Transformer Project Report
Transformer Project Report
Group Members
Project Supervisor
Engr Mughees Ahmed
Lab Engineeer
Abstract
The following report is written about the construction of a transformer. The
transformer we are making is a single phase transformer with one primary
winding and two secondary windings. This transformer is commonly used in
labs for practical works and various tests. Construction of a transformer
requires calculation for selection of framework, wire gauges, and no of turns
for each winding. We also calculated the quantity of wire required for each
winding. First winding that is wounded on the framework is primary winding,
after each winding a cover of masking tape and wax paper is applied to
prevent the physical connection between different windings. When all the
windings are completed, we started to insert silicon iron sheets of shape E and
I which are normally referred as core of transformer. After insertion of core,
last step is to test your working. We tested the primary and secondary voltages
using a voltmeter. The results proved that our transformer is in working
condition.
II
Air University
Table of Contents
TRANSFORMER .............................................................................................. I
Abstract ......................................................................................................... II
List of Tables .................................................................................................... V
Introduction .................................................................................................... 1
Design Calculation ......................................................................................... 1
Design Procedure ........................................................................................... 4
Results and Discussion .................................................................................. 5
Open Circuit Test ....................................................................................... 6
Short Circuit Test ....................................................................................... 8
Efficiency ................................................................................................. 10
Voltage Regulation .................................................................................. 10
Conclusion ................................................................................................... 14
References .................................................................................................... 15
Appendix A .................................................................................................. 16
Appendix B .................................................................................................. 17
III
Air University
List of Figures
Figure 1: Open Circuit Test ............................................................................... 6
Figure 2: Open Circuit Test Readings ............................................................... 7
Figure 3: Short Circuit Test ............................................................................... 8
Figure 4: Short Circuit Test Reading ................................................................. 9
Figure 5: Unity Power Factor Reading Table .................................................. 10
Figure 6: Unity Power Factor Graph ............................................................... 11
Figure 7: Leading Power Factor Reading Table .............................................. 11
Figure 8: Leading Power Factor Graph ........................................................... 12
Figure 9: Lagging Power Factor Reading Table .............................................. 12
Figure 10: Lagging Power Factor Graph ......................................................... 13
IV
Air University
List of Tables
Table 1: Transformer Windings Requirements.................................................. 1
Table 2: No of turns for windings ...................................................................... 2
Table 3: AWG SWG Table ................................................................................ 3
Table 4: Measured Values ................................................................................. 5
Table 5: AWG SWG table ............................................................................... 16
Table 6:Cost Prices .......................................................................................... 17
V
Air University
Introduction
Transformer is a static electrical device used for transmission of electrical
energy between two or more circuits. Transformer works on the principle of
mutual induction. A varying current in one coil of the transformer produces a
varying magnetic flux, which, in turn, induces a varying electromotive
force across a second coil wound around the same core. Electrical energy can
be transferred between two coils without a metallic connection between two
circuits. In this project we constructed a transformer to better understand the
phenomenon of working of transformer and a general knowhow of its
construction. The transformer we built is a single phase transformer with one
primary and two secondary windings. Our requirement is listed in table 1
Design Calculation
First of all we need to select a framework for transformer on which all the
primary and secondary windings will be wounded. To select the area
framework we have an equation
1
Air University
𝐴 = √𝑆 𝑐𝑚2
𝐴 = √55 𝑐𝑚2
𝐴 = 7.416 𝑐𝑚2
𝐴 = 14.83 𝑐𝑚2
42
𝛼=
𝐴
42
𝛼=
16
2
Air University
Now we need to select the wire gauges for different values of currents with the
help of AWG or SWG table
To select the length of wire required for each winding we need to calculate the
circumference of framework
𝐶 = 2〈𝑊 + 𝐿〉
𝐶 = 2〈4 + 4〉
𝐶 = 16 𝑐𝑚
𝐿𝑝 = 9240 + 924
𝐿𝑝 = 10164𝑐𝑚
𝐿𝑝 = 101.64𝑚
′
𝐿𝑠1 = (16 × 997.5) + 𝑙𝑠1
3
Air University
𝐿𝑠1 = 17556𝑐𝑚
𝐿𝑠1 = 175.56𝑚
′
𝐿𝑠2 = (16 × 577.5) + 𝑙𝑠2
𝐿𝑠2 = 10164𝑐𝑚
𝐿𝑠2 = 101.64𝑚
Design Procedure
As discussed in the design calculations, we need to select a 4cm x 4cm
framework. Start with the primary winding of gauge 31 and start winding.
Carefully count the no of turns as increasing or decreasing no of turns will
cause change in required voltage. For convenience after each 100 turn place a
mark using masking tape. When primary winding is completed, wrap a full
cover of masking tape and then one layer of wax paper on top for insulation so
that both windings do not touch each other. If the primary winding is
clockwise then both secondary windings must be wounded clockwise. If not,
we may experience between primary and secondary voltages. Now start with
the secondary winding using 33 gauge wire, in this case we have tapping, for
first tapping after 190V or 500 turns pull out a loop and continue to wind.
Similarly for second tap pull out another loop after 365 turns and complete the
secondary winding after another 135 turns. Again cover the winding with a
layer of masking tape and wax paper. Now start with the second secondary
winding, this time using 31 gauge wire, after 290 turns pull out a loop and
then after another 290 turns, complete the secondary winding. Make sure that
all the windings are coming out from different regions of framework. Apply
another layer of masking tape and wax paper. Cover the wax paper with
binding tape so it does not detach.
4
Air University
Now start inserting E type core alternatively from each side. When there is no
space to insert more, start inserting I in between E’s on both side. Use hammer
where necessary. After inserting the core, tighten it using nut and bolts.
Remove the enamel coating from each end of wire and loops coming from the
transformer using sand paper to give external connection. Make sure that the
loop does not break. Solder the wires coming out of transformer and external
wires, also apply thermal insulation for safety. Attach a connecting strip to the
transformer and connect both all secondary wires inside it because it makes it
easier to measure the voltage.
For testing, we connected the primary with 220V and measured the secondary
voltages.
We noticed that the measured values are different from required voltages. The
reason for this is variation in no of turns and less than required primary
voltage.
5
Air University
6
Air University
𝐼𝑜𝑐 = 0.557 𝐴
𝑉𝑜𝑐 = 214 𝑉
𝑃𝑜𝑐 = 28.15 𝑊
28.15
𝑐𝑜𝑠𝜃𝑜𝑐 =
214 × 0.557
𝑐𝑜𝑠𝜃𝑜𝑐 = 0.236
𝜃𝑜𝑐 = 76.35
𝐼𝑜𝑐
𝑌𝑎𝑏𝑠 = = 0.00260 𝑆
𝑉𝑜𝑐
𝑌 = 𝑌𝑎𝑏𝑠 𝜃𝑜𝑐
Comparing with
1 𝑗
𝑌= −
𝑅𝑐 𝑋𝑚
𝑅𝑐 = 163𝑘𝑜ℎ𝑚
𝑋𝑚 = 396 𝑜ℎ𝑚
7
Air University
8
Air University
𝐼𝑠𝑐 = 0.248 𝐴
𝑉𝑠𝑐 = 26.54 𝑉
𝑃𝑠𝑐 = 3.887 𝑊
3.887
𝑐𝑜𝑠𝜃𝑠𝑐 =
26.54 × 0.248
𝑐𝑜𝑠𝜃𝑠𝑐 = 0.591
𝜃𝑠𝑐 = 53.803
𝑉𝑠𝑐 26.54
𝑍𝑎𝑏𝑠 = = = 107.016 𝑆
𝐼𝑠𝑐 0.248
𝑍 = 𝑍𝑎𝑏𝑠 𝜃𝑠𝑐
𝑍 = 61.68 + 𝑗87.45
Comparing with
𝑍 = 𝑅𝑠 + 𝑗𝑋𝑠
𝑅𝑠 = 61.68 𝑜ℎ𝑚
9
Air University
𝑋𝑠 = 87.45 𝑜ℎ𝑚
Efficiency
Efficiency of a transformer can be defined as the output power divided by the
input power. That is efficiency = output / input.
Transformers are the most highly efficient electrical devices. Most of the
transformers have full load efficiency between 95% and 98.5%. As a
transformer being highly efficient, output and input are having nearly same
value, and hence it is impractical to measure the efficiency of transformer by
using output / input. A better method to find efficiency of a transformer is
using, efficiency = (input - losses) / input = 1 - (losses / input).
Voltage Regulation
The measure of how well a power transformer maintains constant secondary
voltage over a range of load currents is called the transformer’s voltage
regulation. It can be calculated from the following formula:
11
Air University
12
Air University
13
Air University
Conclusion
We constructed a single phase transformer following the basic design
procedure. This transformer is commonly used in labs for practical works and
performing open circuit test, short circuit test and to calculate voltage
regulation. Basically it is a step up transformer of ratio 11:19 and 1:1 if we
consider primary and secondary-II winding. In a way we can also refer it as a
step down transformer because of the tapping. We realize that the primary
voltage is less as compared to secondary but primary current is high as
compared to secondary. If we calculate the reactive power of both windings it
comes out to be 55VA which means reactive power throughout the
transformer remains same. We also used laminated silicon iron sheets to
reduce the eddy current losses. To reduce hysteresis loss we used soft
ferromagnetic material which is iron. Open circuit test and short circuit test
were performed on the transformer to measure the values of components that
deal with the losses of transformer. We also measured efficiency and voltage
regulation of transformer at unity, leading and lagging power factor.
14
Air University
References
http://www.construyasuvideorockola.com/transformador.php
https://www.youtube.com/watch?v=s6NyTprQCBI
https://en.wikipedia.org/wiki/Transformer
15
Air University
Appendix A
16
Air University
Appendix B
Table 6:Cost Prices
Items Price in Rs
Framework 80
Core 680
Wax Paper 35
Masking Tape 60
Wire 450
Total 1505
17