CANAL ESTIMATE Template
CANAL ESTIMATE Template
L 45.00 L.M.
A. Flooring
Volume = 45.00 x 0.70 x 0.10 = 3.15 cu.m
Cement = 3.15 x 9.50 = 29.93 bags
Sand = 3.15 x 0.53 = 1.67 cu.m
Gravel = 3.15 x 0.85 = 2.68 cu.m
10mm Rebar = 4.00 x 100.00 = 400.00 l.m. 66.67 say
67.00 pcs
TieWires #16 = 7.00 pcs
B. Wall
no. of CHB = 45.00 x 0.60 x 13.00 x 2.00 = 773.00 pcs
vol. of Mortar = 773.00 x 0.0045 = 3.48 cu.m
Cement = 3.48 x 11.00 = 38.26 cu.m
Sand = 3.48 x 1.00 = 3.48 cu.m
10mm Rebar = [( 100 / 0.30) + 1 ](1.5) + 4.00 x 100.00 = 901.50 l.m. 150.25 say
151.00 pcs
TieWires #16 = 7.00 pcs
C. Plastering
Volume = 45.00 x 0.60 x 0.03 x 2.00 = 1.35 cu.m
Cement = 1.35 x 11.00 = 14.85 bag
Sand = 1.35 x 1.00 = 1.35 cu.m
D. Cover
Volume = 45.00 x 0.70 x 0.10 = 7.00 cu.m
Cement = 7.00 x 9.50 = 66.50 bags
Sand = 7.00 x 0.53 = 3.71 cu.m
Gravel = 7.00 x 0.85 = 5.95 cu.m
10mm Rebar = [ ( 100 / 0.20) + 1 ](.7) + 4.00 x 100.00 = 338.20 l.m. 56.37 say
57.00 pcs
TieWires #16 = 7.00 pcs
Materials
Description Unit Qty Unit Cost Amount
6" CHB thk pcs 773.00 16.00 12,368.00
Cement bags 151.00 235.00 35,485.00
Sand cu.m 12.00 850.00 10,200.00
Gravel cu.m 9.00 900.00 8,100.00
10mm dia x 6m pcs 290.00 200.00 58,000.00
TieWires #16 kgs 21.00 90.00 1,890.00
126,043.00
Labor
Pouring of Concrete
Capacity of 1 gang = 7.50 cu.m / day
No. of days = 7.00
= 0.93 say 1 day
7.50
1 Construction Foreman
1 Mason
4 Laborers
Installation of CHB, of Mortar & Installation of Rebars
Capacity of 1 gang = 116.00 pcs / day
No. of days = 773.00
= 6.66 say 14 day
116.00
1 Construction Foreman
1 Mason
4 Laborers
Materials 126,043.00
Labor 60,000.00
Equipment 6,000.00
Direct Cost 192,043.00
Say 1,920.00