Docl Ies Dep FGS PDF
Docl Ies Dep FGS PDF
Document Title
1 INTRODUCTION ................................................................................................ 5
1.1 General ....................................................................................................................... 5
1.2 Purpose ...................................................................................................................... 5
1.3 Objective ..................................................................................................................... 5
2 ABBREVIATIONS .............................................................................................. 6
2.1 Reference Document ................................................................................................. 7
2.2 Specifications, Codes and Standards ...................................................................... 7
2.3 International Standards ............................................................................................. 7
2.4 Order of Precedence .................................................................................................. 8
2.5 Definitions .................................................................................................................. 8
2.6 Facility Block Flow ................................................................................................... 10
3 VENDOR RESPONSIBILITY ........................................................................... 11
4 FIRE WATER SYSTEM ................................................................................... 12
4.1 Fire Water Storage Tanks ........................................................................................ 12
4.2 Fire Water Pumps..................................................................................................... 12
4.3 Jockey Pumps .......................................................................................................... 13
4.4 Fire Water Ring Main................................................................................................ 13
4.5 Hose box ................................................................................................................... 13
4.6 Hydrants ................................................................................................................... 14
4.7 Firewater Hose reels ................................................................................................ 14
4.8 Firewater Monitors ................................................................................................... 15
4.9 Foam system ............................................................................................................ 16
4.10 Fixed Foam Systems Specification......................................................................... 16
5 EXTINGUISHERS ............................................................................................ 19
5.1 Portable Dry Chemical Powder Extinguisher ......................................................... 19
5.2 Wheeled Dry Chemical Powder Extinguisher......................................................... 19
5.3 Portable CO2 Extinguisher ...................................................................................... 20
5.4 Wheeled CO2 Extinguisher...................................................................................... 20
6 PAINTING, IDENTIFICATION AND MARKING ............................................... 21
6.1 Painting..................................................................................................................... 21
6.2 Identification and Marking ....................................................................................... 21
7 TESTING .......................................................................................................... 22
7.1 Test Program ............................................................................................................ 22
7.2 Test Procedures ....................................................................................................... 22
7.3 Equipment Testing ................................................................................................... 22
7.4 Site Test Requirements ........................................................................................... 22
8 DOCUMENTATION ......................................................................................... 24
LIST OF TABLES
Table 1: Abbreviations ............................................................................................................. 7
Table 2: Reference Document ................................................................................................. 7
Table 3: Codes and Standards ................................................................................................ 8
1 INTRODUCTION
1.1 General
(DICL) intends to carry out a Front-End Engineering Design (FEED) for the proposed
Energy Park. The purpose of this design is to ensure that the project requirements for
a complete engineering design package are well defined and properly outlined for the
execution of the integration of the components of the Energy Park.
1.2 Purpose
The purpose of this document is to specify minimum requirement for firefighting
equipment to be used within the Duport Energy Park facility.
1.3 Objective
The overall objective of this document is to ensure a safe and reliable plant based on
proven design practice and technology and with risks from potential fire hazards
detection. The main reason for the Firefighting Equipment Specification is to ensure
that an acceptable level of safety is achieved in order to protect personnel, installation
and environment against fire and explosion hazards.
2 ABBREVIATIONS
Abbreviation Meaning
BS British Standard
FM Factory Mutual
H2 Hydrogen
IR Infra-Red
UL Underwriters Laboratory
UV Ultra Violet
Table 1: Abbreviations
Unless the edition of any code, standard or document is specifically mentioned, the
latest editions shall apply and where conflict exists between requirements of these
documents, it shall be addressed to the CLIENT for clarification.
Codes Title
API Publication 2021A Prevention and Suppression of Fires in Large
Aboveground Atmospheric Storage Tanks
In case of a conflict, the regulations, codes and standards listed shall be applied in the
following order of priority:
2.5 Definitions
For the purpose of this specification, the following definitions shall have the meanings
stated:
MUST/SHALL – Indicates a mandatory requirement.
SHOULD - Indicates a preferred course of action or strongly recommended to comply
with the requirements of this document.
MAY – Indicates an acceptable course of action.
CLIENT - The party who initiates the project and ultimately specifies the technical
requirements, which is ENERGY PARK.
CONTRACTOR - The party who carries out all or part of the engineering
2.6 Facility Block Flow
3 VENDOR RESPONSIBILITY
The Vendor shall be responsible for the complete design, fabrication, supply, and
inspection/testing of equipment in their scope of supplies. Datasheets/ specifications
give the minimum requirements and would not override Local Government Legislation
and Regulations or applicable design codes and standards.
4 FIRE WATER SYSTEM
The fire water systems shall comprise of the following main items but not limited to:
2 hours minimum flow capacity from fire water storage tank is expected via the
fire water pump to fight fire.
Tank capacity of 2 hours minimum shall be calculated, in accordance with the
requirements of NFPA 22.
Three by 50% fire water pumps (2 working one on standby) are to be leveraged upon
for the use of the Firefighting system at Duport Energy Park facility. The pumps are
all diesel engine powered pumps in operation, which takes suction from the fire water
storage tank.
Fire pump shall be configured for manual and automatic start. Automatic starting of
the fire water pump shall be as a result confirmed fire within the facility, Low
pressure in the ringmain.
Individual pressure sensors shall be provided for each fire pump. Stopping of the fire
pumps shall only be manually at the local control panel of the fire pumps.
A fire pump test line with flow meter shall be provided (with flow returned to the
storage tank) to allow for periodic testing of the hydraulic performance of the pumps.
Two by 100% electrically driven jockey pump (One working and one on stand by)
shall be provided to pressurize the fire water ring main system and a backup should
also be planed for. Jockey pump shall be continuously operated to maintain pressure
of the ring main.
The jockey pump shall have a normal flow rate calculated in cubic meter as stated in
the firewater demand calculation: DMCL-IES-DEP-PRO-CAL-00003 Fire Water
Demand calculaton Report.
One Hose cabinet containing firefighting equipment for use shall be located adjacent
to hydrants or groups of hydrants. The equipment, contained shall be sufficient to
allow two hydrants hose streams to be operated and will be typically:
2 off 65 ft of 1 ½” collapsible hose.
2 off jet/fog/off nozzles.
Quick connections system.
Adapters and wrenches.
Axe.
4.6 Hydrants
Hydrants shall be readily accessible from roads and be located in such a way that
possible damage by road traffic will not occur or will be minimized. Hydrant to hydrant
shall be located within 40-60 meters from each other. The total hydrant shall be as
stated on the layout drawing, for Fire Fighting Equipment Layout: DMCL-IES-DEP-
FGS-LAY-00001
Fire hydrants shall be the wet barrel, two-outlet, or one-outlet in the facility and
generally fabricated from ASTM A 105 carbon steel and protectively coated internally
after all welding and inspection is completed.
Fire hydrants shall be suitable for a maximum working pressure of 15 barg and have a
4’’ diameter riser terminating with a 4" flange to suit the applicable piping class at the
bottom and 4" standard pipe cap at the top. Mating connections for hydrant valves
shall be of suitable size and rating for the application.
Each hydrant connection shall be provided complete with a blanking cap, which shall
be attached to the valve by a suitable non-corrodible chain.
Hydrants shall be located at least 15 meters from the buildings or process equipment
to be protected.
In tank areas, hydrants shall be located so that all parts of the tank can be reached
with a hose no longer than 150 meters and cooling can be provided to any tank from
two directions.
The firewater mating connection shall be 1½" NPT to suit the applicable piping class.
The hose reel assembly shall include a quarter turn ball valve for isolation from the
firewater supply. The isolation valve shall be solid brass or bronze.
All firewater hose reel assemblies shall be supplied complete with a hot dip
galvanised steel pedestal.
The hose reel assembly shall be designed for manual rewinding of the hose. It shall
have a travelling hose guide for placing the hose correctly on the reel.
The entire hose reel assembly shall be hot dip galvanized to ASTM A123 prior to
painting.
The hose reel shall be equipped with a low point drain valve.
Hose reel assemblies shall have a heavy duty red canvas cover marked in white,
with 1" letters, "FIRE HOSE".
Hose reels shall be located such that process areas and manifolds are within 30
meters of two hoses. The location distance of hose reels shall not be closer than 6
meters from process equipment or the building being protected.
Firewater monitors shall be designed for a minimum pressure drop when operating at
firewater supply pressure of 10.4 barg. The units shall be rated for 17.3 barg at 38°C.
Firewater monitors shall be designed for operation by one person. The operating
mechanism shall be a butterfly valve requiring one quarter turn to open or close. The
valve shall be located upstream of the monitor flange base.
Firewater monitors shall be operated by control arms and capable of 360 degree
rotation in the horizontal plane and +90/-45 degree elevation in the vertical plane.
The swivel joints shall be furnished with bronze balls and grease zerks for easy
lubrication and shall also be capable of being locked in all operating positions.
The inlet flange to the monitor shall be a 4" Class 150# flat face flange. The firewater
piping mating flange shall match the firewater monitor inlet flange.
The firewater monitor shall be equipped with drain valve at the flange base for
draining firewater after use.
The firewater monitor body shall be brass, leaded gunmetal or equivalent, control
arms shall be chromed brass.
The firewater monitor shall be equipped with constant flow straight stream to wide
fog. The nozzle shall be rated for 1325 lpm (350 US gpm) or more at an operating
pressure of 7 barg with an effective range of at least 50m when on solid stream
setting or any approved company ( DUPORT MIDSTREAM COMPANY LIMITED)
type.
Fixed foam system shall be designed to meet the requirement of NFPA 11, Standard
for Low Expansion Foam. The fixed system shall have a valve connection to enable
fire truck provide back up.
The foam system design basis shall be seal area fire. The foam discharge outlets
shall be located above the seal as described in NFPA 11.
Foam shall be generated by a diaphragm (bladder) pressure proportioning tank,
which uses water pressure as source of power.
The bladder tank shall be Ansul (vertical) type, designed and constructed in
accordance with the latest revision to ASME code, Section VIII for unfired pressure
vessel with a working pressure of 12 barg (175 psig) and tested to at least 18 barg
(262 psig)
The nominal capacity of the bladder tank shall be specified based on the minimum
design rate of solution for fire fighting areas and locations. The foam concentrate
specified for this duty shall be 3% AFFF resistant foam.
The bladder tank shall be sized to provide foam supply to the areas where product
tanks are in sequence. The foam application period shall be in accordance with
NFPA 11 requirement.
The bladder tank shall have a label specifying the type of foam concentrate designed
for the system, the quantity of concentrate and any other pertinent warnings. In
addition, the tank assembly shall be UL listed and FM approved.
The foam concentrate shall have mix flexibility from 1% to 6%. The system shall be
equipped to allow for adjustment of the foam mix to a desired preference.
The bladder tank assembly shall be equipped with a porous centre tube of PVC or
other material compatible with the foam agent. In addition, the tank shall have side
gauge level indicator to monitor the level of foam in the bladder
Connection piping for the foam system shall provide for inlet pressure between 5.0
barg and 7.0 barg (75 to 100 psig) at the foam generators.
Valved connections shall be provided at the suction and discharge ends of the
bladder tank to be used as back up by the terminal fire truck for foam proportioning
and re-filling of the bladder tank during response.
Unless otherwise specified, fresh water service piping shall be galvanized carbon
steel. For salt-water service if need be, piping shall be epoxy-lined.
The foam system shall be designed to accommodate periodic testing with water.
Suitable facilities shall be installed to direct water from the nozzles away from the
floating roof during testing.
Bladder tank connection point for the foam piping system shall be located at a
distance not less than 30 meters (100 ft) outside the tank berm area accessible by
the facility’s foam truck for back-up.
5 EXTINGUISHERS
6.1 Painting
Protective coating of all carbon steel components and other equipment shall be in
accordance with the requirements of COMPANY Approval.
The VENDOR shall ensure appropriate painting and other treatment to afford
protection for the equipment during transportation and storage prior to erection and
during normal operation.
In general, the painting of equipment shall be as per COMPANY Specification.
VENDOR may suggest alternate painting system, however, they must prove /
guarantee that the proposed system is either equivalent to COMPANY recommended
system or higher.
Equipment Name
Equipment Number
VENDOR name
Certified Weight
Purchase order number
Year manufactured
Serial Number