Method Statement For MDB & DB-MSB

The document outlines the scope, methodology, materials, and safety procedures for installing electrical distribution boards. It includes details on site preparation, installation steps, testing and commissioning, preferred materials, project organization, risks and controls, access, lighting, equipment, training certification, waste management, and special control measures. Appendices provide checklists and documentation for cable containment, project organization, risk assessment, and training certification.

Uploaded by

elbarani
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
651 views

Method Statement For MDB & DB-MSB

The document outlines the scope, methodology, materials, and safety procedures for installing electrical distribution boards. It includes details on site preparation, installation steps, testing and commissioning, preferred materials, project organization, risks and controls, access, lighting, equipment, training certification, waste management, and special control measures. Appendices provide checklists and documentation for cable containment, project organization, risk assessment, and training certification.

Uploaded by

elbarani
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 10

United Engineers ( Singapore ) Pte. Ltd.

257 Jalan Ahmad Ibrahim


Singapore 629147
Tel: +6562660988
Fax: +6562686993

CONTENTS:

1. Scope of works
2. Project organization for Health & Safety Control
3. Health & Safety Risk and Control
4. Access / Egress
5. Lighting
6. Plant & Equipment
7. Personnel Training Certificate
8. Hazardous Materials & Substances
9. Waste Management
10. Special Control Measures
Appendixes
Appendix 1: Checklist for cable containment
Appendix 2: Project Organization for Health & Safety control
Appendix 3: Risk Assessment
Appendix 4: Personnel Training Certificate
United Engineers ( Singapore ) Pte. Ltd.
257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

1. Scope of Works

Scope of Activities

This scope defines the minimum standards to be adopted when installing Electrical
Distribution Boards is installed in surfaced concrete/brick wall according to
construction co-ordination drawings. A distribution board divides the electrical mains
feed into various circuits, providing a fuse or circuit breaker for each circuit. They
usually include a main switch, and often one or more Residual-current devices
(RCD) or Residual Current Breakers with over current protection (RCBO)

Site Procedure
Site mobilization shall be done with real time monitoring the conditions & progress of
builder works. Before commencement of the work, carry out examination of the
physical condition of the area. Photographs should be taken where necessary, prior
to commencement and during works.
United Engineers ( Singapore ) Pte. Ltd.
257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

Method Statement

1.1 Preparation stage


a. Factory visit and testing to be conducted before shipment to site.
b. Engineer in-charge shall check to ensure that the equipment, instruments,
bus bar size etc., complies with specification and drawings.
c. Engineer shall check to ensure that the switch room architectural finishing
work is completed and any physical obstruction during the delivery MDB/DB.
d. Ensure that the MDB/DB design/equipment provided all are fully comply with
the specification.
e. Supplier shall deliver MDB/DB to site and arrange it in the final position as per
shop drawings.
f. Handle the MDB/DB with care to avoid damage to components, frame and
finish.
g. Verify the handling equipment capacity is sufficient for MDB/DB weight.
h. When the MDB/DB is received, unpack it sufficiently to inspect it for
concealed damage to determine that the shipment is complete and correct.
i. If the MDB/DB is to be stored prior to installation, replace the packing for
protection during that period. When conditions permit, leave the packing intact
until MDB/DB or sections are at their final installation location.
j. Protect the equipment against the dust and debris during construction period.
k. A forklift truck or pallet may offer a more convenient method of handling the
MDB/DB to shift from one location to other.
United Engineers ( Singapore ) Pte. Ltd.
257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

1.2 Installation stage


a. Site survey of the proposed MDB and DB based on approved CSD by
foreman / sub-contractor together with Engineer.
b. Installation must be carried out based on approved shop drawings & samples
by foreman / sub-contractor.
c. Install the MDB/DB in its final position, progressively leveling each section
and bolting the frames together if they are separated.
d. Mark the exact position of the distribution board using respective template.
e. Drill the anchor location and install the distribution board.
f. Tightened all bolted connection in accordance with the manufacturer torque
specifications.
g. Fix all the metering equipment in the distribution board.
h. Name or label all sub-switch boards and distribution boards.
i. After installation of distribution board, Engineer-in-charge shall check the
complete works and complete the Inspection checklist for Electrical
distribution board installation works. ( See annex. 1)
j. Engineer-in-charge shall arrange and request for inspection with the Owner’s
representative Residential Technical Officer (RTO) using approved Main con
Request for Inspection (RIN) form.

1.3 Testing and commissioning


Steps to be taken before energizing the MDB/DB.
a. Qualified personnel should be present when the equipment is
energized for the first time.
b. Tighten all accessible electrical connection to the manufacturer's
torque specification.
c. Remove all blocks or other temporary holding means used for
shipment from all component devices and the DB interior.
d. Check the integrity of all bus mounting means.
United Engineers ( Singapore ) Pte. Ltd.
257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

e. Check the enclosure to see that it is not been damaged in a such a


manner as to reduce electrical spacing.
f. Manually exercise all switches, circuit breakers, and other operating
mechanism to make certain that they operate freely.
g. Conduct and electrical insulation resistance test to ensure that the
main distribution board is free from short circuits and grounds.
h. Check electrical relays, meters, and instrumentation to determine that
the connections are made properly and that the devices function
properly.
i. With all load disconnected, electrically exercise all electrical operated
switches, circuit breakers, and other mechanism to determine that the
devices operate properly.
j. The equipment should be energized in sequence by starting at the
source end of the system and working towards the load end.
k. After all the main, feeder, and branch circuit devices have been closed,
loads such as lighting circuits, contactors, heaters and motors turned
ON.

2 Preferred Materials

Main Distribution SMB, Sun light, ABB, ATCO, Terasaki, GSM, Total Automation Pte
Board Ltd.

3 Project organization for Health & Safety Control


(See annex. 2)

4 Health & Safety risks and controls


(Please refer to attach Risk assessment in respect to above scope of works – Annex.3)
United Engineers ( Singapore ) Pte. Ltd.
257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

5 Access / Egress
Proper step ladders shall be provided for access and egress into Distribution board as
applicable.

6 Lighting
Adequate temporary/task lighting shall be provided if work to be carried at night or at dark
places.

7 Plant & Equipment

S/N Description Unit


1 Center punch 1 lot
2 Brace 1 lot
3 Hammer 1 lot
4 Electrical drill (only for surface installation works) 1 lot

5 Diagonal-Cutting Pliers 1 lot

6 Wire Stripper/Cutter with Spring 1 lot

7 Side-Cutting Pliers 1 lot

8 Level 1lot

9 Shank Screwdriver 1 lot


P.P.E. – Personal Protective Equipment (safety helmet, Boots,
10 1 set per worker
gloves & safety vest )

*The above machinery & Equipment used quantity will be varied depending on site conditions
and production rate.

8 Waste management
The Rubbish which would be created from our scope of works will be disposed to the
designated dumping ground.
United Engineers ( Singapore ) Pte. Ltd.
257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

9 Special Control measures


The following general control measures against Safety, Environment and Quality shall be
required for our scope of work and special control measures are not applicable for us

 Proper PPE must be worn at all time


 Permit to work at height > 2m where applicable
 Lifting operation permit (using crane) where applicable.
 Confined space permit where applicable.
 Approved work method statement and risk assessment will be made available to site. All
workers doing the work shall be briefed on this method statement and risk assessment.
United Engineers ( Singapore ) Pte. Ltd.
257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

ANNEX 1:

Checklist
for
MDB/DB Installation
United Engineers ( Singapore ) Pte. Ltd.
257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

ANNEX 2:
Project Organisation
for Health & Safety
Control
United Engineers ( Singapore ) Pte. Ltd.
257 Jalan Ahmad Ibrahim
Singapore 629147
Tel: +6562660988
Fax: +6562686993

ANNEX 3:
Risk Assessment