
,, 71 Schedule of Debits to Miscellaneous
Heads of Account ..
,, 71A Schedule of transactions adjusted
under the head “Cash Settlement
suspense Account” ..
,, 72A List of cheques drawn ..
,, 72B List of Remittance Transactions ..
169
BOOK OF FORMS
FORM 79 - (Contd.)
No. of
*Form docu- Remarks
Name of document
No. ment
K.P.W. 73 Schedule of Credits to Adjusting Account
between Central and
State Governments ..
” 73 Schedule of Debits to Adjusting Account
between Central and
State Governments ..
,, 73 Schedule of Credits to Adjusting Account
with Railways ..
,, 73 Schedule of Debits to Adjusting Account
with Railways ..
,, 73 Schedule of Credits to Adjusting Account
with P. & T. ..
,, 73 Schedule of Debits to Adjusting Account
with P. & T. ..
,, 73 Schedule of Credits to Adjusting Account
with Defence ..
,, 73 Schedule of Debits to Adjusting Account
with Defence ..
,, 73 Schedule of Debits to Inter-state Suspense
Account ..
,, 73 Schedule of Credits to Inter-state Suspense
Account ..
,, 72 Schedule of Credits to Remittances ..
,, 75 Schedule of Debits to Remittances ..
,, 48 Schedule of Deposits ..
,, 61 Schedule of Settlement with Treasuries (with
Treasury Officer’s certificate of issue and
Consolidated Treasury Receipts Form
K.P.W. 47) ..
,, 12 Schedule of Deposit Works (with Reports of
progress of expenditure) ..
Copies of Tools and Plant Received Sheets in
respect of Special Tools and Plant ..
170
BOOK OF FORMS
FORM 79 - (Concld.)
No. of
*Form
Name of document docu- Remarks
No.
ment
K.P.W. 13 Copies of Tools and Plant indents in respect of
Special Tools and Plant with the supporting
survey reports of stores, Form 17, Sale Accounts,
Form 18 and acknowledgements of articles
transferred to other divisions including divisions
of other Governments ..
*Strike out the Form numbers of any document not forwarded, the submission
of which is unnecessary. If any document required to be submitted is not
ready, a suitable note should be recorded against it in the column for “Remarks”
and the probable date of its submission should be stated.
† Including those in support of the Schedules of Remittances and
Miscellaneous Heads of Account and Adjusting Account between Central
and State Governments.
The vouchers enumerated below do not accompany for the reason stated
against each: -
Reference to Voucher Probable date
Reason for
Schedule Amount
No. non-submission of submission
Docket
1 2 3 4 5
`. P.
Divisional Accountant.
Forwarded to the Accountant General
Divisional Officer.
Station……………………
Dated the…………20..…
171
BOOK OF FORMS
FORM 80
DIVISIONAL OFFICER’S REPORT OF SCRUTINY
OF ACCOUNTS
(Referred to in para 22.4.18)
Month………………………20………….
After due examination of the office copies of the Monthly Account, and
supporting documents, for the month ………………20……… which were
despatched under the signature of the Divisional Accountant during my
absence from headquarters, I accept responsibility for the same.
2. I have initialled the office copies of the Monthly Account and the list of
accounts (Form) and a duplicate copy of the Monthly Account signed by
me is attached to this report.
3. I have issued instructions for the adjustment, in the next month’s account
of the errors and omissions detailed below, which my scrutiny of the accounts
has disclosed: -
Divisional Officer.
No……………………
Dated………………..
………………………Division
Enclosure: Monthly Accountant
To
The Accountant General
………………………….
………………………….
172
FORM 81
REGISTER OF INTEREST-BEARING SECURITIES
(Referred to in para 15.6.1)
173
BOOK OF FORMS
Amount*
Item No.
Dated initials of the Divisional Accountant and
of the Divisional Officer verifying Cols. 1 to 11
Number
Loan (or date of issue in the
case of cash certificates)
Number of Account Receipt
*If the Post Office Savings Bank Pass Book pertains to a security deposit recovered in instalments, no entry should be made in this
column until the security has been fully paid up. But if such security deposit is to be refunded before the full amount is recovered it
should be treated as fully paid up and brought on the register before being refunded. In all cases only the original deposit should be
entered here and not the interest.
174
Number
16
Finance
Date
Department
17
of Treasury or
Acknowledgement
Number
security
transfer of the
the return of re-
Date
Orders sanctioning
21
22
Number
23
Date
the security if
FORM 81 - (Concld.)
Letter recalling
Number
24
Finance
Department
Treasury or
Date
25
received back
out of the office letter with which
26
of the depositor
Dated initials of the Divisional Accountant and of the
27
Divisional Officer verifying Cols. 19 to 20
28
Remarks
BOOK OF FORMS
BOOK OF FORMS
*FORM 82
*Deletion G.O.P. No. 766/85/Fin. dated 28-11-1985.
FORM 83
ANNUAL CERTIFICATES OF BALANCES
(Referred to in para 22.4.20)
For the year ended 31st March 20……
Certificate No. 1- Stock
A. Manufactures. - Certified (1) that the closing balance of Rupees…………
in the accounts of the head “Manufacture” for March 20……. consisted,
with the exceptions noted below, only of the unadjusted charges upon
operations in progress, (2) that all out-turn from the operations has been
duly brought to account, and (3) that the closing balance does not relate to
any operations the accounts of which, under the rule in paragraph 11.1.4. of
the K.P.W.A. Code should have been closed and adjusted during the previous
twelve months.
B. Land, Kilns, etc. - Certified (1) that the closing balance of Rupees…………
in the accounts of the head “Land, Kilns, etc.” for March 20……. consists of
the items enumerated below, (2) that all charges recoverable from other heads
of account under rule or order (vide paragraph 11.2.2 of the K.P.W.A. Code)
have been duly credited to this head during the year, and (3) that the balance
in respect of each item represents, in my opinion, a fair residue which the
operations of the coming seasons may be reasonably expected to bear at the
prescribed rates of recovery: -
Gross capital Total credits on
capital account is to be cleared
Total No. of years in which the
To end of previous
To end of previous
Remarks
Total
Total
year
year
1 2 3 4 5 6 7 8 9 10 11 12
` † ` † ` † ` † ` † ` †
175
BOOK OF FORMS
1 2 3 4
† `
1 Unserviceable stock……. (State the steps taken to obtain
(No details are required) the necessary sanction to write
off the loss)
*Of any other period that the local administration may have prescribed.
† In nearest rupees only.
176
BOOK OF FORMS
177
BOOK OF FORMS
outstanding balances
name of
work
2 of Form 29)
20…………)
Serial No.
1 2 3 4 5 6 7
†` †` †`
*If the materials relating to a work were not verified during the previous
twelve months, the reasons for the omission should be recorded in this
column - See paragraph 10.3.8. of the K.P.W.A.Code.
† In nearest rupees only.
C. Contractors and Labourers, Purchases. - Certified (1) that the closing
balances of the accounts of “Contractors” and “Labourers” “Purchases as
maintained in Registers of works in respect of works the accounts of which
were open on the 31st March 20……. were as detailed below, (2) that the total
of the contractors, balance as shown in Certificate 1 has been reconciled by
the Divisional Accountant with the total of the balances in the Contractor’s
Ledger, (3) that the Labourers balances have been similarly reconciled by the
178
BOOK OF FORMS
Details of balance
tions/Advance
Debits/Credits
Other transac-
Full name
Advances
Purchases
of work
Labourers
Serial No.
Payments
Remarks
Secured
1 2 3 4 5 6 7
*` *`
Total
Certified (1) that the register of rents of buildings and lands and other records
of assessment and realization of revenue (vide paragraph 9.5.4. of the K.P.W.A.
Code) for the year ending 31st March 20……….. have been reviewed in detail
and that all immovable properties belonging to the division which are available
for letting out and other important sources of revenue are entered in the
relevant registers with particulars, (2) that adequate action is being taken
under my orders in respect of revenue which remains unrealized for more than
one month by reason of delay on the part of the tenant or other person
concerned, and (3) that there are no arrears which have become or are likely to
be irrecoverable.
179
BOOK OF FORMS
180
FORM 84
REGISTER OF MEASUREMENT BOOKS
(Referred to in para 10.2.9 and 10.2.13)
Part I
Ordinary Measurement Books
Division………………….
Sub-division……………..
181
1 2 3 4 5 6
BOOK OF FORMS
†May be destroyed after ten years from the date of final record in the Division Office, i.e. the date entered in this
column.
FORM 84 - (Concld.)
Part II
For Standard Measurement Books
Serial No.
(Alphabetical)
Remarks
182
1 2 3 4 5 6 7 8 9
BOOK OF FORMS
BOOK OF FORMS
FORM 85
LIST OF MONTHLY SUBDIVISIONAL ACCOUNTS
[Referred to in para 21.1.5.]
Division…………………..……………. Month…………………..………… 20…………
Remarks
*Form No. of
Name of document
No. document
1 2 3 4
K.P.W. 86 Detailed list of Works Abstract A with ..
the Work Abstracts A for
Major Works
,, 86 Detailed list of Works Abstracts B with ..
the Work Abstracts B for Minor Works
,, 50 Transfer entry orders ..
,, 31 Detailed statement of materials at site ..
,, 31A Detailed statement of materials issued ..
to contractors
,, 36 Out-turn statement of manufacture ..
,, 50 Transfer entry orders ..
,, 86 List of Petty Works Requisitions and ..
Accounts
,, 26 Petty Requisitions and Accounts ..
,, 50 Transfer entry orders ..
,, 17 Survey Reports ..
,, 18 Sale Accounts ..
,, 50 Transfer entry orders ..
*Strike out the Form No. of any document not forwarded submission being
unnecessary. If any document is not ready a suitable note of explanation for
delay and the probable date of its submission should be recorded against it
in the column for remarks forwarded to the Divisional Officer.
Sub-divisional Officer
Dated……………..20……….
183
BOOK OF FORMS
FORM 86
A.- For Major Works
DETAILED LIST OF WORKS ABSTRACTS B.- For Minor Works
Petty Works Requisitions and Account
(Referred to in para 21.1.5)
Division……………………..Month………………20.......Sub-division…………………
Accompanied by
statement of
in the estimate of manufacture orders (Form
material (Form (Form K.P.W.36) K.P.W. 50)
K.P.W. 31)
1 2 3 4 5
Sub-divisional Officer
184
185
1
Item No.
No. and date of authority
2
ordering recovery
Nature and particulars
3
`.
5
Amount recoverable
Substance of orders
P.
recovery
Dated initials of Divisional
7
Accountant
No of voucher or
8
FORM 87
account
9
(Referred to in para 22.2.10.)
Month
`.
Amount
10
REGISTER OF MISCELLANEOUS RECOVERIES
each order
P.
`.
Progressive total of
11
Note of recoveries made against
recoveries
P.
Dated initials of Divisional
12
Accountant
13
Remarks
Division…........………
BOOK OF FORMS
BOOK OF FORMS
FORM 88
MEMO OF REVIEW OF REGISTERS, ETC.
(Referred to in para 22.4.32)
For the year………..………20......….
Division………………….
Dated initials of
1 2 3 4
April 20….
May 20….
June 20….
July 20….
August 20….
September 20….
October 20….
November 20….
December 20….
January 20….
February 20….
March 20….
Supplementary Accounts
186
FORM 89
REGISTER OF DESTRUCTION OF RECORDS
Division…………………………….
Description of records to be destroyed Sanction to destruction Dated
signature of
Period to Reference to Dated initials of the officers
Nature of Volume or Remarks
which the rules or the Divisional witnessing
document size records relate correspondence Officer destruction
Item No.
1 2 3 4 5 6 7 8
FORM 90
187
REGISTER OF TENDERS
Name of
BOOK OF FORMS
Serial No.
quotation
1 2 3 4 5 6 7 8 9 10
`. P.
FORM 91
PASS BOOK
(Referred to in para 22.3.3)
List of cheque cashed against the account of the Officer in charge…………………………..
Particulars of Particulars of
Month cheques cashed Initials of
cheques cashed Amount Initials of Month and
and date date of Amount Treasury
of payment of cheque Treasury of cheque Officers
Officers payment
No. Book No. Book
1 2 3 4 5 6 7 8
`. P. `. P.
188
BOOK OF FORMS
Note .- 1. A separate pass book should be maintained for each treasury with a Divisional Officer having a banking
account.
2. The pass book should be got written up every week when the treasury is at the headquarters of the
Division. Where it is at a distance it may be forwarded at longer intervals but the dates should be fixed.
BOOK OF FORMS
FORM 92
TEMPORARAY RECEIPT FOR MONEY RECEIVED BYA GOVERNMENT
OFFICER IN THE PUBLIC WORKS DEPARTMENT OTHER
THAN SUB-DIVISIONAL/DIVISIONAL OFFICER
(Referred to in para 6.3.1.)
Temporary receipt
Book No……………………… Section……………………..
Receipt No………………………………..
Dated………………….20……………
Received from………………………………………………………………
……...............………`……………. (Rupees……………………………………
…………………………..) on account of……………………………………..….
(Signature)
(Designation)
Note .- The payee should secure the final receipt in lieu of the temporary
receipt within a week of payment.
(Corresponding to final receipt No……… ……dated…… ………20….…….)
189
FORM 93
REMITTANCE SLIP
(Referred to in para 6.3.5.)
190
I herewith forward `………..on I herewith forward `………..on I herewith forward `………..on
account of miscellaneous receipts account of miscellaneous receipts account of miscellaneous receipts
BOOK OF FORMS
realised, the particulars of which are realised, the particulars of which are realised, the particulars of which are
given overleaf. given overleaf. given overleaf.
(2) The amount was collected on (2) The amount was collected on (2) The amount was collected on
…………../ between ……………. …………../ between ……………. …………../ between …………….
and…………… and…………… and……………
(3) The final receipt in Form No.3 may (3) The final receipt in Form No.3 may (3) The final receipt in Form No.3 may
be sent. be sent. be sent.
191
Your No………....….Dated…..……….
`……………………..………Received.
BOOK OF FORMS
Sub-divisional Officer.
Particulars of sum referred to overleaf Particulars of sum referred to overleaf Particulars of sum referred to overleaf
(The number and date of temporary (The number and date of temporary (The number and date of temporary
receipt in Form No 93.should be given.) receipt in Form No.93 should be given.) receipt in Form No.93 should be given.)
BOOK OF FORMS
FORM
REGISTER OF SUPPLY ORDERS PLACED ON FIRMS,
(Referred to in
Name of firm ................................. Ref to contract .................................
Specification of material ...........................
Amount
Amount
Number
Number
Date
Rate
Unit
Unit
1 2 3 4 5 6 7 8 9 10 11 12
`. P. `. P. `. P.
Note :-
(1) Sufficient space should be left to record the transactions in columns 10 to 21 when a fresh
entry on supply order against the same Firm is made in columns 1 to 9
(2) The balance in column 19 is the quantity remaining to be supplied after deducting the
quantity received from that for which supply order was placed i.e., columns 3-12.
(3) The balance should be struck after each transaction in columns 10 to 18 is entered.
(4) Separate sets of folios may be assigned to record transactions with each form.
(5) Abstract should be worked out at the end of the register.
192
BOOK OF FORMS
94
SUPPLIES MADE AND PAYMENTS EFFECTED
para 10.2.25.)
Stipulated period for completing supply ..............................
Quantity
supply
Ref. to M.B.G.R.S
Additional item
(Col.9-18)
Remarks
Amount
Amount
Number
Charge
Unit
13 14 15 16 17 18 19 20 21 22
`. P. `. P. `. P.
Abstract (Firm-wise)
`. P.
Advance as per column 9
Cost of supplies made `. P.
During the month of ...................... 20....... .. ..
(column 18) etc.
.. ..
Total
.. ..
Balance
Officer-in-charge.
193
*FORM 95A
REGISTER OF RECEIPT, REVIEW AND RETURN OF MEASUREMENT BOOKS BY
THE DIVISIONALACCOUNTANT
[Referred to in para 10.2.4 (b)]
Division…………………………..
Percentage of
Percentage entries of which
Measurement Date fixed Date of
Date of Pages Date of Dated
Book arithmetical
for review receipt for review reviewed of entries return of initials of
reviewed reviewed accuracy of
review M.B. D.A.
calculations were
checked
194
BOOK OF FORMS
1 2 3 4 5
195
BOOK OF FORMS
Rule affected
Date of posting
Serial number of
correction
196
Rule affected
BOOK OF FORMS
Date of posting
Note of posting of corrections
Serial number of
correction
Rule affected
Date of posting