Accelerated Programme
Accelerated Programme
Milestones and Key Dates 285 30-May-19 10-Mar-20 10-Mar-20, Milestones and Key Dates
Intake Relocation Works (AWTIP/IDSSP Scope of Work) 344 22-Feb-19 31-Jan-20 31-Jan-20, Intake Relocation Works (AWTIP/IDSSP Scope of W
Diapraghm Wall 344 22-Feb-19 31-Jan-20 31-Jan-20, Diapraghm Wall
A1010 Mobilisation of Hydromil Rig 1 22-Feb-19 22-Feb-19 Mobilisation of Hydromil Rig
A1020 Excavation of guide wall 15 22-Feb-19 08-Mar-19 Excavation of guide wall
A1030 Rebar for guide wall 13 25-Feb-19 09-Mar-19 Rebar for guide wall
A1040 Forms for guide wall 13 25-Feb-19 09-Mar-19 Forms for guide wall
A1050 Concrete casting for guide wall 13 26-Feb-19 10-Mar-19 Concrete casting for guide wall
A1530 Pre-drilling works 11 02-Mar-19 12-Mar-19 Pre-drilling works
A1060 Diapraghm wall excavation/construction 41 02-Mar-19 11-Apr-19 Diapraghm wall excavation/construction
A1660 Excavation works inside diapraghm wall (by TBM) 15 02-May-19 16-May-19 Excavation works inside diapraghm wall (by TBM)
A1070 Diapraghm wall capping beam 9 13-May-19 21-May-19 Diapraghm wall capping beam
A3610 Demolition of diapraghm wall (frontal area) 30 02-Jan-20 31-Jan-20 Demolition of diapraghm wall (frontal area)
Underwater demolition/excavation 127 17-May-19 20-Sep-19 20-Sep-19, Underwater demolition/excavation
A3190 Underwater Demolition 98 17-May-19 22-Aug-19 Underwater Demolition
A3270 Underwater excavation 80 09-Jun-19 27-Aug-19 Underwater excavation
A3290 Hauling of excavated materials 45 18-Jul-19 31-Aug-19 Hauling of excavated materials
A3300 Gabion Matress installation 20 01-Sep-19 20-Sep-19 Gabion Matress installation
MW2 Construction - Retaining Wall (IDSSP Scope of Works) 33 10-Apr-19 12-May-19 12-May-19, MW2 Construction - Retaining Wall (IDSSP Scope of Works)
Time Related Resources 33 10-Apr-19 12-May-19 12-May-19, Time Related Resources
A4400 Foreman (CMC) 33 10-Apr-19 12-May-19 Foreman (CMC)
Foundation 7 10-Apr-19 16-Apr-19 16-Apr-19, Foundation
A1080 Delivery rebar for foundation 2 10-Apr-19 11-Apr-19 Delivery rebar for foundation
A1090 Delivery forms for foundation 2 10-Apr-19 11-Apr-19 Delivery forms for foundation
A1110 Lean concrete 2 11-Apr-19 12-Apr-19 Lean concrete
A1100 Fabrication form for foundation 2 11-Apr-19 12-Apr-19 Fabrication form for foundation
A1120 Rebar installation 2 13-Apr-19 14-Apr-19 Rebar installation
A1640 Forms installation 2 14-Apr-19 15-Apr-19 Forms installation
A1650 Concrete casting 1 16-Apr-19 16-Apr-19 Concrete casting
Phase-1 (Right Side) 0
Phase-1 (Left Side) 0
Elevation 33 10-Apr-19 12-May-19 12-May-19, Elevation
First Lift 12 10-Apr-19 21-Apr-19 21-Apr-19, First Lift
A1730 Delivery rebar 2 10-Apr-19 11-Apr-19 Delivery rebar
Tunnel-Inside balance Works 112 22-Feb-19 13-Jun-19 13-Jun-19, Tunnel-Inside balance Works
A2330 Back Grouting works 98 22-Feb-19 30-May-19 Back Grouting works
A2340 Segmental lining repair works 68 22-Feb-19 30-Apr-19 Segmental lining repair works
A2520 Removal of backgrouting machine / silo 14 31-May-19 13-Jun-19 Removal of backgrouting machine / silo
TBM Disassembly and Removal 50 16-May-19 04-Jul-19 04-Jul-19, TBM Disassembly and Removal
A2380 Installation of Truck Crane and other Equipment 1 16-May-19 16-May-19 Installation of Truck Crane and other Equipment
A2390 TBM dismante & removal 9 17-May-19 25-May-19 TBM dismante & removal
A2530 Backup dismantle and removal 36 30-May-19 04-Jul-19 Backup dismantle and removal
Tunnel Backup & Tunnel Services Disassembly 70 05-Jul-19 12-Sep-19 12-Sep-19, Tunnel Backup & Tunnel Services Disassembly
A2540 Tunnel services & rail removal 70 05-Jul-19 12-Sep-19 Tunnel services & rail removal
Project Close-out and Hand-over 61 10-Jan-20 10-Mar-20 10-Mar-20, Project Close-out and Hand-over
A3800 Punchlist 30 10-Jan-20 08-Feb-20 Punchlist
A3810 Close-out documentation 30 10-Jan-20 08-Feb-20 Close-out documentation
A3820 As-built drawings 30 10-Jan-20 08-Feb-20 As-built drawings
A3830 Taking-over Certification 1 09-Feb-20 09-Feb-20 Taking-over Certification
A3840 Demobilization 30 10-Feb-20 10-Mar-20 Demobilization
A3850 Issuance of Completion Certificate 0 10-Mar-20 Issuance of Completion Certificate,