Method Statement of Casing Frame
Method Statement of Casing Frame
KUBER ENTERPRISES
TABLE OF CONTENTS
S.l.no Description
1 Scope
4 Material Transportation
5 Rigging Plan
6 Procedure
1. SCOPE
Material loading from DPSI Yard, Transportation from Yard to ESP#1 and Unloading of material at
ESP# 1 area by using Hydra.
Height work, hot work (Cutting, Grinding, Welding), Lifting& Shifting.
Bed preparation and Putting Frame on bed for Pre Assembly& inspection.
Inspection of Frame
Scaffolding Erection
Erection of Frame, Locking, alignment and Welding.
A) Crawler Crane
i) Crawler crane 250MT – 01 Nos.
ii) Crawler Crane 75MT – 01 Nos.
4. Material Transportation
Material shall be transported in manner of following lifting, shifting and Traffic rules of DPSI by 12
meter length trailer and 23MT hydra used for loading and unloading of material at yard and site.
5. Rigging Plan
Erection Crane
Crane Type 250MT crawler crane
Required Max Radius – 34 Meter
Rated Capacity of crane at required Radius – 19.4MT as per load chart
Weight of casing frame assembly – 16.5MT
Tension on sling – 9.52MT
Safety margin = 19.4-16.5= 2.9MT
METHOD STATEMENT FOR ERECTION OF CASING FRAME IN ESP UNIT – 1& 2
Tailing time
Erection crane – 250 MT
Tailing crane – 75MT
6. Procedure
Lifting procedure for Casing Frame Assembly for ESP Unit# 1
The Casing Column Frame assembly will lift by 250MT Crawler Crane and another crawler Crane 75MT
is used for Tailing of casing frame assembly as mentioned in the lifting procedure.
H. After erection of frame rough alignment and temporary locking will be done and welding to be
done, guy rope will be used as temporary support for alignment & safety of frame.
I. After welding and temporary locking with guy rope crane will be released for erection of other
frame, after erection, alignment& welding of other frame, both the frames will be interlocked by
permanent members.
J. Lifting tools are analysed, load is compared and verified against performance specification.
K. Slinging of load followed by safe method is done by slingers.
L. Material shall be hold by Crane at the safe distance and the lifting procedure shall be followed with
3.3.3 rules.
M. Materials and safe working load for the duration of lifting operation are calculated at each
participating hook.
METHOD STATEMENT FOR ERECTION OF CASING FRAME IN ESP UNIT – 1& 2
a) Prior to commencement of work a TBM shall be conducted along with the rigging crew and all possible
hazards and its control measures shall be discussed.
b) Experienced rigging crew shall be engaged for rigging, shifting and erection of Frame.
c) Proper signalling shall be ensured by the rigging foreman.
d) Megaphone/hooter will used during the erection time
e) 3.3.3 Lifting safety rules to be followed during erection of load.
I. Shall follow the client emergency procedure during the work period.
II. Emergency vehicle shall be present at site all around the time of lifting panel.