SATIP Q 006 02 (Recovered)

This document outlines Saudi Aramco's typical inspection plan for the Hawiyah and Haradh Development Satellite Gas Compression project. It details inspection responsibilities and quality procedures for project phases including document review, receiving inspection, installation, and pre-commissioning. Saudi Aramco inspectors are responsible for reviewing and approving documents, witnessing tests, and surveillance. The contractor is responsible for inspection, testing, and submitting documents for review. The inspection plan specifies hold points, witness points, and surveillance levels for quality assurance.

Uploaded by

Abdul Hannan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views

SATIP Q 006 02 (Recovered)

This document outlines Saudi Aramco's typical inspection plan for the Hawiyah and Haradh Development Satellite Gas Compression project. It details inspection responsibilities and quality procedures for project phases including document review, receiving inspection, installation, and pre-commissioning. Saudi Aramco inspectors are responsible for reviewing and approving documents, witnessing tests, and surveillance. The contractor is responsible for inspection, testing, and submitting documents for review. The inspection plan specifies hold points, witness points, and surveillance levels for quality assurance.

Uploaded by

Abdul Hannan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 10

SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016) Rev. 2016.06.

00 30-Jun-16
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Conventional & Sulfur Extended Asphalt Paving SATIP-Q-006-02 15-Nov-17 MAH-SA-RFI-C-
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

HAWIYAH AND HARADH DEVELOPMENT SATELLITE GAS COMPRESSION 10 - 01996 / 0007 MOFARREH AL-HARBI & PARTNERS
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Aggregate Subbase and Base Course


Contractor - "RH" of Documents and "H" for Material Sampling and Testing.
1.1 Materials Sampling, Testing & Review SAIC-Q-1035 SAIC-Q-1035 RH/H RH/W SAUDI ARAMCO - "RH" of Documents and "W" for Material Sampling and Testing.
of Test Reports
Raw Materials Sampling, Testing and Contractor - "RH" of Documents and "H" for Material Sampling and Testing.
1.2
Asphalt Mix Design Review
SAIC-Q-1036 SAIC-Q-1036 RH/H RH/W SAUDI ARAMCO - "RH" of Documents and "W" for Material Sampling and Testing.
2.0 RECEIVING INSPECTION
Subbase and Aggregate Base Course SAUDI ARAMCO - Witness delivery of subbase and aggregate base materials for
2.1
Material Receiving Inspection
SAIC-Q-1037 SAIC-Q-1037 W S the first 2 delivery days, and once every 3 delivery days thereafter.
3.0 INSTALLATION
Grades, Elevation and Surface
3.1
Preparation Inspection
SAIC-Q-1039 SAIC-Q-1039 W W
Foamed Asphalt Stabilization
3.2 Refer to SATIP-Q-006-03 for Foamed Asphalt Stabilization
Inspection (If Required)
Placement and Compaction of
3.3 Subbase and Aggregate Base Course SAIC-Q-1040 SAIC-Q-1040 W S
Inspection
3.4 Compaction Testing SAIC-A-1005 SAIC-A-1005 W W
Prime Coating and Tack Coating
3.5
Inspection
SAIC-Q-1041 SAIC-Q-1041 H W
Conventional Asphalt & Sulfur
Contractor - "H" for Material Sampling and Testing.
3.6 Extended Asphalt Concrete Receiving, SAIC-Q-1061 SAIC-Q-1061 H W SAUDI ARAMCO - "W" for Material Sampling and Testing .
Placement and Testing Inspection

Contractor - "H" for Material Sampling and Testing.


3.7 Asphalt Core Density Testing SAIC-Q-1043 SAIC-Q-1043 H W SAUDI ARAMCO - "W" for Material Sampling and Testing .

3.8 Asphalt Paving Final Inspection SAIC-Q-1044 SAIC-Q-1044 W W


4.0 PRE-COMMISSIONING
4.1 N/A

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels of Saudi Aramco
1 participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization

3 Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is not present.

4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016) Rev. 2016.06.00 30-Jun-16
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Conventional & Sulfur Extended Asphalt Paving SATIP-Q-006-02 15-Nov-17 MAH-SA-RFI-C-
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

HAWIYAH AND HARADH DEVELOPMENT SATELLITE GAS COMPRESSION 10 - 01996 / 0007 MOFARREH AL-HARBI & PARTNERS
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection/Test
SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016)

Saudi Aramco: Company General Use


Rev. 2016.06.00

###

Saudi Aramco: Company General Use


30-Jun-16

Saudi Aramco: Company General Use


### ###

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016)