0% found this document useful (0 votes)
406 views17 pages

Standardized Work Analyze Tool V.3.2+video

This document is an instruction manual for the "Standardized Work Analyze Tool v.3.2" software. It explains that the software is registered for only one computer and should not be copied or moved. It provides instructions on how to use the software to record work times, including manual work, automatic work, walking, and waiting times. It also includes templates for recording standardized work combination tables and irregular work times.

Uploaded by

Robi Cahyadi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
406 views17 pages

Standardized Work Analyze Tool V.3.2+video

This document is an instruction manual for the "Standardized Work Analyze Tool v.3.2" software. It explains that the software is registered for only one computer and should not be copied or moved. It provides instructions on how to use the software to record work times, including manual work, automatic work, walking, and waiting times. It also includes templates for recording standardized work combination tables and irregular work times.

Uploaded by

Robi Cahyadi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 17

Standardized Work Analyze Tool+Video Capture

Ver 3.2 Created by Yaser Ali Husen ([email protected])


First time,Please click Start Button! (This Program is registered only for this Computer, could not be copied or moved to another Computer)
Source:lean-tool.com

*Don’t rename each sheet in this program

Welcome to use "Standardized Work Analyze Tool v.3.2"


Please run it only for 1 computer, if you use in different computer,the license will not be valid
2
PART NO SECTION LINE DATE
PROCESS NAME TIME STUDY SHEET TYPE TAKT TIME MEASURED BY
WORK NAME
Manual ADJUSTMENT MACHINE TIME AUTO
NO For walk activity, please write : OPERATION TIME OPERATION MACHINE NO
(Will be used for SWCT Line) (MACHINE TIME)
Walk; walk; walking; return; Return 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5

10

11

12

13

14

15

16

CYCLE TIME 0 0

yaser:
Don’t change this name!
Irregular Work (example : Take new polybox, etc) 3

Time
Time
NO Irregular Work Average Time Piece
(sec/pc)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

10

0.00
2 ###
###
DATE TAKEN APPROVED CHECKED PREPARED
PART NO
PCS / DAY
STANDARDIZED WORK COMBINATION TABLE SHEET LINE TAKT TIME
PROCESS
SECTION / LINE

NO WORK NAME MAN AUTO WALK 5" 10" 15" 20" 25" 30" 35" 40" 45" 50" 55" 60" 65" 70" 75" 80" 85" 90" 95" 100" 105" 110" 115"

Wait akhir
TOTAL 0.0 0.0
27.0

= Manual = Automatic
= Walking = Waiting
2 0
PART NO SECTION LINE DATE
PROCESS NAME TIME STUDY SHEET TYPE TAKT TIME MEASURED BY
WORK NAME
Manual ADJUSTMENT MACHINE TIME AUTO
NO For walk activity, please write : OPERATION TIME OPERATION MACHINE NO
(Will be used for SWCT Line) (MACHINE TIME)
Walk; walk; walking; return; Return 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5

10

11

12

13

14

15

CYCLE TIME 0 0

Irregular Work (example : Take new polybox, etc) 3

Time
Time
NO Irregular Work Average Time Piece
(sec/pc)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

10

0.00
2 ###
###
DATE TAKEN APPROVED CHECKED PREPARED
PART NO
PCS / DAY
STANDARDIZED WORK COMBINATION TABLE SHEET LINE TAKT TIME
PROCESS
SECTION / LINE

NO WORK NAME MAN AUTO WALK 5" 10" 15" 20" 25" 30" 35" 40" 45" 50" 55" 60" 65" 70" 75" 80" 85" 90" 95" 100" 105" 110" 115"

Wait akhir
TOTAL 0.0 0.0
0.0

= Manual = Automatic
= Walking = Waiting
2 0
PART NO SECTION LINE DATE
PROCESS NAME TIME STUDY SHEET TYPE TAKT TIME MEASURED BY
WORK NAME
Manual ADJUSTMENT MACHINE TIME AUTO
NO For walk activity, please write : OPERATION TIME OPERATION MACHINE NO
(Will be used for SWCT Line) (MACHINE TIME)
Walk; walk; walking; return; Return 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5

10

11

12

13

14

15

CYCLE TIME 0 0

Irregular Work (example : Take new polybox, etc) 3

Time
Time
NO Irregular Work Average Time Piece
(sec/pc)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

10

0.00
2 ###
###
DATE TAKEN APPROVED CHECKED PREPARED
PART NO
PCS / DAY
STANDARDIZED WORK COMBINATION TABLE SHEET LINE TAKT TIME
PROCESS
SECTION / LINE

NO WORK NAME MAN AUTO WALK 5" 10" 15" 20" 25" 30" 35" 40" 45" 50" 55" 60" 65" 70" 75" 80" 85" 90" 95" 100" 105" 110" 115"

Wait akhir
TOTAL 0.0 0.0
0.0

= Manual = Automatic
= Walking = Waiting
2 0
PART NO SECTION LINE DATE
PROCESS NAME TIME STUDY SHEET TYPE TAKT TIME MEASURED BY
WORK NAME
Manual ADJUSTMENT MACHINE TIME AUTO
NO For walk activity, please write : OPERATION TIME OPERATION MACHINE NO
(Will be used for SWCT Line) (MACHINE TIME)
Walk; walk; walking; return; Return 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5

10

11

12

13

14

15

CYCLE TIME 0 0

Irregular Work (example : Take new polybox, etc) 3

Time
Time
NO Irregular Work Average Time Piece
(sec/pc)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

10

0.00
2 ###
###
DATE TAKEN APPROVED CHECKED PREPARED
PART NO
PCS / DAY
STANDARDIZED WORK COMBINATION TABLE SHEET LINE TAKT TIME
PROCESS
SECTION / LINE

NO WORK NAME MAN AUTO WALK 5" 10" 15" 20" 25" 30" 35" 40" 45" 50" 55" 60" 65" 70" 75" 80" 85" 90" 95" 100" 105" 110" 115"

Wait akhir
TOTAL 0.0 0.0
0.0

= Manual = Automatic
= Walking = Waiting
2 0
PART NO SECTION LINE DATE
PROCESS NAME TIME STUDY SHEET TYPE TAKT TIME MEASURED BY
WORK NAME
Manual ADJUSTMENT MACHINE TIME AUTO
NO For walk activity, please write : OPERATION TIME OPERATION MACHINE NO
(Will be used for SWCT Line) (MACHINE TIME)
Walk; walk; walking; return; Return 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5

10

11

12

13

14

15

CYCLE TIME 0 0

Irregular Work (example : Take new polybox, etc) 3

Time
Time
NO Irregular Work Average Time Piece
(sec/pc)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

10

0.00
2 ###
###
DATE TAKEN APPROVED CHECKED PREPARED
PART NO
PCS / DAY
STANDARDIZED WORK COMBINATION TABLE SHEET LINE TAKT TIME
PROCESS
SECTION / LINE

NO WORK NAME MAN AUTO WALK 5" 10" 15" 20" 25" 30" 35" 40" 45" 50" 55" 60" 65" 70" 75" 80" 85" 90" 95" 100" 105" 110" 115"

Wait akhir
TOTAL 0.0 0.0
0.0

= Manual = Automatic
= Walking = Waiting
0
SECTION NAME PART NO. : APPROVED BY CHECKED BY CREATED BY
TYPE
PRODUCTION PART NAME :
NO. OF CAPACITY SHEET DOC. NO. :
UNITS PAGE DATE :
BASIC TIME TOOLS
PROCESSING
MACHINE
NO OPERATION CAPACITY
NO MANUAL AUTO
TIME TO NO
TIME TAKEN (0) 0 2 4 6 8 10 12

COMPLETE CHANGED

TOTAL 0.0
Second Yamazumi Chart
30

25

20

Baratsuki
Empty
Dandori (sec/pc)
Irregular
CT

15 Average
Baratsuki
Actual CT
TaktTime

27

10

0 0
Operator1
Second Yamazumi Chart
30

25

20

B aratsuki

15 E mpty
Dandori (sec/pc)
Irregular
CT

27 Average
B aratsuki
A ctual CT
TaktTime

10

0 0 0 0 0
Operator1 Operator2
Second Yamazumi Chart
30

25

20

Baratsuki

15 Empty
Dandori (sec/pc)
Irregular
CT

27 Average
Baratsuki
Actual CT
TaktTime

10

0 0 0 0 0 0 0 0
Operator1 Operator2 Operator3
Second Yamazumi Chart
30

25

20

B aratsuki

15
E mpty

Dandori (sec/pc)

Irregular

CT

27 Average
B aratsuki

A ctual CT

TaktTime

10

0 0 0 0 0 0 0 0 0 0 0
Operator1 Operator2 Operator3 Operator4
Second Yamazumi Chart
30

25

20

B aratsuki

15
E mpty

Dandori (sec/pc)

Irregular

CT

27 Average
B aratsuki

A ctual CT

TaktTime

10

0 0 0 0 0 0 0 0 0 0 0 0 0 0
Operator1 Operator2 Operator3 Operator4 Operator5