0% found this document useful (0 votes)
662 views

Process Flow Chart On Arbitration of Construction Claims Dispute PDF

The document outlines the process flow chart for arbitration of construction claims and disputes by the Construction Industry Arbitration Commission. The process involves two main stages - from filing to signing the terms of reference, and the arbitration proceedings from the hearing up to enforcement of the award. Key steps include filing a request for arbitration, payment of fees, appointment of arbitrators, preliminary conference, finalizing the terms of reference, holding hearings, rendering an award, and potential appeal or enforcement of the award.

Uploaded by

roytanladiasan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
662 views

Process Flow Chart On Arbitration of Construction Claims Dispute PDF

The document outlines the process flow chart for arbitration of construction claims and disputes by the Construction Industry Arbitration Commission. The process involves two main stages - from filing to signing the terms of reference, and the arbitration proceedings from the hearing up to enforcement of the award. Key steps include filing a request for arbitration, payment of fees, appointment of arbitrators, preliminary conference, finalizing the terms of reference, holding hearings, rendering an award, and potential appeal or enforcement of the award.

Uploaded by

roytanladiasan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Construction Industry Arbitration Commission

Arbitration of Construction Claims/Disputes


Process Flow Chart

A.Filing to TOR Signing B. Arbitration Proceedings


(Hearing up to Enforcement of Award)
A.
1 Filing of Request for Arbitration (RFA) (Hearing up to Enforcement
* Payment of Filing Fee (100%), Administrative Fee (100%), Arbitrator’s of Award)
Fee (25%), & Special Assessment Fee or ADF (100%) With Hearing Without Hearing
ARBITRATION PROPER
7a 7c 7b
Maximum of 3 Days
Hearings Filing of additional
2 Notice to Respondent Maximum of 10 Days Pleadings, Documents,
Evidences, Memoranda
8a
Maximum of 15 Days
Submission of Final 8b
Memoranda / Draft Decisions
Answer to RFA * Payment of balance of Submission of Issues for
3a
3 * Payment by Respondent of same fees paid by Arbitrator’s Fees (25%) Resolution
Claimant in # 1 above based on counterclaims if Nomination of *Payment of balance of
any Arbitrator/s Arbitrator’s Fees (25%)
3b
Maximum
Replyofto15 Days Maximum of 30 Days
Counterclaim
(if any) 9 Maximum of 30 Days
Rendering of Award and
4 Appointment of Arbitrators Notice of Award to Parties
Acceptance of
Maximum of 15 Days Maximum of 5 Days
Maximum of 5 Days Appointment /
Disclosure/s Appeal to Court of
15 Days from Notice
Appeals / Supreme Court

5 Preliminary Conference 10
Issuance of Writ of Execution
Maximum of 5 Days

6 Finalization & Signing of Terms


of Reference (TOR)
* Payment of 50% Arbitrator’s
B
Fee

Prescribed Time from steps 1 – 6:1.77 months Maximum Time from steps 6 – 9:6 months