0% found this document useful (0 votes)
2K views

CANAL ESTIMATE Template

The document provides specifications and cost estimates for a canal construction project involving concrete flooring, CHB walls with mortar, plastering, and a concrete cover. Materials needed include CHB blocks, cement, sand, gravel, rebar, and tie wires. Labor requirements and rates are also listed for pouring concrete, installing blocks and mortar, and rebar work. A total project cost of PHP 258,105.79 is estimated based on material, labor, equipment, and overhead costs.

Uploaded by

Edison G. Caluza
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views

CANAL ESTIMATE Template

The document provides specifications and cost estimates for a canal construction project involving concrete flooring, CHB walls with mortar, plastering, and a concrete cover. Materials needed include CHB blocks, cement, sand, gravel, rebar, and tie wires. Labor requirements and rates are also listed for pouring concrete, installing blocks and mortar, and rebar work. A total project cost of PHP 258,105.79 is estimated based on material, labor, equipment, and overhead costs.

Uploaded by

Edison G. Caluza
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

SPL CHB CANAL (3 LAYER) w/ cover

L 45.00 L.M.

A. Flooring
Volume = 45.00 x 0.70 x 0.10 = 3.15 cu.m
Cement = 3.15 x 9.50 = 29.93 bags
Sand = 3.15 x 0.53 = 1.67 cu.m
Gravel = 3.15 x 0.85 = 2.68 cu.m
10mm Rebar = 4.00 x 100.00 = 400.00 l.m. 66.67 say
67.00 pcs
TieWires #16 = 7.00 pcs

B. Wall
no. of CHB = 45.00 x 0.60 x 13.00 x 2.00 = 773.00 pcs
vol. of Mortar = 773.00 x 0.0045 = 3.48 cu.m
Cement = 3.48 x 11.00 = 38.26 cu.m
Sand = 3.48 x 1.00 = 3.48 cu.m
10mm Rebar = [( 100 / 0.30) + 1 ](1.5) + 4.00 x 100.00 = 901.50 l.m. 150.25 say
151.00 pcs
TieWires #16 = 7.00 pcs

C. Plastering
Volume = 45.00 x 0.60 x 0.03 x 2.00 = 1.35 cu.m
Cement = 1.35 x 11.00 = 14.85 bag
Sand = 1.35 x 1.00 = 1.35 cu.m

D. Cover
Volume = 45.00 x 0.70 x 0.10 = 7.00 cu.m
Cement = 7.00 x 9.50 = 66.50 bags
Sand = 7.00 x 0.53 = 3.71 cu.m
Gravel = 7.00 x 0.85 = 5.95 cu.m
10mm Rebar = [ ( 100 / 0.20) + 1 ](.7) + 4.00 x 100.00 = 338.20 l.m. 56.37 say
57.00 pcs
TieWires #16 = 7.00 pcs

Materials
Description Unit Qty Unit Cost Amount
6" CHB thk pcs 773.00 16.00 12,368.00
Cement bags 151.00 235.00 35,485.00
Sand cu.m 12.00 850.00 10,200.00
Gravel cu.m 9.00 900.00 8,100.00
10mm dia x 6m pcs 290.00 200.00 58,000.00
TieWires #16 kgs 21.00 90.00 1,890.00
126,043.00

Labor
Pouring of Concrete
Capacity of 1 gang = 7.50 cu.m / day
No. of days = 7.00
= 0.93 say 1 day
7.50

1 Construction Foreman
1 Mason
4 Laborers
Installation of CHB, of Mortar & Installation of Rebars
Capacity of 1 gang = 116.00 pcs / day
No. of days = 773.00
= 6.66 say 14 day
116.00

1 Construction Foreman
1 Mason
4 Laborers

Designation Number No. of days Rate/day Amount


Const. Foreman 1 15 600 9,000.00
Mason 2 15 500 15,000.00
Laborers 8 15 300 36,000.00
Total Labor Cost 60,000.00
Minor Tools 6,000.00

Materials 126,043.00
Labor 60,000.00
Equipment 6,000.00
Direct Cost 192,043.00

Unit Cost 1,920.43

Say 1,920.00

For Length l.m. #REF!


Total Cost #REF!
Mark Up 38,408.60
VAT 27,654.19
Total Cost 258,105.79
1,920.00

#REF!

You might also like