ALP-10 EDC V1 E NATO Logistics Program ILS PDF
ALP-10 EDC V1 E NATO Logistics Program ILS PDF
ALP-10
23 October 2017
Edvardas MAZEIKIS
Major General, LTUAF
Director, NATO Standardization Office
INTENTIONALLY BLANK
ALP-10
I Edition C Version 1
ALP-10
INTENTIONALLY BLANK
II Edition C Version 1
ALP-10
RECORD OF RESERVATIONS
Note: The reservations listed on this page include only those that were recorded at time of
promulgation and may not be complete. Refer to the NATO Standardization Document
Database for the complete list of existing reservations.
INTENTIONALLY BLANK
IV Edition C Version 1
ALP-10
Note: The reservations listed on this page include only those that were recorded at time of
promulgation and may not be complete. Refer to the NATO Standardization Document
Database for the complete list of existing reservations.
V Edition C Version 1
ALP-10
INTENTIONALLY BLANK
VI Edition C Version 1
ALP-10
TABLE OF CONTENTS
1. GENERAL........................................................................................................ 1
1.1 Aim ............................................................................................................... 1
1.2 Applicability .................................................................................................. 1
2. DEFINITIONS .................................................................................................. 1
3. POLICY AND PROCEDURES ......................................................................... 1
3.1 General ........................................................................................................ 1
3.2 Systems Engineering and Utilisation/Support Relationship .......................... 2
3.3 ILS Elements: ............................................................................................... 4
3.4 Life Cycle Cost (LCC)................................................................................... 7
4. PROGRAMME RESPONSIBILITIES AND ILS MANAGEMENT ...................... 8
4.1 General ........................................................................................................ 8
4.2 Organisation ................................................................................................. 8
5. IMPLEMENTATION ......................................................................................... 9
ANNEX A GLOSSARY OF TERMS ...................................................................... A-1
ANNEX B PHASED ARMAMENTS PROGRAMMING SYSTEM (PAPS) ............. B-1
ANNEX C INTEGRATED LOGISTICS SUPPORT CONSIDERATIONS IN THE
MULTINATIONAL ARMAMENT PROGRAMME ...................................................... C-1
ANNEX D INTEGRATED LOGISTICS SUPPORT CONSIDERATIONS IN THE
NON-DEVELOPMENTAL ACQUISITION PROCESS ............................................. D-1
ANNEX E ILS PLAN TEMPLATE ......................................................................... E-1
ANNEX F PROJECT MANAGEMENT ILS RESPONSIBILITIES ......................... F-1
INTENTIONALLY BLANK
1. GENERAL
1.1 Aim
The aim of this document is to provide general guidance on the policy, implementation
and responsibilities for the application of Integrated Logistics Support (ILS) in
multinational armament programmes within NATO.
1.2 Applicability
This guidance applies to armament programmes whereby two or more NATO nations
collectively manage the logistics support of the materiel solution/component, in the
form of one or more Systems-of-Interest (SOI), through its life cycle stages, as
described in the Handbook on the Phased Armaments Programming System (PAPS,
AAP-20) document. It includes commonly, co-operatively, multinationally, as well as
jointly funded armament programmes, and may also be applied to national armaments
programmes. While ILS can be applied to all armament programmes, the level of
implementation will be dependent on the degree of innovation and complexity of the
materiel solution, support environment, and the availability of resources such as
funding and specialized personnel.
2. DEFINITIONS
ILS is the management and technical process through which supportability and
logistics support considerations of materiel (hardware or software) solutions are
integrated from the early stages and throughout the life cycle of an armament
programme and by which all elements of logistics support are planned, acquired,
implemented, tested and provided in a timely and cost-effective manner.
3.1 General
1 Edition C Version 1
ALP-10
ILS is structured around the life cycle management model used in the Phased
Armaments Programming System (PAPS). The model portrays the total life span of a
system commencing with considerations in the Pre-Concept Stage and extending
through the Utilisation Stage to its eventual withdrawal in the Retirement Stage. The
stages and approval documents used in the PAPS are shown in Annex B.
The ILS process should begin at the Concept Stage of the life cycle of the armament
programme and continue for the life of the system. The primary objective of the ILS
programme should be to achieve the required system operational availability at
minimum life cycle cost. Early ILS activities should focus on designing desirable
support characteristics and on determining support requirements. Subsequent activity
focuses on equipment support requirement evaluation and preparation of provision of
support resources. The scope and level of detail should be tailored to meet specific
programme needs at each stage of the system life cycle. Annex C lists the ILS
considerations for each stage of an armaments programme.
The full ILS process, as described, would be applied in its entirety to a complex
armament programme involving the incorporation of new technologies, design
development, integration and manufacturing. However, not all armament programmes
proceed in perfect accordance with the “regular” stage life cycle model as described in
AAP-20, Section 3. Stages may be by-passed or deliberately conducted in parallel,
such as production of end items while sub-system continues to evolve. The ILS
process would apply in all cases, but some ILS activities may be undertaken out of
sequence or may not be appropriate to all programmes.
Some military needs can be satisfied by utilizing the Accelerated Fielding process that
is described in the PAPS, Chapter 4. The procurement of “off-the-shelf” items is one
such alternative and is the one that ALP-10 will highlight. Such acquisitions are referred
to as non-developmental items and are normally identified within the Concept Stage.
Therefore, the Development and Production Stages would not be carried out as
described in Annex C. ILS considerations for non-developmental items are described
in Annex D.
2 Edition C Version 1
ALP-10
Design and support decisions during system development and modification have the
greatest impact on performance, life cycle cost, and RAMST when accomplished early
in and throughout the systems engineering process.
One of the principal vehicles for achieving ILS objectives in this process is the Logistics
Support Analysis (LSA). LSA is a disciplined process which includes actions to define,
analyse, and quantify logistics support requirements, and to influence design for
supportability, throughout system development. It stresses simplicity and reduced
logistics requirements. The objective of an LSA is to enable optimum system
performance, continuity and availability to be achieved at minimum life cycle cost. The
LSA is conducted on an iterative basis throughout the acquisition cycle as studies,
trade-offs, service advice and test and evaluation lead to successive design
refinement. The LSA should be tailored to the level of complexity of the system to which
it is applied, as well as to the availability of resources within nations participating in the
armament programme. Any changes that affect the ILS elements may require the LSA
process to be performed again.
Information obtained from systems engineering sources is required to ensure that all
aspects of utilisation support are recognized and considered during the planning and
acquisition of the support elements (i.e. support equipment, repair parts, personnel and
training, facilities, communication, security, Information Technology (IT) framework,
supply and maintenance technical assistance, equipment and software publications).
During design within the Development Stage, the analysis is oriented toward assisting
the systems engineer in incorporating logistics requirements into equipment design.
This includes the incorporation in the design process of the key logistics-related design
objective, cost-effective supportability. The goal is to produce a system that meets
specifications and the operation and support of which is cost effective over its planned
life cycle.
As the armament programme progresses and designs mature to become stable, the
LSA process concentrates on providing detailed descriptions of specific resources
required to support a system throughout its Utilisation Stage by providing timely valid
data for all areas of ILS. This data is used to plan, acquire and position support
resources (personnel, funding and material) to ensure deployed systems meet their
availability requirements. During the later production and utilisation stages of the
armament programme field, feedback of operational use and maintenance data is used
3 Edition C Version 1
ALP-10
to review the continuing validity of the data to ensure that life cycle cost plans are being
realized.
Levels of repair
Repair times
System Reliability, Maintainability, Testability characteristics
Support equipment needs
Training
Manpower skills
Inter-service, organic and contractor mix of repair responsibility
Site activation
Certification (e.g. safety and security)
Establishment of maintenance programs using condition-based maintenance,
reliability-centered maintenance, and/or post production software support
4 Edition C Version 1
ALP-10
Supply Support ILS Element comprises all management actions, procedures, and
techniques necessary to determine requirements to acquire, catalogue, receive,
implement, store, transfer, issue and dispose of spares, repair parts, updates and
supplies. This includes initial provisioning for stock of spare parts and support, as
well as acquiring, distributing, updating and replenishing inventories in support of
supply chain management.
3.1.3 Personnel
Personnel ILS Element involves identifying, planning and supporting the availability
of qualified personnel required to operate, maintain, and support the system over its
life cycle.
The Support and Test Equipment ILS Element includes the identifying, planning and
ensuring the availability of equipment (fixed or mobile) required to support the
operation and maintenance of a system. Examples of support and test equipment
are: associated multi-use end items, maintenance equipment, tools, software support
and reporting environment, metrology and calibration equipment.
The aim of this ILS Element is to participate in the systems engineering process to
impact the design from the early stages throughout the life cycle, facilitating
supportability to maximize the availability, effectiveness and capability of the system.
5 Edition C Version 1
ALP-10
Technical information and data can be provided through various media to include
paper, fiche, graphics, video and digital. Data rights and data delivery, as well as use
of any proprietary data, should be addressed as part of this element and included in
the overall programme plan.
One of the most effective ways to collect, review, and analyse this data is through the
use of a resource planning software tool. This tool can be a data mine linking
technical information, financial information and supply information. The benefits for
the armament programme can be:
Tracking operational availability through the life of the equipment
Creating and monitoring performance criteria for the support of the equipment
Maintaining a real time configuration management, supply and maintenance
databases
Providing the capacity to assess engineering changes proposals, track
approved changes, with the inclusion of costing information
Providing end item tracking and asset visibility
Tracking and maintaining commonality with industry-supported engineering
activities
6 Edition C Version 1
ALP-10
The goals of LCC analysis are to (1) identify the comparative overall costs of alternative
means of attaining system performance and availability objectives, and achieving
production schedules; (2) estimate the cost impact of various designs and support
options; (3) refine cost estimate of the selected design as it progresses in the life cycle.
The use of LCC is most effective during the early stages of the life cycle. Typically, by
the end of the Concept Stage roughly 85 percent of the system’s LCC has been
committed by design and logistics choices made within or prior to this period.
Early in the life cycle, the LCC analysis concentrates on quantifying the cost
implications of selected design alternatives, which provide the desired level of
performance. ILS activities at that stage focus on designing supportability
characteristics into the system and evaluating the life cycle cost of hardware, software,
support requirements, and other related costs. In later stages, evaluations are oriented
7 Edition C Version 1
ALP-10
LSA can provide valuable data for inputs to logistics simulations, cost effectiveness
models, trade-offs studies and LCC analysis. LSA and LCC analysis interface
throughout the life of the system to ensure that all data changes generated by iterative
LSA actions are evaluated to assess their consequences on acquisition, operation and
support cost.
4.1 General
4.2 Organisation
8 Edition C Version 1
ALP-10
5. IMPLEMENTATION
The MOU(s) for the armament programme and the terms of reference (TOR) or
statement of work (SOW) for the conduct of activities in the respective life cycle stages
of the programme should recognise the general applicability of, and make reference to
this ILS guidance document.
9 Edition C Version 1
ALP-10
INTENTIONALLY BLANK
10 Edition C Version 1
ANNEX A TO
ALP-10
ILS Manager/Staff Officer - An individual responsible for the execution of ILS within a
project/programme management organization.
ILS Plan - The formal planning document for the integration of the activities concerned
with logistics support. It is kept current throughout the project life. It sets forth the
concept of operational support, provides a detailed ILS programme to fit with the overall
programme and results in the necessary ILS information required by decision making
bodies to make sound decisions in system development and production.
IT Infrastructure – All the hardware, software, network, facilities etc. that are required
to develop, test, deliver, monitor, control or support IT services. The term IT
infrastructure includes all of the Information Technology but not the associated people,
processes and documentation (ITIL v3).
Life Cycle Cost (LCC) – Consists of all direct costs plus indirect variable costs
associated with the Life Cycle stages of the System of Interest.
(b) Defining support requirements that are related optimally to design and to each
other.
(d) Providing the required support during the operational phase at minimum cost.
During the later production and the in-service phase LSA is conducted on a repetitive
basis in order to meet life cycle costs, readiness and supportability objectives.
Reliability – The ability of an item to perform a required function under stated conditions
for a specific period of time.
System Life Cycle - The period divided into stages, ranging from the first
considerations on the need for a system in the Pre-Concept Stage through the
Concept, Development, Production and Utilisation/Support Stages down to the
Retirement Stage.
Trade off (Analysis) - The determination of the optimum balance between system
characteristics (cost, schedule, performance and supportability).
INTENTIONALLY BLANK
PRE CONCEPT
TOR or MOU /
STAGE APPROVAL DOCUMENT
FOR CONECEPT STAGE
CONCEPT
PROGRAMME MOU /
STAGE APPROVAL DOCUMENT
FOR DEVELOPMENT STAGE
DEVELOPMENT
PROGRAMME MOU /
STAGE APPROVAL DOCUMENT
FOR PRODUCTION STAGE
PRODUCTION
PROGRAMME MOU /
STAGE APPROVAL DOCUMENT
FOR UTILISATION/SUPPORT STAGE
UTILISATION / SUPPORT
PROGRAMME MOU /
STAGE APPROVAL DOCUMENT
FOR RETIREMENT STAGE
RETIREMENT
INTENTIONALLY BLANK
The following are ILS considerations for each stage of the life-cycle of a multinational
armament programme. The grouping and listing of activities are not to be used as an
all inclusive checklist or model of the single correct approach to ILS activities, because
all programmes have unique materiel requirements and schedules. Therefore, the
activities described below are not necessarily complete and may differ for specific
armament programmes.
1. Pre-Concept Stage
2. Concept Stage
b) Estimate for each alternative the life-cycle costs and the gross
percentages of the total costs that will have to be allotted for operations
and support, in order to facilitate the participating nations’ understanding
of the operations and support costs involved.
d) For each alternative solution being evaluated, identify and take into
account potential logistics support, manpower and training requirements
or constraints. Draft an ILS Plan with milestones and costs for critical
requirements for each alternative.
h) For commonly funded projects, identify the ownership and territorial host
nation(s) of the SOI and the related support matters such as facilities and
personnel.
a) If not yet arranged for, establish a Joint Logistics Working Group in the
framework of the Project/Programme Steering Committee to coordinate
the policy aspects of the application of ILS in the project.
3. Development Stage
a) Verify by test and evaluation the attainment of the objectives for RAMST
and other logistics support parameters.
j) Ensure that the test and evaluation of the planned logistics support is
conducted and that operational objectives are met. This may be
demonstrated through a contractual utilisation reliability assessment.
4. Production Stage
Technical publications.
Tools and test equipment.
Initial provision of spares.
Software licences and support software licences.
Manpower and facilities required for equipping the first and
subsequent operational organization.
f) Update maintenance plans. Make sure, that the user is presented with
full briefings and explanations of the system and its peculiarities.
5. Utilisation Stage
d) Identify and develop RAMST and life cycle cost improvements in fielded
equipment and support systems.
6. Retirement Stage
The Retirement Stage is to demilitarize and dispose of the SOI at the end
of its useful life and remove related operational and support services.
Demilitarization and retirement requirements are addressed in the
preceding stages. Disposal should be carried out in a way that is in
accordance with all legal and regulatory requirements relating to safety,
security, and the environment. Environmental considerations are
particularly critical during retirement, as there may be international
treaties or other legal considerations requiring intensive management of
the system's demilitarization and retirement.
c) Ensure the ILS data and information for the SOI is archived, for possible
future use, in an appropriate manner.
INTENTIONALLY BLANK
The following are the two stages and associated ILS activities for non-developmental
acquisition, which replace the development and production stages of the life cycle
model.
1. Concept Stage
(d) Estimate, for each possible alternative, the life cycle costs and the gross
percentages of the total costs that will have to be allotted to operations
and support.
(e) Identify critical supportability test issues and include plans for contractor
compliance tests, preproduction tests and initial production tests.
(f) Complete actions relative to the deployment plan, personnel and training
requirements.
2. Acquisition/Deployment Phase
(d) Monitor, test and evaluation to ensure support deficiencies are identified
and corrected. Expedite correction of support deficiencies revealed by
initial using units.
Cover Page
Signature
Table of Contents
Update and Revision Log
1. General
1.1. Introduction
1.2. System Description
1.3. Program Management
1.4. Milestone Schedule
1.5. Applicable Documents
2. Supportability in the Acquisition Program
2.1. Operational and supportability requirements
2.2. Acquisition strategy
2.3. Performance based logistics
2.4. ILS/Supportability funding
2.5. Supportability Analysis strategy
2.6. Supportability T&E
3. ILS element plans
3.1. Maintenance Planning
3.2. Supply support
3.3. Personnel
3.4. Support and test equipment
3.5. Design influence/ interface
3.6. Technical information and data
3.7. Training and training support
3.8. Facilities and infrastructure
3.9. Packaging, handling, storage, and transportation
4. Supportability in fielding and operational life
4.1. Initial fielding
4.2. Program transition
4.3. Post production support
4.4. Post fielding support analysis
4.5. Disposal
1.2 System Description – Describe the overall materiel system including its
physical configuration and functional requirements. The ILS Plan may
include pictures, tables, charts, graphs, and so on.
1.5 Applicable Documents - List the applicable documents which can provide
additional information and guidance with regard to the acquisition program.
2.2.1 Support risks: Identify risk associated with system support alternatives. As a
minimum, the following areas should be addressed:
2.2.3 Source selection: Describe how ILS and supportability will be addressed in
the source selection process. Include any plans to consider estimated cost
of operation, maintenance, and support, in addition to anticipated
acquisition cost, when making the source selection evaluation.
2.3 Performance based logistics (PBL) – Discuss the PBL strategy and
implementation, to include the use of performance based contracts rather
than transaction based contracts.
2.6.1 Peculiar test requirements that are directly related to the ILS Plan.
2.6.2 Anticipated critical supportability issues and their impact on the support
planning.
2.6.3 Testing and evaluation necessary to assess actions taken to resolve critical
issues.
2.6.6 The interface between the LMI and the test data collection systems.
2.6.8 How completed test results will affect planned test actions, criteria,
requirements, and so forth.
2.6.10 Plans for the Logistics Demonstration (LD), verifying the LMI and
components of the system support package, draft/final equipment
publications, all test, measurement, and diagnostic equipment, the
maintenance allocation chart, the repair parts/special tool list, recovery
tools,etc. The LD should be accomplished as soon as feasible after a
representative engineering development unit/software release is available
(during military suitability or feasibility testing for Non Developmental Items
(NDI)). LD must be completed in a timely manner so that the source and
availability of the system support package components can be established
prior to the developmental and operational testing).
3. ILS element plans - Provide details on plans for each ILS element. The bulk of
the ILS Plan will be in this subsection which explains issues and requirements in
detail for each of the ILS elements. Each ILS element needs full consideration in
the ILS Plan. If the area is not applicable, provide supporting rationale. Each ILS
element will include consideration of the relevant personnel requirements and
constraints.
3.1.1. Describe the maintenance concept for the system including all levels of
maintenance. Identify tradeoffs to be performed and maintenance
considerations peculiar to the system.
3.1.2. Identify maintenance tasks required to sustain the end item at a defined
level of readiness, include all critical and high driver tasks. The LMI data
product format can be used to provide part of the maintenance planning
data.
3.1.4. Indicate strengths and weaknesses of each support alternative and the
effect of the support concept on the system design, acquisition and O&S
costs, and on affected ILS elements.
3.1.5. For systems being acquired for multi-national use, address the
feasibility and desirability of centralized repair and supply support by a
single nation, the predominant user in a geographical area or the one with
centralized support capability.
3.2.3. Include plans for reviewing and adjusting the usage and failure factors
based on SA/LMI, test data, and field experience data. Include support
planning not only for the end items being procured, but for any of the
following claimants receiving assets:
3.2.5. Describe method and type of supply support (for example, piece part,
assembly, module or fabrication concept of replacement of parts).
3.2.9. Identify requirements for basic sustainment material (BSM). BSM is the
material consumed in the operation, and will include, but not be limited to,
ammunition, POL, power sources (for example, batteries), data
processing paper and tapes, war reserve requirements, and other
consumable and bulk supplies. These requirements will include both
those for initial fielding and those projected for annual unit consumption
during peacetime (training) and wartime.
3.3. Personnel
3.3.3. Define coordination with all ILS functions, and use of LMI as data
source. Define data requirements.
3.3.4. Identify system safety and human factors constraints to help minimize
problems with the human interface during system operation,
maintenance, and transport. Include any system safety and hazard
assessment requirements and results as applicable.
Include the TMDE register and preferred items list for mandatory use of
specific items.
Define procedures for establishing TMDE requirements during SA.
Describe use of LMI for establishing materiel system unique support
equipment requirements by maintenance level.
Identify requirements for TMDE registration and acquisition approval.
Indicate direction to be given to the contractor regarding the use of
common TMDE, including requirements for calibration and calibration
support.
Identify calibration requirements of the system and its support
equipment.
3.5.1. Describe how ILS and Life Cycle Cost (LCC) will influence source
selection, system design, and acquisition decisions. Explain design
constraints related to ILS and any plans to ensure that ILS is fully
considered in design proposals and proposed engineering changes.
Describe the extent and nature of the ILS personnel participation in
design reviews and tradeoff studies. List and discuss any factors that
might influence design.
3.6.4. Identify actions, events, milestones, and schedules for preparation and
printing of final publications.
3.6.6. Describe plan for determining if a technical data package (TDP) will be
purchased, amount of data needed for example, no data or level 1
drawings for non-developmental items (NDI) with CLS versus level 3
drawings for organic maintenance/training), and what effect this will have
on the acquisition strategy and acquisition plan.
3.7.1. Describe how training and training device requirements will be met and
who is responsible for meeting those requirements. Include description of
Government and contractor responsibilities and of training T&E
procedures. Provide information on training constraints and target
audiences.
3.7.3. Describe plan for acquiring the required training and training devices.
3.8.1. Describe all facility requirements for the use, storage, testing, training,
maintenance, and disposal of the system of interest and its support
equipment.
3.8.5. Describe any new facilities requirements for personnel using, testing,
training, operating, and doing field and depot maintenance.
3.8.7. Describe any special security requirements for storage and use of
classified end items, components, manuals, data and information set, test
program set, etc. Include quantity and volume of materiel, security level
of materiel, and any electronic and INFOSEC countermeasures.
3.9.7. Verify PHS&T test requirements have been identified and included in
the test and evaluation master plan.
3.9.8. Identify special care required during PHS&T (that is, removal of
sensitive components, calibration, special PHS&T requirements during
repair and movement).
3.9.14. For systems being acquired for multiservice use, the following
apply:
Briefly describe planning for initial fielding and achieving initial operational
capability. Summarize the procedure and schedule for preparation of all materiel
fielding documentation. Provide information on how fielding will be implemented.
4.3.1. An initial post production support plan will be developed during the
early part of the Development stage. It will document resources and
management actions to ensure the sustainment of requirements and
logistic support at all levels following the cessation of the Production
stage for a system
4.3.2. A schedule for updating the PPS plan will be developed to ensure the
plan is maintained current. The PPS plan will be updated prior to the
production decision, at production phase-out, and at any other time a
significant change has occurred in the anticipated support timeframe.
4.5. Disposal
This portion of the ILS Plan is often neglected. It is important to plan for disposal
even though the system is expected to have a long service life. Although
salvage is of little economic concern, the potential environmental impact of
system components is the driver for the emphasis on disposal planning. And
disposal at any time during the life of a
system if a catastrophic failure or accident results in the need to scrap it.
The arrangements under which nations participate in one or more successive stages of
the life cycle of a jointly funded multinational armaments programme are set out in a
Memorandum of Understanding (MOU). This MOU contains arrangements for the
governmental organization which will be responsible for the implementation of the
memorandum. Prior to or starting with the Concept Stage the governmental organization
may consist of:
The Policy Committee, which makes its decisions unanimously and consists of
representatives from the participating nations, will be responsible for direction of the task
to be carried out. It will have authority over and issue directives to the head of the
Executive Body concerned. The Head of the Executive Body should have overall
responsibility for establishing and managing an ILS Plan that relates support to system
availability objectives, system design and acquisition, operations and support cost. That
person should be supported by the ILS Manager or staff officer to assist in executing ILS
responsibilities and to maintain a continuous interaction with the support community
throughout the acquisition process.
The Policy Committee should establish a Working Group on ILS responsible for co-
ordinating the policy aspects with respect to the policy aspects with respect to the
implementation of ILS in the project. The ILS Working Group will assist and advise the
ILS Manager in all activities, which will be carried out to develop, update and implement
the ILS Plan on behalf of participating nations. More specifically, members of the ILS
Working Group should be responsible for national staffing and co-ordination with other
Working Groups of all aspects of the ILS Plan prior to its implementation.
(b) The overall financial management of the budget of the executive body.
7. In the ILS process most elements represent functional areas which are
individually managed by technical specialists. The ILS Manager’s role should be to co-
ordinate and interface these functional areas to achieve integration of all ILS elements
into an ILS Plan. Thus, responsibilities of the ILS Manager or staff officer are intended to:
(a) Develop an ILS Plan and monitor its implementation, integrate schedules
and identify inter-relationships among ILS elements and design activities;
(c) Update the ILS Plan as the project/programme progresses through the
acquisition phases;
(d) Prepare ILS input for contractual documents and evaluate output of
contractor’s ILS organization;
(e) Coordinate all ILS efforts which influence equipment design from the
supportability viewpoint and monitor accomplishment;
(f) Maintain visibility of all essential ILS resource requirement assets, and the
extent to which budgeted resources are or will be available to meet these
asset requirements.
(h) Interface and coordinate logistic support activities with other NATO
organizations (e.g. NAMSA, NATO military commands, and national
organizations).
(i) Ensure an orderly, timely and efficient transfer of overall logistic support
responsibilities and know-how to the system user or in-service support
organization.
APPENDIX 1 to ANNEX F
Relationship of Organizations/Individuals Having ILS Reponsibilities
PROJECT
POLICY COMMITEE
WG WG WG
ON ON ON
…. …. ….
PROJECT MANAGER/
GENEREAL MANAGER/
PROJECT TEAM LEADER
INDUSTRY
PRIME CONTACTOR
INTERNATIONAL CONSORTUIM
JOINT VENTURE
ETC.