CG Analysis-2015
CG Analysis-2015
1 Excavation for all types and sizes of foundations, trenches and drains or for any other purpose including disposal of
excavated stuff upto 1.5 m lift and lead upto 50m (at least 5m away from the excavated area), including dressing and
leveling of pits.
0017 Hire and running charges of pneumatic cutters/ 800.00 day 0.5 day 400.00
hammers with operator.
Labour-
0115 Rock Excavator 190.00 day 0.7 day 133.00
0116 Rock Breaker 190.00 day 1.6 day 304.00
0123 Rock driller 190.00 day 0.35 day 66.50
0114 Beldar 190.00 day 2 day 380.00
TOTAL 2308.50
Add 5 % for water, electricity, sundries and other 115.43
overhead charges
TOTAL 2423.93
Add 10 % for contractor's profit 242.39
Cost of 10 cum. 2666.32
Cost of 1 cum. 266.63
Say 267.00
0017 Hire and running charges of pneumatic cutters/ 800.00 day 0.75 day 600.00
hammers with operator.
TOTAL 3923.00
Add 5 % for water, electricity, sundries and other 196.15
overhead charges
TOTAL 4119.15
Add 10 % for contractor's profit 411.92
Cost of 10 cum. 4531.07
Cost of 1 cum. 453.10
Say 453.00
1.1 Excavation for all types and sizes of foundations, trenches and drains or for any other purpose including disposal of
excavated stuff upto 1.5 m lift and lead upto 50m (at least 5m away from the excavated area), including dressing and
leveling of pits.
0017 Hire and running charges of pneumatic cutters/ 800.00 day 3.5 day 2800.00
hammers with operator.
Labour-
0114 Beldar 190.00 day 2 day 380.00
TOTAL 6905.00
Add 5 % for water, electricity, sundries and other 345.25
overhead charges
TOTAL 7250.25
0010 Hire charges of Pumpset of capacity 4000 500.00 day 0.625 day 312.50
litres/hour.
3502 Diesel oil 56.87 litre 10 litre 568.70
0114 Beldar 190.00 day 2 day 380.00
TOTAL 1261.20
Add 5 % for water, electricity, sundries and other 63.06
overhead charges
TOTAL 1324.26
Add 10 % for contractor's profit 132.43
Cost of 10 cum 1456.69
Cost of 1 cum 145.66
Say 146.00
1.11 Open timbering in foundation trenches including strutting and shoring complete (measurements to be taken of the
face area timbered.)
1.11.1 Depth not exceeding 1.5 M.
Code Description Rate Unit Qty Total
MATERIALS:
The Material can be used eight times on the same
work, the effective area = 8x90 = 720 sqm
MATERIALAS
2806 Sal, bija, Haldu wood in planks 48000.00 cum 1.14 cum 54720.00
Poling board 1.5mx0.25xx0.038m :
2x40x1.5x0.25x0.038 = 1.14cum = 1140 dm³
2804 Sal, bija, Haldu wood in scantling 48500.00 cum 1.2 cum 58200.00
Walling 100mmx100mm : 4x30mx0.1mx0.1m =
1.20cum = 1200 dm³
2815 Nilgiri ballies 125 mm diameter 42.00 metre 51 metre 2142.00
Safeda Ballies struts (125mm dia. And 1.5m long)-
2x17x1.50 = 51m
2814 Less Credit for unserviseable wood 2000.00 cum -2.96 cum -5920.00
2466 Wire nails 52.00 kg 0.5 kg 26.00
LABOUR :
0106 Carpenter 2nd class 197.00 day 2 day 394.00
0114 Beldar 190.00 day 8 day 1520.00
TOTAL 111082.00
Add 5 % for water, electricity, sundries and other 5554.10
overhead charges
TOTAL 116636.10
Add 10 % for contractor's profit 11663.61
Cost of 720 Sqm 128299.71
Cost per sqm. 178.19
Say 178.00
1.11 Open timbering in foundation trenches including strutting and shoring complete (measurements to be taken of the
face area timbered.)
1.11.2 Depth exceeding 1.5 M. but not exceeding 3 M.
Code Description Rate Unit Qty Total
Details of cost for a trench of length 30m and
1.50m deep surface area - 2x30x1.5 = 90 sqm.
MATERIALS:
The Material can be used eight times on the same
work, the effective area = 8x90 = 720 sqm
MATERIALAS
2806 Sal, bija, Haldu wood in planks 48000.00 cum 1.14 cum 54720.00
Poling board 1.5mx0.25xx0.038m :
2x40x1.5x0.25x0.038 = 1.14cum = 1140 dm³
2804 Sal, bija, Haldu wood in scantling 48500.00 cum 1.2 cum 58200.00
Walling 100mmx100mm : 4x30mx0.1mx0.1m =
1.20cum = 1200 dm³
2815 Nilgiri ballies 125 mm diameter 42.00 metre 51 metre 2142.00
Safeda Ballies struts (125mm dia. And 1.5m long)-
2x17x1.50 = 51m
MATERIALS:
The Material can be used eight times on the same
work, the effective area = 8x90 = 720 sqm
MATERIALAS
2806 Sal, bija, Haldu wood in planks 48000.00 cum 1.14 cum 54720.00
Poling board 1.5mx0.25xx0.038m :
2x40x1.5x0.25x0.038 = 1.14cum = 1140 dm³
2804 Sal, bija, Haldu wood in scantling 48500.00 cum 1.2 cum 58200.00
Walling 100mmx100mm : 4x30mx0.1mx0.1m =
1.20cum = 1200 dm³
2815 Nilgiri ballies 125 mm diameter 42.00 metre 51 metre 2142.00
Safeda Ballies struts (125mm dia. And 1.5m long)-
2x17x1.50 = 51m
2814 Less Credit for unserviseable wood 2000.00 cum -2.96 cum -5920.00
2466 Wire nails 52.00 kg 0.5 kg 26.00
LABOUR :
0106 Carpenter 2nd class 197.00 day 8 day 1576.00
0114 Beldar 190.00 day 24 day 4560.00
TOTAL 115304.00
Add 5 % for water, electricity, sundries and other 5765.20
overhead charges
TOTAL 121069.20
Add 10 % for contractor's profit 12106.92
Cost of 720 Sqm 133176.12
Cost per sqm. 184.96
Say 185.00
1.12 Open timbering in case of shaft, wells cesspit, manholes and like, including strutting, shoring etc. complete
(measurements to be taken of face are timbered)
MATERIALS :
2806 Sal, bija, Haldu wood in planks 48000.00 cum 0.086 cum 4128.00
Polling boards 250mm wide and 38mm thick :
6x0.25x1.5x0.038 = 0.086 cum = 86dm³
2804 Sal, bija, Haldu wood in scantling 48500.00 cum 0.048 cum 2328.00
Walling 100mmx100mm
4x1.2x0.1x0.1 = 0.048 cum = 48 dm³
2815 Nilgiri ballies 125 mm diameter 42.00 metre 6.4 metre 268.80
(4x1.0=4.0)+(2x1.2=2.4) = 6.4m
2466 Wire nails 52.00 kg 0.1 kg 5.20
2814 Less Credit for unserviseable wood 2000.00 cum -0.134 cum -268.00
LABOUR :
0106 Carpenter 2nd class 197.00 day 0.5 day 98.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 6750.50
Add 5 % for water, electricity, sundries and other 337.53
overhead charges
TOTAL 7088.03
Add 10 % for contractor's profit 708.80
Cost of 52.8 sqm. 7796.83
Cost per sqm. 147.66
Say 148.00
1.12 Open timbering in case of shaft, wells cesspit, manholes and like, including strutting, shoring etc. complete
(measurements to be taken of face are timbered)
1.12.2 Depth exceeding 1.5 M. but not exceeding 3 M.
Code Description Rate Unit Qty Total
Details of cost for a manhole 1.2x 1m x 1.5m -
Surface area 2(1.2+1.0)x1.5 = 6.6 sqm
MATERIALS :
2806 Sal, bija, Haldu wood in planks 48000.00 cum 0.086 cum 4128.00
Polling boards 250mm wide and 38mm thick :
6x0.25x1.5x0.038 = 0.086 cum = 86dm³
2804 Sal, bija, Haldu wood in scantling 48500.00 cum 0.048 cum 2328.00
Walling 100mmx100mm
4x1.2x0.1x0.1 = 0.048 cum = 48 dm³
2815 Nilgiri ballies 125 mm diameter 42.00 metre 6.4 metre 268.80
MATERIALS :
2806 Sal, bija, Haldu wood in planks 48000.00 cum 0.086 cum 4128.00
Polling boards 250mm wide and 38mm thick :
6x0.25x1.5x0.038 = 0.086 cum = 86dm³
2804 Sal, bija, Haldu wood in scantling 48500.00 cum 0.048 cum 2328.00
Walling 100mmx100mm
4x1.2x0.1x0.1 = 0.048 cum = 48 dm³
2815 Nilgiri ballies 125 mm diameter 42.00 metre 6.4 metre 268.80
(4x1.0=4.0)+(2x1.2=2.4) = 6.4m
2466 Wire nails 52.00 kg 0.1 kg 5.20
2814 Less Credit for unserviseable wood 2000.00 cum -0.134 cum -268.00
LABOUR :
0106 Carpenter 2nd class 197.00 day 3 day 591.00
0114 Beldar 190.00 day 6 day 1140.00
TOTAL 8193.00
Add 5 % for water, electricity, sundries and other 409.65
overhead charges
TOTAL 8602.65
Add 10 % for contractor's profit 860.27
Cost of 52.8 sqm. 9462.92
Cost per sqm. 179.22
Say 179.00
1.13 Extra for planking and strutting in open timbering if required to be left permanently in position (Face to face area of
the timber permanently left to be measured).
2804 Sal, bija, Haldu wood in scantling 48500.00 cum 1.05 cum 50925.00
Walling 100mmx100mm : 4x30mx0.1mx0.1m =
1.20cum = 1200 dm³_x000D_
(Rate per II class kail wood in scantling)
2815 Nilgiri ballies 125 mm diameter 42.00 metre 44.63 metre 1874.46
Safeda Ballies struts (125mm dia. And 1.5m long)-
2x17x1.5 = 51m
Less @ 1/8 of Qty as timber is supposed to be used
once before = 51 - 6.37 = 44.63 m
TOTAL 100679.46
Add 5 % for water, electricity, sundries and other 5033.97
overhead charges
TOTAL 105713.43
Add 10 % for contractor's profit 10571.34
Cost of 90 sqm. 116284.77
Cost per sqm. 1292.05
Say 1292.00
1.14 Close timbering in foundation trenches including strutting, shoring and packing cavities where ever required
complete (Measurement to be taken of the face area timbered).
1.14.1 Depth not exceeding 1.5 M.
Code Description Rate Unit Qty Total
Details of cost for a trench 30m long and 1.5m
deep area 2x30x1.5=90 sqm-
The Material can be used eight times on the same
work so the effective area = 8x90 = 720 sqm
MATERIALS
2806 Sal, bija, Haldu wood in planks 48000.00 cum 3.42 cum 164160.00
Poling boards of 2nd class Kail wood planks :
90x0.038 = 3.42 cum
2804 Sal, bija, Haldu wood in scantling 48500.00 cum 1.2 cum 58200.00
Walings 100mmx100mm of 2nd class kail wood in
scantling: 4x30x0.10x0.10 = 1.20cum
MATERIALS
2806 Sal, bija, Haldu wood in planks 48000.00 cum 3.42 cum 164160.00
Poling boards of 2nd class Kail wood planks :
90x0.038 = 3.42 cum
2804 Sal, bija, Haldu wood in scantling 48500.00 cum 1.2 cum 58200.00
Walings 100mmx100mm of 2nd class kail wood in
scantling: 4x30x0.10x0.10 = 1.20cum
MATERIALS
2806 Sal, bija, Haldu wood in planks 48000.00 cum 3.42 cum 164160.00
Poling boards of 2nd class Kail wood planks :
90x0.038 = 3.42 cum
2804 Sal, bija, Haldu wood in scantling 48500.00 cum 1.2 cum 58200.00
Walings 100mmx100mm of 2nd class kail wood in
scantling: 4x30x0.10x0.10 = 1.20cum
MATERIALS
2806 Sal, bija, Haldu wood in planks 48000.00 cum 0.251 cum 12048.00
Poling boards of 2nd class Kail wood planks:
6.6x0.038 = 0.251 cum
2804 Sal, bija, Haldu wood in scantling 48500.00 cum 0.082 cum 3977.00
Walling of 2nd class kail wood scantling
2x2x1.124x0.1x0.1 = 0.045 cum
2x2x0.924x0.1x0.1 = 0.037 cum.
Total Kail wood = 0.082 cum.
2815 Nilgiri ballies 125 mm diameter 42.00 metre 6.592 metre 276.86
2x2x0.924 = 3.696
2x2x0.724 = 2.896
Total of balli = 6.592m
2466 Wire nails 52.00 kg 0.1 kg 5.20
2814 Less Credit for unserviseable wood 2000.00 cum -0.338 cum -676.00
LABOUR :
0106 Carpenter 2nd class 197.00 day 2 day 394.00
0114 Beldar 190.00 day 4 day 760.00
TOTAL 16785.06
Add 5 % for water, electricity, sundries and other 839.25
overhead charges
TOTAL 17624.31
Add 10 % for contractor's profit 1762.43
Cost of 52.80 sqm. 19386.74
Cost per sqm. 367.17
Say 367.00
1.15 Close timbering in case of shaft, walls, cesspit, manholes and like including strutting shoring and packing cavities
(wherever required complete measurement to be taken of the face area timbered).
1.15.2 Depth exceeding 1.5 M. but not exceeding 3 M.
Code Description Rate Unit Qty Total
Details of cost for a manhole 1.2m x 1.0m x1.5m-
Surface area: 2x(1.2+1.0)x1.5 = 6.6sqm
MATERIALS
2806 Sal, bija, Haldu wood in planks 48000.00 cum 0.251 cum 12048.00
Poling boards of 2nd class Kail wood planks:
6.6x0.038 = 0.251 cum
2804 Sal, bija, Haldu wood in scantling 48500.00 cum 0.082 cum 3977.00
Walling of 2nd class kail wood scantling
2x2x1.124x0.1x0.1 = 0.045 cum
2x2x0.924x0.1x0.1 = 0.037 cum.
Total Kail wood = 0.082 cum.
2815 Nilgiri ballies 125 mm diameter 42.00 metre 6.592 metre 276.86
Safeda Balli struts (12.5mm dia and 1.5m long)
2x2x0.924 = 3.696
2x2x0.724 = 2.896
Total of balli = 6.592m
2466 Wire nails 52.00 kg 0.1 kg 5.20
2814 Less Credit for unserviseable wood 2000.00 cum -0.338 cum -676.00
LABOUR :
0106 Carpenter 2nd class 197.00 day 4 day 788.00
0114 Beldar 190.00 day 8 day 1520.00
TOTAL 17939.06
MATERIALS
2806 Sal, bija, Haldu wood in planks 48000.00 cum 0.251 cum 12048.00
Poling boards of 2nd class Kail wood planks:
6.6x0.038 = 0.251 cum
2804 Sal, bija, Haldu wood in scantling 48500.00 cum 0.082 cum 3977.00
Walling of 2nd class kail wood scantling
2x2x1.124x0.1x0.1 = 0.045 cum
2x2x0.924x0.1x0.1 = 0.037 cum.
Total Kail wood = 0.082 cum.
2815 Nilgiri ballies 125 mm diameter 42.00 metre 6.592 metre 276.86
Safeda Balli struts (12.5mm dia and 1.5m long)
2x2x0.924 = 3.696
2x2x0.724 = 2.896
Total of balli = 6.592m
2466 Wire nails 52.00 kg 0.1 kg 5.20
2814 Less Credit for unserviseable wood 2000.00 cum -0.338 cum -676.00
LABOUR :
0106 Carpenter 2nd class 197.00 day 6 day 1182.00
0114 Beldar 190.00 day 12 day 2280.00
TOTAL 19093.06
Add 5 % for water, electricity, sundries and other 954.65
overhead charges
TOTAL 20047.71
Add 10 % for contractor's profit 2004.77
Cost of 52.80 sqm. 22052.48
Cost per sqm. 417.66
Say 418.00
1.16 Extra for planking, strutting and packing materials for cavities in close timbering if required to be left permanently in
position (face area of the timber permanently left, to be measured).
Code Description Rate Unit Qty Total
Details of cost for a trench 30m long and 1.5m
deep area 2x30x1.5=90 sqm-
MATERIALS
2806 Sal, bija, Haldu wood in planks 48000.00 cum 2.9925 cum 143640.00
Poling boards of 2nd class Kail wood planks :
90x0.038 = 3.42 cum = 3420 dm³
Less @ 1/8 of Qty as timber is supposed to be used
once before = 3.420 - 0.427.5 = 2.9925 m ³
2804 Sal, bija, Haldu wood in scantling 48500.00 cum 1.05 cum 50925.00
Walings 100mmx100mm of 2nd class kail wood in
scantling: 4x30x0.10x0.10 = 1.20cum = 1200 dm³
2815 Nilgiri ballies 125 mm diameter 42.00 metre 44.63 metre 1874.46
Safeda Balli struts (12.5mm dia and 1.5m long):
2x17x1.5 = 51m
Less @ 1/8 of Qty as timber is supposed to be used
once before = 51 - 6.37 = 44.63 m
TOTAL 196439.46
Add 5 % for water, electricity, sundries and other 9821.97
overhead charges
TOTAL 206261.43
Add 10 % for contractor's profit 20626.14
Cost of 90 Sqm. 226887.57
Cost per sqm. 2520.97
Say 2521.00
1.17 Filling from available excavated stuff (Excluding rock) in trenches, plinth, sides of foundation etc. in layers not
exceeding 20cm in depth consolidating each deposited layer by ramming and watering with a lead upto 50 M. and
lift upto 1.5 M.
0030 Hire charges of Chemical sprayer 25.00 day 0.1 day 2.50
Labour-
0120 Mate 197.00 day 0.1 day 19.70
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 128.67
Add 5 % for water, electricity, sundries and other 6.43
overhead charges
TOTAL 135.10
Add 10 % for contractor's profit 13.51
Cost of 10 metres 148.61
Cost of 1 metre 14.86
Say 15.00
1.23 Diluting chemical emulsion (chlorpyrifos/ lindane) in water as per manufacturers recommendation and injecting for
post - constructional ani-termite treatment (excluding cost of chemical emulsion):
1.23.3 Treatment of masonry wall/ soil under existing floors using diluted chemical emulsion @ one litre per hole,
including drilling 12 mm diameter holes at the junction of floor and walls along the cracks on the floor at the
interval of 300 mm and plugging with cement mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor :
0030 Hire charges of Chemical sprayer 25.00 day 0.1 day 2.50
Labour-
0120 Mate 197.00 day 0.1 day 19.70
0114 Beldar 190.00 day 0.12 day 22.80
TOTAL 92.31
Add 5 % for water, electricity, sundries and other 4.62
overhead charges
TOTAL 96.93
Add 10 % for contractor's profit 9.69
Cost of 10 metres 106.62
0030 Hire charges of Chemical sprayer 25.00 day 0.12 day 3.00
Labour-
0120 Mate 197.00 day 0.15 day 29.55
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 1025.05
Add 5 % for water, electricity, sundries and other 51.25
overhead charges
TOTAL 1076.30
Add 10 % for contractor's profit 107.63
Cost of 10 metres 1183.93
Cost of 1 metre 118.39
Say 118.00
1.25 Diluting chemical emulsion (chlorpyrifos/ lindane) in water as per manufacturers recommendation and injecting for
pre-constructional curative cum preventive anti-termite treatment:(Five year service guarantee bond to be signed
by contractor)
1.25.1 Surface treatment by spreading emulsion under floor, over the plinth area before laying base concrete @ 5 litres /
sqm
Code Description Rate Unit Qty Total
Details of cost for 10 sqm
MACHINERY
0030 Hire charges of Chemical sprayer 25.00 day 0.3 day 7.50
Labour-
0120 Mate 197.00 day 0.3 day 59.10
0114 Beldar 190.00 day 0.9 day 171.00
TOTAL 237.60
Add 5 % for water, electricity, sundries and other 11.88
overhead charges
TOTAL 249.48
Add 10 % for contractor's profit 24.95
Cost of 10 sqm 274.43
Cost of 1 sqm 27.44
Say 27.50
1.25 Diluting chemical emulsion (chlorpyrifos/ lindane) in water as per manufacturers recommendation and injecting for
pre-constructional curative cum preventive anti-termite treatment:(Five year service guarantee bond to be signed
by contractor)
0030 Hire charges of Chemical sprayer 25.00 day 0.12 day 3.00
Labour-
0120 Mate 197.00 day 0.12 day 23.64
0114 Beldar 190.00 day 0.24 day 45.60
TOTAL 162.86
Add 5 % for water, electricity, sundries and other 8.14
overhead charges
TOTAL 171.00
Add 10 % for contractor's profit 17.10
Cost of 10 metres 188.10
Cost of 1 metre 18.81
Say 19.00
1.25 Diluting chemical emulsion (chlorpyrifos/ lindane) in water as per manufacturers recommendation and injecting for
pre-constructional curative cum preventive anti-termite treatment:(Five year service guarantee bond to be signed
by contractor)
1.25.3 Treatment of outer side of plinth masonry wall using diluted chemical emulsion @ 1.5 litre per hole, including
drilling 12 mm diameter holes in plinth wall at the junction of floor at the interval of 300 mm and plugging with
cement mortar 1 :2 (1 cement : 2 Coarse sand).
0030 Hire charges of Chemical sprayer 25.00 day 0.08 day 2.00
Labour-
0120 Mate 197.00 day 0.08 day 15.76
0114 Beldar 190.00 day 0.16 day 30.40
TOTAL 115.63
Add 5 % for water, electricity, sundries and other 5.78
overhead charges
TOTAL 121.41
Add 10 % for contractor's profit 12.14
Cost of 10 metres 133.55
Cost of 1 metre 13.35
Say 13.50
1.26 Carriage by mechanical transport upto 5 km lead:
1.26.1 Earth
Code Description Rate Unit Qty Total
MACHINERY
0004 Hire and running charges of tipper 1700.00 day 1 day 1700.00
3502 Diesel oil 56.87 litre 28 litre 1592.36
3504 Mobil oil 182.00 litre 1 litre 182.00
TOTAL 3474.36
Add 5 % for water, electricity, sundries and other 173.72
overhead charges
TOTAL 3648.08
Add 10 % for contractor's profit 364.81
Cost of 448 cum km 4012.89
Cost of 1 cum for 1 km 8.95
Say 9.00
1.27 Extra for mechanical transport for every one km or part thereof beyond first 5 km lead.
1.27.2 Sludge
Code Description Rate Unit Qty Total
Details of cost for 8 cum x 140 km (Taking capacity
of truck 8 cum and run in one day as 140 Km in 3
trips Net Qty = 8 x 140/2 =448 cum km
MACHINERY
0004 Hire and running charges of tipper 1700.00 day 1 day 1700.00
3502 Diesel oil 56.87 litre 28 litre 1592.36
3504 Mobil oil 182.00 litre 1 litre 182.00
TOTAL 3474.36
Add 5 % for water, electricity, sundries and other 173.72
overhead charges
TOTAL 3648.08
Add 10 % for contractor's profit 364.81
MACHINERY
0004 Hire and running charges of tipper 1700.00 day 1 day 1700.00
3502 Diesel oil 56.87 litre 28 litre 1592.36
3504 Mobil oil 182.00 litre 1 litre 182.00
TOTAL 3474.36
Add 5 % for water, electricity, sundries and other 173.72
overhead charges
TOTAL 3648.08
Add 10 % for contractor's profit 364.81
Cost of 448 cum km 4012.89
Cost of 1 cum for 1 km 8.95
Say 9.00
Materials :
0232 Wall form panel 1250x500 mm 1050.00 each 0.34 each 357.00
Qty taken for cost of using once =_x000D_
16x0.85/40 = 0.34
0237 Corner angle 45x45x5 mm 1.50 m long 300.00 each 0.085 each 25.50
Qty taken for cost of using once =_x000D_
4x0.85/40 = 0.085
0238 100 mm channel shoulder 2.5 m long 1160.00 each 0.17 each 197.20
Qty taken for cost of using once =_x000D_
8x0.85/40 = 0.17
0223 Double clip ( bridge clip) 97.00 each 0.34 each 32.98
Qty taken for cost of using once =_x000D_
16x0.85/40 = 0.34
0224 Single clip 77.00 each 0.17 each 13.09
Qty taken for cost of using once =_x000D_
8x0.85/40 = 0.17
1042 M.S. tube 40 mm dia 294.00 metre 0.2295 metre 67.47
Qty taken for cost of using once =_x000D_
10.8x0.85/40 = 0.2295
2467 Seam bolts and nuts 6 mm dia and 25 mm long 3.50 each 10 each 35.00
Materials :
0232 Wall form panel 1250x500 mm 1050.00 each 0.51 each 535.50
2x3x2x2 = 24Nos._x000D_
Qty taken for cost of using once = 24x_x000D_
0.85/40 = 0.51
0238 100 mm channel shoulder 2.5 m long 1160.00 each 0.17 each 197.20
4x2 = 8_x000D_
Qty taken for cost of using once =_x000D_
8x0.85/40 = 0.17
0223 Double clip ( bridge clip) 97.00 each 0.51 each 49.47
2x6x2 = 24_x000D_
Qty taken for cost of using once =_x000D_
24x0.85/40 = 0.51
2467 Seam bolts and nuts 6 mm dia and 25 mm long 3.50 each 12 each 42.00
Cubical contents
MATERIAL
1. Steel plates for side and bottom (plate size 1.50 x
0.30m)
Angle 40x40x5mm
2x1.50 = 3.00 m
3x0.30 = 0.9 m
Total = 3.90 m @ 3.00 kg/m = 11.70 kg
sheet 1.6 mm thick
1.50m x 0.30 m = 0.45 sqm @ 12.55 kg/sqm. =
5.65 kg.
Weight of one plate = 16.94 kg.
Weight of 3 plates = 50.82 kg.
9.1 Steel work Single section (Rate as per Item No 9.1) 61.46 kg 50.82 kg 3123.40
0229 Beam clamp 300-380 mm (450-1070 mm) 422.00 set 2 set 844.00
2467 Seam bolts and nuts 6 mm dia and 25 mm long 3.50 each 2.5 each 8.75
TOTAL 10723.56
Add 10 % for contractor's profit on all except (A) 760.02
i.e. on (10723.56 - 3123.40) = 7600.16
Horizontal 2x4x0.075x0.1x0.5=0.030
Horizontal 2x4x0.075x0.1x1.5=0.090
(iii) Vertical battens
16x0.15x0.075x0.030m = 0.0054
(iv) Struts
16x0.25x0.075x0.075=0.0225
Total = 0.1479
Wastage @5% = 0.0074
Total = 0.1553 cum
2816 Any local wood for shuttering in scantling 24500.00 cum 0.1553 cum 3804.85
Salvage value of timber
Planks = 0.057 cum.
Battens = 0.155 cum.
Total = 0.212 cum.
2814 Less Credit for unserviseable wood 2000.00 cum -0.212 cum -424.00
LABOUR
For assembling erection dismantling & cleaning.
Materials :
0232 Wall form panel 1250x500 mm 1050.00 each 0.17 each 178.50
Qty taken for cost of using once =_x000D_
8x0.85/40 = 0.17
0237 Corner angle 45x45x5 mm 1.50 m long 300.00 each 0.085 each 25.50
Qty taken for cost of using once =_x000D_
4x0.85/40 = 0.085
0225 Column clamp 450x1070 m 1220.00 each 0.1063 each 129.69
Qty taken for cost of using once =
5x0.85/40_x000D_
=0.1063
0226 Prop 2 m (2-3.5m) 830.00 each 0.085 each 70.55
Qty taken for cost of using once =
4x0.85/40_x000D_
=0.085
2467 Seam bolts and nuts 6 mm dia and 25 mm long 3.50 each 11 each 38.50
TOTAL 3561.12
Add 5 % for water, electricity, sundries and other 0.00
overhead charges on all except (A) i.e. on (3561.12
- 3561.12) = 0.00
TOTAL 3561.12
Add 10 % for contractor's profit on all except (A) 0.00
i.e. on (3561.12 - 3561.12) = 0.00
Cost of 10 sqm. 3561.12
Cost of 1 sqm. 356.11
0227 Adjustable span ESO+SI (2.35-3.40) 1825.00 each 0.1063 each 194.00
Qty taken for cost using once = 5x0.85/40
=_x000D_
0.1063
0228 Adjustable telescopic prop 3 m (2.02-3.75 m) 1150.00 each 0.1275 each 146.63
Labour:
0107 Fitter 1st class 207.00 day 3 day 621.00
0114 Beldar 190.00 day 6 day 1140.00
0221 Shuttering oil 55.00 litre 2.25 litre 123.75
TOTAL 2826.15
Add 5 % for water, electricity, sundries and other 113.02
overhead charges on all except (A) i.e. on (2826.15
- 565.77) = 2260.38
TOTAL 2939.17
Add 10 % for contractor's profit on all except (A) 237.34
i.e. on (2939.17 - 565.77) = 2373.40
Cubical contents
6.60x0.5x0.3 = 0.99 cum
Area in contact with concrete
1x1.30x6.00 = 7.80 sqm
Assuming shuttering will become unserviceable
after use of 40 times
Effective area of shuttering = 40x7.80=312 m2
MATERIAL
1. Steel plates for side and bottom (plate size 1.20 x
0.50m)
Angle 40x40x5mm
2x1.20 = 2.40 m
3x0.50 = 1.50 m
3.90 m @ 3.00 kg/m = 11.70 kg
MS sheet 1.6 mm thick
1.20m x 0.50 m = 0.60 sqm.
0.60 sqm @ 12.55 kg/sqm. = 7.53 kg.
Weight of one plate = 19.23 kg.
Add for wastage 5% 0.96 kg._x000D_
Total =20.19 kg.
Total weight of all plates_x000D_
3x5x20.19 = 302.85 kg
Qty taken for cost of using once = 302.85 x_x000D_
85/40 = 6.4356 kg
9.1 Steel work Single section (Rate as per Item No 9.1) 61.46 kg 6.4356 kg 395.53
0228 Adjustable telescopic prop 3 m (2.02-3.75 m) 1150.00 each 0.1275 each 146.63
TOTAL 1467.31
4x4x1.25 = 20.00
23x0.65 =3.90
= 23.90sqm
Wastage @ 5% = 1.20
= 25.10sqm.
Qty for cost using once = 25.10/8 = 3.14 cudm
2817 Shuttering ply 12mm thick 700.00 sqm 3.14 sqm 2198.00
(ii) Battens (2nd class kail wood)-
4x2x5x0.60x0.075x0.050=0.090
3x2x5x1.00x0.075x0.050=0.112
2x6x0.60x0.075x0.100=0.054
= 0.256cum
Wastage @ 5% = 0.013cum
= 0.269cum = 269cudm
Qty for cost using once = 269/8 = 33.625 cudm
2816 Any local wood for shuttering in scantling 24500.00 cum 0.033625 cum 823.81
(iii) Safeda Ballies 125mm dia-
2x2x6x4.00 = 96m
Wastage @5% = 4.8m
= 100.8 m
Qty for cost using once = 100.8/8 = 12.6 m
2815 Nilgiri ballies 125 mm diameter 42.00 metre 12.6 metre 529.20
0221 Shuttering oil 55.00 litre 2 litre 110.00
(iv) Credit for unserviseable timber-
Planks = 0.1192 cum
Battens = 0.03362 cum
Ballies 12.6x(0.125)x(0.125)/4x3.142=0.1545 cum
9.1 Steel work Single section (Rate as per Item No 9.1) 61.46 kg 412.5 kg 25352.25
2467 Seam bolts and nuts 6 mm dia and 25 mm long 3.50 each 30 each 105.00
TOTAL 97319.25
Add 10 % for contractor's profit on all except (A) 7196.70
i.e. on (97319.25 - 25352.25) = 71967.00
MATERIAL
Frame work in 2nd class kail wood
Tie-1x3.6x0.15x0.20 = 0.108cum.
Struts-3x1.8x0.10x0.10 =0.054cum
Struts-2x2.55x0.10x0.10=0.051cum.
Ribs-4x1.38x.075x0.075=0.031cum.
Total = 0.244 cum.
Quantity for 7 such frames
7x0.244 = 1.708cum.
Strips 5cmx2.5cm = 7.5cm
center to center
5.66/0.075x0.05x0.025x3.6 = 0.342cum.
Total = 2.050 cum = 2050 cudm
2816 Any local wood for shuttering in scantling 24500.00 cum 2.05 cum 50225.00
Safeda Balli supports 12.5cm dia
7x4x3.6= 100.8m
2815 Nilgiri ballies 125 mm diameter 42.00 metre 100.8 metre 4233.60
G.I. Plain sheet 20.37 sqm m 116kg. Or 1.16 quintal
2371 Galvanised steel plain sheets 5670.00 quintal 1.16 quintal 6577.20
Credit for unserviceable timber
Kail wood = 2.05cum.
Ballies - 100.8x(.125)2/4x3.142 = 1.24cum.
Total = 3.29 cum.
2814 Less Credit for unserviseable wood 2000.00 cum -3.21 cum -6420.00
Labour:
0106 Carpenter 2nd class 197.00 day 48 day 9456.00
0114 Beldar 190.00 day 96 day 18240.00
Radius R = 5m 2R-2 = 8
tan -¹ (4/3)=53.28°
2x53.28° = 106°
Surface area =2x22/7x5x3.6x106/360=33.31sqm.
Arc=9.25m
Assuming that shuttering will be used 8 times
before becoming unserciseable so the effective
area = 33.31x8 = 266.48 sqm
Material :
Tie-2x8x0.18x0.05 =0.144cum
Struts-2x2.5x0.1x0.1 =0.050cum.
Struts-2x1.77x0.1x0.1=0.035cum.
Ribs-6x1.54x0.23x0.1=0.213cum.
Struts-2x1.72x0.1x0.1=0.034cum.
Total=0.476cum.
For four such frames
=0.476x4 = 1.904 cum.
laggings-75x3.6x0.125x0.075=2.531cum.
Tie-2x3.6x0.225x0.038=0.062cum.
Brace-3x2x2.14x0.225x0.038=0.110
Brace-3x4x3.8x0.225x0.038=0.390
Sleepers-4x3.6x0.20x0.15=0.432
Sleepers-2x4x3.6x0.175x0.075=0.378
Vertical post-4x4x3.6x0.15x0.15=1.296
Total = 5.199 cum
G. Total =7.103 cum
2816 Any local wood for shuttering in scantling 24500.00 cum 7.103 cum 174023.50
2815 Nilgiri ballies 125 mm diameter 42.00 metre 30 metre 1260.00
Fittings:
3 way straps 50mmx10mm = 32 Nos.
1.5mx1.2m
Size of weather shade 1.80x0.45m
Thickness at front = 0.05m
Thickness at fixed edge = 0.07m
Area in contact with concrete Bottom 1x0.45x1.80
= 0.810
1x0.05x1.80 = 0.094
2x0.45x0.06 = 0.027
Total = 0.954 sqm.
Assuming that the timber will become
unserviceable after being used 8 times.
Effective area = 8x0.954 = 7.63sqm
Materials :
Assuming that the timber will become
unserviceable after being used 8 times.
IInd class kail wood
(i) Planking
Bottom 1x1.876x0.488 = 0.915 sqm.
1x1.876x0.05 = 0.94 sqm.
2x0.45x0.06 = 0.027 sqm.
Total = 1.036 sqm.
Add 5% wastage = 0.052 sqm.
Total = 1.088 sqm.
MATERIAL
(i) Planks
4x4x1.25 = 20.00
23x0.65 =3.90
= 23.90sqm
Wastage @ 5% = 1.20
= 25.10sqm.
2817 Shuttering ply 12mm thick 700.00 sqm 25.1 sqm 17570.00
(ii) Battens (2nd class kail wood)-
4x2x5x0.60x0.075x0.050=0.090
3x2x5x1.00x0.075x0.050=0.112
2x6x0.60x0.075x0.100=0.054
= 0.256cum
Wastage @ 5% = 0.013cum
= 0.269cum = 269cudm
2816 Any local wood for shuttering in scantling 24500.00 cum 0.269 cum 6590.50
(iii) Safeda Ballies 125mm dia-
2x2x6x4.00 = 96m
Wastage @5% = 4.8m
= 100.8 m
2815 Nilgiri ballies 125 mm diameter 42.00 metre 100.8 metre 4233.60
0221 Shuttering oil 55.00 litre 15 litre 825.00
(iv) Credit for unserviseable timber-
Planks = 0.954
Battens = 0.269
Ballies 100.8x(.125)2/4x3.142=1.238cum
Total = 2.461 cum
2814 Less Credit for unserviseable wood 2000.00 cum -1.223 cum -2446.00
Labour:
For assembling, erection, dismantling and cleaning
MATERIAL
0230 Prop 4 m 1310.00 each 21 each 27510.00
0228 Adjustable telescopic prop 3 m (2.02-3.75 m) 1150.00 each -21 each -24150.00
2467 Seam bolts and nuts 6 mm dia and 25 mm long 3.50 each 30 each 105.00
TOTAL 296.76
Add 5 % for water, electricity, sundries and other 0.00
overhead charges on all except (A) i.e. on (296.76 -
296.76) = 0.00
TOTAL 296.76
Add 10 % for contractor's profit on all except (A) 0.00
i.e. on (296.76 - 296.76) = 0.00
Cost of 10 sqm. 296.76
Cost of 1 sqm. 29.67
Say 29.50
0302 Stone Aggregate (Single size) : 20 mm nominal size 850.00 cum 0.24 cum 204.00
LABOUR
0101 Mason 1st class 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 1.68 day 319.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.07 day 49.00
0011 Hire charges of Vibrator (Needle type 40mm) 250.00 day 0.07 day 17.50
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.4 day 80.00
Total 2085.74
Add 5 % for water, electricity, sundries and other 104.29
overhead charges
Total 2190.03
Add 10 % for contractor's profit 219.00
Cost per 1.00 cum 2409.03
Say 2409.00
3.1 Providing and laying nominal mix plain cement concrete with crushed stone aggregate using concrete mixer in all
works upto plinth level excluding cost of form work.
3.1.2 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40mm nominal size).
Code Description Rate Unit Qty Total
Details of cost for 1.00 cum
MATERIAL
0251 Portland Cement 5400.00 tonne 0.17 tonne 918.00
0253 Coarse sand 360.00 cum 0.47 cum 169.20
0301 Stone Aggregate (Single size) : 40 mm nominal size 800.00 cum 0.65 cum 520.00
0302 Stone Aggregate (Single size) : 20 mm nominal size 850.00 cum 0.24 cum 204.00
LABOUR
0101 Mason 1st class 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 1.68 day 319.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.07 day 49.00
0011 Hire charges of Vibrator (Needle type 40mm) 250.00 day 0.07 day 17.50
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.4 day 80.00
Total 2301.74
0302 Stone Aggregate (Single size) : 20 mm nominal size 850.00 cum 0.24 cum 204.00
LABOUR
0101 Mason 1st class 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 1.68 day 319.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.07 day 49.00
0011 Hire charges of Vibrator (Needle type 40mm) 250.00 day 0.07 day 17.50
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.4 day 80.00
Total 2571.74
Add 5 % for water, electricity, sundries and other 128.59
overhead charges
Total 2700.33
Add 10 % for contractor's profit 270.03
Cost per 1.00 cum 2970.36
Say 2970.00
3.1 Providing and laying nominal mix plain cement concrete with crushed stone aggregate using concrete mixer in all
works upto plinth level excluding cost of form work.
3.1.4 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 40mm nominal size).
Code Description Rate Unit Qty Total
Details of cost for 1.00 cum
MATERIAL
0251 Portland Cement 5400.00 tonne 0.32 tonne 1728.00
0253 Coarse sand 360.00 cum 0.445 cum 160.20
0301 Stone Aggregate (Single size) : 40 mm nominal size 800.00 cum 0.52 cum 416.00
0302 Stone Aggregate (Single size) : 20 mm nominal size 850.00 cum 0.22 cum 187.00
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.11 cum 93.50
LABOUR
0101 Mason 1st class 207.00 day 0.12 day 24.84
0011 Hire charges of Vibrator (Needle type 40mm) 250.00 day 0.07 day 17.50
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.4 day 80.00
Total 3075.24
Add 5 % for water, electricity, sundries and other 153.76
overhead charges
Total 3229.00
Add 10 % for contractor's profit 322.90
Cost per 1.00 cum 3551.90
Say 3552.00
3.1 Providing and laying nominal mix plain cement concrete with crushed stone aggregate using concrete mixer in all
works upto plinth level excluding cost of form work.
3.1.5 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20mm nominal size).
Code Description Rate Unit Qty Total
Details of cost for 1.00 cum
MATERIAL
0251 Portland Cement 5400.00 tonne 0.4 tonne 2160.00
0253 Coarse sand 360.00 cum 0.425 cum 153.00
0302 Stone Aggregate (Single size) : 20 mm nominal size 850.00 cum 0.57 cum 484.50
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.28 cum 238.00
LABOUR
0101 Mason 1st class 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 1.68 day 319.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.07 day 49.00
0011 Hire charges of Vibrator (Needle type 40mm) 250.00 day 0.07 day 17.50
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.4 day 80.00
Total 3526.04
Add 5 % for water, electricity, sundries and other 176.30
overhead charges
Total 3702.34
Add 10 % for contractor's profit 370.23
Cost per 1.00 cum 4072.57
Say 4073.00
3.2 Providing and laying nominal mix reinforced cement concrete with crushed stone aggregate using concrete mixer in
all works upto plinth level excluding cost of form work._x000D_
(Note :Excess/ less cement used as per design mix is payable/ recoverable separately)
3.2.1 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20mm nominal size).
Code Description Rate Unit Qty Total
Details of cost for 1.00 cum
MATERIAL
0251 Portland Cement 5400.00 tonne 0.4 tonne 2160.00
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.28 cum 238.00
LABOUR
0101 Mason 1st class 207.00 day 0.25 day 51.75
0114 Beldar 190.00 day 1.95 day 370.50
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.07 day 49.00
0011 Hire charges of Vibrator (Needle type 40mm) 250.00 day 0.07 day 17.50
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.4 day 80.00
Total 3604.25
Add 5 % for water, electricity, sundries and other 180.21
overhead charges
Total 3784.46
Add 10 % for contractor's profit 378.45
Cost per 1.00 cum 4162.91
Say 4163.00
3.3 Providing and laying design mix reinforced cement concrete with crushed graded stone aggregate 20mm nominal
size using batching plant, transit mixer and concrete pump, in all works upto plinth level excluding cost of form
work.
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.28 cum 238.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.4 day 80.00
Total 3663.23
Add 5 % for water, electricity, sundries and other 183.16
overhead charges
Total 3846.39
Add 10 % for contractor's profit 384.64
Cost per 1.00 cum 4231.03
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.28 cum 238.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.4 day 80.00
Total 3720.88
Add 5 % for water, electricity, sundries and other 186.04
overhead charges
Total 3906.92
Add 10 % for contractor's profit 390.69
Cost per 1.00 cum 4297.61
Say 4298.00
3.3 Providing and laying design mix reinforced cement concrete with crushed graded stone aggregate 20mm nominal
size using batching plant, transit mixer and concrete pump, in all works upto plinth level excluding cost of form
work.
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.28 cum 238.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.4 day 80.00
Total 3776.70
Add 5 % for water, electricity, sundries and other 188.84
overhead charges
Total 3965.54
Add 10 % for contractor's profit 396.55
Cost per 1.00 cum 4362.09
Say 4362.00
3.3 Providing and laying design mix reinforced cement concrete with crushed graded stone aggregate 20mm nominal
size using batching plant, transit mixer and concrete pump, in all works upto plinth level excluding cost of form
work.
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.28 cum 238.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.4 day 80.00
Total 3832.16
Add 5 % for water, electricity, sundries and other 191.61
overhead charges
Total 4023.77
Add 10 % for contractor's profit 402.38
Cost per 1.00 cum 4426.15
Say 4426.00
3.3 Providing and laying design mix reinforced cement concrete with crushed graded stone aggregate 20mm nominal
size using batching plant, transit mixer and concrete pump, in all works upto plinth level excluding cost of form
work.
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.28 cum 238.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.4 day 80.00
Total 3887.62
Add 5 % for water, electricity, sundries and other 194.38
overhead charges
Total 4082.00
Add 10 % for contractor's profit 408.20
Cost per 1.00 cum 4490.20
Say 4490.00
3.4 Extra for laying PCC/RCC of any grade in superstructure above plinth level for every floor or part thereof in addition
to rate for foundation and plinth:
Code Description Rate Unit Qty Total
Cost for 10 cum
MACHINARY
0046 Concrete/ Mortar/ Bricks lifting machine 3000.00 day 0.25 day 750.00
LABOUR
0114 Beldar 190.00 day 0.5 day 95.00
Total 845.00
Add 5 % for water, electricity, sundries and other 42.25
overhead charges
Total 887.25
Add 10 % for contractor's profit 88.73
Cost for 10 cum 975.98
Cost per 1.00 cum 97.59
Say 97.50
3.5 Providing and laying pre-stressed cement concrete of M-35 grade in superstructure including form work but
excluding reinforcement complete as per drawing and specifications and IS : 1343-2012.
Code Description Rate Unit Qty Total
Details of cost for 1.00 cum
MATERIAL
0251 Portland Cement 5400.00 tonne 0.428 tonne 2311.20
0253 Coarse sand 360.00 cum 0.425 cum 153.00
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.28 cum 238.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.4 day 80.00
0028 Hire charges of Special shuttering for prestressed 300.00 sqm 4 sqm 1200.00
concrete
0035 Hire charges of Heavy duty scafolding for precast 2200.00 sqm 0.15 sqm 330.00
blocks for prestressing
Total 5476.00
Add 5 % for water, electricity, sundries and other 273.80
overhead charges
Total 5749.80
Add 10 % for contractor's profit 574.98
Cost per 1.00 cum 6324.78
Say 6325.00
3.6 Providing and laying High tensile steel wires/ strands at any level including all accessories i.e. sheathing duct, tube
anchorage set, and stressing, stressing operations and grouting with cement complete as per drawing and technical
specifications.
0033 Hire charges of Stressing Jack with pump 420.00 day 4 day 1680.00
TOTAL 47343.15
Add 5 % for water, electricity, sundries and other 2367.16
overhead charges
TOTAL 49710.31
MATERIALS
5.3 Cement Mortar C.M. 1:3 (1 cement : 3 fine sand) 3356.27 cum 0.0001 cum 0.34
(Rate as per item No 5.3)
LABOUR
0101 Mason 1st class 207.00 day 0.01 day 2.07
0114 Beldar 190.00 day 0.01 day 1.90
Total 24.63
Add 5 % for water, electricity, sundries and other 0.22
overhead charges on all except (A) i.e. on (24.63 -
20.32) = 4.31
Total 24.85
Add 10 % for contractor's profit on all except (A) 0.45
i.e. on (24.85 - 20.32) = 4.53
Cost for 0.054 25.30
Cost of 1.00 cum 468.51
Say 469.00
3.10 Extra for laying PCC/ RCC, in or under water or liquid mud including cost of pumping or bailing out of water and
removing slush etc. complete:
Code Description Rate Unit Qty Total
Details of cost for depth of water 0.30 m.
Quantity of concrete = 14 cum.
pumping hours = 3 hrs. or 0.375 day.
LABOUR
0114 Beldar 190.00 day 4 day 760.00
0010 Hire charges of Pumpset of capacity 4000 500.00 day 0.375 day 187.50
litres/hour.
TOTAL 947.50
Add 5 % for water, electricity, sundries and other 47.38
overhead charges
TOTAL 994.88
Add 10 % for contractor's profit 99.49
Cost of 14cum. per 0.30m depth 1094.37
Cost of cum. per m depth 260.56
Say 261.00
3.11 Extra for laying PCC/ RCC, in or under foul conditions.
Code Description Rate Unit Qty Total
Details of cost for 1 cum.
LABOUR
0101 Mason 1st class 207.00 day 0.02 day 4.14
0104 Mason 2nd class 197.00 day 0.02 day 3.94
0114 Beldar 190.00 day 0.4 day 76.00
TOTAL 84.08
Add 5 % for water, electricity, sundries and other 4.20
overhead charges
TOTAL 88.28
Add 10 % for contractor's profit 8.83
Cost for 1 cum. 97.11
Say 97.00
TOTAL 2177.94
Add 5 % for water, electricity, sundries and other 8.08
overhead charges on all except (A) i.e. on (2177.94
- 2016.34) = 161.60
TOTAL 2186.02
Add 10 % for contractor's profit on all except (A) 16.97
i.e. on (2186.02 - 2016.34) = 169.68
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.12 cum 102.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.2 day 40.00
TOTAL 2366.64
Add 5 % for water, electricity, sundries and other 118.33
overhead charges
TOTAL 2484.97
Add 10 % for contractor's profit 248.50
Cost of 10.00 sqm 2733.47
Cost of 1.00 sqm 273.34
Say 273.00
3.17 Providing and laying 25mm thick eves board/ facia made with cement mortar 1:3 (1 cement: 3 coarse sand) and
chicken mesh including cost of form work required but excluding steel reinforcement.
Code Description Rate Unit Qty Total
Details of cost for 1.50 sqm (5mx0.3m)
MATERIAL
Wire mesh = 1.50 sqm + wastage @10% = 0.15 =
1.65 sqm
2462 Wire mesh (rabbit) 38.00 sqm 1.65 sqm 62.70
5.3 Cement Mortar C.M. 1:3 (1 cement : 3 fine sand) 3356.27 cum 0.0375 cum 125.86
(Rate as per item No 5.3)
2.1.0.9 Form work for fins (Rate as per Item No 2.1.9) 336.10 sqm 1.75 sqm 588.18
TOTAL 1098.81
Add 10 % for contractor's profit on all except (A) 51.06
i.e. on (1098.81 - 588.18) = 510.63
Cost per meter length per cm. depth, per cm width 5.09
Say 5.10
3.19 Providing and fixing in position copper plate as per design for expansion joints.
Code Description Rate Unit Qty Total
Detail of cost for 3.0m length, 250mm width and
1.6mm thick = 0.75 sqm
MATERIAL
3262 Copper plate 575.00 kg 10.56 kg 6072.00
LABOUR
2958 Circular PU back up rod for 25mm gap 30.00 metre 10 metre 300.00
LABOUR
0108 Fitter 2nd class 197.00 day 2 day 394.00
0114 Beldar 190.00 day 2 day 380.00
TOTAL 4502.60
Add 5 % for water, electricity, sundries and other 225.13
overhead charges
TOTAL 4727.73
Add 10 % for contractor's profit 472.77
Cost for 10 metre 5200.50
Rate for 1 metre 520.05
Say 520.00
2957 Polymer based solvent primer 910.00 litre 0.8 litre 728.00
2x10mx0.08m = 1.6 sqm @ 0.5 litre/ sqm = 0.8 litre
2959 Circular PU back up rod for 40mm gap 50.00 metre 10 metre 500.00
LABOUR
0108 Fitter 2nd class 197.00 day 2 day 394.00
0114 Beldar 190.00 day 2 day 380.00
TOTAL 8326.80
Add 5 % for water, electricity, sundries and other 416.34
overhead charges
TOTAL 8743.14
Add 10 % for contractor's profit 874.31
Cost for 10 metre 9617.45
Rate for 1 metre 961.74
Say 962.00
3.24 Providing and applying for hermetically water proof sealing of vertical / horizontal expansion joint with approved
make Poly Sulphide Sealant compound (two component elastomeric sealant) having 80% tensile modulus
elongation, proper bonding with building surface complete with cleaning and preparing of building surface, applying
polymer solvent primer, providing and fixing PU back up rod of suitable dia in expansion joint for core making, filling
with Poly Sulphide Sealant (Sealant filling depth should be minimum half of the joint gap), finishing and smoothing
the surface etc complete._x000D_
The application shall be got done through the authorised applicator of the manufacture of compound
2959 Circular PU back up rod for 40mm gap 50.00 metre 10 metre 500.00
LABOUR
4.4.2 Dumb bell with central bulb (180mm wide, 8mm thick).
Code Description Rate Unit Qty Total
Details of cost for 100 metres
MATERIAL
3404 Water stops Dumb bell with central bulb 351.00 metre 100 metre 35100.00
1007 Binding wire 48.15 kg 0.1 kg 4.82
LABOUR
0114 Beldar 190.00 day 2.2 day 418.00
TOTAL 35522.82
Add 5 % for water, electricity, sundries and other 1776.14
overhead charges
TOTAL 37298.96
Add 10 % for contractor's profit 3729.90
Cost for 100 metres 41028.86
Cost for 1 metre 410.28
Say 410.00
4.4 Providing and placing in position suitable PVC water stops conforming to IS:12200 for construction/ expansion joints
between two RCC members and fixed to the reinforcement with binding wire before pouring concrete etc.
complete :
LABOUR
0120 Mate 197.00 day 0.04 day 7.88
0101 Mason 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 3.5 day 665.00
MACHINERY
0009 Hire charges of 1 BHP water supply pump 200.00 day 1 day 200.00
TOTAL 5287.75
Add 5 % for water, electricity, sundries and other 264.39
overhead charges
TOTAL 5552.14
Add 10 % for contractor's profit 555.21
Cost for 10 sqm 6107.35
Cost for one sqm 610.73
Say 611.00
4.8 Providing and laying six course damp proof treatment in basement, sump, reservoir etc. consisting of first, third,
fifth course of blown type petroleum bitumen of IS grade 85/25 hot @ 1.6kg/ sqm and 2nd & 4th course of self
finished bitumen tar felt with priming coat with bitumen solution applied at the rate of 0.25 litre per sqm and sixth
and final course of stone grit 6mm and down pea sized gravel spreaded at 0.008 cum per sqm including preparation
of surface by grouting cracks, providing C.C. fillets, rounding of corners and cleaning and drying of the surface before
priming coat is applied complete.
4.8.1 With bitumen felt of type 2, grade 2 (Fibre base) in 2nd and 4th course.
Code Description Rate Unit Qty Total
Detail of cost for 30 sqm
3302 Blown type petroleum bitumen of penetration 37000.00 tonne 0.144 tonne 5328.00
85/25 of approved quality
1.60x3x30 = 144 kg = 0.144t
3305 Bitumen felt fibre base (vegetable or animal):Type 55.00 sqm 66 sqm 3630.00
2 grade 1
30x2 = 60 sqm.
Add for over lapping @ 10% = 6 sqm.
Total = 66 sqm
0306 Stone grit 6 mm and down size or pea sized gravel 850.00 cum 0.18 cum 153.00
4.8.2 With bitumen felt of type 3, grade 2 (Hessian base) in 2nd and 4th course.
Code Description Rate Unit Qty Total
Detail of cost for 30 sqm
3302 Blown type petroleum bitumen of penetration 37000.00 tonne 0.144 tonne 5328.00
85/25 of approved quality
1.60x3x30 = 144 kg = 0.144t
3306 Bitumen felt :Type 3 grade 1 50.00 sqm 66 sqm 3300.00
30x2 = 60 sqm.
Add for over lapping @ 10% = 6 sqm.
Total = 66 sqm
0306 Stone grit 6 mm and down size or pea sized gravel 850.00 cum 0.18 cum 153.00
4.8.3 With bitumen felt of type 2, grade 2 (Fibre base) in 2nd course and & type 3, grade 2 (Hessian base) in 4th course.
4.9.1 With bitumen felt of type 2, grade 2 (Fibre base) in 2nd, 4th & 6th course.
Code Description Rate Unit Qty Total
Detail of cost for 30 sqm
3302 Blown type petroleum bitumen of penetration 37000.00 tonne 0.192 tonne 7104.00
85/25 of approved quality
1.60x4x30 = 192 kg = 0.192t
3305 Bitumen felt fibre base (vegetable or animal):Type 55.00 sqm 99 sqm 5445.00
2 grade 1
30x3 = 90 sqm.
Add for over lapping @ 10% = 9 sqm.
Total = 99 sqm
0306 Stone grit 6 mm and down size or pea sized gravel 850.00 cum 0.18 cum 153.00
4.9.2 With bitumen felt of type 3, grade 2 (Hessian base) three courses.
Code Description Rate Unit Qty Total
Detail of cost for 30 sqm
3302 Blown type petroleum bitumen of penetration 37000.00 tonne 0.192 tonne 7104.00
85/25 of approved quality
1.60x4x30 = 192 kg = 0.192t
3306 Bitumen felt :Type 3 grade 1 50.00 sqm 99 sqm 4950.00
30x3 = 90 sqm.
Add for over lapping @ 10% = 9 sqm.
Total = 99 sqm
0306 Stone grit 6 mm and down size or pea sized gravel 850.00 cum 0.18 cum 153.00
4.9.4 With bitumen felt of type 2, grade 2 (Fibre base) one course and two courses with type 3 grade 2 (Hessian base).
Labour:
0111 Painter 197.00 day 0.17 day 33.49
0114 Beldar 190.00 day 0.17 day 32.30
2602 Painting Brush 60.00 each 0.27 each 16.20
TOTAL 177.99
Add 5 % for water, electricity, sundries and other 8.90
overhead charges
TOTAL 186.89
Add 10 % for contractor's profit 18.69
Cost of 10.00 Sqm. 205.58
Cost of 1.00 Sqm. 20.55
Say 20.50
4.12 Deduct for omitting in water proofing treatment final course of spreading stone grit 6mm down size or pea sized
gravel :
4.12.1 At 6 cudm per sqm.
Code Description Rate Unit Qty Total
LABOUR
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 98.50
Add 5 % for water, electricity, sundries and other 4.93
overhead charges
TOTAL 103.43
Add 10 % for contractor's profit 10.34
Cost of 10.00 Sqm. 113.77
Cost of 1.00 Sqm. 11.37
Say 11.50
4.12 Deduct for omitting in water proofing treatment final course of spreading stone grit 6mm down size or pea sized
gravel :
4.12.2 At 8 cudm per sqm.
Code Description Rate Unit Qty Total
Details of cost for 10 sqm.
Materials:
0306 Stone grit 6 mm and down size or pea sized gravel 850.00 cum 0.08 cum 68.00
LABOUR
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 115.50
Add 5 % for water, electricity, sundries and other 5.78
overhead charges
TOTAL 121.28
Add 10 % for contractor's profit 12.13
Cost of 10.00 Sqm. 133.41
Cost of 1.00 Sqm. 13.34
Say 13.50
4.13 Grading roof for water proofing treatment with:
4.13.1 Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
Code Description Rate Unit Qty Total
Details of cost for one cum.
0302 Stone Aggregate (Single size) : 20 mm nominal size 850.00 cum 0.67 cum 569.50
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.22 cum 187.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.25 day 50.00
TOTAL 3304.40
Add 5 % for water, electricity, sundries and other 165.22
overhead charges
TOTAL 3469.62
Add 10 % for contractor's profit 346.96
Cost of one cum 3816.58
Say 3817.00
4.13 Grading roof for water proofing treatment with:
4.13.2 Cement mortar 1:3 (1 cement : 3 coarse sand)
Code Description Rate Unit Qty Total
Details of cost for one cum.
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 1 cum 3356.27
(Rate as per item No 5.8)
Labour:-
0101 Mason 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 2 day 380.00
MACHINERY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.25 day 50.00
TOTAL 3993.27
Add 5 % for water, electricity, sundries and other 199.66
overhead charges
TOTAL 4192.93
Add 10 % for contractor's profit 419.29
Cost of one cum 4612.22
Say 4612.00
4.13 Grading roof for water proofing treatment with:
4.13.3 Cement mortar 1:4 (1cement : 4 coarse sand)
Code Description Rate Unit Qty Total
Details of cost for one cum.
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 1 cum 2654.27
(Rate as per item No 5.9)
Labour:-
0114 Beldar 190.00 day 2 day 380.00
0101 Mason 1st class 207.00 day 1 day 207.00
MACHINERY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.25 day 50.00
TOTAL 3291.27
Add 5 % for water, electricity, sundries and other 164.56
overhead charges
TOTAL 3455.83
Add 10 % for contractor's profit 345.58
Cost of one cum 3801.41
Say 3801.00
TOTAL 6762.95
Add 10 % for contractor's profit on all except (A) 587.50
i.e. on (6762.95 - 887.98) = 5874.97
LABOUR :
0101 Mason 1st class 207.00 day 2 day 414.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 5981.57
Say 5982.00
5.2 Cement mortar 1:2 (1 cement : 2 fine sand).
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
(0.475 cum. of cement = 0.68 tonne)
0251 Portland Cement 5400.00 tonne 0.68 tonne 3672.00
0254 Fine sand 360.00 cum 0.95 cum 342.00
LABOUR
0120 Mate 197.00 day 0.01 day 1.97
0114 Beldar 190.00 day 0.78 day 148.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.067 day 46.90
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 4231.07
Say 4231.00
5.3 Cement mortar 1:3 (1 cement : 3 fine sand).
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
(0.357 cum. of cement = 0.51 tonne)
0251 Portland Cement 5400.00 tonne 0.51 tonne 2754.00
0254 Fine sand 360.00 cum 1.07 cum 385.20
LABOUR
0120 Mate 197.00 day 0.01 day 1.97
0114 Beldar 190.00 day 0.78 day 148.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.067 day 46.90
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 2654.27
Say 2654.00
5.5 Cement mortar 1:5 (1 cement : 5 fine sand).
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
(0.214 cum. of cement = 0.31 tonne)
0251 Portland Cement 5400.00 tonne 0.31 tonne 1674.00
0254 Fine sand 360.00 cum 1.07 cum 385.20
LABOUR
0120 Mate 197.00 day 0.01 day 1.97
0114 Beldar 190.00 day 0.78 day 148.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.067 day 46.90
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 2276.27
Say 2276.00
5.6 Cement mortar 1:6 (1 cement : 6 fine sand).
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
(0.178 cum. of cement = 0.25 tonne)
0251 Portland Cement 5400.00 tonne 0.25 tonne 1350.00
0254 Fine sand 360.00 cum 1.07 cum 385.20
LABOUR
0120 Mate 197.00 day 0.01 day 1.97
0114 Beldar 190.00 day 0.78 day 148.20
MACHINERY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 1952.27
Say 1952.00
5.7 Cement mortar 1:2 (1 cement : 2 coarse sand).
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
(0.476 cum. of cement = 0.68 tonne)
0251 Portland Cement 5400.00 tonne 0.68 tonne 3672.00
0253 Coarse sand 360.00 cum 0.95 cum 342.00
LABOUR
0120 Mate 197.00 day 0.01 day 1.97
0114 Beldar 190.00 day 0.78 day 148.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.067 day 46.90
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 4231.07
Say 4231.00
5.8 Cement mortar 1:3 (1 cement : 3 coarse sand).
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
(0.357 cum. of cement = 0.51 tonne)
0251 Portland Cement 5400.00 tonne 0.51 tonne 2754.00
0253 Coarse sand 360.00 cum 1.07 cum 385.20
LABOUR
0120 Mate 197.00 day 0.01 day 1.97
0114 Beldar 190.00 day 0.78 day 148.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.067 day 46.90
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 3356.27
Say 3356.00
5.9 Cement mortar 1:4 (1 cement : 4 coarse sand).
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
(0.268 cum. of cement = 0.38 tonne)
0251 Portland Cement 5400.00 tonne 0.38 tonne 2052.00
0253 Coarse sand 360.00 cum 1.07 cum 385.20
LABOUR
0120 Mate 197.00 day 0.01 day 1.97
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 2654.27
Say 2654.00
5.10 Cement mortar 1:5 (1 cement : 5 coarse sand).
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
(0.214 cum. of cement = 0.31 tonne)
0251 Portland Cement 5400.00 tonne 0.31 tonne 1674.00
0253 Coarse sand 360.00 cum 1.07 cum 385.20
LABOUR
0120 Mate 197.00 day 0.01 day 1.97
0114 Beldar 190.00 day 0.78 day 148.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.067 day 46.90
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
TOTAL 2276.27
Say 2276.00
5.11 Cement mortar 1:6 (1 cement : 6 coarse sand).
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
(0.178 cum. of cement = 0.25 tonne)
0251 Portland Cement 5400.00 tonne 0.25 tonne 1350.00
0253 Coarse sand 360.00 cum 1.07 cum 385.20
LABOUR
0120 Mate 197.00 day 0.01 day 1.97
0114 Beldar 190.00 day 0.78 day 148.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.067 day 46.90
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 1952.27
Say 1952.00
5.12 Cement mortar 1:8 (1 cement : 8 Coarse sand).
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
(0.134 cum. of cement = 0.19 tonne)
0251 Portland Cement 5400.00 tonne 0.19 tonne 1026.00
0253 Coarse sand 360.00 cum 1.07 cum 385.20
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 1628.27
Say 1628.00
5.13 Cement mortar 1:2 (1 cement : 2 stone dust).
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
(0.475 cum. of cement = 0.68 tonne)
0251 Portland Cement 5400.00 tonne 0.68 tonne 3672.00
0256 Stone dust 360.00 cum 0.95 cum 342.00
LABOUR
0120 Mate 197.00 day 0.01 day 1.97
0114 Beldar 190.00 day 0.78 day 148.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.067 day 46.90
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 4231.07
Say 4231.00
5.14 Cement mortar 1:2 (1 cement : 2 marble dust).
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
(0.475 cum. of cement = 0.68 tonne)
0251 Portland Cement 5400.00 tonne 0.68 tonne 3672.00
1151 Marble dust/ powder 1200.00 cum 0.95 cum 1140.00
LABOUR
0120 Mate 197.00 day 0.01 day 1.97
0114 Beldar 190.00 day 0.78 day 148.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.067 day 46.90
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 5029.07
Say 5029.00
5.15 White cement mortar 1:5 (1 white cement : 5 marble dust).
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
(0.214 cum. of cement = 0.31 tonne)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 3175.07
Say 3175.00
5.16 White cement mortar 1: 2 (1 white cement : 2 marble dust).
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
(0.475 cum. of cement = 0.68 tonne)
0252 White Cement 14000.00 tonne 0.68 tonne 9520.00
1151 Marble dust/ powder 1200.00 cum 0.95 cum 1140.00
LABOUR
0120 Mate 197.00 day 0.01 day 1.97
0114 Beldar 190.00 day 0.78 day 148.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.067 day 46.90
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 10877.07
Say 10877.00
5.17 White cement mortar 1:3 (1 white cement : 3 marble dust).
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
(0.357 cum. of cement = 0.51 tonne)
0252 White Cement 14000.00 tonne 0.51 tonne 7140.00
1151 Marble dust/ powder 1200.00 cum 1.07 cum 1284.00
LABOUR
0120 Mate 197.00 day 0.01 day 1.97
0114 Beldar 190.00 day 0.78 day 148.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.067 day 46.90
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 8641.07
Say 8641.00
5.18 White cement mortar 1:5 (1 white cement : 5 marble dust)
Code Description Rate Unit Qty Total
Details of cost for 1 cum
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 5841.07
Say 5841.00
5.19 Cement mortar 1:1:3 (1 cement : 1 marble dust : 3 stone dust)
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
(0.214 cum. of cement = 0.31 tonne)
1151 Marble dust/ powder 1200.00 cum 0.38 cum 456.00
0252 White Cement 14000.00 tonne 0.31 tonne 4340.00
0256 Stone dust 360.00 cum 1.07 cum 385.20
LABOUR
0120 Mate 197.00 day 0.01 day 1.97
0114 Beldar 190.00 day 0.78 day 148.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.067 day 46.90
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 5398.27
Say 5398.00
5.20 Mud mortar
Code Description Rate Unit Qty Total
Details of cost for 1 cum
MATERIALS
3621 Mud (dry) 30.00 cum 1.08 cum 32.40
LABOUR
0120 Mate 197.00 day 0.01 day 1.97
0114 Beldar 190.00 day 1 day 190.00
MACHINERY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
Cost of 1.00 cum 244.37
Say 244.00
5.21 Cement Concrete 1: 6 : 12 (1 cement : 6 coarse sand : 12 crushed stone aggregate 12.5mm)
Code Description Rate Unit Qty Total
Details of cost for 1.00 cum
MATERIAL
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.29 cum 246.50
LABOUR
0101 Mason 1st class 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 1.68 day 319.20
MACHINERY
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.07 day 49.00
0011 Hire charges of Vibrator (Needle type 40mm) 250.00 day 0.07 day 17.50
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.4 day 80.00
Total 2102.44
Add 5 % for water, electricity, sundries and other 105.12
overhead charges
Total 2207.56
Add 10 % for contractor's profit 220.76
Cost per 1.00 cum 2428.32
Say 2428.00
5.11 Cement Mortar C.M. 1:6 (1 cement : 6 coarse sand) 1952.27 cum 0.33 cum 644.25
(Rate as per item No 5.11)
LABOUR ;
0104 Mason 2nd class 197.00 day 1 day 197.00
0114 Beldar 190.00 day 2 day 380.00
MACHINERY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 2177.67
Add 5 % for water, electricity, sundries and other 108.88
overhead charges
TOTAL 2286.55
Add 10 % for contractor's profit 228.66
Cost of 1 cum. 2515.21
Say 2515.00
6.2 Extra for random rubble masonry with hard stone in superstructure above plinth level for every floor or part thereof
in addition to rate for foundation and plinth:
Code Description Rate Unit Qty Total
Details of cost for 1 cum.
Labour :
0114 Beldar 190.00 day 0.75 day 142.50
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 3 sqm 33.00
TOTAL 175.50
Add 5 % for water, electricity, sundries and other 8.78
overhead charges
TOTAL 184.28
Add 10 % for contractor's profit 18.43
Cost of 1 cum. 202.71
Say 203.00
6.3 Extra for random rubble masonry with hard stone in square or rectangular pillars.
Code Description Rate Unit Qty Total
Details of cost for 1 cum.
Labour:
0104 Mason 2nd class 197.00 day 0.58 day 114.26
0114 Beldar 190.00 day 0.27 day 51.30
TOTAL 165.56
0373 Through and bond stone of size 25.00 each 7 each 175.00
(24cmx24xcmx39cm)
Labour:
0104 Mason 2nd class 197.00 day 1.75 day 344.75
5.11 Cement Mortar C.M. 1:6 (1 cement : 6 coarse sand) 1952.27 cum 0.243 cum 474.40
(Rate as per item No 5.11)
LABOUR :
0101 Mason 1st class 207.00 day 0.36 day 74.52
0104 Mason 2nd class 197.00 day 0.36 day 70.92
0114 Beldar 190.00 day 1.45 day 275.50
MACHINERY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.08 day 16.00
TOTAL 2666.34
Add 5 % for water, electricity, sundries and other 133.32
overhead charges
TOTAL 2799.66
Add 10 % for contractor's profit 279.97
Cost of 1 Cum. 3079.63
Say 3080.00
7.3 Brick work with non-modular well burnt (open bhatta) clay bricks of crushing strength not less than 20 kg/sqcm and
water absorption not more than 25% in foundation and plinth in:
7.3.2 Cement Mortar 1:8 (1 Cement : 8 Coarse Sand)
Code Description Rate Unit Qty Total
Details of cost for 1 cum.
MATERIALS :
0404 Non-Modular bricks open Bhutta 20kg/sqcm 3.75 each 468 each 1755.00
5.12 Cement Mortar C.M. 1:8 (1 cement : 8 coarse sand) 1628.27 cum 0.243 cum 395.67
(Rate as per item No 5.12)
LABOUR :
0101 Mason 1st class 207.00 day 0.36 day 74.52
0104 Mason 2nd class 197.00 day 0.36 day 70.92
0114 Beldar 190.00 day 1.45 day 275.50
MACHINERY
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.233 cum 782.01
(Rate as per item No 5.8)
LABOUR :
0101 Mason 1st class 207.00 day 0.36 day 74.52
0104 Mason 2nd class 197.00 day 0.36 day 70.92
0114 Beldar 190.00 day 1.45 day 275.50
MACHINERY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.08 day 16.00
TOTAL 3152.15
Add 5 % for water, electricity, sundries and other 157.61
overhead charges
TOTAL 3309.76
Add 10 % for contractor's profit 330.98
Cost of 1 Cum. 3640.74
Say 3641.00
7.5 Brick work with modular fly-ash lime bricks (FaLG Bricks) confirming to IS:12894-2002 of class designation 40 in
foundation and plinth in:
7.5.2 Cement Mortar 1:4 (1 cement : 4 coarse sand)
Code Description Rate Unit Qty Total
Details of cost for 1 cum.
MATERIALS :
0405 Modular fly-ash lime bricks class designation 40 3.60 each 537 each 1933.20
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 0.233 cum 618.44
(Rate as per item No 5.9)
LABOUR :
0101 Mason 1st class 207.00 day 0.36 day 74.52
0104 Mason 2nd class 197.00 day 0.36 day 70.92
0114 Beldar 190.00 day 1.45 day 275.50
MACHINERY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.08 day 16.00
TOTAL 2988.58
Add 5 % for water, electricity, sundries and other 149.43
overhead charges
TOTAL 3138.01
Add 10 % for contractor's profit 313.80
Cost of 1 Cum. 3451.81
5.10 Cement Mortar C.M. 1:5 (1 cement : 5 coarse sand) 2276.27 cum 0.233 cum 530.37
(Rate as per item No 5.10)
LABOUR :
0101 Mason 1st class 207.00 day 0.36 day 74.52
0104 Mason 2nd class 197.00 day 0.36 day 70.92
0114 Beldar 190.00 day 1.45 day 275.50
MACHINERY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.08 day 16.00
TOTAL 2900.51
Add 5 % for water, electricity, sundries and other 145.03
overhead charges
TOTAL 3045.54
Add 10 % for contractor's profit 304.55
Cost of 1 Cum. 3350.09
Say 3350.00
7.5 Brick work with modular fly-ash lime bricks (FaLG Bricks) confirming to IS:12894-2002 of class designation 40 in
foundation and plinth in:
7.5.4 Cement Mortar 1:6 (1 cement : 6 coarse sand)
Code Description Rate Unit Qty Total
Details of cost for 1 cum.
MATERIALS :
0405 Modular fly-ash lime bricks class designation 40 3.60 each 537 each 1933.20
5.11 Cement Mortar C.M. 1:6 (1 cement : 6 coarse sand) 1952.27 cum 0.233 cum 454.88
(Rate as per item No 5.11)
LABOUR :
0101 Mason 1st class 207.00 day 0.36 day 74.52
0104 Mason 2nd class 197.00 day 0.36 day 70.92
0114 Beldar 190.00 day 1.45 day 275.50
MACHINERY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.08 day 16.00
TOTAL 2825.02
Add 5 % for water, electricity, sundries and other 141.25
overhead charges
TOTAL 2966.27
Add 10 % for contractor's profit 296.63
Cost of 1 Cum. 3262.90
Say 3263.00
7.5 Brick work with modular fly-ash lime bricks (FaLG Bricks) confirming to IS:12894-2002 of class designation 40 in
foundation and plinth in:
5.12 Cement Mortar C.M. 1:8 (1 cement : 8 coarse sand) 1628.27 cum 0.223 cum 363.10
(Rate as per item No 5.12)
LABOUR :
0101 Mason 1st class 207.00 day 0.36 day 74.52
0104 Mason 2nd class 197.00 day 0.36 day 70.92
0114 Beldar 190.00 day 1.45 day 275.50
MACHINERY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.08 day 16.00
TOTAL 2733.24
Add 5 % for water, electricity, sundries and other 136.66
overhead charges
TOTAL 2869.90
Add 10 % for contractor's profit 286.99
Cost of 1 Cum. 3156.89
Say 3157.00
7.6 Extra for brick work in superstructure above plinth level for every floor or part thereof in addition to rate for
foundation and plinth:
Code Description Rate Unit Qty Total
Details of cost for 1 cum.
Labour :
0114 Beldar 190.00 day 0.55 day 104.50
TOTAL 104.50
Add 5 % for water, electricity, sundries and other 5.23
overhead charges
TOTAL 109.73
Add 10 % for contractor's profit 10.97
Cost of 1 cum. 120.70
Say 121.00
7.7 Extra for brick work in square and rectangular pillars. (size not more than 600mm in any direction)
Code Description Rate Unit Qty Total
Details of cost for 1.00 cum
LABOUR
0101 Mason 1st class 207.00 day 0.27 day 55.89
0104 Mason 2nd class 197.00 day 0.27 day 53.19
0114 Beldar 190.00 day 0.27 day 51.30
TOTAL 160.38
Add 5 % for water, electricity, sundries and other 8.02
overhead charges
TOTAL 168.40
Add 10 % for contractor's profit 16.84
Cost for 1 cum 185.24
Say 185.00
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.158 cum 530.29
(Rate as per item No 5.8)
LABOUR :
0101 Mason 1st class 207.00 day 0.6 day 124.20
0104 Mason 2nd class 197.00 day 0.6 day 118.20
0114 Beldar 190.00 day 3.6 day 684.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 5 sqm 55.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.3 day 60.00
TOTAL 3414.89
Add 5 % for water, electricity, sundries and other 170.74
overhead charges
TOTAL 3585.63
Add 10 % for contractor's profit 358.56
Cost for 10 sqm. 3944.19
Cost for 1 sqm. 394.41
Say 394.00
7.11 Half brick thick brick masonry with fly-ash lime bricks (FaLG Bricks) confirming to IS:12894-2002 of class designation
40 in superstructure above plinth level upto plinth level:
7.11.2 Cement Mortar 1:4 (1 cement : 4 coarse sand)
Code Description Rate Unit Qty Total
Details of cost for 10 sqm.
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 0.158 cum 419.37
(Rate as per item No 5.9)
LABOUR :
0101 Mason 1st class 207.00 day 0.6 day 124.20
0104 Mason 2nd class 197.00 day 0.6 day 118.20
0114 Beldar 190.00 day 3.6 day 684.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 5 sqm 55.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.3 day 60.00
TOTAL 3303.97
Add 5 % for water, electricity, sundries and other 165.20
overhead charges
TOTAL 3469.17
Add 10 % for contractor's profit 346.92
Cost for 10 sqm. 3816.09
Cost for 1 sqm. 381.60
Say 382.00
7.12 Extra for half brick work in superstructure above plinth level for every story or part thereof in addition to rate for
upto plinth level:
Code Description Rate Unit Qty Total
Details of cost for 10 sqm.
Labour :
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 95.00
Add 5 % for water, electricity, sundries and other 4.75
overhead charges
TOTAL 99.75
Add 10 % for contractor's profit 9.98
Cost for 10 sqm. 109.73
Rate for 1 sqm 10.97
Say 11.00
7.13 Half brick thick honey comb brick work with modular well burnt clay bricks of crushing strength not less than 35
kg/sqcm and water absorption not more than 20% upto plinth level.
7.13.1 Cement Mortar 1:3 (1 cement : 3 coarse sand)
Code Description Rate Unit Qty Total
Details of cost for 10 sqm.
MATERIAL
0401 Modular bricks class designation 35 4.50 each 342 each 1539.00
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.1 cum 335.63
(Rate as per item No 5.8)
LABOUR :
0101 Mason 1st class 207.00 day 0.6 day 124.20
0104 Mason 2nd class 197.00 day 0.6 day 118.20
0114 Beldar 190.00 day 3.6 day 684.00
MACHINERY
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.1 cum 335.63
(Rate as per item No 5.8)
LABOUR :
0101 Mason 1st class 207.00 day 0.6 day 124.20
0104 Mason 2nd class 197.00 day 0.6 day 118.20
0114 Beldar 190.00 day 3.6 day 684.00
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 0.1 cum 265.43
(Rate as per item No 5.9)
LABOUR :
0101 Mason 1st class 207.00 day 0.6 day 124.20
0104 Mason 2nd class 197.00 day 0.6 day 118.20
0114 Beldar 190.00 day 3.6 day 684.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 5 sqm 55.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.3 day 60.00
TOTAL 2538.03
Add 5 % for water, electricity, sundries and other 126.90
overhead charges
TOTAL 2664.93
Add 10 % for contractor's profit 266.49
Cost for 10 sqm. 2931.42
Cost for 1 sqm. 293.14
Say 293.00
7.16 Extra for half brick thick honey comb brick work in superstructure above plinth level for every story or part thereof
in addition to rate for upto plinth level:
Code Description Rate Unit Qty Total
Details of cost for 10 sqm
Labour :
0114 Beldar 190.00 day 0.55 day 104.50
TOTAL 104.50
Add 5 % for water, electricity, sundries and other 5.23
overhead charges
TOTAL 109.73
Add 10 % for contractor's profit 10.97
Cost of 10 sqm 120.70
5.11 Cement Mortar C.M. 1:6 (1 cement : 6 coarse sand) 1952.27 cum 0.11 cum 214.75
(Rate as per item No 5.11)
LABOUR :
0101 Mason 1st class 207.00 day 0.36 day 74.52
0104 Mason 2nd class 197.00 day 0.36 day 70.92
0114 Beldar 190.00 day 1.45 day 275.50
MACHINERY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.08 day 16.00
TOTAL 4051.69
Add 5 % for water, electricity, sundries and other 202.58
overhead charges
TOTAL 4254.27
Add 10 % for contractor's profit 425.43
Cost of 1 Cum. 4679.70
Say 4680.00
5.11 Cement Mortar C.M. 1:6 (1 cement : 6 coarse sand) 1952.27 cum 0.11 cum 214.75
(Rate as per item No 5.11)
LABOUR :
0101 Mason 1st class 207.00 day 0.36 day 74.52
0104 Mason 2nd class 197.00 day 0.36 day 70.92
0114 Beldar 190.00 day 1.45 day 275.50
MACHINERY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.08 day 16.00
TOTAL 3931.69
Add 5 % for water, electricity, sundries and other 196.58
overhead charges
TOTAL 4128.27
Add 10 % for contractor's profit 412.83
Cost of 1 Cum. 4541.10
Say 4541.00
6x3x(38/1000)x50/1000)=0.0342 cum.
= 0.1580 cum.+
Add for wastage @ 5% = 0.0079 cum.
= 0.1659 cum. say 0.166 cum.
2801 Teak wood in scantling 95000.00 cum 0.166 cum 15770.00
2608 Lime glue 65.00 kg 0.05 kg 3.25
1017 Iron Nails 55.10 kg 1.2 kg 66.12
Labour:
0105 Carpenter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1 day 190.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 4.5 sqm 49.50
TOTAL 16285.87
Add 5 % for water, electricity, sundries and other 814.29
overhead charges
TOTAL 17100.16
Add 10 % for contractor's profit 1710.02
Cost of 0.158 cum. 18810.18
Cost per cum. 119051.77
Say 119052.00
8.2 Providing wood work in frames of false ceiling, partition etc. sawn and put in position with main batten 125x50mm
(nominal) and cross batten 50x38mm (nominal) both at spacing of 600mm center to center.
6x3x(38/1000)x50/1000)=0.0342 cum.
TOTAL 67.42
Add 10 % for contractor's profit on all except (A) 5.26
i.e. on (67.42 - 14.85) = 52.57
Cost for 1 hold fast 72.68
Say 72.50
8.4 Providing and fixing Dash fastener (for fixing door/ window frames) on C.C. / R.C.C./ Brick masonry surface backing
including drilling necessary holes and the cost of bolt etc complete.
8.4.1 Dash fastener 6x75mm
TOTAL 177.40
Add 5 % for water, electricity, sundries and other 8.87
overhead charges
TOTAL 186.27
Add 10 % for contractor's profit 18.63
Cost of 10 Nos 204.90
Cost of 1 No 20.49
Say 20.50
8.4 Providing and fixing Dash fastener (for fixing door/ window frames) on C.C. / R.C.C./ Brick masonry surface backing
including drilling necessary holes and the cost of bolt etc complete.
8.4.2 Dash fastener 10x75mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0956 Dash fastner 10x75mm 15.00 each 10 each 150.00
Labour-
0108 Fitter 2nd class 197.00 day 0.2 day 39.40
0114 Beldar 190.00 day 0.2 day 38.00
Machinary
0031 Hire charges of Portable Electric Drill Machine 50.00 day 0.2 day 10.00
TOTAL 237.40
Add 5 % for water, electricity, sundries and other 11.87
overhead charges
TOTAL 249.27
Add 10 % for contractor's profit 24.93
Cost of 10 Nos 274.20
Cost of 1 No 27.42
Say 27.50
8.4 Providing and fixing Dash fastener (for fixing door/ window frames) on C.C. / R.C.C./ Brick masonry surface backing
including drilling necessary holes and the cost of bolt etc complete.
8.4.3 Dash fastener 12x100mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0957 Dash fastner 12x100mm 25.00 each 10 each 250.00
Labour-
0108 Fitter 2nd class 197.00 day 0.2 day 39.40
TOTAL 337.40
Add 5 % for water, electricity, sundries and other 16.87
overhead charges
TOTAL 354.27
Add 10 % for contractor's profit 35.43
Cost of 10 Nos 389.70
Cost of 1 No 38.97
Say 39.00
8.5 Extra for additional labour for circular work such as frames of fan lights.
8.5.1 Teak wood
Code Description Rate Unit Qty Total
Details of cost for Chowkhat of a door
cross section chowkhat 9.5 cm x 7.0 cm
206.75x117.5cm
2x 206.75cm x 7.5cm x 7.0cm = 0.028 cum
1 x 117.5cm x 9.5cm x 7.0cm = 0.008 cum Total =
0.036 cum
Extra Materials for wastage @ 10% on quantity =
0.036 x 0.1 = 0.0036
Extra material & labour taking 10 % quantity of
chowkhat
Materials :
2801 Teak wood in scantling 95000.00 cum 0.0036 cum 342.00
Labour :
0105 Carpenter 1st class 207.00 day 0.072 day 14.90
0114 Beldar 190.00 day 0.007 day 1.33
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 2 sqm 22.00
TOTAL 380.23
Add 5 % for water, electricity, sundries and other 19.01
overhead charges
TOTAL 399.24
Add 10 % for contractor's profit 39.92
Cost of 0.036 cum. 439.16
Cost per cum. 12198.88
Say 12199.00
8.5 Extra for additional labour for circular work such as frames of fan lights.
8.5.2 Sal, bijasal, benteak, khair, haldu
Code Description Rate Unit Qty Total
Details of cost for Chowkhat of a door
cross section chowkhat 9.5 cm x 7.0 cm
206.75x117.5cm
2 x 206.75cm x 7.5cm x 7.0cm = 0.028 cum
1 x 117.5cm x 9.5cm x 7.0cm = 0.008 cum Total =
0.036cum
2301 Float glass panes 4mm thick 302.40 sqm 0.8 sqm 241.92
Labour-
0113 Glazier 197.00 day 0.23 day 45.31
TOTAL 287.23
Add 5 % for water, electricity, sundries and other 14.36
overhead charges
TOTAL 301.59
Add 10 % for contractor's profit 30.16
Cost of 0.8 sqm. 331.75
Cost of 1 sqm. 414.68
Say 415.00
8.11 Providing and fixing glass panes in glazed or paneled and glazed shutters of doors and window, clearstory windows
etc (Only area of glass panes to be measured).
2302 Float glass panes 5mm thick 378.00 sqm 0.8 sqm 302.40
Labour-
0113 Glazier 197.00 day 0.23 day 45.31
TOTAL 347.71
Add 5 % for water, electricity, sundries and other 17.39
overhead charges
TOTAL 365.10
Add 10 % for contractor's profit 36.51
Cost of 0.8 sqm. 401.61
Cost of 1 sqm. 502.01
Say 502.00
8.11 Providing and fixing glass panes in glazed or paneled and glazed shutters of doors and window, clearstory windows
etc (Only area of glass panes to be measured).
8.11.3 6mm thick
Code Description Rate Unit Qty Total
Details of cost for shutters of a door size
200x108cm = 2.16 sqm with 1/3 rd panelling
2303 Float glass panes 6mm thick 453.60 sqm 0.8 sqm 362.88
Labour-
0113 Glazier 197.00 day 0.23 day 45.31
TOTAL 408.19
Add 5 % for water, electricity, sundries and other 20.41
overhead charges
TOTAL 428.60
Add 10 % for contractor's profit 42.86
Cost of 0.8 sqm. 471.46
Cost of 1 sqm. 589.32
Say 589.00
8.11 Providing and fixing glass panes in glazed or paneled and glazed shutters of doors and window, clearstory windows
etc (Only area of glass panes to be measured).
8.11.4 8mm thick
Code Description Rate Unit Qty Total
2304 Float glass panes 8 mm thick 648.00 sqm 0.8 sqm 518.40
Labour-
0113 Glazier 197.00 day 0.23 day 45.31
TOTAL 563.71
Add 5 % for water, electricity, sundries and other 28.19
overhead charges
TOTAL 591.90
Add 10 % for contractor's profit 59.19
Cost of 0.8 sqm. 651.09
Cost of 1 sqm. 813.86
Say 814.00
8.12 Providing and fixing flush door shutters, conforming to IS : 2202 (Part-I), decorative type core of block board
construction with frame of first class hard wood and well matched teak ply veneering with vertical grains or cross
bands and face veneers on both faces of shutters excluding hinges.
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 4699.40
Add 5 % for water, electricity, sundries and other 234.97
overhead charges
TOTAL 4934.37
Add 10 % for contractor's profit 493.44
Cost for 2.2 sqm. 5427.81
Cost of 1 sqm. 2467.18
Say 2467.00
8.12 Providing and fixing flush door shutters, conforming to IS : 2202 (Part-I), decorative type core of block board
construction with frame of first class hard wood and well matched teak ply veneering with vertical grains or cross
bands and face veneers on both faces of shutters excluding hinges.
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 3819.40
Add 5 % for water, electricity, sundries and other 190.97
overhead charges
TOTAL 4010.37
Add 10 % for contractor's profit 401.04
Cost for 2.2 sqm. 4411.41
Cost of 1 sqm. 2005.18
Say 2005.00
8.12 Providing and fixing flush door shutters, conforming to IS : 2202 (Part-I), decorative type core of block board
construction with frame of first class hard wood and well matched teak ply veneering with vertical grains or cross
bands and face veneers on both faces of shutters excluding hinges.
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 3489.40
Add 5 % for water, electricity, sundries and other 174.47
overhead charges
TOTAL 3663.87
Add 10 % for contractor's profit 366.39
Cost for 2.2 sqm. 4030.26
Cost of 1 sqm. 1831.93
Say 1832.00
8.12 Providing and fixing flush door shutters, conforming to IS : 2202 (Part-I), decorative type core of block board
construction with frame of first class hard wood and well matched teak ply veneering with vertical grains or cross
bands and face veneers on both faces of shutters excluding hinges.
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 3159.40
8.12.5 25 mm. thick (double leaf for cupboard shutters with piano type hinges
Code Description Rate Unit Qty Total
Details of cost for 2.2 sqm.
Materials-
2834 Flush door 25 mm thick block board construction 1400.00 sqm 2.2 sqm 3080.00
with teak wood ply on both faces
Labour-
0105 Carpenter 1st class 207.00 day 0.25 day 51.75
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 3179.25
Add 5 % for water, electricity, sundries and other 158.96
overhead charges
TOTAL 3338.21
Add 10 % for contractor's profit 333.82
Cost for 2.2 sqm. 3672.03
Cost of 1 sqm. 1669.10
Say 1669.00
8.13 Providing and fixing flush door shutters, conforming to IS 2202 (Part 1), interior grade, commercial type, core of
block board construction with frame of first class hard wood and well matched commercial ply veneering with
vertical grains, cross bands and face veneers on both faces of shutters excluding hinges.
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 3049.40
Add 5 % for water, electricity, sundries and other 152.47
overhead charges
TOTAL 3201.87
Add 10 % for contractor's profit 320.19
Cost for 2.2 sqm. 3522.06
Cost of 1 sqm. 1600.93
Say 1601.00
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 2609.40
Add 5 % for water, electricity, sundries and other 130.47
overhead charges
TOTAL 2739.87
Add 10 % for contractor's profit 273.99
Cost for 2.2 sqm. 3013.86
Cost of 1 sqm. 1369.93
Say 1370.00
8.13 Providing and fixing flush door shutters, conforming to IS 2202 (Part 1), interior grade, commercial type, core of
block board construction with frame of first class hard wood and well matched commercial ply veneering with
vertical grains, cross bands and face veneers on both faces of shutters excluding hinges.
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 2279.40
Add 5 % for water, electricity, sundries and other 113.97
overhead charges
TOTAL 2393.37
Add 10 % for contractor's profit 239.34
Cost for 2.2 sqm. 2632.71
Cost of 1 sqm. 1196.68
Say 1197.00
8.13 Providing and fixing flush door shutters, conforming to IS 2202 (Part 1), interior grade, commercial type, core of
block board construction with frame of first class hard wood and well matched commercial ply veneering with
vertical grains, cross bands and face veneers on both faces of shutters excluding hinges.
8.13.5 25 mm. thick (double leaf for cupboard shutters with piano type hinges
Code Description Rate Unit Qty Total
Details of cost for 2.2 sqm.
Materials-
2842 Flush door 25 mm thick block board construction 900.00 sqm 2.2 sqm 1980.00
with commmercial ply on both faces
Labour-
0105 Carpenter 1st class 207.00 day 0.25 day 51.75
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 2079.25
Add 5 % for water, electricity, sundries and other 103.96
overhead charges
TOTAL 2183.21
Add 10 % for contractor's profit 218.32
Cost for 2.2 sqm. 2401.53
Cost of 1 sqm. 1091.60
Say 1092.00
8.14 Providing and fixing flush door shutters, core of block board construction with frame of first class hard wood and
well matched first class Indian teak ply veneering on one face and commercial ply veneering on the other face of the
shutter with vertical grains, cross bands and face veneering excluding hinges.
Labour-
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 3214.40
Add 5 % for water, electricity, sundries and other 160.72
overhead charges
TOTAL 3375.12
Add 10 % for contractor's profit 337.51
Cost for 2.2 sqm. 3712.63
Cost of 1 sqm. 1687.55
Say 1688.00
8.14 Providing and fixing flush door shutters, core of block board construction with frame of first class hard wood and
well matched first class Indian teak ply veneering on one face and commercial ply veneering on the other face of the
shutter with vertical grains, cross bands and face veneering excluding hinges.
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 2884.40
Add 5 % for water, electricity, sundries and other 144.22
overhead charges
TOTAL 3028.62
Add 10 % for contractor's profit 302.86
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 2609.40
Add 5 % for water, electricity, sundries and other 130.47
overhead charges
TOTAL 2739.87
Add 10 % for contractor's profit 273.99
Cost for 2.2 sqm. 3013.86
Cost of 1 sqm. 1369.93
Say 1370.00
8.14 Providing and fixing flush door shutters, core of block board construction with frame of first class hard wood and
well matched first class Indian teak ply veneering on one face and commercial ply veneering on the other face of the
shutter with vertical grains, cross bands and face veneering excluding hinges.
8.14.5 25 mm. thick (double leaf for cupboard shutters with piano type hinges
Code Description Rate Unit Qty Total
Details of cost for 2.2 sqm.
Materials-
2838 Flush door 25 mm thick block board construction 1150.00 sqm 2.2 sqm 2530.00
with teak wood ply on one face and commercial on
other faces
Labour-
0105 Carpenter 1st class 207.00 day 0.25 day 51.75
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 2629.25
Add 5 % for water, electricity, sundries and other 131.46
overhead charges
TOTAL 2760.71
Add 10 % for contractor's profit 276.07
Cost for 2.2 sqm. 3036.78
Cost of 1 sqm. 1380.35
Say 1380.00
8.15 Extra for double leaf shutter instead of single leaf.
Code Description Rate Unit Qty Total
Details of cost for 2.2 sqm.
Labour-
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 3775.40
Add 5 % for water, electricity, sundries and other 188.77
overhead charges
TOTAL 3964.17
Add 10 % for contractor's profit 396.42
Cost for 2.2 sqm. 4360.59
Cost of 1 sqm. 1982.08
Say 1982.00
8.16 Providing and fixing PVC membrane foil coated (laminated) flush door shutters, made with core of block board with
frame of first class hard wood, coated with 0.30mm membrane pasted with resin using vacuam treatment process
complete all but excluding hinges.
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 3005.40
Add 5 % for water, electricity, sundries and other 150.27
overhead charges
TOTAL 3155.67
Add 10 % for contractor's profit 315.57
Cost for 2.2 sqm. 3471.24
Cost of 1 sqm. 1577.83
Say 1578.00
8.17 Providing and fixing PVC membrane foil coated (laminated) flush door shutters, made of partical board coated with
0.30mm membrane pasted with resin using vacuum treatment process complete all but excluding hinges.
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 2609.40
Add 5 % for water, electricity, sundries and other 130.47
overhead charges
TOTAL 2739.87
8.19.2 Circular
Code Description Rate Unit Qty Total
Details of cost for one circular vision panel of size
35 cm diameter
LABOUR
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 79.40
Add 5 % for water, electricity, sundries and other 3.97
overhead charges
TOTAL 83.37
Add 10 % for contractor's profit 8.34
Cost for one circular vision panel 91.71
Say 91.50
8.20 Extra for providing louvers in flush doors upto 0.20 sqm
8.20.1 Decorative type doors (50 x 5 mm)
Code Description Rate Unit Qty Total
Details of cost for 1 sqm. of door area
MATERIALS
lovers = 0.80x0.25m = 0.20sqm
Qty = 6x0.80x0.05x0.005 = 0.0012 cum
Wastage 10% =0.0001 Total = 0.0013
2802 Teak wood in planks 85000.00 cum 0.0013 cum 110.50
2608 Lime glue 65.00 kg 0.05 kg 3.25
LABOUR
0105 Carpenter 1st class 207.00 day 0.25 day 51.75
TOTAL 165.50
2857 12 mm thick prelaminated particle board with one 740.00 sqm 0.8 sqm 592.00
side decorative and other side balancing
lamination, flat pressed 3 layer & graded (medium
density) Grade I, Type II conforming to IS : 12823
(exterior grade)
2858 12 mm thick prelaminated particle board with both 780.00 sqm 0.8 sqm 624.00
sides decorative lamination, flat pressed 3 layer &
graded (medium density) Grade I, Type II
conforming to IS : 12823 (exterior grade)
2851 Pre-laminated with decorative lamination one side 641.25 sqm 0.8 sqm 513.00
and other side balancing lamination exterior Grade
- I MDF Board 12 mm thick confirming to IS:14587
2854 Pre-laminated with decorative lamination on both 691.90 sqm 0.8 sqm 553.52
side exterior Grade - I MDF Board 12 mm thick
confirming to IS:14587
2826 12 mm thick ply teak veneering on both faces 1335.00 sqm 0.8 sqm 1068.00
2847 12 mm thick solid PVC sheet with decorative 600.00 sqm 0.8 sqm 480.00
lamination one side and other side balancing
lamination of approved quality and make
2848 12 mm thick solid PVC sheet with decorative 650.00 sqm 0.8 sqm 520.00
lamination on both sides of approved quality and
make
Deduct for
2391 Galvanised wire mesh of average width of aperture 152.25 sqm -1 sqm -152.25
1.56 mm and nominal dia. of wire 0.45 mm
TOTAL 15.75
Add 5 % for water, electricity, sundries and other 0.79
overhead charges
TOTAL 16.54
Add 10 % for contractor's profit 1.65
Materials-
Teakwood IInd class
Jaffri 210x120x1.0cm = 0.025cum.+
Beading 660x5x1.2cm = 0.004cum.
= 0.029 cum.+
Add wastage @ 10% = 0.003 cum.
Total = 0.032 cum
2802 Teak wood in planks 85000.00 cum 0.032 cum 2720.00
2608 Lime glue 65.00 kg 0.25 kg 16.25
Labour-
0105 Carpenter 1st class 207.00 day 1 day 207.00
0106 Carpenter 2nd class 197.00 day 1 day 197.00
0114 Beldar 190.00 day 1 day 190.00
TOTAL 3330.25
Add 5 % for water, electricity, sundries and other 166.51
overhead charges
TOTAL 3496.76
Add 10 % for contractor's profit 349.68
Cost of 2.2 sqm. 3846.44
Cost of 1 sqm. 1748.38
Materials-
Salwood
Jaffri 210x120x1.0cm = 0.025cum.+
Beading 660x5x1.2cm = 0.004cum.
= 0.029 cum.+
Add wastage @ 10% = 0.003 cum.
Total = 0.032 cum
2804 Sal, bija, Haldu wood in scantling 48500.00 cum 0.032 cum 1552.00
2608 Lime glue 65.00 kg 0.25 kg 16.25
Labour-
0105 Carpenter 1st class 207.00 day 1 day 207.00
0106 Carpenter 2nd class 197.00 day 1 day 197.00
0114 Beldar 190.00 day 1 day 190.00
TOTAL 2162.25
Add 5 % for water, electricity, sundries and other 108.11
overhead charges
TOTAL 2270.36
Add 10 % for contractor's profit 227.04
Cost of 2.2 sqm. 2497.40
Cost of 1 sqm. 1135.18
Say 1135.00
8.29 Providing and fixing plain jaffri door, windows shutters excluding, 35x10mm laths placed 35 mm apart including
fixing 50x12 mm beading complete excluding hinges with.
8.29.1 Teak Wood
Code Description Rate Unit Qty Total
Details of cost of a jaffri shutter 176x86 cm = 1.51
sqm
Materials
Teak wood 2nd class
Styles 2x176x7.5x3.5 cm = 0.0092 cum
Rails 3x86x7.5x3.5 = 0.0068 cum
Total 0.0160 cum (a)
Plain Jaffri work
164 cm x 81 cm x 1 cm = 0.0133
Beading 490 cm x 5 cm x 1.2 cm = 0.0029
Total = 0.0162 (b)
Total a+b = 0.0322
Add wastage @ 10 % = 0.0032
Total = 0.0354 cum
2802 Teak wood in planks 85000.00 cum 0.0354 cum 3009.00
0532 M.S. bright finished or black enamelled or black 0.70 each 240 each 168.00
enamelled screws 50 mm
2608 Lime glue 65.00 kg 0.5 kg 32.50
Labour:
For planning and fixing
0105 Carpenter 1st class 207.00 day 2.35 day 486.45
0114 Beldar 190.00 day 1.9 day 361.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 2.5 sqm 27.50
TOTAL 43982.65
TOTAL 46170.15
Add 10 % for contractor's profit on all except (A) 4593.75
i.e. on (46170.15 - 232.70) = 45937.45
0532 M.S. bright finished or black enamelled or black 0.70 each 240 each 168.00
enamelled screws 50 mm
2608 Lime glue 65.00 kg 0.5 kg 32.50
Labour:
0105 Carpenter 1st class 207.00 day 2.25 day 465.75
0114 Beldar 190.00 day 1.85 day 351.50
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 2.5 sqm 27.50
TOTAL 28112.45
Add 5 % for water, electricity, sundries and other 1393.99
overhead charges on all except (A) i.e. on
(28112.45 - 232.70) = 27879.75
TOTAL 29506.44
Add 10 % for contractor's profit on all except (A) 2927.37
i.e. on (29506.44 - 232.70) = 29273.74
0532 M.S. bright finished or black enamelled or black 0.70 each 240 each 168.00
enamelled screws 50 mm
2608 Lime glue 65.00 kg 0.5 kg 32.50
Labour:
0105 Carpenter 1st class 207.00 day 2.25 day 465.75
0114 Beldar 190.00 day 1.85 day 351.50
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 2.5 sqm 27.50
TOTAL 22832.45
Add 5 % for water, electricity, sundries and other 1129.99
overhead charges on all except (A) i.e. on
(22832.45 - 232.70) = 22599.75
TOTAL 23962.44
Add 10 % for contractor's profit on all except (A) 2372.97
i.e. on (23962.44 - 232.70) = 23729.74
0532 M.S. bright finished or black enamelled or black 0.70 each 240 each 168.00
enamelled screws 50 mm
Labour:
0105 Carpenter 1st class 207.00 day 1.28 day 264.96
0114 Beldar 190.00 day 1.43 day 271.70
TOTAL 8864.13
Add 10 % for contractor's profit on all except (A) 863.14
i.e. on (8864.13 - 232.70) = 8631.43
8.30 P.F. Wood plug 50x50x50mm in wall etc (Rate as 20.36 each 26 each 529.36
per Item No 8.30)
2608 Lime glue 65.00 kg 0.2 kg 13.00
Labour:
0105 Carpenter 1st class 207.00 day 3 day 621.00
0121 Mistry 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 2.5 day 475.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 1.5 sqm 16.50
TOTAL 6998.84
Add 5 % for water, electricity, sundries and other 321.85
overhead charges on all except (A) i.e. on (6998.84
- 561.94) = 6436.90
TOTAL 7320.69
Add 10 % for contractor's profit on all except (A) 675.88
i.e. on (7320.69 - 561.94) = 6758.75
8.30 P.F. Wood plug 50x50x50mm in wall etc (Rate as 20.36 each 26 each 529.36
per Item No 8.30)
2608 Lime glue 65.00 kg 0.12 kg 7.80
Labour:
0105 Carpenter 1st class 207.00 day 2.5 day 517.50
0121 Mistry 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 2.2 day 418.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 1.5 sqm 16.50
TOTAL 4878.14
Add 5 % for water, electricity, sundries and other 215.81
overhead charges on all except (A) i.e. on (4878.14
- 561.94) = 4316.20
TOTAL 5093.95
Add 10 % for contractor's profit on all except (A) 453.20
i.e. on (5093.95 - 561.94) = 4532.01
TOTAL 8778.71
Add 10 % for contractor's profit on all except (A) 854.60
i.e. on (8778.71 - 232.70) = 8546.01
TOTAL 5477.51
Add 10 % for contractor's profit on all except (A) 524.48
i.e. on (5477.51 - 232.70) = 5244.81
TOTAL 19746.66
Add 10 % for contractor's profit on all except (A) 1753.03
i.e. on (19746.66 - 2216.34) = 17530.32
Labour-
0105 Carpenter 1st class 207.00 day 0.6 day 124.20
0114 Beldar 190.00 day 0.15 day 28.50
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 0.5 sqm 5.50
TOTAL 529.32
TOTAL 555.36
Add 10 % for contractor's profit on all except (A) 54.68
i.e. on (555.36 - 8.61) = 546.75
Cost of 5 m. 610.04
Cost of 1m 122.00
Say 122.00
8.39 Providing and fixing teak wood moulded beading to doors windows frames including necessary screws and primary
coat on exposed surface.
8.39.5 50x19mm
Code Description Rate Unit Qty Total
Details of cost for beading of a window of size
140x110cm i.e. 500cm. long (5metre)
Materials-
Teak wood IInd class in planks
5x0.053x0.022m = 0.00583 cum+
Add for wastage @ 5% = 0.0003 cum.
= 0.00613 cum.
2802 Teak wood in planks 85000.00 cum 0.00613 cum 521.05
1017 Iron Nails 55.10 kg 0.1 kg 5.51
Painting with priming coat Area = 500(5+2+2) =
0.45 sqm
14.20 Primer on wood work (Rate as per item no 14.20) 23.27 sqm 0.45 sqm 10.47
Labour-
For plaining, fixing and making design
0105 Carpenter 1st class 207.00 day 0.7 day 144.90
0114 Beldar 190.00 day 0.2 day 38.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 0.5 sqm 5.50
TOTAL 725.43
Add 5 % for water, electricity, sundries and other 35.75
overhead charges on all except (A) i.e. on (725.43 -
10.47) = 714.96
TOTAL 761.18
Add 10 % for contractor's profit on all except (A) 75.07
i.e. on (761.18 - 10.47) = 750.71
Cost of 5 m. 836.25
Cost of 1m 167.25
Say 167.00
8.40 Providing and fixing 200 mm wide teak wood moulding such as base moulding, chair rail, architrave, moulded posts
moulding skirting including necessary screws and painting on unexposed surfaces with wood primer etc complete
for per cm thick.
8.30 P.F. Wood plug 50x50x50mm in wall etc (Rate as 20.36 each 65 each 1323.40
per Item No 8.30)
Labour-
0105 Carpenter 1st class 207.00 day 12 day 2484.00
0102 Mason 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 7 day 1330.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 3 sqm 33.00
TOTAL 43780.80
Add 5 % for water, electricity, sundries and other 2115.89
overhead charges on all except (A) i.e. on
(43780.80 - 1463.02) = 42317.78
TOTAL 45896.69
Add 10 % for contractor's profit on all except (A) 4443.37
i.e. on (45896.69 - 1463.02) = 44433.67
Materials-
Teak wood 1st class in planks
Qty = 3.62 m x 0.30 m x 0.10 m = 0.109 cum
Add for wastage @ 10% = 0.011 cum.
Total = 0.120 cum.
2802 Teak wood in planks 85000.00 cum 0.12 cum 10200.00
1017 Iron Nails 55.10 kg 1 kg 55.10
priming coat with wood primer
Qty = 30.0 x 0.20 = 6.0 sqm
14.20 Primer on wood work (Rate as per item no 14.20) 23.27 sqm 1.85 sqm 43.05
8.30 P.F. Wood plug 50x50x50mm in wall etc (Rate as 20.36 each 14 each 285.04
per Item No 8.30)
Labour-
TOTAL 13667.92
Add 10 % for contractor's profit on all except (A) 1333.98
i.e. on (13667.92 - 328.09) = 13339.83
1012 Mild steel flat strap fitting 4239.70 quintal 0.00025 quintal 1.06
0944 Rawl plug 10x50 mm 7.90 each 2 each 15.80
1017 Iron Nails 55.10 kg 0.3 kg 16.53
LABOUR
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 0.3 sqm 3.30
8.42.3 12 mm thick ply board, commercial veneering on one face and teak veneering on other face.
Code Description Rate Unit Qty Total
Details of cost for a pelmet 2m long
Materials-
12mm thick board
Front-1x1.76x0.10= 0.176sqm.
Sides-2x0.10x0.10= 0.02sqm.
Total = 0.196sqm.+
Add wastage @ 5% = 0.0098 sqm.
= 0.2058sqm. Say 0.206 sqm.
2828 12 mm thick ply teak veneering on one face and 1073.00 sqm 0.206 sqm 221.04
commercial on other face
6mm thick commercial ply wood
Top-1x1.76x0.10= 0.176sqm.
Add wastage @ 5% = 0.0088 sqm.
= 0.1848 sqm. Say 0.185 sqm.
2825 6mm thick teak ply 736.00 sqm 0.185 sqm 136.16
2608 Lime glue 65.00 kg 0.05 kg 3.25
0592 Nickle plated M.S. pipe 20 mm dia. 81.00 metre 1.65 metre 133.65
0593 Nickle plated M.S. Brackets for curtain rod 20 mm 5.05 each 0.03 each 0.15
1012 Mild steel flat strap fitting 4239.70 quintal 0.00025 quintal 1.06
0944 Rawl plug 10x50 mm 7.90 each 2 each 15.80
1017 Iron Nails 55.10 kg 0.3 kg 16.53
LABOUR
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.2 day 38.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 0.3 sqm 3.30
TOTAL 798.02
Add 5 % for water, electricity, sundries and other 39.90
overhead charges
TOTAL 837.92
Add 10 % for contractor's profit 83.79
Cost of 2 m 921.71
Cost of 1m. 460.85
Say 461.00
8.43 Providing and fixing 12mm thick, 150mm wide pelmet with 6mm thick top cover, 20mm dia nickel plated M.S. pipe
(heavy duty) curtain rod and bracket including fixing with 10cm long 25x3mm M.S. flat, rawl plugs etc complete.
8.43.3 12 mm thick ply board, commercial veneering on one face and teak veneering on other face.
Code Description Rate Unit Qty Total
Details of cost for a pelmet 2m long
Materials-
12mm thick board
Front-1x1.76x0.15= 0.264sqm.
Sides-2x0.15x0.15= 0.045sqm.
Total = 0.309sqm.+
Add wastage @ 5% = 0.0154sqm.
= 0.3244sqm. Say 0.324 sqm.
2828 12 mm thick ply teak veneering on one face and 1073.00 sqm 0.324 sqm 347.65
commercial on other face
6mm thick commercial ply wood
Top-1x1.76x0.15= 0.264sqm.+
Add wastage @ 5% = 0.013 sqm.
= 0.2772 sqm. Say 0.277 sqm.
2825 6mm thick teak ply 736.00 sqm 0.277 sqm 203.87
2608 Lime glue 65.00 kg 0.05 kg 3.25
0592 Nickle plated M.S. pipe 20 mm dia. 81.00 metre 1.65 metre 133.65
8.44.1 12 mm dia
Code Description Rate Unit Qty Total
Details of cost for 2m long
Materials-
0854 Stainless steel curtain rod 20 mm dia 113.00 metre 2 metre 226.00
0857 Stainless steel curtain rod brackets 14.05 each 2 each 28.10
0763 Nickle plated Steel screws 30 mm 0.70 each 6 each 4.20
1041 Mild steel conduit pipe (heavy type) ISI marked-20 59.85 metre -2 metre -119.70
mm dia.
0593 Nickle plated M.S. Brackets for curtain rod 20 mm 5.05 each -2 each -10.10
0533 M.S. bright finished or black enamelled or black 0.60 each -6 each -3.60
enamelled screws 40 mm
8.30 P.F. Wood plug 50x50x50mm in wall etc (Rate as 20.36 each 2 each 40.72
per Item No 8.30)
LABOUR
0105 Carpenter 1st class 207.00 day 0.05 day 10.35
TOTAL 175.97
Add 5 % for water, electricity, sundries and other 6.76
overhead charges on all except (A) i.e. on (175.97 -
40.72) = 135.25
TOTAL 182.73
Add 10 % for contractor's profit on all except (A) 14.20
i.e. on (182.73 - 40.72) = 142.01
Cost of 2m 196.93
Cost of 1m. 98.46
Say 98.50
8.44 Extra for providing and fixing heavy duty stainless steel pipe for curtain rod with two stainless steel brackets in
pelmets instead of M.S. curtain rod of 20mm dia and M.S. brackets. (actual length of rod to be measured)
8.44.3 25 mm dia
Code Description Rate Unit Qty Total
Details of cost for 2m long
Materials-
0856 Stainless steel eleptical curtain rod made of 25 mm 169.00 metre 2 metre 338.00
dia
0857 Stainless steel curtain rod brackets 14.05 each 2 each 28.10
0648 Brass polished MS screws 40 mm 0.80 each 6 each 4.80
0944 Rawl plug 10x50 mm 7.90 each 2 each 15.80
LABOUR
0105 Carpenter 1st class 207.00 day 0.05 day 10.35
TOTAL 397.05
Add 5 % for water, electricity, sundries and other 19.85
overhead charges
TOTAL 416.90
Add 10 % for contractor's profit 41.69
Cost of 2m 458.59
Cost of 1m. 229.29
Say 229.00
8.45 Providing and fixing heavy duty stainless steel pipe for curtain/ cloth hanging with two stainless steel brackets in
wooden pelmet or wardrobe or any other space including screws and or plastic rawl plugs etc. wherever necessary.
TOTAL 1958.70
TOTAL 1307.17
Add 10 % for contractor's profit on all except (A) 129.89
i.e. on (1307.17 - 8.32) = 1298.85
Cost of 0.6 sqm. 1437.06
Cost of 1 sqm. 2395.10
Say 2395.00
8.51 Providing and fixing 38 mm thick wooden shelves supported on 40x40x6 mm T or L in brackets fixed at suitable
distance in 75x75x150mm blocks of cement concrete 1:2:4:
8.51.1 Teak wood
TOTAL 2494.20
Add 10 % for contractor's profit on all except (A) 248.59
i.e. on (2494.20 - 8.32) = 2485.88
Cost of 0.6 sqm. 2742.79
Cost of 1 sqm. 4571.31
Say 4571.00
8.51 Providing and fixing 38 mm thick wooden shelves supported on 40x40x6 mm T or L in brackets fixed at suitable
distance in 75x75x150mm blocks of cement concrete 1:2:4:
8.51.2 Bijasal, Haldu, Benteak, Khair
Code Description Rate Unit Qty Total
Details of cost for 2 x 1.0 m x 0.3 m = 0.6 sqm
shelves
Materials-
Teak wood 2nd class in planks
Qty = 2.0 m x 0.30 m x 0.035 m = 0.021cum
Add wastage @ 10% = 0.002cum.
TOTAL 1612.72
Add 10 % for contractor's profit on all except (A) 160.44
i.e. on (1612.72 - 8.32) = 1604.40
Cost of 0.6 sqm. 1773.16
Cost of 1 sqm. 2955.26
Say 2955.00
8.52 Providing, and fixing M.S. round and square bars with MS flat of required pattern in wooden frames for windows &
clerestory windows including applying a priming coat of red oxide zinc chromate primer, welding etc complete
Material-
M.S. bar 16mm dia. metre- 11x86cm = 9.46m.
@ 1.58kg/m = 14.95kg+
Add wastage @ 10% = 1.50kg.
= 16.45kg. Say 0.165q
1002 Mild steel round bar above 12 mm dia 4013.00 quintal 0.165 quintal 662.15
M.S. flat 25x3.15mm
2x120cm = 2.40m+
2x90cm = 1.80m+
1x120cm = 1.20m+
TOTAL 1147.17
Add 10 % for contractor's profit on all except (A) 112.85
i.e. on (1147.17 - 18.65) = 1128.52
Material-
M.S. bar 16mm dia. metre- 11x86cm = 9.46m.
@ 1.58kg/m = 14.95kg+
Add wastage @ 10% = 1.50kg.
= 16.45kg. Say 0.165q
1002 Mild steel round bar above 12 mm dia 4013.00 quintal 0.165 quintal 662.15
M.S. flat 25x3.15mm
2x120cm = 2.40m+
2x90cm = 1.80m+
1x120cm = 1.20m+
2x15cm = 0.30m
=5.70m
5.70m @ 0.63kg/m = 3.59kg+
Add wastage @ 10% = 0.36kg.
= 3.95kg. Say 4 kg. or 0.04q
1010 Flats upto 10 mm in thickness 4433.10 quintal 0.04 quintal 177.32
TOTAL 1284.73
Add 10 % for contractor's profit on all except (A) 126.61
i.e. on (1284.73 - 18.65) = 1266.08
TOTAL 1302.94
Add 10 % for contractor's profit on all except (A) 127.63
i.e. on (1302.94 - 26.60) = 1276.34
TOTAL 1499.56
Add 10 % for contractor's profit on all except (A) 147.30
i.e. on (1499.56 - 26.60) = 1472.96
8.59.1 150x125x27x5 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0608 Brass parliamentary hinges 150x125x27x5 mm 354.00 each 10 each 3540.00
8.59.2 125x125x27x5 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0609 Brass parliamentary hinges 125x125x27x5 mm 293.00 each 10 each 2930.00
8.59.3 100x125x27x5 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0610 Brass parliamentary hinges 100x125x27x5 mm 236.00 each 10 each 2360.00
8.59.4 75x100x20x3.20 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0611 Brass parliamentary hinges75x100x20x3.2 mm 84.40 each 10 each 844.00
8.60.1 300x16mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
8.60.2 250x16mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0638 Brass sliding bolt 250 x 16 mm 281.00 each 10 each 2810.00
0649 Brass polished MS screws 30 mm 0.70 each 40 each 28.00
Labour-
0105 Carpenter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 2979.50
Add 5 % for water, electricity, sundries and other 148.98
overhead charges
TOTAL 3128.48
Add 10 % for contractor's profit 312.85
Cost of 10 sliding bolts 3441.33
Cost of 1 sliding bolt 344.13
Say 344.00
8.61 Providing and fixing brass door latch with brass polished MS screws complete:
8.61.1 300x16x5 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0623 Brass door latch 300x16x5 mm (0.380 kg) 338.00 each 10 each 3380.00
0650 Brass polished MS screws 25 mm 0.35 each 90 each 31.50
Labour-
0105 Carpenter 1st class 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 0.06 day 11.40
TOTAL 3447.74
Add 5 % for water, electricity, sundries and other 172.39
overhead charges
TOTAL 3620.13
Add 10 % for contractor's profit 362.01
8.62.1 250x10mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0612 Brass tower bolt (barrel type) 250x10 mm 229.70 each 10 each 2297.00
0649 Brass polished MS screws 30 mm 0.70 each 100 each 70.00
Labour-
0105 Carpenter 1st class 207.00 day 0.1 day 20.70
TOTAL 2387.70
Add 5 % for water, electricity, sundries and other 119.39
overhead charges
TOTAL 2507.09
Add 10 % for contractor's profit 250.71
Cost of 10 tower bolts 2757.80
Cost of 1 tower bolt 275.78
Say 276.00
8.62 Providing and fixing bright finished brass tower bolts (barrel type) with brass polished MS screws complete:
8.62.2 200x10mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0613 Brass tower bolt (barrel type) 200x10 mm 192.70 each 10 each 1927.00
0649 Brass polished MS screws 30 mm 0.70 each 80 each 56.00
8.62.3 150x10mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0614 Brass tower bolt (barrel type) 150x10 mm 145.00 each 10 each 1450.00
0649 Brass polished MS screws 30 mm 0.70 each 80 each 56.00
Labour-
0105 Carpenter 1st class 207.00 day 0.1 day 20.70
TOTAL 1526.70
Add 5 % for water, electricity, sundries and other 76.34
overhead charges
TOTAL 1603.04
Add 10 % for contractor's profit 160.30
Cost of 10 tower bolts 1763.34
Cost of 1 tower bolt 176.33
Say 176.00
8.62 Providing and fixing bright finished brass tower bolts (barrel type) with brass polished MS screws complete:
8.62.4 100x10mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0615 Brass tower bolt (barrel type) 100x10 mm 96.35 each 10 each 963.50
0649 Brass polished MS screws 30 mm 0.70 each 60 each 42.00
Labour-
0105 Carpenter 1st class 207.00 day 0.1 day 20.70
TOTAL 1026.20
Add 5 % for water, electricity, sundries and other 51.31
overhead charges
TOTAL 1077.51
Add 10 % for contractor's profit 107.75
Cost of 10 tower bolts 1185.26
Cost of 1 tower bolt 118.52
Say 119.00
8.63 Providing and fixing bright finished brass flush bolt with brass polished MS screws complete:
Materials-
0641 Brass hanging type door stopper 150 mm 61.90 each 10 each 619.00
0650 Brass polished MS screws 25 mm 0.35 each 20 each 7.00
Labour-
0105 Carpenter 1st class 207.00 day 0.03 day 6.21
0114 Beldar 190.00 day 0.01 day 1.90
TOTAL 634.11
Add 5 % for water, electricity, sundries and other 31.71
overhead charges
TOTAL 665.82
Add 10 % for contractor's profit 66.58
Cost of 10 floor door stoppers 732.40
Cost of 1 floor door stopper 73.24
Say 73.00
8.74 Providing and fixing bright finished brass hard drawn hooks & eyes with brass polished MS screws etc complete.
8.74.1 300 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0629 Brass hard drawn hooks and eyes 300 mm 67.50 each 10 each 675.00
8.74.2 250 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0630 Brass hard drawn hooks and eyes 250 mm 61.90 each 10 each 619.00
0648 Brass polished MS screws 40 mm 0.80 each 40 each 32.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 669.12
Add 5 % for water, electricity, sundries and other 33.46
overhead charges
TOTAL 702.58
Add 10 % for contractor's profit 70.26
Cost of 10 hooks and eyes 772.84
Cost of 1 hook and eye 77.28
Say 77.50
8.74 Providing and fixing bright finished brass hard drawn hooks & eyes with brass polished MS screws etc complete.
8.74.3 200 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0631 Brass hard drawn hooks and eyes 200 mm 50.65 each 10 each 506.50
0649 Brass polished MS screws 30 mm 0.70 each 40 each 28.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 552.62
Add 5 % for water, electricity, sundries and other 27.63
overhead charges
TOTAL 580.25
Add 10 % for contractor's profit 58.03
8.74.4 150 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0632 Brass hard drawn hooks and eyes 150 mm 39.40 each 10 each 394.00
0649 Brass polished MS screws 30 mm 0.70 each 40 each 28.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 440.12
Add 5 % for water, electricity, sundries and other 22.01
overhead charges
TOTAL 462.13
Add 10 % for contractor's profit 46.21
Cost of 10 hooks and eyes 508.34
Cost of 1 hook and eye 50.83
Say 51.00
8.74 Providing and fixing bright finished brass hard drawn hooks & eyes with brass polished MS screws etc complete.
8.74.5 100 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0633 Brass hard drawn hooks and eyes 100 mm 28.15 each 10 each 281.50
0650 Brass polished MS screws 25 mm 0.35 each 40 each 14.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 313.62
Add 5 % for water, electricity, sundries and other 15.68
overhead charges
TOTAL 329.30
Add 10 % for contractor's profit 32.93
Cost of 10 hooks and eyes 362.23
Cost of 1 hook and eye 36.22
Say 36.00
8.75 Providing and fixing bright finished brass hasp and staple (safety type) with brass polished MS screws complete
8.75.1 150 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
8.75.2 115 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0635 Brass hasps and staples (safety type) 115 mm 45.00 each 10 each 450.00
8.75.3 90 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0636 Brass hasps and staples (safety type) 90 mm 33.75 each 10 each 337.50
Labour-
0105 Carpenter 1st class 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 2217.98
Add 5 % for water, electricity, sundries and other 110.90
overhead charges
TOTAL 2328.88
Add 10 % for contractor's profit 232.89
Cost for 10 nos. 2561.77
Cost of 1 no. 256.17
Say 256.00
8.77 Providing and fixing antique/ SS finished brass butt hinges with antique/ SS polished MS screw complete:
Labour-
0105 Carpenter 1st class 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 1777.98
Add 5 % for water, electricity, sundries and other 88.90
overhead charges
TOTAL 1866.88
Add 10 % for contractor's profit 186.69
Cost for 10 nos. 2053.57
Cost of 1 no. 205.35
Say 205.00
8.77 Providing and fixing antique/ SS finished brass butt hinges with antique/ SS polished MS screw complete:
Labour-
0105 Carpenter 1st class 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 804.98
Add 5 % for water, electricity, sundries and other 40.25
overhead charges
TOTAL 845.23
Add 10 % for contractor's profit 84.52
Cost for 10 nos. 929.75
Cost of 1 no. 92.97
Say 93.00
8.77 Providing and fixing antique/ SS finished brass butt hinges with antique/ SS polished MS screw complete:
Labour-
0105 Carpenter 1st class 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 1367.98
Labour-
0105 Carpenter 1st class 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 1093.98
Add 5 % for water, electricity, sundries and other 54.70
overhead charges
TOTAL 1148.68
Add 10 % for contractor's profit 114.87
Cost for 10 nos. 1263.55
Cost of 1 no. 126.35
Say 126.00
8.77 Providing and fixing antique/ SS finished brass butt hinges with antique/ SS polished MS screw complete:
Labour-
0105 Carpenter 1st class 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 686.48
Add 5 % for water, electricity, sundries and other 34.32
overhead charges
TOTAL 720.80
Add 10 % for contractor's profit 72.08
Cost for 10 nos. 792.88
Cost of 1 no. 79.28
Say 79.50
Labour-
0105 Carpenter 1st class 207.00 day 0.1 day 20.70
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 554.20
Add 5 % for water, electricity, sundries and other 27.71
overhead charges
TOTAL 581.91
Add 10 % for contractor's profit 58.19
Cost of 10 hinges 640.10
Cost of 1 hinge 64.01
Say 64.00
8.78 Providing and fixing antique/ SS finished brass parliamentary hinges with antique/ SS polished MS screw complete:
8.78.1 150x125x27x5 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0678 Antique finished brass parliamentary hinges 371.00 each 10 each 3710.00
150x125x27x5mm
0711 Antique finished Brass polished MS screws 40 mm 0.80 each 80 each 64.00
Labour-
0105 Carpenter 1st class 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 0.14 day 26.60
TOTAL 3829.58
Add 5 % for water, electricity, sundries and other 191.48
overhead charges
TOTAL 4021.06
Add 10 % for contractor's profit 402.11
Cost of 10 hinges 4423.17
Cost of 1 hinge 442.31
Say 442.00
8.78 Providing and fixing antique/ SS finished brass parliamentary hinges with antique/ SS polished MS screw complete:
8.78.2 125x125x27x5 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0679 Antique finished brass parliamentary hinges 307.00 each 10 each 3070.00
125x125x27x5mm
Labour-
0105 Carpenter 1st class 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 0.14 day 26.60
TOTAL 3189.58
Add 5 % for water, electricity, sundries and other 159.48
overhead charges
TOTAL 3349.06
Add 10 % for contractor's profit 334.91
Cost of 10 hinges 3683.97
Cost of 1 hinge 368.39
Say 368.00
8.78 Providing and fixing antique/ SS finished brass parliamentary hinges with antique/ SS polished MS screw complete:
8.78.3 100x125x27x5 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0680 Antique finished brass parliamentary hinges 248.00 each 10 each 2480.00
100x125x27x5mm
0711 Antique finished Brass polished MS screws 40 mm 0.80 each 80 each 64.00
Labour-
0105 Carpenter 1st class 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 0.14 day 26.60
TOTAL 2599.58
Add 5 % for water, electricity, sundries and other 129.98
overhead charges
TOTAL 2729.56
Add 10 % for contractor's profit 272.96
Cost of 10 hinges 3002.52
Cost of 1 hinge 300.25
Say 300.00
8.78 Providing and fixing antique/ SS finished brass parliamentary hinges with antique/ SS polished MS screw complete:
8.78.4 75x100x20x3.20 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0681 Antique finished brass parliamentary hinges 88.90 each 10 each 889.00
75x100x20x3.2mm
0712 Antique finished Brass polished MS screws 30 mm 0.70 each 60 each 42.00
Labour-
0105 Carpenter 1st class 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 0.14 day 26.60
TOTAL 986.58
Add 5 % for water, electricity, sundries and other 49.33
overhead charges
0713 Antique finished Brass polished MS screws 25 mm 0.35 each 40 each 14.00
Labour-
0105 Carpenter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 4295.50
Add 5 % for water, electricity, sundries and other 214.78
overhead charges
TOTAL 4510.28
Add 10 % for contractor's profit 451.03
Cost of 10 sliding bolts 4961.31
Cost of 1 sliding bolt 496.13
Say 496.00
8.79 Providing and fixing antique/ SS finished brass sliding door bolt with necessary bolts, nuts and antique/ SS polished
MS screw complete:
8.79.2 250 x 16mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0693 Antique finished Brass sliding door bolt 250x16 408.00 each 10 each 4080.00
0713 Antique finished Brass polished MS screws 25 mm 0.35 each 40 each 14.00
Labour-
0105 Carpenter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 4235.50
Add 5 % for water, electricity, sundries and other 211.78
overhead charges
TOTAL 4447.28
Add 10 % for contractor's profit 444.73
Cost of 10 sliding bolts 4892.01
Cost of 1 sliding bolt 489.20
Say 489.00
8.80 Providing and fixing antique/ SS finished brass door latch with antique/ SS polished MS screw complete:
Labour-
0105 Carpenter 1st class 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 0.06 day 11.40
TOTAL 3667.74
Add 5 % for water, electricity, sundries and other 183.39
overhead charges
TOTAL 3851.13
Add 10 % for contractor's profit 385.11
Cost of 10 nos. 4236.24
Cost of 1 no. 423.62
Say 424.00
8.80 Providing and fixing antique/ SS finished brass door latch with antique/ SS polished MS screw complete:
8.80.2 250x16x5 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0695 Antique finished Brass door latch 250x16x5 mm 236.00 each 10 each 2360.00
(0.350 kg)
0713 Antique finished Brass polished MS screws 25 mm 0.35 each 90 each 31.50
Labour-
0105 Carpenter 1st class 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 0.06 day 11.40
TOTAL 2427.74
Add 5 % for water, electricity, sundries and other 121.39
overhead charges
TOTAL 2549.13
Add 10 % for contractor's profit 254.91
Cost of 10 nos. 2804.04
Cost of 1 no. 280.40
Say 280.00
8.81 Providing and fixing antique/ SS finished brass tower bolts (Barrel type) with antique/ SS polished MS screw
complete:
8.81.1 250 x10 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0682 Antique finished Brass tower bolt (barrel type) 248.00 each 10 each 2480.00
250x10 mm
0712 Antique finished Brass polished MS screws 30 mm 0.70 each 100 each 70.00
Labour-
0105 Carpenter 1st class 207.00 day 0.1 day 20.70
TOTAL 2156.70
Add 5 % for water, electricity, sundries and other 107.84
overhead charges
TOTAL 2264.54
Add 10 % for contractor's profit 226.45
Cost of 10 tower bolts 2490.99
Cost of 1 tower bolt 249.09
Say 249.00
8.81 Providing and fixing antique/ SS finished brass tower bolts (Barrel type) with antique/ SS polished MS screw
complete:
8.81.3 150 x 10 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0684 Antique finished Brass tower bolt (barrel type) 156.00 each 10 each 1560.00
150x10 mm
0712 Antique finished Brass polished MS screws 30 mm 0.70 each 80 each 56.00
Labour-
0105 Carpenter 1st class 207.00 day 0.1 day 20.70
TOTAL 1636.70
Add 5 % for water, electricity, sundries and other 81.84
overhead charges
TOTAL 1718.54
Add 10 % for contractor's profit 171.85
Cost of 10 tower bolts 1890.39
Cost of 1 tower bolt 189.03
Labour-
0105 Carpenter 1st class 207.00 day 0.1 day 20.70
TOTAL 1102.70
Add 5 % for water, electricity, sundries and other 55.14
overhead charges
TOTAL 1157.84
Add 10 % for contractor's profit 115.78
Cost of 10 tower bolts 1273.62
Cost of 1 tower bolt 127.36
Say 127.00
8.82 Providing and fixing antique/ SS finished brass flush bolts with antique/ SS polished MS screw complete:
8.82.1 250 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0686 Antique finished brass flush bolt 250 mm 236.00 each 10 each 2360.00
0713 Antique finished Brass polished MS screws 25 mm 0.35 each 60 each 21.00
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 2441.40
Add 5 % for water, electricity, sundries and other 122.07
overhead charges
TOTAL 2563.47
Add 10 % for contractor's profit 256.35
Cost of 10 hinges 2819.82
Cost of 1 hinge 281.98
Say 282.00
8.82 Providing and fixing antique/ SS finished brass flush bolts with antique/ SS polished MS screw complete:
8.82.2 150 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0687 Antique finished brass flush bolt 150 mm 142.00 each 10 each 1420.00
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 1501.40
Add 5 % for water, electricity, sundries and other 75.07
overhead charges
TOTAL 1576.47
Add 10 % for contractor's profit 157.65
Cost of 10 hinges 1734.12
Cost of 1 hinge 173.41
Say 173.00
8.82 Providing and fixing antique/ SS finished brass flush bolts with antique/ SS polished MS screw complete:
8.82.3 100 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0688 Antique finished brass flush bolt 100 mm 94.50 each 10 each 945.00
0713 Antique finished Brass polished MS screws 25 mm 0.35 each 60 each 21.00
Labour-
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 1026.40
Add 5 % for water, electricity, sundries and other 51.32
overhead charges
TOTAL 1077.72
Add 10 % for contractor's profit 107.77
Cost of 10 hinges 1185.49
Cost of 1 hinge 118.54
Say 119.00
8.83 Providing and fixing antique/ SS finished brass indicating bolt (Vacant/ engaged) with antique/ SS polished MS
screw complete:
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0709 Antique finished brass indicating bolt 146.00 each 10 each 1460.00
0713 Antique finished Brass polished MS screws 25 mm 0.35 each 60 each 21.00
Labour-
0105 Carpenter 1st class 207.00 day 0.25 day 51.75
0114 Beldar 190.00 day 0.12 day 22.80
TOTAL 1555.55
Add 5 % for water, electricity, sundries and other 77.78
overhead charges
TOTAL 1633.33
Add 10 % for contractor's profit 163.33
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 504.62
Add 5 % for water, electricity, sundries and other 25.23
overhead charges
TOTAL 529.85
Add 10 % for contractor's profit 52.99
Cost of 10 handles 582.84
Cost of 1 handle 58.28
Say 58.50
8.84 Providing and fixing antique/ SS finished brass handles with antique/ SS polished MS screw complete:
8.84.2 100 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0690 Antique finished Brass handles 100 mm with plate 41.65 each 10 each 416.50
150x32 mm
0713 Antique finished Brass polished MS screws 25 mm 0.35 each 40 each 14.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 448.62
Add 5 % for water, electricity, sundries and other 22.43
overhead charges
TOTAL 471.05
Add 10 % for contractor's profit 47.11
Cost of 10 handles 518.16
Cost of 1 handle 51.81
Say 52.00
8.84 Providing and fixing antique/ SS finished brass handles with antique/ SS polished MS screw complete:
8.84.3 75 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 268.62
Add 5 % for water, electricity, sundries and other 13.43
overhead charges
TOTAL 282.05
Add 10 % for contractor's profit 28.21
Cost of 10 handles 310.26
Cost of 1 handle 31.02
Say 31.00
8.85 Providing and fixing antique/ SS finished brass furniture handles 50 mm with antique/ SS polished MS screws/nuts
etc complete.
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0639 Brass furniture handle 42.75 each 10 each 427.50
0651 Brass polished MS screws 20 mm 0.30 each 20 each 6.00
Labour-
0105 Carpenter 1st class 207.00 day 0.08 day 16.56
TOTAL 450.06
Add 5 % for water, electricity, sundries and other 22.50
overhead charges
TOTAL 472.56
Add 10 % for contractor's profit 47.26
Cost of 10 cupboard knob 519.82
Cost of 1 cupboard knob 51.98
Say 52.00
8.86 Providing and fixing 100mm antique/ SS finished brass mortise latch and lock with six levers and a pair of lever
handles with antique/ SS polished MS screw complete.
Code Description Rate Unit Qty Total
Details of cost for one No
Materials-
0696 Antique finished Brass mortice latch and lock 827.00 each 1 each 827.00
100x65 mm with 6 levers and a pair of Antique
finisheded lever handles
0710 Antique finished Brass polished MS screws 50 mm 1.00 each 4 each 4.00
Labour-
0105 Carpenter 1st class 207.00 day 0.16 day 33.12
0114 Beldar 190.00 day 0.08 day 15.20
TOTAL 879.32
Add 5 % for water, electricity, sundries and other 43.97
overhead charges
TOTAL 923.29
Add 10 % for contractor's profit 92.33
0710 Antique finished Brass polished MS screws 50 mm 1.00 each 4 each 4.00
Labour-
0105 Carpenter 1st class 207.00 day 0.16 day 33.12
0114 Beldar 190.00 day 0.08 day 15.20
TOTAL 790.32
Add 5 % for water, electricity, sundries and other 39.52
overhead charges
TOTAL 829.84
Add 10 % for contractor's profit 82.98
Cost of 1 mortice latch and lock 912.82
Say 913.00
8.88 Providing and fixing 100 mm antique/ SS finished brass rim latch and lock with a pair of knobs with antique/ SS
polished MS screw complete.
Code Description Rate Unit Qty Total
Details of cost for one No
Materials-
0698 Antique finished Brass rim latch and lock and pair 354.00 each 1 each 354.00
of nob
0710 Antique finished Brass polished MS screws 50 mm 1.00 each 4 each 4.00
Labour-
0105 Carpenter 1st class 207.00 day 0.16 day 33.12
0114 Beldar 190.00 day 0.08 day 15.20
TOTAL 406.32
Add 5 % for water, electricity, sundries and other 20.32
overhead charges
TOTAL 426.64
Add 10 % for contractor's profit 42.66
Cost of 1 mortice latch and lock 469.30
Say 469.00
8.89 Providing & fixing 100mm antique/ SS finished brass rim latch with a dead bolt and pair of knobs with antique/ SS
polished MS screw complete.
Code Description Rate Unit Qty Total
Details of cost for one No
Materials-
0699 Antique finished Brass rim latch with dead bolt and 331.00 each 1 each 331.00
pair of nob
0710 Antique finished Brass polished MS screws 50 mm 1.00 each 4 each 4.00
Labour-
Materials-
0700 Antique finished Brass 100 mm floor door stopper 65.25 each 10 each 652.50
(115gms)
0713 Antique finished Brass polished MS screws 25 mm 0.35 each 20 each 7.00
Labour-
0105 Carpenter 1st class 207.00 day 0.03 day 6.21
0114 Beldar 190.00 day 0.01 day 1.90
TOTAL 667.61
Add 5 % for water, electricity, sundries and other 33.38
overhead charges
TOTAL 700.99
Add 10 % for contractor's profit 70.10
Cost of 10 floor door stoppers 771.09
Cost of 1 floor door stopper 77.10
Say 77.00
8.91 Providing and fixing antique/ SS finished brass hard drawn hooks and eyes with antique/ SS polished MS screw
complete:
8.91.1 300 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0701 Antique finished brass hard drawn hooks and eyes 70.90 each 10 each 709.00
300 mm
0711 Antique finished Brass polished MS screws 40 mm 0.80 each 40 each 32.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 759.12
Add 5 % for water, electricity, sundries and other 37.96
overhead charges
TOTAL 797.08
Add 10 % for contractor's profit 79.71
Cost of 10 hooks and eyes 876.79
Cost of 1 hook and eye 87.67
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 702.62
Add 5 % for water, electricity, sundries and other 35.13
overhead charges
TOTAL 737.75
Add 10 % for contractor's profit 73.78
Cost of 10 hooks and eyes 811.53
Cost of 1 hook and eye 81.15
Say 81.00
8.91 Providing and fixing antique/ SS finished brass hard drawn hooks and eyes with antique/ SS polished MS screw
complete:
8.91.3 200 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0703 Antique finished brass hard drawn hooks and eyes 52.90 each 10 each 529.00
200 mm
0712 Antique finished Brass polished MS screws 30 mm 0.70 each 40 each 28.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 575.12
Add 5 % for water, electricity, sundries and other 28.76
overhead charges
TOTAL 603.88
Add 10 % for contractor's profit 60.39
Cost of 10 hooks and eyes 664.27
Cost of 1 hook and eye 66.42
Say 66.50
8.91 Providing and fixing antique/ SS finished brass hard drawn hooks and eyes with antique/ SS polished MS screw
complete:
8.91.4 150 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 462.62
Add 5 % for water, electricity, sundries and other 23.13
overhead charges
TOTAL 485.75
Add 10 % for contractor's profit 48.58
Cost of 10 hooks and eyes 534.33
Cost of 1 hook and eye 53.43
Say 53.50
8.91 Providing and fixing antique/ SS finished brass hard drawn hooks and eyes with antique/ SS polished MS screw
complete:
8.91.5 100 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0705 Antique finished brass hard drawn hooks and eyes 29.80 each 10 each 298.00
100 mm
0712 Antique finished Brass polished MS screws 30 mm 0.70 each 40 each 28.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 344.12
Add 5 % for water, electricity, sundries and other 17.21
overhead charges
TOTAL 361.33
Add 10 % for contractor's profit 36.13
Cost of 10 hooks and eyes 397.46
Cost of 1 hook and eye 39.74
Say 39.50
8.92 Providing and fixing antique/ SS finished brass hasp and staple (safety type) with antique/ SS polished MS screw
complete:
8.92.1 150 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0706 Antique finished brass hasps and staples (safety 70.90 each 10 each 709.00
type) 165mm
0713 Antique finished Brass polished MS screws 25 mm 0.35 each 80 each 28.00
Labour-
0105 Carpenter 1st class 207.00 day 0.08 day 16.56
TOTAL 753.56
Labour-
0105 Carpenter 1st class 207.00 day 0.08 day 16.56
TOTAL 510.06
Add 5 % for water, electricity, sundries and other 25.50
overhead charges
TOTAL 535.56
Add 10 % for contractor's profit 53.56
Cost of 10 hasps and staples 589.12
Cost of 1 hasps and staple 58.91
Say 59.00
8.92 Providing and fixing antique/ SS finished brass hasp and staple (safety type) with antique/ SS polished MS screw
complete:
8.92.3 90 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0708 Antique finished brass hasps and staples (safety 36.00 each 10 each 360.00
type) 90mm
0714 Antique finished Brass polished MS screws 20 mm 0.30 each 70 each 21.00
Labour-
0105 Carpenter 1st class 207.00 day 0.08 day 16.56
TOTAL 397.56
Add 5 % for water, electricity, sundries and other 19.88
overhead charges
TOTAL 417.44
Add 10 % for contractor's profit 41.74
Cost of 10 hasps and staples 459.18
Cost of 1 hasps and staple 45.91
Say 46.00
8.93 Providing and fixing antique/ SS finished brass hanging door stopper with necessary antique/ SS finished MS steel
screws complete.
Code Description Rate Unit Qty Total
8.95.1 150x125x27x2.80 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0505 M.S. Bright finished or black enamelled 56.70 each 10 each 567.00
Parliamentry hinges 150x125x27x2.8 mm
0587 M.S. powder coated screws 40 mm 0.70 each 80 each 56.00
Labour-
0105 Carpenter 1st class 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 0.14 day 26.60
TOTAL 678.58
Add 5 % for water, electricity, sundries and other 33.93
overhead charges
TOTAL 712.51
Add 10 % for contractor's profit 71.25
Cost of 10 nos. 783.76
Cost of 1 no 78.37
Say 78.50
8.95 Providing and fixing M.S. bright finished or black enameled Parliamentary hinges with necessary iron screws:
8.95.2 125x125x27x2.80 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0506 M.S. Bright finished or black enamelled 47.25 each 10 each 472.50
Parliamentry hinges 125x125x27x2.8 mm
0587 M.S. powder coated screws 40 mm 0.70 each 80 each 56.00
Labour-
0105 Carpenter 1st class 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 0.14 day 26.60
TOTAL 584.08
Add 5 % for water, electricity, sundries and other 29.20
overhead charges
TOTAL 613.28
Add 10 % for contractor's profit 61.33
Cost of 10 nos. 674.61
Cost of 1 no 67.46
Say 67.50
8.95 Providing and fixing M.S. bright finished or black enameled Parliamentary hinges with necessary iron screws:
8.95.3 100x125x27x2.80 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
8.95.4 75x100x20x2.24 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0508 M.S. Bright finished or black enamelled 24.30 each 10 each 243.00
Parliamentry hinges 75x100x20x2.24 mm
0587 M.S. powder coated screws 40 mm 0.70 each 80 each 56.00
Labour-
0105 Carpenter 1st class 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 0.14 day 26.60
TOTAL 354.58
Add 5 % for water, electricity, sundries and other 17.73
overhead charges
TOTAL 372.31
Add 10 % for contractor's profit 37.23
Cost of 10 nos. 409.54
Cost of 1 no 40.95
Say 41.00
8.96 Providing and fixing M.S. bright finished or black enameled Double spring hinges with iron screws:
8.96.1 150 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0509 MS bright finished or black enamelled double 256.00 each 10 each 2560.00
acting spring hinges 150 mm
0586 M.S. powder coated screws 50 mm 0.85 each 80 each 68.00
Labour-
0105 Carpenter 1st class 207.00 day 0.4 day 82.80
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 2748.80
Add 5 % for water, electricity, sundries and other 137.44
overhead charges
8.102.1 250 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0517 MS bright finished or black enamelled tower bolt 24.30 each 10 each 243.00
(barrel type) 250x10 mm
0589 M.S. powder coated screws 30 mm 0.35 each 100 each 35.00
Labour-
0105 Carpenter 1st class 207.00 day 0.1 day 20.70
TOTAL 298.70
Add 5 % for water, electricity, sundries and other 14.94
overhead charges
TOTAL 313.64
Add 10 % for contractor's profit 31.36
Cost of 10 nos. 345.00
8.102.2 200 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0518 MS bright finished or black enamelled tower bolt 20.25 each 10 each 202.50
(barrel type) 200x10 mm
0589 M.S. powder coated screws 30 mm 0.35 each 80 each 28.00
Labour-
0105 Carpenter 1st class 207.00 day 0.1 day 20.70
TOTAL 251.20
Add 5 % for water, electricity, sundries and other 12.56
overhead charges
TOTAL 263.76
Add 10 % for contractor's profit 26.38
Cost of 10 nos. 290.14
Cost of 1 no. 29.01
Say 29.00
8.102 Providing and fixing M.S. bright finished or black enameled Tower bolts (Barrel type) with necessary iron screws:
8.102.3 150 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0519 MS bright finished or black enamelled tower bolt 14.85 each 10 each 148.50
(barrel type) 150x10 mm
0589 M.S. powder coated screws 30 mm 0.35 each 80 each 28.00
Labour-
0105 Carpenter 1st class 207.00 day 0.1 day 20.70
TOTAL 197.20
Add 5 % for water, electricity, sundries and other 9.86
overhead charges
TOTAL 207.06
Add 10 % for contractor's profit 20.71
Cost of 10 nos. 227.77
Cost of 1 no. 22.77
Say 23.00
8.102 Providing and fixing M.S. bright finished or black enameled Tower bolts (Barrel type) with necessary iron screws:
8.102.4 100 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0520 MS bright finished or black enamelled tower bolt 10.10 each 10 each 101.00
(barrel type) 100x10 mm
0589 M.S. powder coated screws 30 mm 0.35 each 60 each 21.00
8.105.1 150 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0529 MS bright finished or black enamelled Hasp and 27.00 each 10 each 270.00
staple (safety type) 165 mm
0590 M.S. powder coated screws 25 mm 0.25 each 80 each 20.00
Labour-
0105 Carpenter 1st class 207.00 day 0.08 day 16.56
TOTAL 306.56
Add 5 % for water, electricity, sundries and other 15.33
overhead charges
TOTAL 321.89
Add 10 % for contractor's profit 32.19
Cost of 10 nos. 354.08
Cost of 1 no. 35.40
Say 35.50
8.105 Providing and fixing M.S. bright finished or black enameled safety hasp and staples with necessary iron screws:
8.105.2 115 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0530 MS bright finished or black enamelled Hasp and 8.10 each 10 each 81.00
staple (safety type) 115 mm
8.105.3 90 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0531 MS bright finished or black enamelled Hasp and 6.75 each 10 each 67.50
staple (safety type) 90 mm
0590 M.S. powder coated screws 25 mm 0.25 each 70 each 17.50
Labour-
0105 Carpenter 1st class 207.00 day 0.08 day 16.56
TOTAL 101.56
Add 5 % for water, electricity, sundries and other 5.08
overhead charges
TOTAL 106.64
Add 10 % for contractor's profit 10.66
Cost of 10 nos. 117.30
Cost of 1 no. 11.73
Say 11.50
8.106 Providing and fixing MS bright finished single hanging door stopper with necessary MS steel screws complete.
0586 M.S. powder coated screws 50 mm 0.85 each 100 each 85.00
Labour-
0105 Carpenter 1st class 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 0.09 day 17.10
TOTAL 316.58
Add 5 % for water, electricity, sundries and other 15.83
overhead charges
TOTAL 332.41
Add 10 % for contractor's profit 33.24
Cost of 10 nos. 365.65
Cost of 1 no 36.56
Say 36.50
8.107 Providing and fixing powder coated M.S. butt hinges with necessary iron screws:
8.107.2 100x58x1.90 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0552 MS powder coated butt hinges 100x58x1.90 mm 10.95 each 10 each 109.50
8.122.5 75 x10mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0879 Aluminium tower bolt (barrel type) 75x10 mm 16.90 each 10 each 169.00
8.123.2 125 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0881 Aluminium door handle 125x2.5mm thick 19.70 each 10 each 197.00
0590 M.S. powder coated screws 25 mm 0.25 each 40 each 10.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 225.12
Add 5 % for water, electricity, sundries and other 11.26
overhead charges
TOTAL 236.38
Add 10 % for contractor's profit 23.64
Cost of 10 nos. 260.02
Cost of 1 no. 26.00
Say 26.00
8.123 Providing and fixing aluminium door handles 2.5mm thick with necessary nickel plated iron screws etc complete.
8.123.3 100 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0882 Aluminium door handle 100x2.5mm thick 15.75 each 10 each 157.50
0590 M.S. powder coated screws 25 mm 0.25 each 40 each 10.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
8.124.1 Single
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0883 Aluminium door mounted door stopper 16.90 each 10 each 169.00
0851 Stainless steel screws 30 mm 1.10 each 40 each 44.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 231.12
Add 5 % for water, electricity, sundries and other 11.56
overhead charges
TOTAL 242.68
Add 10 % for contractor's profit 24.27
Cost of 10 hooks and eyes 266.95
Cost of 1 hook and eye 26.69
Say 26.50
8.124 Providing and fixing hanging aluminium door stopper with necessary nickel plated iron screws etc complete.
8.124.2 Double
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0884 Aluminium door stopper double 23.65 each 10 each 236.50
0851 Stainless steel screws 30 mm 1.10 each 60 each 66.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 320.62
Add 5 % for water, electricity, sundries and other 16.03
overhead charges
TOTAL 336.65
Add 10 % for contractor's profit 33.67
Cost of 10 hooks and eyes 370.32
Cost of 1 hook and eye 37.03
Say 37.00
8.125 Providing and fixing aluminium door mounted door stopper with necessary nickel plated iron screws etc complete.
8.125.2 75 mm long
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0886 Aluminium door mounted door stopper 75x20mm 28.15 each 10 each 281.50
8.125.3 60 mm long
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0887 Aluminium door mounted door stopper 60x20mm 22.50 each 10 each 225.00
8.125.4 50 mm long
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0888 Aluminium door mounted door stopper 50mm 16.90 each 10 each 169.00
8.128.5 75 x10mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0909 Powder coated aluminium tower bolt (barrel type) 17.70 each 10 each 177.00
75x10 mm
8.129.1 150 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0910 Powder coated aluminium door handle 150x2.5mm 24.75 each 10 each 247.50
thick
0590 M.S. powder coated screws 25 mm 0.25 each 40 each 10.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 275.62
Add 5 % for water, electricity, sundries and other 13.78
overhead charges
TOTAL 289.40
Add 10 % for contractor's profit 28.94
Cost of 10 nos. 318.34
Cost of 1 no. 31.83
Say 32.00
8.129 Providing and fixing powder coated aluminium door handles 2.5mm thick with necessary M.S. screws etc complete.
8.129.2 125 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0911 Powder coated aluminium door handle 125x2.5mm 20.80 each 10 each 208.00
thick
0590 M.S. powder coated screws 25 mm 0.25 each 40 each 10.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 236.12
Add 5 % for water, electricity, sundries and other 11.81
overhead charges
TOTAL 247.93
Add 10 % for contractor's profit 24.79
8.129.3 100 mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0912 Powder coated aluminium door handle 100x2.5mm 16.55 each 10 each 165.50
thick
0590 M.S. powder coated screws 25 mm 0.25 each 40 each 10.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 193.62
Add 5 % for water, electricity, sundries and other 9.68
overhead charges
TOTAL 203.30
Add 10 % for contractor's profit 20.33
Cost of 10 nos. 223.63
Cost of 1 no. 22.36
Say 22.50
8.130 Providing and fixing hanging powder coated aluminium door stopper with necessary M.S. screws etc complete.
8.130.1 Single
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0913 Powder coated aluminium door stopper single 17.70 each 10 each 177.00
8.130.2 Double
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
8.139.5 75 x10mm
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0829 Stainless steel tower bolt (barrel type) 750x10 mm 24.75 each 10 each 247.50
8.143.1 Single
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0842 Stainless steel door stopper single 36.00 each 10 each 360.00
0853 Stainless steel screws 20 mm 0.70 each 40 each 28.00
8.143.2 Double
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0843 Stainless steel door stopper double 50.25 each 10 each 502.50
0853 Stainless steel screws 20 mm 0.70 each 60 each 42.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 562.62
Add 5 % for water, electricity, sundries and other 28.13
overhead charges
TOTAL 590.75
Add 10 % for contractor's profit 59.08
Cost of 10 hooks and eyes 649.83
Cost of 1 hook and eye 64.98
Say 65.00
8.144 Providing and fixing stainless steel fixed stopper with necessary stainless steel screws complete.
8.144.1 100 mm long
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0844 Stainless steel door mounted door stopper 79.50 each 10 each 795.00
100x20mm
0853 Stainless steel screws 20 mm 0.70 each 30 each 21.00
Labour-
0105 Carpenter 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 834.12
Add 5 % for water, electricity, sundries and other 41.71
overhead charges
TOTAL 875.83
Add 10 % for contractor's profit 87.58
Cost of 10 hooks and eyes 963.41
0807 Stainless steel butt hinges 75x1.7 mm (Light) 14.30 each 3 each 42.90
0807 Stainless steel butt hinges 75x1.7 mm (Light) 14.30 each 3 each 42.90
8.149.1 24 mm thick door shutters with styles and rails of size 59x24 mm
Code Description Rate Unit Qty Total
Detail of cost for 2.38 sqm_x000D_
one door shutter 2.20x1.08m = 2.38 sqm
MATERIALS
3005 PVC door shutters with frame 24 mm thick (factory 2013.00 sqm 2.38 sqm 4790.94
made) with rails and panels of PVC extruded
sections in white, grey or wooden finish
8.149.2 30 mm thick door shutters with styles and rails of size 60x30 mm
Code Description Rate Unit Qty Total
Detail of cost for 2.38 sqm.
one door shutter 2.20x1.08m = 2.38 sqm
MATERIALS
3004 PVC door shutters with frame 30 mm thick (factory 2090.00 sqm 2.38 sqm 4974.20
made) with rails and panels of PVC extruded
sections in white, grey or wooden finish
Materials-
3013 Factory made door frame PVC extruded sheet i/c 269.00 metre 5 metre 1345.00
carriage
0944 Rawl plug 10x50 mm 7.90 each 12 each 94.80
Labour-
0105 Carpenter 1st class 207.00 day 0.15 day 31.05
0114 Beldar 190.00 day 0.15 day 28.50
TOTAL 1499.35
Add 5 % for water, electricity, sundries and other 74.97
overhead charges
TOTAL 1574.32
Add 10 % for contractor's profit 157.43
Cost of 5 metres 1731.75
Cost of 1 No 346.35
Say 346.00
8.152 Providing and fixing 30mm thick factory made panel PVC door shutter consisting of frame made out of M.S. tubes of
19 gauge thickness and size of 19mm x 19mm for styles and 15x15mm for top & bottom rails. M.S. frame shall have
a coat of steel primers of approved make and manufacture. M.S. frame covered with 5mm thick heat moulded PVC
'C' channel of size 30mm thickness, 70mm width out of which 50mm shall be flat and 20mm shall be tapered in
45degree angle on either side forming styles; and 5mm thick, 95mm wide PVC sheet out of which 75mm shall be flat
and 20mm shall be tapered in 45 degree on the inner side to form top and bottom rail and 115mm wide PVC sheet
out of which 75mm shall be flat and 20mm shall be tapered on both sides to form lock rail. Top, bottom and lock
rails shall be provided either side of the panel. 10mm (5mm x 2 ) thick, 20mm wide cross PVC sheet be provided as
gap insert for top rail & bottom rail. paneling of 5mm thick both side PVC sheet to be fitted in the M.S. frame
welded/ sealed to the styles & rails with 7mm (5mm+2mm) thick x 15mm wide PVC sheet beading on inner side,
and joined together with solvent cement adhesive. An additional 5mm thick PVC strip of 20mm width is to be stuck
on the interior side of the 'C' Channel using PVC solvent adhesive etc. complete as per Manufacturer’s specification
including 3 nos ISI marked stainless steel hinges of size 100x58x1.9 mm complete. (for W.C. and bathroom door
shutter).
0806 Stainless steel butt hinges 100x1.7 mm (Light) IS : 23.40 each 3 each 70.20
12817 marked
0851 Stainless steel screws 30 mm 1.10 each 12 each 13.20
Labour-
0105 Carpenter 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.33 day 62.70
TOTAL 5835.97
Add 5 % for water, electricity, sundries and other 291.80
overhead charges
TOTAL 6127.77
Add 10 % for contractor's profit 612.78
Cost of 2.38 sqm 6740.55
Cost per sqm 2832.16
Say 2832.00
0533 M.S. bright finished or black enamelled or black 0.60 each 48 each 28.80
enamelled screws 40 mm
0851 Stainless steel screws 30 mm 1.10 each 12 each 13.20
Labour-
0105 Carpenter 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.33 day 62.70
TOTAL 4352.35
Add 5 % for water, electricity, sundries and other 217.62
overhead charges
TOTAL 4569.97
Add 10 % for contractor's profit 457.00
Cost of 2.38 sqm 5026.97
Cost per sqm 2112.17
Say 2112.00
8.154 Providing and fixing 30mm thick fibreglass reinforced plastic (F.R.P.) flush door shutter in different plain and wood
finish made with fire retardant grade unsaturated polyester resin, moulded to 3mm thick FRP laminate all around,
with suitable wooden blocks inside at required places for fixing of fittings and polyurethane foam (PUF) /
Polystyrene foam to be used as filler material throughout the hollow panel, casted monolithically with testing
parameters of F.R.P. laminate conforming to table - 3 of IS: 14856 : 2000, complete.
0533 M.S. bright finished or black enamelled or black 0.60 each 48 each 28.80
enamelled screws 40 mm
0851 Stainless steel screws 30 mm 1.10 each 12 each 13.20
Labour-
0105 Carpenter 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.33 day 62.70
TOTAL 5347.19
Add 5 % for water, electricity, sundries and other 267.36
overhead charges
TOTAL 5614.55
Add 10 % for contractor's profit 561.46
Cost of 2.38 sqm 6176.01
0819 Stainless steel piono hinges 1 mm thick 35 mm 52.00 metre 4.4 metre 228.80
wide
0590 M.S. powder coated screws 25 mm 0.25 each 125 each 31.25
2803 Teak wood lipping 25 mm wide x 12 mm thick 42.00 metre 7 metre 294.00
Labour
0105 Carpenter 1st class 207.00 day 0.55 day 113.85
0114 Beldar 190.00 day 0.55 day 104.50
TOTAL 3408.33
Add 5 % for water, electricity, sundries and other 170.42
overhead charges
TOTAL 3578.75
Add 10 % for contractor's profit 357.88
Cost for 2.20sqm. 3936.63
Cost per sqm. 1789.37
Say 1789.00
8.157 Providing and fixing aluminum U beading of required size to Pre-laminated /flush door shutter including fixing etc.
complete as per direction of Engineer-in-charge.
Code Description Rate Unit Qty Total
Details of cost for 1kg.
Material
Aluminum U beading = 1.00kg +
Add 10% wastage = 0.10
= 1.10kg.
3208 Aluminium U beading 218.40 kg 1.1 kg 240.24
0591 M.S. powder coated screws 20 mm 0.20 each 13 each 2.60
LABOUR
0105 Carpenter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 441.34
Add 5 % for water, electricity, sundries and other 22.07
overhead charges
TOTAL 463.41
Add 10 % for contractor's profit 46.34
Cost per kg. 509.75
Say 510.00
8.158 Providing and fixing IS: 3564 marked aluminium die cast body tubular type universal hydraulic door closer with
necessary accessories and screws etc complete.
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials-
0932 Hydraulic door closer bottle type M.S. body with 1205.00 each 10 each 12050.00
necessary accessories and screws complete
8.160.1 25 mm long
Code Description Rate Unit Qty Total
Details of cost of 10 nos.
Materials:
0945 Expandable fastner with plastic sleeve and M.S. 1.15 each 10 each 11.50
screws. 25 mm long
LABOUR
0105 Carpenter 1st class 207.00 day 0.1 day 20.70
0114 Beldar 190.00 day 0.1 day 19.00
MACHINERY
0017 Hire and running charges of pneumatic cutters/ 800.00 day 0.1 day 80.00
hammers with operator.
TOTAL 131.20
Add 5 % for water, electricity, sundries and other 6.56
overhead charges
TOTAL 137.76
Add 10 % for contractor's profit 13.78
8.160.2 32 mm long
Code Description Rate Unit Qty Total
Details of cost of 10 nos.
Materials:
0946 Expandable fastner with plastic sleeve and M.S. 1.40 each 10 each 14.00
screws. 32 mm long
LABOUR
0105 Carpenter 1st class 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 0.12 day 22.80
MACHINERY
0017 Hire and running charges of pneumatic cutters/ 800.00 day 0.15 day 120.00
hammers with operator.
TOTAL 181.64
Add 5 % for water, electricity, sundries and other 9.08
overhead charges
TOTAL 190.72
Add 10 % for contractor's profit 19.07
Cost of 10 nos. 209.79
Cost of 1 no. 20.97
Say 21.00
8.160 Providing and fixing expandable fasteners of specified size with necessary plastic sleeves and galvanized M.S screws
including drilling holes in masonry work /CC/ R.C.C by drilling machine and making good etc complete.
8.160.3 40 mm long
Code Description Rate Unit Qty Total
Details of cost of 10 nos.
Materials:
0947 Expandable fastner with plastic sleeve and M.S. 1.70 each 10 each 17.00
screws. 40 mm long
LABOUR
0105 Carpenter 1st class 207.00 day 0.15 day 31.05
0114 Beldar 190.00 day 0.15 day 28.50
MACHINERY
0017 Hire and running charges of pneumatic cutters/ 800.00 day 0.2 day 160.00
hammers with operator.
TOTAL 236.55
Add 5 % for water, electricity, sundries and other 11.83
overhead charges
TOTAL 248.38
Add 10 % for contractor's profit 24.84
Cost of 10 nos. 273.22
Cost of 1 no. 27.32
Say 27.50
8.160.4 50 mm long
Code Description Rate Unit Qty Total
Details of cost of 10 nos.
Materials:
0948 Expandable fastner with plastic sleeve and M.S. 2.25 each 10 each 22.50
screws. 50 mm long
LABOUR
0105 Carpenter 1st class 207.00 day 0.15 day 31.05
0114 Beldar 190.00 day 0.15 day 28.50
MACHINERY
0017 Hire and running charges of pneumatic cutters/ 800.00 day 0.22 day 176.00
hammers with operator.
TOTAL 258.05
Add 5 % for water, electricity, sundries and other 12.90
overhead charges
TOTAL 270.95
Add 10 % for contractor's profit 27.10
Cost of 10 nos. 298.05
Cost of 1 no. 29.80
Say 30.00
8.161 Supplying and fixing teak wood fillets (10 mm x 10 mm size) including nails etc complete.
Code Description Rate Unit Qty Total
Details of cost for 10 metres length
MATERIALS
2nd class teak wood in planks
10x0.01x0.01 = 0.001 cum
Add 15% wastage = 0.0002 cum
Total = 0.0012 cum
2802 Teak wood in planks 85000.00 cum 0.0012 cum 102.00
1017 Iron Nails 55.10 kg 0.4 kg 22.04
LABOUR
0105 Carpenter 1st class 207.00 day 0.28 day 57.96
0114 Beldar 190.00 day 0.28 day 53.20
TOTAL 235.20
Add 5 % for water, electricity, sundries and other 11.76
overhead charges
TOTAL 246.96
Add 10 % for contractor's profit 24.70
Cost of 10.00 metre 271.66
Cost of 1.00 metre 27.16
Say 27.00
MATERIALS
2393 Fiber glass reinforced plastic chajja. 3885.00 sqm 0.54 sqm 2097.90
0949 Cadmium plated full threaded steel screws (30x4 1.95 each 30 each 58.50
mm dia.)
3204 Aluminium washer 2 mm thick 15 mm dia 0.10 each 30 each 3.00
5.7 Cement Mortar C.M. 1:2 (1 cement : 2 coarse sand) 4231.07 cum 0.01 cum 42.31
(Rate as per item No 5.7)
LABOUR
0105 Carpenter 1st class 207.00 day 0.3 day 62.10
0101 Mason 1st class 207.00 day 0.1 day 20.70
0114 Beldar 190.00 day 0.4 day 76.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 1 sqm 11.00
TOTAL 2371.51
Add 5 % for water, electricity, sundries and other 118.58
overhead charges
Total 2490.09
Add 10 % for contractor's profit 249.01
Cost for 0.54 sqm 2739.10
Cost for 1 sqm 5072.40
Say 5072.00
TOTAL 5592.40
Add 10 % for contractor's profit on all except (A) 554.06
i.e. on (5592.40 - 51.81) = 5540.59
TOTAL 19523.23
Add 10 % for contractor's profit on all except (A) 1942.51
i.e. on (19523.23 - 98.09) = 19425.14
TOTAL 9568.97
Add 10 % for contractor's profit on all except (A) 952.06
i.e. on (9568.97 - 48.36) = 9520.61
TOTAL 10093.97
Add 10 % for contractor's profit on all except (A) 1004.56
i.e. on (10093.97 - 48.36) = 10045.61
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 48.29 sqm 833.97
14.21)
LABOUR
0109 Blacksmith 1st class 207.00 day 3 day 621.00
0114 Beldar 190.00 day 3 day 570.00
MACHINARY
0037 Hire charges of ladder 3.5 metre 16.00 day 3 day 48.00
TOTAL 32275.94
TOTAL 33848.04
Add 10 % for contractor's profit on all except (A) 3301.41
i.e. on (33848.04 - 833.97) = 33014.07
TOTAL 1348.96
Add 10 % for contractor's profit on all except (A) 133.86
i.e. on (1348.96 - 10.36) = 1338.60
TOTAL 10913.84
Add 10 % for contractor's profit on all except (A) 1073.25
i.e. on (10913.84 - 181.34) = 10732.50
TOTAL 13514.80
Add 10 % for contractor's profit on all except (A) 1308.51
i.e. on (13514.80 - 429.67) = 13085.13
TOTAL 9008.37
Add 10 % for contractor's profit on all except (A) 872.25
i.e. on (9008.37 - 285.84) = 8722.53
TOTAL 4613.42
Add 10 % for contractor's profit on all except (A) 452.64
i.e. on (4613.42 - 87.04) = 4526.38
@ 1.58kg/m = 14.95kg+
Add wastage @ 5% = 0.75kg.
= 15.70kg. Say 0.157q
1002 Mild steel round bar above 12 mm dia 4013.00 quintal 0.157 quintal 630.04
M.S. flat 25x3.15mm
TOTAL 1138.31
Add 10 % for contractor's profit on all except (A) 111.97
i.e. on (1138.31 - 18.65) = 1119.66
MATERIAL
Tee iron 40x40x6mm = 2m+2m+1m = 5 metres
TOTAL 1184.54
Add 10 % for contractor's profit on all except (A) 114.40
i.e. on (1184.54 - 40.55) = 1143.99
MATERIAL
Angle iron 40x40x6mm = 2m+2m+1m = 5 metres
TOTAL 1173.67
Add 10 % for contractor's profit on all except (A) 113.31
i.e. on (1173.67 - 40.55) = 1133.12
MATERIAL
MS ractangular section 40x40x6mm = 2m+2m+1m
= 5 metres
5 metres @3.5Kg/m = 17.5kg.+
Add wastage @ 5% = 0.87Kg.
= 18.37 kg. Say 0.18 qunital
1008 Hollow steel tube thickness 1.6 mm 50.50 kg 18.37 kg 927.69
M.S. bars 10mm = 1x1m = 1 metre
1 metre @ 0.60kg/m = 0.60Kg.+
Add wastage @ 5% = 0.03Kg.
TOTAL 1285.90
Add 10 % for contractor's profit on all except (A) 124.54
i.e. on (1285.90 - 40.55) = 1245.35
TOTAL 2432.28
Add 10 % for contractor's profit on all except (A) 202.39
i.e. on (2432.28 - 408.40) = 2023.88
0552 MS powder coated butt hinges 100x58x1.90 mm 10.95 each 6 each 65.70
1009 Structurals such as tees,angles channels and R.S. 4560.00 quintal 0.03 quintal 136.80
joists
50x25x5mm. M.S. Angle for threshold 1 metre @
2.75kg per uds =2.75kg. Say 0.03
1010 Flats upto 10 mm in thickness 4433.10 quintal 0.0021 quintal 9.31
Flat15x3 mm, 6x0.10=0.60 m@ 0.35 kg/m =0.21kg
Welding 6x22+2x26=184 cm
0042 Welding by electric plant 1.50 cm 184 cm 276.00
C.C. Block = 0.009 cum
3.1.0.3 Cement concrete 1:3:6 (stone aggregate 20mm) 2970.36 cum 0.029 cum 86.14
(Rate as per Item No 3.1.3)
steel primer 5.00x2(0.08+0.05)=1.30 sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 1.3 sqm 22.45
14.21)
LABOUR
TOTAL 1651.10
Add 10 % for contractor's profit on all except (A) 154.25
i.e. on (1651.10 - 108.59) = 1542.51
0552 MS powder coated butt hinges 100x58x1.90 mm 10.95 each 6 each 65.70
1009 Structurals such as tees,angles channels and R.S. 4560.00 quintal 0.03 quintal 136.80
joists
1010 Flats upto 10 mm in thickness 4433.10 quintal 0.0021 quintal 9.31
flat15x3 mm 6x0.10=0.60 m@ 0.35 kg/m =0.21kg
Welding 6x22+2x26=184 cm
0042 Welding by electric plant 1.50 cm 184 cm 276.00
C.C. Block = 0.009 cum
3.1.0.3 Cement concrete 1:3:6 (stone aggregate 20mm) 2970.36 cum 0.029 cum 86.14
(Rate as per Item No 3.1.3)
steel primer 5.00x2(0.08+0.05)=1.30 sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 1.3 sqm 22.45
14.21)
LABOUR
0110 Blacksmith 2nd class 197.00 day 0.15 day 29.55
0107 Fitter 1st class 207.00 day 0.18 day 37.26
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 1897.21
Add 5 % for water, electricity, sundries and other 89.43
overhead charges on all except (A) i.e. on (1897.21
- 108.59) = 1788.62
0552 MS powder coated butt hinges 100x58x1.90 mm 10.95 each 6 each 65.70
1009 Structurals such as tees,angles channels and R.S. 4560.00 quintal 0.03 quintal 136.80
joists
1010 Flats upto 10 mm in thickness 4433.10 quintal 0.0021 quintal 9.31
Flat15x3 mm 6x0.10=0.60 m@ 0.35 kg/m =0.21kg
Welding 6x22+2x26=184 cm
0042 Welding by electric plant 1.50 cm 184 cm 276.00
C.C. Block = 0.009 cum
3.1.0.3 Cement concrete 1:3:6 (stone aggregate 20mm) 2970.36 cum 0.034 cum 100.99
(Rate as per Item No 3.1.3)
steel primer 5.00x2(0.10+0.05)=1.50sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 1.5 sqm 25.91
14.21)
LABOUR
0110 Blacksmith 2nd class 197.00 day 0.15 day 29.55
0107 Fitter 1st class 207.00 day 0.18 day 37.26
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 1710.77
Add 5 % for water, electricity, sundries and other 79.19
overhead charges on all except (A) i.e. on (1710.77
- 126.90) = 1583.87
TOTAL 1789.96
Add 10 % for contractor's profit on all except (A) 166.31
i.e. on (1789.96 - 126.90) = 1663.06
0552 MS powder coated butt hinges 100x58x1.90 mm 10.95 each 6 each 65.70
1009 Structurals such as tees,angles channels and R.S. 4560.00 quintal 0.03 quintal 136.80
joists
1010 Flats upto 10 mm in thickness 4433.10 quintal 0.0021 quintal 9.31
flat15x3 mm 6x0.10=0.60 m@ 0.35 kg/m =0.21kg
Welding 6x22+2x26=184 cm
0042 Welding by electric plant 1.50 cm 184 cm 276.00
C.C. Block = 0.009 cum
3.1.0.3 Cement concrete 1:3:6 (stone aggregate 20mm) 2970.36 cum 0.034 cum 100.99
(Rate as per Item No 3.1.3)
steel primer 5.00x2(0.10+0.05)=1.50 sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 1.5 sqm 25.91
14.21)
LABOUR
0110 Blacksmith 2nd class 197.00 day 0.2 day 39.40
0107 Fitter 1st class 207.00 day 0.25 day 51.75
0114 Beldar 190.00 day 0.3 day 57.00
TOTAL 2070.11
Add 5 % for water, electricity, sundries and other 97.16
overhead charges on all except (A) i.e. on (2070.11
- 126.90) = 1943.21
TOTAL 2167.27
Add 10 % for contractor's profit on all except (A) 204.04
i.e. on (2167.27 - 126.90) = 2040.37
0552 MS powder coated butt hinges 100x58x1.90 mm 10.95 each 6 each 65.70
1009 Structurals such as tees,angles channels and R.S. 4560.00 quintal 0.03 quintal 136.80
joists
1010 Flats upto 10 mm in thickness 4433.10 quintal 0.0021 quintal 9.31
flat15x3 mm 6x0.10=0.60 m@ 0.35 kg/m =0.21kg
Welding 6x22+2x26=184 cm
0042 Welding by electric plant 1.50 cm 184 cm 276.00
C.C. Block = 0.009 cum
3.1.0.3 Cement concrete 1:3:6 (stone aggregate 20mm) 2970.36 cum 0.038 cum 112.87
(Rate as per Item No 3.1.3)
steel primer 5.00x2(0.015+0.05)=1.65sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 1.65 sqm 28.50
14.21)
LABOUR
0110 Blacksmith 2nd class 197.00 day 0.25 day 49.25
0107 Fitter 1st class 207.00 day 0.3 day 62.10
0114 Beldar 190.00 day 0.35 day 66.50
TOTAL 2303.28
Add 5 % for water, electricity, sundries and other 108.10
overhead charges on all except (A) i.e. on (2303.28
- 141.37) = 2161.91
TOTAL 2411.38
Add 10 % for contractor's profit on all except (A) 227.00
i.e. on (2411.38 - 141.37) = 2270.01
0565 M.S. powder coated sliding door bolt 300x16 mm 77.60 each 2 each 155.20
0569 M.S. powder coated tower bolt (barrel type) 31.05 each 2 each 62.10
250x10 mm
0583 M.S. powder coated handles 125 mm 50.60 each 2 each 101.20
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0109 Blacksmith 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1.5 day 285.00
TOTAL 4169.73
Add 5 % for water, electricity, sundries and other 204.13
overhead charges on all except (A) i.e. on (4169.73
- 87.04) = 4082.69
TOTAL 4373.86
Add 10 % for contractor's profit on all except (A) 428.68
i.e. on (4373.86 - 87.04) = 4286.82
TOTAL 235.16
Add 10 % for contractor's profit on all except (A) 20.84
i.e. on (235.16 - 26.73) = 208.43
Cost of 25 kg 256.00
Cost per kg 10.24
Say 10.00
9.21 Providing and fixing float glass panes with steel glazing clips and special metal sash putty of approved make in steel
doors, windows, ventilators:
9.21.1 4mm thick
Code Description Rate Unit Qty Total
Details of cost for a glass sheet of 1.20X0.45 m
area=0.54 sqm
MATERIALS
2301 Float glass panes 4mm thick 302.40 sqm 0.594 sqm 179.63
= 0.54+10% wastage = 0.594 sqm
2358 Glazing clip 1.00 each 10 each 10.00
2x(3+2)=10 nos
2653 Metal sash putty 30.00 kg 0.726 kg 21.78
= 2x(1.20+0.45) = 3.3 metre @ 0.2 kg/m = 0.66 kg
TOTAL 28.61
Add 10 % for contractor's profit on all except (A) 2.65
i.e. on (28.61 - 2.07) = 26.54
Cost of 1 metre 31.26
Say 31.50
9.27 Supplying and fixing rolling shutter of approved makes made of M.S. laths interlocked together through their entire
length and jointed together at the end by end locks, mounted on specially designed pipe shaft with brackets, side
guides and arrangements for inside and out side locking with push and pull arrangement complete but excluding the
cost of top cover and spring.
3.1.0.3 Cement concrete 1:3:6 (stone aggregate 20mm) 2970.36 cum 0.036 cum 106.93
(Rate as per Item No 3.1.3)
LABOUR
0107 Fitter 1st class 207.00 day 2.5 day 517.50
TOTAL 11539.33
Add 10 % for contractor's profit on all except (A) 1143.24
i.e. on (11539.33 - 106.93) = 11432.40
3.1.0.3 Cement concrete 1:3:6 (stone aggregate 20mm) 2970.36 cum 0.036 cum 106.93
(Rate as per Item No 3.1.3)
LABOUR
0107 Fitter 1st class 207.00 day 2.5 day 517.50
0114 Beldar 190.00 day 2.5 day 475.00
0101 Mason 1st class 207.00 day 0.25 day 51.75
TOTAL 10207.43
Add 5 % for water, electricity, sundries and other 505.03
overhead charges on all except (A) i.e. on
(10207.43 - 106.93) = 10100.50
TOTAL 10712.46
Add 10 % for contractor's profit on all except (A) 1060.55
i.e. on (10712.46 - 106.93) = 10605.53
3.1.0.3 Cement concrete 1:3:6 (stone aggregate 20mm) 2970.36 cum 0.036 cum 106.93
(Rate as per Item No 3.1.3)
LABOUR
0107 Fitter 1st class 207.00 day 2.5 day 517.50
0114 Beldar 190.00 day 2.5 day 475.00
0101 Mason 1st class 207.00 day 0.25 day 51.75
TOTAL 9656.18
Add 5 % for water, electricity, sundries and other 477.46
overhead charges on all except (A) i.e. on (9656.18
- 106.93) = 9549.25
TOTAL 10133.64
Add 10 % for contractor's profit on all except (A) 1002.67
i.e. on (10133.64 - 106.93) = 10026.71
MATERIAL
0944 Rawl plug 10x50 mm 7.90 each 4 each 31.60
LABOUR
0107 Fitter 1st class 207.00 day 2 day 414.00
0114 Beldar 190.00 day 2 day 380.00
MACHINERY
0017 Hire and running charges of pneumatic cutters/ 800.00 day 0.25 day 200.00
hammers with operator.
TOTAL 4910.60
Add 5 % for water, electricity, sundries and other 245.53
overhead charges
TOTAL 5156.13
Add 10 % for contractor's profit 515.61
Cost of 1 Set 5671.74
MATERIAL
1038 Mild steel tubes hot finished welded type 48.60 kg 20.46 kg 994.36
Priming coat 40mm dia.Tube-5.4x22/7x0.0483 =
0.82 sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.82 sqm 14.16
14.21)
0042 Welding by electric plant 1.50 cm 72 cm 108.00
LABOUR
0109 Blacksmith 1st class 207.00 day 0.25 day 51.75
0114 Beldar 190.00 day 1 day 190.00
MACHINERY
0040 Hire charges of hand grinder for steel surface 120.00 day 0.05 day 6.00
TOTAL 1364.27
TOTAL 1431.78
Add 10 % for contractor's profit on all except (A) 141.76
i.e. on (1431.78 - 14.16) = 1417.62
MATERIALS
1040 Mild steel tubes electric resistant or inductionbutt 54.25 kg 18.59 kg 1008.51
welded Grade-250
Priming coat 40mm dia.Tube-5.4x22/7x0.0483 =
0.82 sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.82 sqm 14.16
14.21)
0042 Welding by electric plant 1.50 cm 72 cm 108.00
LABOUR
0109 Blacksmith 1st class 207.00 day 0.25 day 51.75
0114 Beldar 190.00 day 1 day 190.00
MACHINERY
0040 Hire charges of hand grinder for steel surface 120.00 day 0.05 day 6.00
TOTAL 1378.42
Add 5 % for water, electricity, sundries and other 68.21
overhead charges on all except (A) i.e. on (1378.42
- 14.16) = 1364.26
TOTAL 1446.63
Add 10 % for contractor's profit on all except (A) 143.25
i.e. on (1446.63 - 14.16) = 1432.47
MATERIALS
1805 G.I. pipes "B" class 40 mm dia 216.35 metre 5.67 metre 1226.70
Priming coat 40mm dia.Tube-5.4x22/7x0.0483 =
0.82 sqm
TOTAL 1615.61
Add 5 % for water, electricity, sundries and other 80.07
overhead charges on all except (A) i.e. on (1615.61
- 14.16) = 1601.45
TOTAL 1695.68
Add 10 % for contractor's profit on all except (A) 168.15
i.e. on (1695.68 - 14.16) = 1681.52
MATERIAL
1038 Mild steel tubes hot finished welded type 48.60 kg 20.46 kg 994.36
Add wastage @ 5% = 0.97 kg
Total = 20.46 kg
Priming coat 40mm dia.Tube-5.4x22/7x0.0483 =
0.82 sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.82 sqm 14.16
14.21)
Fixing in walls in c.c.1:3:6
3.1.0.3 Cement concrete 1:3:6 (stone aggregate 20mm) 2970.36 cum 0.003 cum 8.91
(Rate as per Item No 3.1.3)
LABOUR
0109 Blacksmith 1st class 207.00 day 0.15 day 31.05
0114 Beldar 190.00 day 0.75 day 142.50
MACHINERY
0040 Hire charges of hand grinder for steel surface 120.00 day 0.05 day 6.00
TOTAL 1196.98
Add 5 % for water, electricity, sundries and other 58.70
overhead charges on all except (A) i.e. on (1196.98
- 23.07) = 1173.91
TOTAL 1255.68
Add 10 % for contractor's profit on all except (A) 123.26
i.e. on (1255.68 - 23.07) = 1232.61
MATERIAL
1040 Mild steel tubes electric resistant or inductionbutt 54.25 kg 18.59 kg 1008.51
welded Grade-250
Add wastage @ 5% = 0.97 kg
Total = 20.46 kg
Priming coat 40mm dia.Tube-5.4x22/7x0.0483 =
0.82 sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.82 sqm 14.16
14.21)
Fixing in walls in c.c.1:3:6
3.1.0.3 Cement concrete 1:3:6 (stone aggregate 20mm) 2970.36 cum 0.003 cum 8.91
(Rate as per Item No 3.1.3)
LABOUR
0109 Blacksmith 1st class 207.00 day 0.15 day 31.05
0114 Beldar 190.00 day 0.75 day 142.50
MACHINERY
0040 Hire charges of hand grinder for steel surface 120.00 day 0.05 day 6.00
TOTAL 1211.13
Add 5 % for water, electricity, sundries and other 59.40
overhead charges on all except (A) i.e. on (1211.13
- 23.07) = 1188.06
TOTAL 1270.53
Add 10 % for contractor's profit on all except (A) 124.75
i.e. on (1270.53 - 23.07) = 1247.46
MATERIAL
1805 G.I. pipes "B" class 40 mm dia 216.35 metre 5.67 metre 1226.70
Add wastage @ 5% = 2.27m
Total = 5.67m
Priming coat 40mm dia.Tube-5.4x22/7x0.0483 =
0.82 sqm
TOTAL 1429.32
Add 5 % for water, electricity, sundries and other 70.31
overhead charges on all except (A) i.e. on (1429.32
- 23.07) = 1406.25
TOTAL 1499.63
Add 10 % for contractor's profit on all except (A) 147.66
i.e. on (1499.63 - 23.07) = 1476.56
LABOUR
0110 Blacksmith 2nd class 197.00 day 0.04 day 7.88
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 84.17
Add 5 % for water, electricity, sundries and other 4.19
overhead charges on all except (A) i.e. on (84.17 -
0.47) = 83.70
TOTAL 88.36
Add 10 % for contractor's profit on all except (A) 8.79
i.e. on (88.36 - 0.47) = 87.89
Cost for 1 clamp 97.15
Say 97.00
9.38 Providing and fixing broken glass 100 mm high in spacing not more than 40 mm both ways and laid in 50 mm thick
(average) cement mortar 1:4 (1 cement : 4 coarse sand ) over compound walls, prapet walls and the like.
TOTAL 2639.64
Add 10 % for contractor's profit on all except (A) 268.80
i.e. on (2639.64 - -48.36) = 2688.00
LABOUR
For fabrication of frame
0107 Fitter 1st class 207.00 day 0.62 day 128.34
0114 Beldar 190.00 day 0.9 day 171.00
TOTAL 11459.19
Add 5 % for water, electricity, sundries and other 572.96
overhead charges
TOTAL 12032.15
Add 10 % for contractor's profit 1203.22
Cost for 40.02 kg 13235.37
Cost for 1 kg 330.71
Say 331.00
9.47 Providing and fixing aluminium work for doors, windows, ventilators and partitions made out of extruded
aluminium standard sections (main section with minimum 1.5mm thickness) conforming to IS: 733, IS: 1285 mitred
and jointed mechanically including aluminium cleats, neoprene weather stripping gasket beveled edge beading,
screws duly fixed in wall/ floor with fixing clips or hold fasteners or bolts and nuts as required aluminium sections
shall be anodized transparent or dyed to approved shade according to IS: 1868, minimum anodic coating shall be of
grade AC-15. (Glazing to be paid for separately:
9.47.2 For shutter of doors, windows & ventilators including providing and making provision for fixing of fitting wherever
required including the cost of PVC/ neoprene gasket required (Fittings shall be paid for separately).
LABOUR
0107 Fitter 1st class 207.00 day 0.32 day 66.24
0105 Carpenter 1st class 207.00 day 0.18 day 37.26
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 5909.23
Add 5 % for water, electricity, sundries and other 295.46
overhead charges
TOTAL 6204.69
Add 10 % for contractor's profit 620.47
Cost for 20.21 kg 6825.16
Cost for 1 kg 337.71
Say 338.00
9.48 Extra for powder coated (minimum 50 micron) aluminium sections instead of anodized.
Code Description Rate Unit Qty Total
Details of cost for 20.21 kg
MATERIALS
Add for :
3252 Epoxy powder coating 50 microns on aluminium 64.00 kg 21.65 kg 1385.60
sections.
Deduct for:
3251 Anodising 15 microns on aluminium sections 42.00 kg -21.65 kg -909.30
TOTAL 476.30
Add 5 % for water, electricity, sundries and other 23.82
overhead charges
TOTAL 500.12
Add 10 % for contractor's profit 50.01
Cost of 20.21 kg 550.13
Cost of 1 kg. 27.22
Say 27.00
9.49 Extra for polyester powder coated (minimum 50 micron) aluminium sections instead of anodized.
Code Description Rate Unit Qty Total
Details of cost for 20.21 kg
MATERIALS
Add for:
3253 Polyester powder coating 50 microns on aluminium 70.00 kg 21.65 kg 1515.50
sections
Deduct for:
TOTAL 606.20
Add 5 % for water, electricity, sundries and other 30.31
overhead charges
TOTAL 636.51
Add 10 % for contractor's profit 63.65
Cost of 20.21 kg 700.16
Cost of 1 kg. 34.64
Say 34.50
9.50 Providing and fixing 12mm thick pre-laminated particle board flat pressed with decorative lamination and
balancing lamination on specified sides exterior Grade – I MDF Board 12 mm thick confirming to IS:14587, including
fixed in aluminium doors, windows shutters and partition frames with C.P. brass/ stainless steel screws etc.
complete.
9.50.1 With decorative lamination on one side and balancing lamination on other side.
Code Description Rate Unit Qty Total
Details of cost for 7 sqm
MATERIAL
12 mm thick particle board = 7.00 sqm
Add 5% wastage = 0.35 sqm
Total qty = 7.35 sqm
2851 Pre-laminated with decorative lamination one side 641.25 sqm 7.35 sqm 4713.19
and other side balancing lamination exterior Grade
- I MDF Board 12 mm thick confirming to IS:14587
= 1.10 sqm
2302 Float glass panes 5mm thick 378.00 sqm 1.1 sqm 415.80
3255 Neoprin/EPDM rubber gasket 25.00 metre 4 metre 100.00
= 1.10 sqm
2303 Float glass panes 6mm thick 453.60 sqm 1.1 sqm 498.96
3255 Neoprin/EPDM rubber gasket 25.00 metre 4 metre 100.00
LABOUR :
0113 Glazier 197.00 day 0.25 day 49.25
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 695.71
Add 5 % for water, electricity, sundries and other 34.79
overhead charges
TOTAL 730.50
Add 10 % for contractor's profit 73.05
Cost for 1 sqm 803.55
Say 804.00
9.51 Providing and fixing glazing in aluminium door, window, ventilator shutters and partitions etc. with PVC/ neoprene
gasket etc. complete. (Cost of aluminium snap beading shall be paid in basic item):
9.51.4 With float glass panes of 8 mm thickness
Code Description Rate Unit Qty Total
Details of cost for 1.0x1.0 = 1.00 sqm
MATERIAL
Float Glass panes 4.0 mm thick = 1.00 sqm
Add for wastage & breakage @ 10% = 0.10 sqm
= 1.10 sqm
2304 Float glass panes 8 mm thick 648.00 sqm 1.1 sqm 712.80
3255 Neoprin/EPDM rubber gasket 25.00 metre 4 metre 100.00
LABOUR :
0113 Glazier 197.00 day 0.25 day 49.25
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 909.55
TOTAL 533.53
Add 10 % for contractor's profit on all except (A) 51.63
i.e. on (533.53 - 17.27) = 516.26
Cost of 1 sqm 585.16
Say 585.00
9.53 Providing and fixing double glazed hermetically sealed glazing in aluminium windows, ventilators and partition etc.
with 6 mm thick clear float glass both side having 12 mm air gap including providing EPDM gasket, perforated
aluminium spacers, desiccants, sealant (Both primary and secondary sealant) etc. complete.
MATERIAL
Anodized aluminium grill = 1 sqm
Add for wastage @ 5% = 0.05 sqm
Total = 1.05 sqm
3202 Anodized aluminium grill (Approx. wt 2.70 kg/sqm) 822.15 sqm 1.05 sqm 863.26
LABOUR
0105 Carpenter 1st class 207.00 day 0.2 day 41.40
Total 514.40
Add 5 % for water, electricity, sundries and other 25.72
overhead charges
Total 540.12
Add 10 % for contractor's profit 54.01
Cost of 1 no 594.13
Say 594.00
9.56 Providing and fixing of floor spring IS: marked (Everite, Door link or any equivalent make) with stainless steel cover
plate
Code Description Rate Unit Qty Total
Details of cost for one number
MATERIAL
TOTAL 1746.31
Add 10 % for contractor's profit on all except (A) 173.92
i.e. on (1746.31 - 7.10) = 1739.21
Cost for each 1920.23
Say 1920.00
9.57 Providing stainless steel railing/ grill made of S.S. flats, hollow S.S. pipe or square/ rectangular sections of approved
design fixing in stair case, balcony or other places with metal fasteners and stainless steel bolts etc complete.
MATERIAL
0860 Stainless steel railing/ grill of SS grade 204 and of 300.00 kg 4.5 kg 1350.00
approved design
0943 Dash fastner 6x75mm 9.00 each 14 each 126.00
LABOUR
0109 Blacksmith 1st class 207.00 day 0.75 day 155.25
0114 Beldar 190.00 day 1 day 190.00
TOTAL 1821.25
Add 5 % for water, electricity, sundries and other 91.06
overhead charges
TOTAL 1912.31
Add 10 % for contractor's profit 191.23
Cost for 4.5 kg. 2103.54
Cost for 1 kg. 467.45
Say 467.00
9.57 Providing stainless steel railing/ grill made of S.S. flats, hollow S.S. pipe or square/ rectangular sections of approved
design fixing in stair case, balcony or other places with metal fasteners and stainless steel bolts etc complete.
MATERIAL
0861 Stainless steel railing/ grill of SS grade 304 and of 350.00 kg 4.5 kg 1575.00
approved design
LABOUR
TOTAL 253806.36
Add 5 % for water, electricity, sundries and other 11656.42
overhead charges on all except (A) i.e. on
(253806.36 - 20677.98) = 233128.38
TOTAL 265462.78
Add 10 % for contractor's profit on all except (A) 24478.48
i.e. on (265462.78 - 20677.98) = 244784.80
LABOUR :
0106 Carpenter 2nd class 197.00 day 2 day 394.00
0114 Beldar 190.00 day 2 day 380.00
TOTAL 15838.00
Add 5 % for water, electricity, sundries and other 791.90
overhead charges
TOTAL 16629.90
Add 10 % for contractor's profit 1662.99
Cost for 7 sqm 18292.89
Cost for 1 sqm 2613.27
Say 2613.00
LABOUR
0109 Blacksmith 1st class 207.00 day 0.15 day 31.05
0114 Beldar 190.00 day 0.15 day 28.50
TOTAL 59.55
Add 5 % for water, electricity, sundries and other 2.98
overhead charges
TOTAL 62.53
Add 10 % for contractor's profit 6.25
Cost of 3.00 metres 68.78
Cost of 1.00 metre 22.92
Say 23.00
10.2 Extra for straight cutting in C.G.I. sheet roofing for making opening of area exceeding 0.40 sqm for chimney stacks,
sky light etc.
LABOUR
0109 Blacksmith 1st class 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 0.14 day 26.60
TOTAL 55.58
Add 5 % for water, electricity, sundries and other 2.78
overhead charges
TOTAL 58.36
Add 10 % for contractor's profit 5.84
Cost of 3.00 metres 64.20
Cost of 1.00 metre 21.40
Say 21.50
10.2 Extra for straight cutting in C.G.I. sheet roofing for making opening of area exceeding 0.40 sqm for chimney stacks,
sky light etc.
10.2.3 0.63 mm thick sheet
Code Description Rate Unit Qty Total
Details of cost for 3 metres periphery
Assuming a hole of of size 100 cmx50cm and area =
0.50 sqm and the perimeter of the hole 3 metre
LABOUR
0109 Blacksmith 1st class 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 0.12 day 22.80
TOTAL 47.64
Add 5 % for water, electricity, sundries and other 2.38
overhead charges
TOTAL 50.02
Add 10 % for contractor's profit 5.00
Cost of 3.00 metres 55.02
Cost of 1.00 metre 18.34
Say 18.50
10.2 Extra for straight cutting in C.G.I. sheet roofing for making opening of area exceeding 0.40 sqm for chimney stacks,
sky light etc.
10.2.4 0.50 mm thick sheet
Code Description Rate Unit Qty Total
Details of cost for 3 metres periphery
Assuming a hole of of size 100 cmx50cm and area =
0.50 sqm and the perimeter of the hole 3 metre
LABOUR
0109 Blacksmith 1st class 207.00 day 0.1 day 20.70
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 39.70
Add 5 % for water, electricity, sundries and other 1.99
overhead charges
LABOUR
0109 Blacksmith 1st class 207.00 day 3.2 day 662.40
0114 Beldar 190.00 day 6.4 day 1216.00
TOTAL 1878.40
Add 5 % for water, electricity, sundries and other 93.92
overhead charges
TOTAL 1972.32
Add 10 % for contractor's profit 197.23
Cost of 15.71 metres 2169.55
Cost of 1.00 metre 138.09
Say 138.00
10.3 Extra for racking or circular cutting in C.G.I. sheets roofing:
10.3.2 0.80 mm thick sheet
Code Description Rate Unit Qty Total
Details of cost for 10 holes of 0.5 metre dia-metre
LABOUR
0109 Blacksmith 1st class 207.00 day 3.15 day 652.05
0114 Beldar 190.00 day 6.3 day 1197.00
TOTAL 1849.05
Add 5 % for water, electricity, sundries and other 92.45
overhead charges
TOTAL 1941.50
Add 10 % for contractor's profit 194.15
Cost of 15.71 metres 2135.65
Cost of 1.00 metre 135.94
Say 136.00
10.3 Extra for racking or circular cutting in C.G.I. sheets roofing:
10.3.3 0.63 mm thick sheet
Code Description Rate Unit Qty Total
Details of cost for 10 holes of 0.5 metre dia-metre
LABOUR
LABOUR
0109 Blacksmith 1st class 207.00 day 2.5 day 517.50
0114 Beldar 190.00 day 5 day 950.00
TOTAL 1467.50
Add 5 % for water, electricity, sundries and other 73.38
overhead charges
TOTAL 1540.88
Add 10 % for contractor's profit 154.09
Cost of 15.71 metres 1694.97
Cost of 1.00 metre 107.89
Say 108.00
10.4 Extra for making opening or recesses in C.G.I. sheets roofing of girth not more than 1 metre.
10.4.1 Upto 100 sq.cm
Code Description Rate Unit Qty Total
Details of cost for 1 no of area 100 sqcm
Periphery = 35.45cm say 35 cm
LABOUR
0105 Carpenter 1st class 207.00 day 0.03 day 6.21
0114 Beldar 190.00 day 0.03 day 5.70
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 1 sqm 11.00
TOTAL 22.91
Add 5 % for water, electricity, sundries and other 1.15
overhead charges
TOTAL 24.06
Add 10 % for contractor's profit 2.41
Cost for each 26.47
Say 26.50
10.4 Extra for making opening or recesses in C.G.I. sheets roofing of girth not more than 1 metre.
10.4.2 Above 100 sq.cm. upto 400 sq.cm
0.9mx1.8m
Three pieces will be 0.9m long and
0.60m wide overlapping 22.5cm.
MATERIAL
G.I. plain sheets 1mm thick
1.80x0.90m size 5 nos. @
13.32 each sheet = 66.60 Kg +
1055 G.I. plain washer for seam bolts 0.25 each 28 each 7.00
2396 Bitumen washer 0.20 each 28 each 5.60
LABOUR
0121 Mistry 207.00 day 0.4 day 82.80
0109 Blacksmith 1st class 207.00 day 2.2 day 455.40
0114 Beldar 190.00 day 2.6 day 494.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 2 sqm 22.00
0017 Hire and running charges of pneumatic cutters/ 800.00 day 0.4 day 320.00
hammers with operator.
TOTAL 5340.40
Add 5 % for water, electricity, sundries and other 267.02
overhead charges
TOTAL 5607.42
Add 10 % for contractor's profit 560.74
Cost of 10.35 metres 6168.16
Cost of 1.00 metre 595.95
Say 596.00
10.5 Providing ridges or hips of 60cm overall width in plain G.I. sheet fixed with galvanized washers J or L hooks, bolts
and nuts 8mm G.I. limpet and bitumen washers complete.
10.5.2 0.80 mm thick sheet with zinc coating not less than 275 gm/sqm
Code Description Rate Unit Qty Total
Consider the length of the ridge 10.35 metres.
0.9mx1.8m
Three pieces will be 0.9m long and
0.60m wide overlapping 22.5cm.
MATERIAL
G.I. plain sheets 0.80 thick
1.80x0.90m size 5 nos. @
11.39Kg. sheet = 56.95Kg +
Add 2% wastage = 1.14 Kg.
= 58.09 Kg. or 0.58 qtl.
2371 Galvanised steel plain sheets 5670.00 quintal 0.58 quintal 3288.60
G.I. seam bolts and nuts-
25mmx6mm (There are 14 joints)
2467 Seam bolts and nuts 6 mm dia and 25 mm long 3.50 each 28 each 98.00
1055 G.I. plain washer for seam bolts 0.25 each 28 each 7.00
2396 Bitumen washer 0.20 each 28 each 5.60
1055 G.I. plain washer for seam bolts 0.25 each 28 each 7.00
2396 Bitumen washer 0.20 each 28 each 5.60
Labour:
0121 Mistry 207.00 day 0.4 day 82.80
0109 Blacksmith 1st class 207.00 day 2.1 day 434.70
0114 Beldar 190.00 day 2.5 day 475.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 2 sqm 22.00
0017 Hire and running charges of pneumatic cutters/ 800.00 day 0.25 day 200.00
hammers with operator.
TOTAL 3990.00
Add 5 % for water, electricity, sundries and other 199.50
overhead charges
TOTAL 4189.50
Add 10 % for contractor's profit 418.95
Cost of 10.35 metres 4608.45
Cost of 1.00 metre 445.26
Say 445.00
0.9mx1.8m
Three pieces will be 0.9m long and
0.60m wide overlapping 22.5cm.
MATERIAL
G.I. plain sheets 1mm thick
1.80x0.90m size 5 nos. @
6.66 kg each sheet = 33.30 Kg +
Add 2% wastage = 0.66 Kg.
= 33.96 Kg. or 0.339 qtl.
2371 Galvanised steel plain sheets 5670.00 quintal 0.339 quintal 1922.13
G.I. seam bolts and nuts-
25mmx6mm (There are 14 joints)
2467 Seam bolts and nuts 6 mm dia and 25 mm long 3.50 each 28 each 98.00
1055 G.I. plain washer for seam bolts 0.25 each 28 each 7.00
2396 Bitumen washer 0.20 each 28 each 5.60
LABOUR
0121 Mistry 207.00 day 0.4 day 82.80
0109 Blacksmith 1st class 207.00 day 2.2 day 455.40
0114 Beldar 190.00 day 2.6 day 494.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 2 sqm 22.00
0017 Hire and running charges of pneumatic cutters/ 800.00 day 0.4 day 320.00
hammers with operator.
TOTAL 3406.93
Add 5 % for water, electricity, sundries and other 170.35
overhead charges
TOTAL 3577.28
Add 10 % for contractor's profit 357.73
Cost of 10.35 metres 3935.01
Cost of 1.00 metre 380.19
Say 380.00
10.6 Providing valley of 90cm overall width in plain G.I. sheet 1.6 mm thick with zinc coating not less than 350gm/sqm
fixed with galvanized iron J or L hooks, bolts and nuts 8 mm dia G.I. limpet and bitumen washers complete.
1055 G.I. plain washer for seam bolts 0.25 each 12 each 3.00
2396 Bitumen washer 0.20 each 12 each 2.40
LABOUR
0121 Mistry 207.00 day 0.4 day 82.80
0109 Blacksmith 1st class 207.00 day 2.2 day 455.40
0114 Beldar 190.00 day 2.5 day 475.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 3 sqm 33.00
0017 Hire and running charges of pneumatic cutters/ 800.00 day 0.6 day 480.00
hammers with operator.
TOTAL 8502.34
Add 5 % for water, electricity, sundries and other 425.12
overhead charges
TOTAL 8927.46
Add 10 % for contractor's profit 892.75
Cost of 9.3250 metres 9820.21
Cost of 1.00 metre 1053.10
Say 1053.00
10.7 Providing and flashing 38cm. over all width in plain G.I. sheet fixed, with galvanized iron J or L hooks bolts and nuts
G.I. limpet washers and fixed in walls with cement mortar 1:3 (1 cement: 3 sand)
10.7.1 G.I. plain sheet 1.25mm thick (weight 10.56 kg/m2)
Code Description Rate Unit Qty Total
Details of cost for 12.125 m
Consider a length of flashing 12.125 metres.
MATERIAL
G.I. plain sheet 1mm thick 3.2x0.75m
2 nos. @ 24.22 Kg./each sheet
qty = 48.44 kg
Add 2% wastage = 0.97 Kg
= 49.41 Kg. or 0.4941 quintal
2371 Galvanised steel plain sheets 5670.00 quintal 0.4941 quintal 2801.55
G.I. seam bolts and nuts-25mmx6mm
(taking 2 bolts per joints)
2467 Seam bolts and nuts 6 mm dia and 25 mm long 3.50 each 6 each 21.00
MATERIAL
G.I. plain sheet 1mm thick 3.2x0.75m
2 nos. @ 20.64 Kg./each sheet
qty = 41.28
Add 2% wastage = 0.83 Kg
= 42.11 Kg. or 0.4211 quintal
2371 Galvanised steel plain sheets 5670.00 quintal 0.4211 quintal 2387.64
G.I. seam bolts and nuts-25mmx6mm
(taking 2 bolts per joints)
2467 Seam bolts and nuts 6 mm dia and 25 mm long 3.50 each 6 each 21.00
2394 Galvanised steel J or L hooks 8 mm dia 7.90 each 476 each 3760.40
2396 Bitumen washer 0.20 each 476 each 95.20
1053 G.I. plain washer thick 0.30 each 476 each 142.80
LABOUR
0121 Mistry 207.00 day 2.34 day 484.38
0106 Carpenter 2nd class 197.00 day 9.34 day 1839.98
0114 Beldar 190.00 day 9.34 day 1774.60
TOTAL 129595.36
Add 5 % for water, electricity, sundries and other 6479.77
overhead charges
TOTAL 136075.13
Add 10 % for contractor's profit 13607.51
Cost of 216.14 sqm. 149682.64
Cost of 1.00 sqm. 692.52
Say 693.00
10.13 Supply and fixing of precoated TILE PATTERN profile sheets of approved make, colour, over all size, corrugation
shape and pitch, having total coated thickness (TCT) 0.45 mm (approx weight 4.9 kg/sqm) with Zn-Al coating and
superior paint and having yeild strength of 550 MPa. Sheet should have protective guard film of 25 microns
minimum to avoid scratches while transportation. The sheet shall be fixed using self drilling /self tapping screws of
size (5.5x 55mm) with EPDM seal or with polymer coated J or L hooks, bolts and nuts 8mm diameter with bitumen
and G.I. limpet washers or with G.I. limpet washers filled with white lead complete upto any pitch excluding the cost
of purlins, rafters and trusses and including cutting to size and shape wherever required.
2394 Galvanised steel J or L hooks 8 mm dia 7.90 each 476 each 3760.40
2396 Bitumen washer 0.20 each 476 each 95.20
1053 G.I. plain washer thick 0.30 each 476 each 142.80
LABOUR
0121 Mistry 207.00 day 2.34 day 484.38
0106 Carpenter 2nd class 197.00 day 9.34 day 1839.98
0114 Beldar 190.00 day 9.34 day 1774.60
TOTAL 176325.36
Add 5 % for water, electricity, sundries and other 8816.27
overhead charges
TOTAL 185141.63
Add 10 % for contractor's profit 18514.16
Cost of 216.14 sqm. 203655.79
Cost of 1.00 sqm. 942.24
Say 942.00
10.14 Providing and fixing 2mm thick semi transparent polycarbonate profile roofing sheet of approved make and colour
to make any normal roofing / covering and fixing as per manufacture specification at spacing not more than 1.2 m
centre to centre with EPDM gasket and silicon sealant fixed with self drilling stainless steel screws all complete as
per direction of Engineer-in-Charge.
= 233.65sqm.
LABOUR
0121 Mistry 207.00 day 0.5 day 103.50
0106 Carpenter 2nd class 197.00 day 2 day 394.00
0114 Beldar 190.00 day 2 day 380.00
TOTAL 877.50
Add 5 % for water, electricity, sundries and other 43.88
overhead charges
TOTAL 921.38
Add 10 % for contractor's profit 92.14
Cost of 216.14 sqm. 1013.52
Cost of 1.00 sqm. 4.68
Say 4.70
10.16 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm +/- 5% total coated thickness
(TCT), Zinc coating 120gsm as per IS: 277 in 240mpa steel grade, 5-7 microns epoxy primer on both side of the sheet
and polyester top coat 15-18 microns using self drilling/ self tapping screws or with polymer coated J or L hooks,
bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers complete :
2374 Precoated galvanised steel plain ridges. 398.00 metre 23.11 metre 9197.78
LABOUR
0121 Mistry 207.00 day 0.14 day 28.98
0106 Carpenter 2nd class 197.00 day 0.55 day 108.35
0114 Beldar 190.00 day 1.64 day 311.60
TOTAL 9646.71
Add 5 % for water, electricity, sundries and other 482.34
overhead charges
TOTAL 10129.05
Add 10 % for contractor's profit 1012.91
Cost of 20.20 metre 11141.96
Cost of 1.00 metre 551.58
Say 552.00
10.16 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm +/- 5% total coated thickness
(TCT), Zinc coating 120gsm as per IS: 277 in 240mpa steel grade, 5-7 microns epoxy primer on both side of the sheet
and polyester top coat 15-18 microns using self drilling/ self tapping screws or with polymer coated J or L hooks,
bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers complete :
MATERIALS
Apron piece is to be fixed with same hooks as the
sheets
2375 Precoated galvanised steel flashings/aprons. 398.00 metre 23.11 metre 9197.78
LABOUR
0121 Mistry 207.00 day 0.07 day 14.49
0106 Carpenter 2nd class 197.00 day 0.28 day 55.16
0114 Beldar 190.00 day 0.82 day 155.80
TOTAL 9423.23
Add 5 % for water, electricity, sundries and other 471.16
overhead charges
TOTAL 9894.39
Add 10 % for contractor's profit 989.44
Cost of 20.20 metre 10883.83
Cost of 1.00 metre 538.80
Say 539.00
10.16 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm +/- 5% total coated thickness
(TCT), Zinc coating 120gsm as per IS: 277 in 240mpa steel grade, 5-7 microns epoxy primer on both side of the sheet
and polyester top coat 15-18 microns using self drilling/ self tapping screws or with polymer coated J or L hooks,
bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers complete :
1055 G.I. plain washer for seam bolts 0.25 each 10 each 2.50
2396 Bitumen washer 0.20 each 5 each 1.00
LABOUR
0121 Mistry 207.00 day 0.04 day 8.28
0106 Carpenter 2nd class 197.00 day 0.06 day 11.82
0114 Beldar 190.00 day 0.4 day 76.00
TOTAL 3465.10
Add 5 % for water, electricity, sundries and other 173.26
overhead charges
TOTAL 3638.36
Add 10 % for contractor's profit 363.84
Cost of 8.23 metre 4002.20
Cost of 1.00 metre 486.29
Say 486.00
MATERIALS
2379 Precoated galvanised steel crimp curve 487.25 sqm 22.483 sqm 10954.84
2394 Galvanised steel J or L hooks 8 mm dia 7.90 each 40 each 316.00
1053 G.I. plain washer thick 0.30 each 40 each 12.00
2396 Bitumen washer 0.20 each 40 each 8.00
LABOUR
0121 Mistry 207.00 day 0.1 day 20.70
0106 Carpenter 2nd class 197.00 day 0.3 day 59.10
0114 Beldar 190.00 day 1 day 190.00
TOTAL 11560.64
Add 5 % for water, electricity, sundries and other 578.03
overhead charges
TOTAL 12138.67
Add 10 % for contractor's profit 1213.87
Cost of 21.412 sqm 13352.54
Cost of 1.00 sqm 623.60
Say 624.00
10.16 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm +/- 5% total coated thickness
(TCT), Zinc coating 120gsm as per IS: 277 in 240mpa steel grade, 5-7 microns epoxy primer on both side of the sheet
and polyester top coat 15-18 microns using self drilling/ self tapping screws or with polymer coated J or L hooks,
bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers complete :
MATERIAL
Appron flashing pieces of 1.08 metre
length = 22 nos.+
Add 5% wastage = 1.08 No.
= 23 nos.
3110 Apron flashing piece 35.20 each 23 each 809.60
LABOUR
MATERIAL
Eaves filler piece of 1.08 metre
length = 22 nos.+
Add 5% wastage = 1.08 No.
= 23 nos.
3111 Eaves filler piece 55.00 each 23 each 1265.00
LABOUR
0121 Mistry 207.00 day 1 day 207.00
0105 Carpenter 1st class 207.00 day 0.3 day 62.10
0114 Beldar 190.00 day 0.9 day 171.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 2.8 sqm 30.80
TOTAL 1735.90
Add 5 % for water, electricity, sundries and other 86.80
overhead charges
TOTAL 1822.70
Add 10 % for contractor's profit 182.27
Cost of 20.20 metre 2004.97
Cost of 1.00 metre 99.25
Say 99.50
10.23 Providing and fixing asbestos cement roofing accessories with galvanized iron J or L hooks, bolts and nuts and/or G.I.
seam bolts & nuts, G.I. plain & bitumen washers etc. complete.
10.23.3 North light and ventilator curves
Code Description Rate Unit Qty Total
Details for shed of 20.2 metres completed length
MATERIAL
North light and ventilator flashing piece of 1.08
metre
MATERIAL
Appron flashing pieces of 2.24 metre
length = 10 nos.+
Add 5% wastage = 0.5 No.
= 11 nos.
3113 Barge Boards 66.00 each 11 each 726.00
LABOUR
0121 Mistry 207.00 day 1 day 207.00
0105 Carpenter 1st class 207.00 day 0.3 day 62.10
0114 Beldar 190.00 day 0.9 day 171.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 2.8 sqm 30.80
TOTAL 1196.90
Add 5 % for water, electricity, sundries and other 59.85
overhead charges
TOTAL 1256.75
Add 10 % for contractor's profit 125.68
Cost of 20.20 metre 1382.43
Cost of 1.00 metre 68.43
Say 68.50
10.23 Providing and fixing asbestos cement roofing accessories with galvanized iron J or L hooks, bolts and nuts and/or G.I.
seam bolts & nuts, G.I. plain & bitumen washers etc. complete.
10.23.5 Ridge finials
10.24.1 2mm thick corrugated (2.5" or 4.2" or 6") or step-down (2"or 3"or 6") as specified.
Code Description Rate Unit Qty Total
Details of cost for area of roof.
2x18.09x5.1 = 184.518 sqm.
Materials:
2537 UV stabilised 2.0 mm thick corrugated FRP sheet 450.00 sqm 240.408 sqm 108183.60
2868 Insulating board 12 mm thick Natural colour face 182.00 sqm 11 sqm 2002.00
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.0836 cum 71.06
TOTAL 588.82
Add 5 % for water, electricity, sundries and other 29.44
overhead charges
TOTAL 618.26
Add 10 % for contractor's profit 61.83
Cost of 10.00 metre 680.09
Cost of 1.00 metre 68.00
Say 68.00
10.42 Making khurras 45x45 cm with average minimum thickness of 5 cm cement concrete 1:2:4 (1 cement : 2 coarse
sand : 4 graded stone aggregate of 20 mm nominal size) over P.V.C. sheet 1mx1mx650 micron thick (0.65mm),
finished with 12mm cement plaster 1:3 (1 cement : 3 coarse sand) and a coat of neat cement rounding the edge
sand making and finishing the outlet complete.
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.0022 cum 1.87
TOTAL 177.84
Add 5 % for water, electricity, sundries and other 8.89
overhead charges
TOTAL 186.73
Add 10 % for contractor's profit 18.67
Cost of 1 no. 205.40
Say 205.00
10.43 Providing and laying single wheel tilling without batten.
Code Description Rate Unit Qty Total
Details of cost for 10 x1.0 = 1.0 sqm
MATERIALS
0423 Single wheel tiles 250x(138+100)mm 6.00 each 395 each 2370.00
LABOUR
Total = 29 Nos
0422 Mangalore ridge tiles 380mmx230mm 12.00 each 29 each 348.00
LABOUR
0101 Mason 1st class 207.00 day 0.1 day 20.70
0114 Beldar 190.00 day 0.2 day 38.00
Total 406.70
Add 5 % for water, electricity, sundries and other 20.34
overhead charges
Total 427.04
Add 10 % for contractor's profit 42.70
Cost for 3.60 meter 469.74
Cost for 1 meter 130.48
Say 130.00
10.48 Providing and fixing Terracota tiles of approved design and size over and including 20mm thick cement plaster 1:3
including floating coat of cement slurry on bed and filling joints with neat cement slurry mixed with pigment to
match the shade of tiles complete.
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.2 cum 671.25
(Rate as per item No 5.8)
LABOUR
0101 Mason 1st class 207.00 day 2 day 414.00
0114 Beldar 190.00 day 2 day 380.00
Total 4555.25
Add 5 % for water, electricity, sundries and other 227.76
overhead charges
Total 4783.01
Add 10 % for contractor's profit 478.30
Cost for 10 sqm 5261.31
Cost for 1 sqm 526.13
Say 526.00
2876 Particle board ceiling tile 12 thick 234.00 sqm -10 sqm -2340.00
Difference of cost 3960.00
Add 5 % for water, electricity, sundries and other 198.00
overhead charges
TOTAL 4158.00
Add 10 % for contractor's profit 415.80
Cost of 10.00 sqm. 4573.80
Cost of 1.00 sqm. 457.38
Say 457.00
10.59 Providing and fixing steel frame work for partition wall made from steel rectangular tube of 50x25mmx1.25mm
(wall thickness) with welded joints complete with grinding the welded joints. The members of the frame work along
the wall/floor/ceiling shall form a grid of not more than 1100mmx1100mm centre to centre of member in any
direction and are to be screwed using 75x10 mm wood screws to the prefixed wooden plugs at an interval of not
more than 500mm centre to center. The vertical members to be grouted in the floor upto 50mm deep including
repairing of wall/floor/ceiling with 1:3 Cement mortar.
TOTAL 3335.20
Add 10 % for contractor's profit on all except (A) 326.68
i.e. on (3335.20 - 68.39) = 3266.81
0037 Hire charges of ladder 3.5 metre 16.00 day 1 day 16.00
TOTAL 6564.81
Add 5 % for water, electricity, sundries and other 328.24
overhead charges
TOTAL 6893.05
Add 10 % for contractor's profit 689.31
Cost for 75.42Kg. 7582.36
Cost for 1 Kg. 100.53
Say 101.00
10.61 Providing and fixing at all height false ceiling consisting of frame work "W" / "U" / "L" sections made of G.I. sheet
with zinc coating of grade 120 consisting of angle cleats of size 25mm wide x 1.6mm thick with flanges of 22mm and
37mm at 1200mm centre to centre one flange fixed to the ceiling with dash fastener 12.5mm diax40mm long with
6mm dia bolts to the angle hangers of 25x25x0.55mm of required length, and other end of angle hanger being fixed
with nut and bolts to G.I. channels 45x15x0.9mm running at the rate of 1200mm centre to centre to which the
ceiling section 0.5mm thick button wedge of 80mm with tapered flanges of 26mm each having clips of 10.5mm at
450mm centre to centre shall be fixed in a direction perpendicular to G.I. channel with connecting clips made out of
2.64mm diax230mm long G.I. wire at every junction including fixing the gypsum board with ceiling section and
perimeter channels 0.55mm thick 27mm high having flanges of 20mm and 30mm long, the perimeter of ceiling fixed
to wall/partition with the help of rawl plugs at 450mm centre to centre with 25mm long drive-all screws @ 230mm
interval including jointing and fixing to a flush finish of tapered and square edges of the board with recommended
filler, jointing tapes, finisher and two coats of primer suitable for board as per manufactures specification and also
including the cost of making openings for light fittings, grills, diffusers, cutouts made with frame of perimeter
channels suitably fixed including providing and fixing 12.5 mm thick tapered edge gypsum board conforming to IS:
2095- Part-I all complete as per drawing and specification and direction of the Engineer in Charge but excluding the
cost of painting.
Code Description Rate Unit Qty Total
Details of cost for 10.8x9.6m = 103.68sqm.
Materials
Gypsum board 12.5mm thick = 103.68 sqm.+
2383 Perimetre channel ("U" section) size 19.00 metre 41.84 metre 794.96
27x20x30xmm made of G.I. sheet 0.55mm thick
(wt = 0.322 kg/m)
2384 Intermediate channel ("U" section) size 30.00 metre 90.72 metre 2721.60
45x15x15mm made of G.I. sheet 0.90mm thick (wt
= 0.512 kg/m)
2387 Ceiling angle ("L" section) size 25x25mm made of 12.00 metre 10.8 metre 129.60
G.I. sheet 0.55mm thick (wt = 0.202 kg/m)
TOTAL 59049.72
Add 5 % for water, electricity, sundries and other 2952.49
overhead charges
TOTAL 62002.21
Add 10 % for contractor's profit 6200.22
Cost for 103.68 sqm. 68202.43
Cost of 1 Sqm. 657.81
Say 658.00
10.62 Providing and fixing Gypsum board wall paneling consisting of frame work "W" / "U" / "L" sections made of G.I.
sheet with zinc coating of grade 120 consisting of G.I. section, 'W' profile (0.55mm thick ) having a knurled web of
51.55mm and two flanges of 26mm each with lips of 10.5 mm placed at 610mm center to center in perimeter
channel having one flange of 20mm and another flange of 30mm with thickness of 0.55mm and web of length
27mm fixed on the floor and the ceiling with the nylon sleeves with fully threaded self-tapping drive all screws, and
12.5mm Gypsum board conforming to IS: 2095 - 1996: Part - I, fixed to 'W' profile with 25 mm countersunk ribbed
head screws at 200mm center to center, joints of the boards are finished with specially formulated jointing
compound and 48mm wide fibre tape to provide seamless finish all complete as per the drawing & directions of
Engineer-in-charge.
MATERIALS
3852 Nylon sleeves & wooden screws (40mm) 1.80 each 64 each 115.20
3853 Counter sunk ribbed head screw 25mm. 0.70 each 176 each 123.20
3805 Joint paper tape roll (120m) 143.00 roll 0.19 roll 27.17
2624 Primer ( for gypsum board) 126.00 litre 2.25 litre 283.50
LABOUR:-
0105 Carpenter 1st class 207.00 day 3.8 day 786.60
0114 Beldar 190.00 day 4.6 day 874.00
0111 Painter 197.00 day 0.25 day 49.25
MACHINERY
0031 Hire charges of Portable Electric Drill Machine 50.00 day 1.9 day 95.00
2386 Stud channel ("U" section) size 48x34x36mm made 30.00 metre 40.15 metre 1204.50
of G.I. sheet 0.55mm thick (wt = 0.493 kg/m)
0594 All drive screws ( for gypsum board) 0.50 each 392 each 196.00
0943 Dash fastner 6x75mm 9.00 each 22 each 198.00
0944 Rawl plug 10x50 mm 7.90 each 18 each 142.20
2645 Plaster of Paris 6.40 kg 19.27 kg 123.33
2609 Glue 55.00 kg 4.82 kg 265.10
3805 Joint paper tape roll (120m) 143.00 roll 0.584 roll 83.51
2624 Primer ( for gypsum board) 126.00 litre 5.26 litre 662.76
1051 Galvanised steel bolts & nuts 6 mm dia and 25 0.80 each 44 each 35.20
mmlong round head with slots
1055 G.I. plain washer for seam bolts 0.25 each 44 each 11.00
Labour
0107 Fitter 1st class 207.00 day 9 day 1863.00
0111 Painter 197.00 day 1 day 197.00
0114 Beldar 190.00 day 9 day 1710.00
MACHINERY
0031 Hire charges of Portable Electric Drill Machine 50.00 day 4.5 day 225.00
2363 G.I. suspension rod 4mm dia 29.00 metre 15 metre 435.00
5x3x1m = 15m
2364 Galvanised suspension spring clip 29.00 each 15 each 435.00
5x3 = 15 nos
2365 Wall trim box of size 15x30x15mm made from 103.00 metre 29.6 metre 3048.80
0.4mm thick aluminium alloy sheet
(10+4.5)x2 = 29 m
+ 0.6 m (wastage @2%) = 29.6 m
0944 Rawl plug 10x50 mm 7.90 each 15 each 118.50
Labour
0107 Fitter 1st class 207.00 day 10 day 2070.00
0114 Beldar 190.00 day 20 day 3800.00
MACHINERY
0031 Hire charges of Portable Electric Drill Machine 50.00 day 5 day 250.00
10.64.2 With long perforated panels having perforation with 2.0mm dia and 5mm center to center and pasted with non
woven tissue on the back side
Code Description Rate Unit Qty Total
Cost for 45 sqm (4.5mx10m)
Material
2363 G.I. suspension rod 4mm dia 29.00 metre 15 metre 435.00
5x3x1m = 15m
2364 Galvanised suspension spring clip 29.00 each 15 each 435.00
5x3 = 15 nos
2365 Wall trim box of size 15x30x15mm made from 103.00 metre 29.6 metre 3048.80
0.4mm thick aluminium alloy sheet
(10+4.5)x2 = 29 m
+ 0.6 m (wastage @2%) = 29.6 m
0944 Rawl plug 10x50 mm 7.90 each 15 each 118.50
Labour
0107 Fitter 1st class 207.00 day 10 day 2070.00
0114 Beldar 190.00 day 20 day 3800.00
MACHINERY
0031 Hire charges of Portable Electric Drill Machine 50.00 day 5 day 250.00
10.65.2 With perforated tiles having perforation with 2.5mm dia and 5mm center to center and pasted with non woven
tissue on the back side
Code Description Rate Unit Qty Total
Cost for 45 sqm (4.5mx10m)
Material
0307 Stone chippings/ screenings 10/ 11.2 mm nominal 850.00 cum 0.14 cum 119.00
size
0253 Coarse sand 360.00 cum 0.04 cum 14.40
0251 Portland Cement 5400.00 tonne 0.12 tonne 648.00
2602 Painting Brush 60.00 each 0.5 each 30.00
LABOUR
0101 Mason 1st class 207.00 day 3.5 day 724.50
0114 Beldar 190.00 day 3.5 day 665.00
MACHINARY
0036 Hire charges of scaffolding 11.00 sqm 3 sqm 33.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.5 day 100.00
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.01 day 7.00
TOTAL 2723.11
Add 5 % for water, electricity, sundries and other 136.16
overhead charges
TOTAL 2859.27
Add 10 % for contractor's profit 285.93
Cost of 10.00 sqm 3145.20
Cost of 1.00 sqm 314.52
Say 315.00
11.23 Extra for providing aluminium channels of size 15mmx10mmx1.5mm in place of sunk and band panels.
Code Description Rate Unit Qty Total
Details of cost for 30 meters
Materials:-
3203 Aluminium T or L sections 220.50 kg 5.762 kg 1270.52
Aluminium channel 15x15x1.5mm
30x3x0.015x0.0015x2710=5.488 kg.
Add wastage 5% = 0.274 kg
Total =5.762 kg
11.33.1 12 mm thick
Code Description Rate Unit Qty Total
Detail of cost for 10 metre long and 10 cm wide
band
MATERIALS
5.4 Cement Mortar C.M. 1:4 (1 cement : 4 fine sand) 2654.27 cum 0.014 cum 37.16
(Rate as per item No 5.4)
LABOUR
0104 Mason 2nd class 197.00 day 0.75 day 147.75
0114 Beldar 190.00 day 0.75 day 142.50
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 2 sqm 22.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.05 day 10.00
TOTAL 359.41
Add 5 % for water, electricity, sundries and other 17.97
overhead charges
TOTAL 377.38
Add 10 % for contractor's profit 37.74
Cost of 10.00 metre long and 10 cm wide band 415.12
11.33.2 18 mm thick
Code Description Rate Unit Qty Total
Detail of cost for 10 metre long and 10 cm wide
band
MATERIALS
5.4 Cement Mortar C.M. 1:4 (1 cement : 4 fine sand) 2654.27 cum 0.024 cum 63.70
(Rate as per item No 5.4)
LABOUR
0104 Mason 2nd class 197.00 day 1 day 197.00
0114 Beldar 190.00 day 1 day 190.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 2 sqm 22.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.05 day 10.00
TOTAL 482.70
Add 5 % for water, electricity, sundries and other 24.14
overhead charges
TOTAL 506.84
Add 10 % for contractor's profit 50.68
Cost of 10.00 metre long and 10 cm wide band 557.52
Say 6.70
11.35 Providing and making 18 mm thick artificial red stone plaster consisting of 12mm thick under coat plaster 1:4 (1
cement : 4 fine sand) and 6mm thick finishing coat of cement mortar 1:1:3 (1 cement :1 marble dust: 3 stone dust)
mixed with red oxide to match the shade of red stone.
LABOUR
0104 Mason 2nd class 197.00 day 2.5 day 492.50
0114 Beldar 190.00 day 3.5 day 665.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 5 sqm 55.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
TOTAL 2003.39
Add 5 % for water, electricity, sundries and other 100.17
overhead charges
TOTAL 2103.56
Add 10 % for contractor's profit 210.36
Cost of 10.00 sqm 2313.92
Cost of 1.00 sqm 231.39
Say 231.00
11.36 Extra for lining over plaster to imitate stone or concrete block walling.
Code Description Rate Unit Qty Total
Detail of cost for 10 sqm
LABOUR
0101 Mason 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
2647 Unslaked lime 500.00 quintal 0.01 quintal 5.00
TOTAL 203.50
Add 5 % for water, electricity, sundries and other 10.18
overhead charges
TOTAL 213.68
Add 10 % for contractor's profit 21.37
Cost of 10.00 sqm 235.05
Cost of 1.00 sqm 23.50
Say 23.50
11.37 Providing and making pointing on brick work with cement Mortar 1:3 (1 cement : 3 fine sand)
11.37.1 Flush pointing
LABOUR
0104 Mason 2nd class 197.00 day 2 day 394.00
0114 Beldar 190.00 day 4 day 760.00
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 2 sqm 22.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.25 day 50.00
TOTAL 1554.36
Add 5 % for water, electricity, sundries and other 77.72
overhead charges
TOTAL 1632.08
Add 10 % for contractor's profit 163.21
Cost of 10.00 sqm 1795.29
Cost of 1.00 sqm 179.52
Say 180.00
11.40 Making grove in cement plaster while plastering upto10 mm deep and 10 mm wide.
Code Description Rate Unit Qty Total
Detail of cost for 10 metre long
LABOUR
0104 Mason 2nd class 197.00 day 0.03 day 5.91
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 11.61
Add 5 % for water, electricity, sundries and other 0.58
overhead charges
TOTAL 12.19
Add 10 % for contractor's profit 1.22
Cost of 10.00 metre 13.41
Cost of 1.00 metre 1.34
Say 1.30
11.41 Providing and fixing chicken mesh weighting not less than 250 gms/ sqm as per IS : specification in the required
width with 40mm long steel nails on vertical and horizontal surface near R.C.C. and brick walls junctions including
scaffolding and all lead and lifts etc. complete before plastering upto 10mts in height.
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.056 cum 47.60
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.5 day 100.00
TOTAL 1430.57
Add 5 % for water, electricity, sundries and other 71.53
overhead charges
TOTAL 1502.10
Add 10 % for contractor's profit 150.21
Cost of 10 sqm. 1652.31
Cost of 1 sqm. 165.23
Say 165.00
12.3 Cement concrete flooring with cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm)
finished with a floating coat of neat cement.
12.3.1 40 mm thick
Code Description Rate Unit Qty Total
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.089 cum 75.65
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.5 day 100.00
TOTAL 1919.28
Add 5 % for water, electricity, sundries and other 95.96
overhead charges
TOTAL 2015.24
Add 10 % for contractor's profit 201.52
Cost of 10 sqm. 2216.76
Cost of 1 sqm. 221.67
Say 222.00
12.3 Cement concrete flooring with cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm)
finished with a floating coat of neat cement.
12.3.2 50 mm thick
Code Description Rate Unit Qty Total
Details of cost for 10 sqm.
Materials:-
0302 Stone Aggregate (Single size) : 20 mm nominal size 850.00 cum 0.334 cum 283.90
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.111 cum 94.35
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.5 day 100.00
TOTAL 2202.93
Add 5 % for water, electricity, sundries and other 110.15
overhead charges
TOTAL 2313.08
Add 10 % for contractor's profit 231.31
Cost of 10 sqm. 2544.39
Cost of 1 sqm. 254.43
Say 254.00
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.168 cum 142.80
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.5 day 100.00
TOTAL 2983.84
Add 5 % for water, electricity, sundries and other 149.19
overhead charges
TOTAL 3133.03
Add 10 % for contractor's profit 313.30
Cost of 10 sqm. 3446.33
Cost of 1 sqm. 344.63
Say 345.00
12.4 52 mm thick cement concrete flooring with under layer of 40mm thick cement concrete 1:2:4 (1 cement : 2 coarse
sand : 4 graded stone aggregate 20mm nominal size) and top layer of 12 mm thick cement metallic hardener
concrete mix 1:2 (1 cement hardener mix : 2 stone aggregate of 6 mm size by volume) with metallic hardening
compound of approved quality mixed with cement in ratio of 4:1 (4 cement : 1 metallic floor hardening compound
by weight) including finishing etc. complete.
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.089 cum 75.65
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.014 cum 46.99
(Rate as per item No 5.8)
5.17 Cement Mortar White C.M. 1:3 (1 white cement : 3 8641.07 cum 0.003 cum 25.92
marble dust) (Rate as per item No 5.17)
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.014 cum 46.99
(Rate as per item No 5.8)
5.17 Cement Mortar White C.M. 1:3 (1 white cement : 3 8641.07 cum 0.003 cum 25.92
marble dust) (Rate as per item No 5.17)
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.014 cum 46.99
(Rate as per item No 5.8)
5.17 Cement Mortar White C.M. 1:3 (1 white cement : 3 8641.07 cum 0.003 cum 25.92
marble dust) (Rate as per item No 5.17)
12.8.2 On floor, steps and risers over 20mm thick bed of cement Mortar 1:4 (1 cement : 4 coarse sand)
Code Description Rate Unit Qty Total
Details of cost for 1 sqm
MATERIAL
Glazed Ceramic floor tiles 300x300 mm size = 1.000
sqm
Add for wastage & breakage @ 2.5 % = 0.025 sqm
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
Total 3502.64
Add 5 % for water, electricity, sundries and other 175.13
overhead charges
Total 3677.77
Add 10 % for contractor's profit 367.78
Cost of 10 sqm 4045.55
Cost of 1 sqm 404.55
Say 405.00
12.18 40mm thick marble chips flooring rubbed and polished to granolithic finish with under layer 34mm thick cement
concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded stone aggregate 12.5 mm nominal size) and top layer 6mm thick
with white or black or white and black marble chips of size from 1mm to 4mm nominal size laid after mixing with
cement marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble
powder mix : 7 marble chips by volume)
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
Total 3886.12
Add 5 % for water, electricity, sundries and other 194.31
overhead charges
Total 4080.43
Add 10 % for contractor's profit 408.04
Cost of 10 sqm 4488.47
Cost of 1 sqm 448.84
Say 449.00
12.18 40mm thick marble chips flooring rubbed and polished to granolithic finish with under layer 34mm thick cement
concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded stone aggregate 12.5 mm nominal size) and top layer 6mm thick
with white or black or white and black marble chips of size from 1mm to 4mm nominal size laid after mixing with
cement marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble
powder mix : 7 marble chips by volume)
12.18.3 Medium shade pigment with approx. 50% white cement, 50% ordinary cement
Code Description Rate Unit Qty Total
Details of cost for 10 sqm
Material
For under layer of 34mm thick
0303 Stone Aggregate (Single size) : 12.5 mm nominal 850.00 cum 0.227 cum 192.95
size
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.076 cum 64.60
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
Total 3506.82
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
Total 3465.94
Add 5 % for water, electricity, sundries and other 173.30
overhead charges
Total 3639.24
Add 10 % for contractor's profit 363.92
Cost of 10 sqm 4003.16
Cost of 1 sqm 400.31
Say 400.00
12.18 40mm thick marble chips flooring rubbed and polished to granolithic finish with under layer 34mm thick cement
concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded stone aggregate 12.5 mm nominal size) and top layer 6mm thick
with white or black or white and black marble chips of size from 1mm to 4mm nominal size laid after mixing with
cement marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble
powder mix : 7 marble chips by volume)
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
Total 3147.64
Add 5 % for water, electricity, sundries and other 157.38
overhead charges
Total 3305.02
Add 10 % for contractor's profit 330.50
Cost of 10 sqm 3635.52
Cost of 1 sqm 363.55
Say 364.00
12.19 40mm thick marble chips flooring rubbed and polished to granolithic finish with under layer 31mm thick cement
concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded stone aggregate 12.5 mm nominal size) and top layer 9mm thick
with white or black or white and black marble chips of size from 4mm to 7mm nominal size laid after mixing with
cement marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble
powder mix : 7 marble chips by volume)
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
Total 3890.50
Add 5 % for water, electricity, sundries and other 194.53
overhead charges
Total 4085.03
Add 10 % for contractor's profit 408.50
Cost of 10 sqm 4493.53
Cost of 1 sqm 449.35
Say 449.00
12.19 40mm thick marble chips flooring rubbed and polished to granolithic finish with under layer 31mm thick cement
concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded stone aggregate 12.5 mm nominal size) and top layer 9mm thick
with white or black or white and black marble chips of size from 4mm to 7mm nominal size laid after mixing with
cement marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble
powder mix : 7 marble chips by volume)
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
Total 4225.58
Add 5 % for water, electricity, sundries and other 211.28
overhead charges
Total 4436.86
Add 10 % for contractor's profit 443.69
Cost of 10 sqm 4880.55
Cost of 1 sqm 488.05
Say 488.00
12.19 40mm thick marble chips flooring rubbed and polished to granolithic finish with under layer 31mm thick cement
concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded stone aggregate 12.5 mm nominal size) and top layer 9mm thick
with white or black or white and black marble chips of size from 4mm to 7mm nominal size laid after mixing with
cement marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble
powder mix : 7 marble chips by volume)
12.19.3 Medium shade pigment with approx. 50% white cement, 50% ordinary cement
Code Description Rate Unit Qty Total
Details of cost for 10 sqm
Material
For Under layer of 31 mm thick
0303 Stone Aggregate (Single size) : 12.5 mm nominal 850.00 cum 0.21 cum 178.50
size
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.07 cum 59.50
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
Total 3896.04
Add 5 % for water, electricity, sundries and other 194.80
overhead charges
Total 4090.84
Add 10 % for contractor's profit 409.08
0001 Hire charges of Concrete Mixer 0.14 cubic metre 700.00 day 0.03 day 21.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
Total 3881.33
Add 5 % for water, electricity, sundries and other 194.07
overhead charges
Total 4075.40
Add 10 % for contractor's profit 407.54
Cost of 10 sqm 4482.94
Cost of 1 sqm 448.29
Say 448.00
12.19 40mm thick marble chips flooring rubbed and polished to granolithic finish with under layer 31mm thick cement
concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded stone aggregate 12.5 mm nominal size) and top layer 9mm thick
with white or black or white and black marble chips of size from 4mm to 7mm nominal size laid after mixing with
cement marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble
powder mix : 7 marble chips by volume)
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
Total 3384.25
Add 5 % for water, electricity, sundries and other 169.21
overhead charges
Total 3553.46
Add 10 % for contractor's profit 355.35
Cost of 10 sqm 3908.81
Cost of 1 sqm 390.88
Say 391.00
12.20 40mm thick marble chips flooring rubbed and polished to granolithic finish with under layer 28mm thick cement
concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded stone aggregate 12.5 mm nominal size) and top layer 12mm thick
with white or black or white and black marble chips of size from 7mm to 10mm nominal size laid after mixing with
cement marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble
powder mix : 7 marble chips by volume)
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 4251.96
Add 5 % for water, electricity, sundries and other 212.60
overhead charges
TOTAL 4464.56
Add 10 % for contractor's profit 446.46
Cost of 10 sqm. 4911.02
Cost of 1 sqm. 491.10
Say 491.00
12.20 40mm thick marble chips flooring rubbed and polished to granolithic finish with under layer 28mm thick cement
concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded stone aggregate 12.5 mm nominal size) and top layer 12mm thick
with white or black or white and black marble chips of size from 7mm to 10mm nominal size laid after mixing with
cement marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble
powder mix : 7 marble chips by volume)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 4721.76
Add 5 % for water, electricity, sundries and other 236.09
overhead charges
TOTAL 4957.85
Add 10 % for contractor's profit 495.79
Cost of 10 sqm. 5453.64
Cost of 1 sqm. 545.36
Say 545.00
12.20 40mm thick marble chips flooring rubbed and polished to granolithic finish with under layer 28mm thick cement
concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded stone aggregate 12.5 mm nominal size) and top layer 12mm thick
with white or black or white and black marble chips of size from 7mm to 10mm nominal size laid after mixing with
cement marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble
powder mix : 7 marble chips by volume)
12.20.3 Medium shade pigment with approx. 50% white cement, 50% ordinary cement
Code Description Rate Unit Qty Total
Details of cost for 10 sqm.
Materials-
For under layer 28 mm thick
0303 Stone Aggregate (Single size) : 12.5 mm nominal 850.00 cum 0.19 cum 161.50
size
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.06 cum 51.00
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 4260.06
Add 5 % for water, electricity, sundries and other 213.00
overhead charges
TOTAL 4473.06
Add 10 % for contractor's profit 447.31
Cost of 10 sqm. 4920.37
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 4239.81
Add 5 % for water, electricity, sundries and other 211.99
overhead charges
TOTAL 4451.80
Add 10 % for contractor's profit 445.18
Cost of 10 sqm. 4896.98
Cost of 1 sqm. 489.69
Say 490.00
12.20 40mm thick marble chips flooring rubbed and polished to granolithic finish with under layer 28mm thick cement
concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded stone aggregate 12.5 mm nominal size) and top layer 12mm thick
with white or black or white and black marble chips of size from 7mm to 10mm nominal size laid after mixing with
cement marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble
powder mix : 7 marble chips by volume)
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 3543.21
Add 5 % for water, electricity, sundries and other 177.16
overhead charges
TOTAL 3720.37
Add 10 % for contractor's profit 372.04
Cost of 10 sqm. 4092.41
Cost of 1 sqm. 409.24
Say 409.00
12.21 Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic finish with layer 6mm thick with white
or black or white and black marble chips of size from smallest of 4mm nominal size laid after mixing with cement
marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble powder
mix ; 7 marble chips by volume)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 3485.49
Add 5 % for water, electricity, sundries and other 174.27
overhead charges
TOTAL 3659.76
Add 10 % for contractor's profit 365.98
Cost of 10 sqm. 4025.74
Cost of 1 sqm. 402.57
Say 403.00
12.21 Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic finish with layer 6mm thick with white
or black or white and black marble chips of size from smallest of 4mm nominal size laid after mixing with cement
marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble powder
mix ; 7 marble chips by volume)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 3720.19
Add 5 % for water, electricity, sundries and other 186.01
overhead charges
TOTAL 3906.20
Add 10 % for contractor's profit 390.62
Cost of 10 sqm. 4296.82
Cost of 1 sqm. 429.68
Say 430.00
12.21 Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic finish with layer 6mm thick with white
or black or white and black marble chips of size from smallest of 4mm nominal size laid after mixing with cement
marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble powder
mix ; 7 marble chips by volume)
12.21.4 Medium shade pigment with approx. 50% white cement, 50% ordinary cement
Code Description Rate Unit Qty Total
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 3490.21
Add 5 % for water, electricity, sundries and other 174.51
overhead charges
TOTAL 3664.72
Add 10 % for contractor's profit 366.47
Cost of 10 sqm. 4031.19
Cost of 1 sqm. 403.11
Say 403.00
12.21 Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic finish with layer 6mm thick with white
or black or white and black marble chips of size from smallest of 4mm nominal size laid after mixing with cement
marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble powder
mix ; 7 marble chips by volume)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 3130.49
Add 5 % for water, electricity, sundries and other 156.52
overhead charges
TOTAL 3287.01
Add 10 % for contractor's profit 328.70
Cost of 10 sqm. 3615.71
Cost of 1 sqm. 361.57
Say 362.00
12.21 Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic finish with layer 6mm thick with white
or black or white and black marble chips of size from smallest of 4mm nominal size laid after mixing with cement
marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble powder
mix ; 7 marble chips by volume)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 3579.47
Add 5 % for water, electricity, sundries and other 178.97
overhead charges
TOTAL 3758.44
Add 10 % for contractor's profit 375.84
Cost of 10 sqm. 4134.28
Cost of 1 sqm. 413.42
Say 413.00
12.21 Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic finish with layer 6mm thick with white
or black or white and black marble chips of size from smallest of 4mm nominal size laid after mixing with cement
marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble powder
mix ; 7 marble chips by volume)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 3814.17
Add 5 % for water, electricity, sundries and other 190.71
overhead charges
TOTAL 4004.88
Add 10 % for contractor's profit 400.49
12.21.10 Medium shade pigment with approx. 50% white cement, 50% ordinary cement
Code Description Rate Unit Qty Total
Details of cost for 10 sqm.
Materials-
For under layer of 15mm thick
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.202 cum 677.97
(Rate as per item No 5.8)
Top layer 6mm thick
1152 Marble chips upto 4mm and downsize White & 325.00 quintal 0.872 quintal 283.40
black
0251 Portland Cement 5400.00 tonne 0.0203 tonne 109.62
0252 White Cement 14000.00 tonne 0.0203 tonne 284.20
1151 Marble dust/ powder 1200.00 cum 0.007 cum 8.40
2684 Green or blue medium shade pigment 65.00 kg 2.84 kg 184.60
Labour:-
0104 Mason 2nd class 197.00 day 3 day 591.00
0114 Beldar 190.00 day 3.5 day 665.00
MACHINERY
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 3584.19
Add 5 % for water, electricity, sundries and other 179.21
overhead charges
TOTAL 3763.40
Add 10 % for contractor's profit 376.34
Cost of 10 sqm. 4139.74
Cost of 1 sqm. 413.97
Say 414.00
12.21 Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic finish with layer 6mm thick with white
or black or white and black marble chips of size from smallest of 4mm nominal size laid after mixing with cement
marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble powder
mix ; 7 marble chips by volume)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 3572.77
Add 5 % for water, electricity, sundries and other 178.64
overhead charges
TOTAL 3751.41
Add 10 % for contractor's profit 375.14
Cost of 10 sqm. 4126.55
Cost of 1 sqm. 412.65
Say 413.00
12.21 Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic finish with layer 6mm thick with white
or black or white and black marble chips of size from smallest of 4mm nominal size laid after mixing with cement
marble powder in mix 3:1 (3 cement :1 marble powder by weight) in proportion of 4:7 (4 cement marble powder
mix ; 7 marble chips by volume)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 3224.47
Add 5 % for water, electricity, sundries and other 161.22
overhead charges
TOTAL 3385.69
Add 10 % for contractor's profit 338.57
Cost of 10 sqm. 3724.26
Cost of 1 sqm. 372.42
Say 372.00
3.1.0.4 Cement concrete 1:2:4 (stone aggregate 20mm) 3551.90 cum 0.25 cum 887.98
(Rate as per Item No 3.1.4)
0251 Portland Cement 5400.00 tonne 0.04 tonne 216.00
Marble pieces for crazy flooring
(Assume 70% of marble stone are and 30% of joint
filer/mixture
7sqmx0.02m = 0.14 cum
1156 White marble makrana second quality plain veined 200.00 quintal 2.4 quintal 480.00
stone pieces for crazy flooring
0252 White Cement 14000.00 tonne 0.0405 tonne 567.00
1151 Marble dust/ powder 1200.00 cum 0.007 cum 8.40
2683 Light shade pigment 85.00 kg 2.84 kg 241.40
1152 Marble chips upto 4mm and downsize White & 325.00 quintal 0.872 quintal 283.40
black
LABOUR
0101 Mason 1st class 207.00 day 1.2 day 248.40
0114 Beldar 190.00 day 2.2 day 418.00
MACHINERY
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
TOTAL 4120.58
Add 5 % for water, electricity, sundries and other 161.63
overhead charges on all except (A) i.e. on (4120.58
- 887.98) = 3232.60
TOTAL 4282.21
Add 10 % for contractor's profit on all except (A) 339.42
i.e. on (4282.21 - 887.98) = 3394.23
12.25.1 30 mm wide
Code Description Rate Unit Qty Total
Details of cost for 10 metre length
Materials-
Glass strips = 10m
Add 10% for wastage = 1m
2343 Glass strip 4 mm thick 30mm wide 8.05 metre 11 metre 88.55
Labour-
0104 Mason 2nd class 197.00 day 0.1 day 19.70
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 127.25
Add 5 % for water, electricity, sundries and other 6.36
overhead charges
TOTAL 133.61
Add 10 % for contractor's profit 13.36
Cost of 10 meter 146.97
Cost of 1 meter 14.69
Say 14.50
12.25 Extra for providing and fixing 4mm thick glass strip in joints of Terrazo floor/ cement concrete floor or like.
12.25.2 40 mm wide
Code Description Rate Unit Qty Total
Details of cost for 10 metre length
Materials-
Glass strips = 10m
Add 10% for wastage = 1m
2342 Glass strip 4 mm thick 40 mm wide 10.75 metre 11 metre 118.25
Labour-
0104 Mason 2nd class 197.00 day 0.1 day 19.70
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 156.95
Add 5 % for water, electricity, sundries and other 7.85
overhead charges
TOTAL 164.80
Add 10 % for contractor's profit 16.48
Cost of 10 meter 181.28
Cost of 1 meter 18.12
Say 18.00
12.25 Extra for providing and fixing 4mm thick glass strip in joints of Terrazo floor/ cement concrete floor or like.
12.25.3 60 mm wide
Code Description Rate Unit Qty Total
Details of cost for 10 metre length
Materials-
Glass strips = 10m
2.1.0.4 Form work on Edge (Rate as per Item No 2.1.4) 33.87 metre 1 metre 33.87
TOTAL 354.12
Add 5 % for water, electricity, sundries and other 16.01
overhead charges on all except (A) i.e. on (354.12 -
33.87) = 320.25
TOTAL 370.13
Add 10 % for contractor's profit on all except (A) 33.63
i.e. on (370.13 - 33.87) = 336.26
Cost of 10 m 403.76
Cost of 1 m 40.37
Say 40.50
12.31 Special surface finishing to treads and risers and the ends of concrete steps and the like including form work.
TOTAL 249.42
Add 5 % for water, electricity, sundries and other 10.78
overhead charges on all except (A) i.e. on (249.42 -
33.87) = 215.55
TOTAL 260.20
Add 10 % for contractor's profit on all except (A) 22.63
i.e. on (260.20 - 33.87) = 226.33
Cost of 10 Sqm. 282.83
Cost of 1sqm. 28.28
Say 28.50
12.32 Precast Terrazzo tiles 22mm thick with graded white or black or white and black marble chips of size upto 6mm laid
in floors, tread of steps and landing on 25mm thick bed of cement mortar 1:6 (1 cement : 6 coarse sand) jointed
with neat cement slurry mixed with pigment to match the shade of tiles, including rubbing and polishing complete
with precast tiles of:
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.224 cum 751.80
(Rate as per item No 5.8)
0251 Portland Cement 5400.00 tonne 0.044 tonne 237.60
0252 White Cement 14000.00 tonne 0.044 tonne 616.00
2683 Light shade pigment 85.00 kg 0.25 kg 21.25
LABOUR
0104 Mason 2nd class 197.00 day 1.6 day 315.20
0114 Beldar 190.00 day 3.5 day 665.00
MACHINERY
0024 Hire charges of Portable Electrical operated stone 100.00 day 0.2 day 20.00
cutter
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 6046.85
Add 5 % for water, electricity, sundries and other 302.34
overhead charges
TOTAL 6349.19
Add 10 % for contractor's profit 634.92
Cost of 10 sqm. 6984.11
Cost of 1 sqm. 698.41
Say 698.00
12.32 Precast Terrazzo tiles 22mm thick with graded white or black or white and black marble chips of size upto 6mm laid
in floors, tread of steps and landing on 25mm thick bed of cement mortar 1:6 (1 cement : 6 coarse sand) jointed
with neat cement slurry mixed with pigment to match the shade of tiles, including rubbing and polishing complete
with precast tiles of:
12.32.2 Medium shade using approximately. 50% white cement and 50% ordinary cement.
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.224 cum 751.80
(Rate as per item No 5.8)
0251 Portland Cement 5400.00 tonne 0.044 tonne 237.60
0252 White Cement 14000.00 tonne 0.044 tonne 616.00
2683 Light shade pigment 85.00 kg 0.25 kg 21.25
Labour-
0104 Mason 2nd class 197.00 day 1.6 day 315.20
0114 Beldar 190.00 day 3.5 day 665.00
MACHINERY
0024 Hire charges of Portable Electrical operated stone 100.00 day 0.2 day 20.00
cutter
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 5826.85
Add 5 % for water, electricity, sundries and other 291.34
overhead charges
TOTAL 6118.19
Add 10 % for contractor's profit 611.82
Cost of 10 sqm. 6730.01
Cost of 1 sqm. 673.00
Say 673.00
12.32 Precast Terrazzo tiles 22mm thick with graded white or black or white and black marble chips of size upto 6mm laid
in floors, tread of steps and landing on 25mm thick bed of cement mortar 1:6 (1 cement : 6 coarse sand) jointed
with neat cement slurry mixed with pigment to match the shade of tiles, including rubbing and polishing complete
with precast tiles of:
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 0.224 cum 594.56
(Rate as per item No 5.9)
0251 Portland Cement 5400.00 tonne 0.044 tonne 237.60
0252 White Cement 14000.00 tonne 0.044 tonne 616.00
2683 Light shade pigment 85.00 kg 0.25 kg 21.25
Labour-
0104 Mason 2nd class 197.00 day 1.6 day 315.20
0114 Beldar 190.00 day 3.5 day 665.00
MACHINERY
0024 Hire charges of Portable Electrical operated stone 100.00 day 0.2 day 20.00
cutter
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
TOTAL 146.10
Add 5 % for water, electricity, sundries and other 7.31
overhead charges
TOTAL 153.41
Add 10 % for contractor's profit 15.34
Cost of 10 Sqm. 168.75
Cost of 1sqm. 16.87
Say 17.00
12.34 Precast Terrazzo tiles 22mm thick with marble chips of size upto 6mm in skirting and risers of steps and exceeding
30cm in height on 12mm thick cement plaster 1:3 (1 cement : 3 coarse sand) jointed with neat cement slurry
including rubbing and polishing complete with tiles of.
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.144 cum 483.30
(Rate as per item No 5.8)
White cement for slurry
0252 White Cement 14000.00 tonne 0.066 tonne 924.00
2683 Light shade pigment 85.00 kg 0.25 kg 21.25
Labour-
0104 Mason 2nd class 197.00 day 3.25 day 640.25
0114 Beldar 190.00 day 3.25 day 617.50
MACHINERY
0024 Hire charges of Portable Electrical operated stone 100.00 day 0.2 day 20.00
cutter
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
12.34.2 Medium shade using approximately. 50% white cement and 50% ordinary cement.
Code Description Rate Unit Qty Total
Details of cost for 10sqm.
Materials-
0330 Precast terrazo tiles 22 mm thick (medium shade) 220.00 sqm 11 sqm 2420.00
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.144 cum 483.30
(Rate as per item No 5.8)
White cement for slurry
0252 White Cement 14000.00 tonne 0.066 tonne 924.00
2683 Light shade pigment 85.00 kg 0.25 kg 21.25
Labour-
0104 Mason 2nd class 197.00 day 3.25 day 640.25
0114 Beldar 190.00 day 3.25 day 617.50
MACHINERY
0024 Hire charges of Portable Electrical operated stone 100.00 day 0.2 day 20.00
cutter
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 5906.30
Add 5 % for water, electricity, sundries and other 295.32
overhead charges
TOTAL 6201.62
Add 10 % for contractor's profit 620.16
Cost of 10 sqm. 6821.78
Cost of 1 sqm. 682.17
Say 682.00
12.34 Precast Terrazzo tiles 22mm thick with marble chips of size upto 6mm in skirting and risers of steps and exceeding
30cm in height on 12mm thick cement plaster 1:3 (1 cement : 3 coarse sand) jointed with neat cement slurry
including rubbing and polishing complete with tiles of.
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.144 cum 483.30
(Rate as per item No 5.8)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 5686.30
Add 5 % for water, electricity, sundries and other 284.32
overhead charges
TOTAL 5970.62
Add 10 % for contractor's profit 597.06
Cost of 10 sqm. 6567.68
Cost of 1 sqm. 656.76
Say 657.00
12.35 Extra if cut tiles other than half tiles are used in risers of steps skirting and dado.
Code Description Rate Unit Qty Total
Details of cost for 10 sqm.
Labour-
0104 Mason 2nd class 197.00 day 0.6 day 118.20
0114 Beldar 190.00 day 0.6 day 114.00
TOTAL 232.20
Add 5 % for water, electricity, sundries and other 11.61
overhead charges
TOTAL 243.81
Add 10 % for contractor's profit 24.38
Cost of 10 Sqm. 268.19
Cost of 1sqm. 26.81
Say 27.00
12.36 Chequered terrazzo tiles 22 mm thick with graded marble chips of size upto 6mm in floors on 25mm thick bed of
cement mortar 1:6 (1 cement : 6 coarse sand) jointed with neat cement slurry mixed with pigment to match the
shade of tiles including grinding rubbing and polishing complete.
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 0.224 cum 594.56
(Rate as per item No 5.9)
0251 Portland Cement 5400.00 tonne 0.044 tonne 237.60
0252 White Cement 14000.00 tonne 0.044 tonne 616.00
2683 Light shade pigment 85.00 kg 0.25 kg 21.25
Labour-
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 6919.61
Add 5 % for water, electricity, sundries and other 345.98
overhead charges
TOTAL 7265.59
Add 10 % for contractor's profit 726.56
Cost of 10 sqm. 7992.15
Cost of 1 sqm. 799.21
Say 799.00
12.36 Chequered terrazzo tiles 22 mm thick with graded marble chips of size upto 6mm in floors on 25mm thick bed of
cement mortar 1:6 (1 cement : 6 coarse sand) jointed with neat cement slurry mixed with pigment to match the
shade of tiles including grinding rubbing and polishing complete.
12.36.2 Medium shade using approximately. 50% white cement and 50% ordinary cement.
Code Description Rate Unit Qty Total
Details of cost for 10sqm.
Materials-
0333 Chequered terrazo tiles 22 mm thick (medium 285.00 sqm 11 sqm 3135.00
shade)
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 0.224 cum 594.56
(Rate as per item No 5.9)
0251 Portland Cement 5400.00 tonne 0.044 tonne 237.60
0252 White Cement 14000.00 tonne 0.044 tonne 616.00
2683 Light shade pigment 85.00 kg 0.25 kg 21.25
Labour-
0104 Mason 2nd class 197.00 day 1.6 day 315.20
0114 Beldar 190.00 day 2.4 day 456.00
MACHINERY
0024 Hire charges of Portable Electrical operated stone 100.00 day 0.2 day 20.00
cutter
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 6175.61
Add 5 % for water, electricity, sundries and other 308.78
overhead charges
TOTAL 6484.39
Add 10 % for contractor's profit 648.44
Cost of 10 sqm. 7132.83
Cost of 1 sqm. 713.28
Say 713.00
12.36 Chequered terrazzo tiles 22 mm thick with graded marble chips of size upto 6mm in floors on 25mm thick bed of
cement mortar 1:6 (1 cement : 6 coarse sand) jointed with neat cement slurry mixed with pigment to match the
shade of tiles including grinding rubbing and polishing complete.
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 0.224 cum 594.56
(Rate as per item No 5.9)
0251 Portland Cement 5400.00 tonne 0.044 tonne 237.60
0252 White Cement 14000.00 tonne 0.044 tonne 616.00
2683 Light shade pigment 85.00 kg 0.25 kg 21.25
Labour-
0104 Mason 2nd class 197.00 day 1.6 day 315.20
0114 Beldar 190.00 day 2.4 day 456.00
MACHINERY
0024 Hire charges of Portable Electrical operated stone 100.00 day 0.2 day 20.00
cutter
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 5790.61
Add 5 % for water, electricity, sundries and other 289.53
overhead charges
TOTAL 6080.14
Add 10 % for contractor's profit 608.01
Cost of 10 sqm. 6688.15
Cost of 1 sqm. 668.81
Say 669.00
12.37 Chequered precast cement concrete tiles 22mm thick in footpath & courtyard jointed with neat cement slurry mixed
with pigment to match the shade of tile including cleaning of joint etc complete on 20 mm thick bed of cement
mortar 1:4 (1 cement :4 coarse sand) :
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 0.22 cum 583.94
(Rate as per item No 5.9)
0251 Portland Cement 5400.00 tonne 0.044 tonne 237.60
0252 White Cement 14000.00 tonne 0.048 tonne 672.00
2683 Light shade pigment 85.00 kg 0.25 kg 21.25
Labour-
0104 Mason 2nd class 197.00 day 1.6 day 315.20
0114 Beldar 190.00 day 2.5 day 475.00
MACHINERY
0024 Hire charges of Portable Electrical operated stone 100.00 day 0.2 day 20.00
cutter
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
12.37.2 Medium shade using approximately. 50% white cement and 50% ordinary cement.
Code Description Rate Unit Qty Total
Details of cost for 10sqm.
Materials-
0328 Precast chequered cement concrete tiles 22 mm 270.00 sqm 11 sqm 2970.00
thick medium shade using 50% white cement, 50%
ordinary cement
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 0.22 cum 583.94
(Rate as per item No 5.9)
Grey cement for grouting @ 2.4 kg per sqm = 24 kg
Total cement = 68 kg
0251 Portland Cement 5400.00 tonne 0.068 tonne 367.20
0252 White Cement 14000.00 tonne 0.024 tonne 336.00
2684 Green or blue medium shade pigment 65.00 kg 0.25 kg 16.25
Labour-
0104 Mason 2nd class 197.00 day 1.6 day 315.20
0114 Beldar 190.00 day 2.5 day 475.00
MACHINERY
0024 Hire charges of Portable Electrical operated stone 100.00 day 0.2 day 20.00
cutter
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 5113.59
Add 5 % for water, electricity, sundries and other 255.68
overhead charges
TOTAL 5369.27
Add 10 % for contractor's profit 536.93
Cost of 10 sqm. 5906.20
Cost of 1 sqm. 590.62
Say 591.00
12.37 Chequered precast cement concrete tiles 22mm thick in footpath & courtyard jointed with neat cement slurry mixed
with pigment to match the shade of tile including cleaning of joint etc complete on 20 mm thick bed of cement
mortar 1:4 (1 cement :4 coarse sand) :
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 0.22 cum 583.94
(Rate as per item No 5.9)
Grey cement for slurry @ 4.4kg/sqm. = 44 kg. +
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 0.22 cum 583.94
(Rate as per item No 5.9)
Grey cement for slurry @ 4.4kg/sqm. = 44 kg. +
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 0.224 cum 594.56
(Rate as per item No 5.9)
0251 Portland Cement 5400.00 tonne 0.05 tonne 270.00
LABOUR
0101 Mason 1st class 207.00 day 1.2 day 248.40
0114 Beldar 190.00 day 3 day 570.00
MACHINERY
0024 Hire charges of Portable Electrical operated stone 100.00 day 1.2 day 120.00
cutter
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 32482.96
Add 5 % for water, electricity, sundries and other 1624.15
overhead charges
TOTAL 34107.11
Add 10 % for contractor's profit 3410.71
Cost of 10 sqm. 37517.82
Cost of 1 sqm. 3751.78
Say 3752.00
12.38 15mm thick Marble stone slab flooring over 18mm (Average) thick base of cement mortar 1:4 (1 cement : 4 coarse
sand) laid and jointed with grey cement slurry including grinding rubbing and polishing etc. complete. (Area of slab
should be 0.50 sqm and above)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 14956.96
Add 5 % for water, electricity, sundries and other 747.85
overhead charges
TOTAL 15704.81
Add 10 % for contractor's profit 1570.48
Cost of 10 sqm. 17275.29
Cost of 1 sqm. 1727.52
Say 1728.00
12.38 15mm thick Marble stone slab flooring over 18mm (Average) thick base of cement mortar 1:4 (1 cement : 4 coarse
sand) laid and jointed with grey cement slurry including grinding rubbing and polishing etc. complete. (Area of slab
should be 0.50 sqm and above)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 21143.96
Add 5 % for water, electricity, sundries and other 1057.20
overhead charges
TOTAL 22201.16
Add 10 % for contractor's profit 2220.12
Cost of 10 sqm. 24421.28
Cost of 1 sqm. 2442.12
Say 2442.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 12964.21
Add 5 % for water, electricity, sundries and other 648.21
overhead charges
TOTAL 13612.42
Add 10 % for contractor's profit 1361.24
Cost of 10 sqm. 14973.66
Cost of 1 sqm. 1497.36
Say 1497.00
12.38 15mm thick Marble stone slab flooring over 18mm (Average) thick base of cement mortar 1:4 (1 cement : 4 coarse
sand) laid and jointed with grey cement slurry including grinding rubbing and polishing etc. complete. (Area of slab
should be 0.50 sqm and above)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 12964.21
Add 5 % for water, electricity, sundries and other 648.21
overhead charges
TOTAL 13612.42
Add 10 % for contractor's profit 1361.24
Cost of 10 sqm. 14973.66
Cost of 1 sqm. 1497.36
Say 1497.00
12.38 15mm thick Marble stone slab flooring over 18mm (Average) thick base of cement mortar 1:4 (1 cement : 4 coarse
sand) laid and jointed with grey cement slurry including grinding rubbing and polishing etc. complete. (Area of slab
should be 0.50 sqm and above)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 15264.21
Add 5 % for water, electricity, sundries and other 763.21
overhead charges
TOTAL 16027.42
Add 10 % for contractor's profit 1602.74
Cost of 10 sqm. 17630.16
Cost of 1 sqm. 1763.01
Say 1763.00
12.38 15mm thick Marble stone slab flooring over 18mm (Average) thick base of cement mortar 1:4 (1 cement : 4 coarse
sand) laid and jointed with grey cement slurry including grinding rubbing and polishing etc. complete. (Area of slab
should be 0.50 sqm and above)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 23627.96
Add 5 % for water, electricity, sundries and other 1181.40
overhead charges
TOTAL 24809.36
Add 10 % for contractor's profit 2480.94
Cost of 10 sqm. 27290.30
Cost of 1 sqm. 2729.03
Say 2729.00
12.38 15mm thick Marble stone slab flooring over 18mm (Average) thick base of cement mortar 1:4 (1 cement : 4 coarse
sand) laid and jointed with grey cement slurry including grinding rubbing and polishing etc. complete. (Area of slab
should be 0.50 sqm and above)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 15232.96
Add 5 % for water, electricity, sundries and other 761.65
overhead charges
TOTAL 15994.61
Add 10 % for contractor's profit 1599.46
Cost of 10 sqm. 17594.07
Cost of 1 sqm. 1759.40
Say 1759.00
12.39 15mm thick Marble stone slab in, tread & risers of steps, skirting, dado, walls and pillars on 12mm (average) thick
base of cement mortar 1:4 (1 cement : 4 coarse sand) and jointed with grey cement slurry including matching
pigment, rubbing and polishing etc. complete. (single stone is to be used for risers and treads of steps and width of
stone for skirting and dado shall be equal to the height of skirting & dado and length of 1.0 M).
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.144 cum 483.30
(Rate as per item No 5.8)
0251 Portland Cement 5400.00 tonne 0.064 tonne 345.60
Labour-
0104 Mason 2nd class 197.00 day 3 day 591.00
0114 Beldar 190.00 day 4 day 760.00
MACHINERY
0024 Hire charges of Portable Electrical operated stone 100.00 day 3 day 300.00
cutter
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm 10 sqm 750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 33159.90
Add 5 % for water, electricity, sundries and other 1658.00
overhead charges
TOTAL 34817.90
Add 10 % for contractor's profit 3481.79
Cost for 10sqm. 38299.69
Cost for 1sqm. 3829.96
Say 3830.00
12.39 15mm thick Marble stone slab in, tread & risers of steps, skirting, dado, walls and pillars on 12mm (average) thick
base of cement mortar 1:4 (1 cement : 4 coarse sand) and jointed with grey cement slurry including matching
pigment, rubbing and polishing etc. complete. (single stone is to be used for risers and treads of steps and width of
stone for skirting and dado shall be equal to the height of skirting & dado and length of 1.0 M).
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 15633.90
Add 5 % for water, electricity, sundries and other 781.70
overhead charges
TOTAL 16415.60
Add 10 % for contractor's profit 1641.56
Cost for 10sqm. 18057.16
Cost for 1sqm. 1805.71
Say 1806.00
12.39 15mm thick Marble stone slab in, tread & risers of steps, skirting, dado, walls and pillars on 12mm (average) thick
base of cement mortar 1:4 (1 cement : 4 coarse sand) and jointed with grey cement slurry including matching
pigment, rubbing and polishing etc. complete. (single stone is to be used for risers and treads of steps and width of
stone for skirting and dado shall be equal to the height of skirting & dado and length of 1.0 M).
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 21820.90
Add 5 % for water, electricity, sundries and other 1091.05
overhead charges
TOTAL 22911.95
Add 10 % for contractor's profit 2291.20
Cost for 10sqm. 25203.15
Cost for 1sqm. 2520.31
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 13641.15
Add 5 % for water, electricity, sundries and other 682.06
overhead charges
TOTAL 14323.21
Add 10 % for contractor's profit 1432.32
Cost for 10sqm. 15755.53
Cost for 1sqm. 1575.55
Say 1576.00
12.39 15mm thick Marble stone slab in, tread & risers of steps, skirting, dado, walls and pillars on 12mm (average) thick
base of cement mortar 1:4 (1 cement : 4 coarse sand) and jointed with grey cement slurry including matching
pigment, rubbing and polishing etc. complete. (single stone is to be used for risers and treads of steps and width of
stone for skirting and dado shall be equal to the height of skirting & dado and length of 1.0 M).
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 13641.15
Add 5 % for water, electricity, sundries and other 682.06
overhead charges
TOTAL 14323.21
Add 10 % for contractor's profit 1432.32
Cost for 10sqm. 15755.53
Cost for 1sqm. 1575.55
Say 1576.00
12.39 15mm thick Marble stone slab in, tread & risers of steps, skirting, dado, walls and pillars on 12mm (average) thick
base of cement mortar 1:4 (1 cement : 4 coarse sand) and jointed with grey cement slurry including matching
pigment, rubbing and polishing etc. complete. (single stone is to be used for risers and treads of steps and width of
stone for skirting and dado shall be equal to the height of skirting & dado and length of 1.0 M).
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 15941.15
Add 5 % for water, electricity, sundries and other 797.06
overhead charges
TOTAL 16738.21
Add 10 % for contractor's profit 1673.82
Cost for 10sqm. 18412.03
Cost for 1sqm. 1841.20
Say 1841.00
12.39 15mm thick Marble stone slab in, tread & risers of steps, skirting, dado, walls and pillars on 12mm (average) thick
base of cement mortar 1:4 (1 cement : 4 coarse sand) and jointed with grey cement slurry including matching
pigment, rubbing and polishing etc. complete. (single stone is to be used for risers and treads of steps and width of
stone for skirting and dado shall be equal to the height of skirting & dado and length of 1.0 M).
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 24304.90
Add 5 % for water, electricity, sundries and other 1215.25
overhead charges
TOTAL 25520.15
Add 10 % for contractor's profit 2552.02
Cost for 10sqm. 28072.17
Cost for 1sqm. 2807.21
Say 2807.00
12.39 15mm thick Marble stone slab in, tread & risers of steps, skirting, dado, walls and pillars on 12mm (average) thick
base of cement mortar 1:4 (1 cement : 4 coarse sand) and jointed with grey cement slurry including matching
pigment, rubbing and polishing etc. complete. (single stone is to be used for risers and treads of steps and width of
stone for skirting and dado shall be equal to the height of skirting & dado and length of 1.0 M).
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 15909.90
Add 5 % for water, electricity, sundries and other 795.50
overhead charges
TOTAL 16705.40
Add 10 % for contractor's profit 1670.54
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 16232.96
Add 5 % for water, electricity, sundries and other 811.65
overhead charges
TOTAL 17044.61
Add 10 % for contractor's profit 1704.46
Cost of 10 sqm. 18749.07
Cost of 1 sqm. 1874.90
Say 1875.00
12.40 15mm thick Marble stone tile flooring over 18mm (Average) thick base of cement mortar 1:4 (1 cement : 4 coarse
sand) laid and jointed with grey cement slurry including grinding rubbing and polishing etc. complete. (Area of tile
should be 0.18 sqm and above)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 8357.96
Add 5 % for water, electricity, sundries and other 417.90
overhead charges
TOTAL 8775.86
Add 10 % for contractor's profit 877.59
Cost of 10 sqm. 9653.45
Cost of 1 sqm. 965.34
Say 965.00
12.40 15mm thick Marble stone tile flooring over 18mm (Average) thick base of cement mortar 1:4 (1 cement : 4 coarse
sand) laid and jointed with grey cement slurry including grinding rubbing and polishing etc. complete. (Area of tile
should be 0.18 sqm and above)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 10982.96
Add 5 % for water, electricity, sundries and other 549.15
overhead charges
TOTAL 11532.11
Add 10 % for contractor's profit 1153.21
Cost of 10 sqm. 12685.32
Cost of 1 sqm. 1268.53
Say 1269.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 8945.46
Add 5 % for water, electricity, sundries and other 447.27
overhead charges
TOTAL 9392.73
Add 10 % for contractor's profit 939.27
Cost of 10 sqm. 10332.00
Cost of 1 sqm. 1033.20
Say 1033.00
12.40 15mm thick Marble stone tile flooring over 18mm (Average) thick base of cement mortar 1:4 (1 cement : 4 coarse
sand) laid and jointed with grey cement slurry including grinding rubbing and polishing etc. complete. (Area of tile
should be 0.18 sqm and above)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 7370.46
Add 5 % for water, electricity, sundries and other 368.52
overhead charges
TOTAL 7738.98
Add 10 % for contractor's profit 773.90
Cost of 10 sqm. 8512.88
Cost of 1 sqm. 851.28
Say 851.00
12.40 15mm thick Marble stone tile flooring over 18mm (Average) thick base of cement mortar 1:4 (1 cement : 4 coarse
sand) laid and jointed with grey cement slurry including grinding rubbing and polishing etc. complete. (Area of tile
should be 0.18 sqm and above)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 8420.46
Add 5 % for water, electricity, sundries and other 421.02
overhead charges
TOTAL 8841.48
Add 10 % for contractor's profit 884.15
Cost of 10 sqm. 9725.63
Cost of 1 sqm. 972.56
Say 973.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 16909.90
Add 5 % for water, electricity, sundries and other 845.50
overhead charges
TOTAL 17755.40
Add 10 % for contractor's profit 1775.54
Cost for 10sqm. 19530.94
Cost for 1sqm. 1953.09
Say 1953.00
12.41 15mm thick Marble tiles in risers and treads of steps skirting dado and pillars laid on 12mm (Average) thick base of
cement mortar 1:3 (1 cement : 3 coarse sand) and jointed with grey cement slurry including rubbing and polishing
etc. complete (Area of tiles to be upto 0.18 sqm)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 9034.90
Add 5 % for water, electricity, sundries and other 451.75
overhead charges
TOTAL 9486.65
Add 10 % for contractor's profit 948.67
Cost for 10sqm. 10435.32
Cost for 1sqm. 1043.53
Say 1044.00
12.41 15mm thick Marble tiles in risers and treads of steps skirting dado and pillars laid on 12mm (Average) thick base of
cement mortar 1:3 (1 cement : 3 coarse sand) and jointed with grey cement slurry including rubbing and polishing
etc. complete (Area of tiles to be upto 0.18 sqm)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 11659.90
Add 5 % for water, electricity, sundries and other 583.00
overhead charges
TOTAL 12242.90
Add 10 % for contractor's profit 1224.29
Cost for 10sqm. 13467.19
Cost for 1sqm. 1346.71
Say 1347.00
12.41 15mm thick Marble tiles in risers and treads of steps skirting dado and pillars laid on 12mm (Average) thick base of
cement mortar 1:3 (1 cement : 3 coarse sand) and jointed with grey cement slurry including rubbing and polishing
etc. complete (Area of tiles to be upto 0.18 sqm)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 9622.40
Add 5 % for water, electricity, sundries and other 481.12
overhead charges
TOTAL 10103.52
Add 10 % for contractor's profit 1010.35
Cost for 10sqm. 11113.87
Cost for 1sqm. 1111.38
Say 1111.00
12.41 15mm thick Marble tiles in risers and treads of steps skirting dado and pillars laid on 12mm (Average) thick base of
cement mortar 1:3 (1 cement : 3 coarse sand) and jointed with grey cement slurry including rubbing and polishing
etc. complete (Area of tiles to be upto 0.18 sqm)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 8047.40
Add 5 % for water, electricity, sundries and other 402.37
overhead charges
TOTAL 8449.77
Add 10 % for contractor's profit 844.98
Cost for 10sqm. 9294.75
Cost for 1sqm. 929.47
Say 929.00
12.41 15mm thick Marble tiles in risers and treads of steps skirting dado and pillars laid on 12mm (Average) thick base of
cement mortar 1:3 (1 cement : 3 coarse sand) and jointed with grey cement slurry including rubbing and polishing
etc. complete (Area of tiles to be upto 0.18 sqm)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 9097.40
Add 5 % for water, electricity, sundries and other 454.87
overhead charges
TOTAL 9552.27
Add 10 % for contractor's profit 955.23
Cost for 10sqm. 10507.50
Cost for 1sqm. 1050.75
Say 1051.00
12.42 Extra for using white cement slurry instead of grey cement slurry in joints of marble stone flooring or tiles for all
thickness
Code Description Rate Unit Qty Total
Details of cost for 10 sqm.
TOTAL 700.50
Add 5 % for water, electricity, sundries and other 35.03
overhead charges
TOTAL 735.53
Add 10 % for contractor's profit 73.55
Cost for 10 m. 809.08
Cost for 1 metre 80.90
Say 81.00
12.44 Extra for nosing in Granite stone for treads.
Code Description Rate Unit Qty Total
Details of cost for 10m
Labour-
0103 Mason (for ornamental stone work) 1st class 207.00 day 1.5 day 310.50
TOTAL 1090.50
Add 5 % for water, electricity, sundries and other 54.53
overhead charges
TOTAL 1145.03
Add 10 % for contractor's profit 114.50
Cost for 10 metres 1259.53
Cost for 1 metre 125.95
Say 126.00
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 0.224 cum 594.56
(Rate as per item No 5.9)
0251 Portland Cement 5400.00 tonne 0.05 tonne 270.00
2682 Dark shade pigment 125.00 kg 0.5 kg 62.50
LABOUR
0101 Mason 1st class 207.00 day 1.2 day 248.40
0114 Beldar 190.00 day 3 day 570.00
MACHINERY
0024 Hire charges of Portable Electrical operated stone 100.00 day 1.2 day 120.00
cutter
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 8195.46
Add 5 % for water, electricity, sundries and other 409.77
overhead charges
TOTAL 8605.23
Add 10 % for contractor's profit 860.52
Cost of 10 sqm. 9465.75
Cost of 1 sqm. 946.57
Say 947.00
12.47 8 mm thick Table rubbed polished Granite stone tile flooring laid over 20mm (Average) thick base of cement mortar
1:4 (1 cement : 4 coarse sand) laid and jointed with grey cement slurry including rubbing and polishing etc.
complete.
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 0.224 cum 594.56
(Rate as per item No 5.9)
0251 Portland Cement 5400.00 tonne 0.05 tonne 270.00
2682 Dark shade pigment 125.00 kg 0.5 kg 62.50
LABOUR
0101 Mason 1st class 207.00 day 1.2 day 248.40
0114 Beldar 190.00 day 3 day 570.00
MACHINERY
0024 Hire charges of Portable Electrical operated stone 100.00 day 1.2 day 120.00
cutter
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 17645.46
Add 5 % for water, electricity, sundries and other 882.27
overhead charges
TOTAL 18527.73
Add 10 % for contractor's profit 1852.77
Cost of 10 sqm. 20380.50
Cost of 1 sqm. 2038.05
Say 2038.00
12.48 8 mm thick Table rubbed polished Granite stone tile in risers and treads of steps skirting dado and pillars laid on
12mm (Average) thick base of cement mortar 1:3 (1 cement : 3 coarse sand) and jointed with grey cement slurry
including rubbing and polishing etc. complete.
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.144 cum 483.30
(Rate as per item No 5.8)
0251 Portland Cement 5400.00 tonne 0.05 tonne 270.00
2682 Dark shade pigment 125.00 kg 0.5 kg 62.50
LABOUR
0101 Mason 1st class 207.00 day 3 day 621.00
0114 Beldar 190.00 day 4 day 760.00
MACHINERY
0024 Hire charges of Portable Electrical operated stone 100.00 day 3 day 300.00
cutter
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 8826.80
Add 5 % for water, electricity, sundries and other 441.34
overhead charges
TOTAL 9268.14
Add 10 % for contractor's profit 926.81
Cost of 10 sqm. 10194.95
Cost of 1 sqm. 1019.49
Say 1019.00
12.48 8 mm thick Table rubbed polished Granite stone tile in risers and treads of steps skirting dado and pillars laid on
12mm (Average) thick base of cement mortar 1:3 (1 cement : 3 coarse sand) and jointed with grey cement slurry
including rubbing and polishing etc. complete.
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.144 cum 483.30
(Rate as per item No 5.8)
0251 Portland Cement 5400.00 tonne 0.05 tonne 270.00
2682 Dark shade pigment 125.00 kg 0.5 kg 62.50
LABOUR
0101 Mason 1st class 207.00 day 3 day 621.00
0114 Beldar 190.00 day 4 day 760.00
MACHINERY
0024 Hire charges of Portable Electrical operated stone 100.00 day 3 day 300.00
cutter
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 18276.80
Add 5 % for water, electricity, sundries and other 913.84
overhead charges
TOTAL 19190.64
Add 10 % for contractor's profit 1919.06
Cost of 10 sqm. 21109.70
Cost of 1 sqm. 2110.97
Say 2111.00
12.49 25 mm thick KOTA stone slab flooring over 20mm (Average) thick base of cement mortar 1:4 laid over and jointed
with grey cement slurry mixed with pigment to match the shade of the slab including grinding rubbing and polishing
etc. complete (Area of slab to be over 0.20 sqm and upto 0.50 sqm)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 7770.06
Add 5 % for water, electricity, sundries and other 388.50
overhead charges
TOTAL 8158.56
Add 10 % for contractor's profit 815.86
Cost for 10sqm. 8974.42
Cost for 1sqm. 897.44
Say 897.00
12.50 KOTA stone slab 25mm thick in risers and treads of steps, skirting dado and pillar laid in 12mm (Average) thick
cement mortar 1:3 (1 cement : 3 coarse sand) and jointed with grey cement slurry mixed with pigment to match the
shade of the slab including rubbing and polishing complete. (single stone is to be used for riser and treads of steps
and the width of stone for skirting and dado shall be equal to the height of skirting/ dado up to length of 1.0 M.)
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 8573.40
Add 5 % for water, electricity, sundries and other 428.67
overhead charges
TOTAL 9002.07
Add 10 % for contractor's profit 900.21
Cost for 10sqm. 9902.28
Cost for 1sqm. 990.22
Say 990.00
12.51 Extra for nosing in steps and treads of Kota stone slab.
Code Description Rate Unit Qty Total
Details of cost for 10m
Labour-
0103 Mason (for ornamental stone work) 1st class 207.00 day 1.5 day 310.50
TOTAL 603.00
Add 5 % for water, electricity, sundries and other 30.15
overhead charges
TOTAL 633.15
Add 10 % for contractor's profit 63.32
Cost for 10sqm. 696.47
Cost for 1sqm. 69.64
Say 69.50
12.52 Extra for nosing in steps and treads of red or white rough dressed sand stone.
Code Description Rate Unit Qty Total
Details of cost for 10m
Labour-
0103 Mason (for ornamental stone work) 1st class 207.00 day 1 day 207.00
0014 Hire charges of hand grinder for mirror polish 200.00 day 0.5 day 100.00
TOTAL 307.00
Add 5 % for water, electricity, sundries and other 15.35
overhead charges
TOTAL 322.35
Add 10 % for contractor's profit 32.24
Cost for 10sqm. 354.59
Cost for 1sqm. 35.45
Say 35.50
12.53 Extra for nosing in steps and treads of red or white fine dressed sand stone.
Code Description Rate Unit Qty Total
Details of cost for 10m
Labour-
0103 Mason (for ornamental stone work) 1st class 207.00 day 2 day 414.00
0014 Hire charges of hand grinder for mirror polish 200.00 day 2 day 400.00
TOTAL 814.00
Add 5 % for water, electricity, sundries and other 40.70
overhead charges
TOTAL 854.70
Add 10 % for contractor's profit 85.47
Cost for 10sqm. 940.17
Cost for 1sqm. 94.01
Say 94.00
12.54 Extra for nosing in steps and treads of red or white fine dressed and rubbed sand stone.
Code Description Rate Unit Qty Total
Details of cost for 10m
Labour-
0103 Mason (for ornamental stone work) 1st class 207.00 day 2.5 day 517.50
TOTAL 1017.50
Add 5 % for water, electricity, sundries and other 50.88
overhead charges
TOTAL 1068.38
Add 10 % for contractor's profit 106.84
Cost for 10sqm. 1175.22
Cost for 1sqm. 117.52
Say 118.00
12.55 Extra for necessary grinding and polishing to get mirror finish on KOTA/ Marble Stone flooring/ steps/ treads instead
of normal grinding and polishing.
Code Description Rate Unit Qty Total
Details of cost for 10 sqm.
MACHINERY
0027 Cost of Table rubbing of sand stone 300.00 sqm 10 sqm 3000.00
0026 Cost of Rubbing charges with Machine (Normal) 75.00 sqm -10 sqm -750.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 2280.00
Add 5 % for water, electricity, sundries and other 114.00
overhead charges
TOTAL 2394.00
Add 10 % for contractor's profit 239.40
Cost for 10 sqm. 2633.40
Cost for 1 sqm. 263.34
Say 263.00
12.56 25mm thick Local RAJIM/ Red Flag stone slab flooring laid over 20mm (Average) thick base of cement mortar 1:4 (1
cement : 4 coarse sand) laid over & jointed with grey cement slurry mixed with pigments to match the shade of the
stone i/c grinding, rubbing and polishing.
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 4468.96
Add 5 % for water, electricity, sundries and other 223.45
overhead charges
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 5151.46
Add 5 % for water, electricity, sundries and other 257.57
overhead charges
TOTAL 5409.03
Add 10 % for contractor's profit 540.90
Cost for 10sqm. 5949.93
Cost for 1sqm. 594.99
Say 595.00
12.58 25mm thick un-polished Local RAJIM/ Red Flag stone slab flooring laid over 20mm (average) thick base of cement
mortar 1:4 (1 cement : 4 coarse sand) laid over & jointed with grey cement slurry mixed with pigments to match the
shade of the stone.
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 7152.81
Add 5 % for water, electricity, sundries and other 357.64
overhead charges
TOTAL 7510.45
Add 10 % for contractor's profit 751.05
Cost for 10sqm. 8261.50
Cost for 1sqm. 826.15
Say 826.00
12.61 Providing and fixing 20mm thick Jaisalmer stone in skirting, coping, dado tread & risers of steps both sides machine
cut over and including 12mm thick cement plaster in CM 1:4 with cost of pigment, cement labour for grinding with
cost of all materials & labour etc. complete at all heights.
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
TOTAL 8012.31
Add 5 % for water, electricity, sundries and other 400.62
overhead charges
TOTAL 8412.93
Add 10 % for contractor's profit 841.29
Cost for 10sqm. 9254.22
Cost for 1sqm. 925.42
Say 925.00
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.073 cum 245.01
(Rate as per item No 5.8)
LABOUR
0101 Mason 1st class 207.00 day 2.5 day 517.50
0104 Mason 2nd class 197.00 day 2.5 day 492.50
0114 Beldar 190.00 day 5 day 950.00
Total 14605.01
Add 5 % for water, electricity, sundries and other 730.25
overhead charges
Total 15335.26
Add 10 % for contractor's profit 1533.53
Cost of 100 metre 16868.79
cost for 1 metre 168.68
Say 169.00
12.67 Providing and laying brush concrete flooring of 12mm thick cement concrete (1 cement :2 black metal, 6mm size)
mixed with granite pigment of approved quality in a ratio of 2.08 kg/sq metre are laid over & including a base of
40mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm size) with 12.50 mm
size graded B.T metal mechanically mixed including neat cement finish over granite with red colour pigment
including glass strip of size 45x3 mm, cost of all material & labor etc. complete.
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.089 cum 75.65
12.68.2 Other than teak wood such as sal, haldoo and Bija
Code Description Rate Unit Qty Total
Details of cost for 2.5x4=10 sqm.
Materials-
First class deodar wood planks
No of joints = 4000/138 = 28.97
= (29-1) = 28 nos
Qty of wood required
2.5(4+0.336)x0.025 = 0.271 cum
Add wastage @ 10 % = 0.027 cum
= 0.2981 cum
2806 Sal, bija, Haldu wood in planks 48000.00 cum 0.2981 cum 14308.80
2812 Extra for selected planks of sal, haldoo, Bija 6000.00 cum 0.2981 cum 1788.60
0586 M.S. powder coated screws 50 mm 0.85 each 200 each 170.00
2609 Glue 55.00 kg 0.75 kg 41.25
Labour-
0105 Carpenter 1st class 207.00 day 2.16 day 447.12
0114 Beldar 190.00 day 1.08 day 205.20
TOTAL 16960.97
Add 5 % for water, electricity, sundries and other 848.05
overhead charges
TOTAL 17809.02
Add 10 % for contractor's profit 1780.90
Cost for 10 sqm. 19589.92
Cost for 1sqm. 1958.99
Say 1959.00
12.69 38 mm thick parquet (wood blocks) flooring of teak wood laid over 25mm thick leveling layer of cement concrete
1:2:4 (1 cement : 2 coarse sand : 4 stone aggregate 10mm nominal size) to be paid separately coated with thin layer
of hot bitumen (blown type) @ 2.45 kg/ sqm including fixing blocks after dipping in hot bitumen (blown type) upto
half depth planned, leveled, smooth and finished complete.
TOTAL 4379.08
Add 5 % for water, electricity, sundries and other 218.95
overhead charges
TOTAL 4241.00
Add 5 % for water, electricity, sundries and other 212.05
overhead charges
TOTAL 4453.05
Add 10 % for contractor's profit 445.31
Cost of 10.00 sqm. 4898.36
Cost of 1.00 sqm. 489.83
Say 490.00
12.72 Providing and fixing in position homogeneous P.V.C. quartz reinforced floor covering tiles conforming to I.S.
3462/1986 of size 300x300 mm over existing smooth and finished surface including removal of dust etc. from
existing floor and laying approved adhesive (Dunlop S- 758, Fevicol SR 998 or equivalent) at the rate of 0.25 kg/ sqm
including rolling with light wooden roller weighing about 5 kg etc. complete.
TOTAL 4792.25
Add 5 % for water, electricity, sundries and other 239.61
overhead charges
TOTAL 5031.86
Add 10 % for contractor's profit 503.19
Cost of 10.00 sqm. 5535.05
Cost of 1.00 sqm. 553.50
Say 554.00
12.72 Providing and fixing in position homogeneous P.V.C. quartz reinforced floor covering tiles conforming to I.S.
3462/1986 of size 300x300 mm over existing smooth and finished surface including removal of dust etc. from
existing floor and laying approved adhesive (Dunlop S- 758, Fevicol SR 998 or equivalent) at the rate of 0.25 kg/ sqm
including rolling with light wooden roller weighing about 5 kg etc. complete.
TOTAL 6721.63
Add 5 % for water, electricity, sundries and other 336.08
overhead charges
TOTAL 7057.71
Add 10 % for contractor's profit 705.77
Cost of 10.00 sqm. 7763.48
Cost of 1.00 sqm. 776.34
Say 776.00
12.73 Dry brick on edge flooring in required pattern with bricks of class designation 35 on a bed of 12 mm mud mortar
including filling joints with fine sand complete.
Code Description Rate Unit Qty Total
Details of cost for 10 sqm.
MATERIALS :
0401 Modular bricks class designation 35 4.50 each 537 each 2416.50
5.20 Mud mortar (Rate as per Item No.5.20) 244.37 cum 0.15 cum 36.66
LABOUR :
0104 Mason 2nd class 197.00 day 1 day 197.00
0114 Beldar 190.00 day 2 day 380.00
MACHINERY
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.0144 cum 48.33
(Rate as per item No 5.8)
5.16 Cement Mortar White C.M. 1:2 (1 white cement : 2 10877.07 cum 0.003 cum 32.63
marble dust) (Rate as per item No 5.16)
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.5 day 103.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.5 day 103.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.5 day 103.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.5 day 103.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.5 day 103.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.5 day 103.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.5 day 103.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.5 day 103.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.5 day 103.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.5 day 103.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.5 day 103.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.5 day 103.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.5 day 103.50
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 0.024 cum 63.70
(Rate as per item No 5.9)
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 1 day 207.00
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.05 day 10.00
TOTAL 3350.70
Add 5 % for water, electricity, sundries and other 167.54
overhead charges
TOTAL 3518.24
Add 10 % for contractor's profit 351.82
Cost for 1.00 sqm. 3870.06
Say 3870.00
13.3 15 mm thick Marble work (machine cut, table rubbed & polished) for kitchen platform, vanity counters, window sills
and similar locations of required size laid over 20mm thick base cement mortar 1:4 (1 cement : 4 coarse sand)
including joints treated with white cement mixed with matching pigment including rubbing and polishing to edge
moulding to give high gloss finish.
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.05 day 10.00
TOTAL 1750.50
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.05 day 10.00
TOTAL 2315.40
Add 5 % for water, electricity, sundries and other 115.77
overhead charges
TOTAL 2431.17
Add 10 % for contractor's profit 243.12
Cost for 1.00 sqm. 2674.29
Say 2674.00
13.3 15 mm thick Marble work (machine cut, table rubbed & polished) for kitchen platform, vanity counters, window sills
and similar locations of required size laid over 20mm thick base cement mortar 1:4 (1 cement : 4 coarse sand)
including joints treated with white cement mixed with matching pigment including rubbing and polishing to edge
moulding to give high gloss finish.
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.05 day 10.00
TOTAL 1565.70
Add 5 % for water, electricity, sundries and other 78.29
overhead charges
TOTAL 1643.99
Add 10 % for contractor's profit 164.40
Cost for 1.00 sqm. 1808.39
Say 1808.00
13.3 15 mm thick Marble work (machine cut, table rubbed & polished) for kitchen platform, vanity counters, window sills
and similar locations of required size laid over 20mm thick base cement mortar 1:4 (1 cement : 4 coarse sand)
including joints treated with white cement mixed with matching pigment including rubbing and polishing to edge
moulding to give high gloss finish.
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.05 day 10.00
TOTAL 1565.70
Add 5 % for water, electricity, sundries and other 78.29
overhead charges
TOTAL 1643.99
Add 10 % for contractor's profit 164.40
Cost for 1.00 sqm. 1808.39
Say 1808.00
13.3 15 mm thick Marble work (machine cut, table rubbed & polished) for kitchen platform, vanity counters, window sills
and similar locations of required size laid over 20mm thick base cement mortar 1:4 (1 cement : 4 coarse sand)
including joints treated with white cement mixed with matching pigment including rubbing and polishing to edge
moulding to give high gloss finish.
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.05 day 10.00
TOTAL 1775.70
Add 5 % for water, electricity, sundries and other 88.79
overhead charges
TOTAL 1864.49
Add 10 % for contractor's profit 186.45
Cost for 1.00 sqm. 2050.94
Say 2051.00
13.3 15 mm thick Marble work (machine cut, table rubbed & polished) for kitchen platform, vanity counters, window sills
and similar locations of required size laid over 20mm thick base cement mortar 1:4 (1 cement : 4 coarse sand)
including joints treated with white cement mixed with matching pigment including rubbing and polishing to edge
moulding to give high gloss finish.
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.05 day 10.00
TOTAL 2542.20
Add 5 % for water, electricity, sundries and other 127.11
overhead charges
TOTAL 2669.31
Add 10 % for contractor's profit 266.93
Cost for 1.00 sqm. 2936.24
Say 2936.00
13.3 15 mm thick Marble work (machine cut, table rubbed & polished) for kitchen platform, vanity counters, window sills
and similar locations of required size laid over 20mm thick base cement mortar 1:4 (1 cement : 4 coarse sand)
including joints treated with white cement mixed with matching pigment including rubbing and polishing to edge
moulding to give high gloss finish.
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.05 day 10.00
TOTAL 1775.70
Add 5 % for water, electricity, sundries and other 88.79
overhead charges
TOTAL 1864.49
Add 10 % for contractor's profit 186.45
Cost for 1.00 sqm. 2050.94
Say 2051.00
13.4 15mm thick Granite work (machine cut, table rubbed & mirror polished) for wall lining (veneer work) in cement
mortar 1:3 (1 cement : 3 coarse sand) including pointing with cement mortar 1:2 (1 white cement: 2 marble dust)
mixed with matching pigment. (Area of slab should be over 0.5 sqm).
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.5 day 103.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.5 day 103.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.5 day 103.50
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.014 cum 46.99
(Rate as per item No 5.8)
5.16 Cement Mortar White C.M. 1:2 (1 white cement : 2 10877.07 cum 0.003 cum 32.63
marble dust) (Rate as per item No 5.16)
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.014 cum 46.99
(Rate as per item No 5.8)
5.16 Cement Mortar White C.M. 1:2 (1 white cement : 2 10877.07 cum 0.003 cum 32.63
marble dust) (Rate as per item No 5.16)
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 1.5 day 310.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 1.5 day 310.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 1.5 day 310.50
3.1.0.3 Cement concrete 1:3:6 (stone aggregate 20mm) 2970.36 cum 0.04 cum 118.81
(Rate as per Item No 3.1.3)
5.16 Cement Mortar White C.M. 1:2 (1 white cement : 2 10877.07 cum 0.003 cum 32.63
marble dust) (Rate as per item No 5.16)
TOTAL 1572.04
Add 10 % for contractor's profit on all except (A) 145.32
i.e. on (1572.04 - 118.81) = 1453.23
3402 Silicon sealant for joint of wall cladding. 315.00 cartridge 1artridge 315.00
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 2.5 day 517.50
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.15 day 30.00
0024 Hire charges of Portable Electrical operated stone 100.00 day 0.75 day 75.00
cutter
TOTAL 4757.95
Add 5 % for water, electricity, sundries and other 209.89
overhead charges on all except (A) i.e. on (4757.95
- 560.20) = 4197.75
TOTAL 4967.84
Add 10 % for contractor's profit on all except (A) 440.76
i.e. on (4967.84 - 560.20) = 4407.64
TOTAL 1259.35
Add 5 % for water, electricity, sundries and other 6.95
overhead charges on all except (A) i.e. on (1259.35
- 1120.40) = 138.95
TOTAL 1266.30
Add 10 % for contractor's profit on all except (A) 14.59
i.e. on (1266.30 - 1120.40) = 145.90
13.15.2 Stainless steel cramps with stainless steel nuts and bolts and washer (total weight not less than 260 gms).
12x0.2 = 2.40
Total = 5.82sqm
14.19 Painting with epoxy paint over and including epoxy 130.72 sqm 5.82 sqm 760.79
priming coat (Rate as per item no 14.19)
LABOUR
0101 Mason 1st class 207.00 day 0.26 day 53.82
0104 Mason 2nd class 197.00 day 0.26 day 51.22
0119 Bandhani 197.00 day 0.67 day 131.99
0109 Blacksmith 1st class 207.00 day 1.34 day 277.38
0114 Beldar 190.00 day 4.92 day 934.80
MACHINERY
17.34 Double scaffolding (Rate as per Item No. 17.34) 112.04 sqm 2.4 sqm 268.90
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.05 day 10.00
Total 9390.83
Add 5 % for water, electricity, sundries and other 359.24
overhead charges on all except (A) i.e. on (9390.83
- 2206.08) = 7184.75
Total 9750.07
Add 10 % for contractor's profit on all except (A) 754.40
i.e. on (9750.07 - 2206.08) = 7543.99
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 1 day 207.00
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 1 day 207.00
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 1 day 207.00
TOTAL 895.50
Add 5 % for water, electricity, sundries and other 44.78
overhead charges
TOTAL 940.28
Add 10 % for contractor's profit 94.03
Cost for 10 metre 1034.31
Cost per metre 103.43
Say 103.00
13.19 Extra for providing edge moulding to 15mm thick stone counters, vanities etc. including machine polishing to edge
to give high gloss finish etc. complete as per design approved by Engineer-in-Charge.
13.19.2 Granite work
Code Description Rate Unit Qty Total
Details of cost for 10.00 m
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 2.5 day 517.50
TOTAL 1492.50
Add 5 % for water, electricity, sundries and other 74.63
overhead charges
TOTAL 1567.13
MATERIAL
0942 Araldite 844.00 kg 0.25 kg 211.00
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum -0.005 cum -13.27
(Rate as per item No 5.9)
1.5x0.15x0.02 = 0.005cum.
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.3 day 62.10
TOTAL 218.80
Add 5 % for water, electricity, sundries and other 10.94
overhead charges
TOTAL 229.74
Add 10 % for contractor's profit 22.97
Cost per opening 252.71
Say 253.00
TOTAL 1791.00
Add 5 % for water, electricity, sundries and other 89.55
overhead charges
TOTAL 1880.55
Add 10 % for contractor's profit 188.06
Cost for 10 sqm. 2068.61
Cost per sqm. 206.86
Say 207.00
13.23 Providing and fixing (Table Rubbed & polished) 30mm thick jali throughout (without sunk or moulded in jali slab) in
white cement mortar 1:2 (1 white cement : 2 marble dust) with and admixture of pigment to match the marble
shade, jali pattern to be cut square to jali slab without any chamfers as per drawings & designs and patterns
approved by the Engineer-in-charge.
5.16 Cement Mortar White C.M. 1:2 (1 white cement : 2 10877.07 cum 0.003 cum 32.63
marble dust) (Rate as per item No 5.16)
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 7.5 day 1552.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 7.5 day 1552.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 7.5 day 1552.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 7.5 day 1552.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 7.5 day 1552.50
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 7.5 day 1552.50
MATERIAL
Raisen stone slab 25mm (average) thick x 1.20 sqm
= 1.20 sqm
Add wastage @10% = 0.12sqm.
Total = 1.32 sqm
0378 Local RAJIM red flag stone 25mm thick one side 195.00 sqm 1.32 sqm 257.40
polished
2682 Dark shade pigment 125.00 kg 0.1 kg 12.50
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.002 cum 6.71
(Rate as per item No 5.8)
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.12 day 24.84
MATERIAL
Raisen stone slab 25mm (average) thick x 1.20 sqm
= 1.20 sqm
Add wastage @10% = 0.12sqm.
Total = 1.32 sqm
0379 Local RAJIM red flag stone 25mm thick both side 260.00 sqm 1.32 sqm 343.20
polished
2682 Dark shade pigment 125.00 kg 0.1 kg 12.50
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.002 cum 6.71
(Rate as per item No 5.8)
LABOUR
0103 Mason (for ornamental stone work) 1st class 207.00 day 0.12 day 24.84
14.1.1 Upto 2 mm thickness to make surface even and smooth in line and level.
Code Description Rate Unit Qty Total
Detail of cost for 10 sqm
MATERIALS
Plaster of paris 10x0.002x1121 = 22.42kg
Add 20% wastage= 4.48kg
Total = 26.9Okg Say 27 kg
2645 Plaster of Paris 6.40 kg 27 kg 172.80
LABOUR
0101 Mason 1st class 207.00 day 0.75 day 155.25
0114 Beldar 190.00 day 0.75 day 142.50
MACHINARY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
0036 Hire charges of scaffolding 11.00 sqm 5 sqm 55.00
TOTAL 545.55
Add 5 % for water, electricity, sundries and other 27.28
overhead charges
TOTAL 572.83
Add 10 % for contractor's profit 57.28
Cost of 10.00 sqm 630.11
Cost of 1.00 sqm 63.01
Say 63.00
14.1 Providing and applying plaster of paris putty over plastered wall surface including scaffolding complete
14.1.2 More than 2 mm thickness to make surface even and smooth in true plumb and line and level.
Code Description Rate Unit Qty Total
Detail of cost for 10 sqm
MATERIALS
Plaster of paris 10x0.003x1121 = 33.63kg
Add 20% wastage= 6.73kg
Total = 40.35kg Say 40 kg
2645 Plaster of Paris 6.40 kg 40 kg 256.00
LABOUR
0101 Mason 1st class 207.00 day 1.2 day 248.40
0114 Beldar 190.00 day 1.2 day 228.00
MACHINARY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
0036 Hire charges of scaffolding 11.00 sqm 5 sqm 55.00
TOTAL 807.40
Add 5 % for water, electricity, sundries and other 40.37
overhead charges
TOTAL 847.77
Add 10 % for contractor's profit 84.78
Cost of 10.00 sqm 932.55
Cost of 1.00 sqm 93.25
14.2.1 Upto 2 mm thickness to make surface even and smooth in line and level.
Code Description Rate Unit Qty Total
Detail of cost for 10 sqm
MATERIALS
Plaster of paris 10x0.002x1121 = 22.42kg
Add 20% wastage= 4.48kg
Total = 26.9Okg Say 27 kg
2645 Plaster of Paris 6.40 kg 27 kg 172.80
LABOUR
0101 Mason 1st class 207.00 day 0.9 day 186.30
0114 Beldar 190.00 day 0.9 day 171.00
MACHINARY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
0036 Hire charges of scaffolding 11.00 sqm 2 sqm 22.00
TOTAL 572.10
Add 5 % for water, electricity, sundries and other 28.61
overhead charges
TOTAL 600.71
Add 10 % for contractor's profit 60.07
Cost of 10.00 sqm 660.78
Cost of 1.00 sqm 66.07
Say 66.00
14.2 Providing and applying plaster of paris putty over plastered ceiling surface including scaffolding complete.
14.2.2 More than 2 mm thickness to make surface even and smooth in true plumb and line and level.
Code Description Rate Unit Qty Total
Detail of cost for 10 sqm
MATERIALS
Plaster of paris 10x0.003x1121 = 33.63kg
Add 20% wastage= 6.73kg
Total = 40.35kg Say 40 kg
2645 Plaster of Paris 6.40 kg 40 kg 256.00
LABOUR
0101 Mason 1st class 207.00 day 1.1 day 227.70
0114 Beldar 190.00 day 1.1 day 209.00
MACHINARY
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.1 day 20.00
0036 Hire charges of scaffolding 11.00 sqm 2 sqm 22.00
TOTAL 734.70
Add 5 % for water, electricity, sundries and other 36.74
overhead charges
TOTAL 771.44
Add 10 % for contractor's profit 77.14
Cost of 10.00 sqm 848.58
14.15.1 On new work (Two or more coats applied @ 1.43 ltr/ 10 sqm over and including priming coat of exterior primer
applied @ 2.20 kg/ 10 sqm)
14.15.2 On old work (One or more coats applied @ 0.83 ltr/ 10 sqm)
Code Description Rate Unit Qty Total
Detail of cost for 10 sqm
MATERIALS
2639 Acrylic exterior paint 128.00 litre 0.83 litre 106.24
2602 Painting Brush 60.00 each 0.3 each 18.00
LABOUR
0111 Painter 197.00 day 0.6 day 118.20
0114 Beldar 190.00 day 0.35 day 66.50
MACHINERY
0037 Hire charges of ladder 3.5 metre 16.00 day 0.6 day 9.60
TOTAL 318.54
Add 5 % for water, electricity, sundries and other 15.93
overhead charges
TOTAL 334.47
Add 10 % for contractor's profit 33.45
Cost of 10.00 sqm 367.92
Cost of 1.00 sqm 36.79
Say 37.00
14.16 Painting exterior surface with PREMIUM ACRYLIC SMOOTH exterior paint of required shade as per manufacturer's
specifications to give protective and decorative finish including cleaning washing of surface etc. complete with:
14.16.1 On new work (Two or more coats applied @ 1.43 ltr/ 10 sqm over and including priming coat of exterior primer
applied @ 2.20 kg/ 10 sqm)
Code Description Rate Unit Qty Total
Detail of cost for 10 sqm
14.16.2 On old work (One or more coats applied @ 0.83 ltr/ 10 sqm)
Code Description Rate Unit Qty Total
Detail of cost for 10 sqm
MATERIALS
2656 Premium Acrylic Exterior paint 240.00 litre 0.83 litre 199.20
2602 Painting Brush 60.00 each 0.3 each 18.00
LABOUR
0111 Painter 197.00 day 0.6 day 118.20
0114 Beldar 190.00 day 0.35 day 66.50
MACHINERY
0037 Hire charges of ladder 3.5 metre 16.00 day 0.6 day 9.60
TOTAL 411.50
Add 5 % for water, electricity, sundries and other 20.58
overhead charges
TOTAL 432.08
Add 10 % for contractor's profit 43.21
Cost of 10.00 sqm 475.29
Cost of 1.00 sqm 47.52
Say 47.50
14.17 Painting exterior surface with TEXTURED exterior paint of required shade as per manufacturer's specifications to
give protective and decorative finish including cleaning washing of surface etc. complete with:
14.17.1 On new work (Two or more coats applied @ 3.28 ltr/10 sqm) over and including priming coat of exterior primer
applied @ 2.20kg/ 10 sqm
Code Description Rate Unit Qty Total
Detail of cost for 10 sqm
MATERIALS
2640 Textured exterior paint 295.00 litre 3.38 litre 997.10
14.17.2 On old work (One or more coats applied @ 1.82 ltr/ 10 sqm)
Code Description Rate Unit Qty Total
Detail of cost for 10 sqm
MATERIALS
2640 Textured exterior paint 295.00 litre 1.82 litre 536.90
2602 Painting Brush 60.00 each 0.2 each 12.00
LABOUR
0111 Painter 197.00 day 0.4 day 78.80
0114 Beldar 190.00 day 0.25 day 47.50
MACHINERY
0037 Hire charges of ladder 3.5 metre 16.00 day 0.4 day 6.40
TOTAL 681.60
Add 5 % for water, electricity, sundries and other 34.08
overhead charges
TOTAL 715.68
Add 10 % for contractor's profit 71.57
Cost of 10.00 sqm 787.25
Cost of 1.00 sqm 78.72
Say 78.50
14.18 Providing and applying synthetic/ acrylic plaster giving protective layer and decorative finish on any surface in
approved design and shade as per manufacturer's specifications:
14.18.1 2.0mm thickness (average) having design scratched with special rollar.
Code Description Rate Unit Qty Total
Detail of cost for 10 sqm
MATERIALS
2701 Synthetic plaster aggregate paste 120.00 kg 27.5 kg 3300.00
LABOUR
0101 Mason 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
MACHINERY
TOTAL 43.51
Add 5 % for water, electricity, sundries and other 2.18
overhead charges
TOTAL 45.69
Add 10 % for contractor's profit 4.57
Cost of 10.00 sqm 50.26
TOTAL 19.30
Add 5 % for water, electricity, sundries and other 0.97
overhead charges
TOTAL 20.27
Add 10 % for contractor's profit 2.03
Cost of 10.00 sqm 22.30
Cost of 1.00 sqm 2.23
Say 2.20
14.25 Providing and laying French sprit polish on new wood work after preparing the surface by rubbing down smooth
with sand papers, covering the knots, if visible, applying a coat of wood filler, cleaning the surface, applying 50 or
more coats of French spirit polish till the surface gives high gloss.
MATERIALS
2629 Black japan paint 90.00 litre 0.56 litre 50.40
2602 Painting Brush 60.00 each 0.1 each 6.00
2601 Stencil 11.00 each 1 each 11.00
LABOUR
0111 Painter 197.00 day 2 day 394.00
0114 Beldar 190.00 day 2 day 380.00
MACHINERY
0037 Hire charges of ladder 3.5 metre 16.00 day 2 day 32.00
TOTAL 873.40
Add 5 % for water, electricity, sundries and other 43.67
overhead charges
TOTAL 917.07
MATERIALS
2629 Black japan paint 90.00 litre 0.37 litre 33.30
2602 Painting Brush 60.00 each 0.1 each 6.00
2601 Stencil 11.00 each 1 each 11.00
LABOUR
0111 Painter 197.00 day 1.5 day 295.50
0114 Beldar 190.00 day 1.5 day 285.00
MACHINERY
0037 Hire charges of ladder 3.5 metre 16.00 day 1.5 day 24.00
TOTAL 654.80
Add 5 % for water, electricity, sundries and other 32.74
overhead charges
TOTAL 687.54
Add 10 % for contractor's profit 68.75
Cost of 100 letters of 15 cm height 756.29
Cost of 1 letters of 1 cm height 0.50
Say 0.50
14.43 Coal tarring two coats on new work using 0.16 and 0.12 litre coal tar per sqm in the first and second coat
respectively.
Code Description Rate Unit Qty Total
Detail of cost for 10 sqm
MATERIALS
2649 Satna lime 500.00 quintal 0.005 quintal 2.50
3307 Coal Tar 25.00 litre 2.8 litre 70.00
2602 Painting Brush 60.00 each 0.1 each 6.00
3501 Kerosene oil 30.00 litre 0.5 litre 15.00
LABOUR
0114 Beldar 190.00 day 0.43 day 81.70
MACHINERY
0037 Hire charges of ladder 3.5 metre 16.00 day 0.1 day 1.60
TOTAL 176.80
Add 5 % for water, electricity, sundries and other 8.84
overhead charges
TOTAL 185.64
Add 10 % for contractor's profit 18.56
Cost of 10.00 sqm 204.20
Cost of 1.00 sqm 20.42
Say 20.50
0020 Hire and running charges of light crane. 2200.00 day 0.06 day 132.00
LABOUR
0121 Mistry 207.00 day 0.08 day 16.56
0114 Beldar 190.00 day 2 day 380.00
TOTAL 17918.56
Add 5 % for water, electricity, sundries and other 895.93
overhead charges
TOTAL 18814.49
Add 10 % for contractor's profit 1881.45
Cost for 20 metre pile 20695.94
Cost for 1 metre pile 1034.79
Say 1035.00
15.1 Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified diameter and
length below the pile cap in cement concrete M-35 grade, to carry safe working load not less than specified,
excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the
pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile
cap):
0020 Hire and running charges of light crane. 2200.00 day 0.06 day 132.00
LABOUR
0020 Hire and running charges of light crane. 2200.00 day 0.06 day 132.00
LABOUR
0121 Mistry 207.00 day 0.08 day 16.56
0114 Beldar 190.00 day 2 day 380.00
TOTAL 26078.56
Add 5 % for water, electricity, sundries and other 1303.93
overhead charges
TOTAL 27382.49
Add 10 % for contractor's profit 2738.25
Cost for 20 metre pile 30120.74
Cost for 1 metre pile 1506.03
Say 1506.00
15.1 Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified diameter and
length below the pile cap in cement concrete M-35 grade, to carry safe working load not less than specified,
excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the
pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile
cap):
0020 Hire and running charges of light crane. 2200.00 day 0.06 day 132.00
LABOUR
0121 Mistry 207.00 day 0.08 day 16.56
0114 Beldar 190.00 day 2 day 380.00
TOTAL 26078.56
Add 5 % for water, electricity, sundries and other 1303.93
overhead charges
TOTAL 27382.49
Add 10 % for contractor's profit 2738.25
Cost for 20 metre pile 30120.74
Cost for 1 metre pile 1506.03
Say 1506.00
15.1 Providing, driving and installing driven cast-in-situ reinforced cement concrete piles of specified diameter and
length below the pile cap in cement concrete M-35 grade, to carry safe working load not less than specified,
excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the
pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile
cap):
0020 Hire and running charges of light crane. 2200.00 day 0.06 day 132.00
LABOUR
0121 Mistry 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 3.5 day 665.00
TOTAL 29775.98
Add 5 % for water, electricity, sundries and other 1488.80
overhead charges
TOTAL 31264.78
Add 10 % for contractor's profit 3126.48
Cost for 15 metre pile 34391.26
Cost for 1 metre pile 2292.75
0020 Hire and running charges of light crane. 2200.00 day 0.06 day 132.00
0018 Hire and running charges of bentonite pump. 4200.00 day 0.38 day 1596.00
0005 Hire and running charges of loader. 4000.00 day 0.3 day 1200.00
0004 Hire and running charges of tipper 1700.00 day 0.3 day 510.00
LABOUR
0121 Mistry 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 2 day 380.00
TOTAL 16578.84
Add 5 % for water, electricity, sundries and other 828.94
overhead charges
TOTAL 17407.78
Add 10 % for contractor's profit 1740.78
Cost for 20 metre pile 19148.56
Cost for 1 metre pile 957.42
Say 957.00
15.2 Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified diameter and length
below the pile cap in cement concrete M-35 grade, to carry a safe working load not less than specified, excluding the
cost of steel reinforcement but including the cost of boring with, bentonite solution and temporary casing of
appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap
etc. all complete, including removal of excavated earth with all lifts and leads (Length of pile for payment shall be
measured upto bottom of pile cap):
0020 Hire and running charges of light crane. 2200.00 day 0.06 day 132.00
0018 Hire and running charges of bentonite pump. 4200.00 day 0.38 day 1596.00
0005 Hire and running charges of loader. 4000.00 day 0.3 day 1200.00
0004 Hire and running charges of tipper 1700.00 day 0.3 day 510.00
LABOUR
0121 Mistry 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 2 day 380.00
TOTAL 16780.34
Add 5 % for water, electricity, sundries and other 839.02
overhead charges
TOTAL 17619.36
Add 10 % for contractor's profit 1761.94
Cost for 20 metre pile 19381.30
Cost for 1 metre pile 969.06
Say 969.00
15.2 Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified diameter and length
below the pile cap in cement concrete M-35 grade, to carry a safe working load not less than specified, excluding the
cost of steel reinforcement but including the cost of boring with, bentonite solution and temporary casing of
appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap
etc. all complete, including removal of excavated earth with all lifts and leads (Length of pile for payment shall be
measured upto bottom of pile cap):
0020 Hire and running charges of light crane. 2200.00 day 0.63 day 1386.00
0018 Hire and running charges of bentonite pump. 4200.00 day 0.38 day 1596.00
0005 Hire and running charges of loader. 4000.00 day 0.3 day 1200.00
0004 Hire and running charges of tipper 1700.00 day 0.3 day 510.00
Labour
0121 Mistry 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 2.5 day 475.00
TOTAL 21946.84
Add 5 % for water, electricity, sundries and other 1097.34
overhead charges
TOTAL 23044.18
Add 10 % for contractor's profit 2304.42
Cost for 20 metre pile 25348.60
0020 Hire and running charges of light crane. 2200.00 day 0.06 day 132.00
0018 Hire and running charges of bentonite pump. 4200.00 day 0.38 day 1596.00
0004 Hire and running charges of tipper 1700.00 day 0.3 day 510.00
0005 Hire and running charges of loader. 4000.00 day 0.3 day 1200.00
LABOUR
0121 Mistry 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 2.5 day 475.00
TOTAL 25205.84
Add 5 % for water, electricity, sundries and other 1260.29
overhead charges
TOTAL 26466.13
Add 10 % for contractor's profit 2646.61
Cost for 20 metre pile 29112.74
Cost for 1 metre pile 1455.63
Say 1456.00
15.2 Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified diameter and length
below the pile cap in cement concrete M-35 grade, to carry a safe working load not less than specified, excluding the
cost of steel reinforcement but including the cost of boring with, bentonite solution and temporary casing of
appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap
etc. all complete, including removal of excavated earth with all lifts and leads (Length of pile for payment shall be
measured upto bottom of pile cap):
0020 Hire and running charges of light crane. 2200.00 day 0.06 day 132.00
0018 Hire and running charges of bentonite pump. 4200.00 day 0.38 day 1596.00
0004 Hire and running charges of tipper 1700.00 day 0.3 day 510.00
0005 Hire and running charges of loader. 4000.00 day 0.3 day 1200.00
LABOUR
0121 Mistry 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 3 day 570.00
TOTAL 30555.84
Add 5 % for water, electricity, sundries and other 1527.79
overhead charges
TOTAL 32083.63
Add 10 % for contractor's profit 3208.36
Cost for 20 metre pile 35291.99
Cost for 1 metre pile 1764.59
Say 1765.00
15.2 Boring, providing and installing bored cast-in-situ reinforced cement concrete pile of specified diameter and length
below the pile cap in cement concrete M-35 grade, to carry a safe working load not less than specified, excluding the
cost of steel reinforcement but including the cost of boring with, bentonite solution and temporary casing of
appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap
etc. all complete, including removal of excavated earth with all lifts and leads (Length of pile for payment shall be
measured upto bottom of pile cap):
0020 Hire and running charges of light crane. 2200.00 day 0.06 day 132.00
0018 Hire and running charges of bentonite pump. 4200.00 day 0.75 day 3150.00
0004 Hire and running charges of tipper 1700.00 day 0.3 day 510.00
0005 Hire and running charges of loader. 4000.00 day 0.3 day 1200.00
LABOUR
0121 Mistry 207.00 day 0.14 day 28.98
0114 Beldar 190.00 day 3.5 day 665.00
TOTAL 30415.98
Add 5 % for water, electricity, sundries and other 1520.80
overhead charges
TOTAL 31936.78
Add 10 % for contractor's profit 3193.68
Cost for 15 metre pile 35130.46
0020 Hire and running charges of light crane. 2200.00 day 0.03 day 66.00
0018 Hire and running charges of bentonite pump. 4200.00 day 0.02 day 84.00
LABOUR
0121 Mistry 207.00 day 0.08 day 16.56
0114 Beldar 190.00 day 2 day 380.00
TOTAL 13034.56
Add 5 % for water, electricity, sundries and other 651.73
overhead charges
TOTAL 13686.29
Add 10 % for contractor's profit 1368.63
Cost for 10 metre pile 15054.92
Cost for 1 metre pile 1505.49
Say 1505.00
15.3 Boring, Providing and installing cast in situ single under reamed piles of specified diameter and length below pile
cap in cement concrete M-35 grade, to carry a safe working load not less than specified, excluding the cost of steel
reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in
pile cap etc. all complete. (Length of pile for payment shall be measured upto to the bottom of pile cap):
0020 Hire and running charges of light crane. 2200.00 day 0.06 day 132.00
0018 Hire and running charges of bentonite pump. 4200.00 day 0.02 day 84.00
LABOUR
0121 Mistry 207.00 day 0.08 day 16.56
0114 Beldar 190.00 day 2 day 380.00
TOTAL 13317.56
Add 5 % for water, electricity, sundries and other 665.88
overhead charges
TOTAL 13983.44
Add 10 % for contractor's profit 1398.34
Cost for 10 metre pile 15381.78
Cost for 1 metre pile 1538.17
Say 1538.00
15.3 Boring, Providing and installing cast in situ single under reamed piles of specified diameter and length below pile
cap in cement concrete M-35 grade, to carry a safe working load not less than specified, excluding the cost of steel
reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in
pile cap etc. all complete. (Length of pile for payment shall be measured upto to the bottom of pile cap):
0020 Hire and running charges of light crane. 2200.00 day 0.06 day 132.00
0018 Hire and running charges of bentonite pump. 4200.00 day 0.02 day 84.00
LABOUR
0121 Mistry 207.00 day 0.08 day 16.56
0114 Beldar 190.00 day 2 day 380.00
TOTAL 13441.56
Add 5 % for water, electricity, sundries and other 672.08
overhead charges
0020 Hire and running charges of light crane. 2200.00 day 0.06 day 132.00
0018 Hire and running charges of bentonite pump. 4200.00 day 0.02 day 84.00
LABOUR
0121 Mistry 207.00 day 0.08 day 16.56
0114 Beldar 190.00 day 2 day 380.00
TOTAL 13472.56
Add 5 % for water, electricity, sundries and other 673.63
overhead charges
TOTAL 14146.19
Add 10 % for contractor's profit 1414.62
Cost for 10 metre pile 15560.81
Cost for 1 metre pile 1556.08
Say 1556.00
15.4 Extra for providing additional bulb in under reamed piles, under specified dia meter (Only the quantity of extra
bulbs are to be paid).
15.4.1 300mm dia piles.
Code Description Rate Unit Qty Total
Details of cost for 1 bulb.
Materials :
Bulb - 0.033 cum
3.3.0.4 RCC M-35 (Rate as per Item No 3.3.4) 4426.15 cum 0.033 cum 0.00
2453 Bentonite 3100.00 tonne 0.003 tonne 9.30
0020 Hire and running charges of light crane. 2200.00 day 0.01 day 22.00
0018 Hire and running charges of bentonite pump. 4200.00 day 0.01 day 42.00
Labour
0121 Mistry 207.00 day 0.02 day 4.14
0114 Beldar 190.00 day 1 day 190.00
Total 947.44
Add 5 % for water, electricity, sundries and other 47.37
overhead charges
Total 994.81
Add 10 % for contractor's profit 99.48
Cost for 1 bulb 1094.29
Say 1094.00
15.4 Extra for providing additional bulb in under reamed piles, under specified dia meter (Only the quantity of extra
bulbs are to be paid).
15.4.2 400mm dia piles.
Code Description Rate Unit Qty Total
Details of cost for 1 bulb.
Materials :
Bulb - 0.063 cum
3.3.0.4 RCC M-35 (Rate as per Item No 3.3.4) 4426.15 cum 0.063 cum 0.00
2453 Bentonite 3100.00 tonne 0.006 tonne 18.60
Machinery
0016 Hire and running charges of hydraulic piling rig with 34000.00 day 0.02 day 680.00
power unit etc. including complete accessories and
shifting at site.
0020 Hire and running charges of light crane. 2200.00 day 0.01 day 22.00
0018 Hire and running charges of bentonite pump. 4200.00 day 0.01 day 42.00
Labour
0121 Mistry 207.00 day 0.02 day 4.14
0114 Beldar 190.00 day 1 day 190.00
Total 956.74
Add 5 % for water, electricity, sundries and other 47.84
overhead charges
Total 1004.58
Add 10 % for contractor's profit 100.46
Cost for 1 bulb 1105.04
Say 1105.00
15.4 Extra for providing additional bulb in under reamed piles, under specified dia meter (Only the quantity of extra
bulbs are to be paid).
15.4.3 450 mm dia piles.
Code Description Rate Unit Qty Total
Details of cost for 1 bulb.
Materials :
0020 Hire and running charges of light crane. 2200.00 day 0.01 day 22.00
0018 Hire and running charges of bentonite pump. 4200.00 day 0.01 day 42.00
Labour
0121 Mistry 207.00 day 0.02 day 4.14
0114 Beldar 190.00 day 1 day 190.00
Total 962.94
Add 5 % for water, electricity, sundries and other 48.15
overhead charges
Total 1011.09
Add 10 % for contractor's profit 101.11
Cost for 1 bulb 1112.20
Say 1112.00
15.4 Extra for providing additional bulb in under reamed piles, under specified dia meter (Only the quantity of extra
bulbs are to be paid).
15.4.4 550 mm dia piles.
Code Description Rate Unit Qty Total
Details of cost for 1 bulb.
Materials :
Bulb - 0.102 cum
3.3.0.4 RCC M-35 (Rate as per Item No 3.3.4) 4426.15 cum 0.102 cum 0.00
2453 Bentonite 3100.00 tonne 0.01 tonne 31.00
Machinery
0016 Hire and running charges of hydraulic piling rig with 34000.00 day 0.02 day 680.00
power unit etc. including complete accessories and
shifting at site.
0020 Hire and running charges of light crane. 2200.00 day 0.01 day 22.00
0018 Hire and running charges of bentonite pump. 4200.00 day 0.02 day 84.00
Labour
0121 Mistry 207.00 day 0.02 day 4.14
0114 Beldar 190.00 day 1 day 190.00
Total 1011.14
Add 5 % for water, electricity, sundries and other 50.56
overhead charges
Total 1061.70
Add 10 % for contractor's profit 106.17
Cost for 1 bulb 1167.87
Say 1168.00
LABOUR
0121 Mistry 207.00 day 0.08 day 16.56
0114 Beldar 190.00 day 2 day 380.00
TOTAL 4957.20
Add 5 % for water, electricity, sundries and other 144.83
overhead charges on all except (A) i.e. on (4957.20
- 2060.64) = 2896.56
TOTAL 5102.03
Add 10 % for contractor's profit on all except (A) 304.14
i.e. on (5102.03 - 2060.64) = 3041.39
LABOUR
0121 Mistry 207.00 day 0.08 day 16.56
0114 Beldar 190.00 day 2 day 380.00
TOTAL 7114.71
Add 5 % for water, electricity, sundries and other 207.33
overhead charges on all except (A) i.e. on (7114.71
- 2968.15) = 4146.56
TOTAL 7322.04
Add 10 % for contractor's profit on all except (A) 435.39
i.e. on (7322.04 - 2968.15) = 4353.89
Labour
0121 Mistry 207.00 day 0.02 day 4.14
0114 Beldar 190.00 day 0.75 day 142.50
Total 292.39
Add 5 % for water, electricity, sundries and other 9.83
overhead charges on all except (A) i.e. on (292.39 -
95.75) = 196.64
Total 302.22
Add 10 % for contractor's profit on all except (A) 20.65
i.e. on (302.22 - 95.75) = 206.47
Cost for 1 bulb 322.87
Say 323.00
15.6 Extra for providing additional bulb in under reamed piles, under specified dia using necessary bulb enlarging tool
and by MANUAL MEANS (Only the quantity of extra bulbs are to be paid):
15.6.2 300 mm dia piles.
Code Description Rate Unit Qty Total
Details of cost for 1 bulb.
Materials :
Bulb - 0.033 cum
3.2.0.1 RCC mix 1:1½:3 (stone aggregate 20mm)(Rate as 4162.91 cum 0.033 cum 137.38
per Item No 3.2.1)
Machinery
Labour
0121 Mistry 207.00 day 0.02 day 4.14
0114 Beldar 190.00 day 0.75 day 142.50
Total 334.02
Add 5 % for water, electricity, sundries and other 9.83
overhead charges on all except (A) i.e. on (334.02 -
137.38) = 196.64
Total 343.85
Add 10 % for contractor's profit on all except (A) 20.65
i.e. on (343.85 - 137.38) = 206.47
Cost for 1 bulb 364.50
Say 365.00
15.7 Providing, driving and installing driven Pre-cast reinforced cement concrete piles of specified diameter and length
below the pile cap in M 35 cement concrete to carry safe working load not less than specified. With a central
through preformed hole with M.S. black pipe of dia, 40mm for grouting with cement sand grouting of mix 1:2 (1
cement : 2 coarse sand) under sufficient positive pressure to ensure complete filling including centering, shuttering,
driving and removing the steel casing pipe and lifting casing etc. complete but excluding the cost of steel
reinforcement. (Length of pile for payment shall be measured from top of the shoe to the bottom of pile cap).
0021 Hire and running charges of crane 20 tonne 9250.00 day 0.06 day 555.00
capacity.
LABOUR
0121 Mistry 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 3 day 570.00
TOTAL 21589.46
Add 5 % for water, electricity, sundries and other 1034.78
overhead charges on all except (A) i.e. on
(21589.46 - 893.84) = 20695.62
TOTAL 22624.24
0021 Hire and running charges of crane 20 tonne 9250.00 day 0.06 day 555.00
capacity.
LABOUR
0121 Mistry 207.00 day 1.08 day 223.56
0114 Beldar 190.00 day 10.78 day 2048.20
TOTAL 23504.97
Add 5 % for water, electricity, sundries and other 1118.63
overhead charges on all except (A) i.e. on
(23504.97 - 1132.43) = 22372.54
TOTAL 24623.60
Add 10 % for contractor's profit on all except (A) 2349.12
i.e. on (24623.60 - 1132.43) = 23491.17
0021 Hire and running charges of crane 20 tonne 9250.00 day 0.06 day 555.00
capacity.
LABOUR
0121 Mistry 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 3 day 570.00
TOTAL 22093.35
Add 5 % for water, electricity, sundries and other 1034.78
overhead charges on all except (A) i.e. on
(22093.35 - 1397.73) = 20695.62
TOTAL 23128.13
Add 10 % for contractor's profit on all except (A) 2173.04
i.e. on (23128.13 - 1397.73) = 21730.40
0021 Hire and running charges of crane 20 tonne 9250.00 day 0.06 day 555.00
capacity.
LABOUR
0121 Mistry 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 3 day 570.00
TOTAL 22387.14
Add 5 % for water, electricity, sundries and other 1034.78
overhead charges on all except (A) i.e. on
(22387.14 - 1691.52) = 20695.62
TOTAL 23421.92
Add 10 % for contractor's profit on all except (A) 2173.04
i.e. on (23421.92 - 1691.52) = 21730.40
0021 Hire and running charges of crane 20 tonne 9250.00 day 0.06 day 555.00
capacity.
LABOUR
0121 Mistry 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 3 day 570.00
TOTAL 24570.10
Add 5 % for water, electricity, sundries and other 1034.78
overhead charges on all except (A) i.e. on
(24570.10 - 3874.48) = 20695.62
TOTAL 25604.88
Add 10 % for contractor's profit on all except (A) 2173.04
i.e. on (25604.88 - 3874.48) = 21730.40
TOTAL 33200.00
Add 5 % for water, electricity, sundries and other 1660.00
overhead charges
TOTAL 34860.00
Add 10 % for contractor's profit 3486.00
Cost per test 38346.00
Say 38346.00
15.8 Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of loading platform and
preparation of pile head or construction of test cap and dismantling of test cap after test etc. complete as per
specification & the direction of Engineer in-charge.
TOTAL 15000.00
TOTAL 40300.00
Add 5 % for water, electricity, sundries and other 2015.00
overhead charges
TOTAL 42315.00
Add 10 % for contractor's profit 4231.50
Cost per test 46546.50
Say 46547.00
15.8 Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of loading platform and
preparation of pile head or construction of test cap and dismantling of test cap after test etc. complete as per
specification & the direction of Engineer in-charge.
TOTAL 23000.00
Add 5 % for water, electricity, sundries and other 1150.00
overhead charges
TOTAL 24150.00
Add 10 % for contractor's profit 2415.00
Cost per test 26565.00
Say 26565.00
15.8 Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of loading platform and
preparation of pile head or construction of test cap and dismantling of test cap after test etc. complete as per
specification & the direction of Engineer in-charge.
TOTAL 48500.00
Add 5 % for water, electricity, sundries and other 2425.00
overhead charges
TOTAL 50925.00
Add 10 % for contractor's profit 5092.50
Cost per test 56017.50
Say 56018.00
15.8 Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of loading platform and
preparation of pile head or construction of test cap and dismantling of test cap after test etc. complete as per
specification & the direction of Engineer in-charge.
TOTAL 29500.00
Add 5 % for water, electricity, sundries and other 1475.00
overhead charges
TOTAL 30975.00
Add 10 % for contractor's profit 3097.50
Cost per test 34072.50
Say 34073.00
15.9 Cyclic vertical load testing of pile in accordance with IS Code of practice IS : 2911 (part IV) including preparation of
pile head etc for.
15.9.2 Upto 50 tonne capacity pile.
Code Description Rate Unit Qty Total
Details of cost for 1 test
3704 Cyclic verticle load testing of piles in accordance 15000.00 per test 1per test 15000.00
with IS : 2911 (Part-IV) including prepration of pile
head etc. for Single pile upto 50 tonne capacity
TOTAL 15000.00
Add 5 % for water, electricity, sundries and other 750.00
overhead charges
TOTAL 15750.00
Add 10 % for contractor's profit 1575.00
Cost per test 17325.00
Say 17325.00
15.9 Cyclic vertical load testing of pile in accordance with IS Code of practice IS : 2911 (part IV) including preparation of
pile head etc for.
15.9.3 Above 50 tonne and upto 100 tonne capacity pile.
Code Description Rate Unit Qty Total
Details of cost for 1 test
TOTAL 23000.00
Add 5 % for water, electricity, sundries and other 1150.00
overhead charges
TOTAL 24150.00
Add 10 % for contractor's profit 2415.00
Cost per test 26565.00
Say 26565.00
15.9 Cyclic vertical load testing of pile in accordance with IS Code of practice IS : 2911 (part IV) including preparation of
pile head etc for.
15.9.5 Upto 50 tonne capacity each .
Code Description Rate Unit Qty Total
Details of cost for 1 test
3706 Cyclic verticle load testing of piles in accordance 29500.00 per test 1per test 29500.00
with IS : 2911 (Part-IV) including prepration of pile
head etc. forGroup of two piles upto 50 tonne
capacity each
TOTAL 29500.00
Add 5 % for water, electricity, sundries and other 1475.00
overhead charges
TOTAL 30975.00
Add 10 % for contractor's profit 3097.50
Cost per test 34072.50
Say 34073.00
15.10 Lateral load testing of single pile in accordance with IS Code of practice IS : 2911 (Part IV) for determining safe
allowable lateral load on pile :
15.10.1 Upto 50 tonne capacity pile.
Code Description Rate Unit Qty Total
Details of cost for 1 test
3707 Lateral load testing of single pile in accordance 15000.00 per test 1per test 15000.00
with IS : 2911 part -IV for determining safe
allowable lateral load on pile. Upto 50 tonne
capacity
TOTAL 15000.00
Add 5 % for water, electricity, sundries and other 750.00
overhead charges
TOTAL 15750.00
Add 10 % for contractor's profit 1575.00
Cost per test 17325.00
Say 17325.00
15.10 Lateral load testing of single pile in accordance with IS Code of practice IS : 2911 (Part IV) for determining safe
allowable lateral load on pile :
15.10.2 Above 50 tonne and upto 100 tonne capacity pile.
Code Description Rate Unit Qty Total
Details of cost for 1 test
TOTAL 23500.00
Add 5 % for water, electricity, sundries and other 1175.00
overhead charges
TOTAL 24675.00
Add 10 % for contractor's profit 2467.50
Cost per test 27142.50
Say 27143.00
LABOUR
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 19.00
Add 5 % for water, electricity, sundries and other 0.95
overhead charges
TOTAL 19.95
Add 10 % for contractor's profit 2.00
Cost of 1.00 quintal / m span 21.95
Cost of 1.00 kg /m span 0.21
Say 0.20
16.34 Extra for dismantling steel work for every additional height of one metre or part thereof beyond 5 metres.
17.3.1 In all colours except White, Ivory, Grey, Fume Red Brown,
Code Description Rate Unit Qty Total
Details of cost for 1 sqm
Materials-
Rectified Ceramic Glazed floor tiles 300x300 mm
size = 1.000 sqm
Add for wastage & breakage @ 2.5 % = 0.025 sqm
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.0072 cum 6.12
LABOUR
0102 Mason 1st class 207.00 day 0.51 day 105.57
TOTAL 404.82
Add 10 % for contractor's profit on all except (A) 36.46
i.e. on (404.82 - 40.18) = 364.64
Cost of 1.00 chowkhat 441.28
Say 441.00
17.9 Fixing chowkhats in existing opening including embedding chowkhats in floors or walls cutting masonry for holdfasts
embedding hold fasts in cement concrete blocks with cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded
stone aggregate 20 mm nominal size) painting two coats of approved wood preservative to sides of chowkhats and
making good the damages to walls and floors as required complete including disposal of rubbish to the dumping
ground within 50 metres lead :
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.0048 cum 4.08
LABOUR
0102 Mason 1st class 207.00 day 0.35 day 72.45
0114 Beldar 190.00 day 0.65 day 123.50
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 0.5 sqm 5.50
TOTAL 277.15
Add 5 % for water, electricity, sundries and other 12.81
overhead charges on all except (A) i.e. on (277.15 -
20.87) = 256.28
TOTAL 289.96
Add 10 % for contractor's profit on all except (A) 26.91
i.e. on (289.96 - 20.87) = 269.09
Cost of 1.00 chowkhat 316.87
Say 317.00
17.9 Fixing chowkhats in existing opening including embedding chowkhats in floors or walls cutting masonry for holdfasts
embedding hold fasts in cement concrete blocks with cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded
stone aggregate 20 mm nominal size) painting two coats of approved wood preservative to sides of chowkhats and
making good the damages to walls and floors as required complete including disposal of rubbish to the dumping
ground within 50 metres lead :
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.0024 cum 2.04
LABOUR
0102 Mason 1st class 207.00 day 0.18 day 37.26
0114 Beldar 190.00 day 0.52 day 98.80
MACHINERY
0036 Hire charges of scaffolding 11.00 sqm 0.5 sqm 5.50
TOTAL 193.18
Add 5 % for water, electricity, sundries and other 8.45
overhead charges on all except (A) i.e. on (193.18 -
24.20) = 168.98
TOTAL 201.63
Add 10 % for contractor's profit on all except (A) 17.74
i.e. on (201.63 - 24.20) = 177.43
Cost of 1.00 chowkhat 219.37
Say 219.00
17.10 Fixing chowkhat in existing opening in brick / RCC wall with dash fasteners/ chemical fastener of appropriate size
(3nos on each vertical member of door chowkhat and 2 nos. on each vertical member of window chowkhats
including cost of dash fasteners/ chemical fastener.
TOTAL 81.50
Add 5 % for water, electricity, sundries and other 4.08
overhead charges
TOTAL 85.58
Add 10 % for contractor's profit 8.56
Cost of 1.00 chowkhat 94.14
Say 94.00
17.11 Making the opening in brick masonry for door/ window/ clerestory window including dismantling in floor or walls
by cutting masonry and making good the damages to walls, flooring and jambs complete to match existing surface
i/c disposal of malba/ rubbish to the nearest municipal dumping ground.
TOTAL 469.16
Add 10 % for contractor's profit on all except (A) 44.43
i.e. on (469.16 - 24.86) = 444.30
Cost of 1.89sqm. 513.59
Cost of 1.00 sqm. 271.74
Say 272.00
17.12 Renewing glass panes, with putty and nails wherever necessary:
17.12.1 Float glass panes of thickness 4 mm
Code Description Rate Unit Qty Total
Detail of cost for 10 glasses area each 0.1sqm.
MATERIALS
2301 Float glass panes 4mm thick 302.40 sqm 1.1 sqm 332.64
2652 Putty for wood work 30.00 kg 0.68 kg 20.40
2466 Wire nails 52.00 kg 0.23 kg 11.96
LABOUR
0113 Glazier 197.00 day 0.23 day 45.31
0114 Beldar 190.00 day 0.23 day 43.70
TOTAL 454.01
Add 5 % for water, electricity, sundries and other 22.70
overhead charges
TOTAL 476.71
Add 10 % for contractor's profit 47.67
Cost of 1.00 sqm 524.38
Say 524.00
17.12 Renewing glass panes, with putty and nails wherever necessary:
17.12.2 Float glass panes of thickness 5.5 mm
Code Description Rate Unit Qty Total
Detail of cost for 10 glasses area each 0.1sqm.
MATERIALS
2302 Float glass panes 5mm thick 378.00 sqm 1.1 sqm 415.80
2652 Putty for wood work 30.00 kg 0.68 kg 20.40
MATERIALS
2301 Float glass panes 4mm thick 302.40 sqm 1.1 sqm 332.64
Wooden fillets -
2802 Teak wood in planks 85000.00 cum 0.00075 cum 63.75
2466 Wire nails 52.00 kg 0.06 kg 3.12
14.23.0.2 Painting on old work (Rate as per item no 14.23.2) 30.08 sqm 0.2 sqm 6.02
LABOUR
0106 Carpenter 2nd class 197.00 day 0.2 day 39.40
0113 Glazier 197.00 day 0.25 day 49.25
0114 Beldar 190.00 day 0.45 day 85.50
TOTAL 579.68
Add 5 % for water, electricity, sundries and other 28.68
overhead charges on all except (A) i.e. on (579.68 -
6.02) = 573.66
TOTAL 608.36
Add 10 % for contractor's profit on all except (A) 60.23
i.e. on (608.36 - 6.02) = 602.34
Cost of 1.00 sqm 668.59
Say 669.00
17.13 Renewing glass panes, with wooden fillets wherever necessary:
17.13.2 Float glass panes of thickness 5.5 mm
Code Description Rate Unit Qty Total
Detail of cost for 10 glasses area each 0.1sqm.
MATERIALS
2302 Float glass panes 5mm thick 378.00 sqm 1.1 sqm 415.80
Wooden fillets -
2802 Teak wood in planks 85000.00 cum 0.00075 cum 63.75
2466 Wire nails 52.00 kg 0.06 kg 3.12
14.23.0.2 Painting on old work (Rate as per item no 14.23.2) 30.08 sqm 0.2 sqm 6.02
LABOUR
TOTAL 695.68
Add 10 % for contractor's profit on all except (A) 68.97
i.e. on (695.68 - 6.02) = 689.66
Cost of 1.00 sqm 764.65
Say 765.00
17.14 Renewing glass panes and refixing existing wooden fillets:
17.14.1 Float glass panes of thickness 4 mm
Code Description Rate Unit Qty Total
Detail of cost for 10 glasses area each 0.1sqm.
MATERIALS
Glass panes = 1 sqm
Add Wastage @ 10% = 0.1 sqm
Total = 1.10 sqm
2301 Float glass panes 4mm thick 302.40 sqm 1.1 sqm 332.64
2466 Wire nails 52.00 kg 0.24 kg 12.48
2654 Spirit 65.00 litre 0.21 litre 13.65
LABOUR
0113 Glazier 197.00 day 0.3 day 59.10
0114 Beldar 190.00 day 0.3 day 57.00
TOTAL 474.87
Add 5 % for water, electricity, sundries and other 23.74
overhead charges
TOTAL 498.61
Add 10 % for contractor's profit 49.86
Cost of 1.00 sqm 548.47
Say 548.00
17.14 Renewing glass panes and refixing existing wooden fillets:
17.14.2 Float glass panes of thickness 5.5 mm
Code Description Rate Unit Qty Total
Detail of cost for 10 glasses area each 0.1sqm.
MATERIALS
Glass panes = 1 sqm
Add Wastage @ 10% = 0.1 sqm
Total = 1.10 sqm
2302 Float glass panes 5mm thick 378.00 sqm 1.1 sqm 415.80
2466 Wire nails 52.00 kg 0.24 kg 12.48
2654 Spirit 65.00 litre 0.21 litre 13.65
LABOUR
0113 Glazier 197.00 day 0.3 day 59.10
LABOUR
0109 Blacksmith 1st class 207.00 day 0.03 day 6.21
0104 Mason 2nd class 197.00 day 0.12 day 23.64
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 127.88
Add 5 % for water, electricity, sundries and other 5.14
overhead charges on all except (A) i.e. on (127.88 -
25.17) = 102.71
TOTAL 133.02
Add 10 % for contractor's profit on all except (A) 10.79
i.e. on (133.02 - 25.17) = 107.85
Cost of 1 each 143.81
Say 144.00
17.20 Replacing Dholpur sand stone slabs 30 to 50 mm thick in roofing laid in cement mortar 1:4 (1 cement : 4 coarse
sand) including necessary repairs and cement pointing with same mortar complete including disposal of rubbish to
dumping ground within 50 metres of lead :
Supporting Wood
2806 Sal, bija, Haldu wood in planks 48000.00 cum 0.306 cum 14688.00
2673 Oil type wood preservative 70.00 litre 1.22 litre 85.40
2602 Painting Brush 60.00 each 0.1 each 6.00
5.4 Cement Mortar C.M. 1:4 (1 cement : 4 fine sand) 2654.27 cum 0.1 cum 265.43
(Rate as per item No 5.4)
LABOUR
0106 Carpenter 2nd class 197.00 day 0.5 day 98.50
0114 Beldar 190.00 day 2.2 day 418.00
0111 Painter 197.00 day 0.183 day 36.05
TOTAL 15597.38
Add 5 % for water, electricity, sundries and other 779.87
overhead charges
TOTAL 16377.25
Add 10 % for contractor's profit 1637.73
Cost of 300 Cudm 18014.98
Cost of 1.00 cum 60049.93
Say 60050.00
17.22 Renewing Bijasal wooden beams in roofs including making good the holes in walls and painting with oil type wood
preservative of approved brand and manufacture complete including removal of rubbish to the dumping ground
within 50 metres lead :
5x1.0x0.1x0.1 =0.05cum
These materials can be used for 16 times
Hence qty for one operation 0.05/16 = 0.0031
2806 Sal, bija, Haldu wood in planks 48000.00 cum 0.3091 cum 14836.80
Painting with oil preservative
(4x1.1)+(2.0x0.25x0.30)=4.4+0.15=4.55 sqm
2673 Oil type wood preservative 70.00 litre 0.455 litre 31.85
2602 Painting Brush 60.00 each 0.03 each 1.80
2815 Nilgiri ballies 125 mm diameter 42.00 metre 2.5 metre 105.00
5.4 Cement Mortar C.M. 1:4 (1 cement : 4 fine sand) 2654.27 cum 0.009 cum 23.89
(Rate as per item No 5.4)
LABOUR
0106 Carpenter 2nd class 197.00 day 1.25 day 246.25
0104 Mason 2nd class 197.00 day 0.13 day 25.61
0114 Beldar 190.00 day 1.65 day 313.50
0111 Painter 197.00 day 0.07 day 13.79
MATERIAL
0036 Hire charges of scaffolding 11.00 sqm 20 sqm 220.00
TOTAL 15818.49
Add 5 % for water, electricity, sundries and other 790.92
overhead charges
TOTAL 16609.41
Add 10 % for contractor's profit 1660.94
Cost of 300 Cudm 18270.35
Cost of 1.00 cum 60901.16
Say 60901.00
17.22 Renewing Bijasal wooden beams in roofs including making good the holes in walls and painting with oil type wood
preservative of approved brand and manufacture complete including removal of rubbish to the dumping ground
within 50 metres lead :
6 x1.0x0.1x0.1 =0.06cum
These materials can be used for 16 times
Hence qty for one operation 0.06/16 = 0.00375
cudm
2806 Sal, bija, Haldu wood in planks 48000.00 cum 0.3867 cum 18561.60
2673 Oil type wood preservative 70.00 litre 0.565 litre 39.55
2602 Painting Brush 60.00 each 0.04 each 2.40
2815 Nilgiri ballies 125 mm diameter 42.00 metre 3.75 metre 157.50
5.4 Cement Mortar C.M. 1:4 (1 cement : 4 fine sand) 2654.27 cum 0.009 cum 23.89
(Rate as per item No 5.4)
LABOUR
0106 Carpenter 2nd class 197.00 day 1.25 day 246.25
0104 Mason 2nd class 197.00 day 0.25 day 49.25
0114 Beldar 190.00 day 2.75 day 522.50
0111 Painter 197.00 day 0.08 day 15.76
MATERIAL
0036 Hire charges of scaffolding 11.00 sqm 20 sqm 220.00
TOTAL 19838.70
Add 5 % for water, electricity, sundries and other 991.94
overhead charges
TOTAL 20830.64
Add 10 % for contractor's profit 2083.06
Cost of 300 Cudm 22913.70
Cost of 1.00 cum 76379.00
Say 76379.00
17.23 Renewing aluminium door/ window by replacing demaged member by anodised/ powder coated aluminium
sections of same diamentions complete including depositng dismentalled section at departmental store.
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0105 Carpenter 1st class 207.00 day 0.25 day 51.75
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 6188.09
Add 5 % for water, electricity, sundries and other 309.40
overhead charges
TOTAL 6497.49
Add 10 % for contractor's profit 649.75
Cost for 20.21 kg 7147.24
Cost for 1 kg 353.64
Say 354.00
17.24 Providing and fixing galvanized wire gauge having M.S. wire dia of 0.45 mm for doors, windows, clerestory windows
excluding hinges.
Code Description Rate Unit Qty Total
Detail of cost for door shutter size = 2.00x1.08m =
2.16 sqm._x000D_
Wire gauge size = 2x160x40cm = 1.28 sqm
Materials-
Beading = 4x(1.6+0.4) = 8m
Taking 25% new = 2 m
2795 Teak wood beading 19 x 12 mm 35.00 Metre 2 Metre 70.00
Wire gauge 2x160x40cm = 1.28 sqm
Add wastage 10% = 0.13 sqm Total = 1.41 sqm.
0858 Stainless steel wire mesh of average width of 315.00 sqm 1.41 sqm 444.15
aperture 1.56 mm and nominal dia. of wire 0.45
mm
17.25.1 12mm thick unveneered Nova teak or equivalent super plain tiles
Code Description Rate Unit Qty Total
Details of cost for 10.00 sqm.
MATERIAL
0425 Plain ceiling tiles (BWP type phenol formaldehyde 110.00 each 30.56 each 3361.60
synthetic resin bonded) (600x600x12 mm)
LABOUR
0109 Blacksmith 1st class 207.00 day 0.35 day 72.45
0114 Beldar 190.00 day 0.35 day 66.50
TOTAL 830.06
Add 5 % for water, electricity, sundries and other 35.51
overhead charges on all except (A) i.e. on (830.06 -
119.91) = 710.15
TOTAL 865.57
Add 10 % for contractor's profit on all except (A) 74.57
i.e. on (865.57 - 119.91) = 745.66
Cost for 20.2 metres 940.14
Cost of 1.00 metre 46.54
Say 46.50
17.29 Renewing bottom rail and/or top runner of collapsible gate including making good all damages and applying priming
coat of zinc chromate yellow primer of approved brand and manufacturer.
Code Description Rate Unit Qty Total
Detail of cost for gate of size 1.52x2.4 m (weight
11.55 kg)
MATERIALS
M.S. Tee 40x40x6 mm
Top rail = 1.725 m
Bottom rail = 1.570 m
Total = 3.295 m say 3.30 m @ 3.5 kg/m = 11.55 kg
3.1.0.3 Cement concrete 1:3:6 (stone aggregate 20mm) 2970.36 cum 0.038 cum 112.87
(Rate as per Item No 3.1.3)
5.6 Cement Mortar C.M. 1:6 (1 cement : 6 fine sand) 1952.27 cum 0.01 cum 19.52
(Rate as per item No 5.6)
3.1.0.4 Cement concrete 1:2:4 (stone aggregate 20mm) 3551.90 cum 0.0077 cum 27.35
(Rate as per Item No 3.1.4)
Priming coat on Tees 0.16x3.3 = 0.53 sqm
LABOUR
0104 Mason 2nd class 197.00 day 0.05 day 9.85
0109 Blacksmith 1st class 207.00 day 0.07 day 14.49
0114 Beldar 190.00 day 1 day 190.00
TOTAL 966.88
TOTAL 1008.21
Add 10 % for contractor's profit on all except (A) 86.80
i.e. on (1008.21 - 140.22) = 867.99
Materials to be dismentled
Weight of 10 nos wheels
10x[3.14x{(4/2)x(4/2)}x4]x7.850/1000 = 3.94 kg
TOTAL 1003.73
Add 10 % for contractor's profit on all except (A) 99.46
i.e. on (1003.73 - 9.15) = 994.58
Cost for 10 nos wheels 1103.19
Cost for 1 nos wheels 110.31
TOTAL 1629.76
Add 10 % for contractor's profit on all except (A) 162.06
i.e. on (1629.76 - 9.15) = 1620.61
Cost for 10 nos wheels 1791.82
Cost for 1 nos wheels 179.18
Say 179.00
17.31 Rubbing and polishing old flooring to the complete satisfaction of Engineer-in-Charge.
17.31.1 Marble chips flooring
Code Description Rate Unit Qty Total
TOTAL 10936.26
Add 10 % for contractor's profit on all except (A) 998.37
i.e. on (10936.26 - 952.59) = 9983.67
1685 100 mm S.C.I. trap with vent heel 315.00 each 1 each 315.00
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.009 cum 30.21
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 1.25 day 258.75
0102 Mason 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 2128.71
Add 5 % for water, electricity, sundries and other 106.44
overhead charges
TOTAL 2235.15
Add 10 % for contractor's profit 223.52
Cost for 1 pan 2458.67
Say 2459.00
18.1 Providing and fixing water closet squatting pan (Indian type W.C. pan ), 100mm sand cast Iron P or S trap, 10 litre
low level P.V.C. flushing cistern (same colour) conforming to IS : 7231, with flush bend and other fittings and fixtures
complete including cutting and making good the walls and floors wherever required :
1685 100 mm S.C.I. trap with vent heel 315.00 each 1 each 315.00
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.009 cum 30.21
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 1.25 day 258.75
0102 Mason 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 2522.46
Add 5 % for water, electricity, sundries and other 126.12
overhead charges
TOTAL 2648.58
1685 100 mm S.C.I. trap with vent heel 315.00 each 1 each 315.00
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.009 cum 30.21
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 1.25 day 258.75
0102 Mason 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 2509.96
Add 5 % for water, electricity, sundries and other 125.50
overhead charges
TOTAL 2635.46
Add 10 % for contractor's profit 263.55
Cost for 1 pan 2899.01
Say 2899.00
18.1 Providing and fixing water closet squatting pan (Indian type W.C. pan ), 100mm sand cast Iron P or S trap, 10 litre
low level P.V.C. flushing cistern (same colour) conforming to IS : 7231, with flush bend and other fittings and fixtures
complete including cutting and making good the walls and floors wherever required :
1685 100 mm S.C.I. trap with vent heel 315.00 each 1 each 315.00
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.009 cum 30.21
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 1.25 day 258.75
0102 Mason 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 3069.46
18.3.1 250x130x30 mm
Code Description Rate Unit Qty Total
Details of cost for one pair
MATERIALS
2177 Vitreous china white Foot rests sixze 250x130x30 200.00 pair 1 pair 200.00
mm
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.003 cum 10.07
(Rate as per item No 5.8)
LABOUR
0102 Mason 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.06 day 11.40
TOTAL 233.89
18.3.2 250x125x25 mm
Code Description Rate Unit Qty Total
Details of cost for one pair
MATERIALS
2178 Vitreous china white Foot rests size 250x125x25 190.00 pair 1 pair 190.00
mm
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.003 cum 10.07
(Rate as per item No 5.8)
LABOUR
0102 Mason 1st class 207.00 day 0.06 day 12.42
0114 Beldar 190.00 day 0.06 day 11.40
TOTAL 223.89
Add 5 % for water, electricity, sundries and other 11.19
overhead charges
TOTAL 235.08
Add 10 % for contractor's profit 23.51
Cost for 1 pair 258.59
Say 259.00
18.4 Providing and fixing vitreous china water closet (European type W.C. pan) with white ISI marked plastic seat and lid,
10 litre low level white P.V.C. flushing cistern (same colour), conforming to IS : 7231, with all fittings and fixtures
complete including cutting and making good the walls and floors wherever required :
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.008 cum 26.85
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 1.25 day 258.75
0102 Mason 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 2495.35
Add 5 % for water, electricity, sundries and other 124.77
overhead charges
TOTAL 2620.12
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.008 cum 26.85
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 1.25 day 258.75
0102 Mason 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 3109.60
Add 5 % for water, electricity, sundries and other 155.48
overhead charges
TOTAL 3265.08
Add 10 % for contractor's profit 326.51
Cost for 1 pan 3591.59
Say 3592.00
18.4 Providing and fixing vitreous china water closet (European type W.C. pan) with white ISI marked plastic seat and lid,
10 litre low level white P.V.C. flushing cistern (same colour), conforming to IS : 7231, with all fittings and fixtures
complete including cutting and making good the walls and floors wherever required :
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.008 cum 26.85
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 1.25 day 258.75
0102 Mason 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 1 day 190.00
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.008 cum 26.85
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 1.25 day 258.75
0102 Mason 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 5166.10
Add 5 % for water, electricity, sundries and other 258.31
overhead charges
TOTAL 5424.41
Add 10 % for contractor's profit 542.44
Cost for 1 pan 5966.85
Say 5967.00
18.5 Providing and fixing vitreous china dual purpose closet suitable for use as squatting pan or European type water
closet (Anglo Indian W.C pan) with ISI marked white plastic seat and lid, 10 litre PVC low level flushing cistern with
fitting and brackets, 40mm flush bend, mosquito proof coupling complete, including painting of brackets, cutting
and making good the walls and floors wherever required :
18.5.1 White
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
2175 White plastic seat (solid) with lid C.P.brass hinges 525.00 each 1 each 525.00
and rubber buffers
2159 Vitreous china White dual purpose closet (Anglo 2066.25 each 1 each 2066.25
Indian W.C.) suitable for use as sequatting pan or
European type water closet as per manufacturer's
specifications
2173 P.V.C. Flushing Cistern 10 lts capacity (low level ) 581.25 each 1 each 581.25
(White) ( with fittings, accessories and flush pipe)
0950 Wedge expansion hold fastner 1/4" or 6 mm 5.65 each 4 each 22.60
18.5.2 Coloured
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
2175 White plastic seat (solid) with lid C.P.brass hinges 525.00 each 1 each 525.00
and rubber buffers
2160 Vitreous china Colour dual purpose closet (Anglo 3202.50 each 1 each 3202.50
Indian W.C.) suitable for use as sequatting pan or
European type water closet as per manufacturer's
specifications
2173 P.V.C. Flushing Cistern 10 lts capacity (low level ) 581.25 each 1 each 581.25
(White) ( with fittings, accessories and flush pipe)
3856 Mosquito proof coupling of approved design 27.60 each 1 each 27.60
0950 Wedge expansion hold fastner 1/4" or 6 mm 5.65 each 4 each 22.60
LABOUR
0107 Fitter 1st class 207.00 day 0.125 day 25.88
0114 Beldar 190.00 day 0.125 day 23.75
TOTAL 630.88
Add 5 % for water, electricity, sundries and other 31.54
overhead charges
TOTAL 662.42
Add 10 % for contractor's profit 66.24
Cost for 1 cistern 728.66
LABOUR
0107 Fitter 1st class 207.00 day 0.125 day 25.88
0114 Beldar 190.00 day 0.125 day 23.75
TOTAL 724.63
Add 5 % for water, electricity, sundries and other 36.23
overhead charges
TOTAL 760.86
Add 10 % for contractor's profit 76.09
Cost for 1 cistern 836.95
Say 837.00
18.8 Providing and fixing vitreous china 10 litre (full flush) capacity controlled flush low level cistern with all fittings
complete.
18.8.1 White
Code Description Rate Unit Qty Total
Details of cost for one no
MATERIALS
2171 White Vitreous china 10 lit. (full flush) capacity 956.25 each 1 each 956.25
controlled low level flushing cistern with all fittings
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 1154.75
Add 5 % for water, electricity, sundries and other 57.74
overhead charges
TOTAL 1212.49
Add 10 % for contractor's profit 121.25
Cost for 1 cistern 1333.74
Say 1334.00
18.8 Providing and fixing vitreous china 10 litre (full flush) capacity controlled flush low level cistern with all fittings
complete.
18.8.2 Coloured
Code Description Rate Unit Qty Total
Details of cost for one no
MATERIALS
2172 Coloured Vitreous china 10 lit. (full flush) capacity 1482.00 each 1 each 1482.00
controlled low level flushing cistern with all fittings
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
18.12.1 White
Code Description Rate Unit Qty Total
Details of cost for one pan
MATERIALS
2161 Vitreous china white W.C. water closet (Pedestal 3843.75 each 1 each 3843.75
composit type) including sheet cover complete
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.008 cum 26.85
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 1.25 day 258.75
0102 Mason 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 4422.85
Add 5 % for water, electricity, sundries and other 221.14
overhead charges
TOTAL 4643.99
Add 10 % for contractor's profit 464.40
Cost for 1 pan 5108.39
Say 5108.00
18.12 Providing and fixing vitreous china pedestal type water closet (European type) with inbuilt 10 litre low level vitreous
china flushing cistern, ISI marked plastic seat and lid (same colour), mosquito proof coupling complete:
18.12.2 Coloured
Code Description Rate Unit Qty Total
Details of cost for one pan
MATERIALS
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.008 cum 26.85
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 1.25 day 258.75
0102 Mason 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 5828.35
Add 5 % for water, electricity, sundries and other 291.42
overhead charges
TOTAL 6119.77
Add 10 % for contractor's profit 611.98
Cost for 1 pan 6731.75
Say 6732.00
18.13 Providing and fixing white vitreous china urinal basin with waste fitting as per IS : 2556, and other couplings in C.P.
brass complete:
18.13.1 Flat back half stall urinal of size 460x380x250mm
Code Description Rate Unit Qty Total
Details of cost for one urinal
MATERIALS
2125 White vitreous china clay half stall urinal flat back 600.00 each 1 each 600.00
460x330x250 mm
2212 Flush pipe with union spreaders and clamps all in 315.00 each 1 each 315.00
C.P. brass for single stall
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.008 cum 26.85
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 0.75 day 155.25
0102 Mason 1st class 207.00 day 0.75 day 155.25
0114 Beldar 190.00 day 1.5 day 285.00
TOTAL 1537.35
Add 5 % for water, electricity, sundries and other 76.87
overhead charges
TOTAL 1614.22
Add 10 % for contractor's profit 161.42
Cost for 1 urinal 1775.64
Say 1776.00
18.13 Providing and fixing white vitreous china urinal basin with waste fitting as per IS : 2556, and other couplings in C.P.
brass complete:
18.13.2 Flat back type urinal of size 460x380x250mm
Code Description Rate Unit Qty Total
Details of cost for one urinal
MATERIALS
2126 Vitreous china white lipped front urinal of size 450.00 each 1 each 450.00
460x330x250 mm
2211 G.I. flush pipe and C.P. brass spreader including C.P. 450.00 each 1 each 450.00
connecting pipe Single lipped urinal
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.008 cum 26.85
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0102 Mason 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 1436.35
Add 5 % for water, electricity, sundries and other 71.82
overhead charges
TOTAL 1508.17
Add 10 % for contractor's profit 150.82
Cost for 1 urinal 1658.99
Say 1659.00
18.14 Providing and fixing white vitreous china urinal basin as per IS : 2556 complete:
18.14.1 Flat back half stall urinal of size 460x380x250mm
Code Description Rate Unit Qty Total
Details of cost for one urinal
MATERIALS
2125 White vitreous china clay half stall urinal flat back 600.00 each 1 each 600.00
460x330x250 mm
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.008 cum 26.85
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0102 Mason 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 1 day 190.00
LABOUR
0107 Fitter 1st class 207.00 day 0.33 day 68.31
0102 Mason 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.67 day 127.30
TOTAL 1239.36
Add 5 % for water, electricity, sundries and other 61.42
overhead charges on all except (A) i.e. on (1239.36
- 10.96) = 1228.40
TOTAL 1300.78
Add 10 % for contractor's profit on all except (A) 128.98
i.e. on (1300.78 - 10.96) = 1289.82
LABOUR
0107 Fitter 1st class 207.00 day 0.33 day 68.31
0102 Mason 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.67 day 127.30
TOTAL 1220.61
Add 5 % for water, electricity, sundries and other 60.48
overhead charges on all except (A) i.e. on (1220.61
- 10.96) = 1209.65
TOTAL 1281.09
Add 10 % for contractor's profit on all except (A) 127.01
i.e. on (1281.09 - 10.96) = 1270.13
LABOUR
0107 Fitter 1st class 207.00 day 0.3 day 62.10
0102 Mason 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.63 day 119.70
TOTAL 1042.60
Add 5 % for water, electricity, sundries and other 51.58
overhead charges on all except (A) i.e. on (1042.60
- 10.96) = 1031.64
TOTAL 1094.18
Add 10 % for contractor's profit on all except (A) 108.32
i.e. on (1094.18 - 10.96) = 1083.22
LABOUR
0107 Fitter 1st class 207.00 day 0.3 day 62.10
TOTAL 1067.83
Add 10 % for contractor's profit on all except (A) 105.69
i.e. on (1067.83 - 10.96) = 1056.87
LABOUR
0107 Fitter 1st class 207.00 day 0.33 day 68.31
0102 Mason 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.67 day 127.30
TOTAL 1391.31
Add 5 % for water, electricity, sundries and other 69.02
overhead charges on all except (A) i.e. on (1391.31
- 10.96) = 1380.35
TOTAL 1460.33
Add 10 % for contractor's profit on all except (A) 144.94
i.e. on (1460.33 - 10.96) = 1449.37
LABOUR
0107 Fitter 1st class 207.00 day 0.33 day 68.31
0102 Mason 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.67 day 127.30
TOTAL 2241.31
Add 5 % for water, electricity, sundries and other 111.52
overhead charges on all except (A) i.e. on (2241.31
- 10.96) = 2230.35
TOTAL 2352.83
Add 10 % for contractor's profit on all except (A) 234.19
i.e. on (2352.83 - 10.96) = 2341.87
LABOUR
0107 Fitter 1st class 207.00 day 0.33 day 68.31
0102 Mason 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.67 day 127.30
TOTAL 1641.36
Add 5 % for water, electricity, sundries and other 81.52
overhead charges on all except (A) i.e. on (1641.36
- 10.96) = 1630.40
TOTAL 1722.88
Add 10 % for contractor's profit on all except (A) 171.19
i.e. on (1722.88 - 10.96) = 1711.92
LABOUR
0107 Fitter 1st class 207.00 day 0.33 day 68.31
0102 Mason 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.67 day 127.30
TOTAL 1612.86
Add 5 % for water, electricity, sundries and other 80.10
overhead charges on all except (A) i.e. on (1612.86
- 10.96) = 1601.90
TOTAL 1692.96
Add 10 % for contractor's profit on all except (A) 168.20
i.e. on (1692.96 - 10.96) = 1682.00
LABOUR
TOTAL 1410.76
Add 10 % for contractor's profit on all except (A) 139.98
i.e. on (1410.76 - 10.96) = 1399.80
LABOUR
0107 Fitter 1st class 207.00 day 0.33 day 68.31
0102 Mason 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.67 day 127.30
TOTAL 1328.31
Add 5 % for water, electricity, sundries and other 65.87
overhead charges on all except (A) i.e. on (1328.31
- 10.96) = 1317.35
TOTAL 1394.18
Add 10 % for contractor's profit on all except (A) 138.32
i.e. on (1394.18 - 10.96) = 1383.22
LABOUR
0107 Fitter 1st class 207.00 day 0.33 day 68.31
0102 Mason 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.67 day 127.30
TOTAL 1886.31
Add 5 % for water, electricity, sundries and other 93.77
overhead charges on all except (A) i.e. on (1886.31
- 10.96) = 1875.35
TOTAL 1980.08
Add 10 % for contractor's profit on all except (A) 196.91
i.e. on (1980.08 - 10.96) = 1969.12
5.18 Cement Mortar White C.M. 1:5 (1 white cement : 5 5841.07 cum 0.01 cum 58.41
marble dust) (Rate as per item No 5.18)
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 978.26
Add 5 % for water, electricity, sundries and other 48.91
overhead charges
TOTAL 1027.17
Add 10 % for contractor's profit 102.72
Cost for one no 1129.89
Say 1130.00
18.19 Providing and fixing vitreous china pedestal for wash basin completely recessed at the back for the reception of
pipes and fittings.
18.19.2 Coloured
Code Description Rate Unit Qty Total
5.18 Cement Mortar White C.M. 1:5 (1 white cement : 5 5841.07 cum 0.01 cum 58.41
marble dust) (Rate as per item No 5.18)
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 1473.26
Add 5 % for water, electricity, sundries and other 73.66
overhead charges
TOTAL 1546.92
Add 10 % for contractor's profit 154.69
Cost for one no 1701.61
Say 1702.00
18.20 Providing and fixing stainless steel AISI-304(18/8) wash basin with C.I. brackets, 32 mm C.P. brass waste of standard
pattern, including painting of brackets, cutting and making good the walls wherever required :
LABOUR
0107 Fitter 1st class 207.00 day 0.3 day 62.10
0102 Mason 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.63 day 119.70
TOTAL 3357.50
Add 5 % for water, electricity, sundries and other 167.33
overhead charges on all except (A) i.e. on (3357.50
- 10.96) = 3346.54
TOTAL 3524.83
Add 10 % for contractor's profit on all except (A) 351.39
i.e. on (3524.83 - 10.96) = 3513.87
LABOUR
0107 Fitter 1st class 207.00 day 0.3 day 62.10
0102 Mason 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.63 day 119.70
TOTAL 3546.50
Add 5 % for water, electricity, sundries and other 176.78
overhead charges on all except (A) i.e. on (3546.50
- 10.96) = 3535.54
TOTAL 3723.28
Add 10 % for contractor's profit on all except (A) 371.23
i.e. on (3723.28 - 10.96) = 3712.32
2401 C.I. bracket for wash basin and sinks 53.00 pair 2 pair 106.00
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.008 cum 26.85
(Rate as per item No 5.8)
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.17 sqm 2.94
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 0.17 sqm 8.02
LABOUR
0107 Fitter 1st class 207.00 day 0.22 day 45.54
0102 Mason 1st class 207.00 day 0.6 day 124.20
0114 Beldar 190.00 day 0.82 day 155.80
TOTAL 10189.35
TOTAL 10698.27
Add 10 % for contractor's profit on all except (A) 1068.73
i.e. on (10698.27 - 10.96) = 10687.31
2401 C.I. bracket for wash basin and sinks 53.00 pair 2 pair 106.00
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.008 cum 26.85
(Rate as per item No 5.8)
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.17 sqm 2.94
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 0.17 sqm 8.02
LABOUR
0107 Fitter 1st class 207.00 day 0.22 day 45.54
0102 Mason 1st class 207.00 day 0.6 day 124.20
0114 Beldar 190.00 day 0.82 day 155.80
TOTAL 7394.85
Add 5 % for water, electricity, sundries and other 369.19
overhead charges on all except (A) i.e. on (7394.85
- 10.96) = 7383.89
TOTAL 7764.04
Add 10 % for contractor's profit on all except (A) 775.31
i.e. on (7764.04 - 10.96) = 7753.08
2401 C.I. bracket for wash basin and sinks 53.00 pair 2 pair 106.00
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.008 cum 26.85
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 0.22 day 45.54
0102 Mason 1st class 207.00 day 0.6 day 124.20
0114 Beldar 190.00 day 0.82 day 155.80
TOTAL 7057.35
Add 5 % for water, electricity, sundries and other 352.32
overhead charges on all except (A) i.e. on (7057.35
- 10.96) = 7046.39
TOTAL 7409.67
Add 10 % for contractor's profit on all except (A) 739.87
i.e. on (7409.67 - 10.96) = 7398.71
2401 C.I. bracket for wash basin and sinks 53.00 pair 2 pair 106.00
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.008 cum 26.85
(Rate as per item No 5.8)
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.17 sqm 2.94
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 0.17 sqm 8.02
LABOUR
0107 Fitter 1st class 207.00 day 0.22 day 45.54
0102 Mason 1st class 207.00 day 0.6 day 124.20
0114 Beldar 190.00 day 0.82 day 155.80
TOTAL 6193.35
Add 5 % for water, electricity, sundries and other 309.12
overhead charges on all except (A) i.e. on (6193.35
- 10.96) = 6182.39
TOTAL 6502.47
Add 10 % for contractor's profit on all except (A) 649.15
i.e. on (6502.47 - 10.96) = 6491.51
2401 C.I. bracket for wash basin and sinks 53.00 pair 1 pair 53.00
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.008 cum 26.85
(Rate as per item No 5.8)
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.17 sqm 2.94
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 0.17 sqm 8.02
LABOUR
0107 Fitter 1st class 207.00 day 0.22 day 45.54
0102 Mason 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.56 day 106.40
TOTAL 5454.56
Add 5 % for water, electricity, sundries and other 272.18
overhead charges on all except (A) i.e. on (5454.56
- 10.96) = 5443.60
TOTAL 5726.74
Add 10 % for contractor's profit on all except (A) 571.58
i.e. on (5726.74 - 10.96) = 5715.78
2401 C.I. bracket for wash basin and sinks 53.00 pair 1 pair 53.00
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.008 cum 26.85
(Rate as per item No 5.8)
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.17 sqm 2.94
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 0.17 sqm 8.02
LABOUR
0107 Fitter 1st class 207.00 day 0.22 day 45.54
0102 Mason 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.56 day 106.40
TOTAL 5378.06
Add 5 % for water, electricity, sundries and other 268.36
overhead charges on all except (A) i.e. on (5378.06
- 10.96) = 5367.10
2401 C.I. bracket for wash basin and sinks 53.00 pair 1 pair 53.00
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.008 cum 26.85
(Rate as per item No 5.8)
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.17 sqm 2.94
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 0.17 sqm 8.02
LABOUR
0107 Fitter 1st class 207.00 day 0.22 day 45.54
0102 Mason 1st class 207.00 day 0.33 day 68.31
0114 Beldar 190.00 day 0.56 day 106.40
TOTAL 3807.56
Add 5 % for water, electricity, sundries and other 189.83
overhead charges on all except (A) i.e. on (3807.56
- 10.96) = 3796.60
TOTAL 3997.39
Add 10 % for contractor's profit on all except (A) 398.64
i.e. on (3997.39 - 10.96) = 3986.43
18.25.1 32 mm dia
Code Description Rate Unit Qty Total
Details of cost for one no
MATERIALS
2063 Flexible (coil shaped) PVC waste pipe for sink and 51.55 each 1 each 51.55
wash basin 32 mm dia with length not less than
700 mm i/c PVC waste fittings
LABOUR
0107 Fitter 1st class 207.00 day 0.02 day 4.14
0114 Beldar 190.00 day 0.02 day 3.80
TOTAL 59.49
Add 5 % for water, electricity, sundries and other 2.97
overhead charges
TOTAL 62.46
Add 10 % for contractor's profit 6.25
Cost for 1 no 68.71
Say 68.50
18.25.2 40 mm dia
Code Description Rate Unit Qty Total
Details of cost for one no
MATERIALS
2064 Flexible (coil shaped) PVC waste pipe for sink and 68.70 each 1 each 68.70
wash basin 40 mm dia with length not less than
700 mm i/c PVC waste fittings
LABOUR
0107 Fitter 1st class 207.00 day 0.02 day 4.14
0114 Beldar 190.00 day 0.02 day 3.80
TOTAL 76.64
Add 5 % for water, electricity, sundries and other 3.83
overhead charges
TOTAL 80.47
Add 10 % for contractor's profit 8.05
Cost for 1 no 88.52
Say 88.50
18.26 Providing and fixing PVC waste coupling in wash basin/ sink.
18.26.1 25 mm
Code Description Rate Unit Qty Total
Details of cost for one no
MATERIALS
2055 PVC waste coupling 25 mm dia 35.00 each 1 each 35.00
LABOUR
0107 Fitter 1st class 207.00 day 0.02 day 4.14
0114 Beldar 190.00 day 0.02 day 3.80
TOTAL 42.94
Add 5 % for water, electricity, sundries and other 2.15
overhead charges
TOTAL 45.09
Add 10 % for contractor's profit 4.51
Cost for 1 no 49.60
Say 49.50
18.26 Providing and fixing PVC waste coupling in wash basin/ sink.
18.26.2 40 mm
Code Description Rate Unit Qty Total
Details of cost for one no
MATERIALS
2056 PVC waste coupling 40 mm dia 45.00 each 1 each 45.00
LABOUR
0107 Fitter 1st class 207.00 day 0.02 day 4.14
0114 Beldar 190.00 day 0.02 day 3.80
TOTAL 52.94
Add 5 % for water, electricity, sundries and other 2.65
overhead charges
TOTAL 55.59
LABOUR
0107 Fitter 1st class 207.00 day 0.02 day 4.14
0114 Beldar 190.00 day 0.02 day 3.80
TOTAL 35.54
Add 5 % for water, electricity, sundries and other 1.78
overhead charges
TOTAL 518.71
Add 5 % for water, electricity, sundries and other 25.94
overhead charges
TOTAL 544.65
Add 10 % for contractor's profit 54.47
Cost of one no. 599.12
Say 599.00
18.30 Providing and fixing mirror of superior glass (of approved quality) and of required shape and size with plastic
moulded frame of approved make and shade with 6 mm thick hard board backing :
18.30.1 5mm thick mirror
Code Description Rate Unit Qty Total
Details of cost for 0.675 sqm
MATERIALS
2357 5mm thick rectangular shape 1500x450 mm Mirror 885.00 each 1 each 885.00
with Plastic moulded frame
Hard board 1.50x0.45 = 0.675 sqm
Add wastage @ 10% = 0.0675 sqm
2865 Hard board 6 mm thick 157.05 sqm 0.74 sqm 116.22
0944 Rawl plug 10x50 mm 7.90 each 6 each 47.40
0764 Nickle plated Steel screws 25 mm 0.35 each 6 each 2.10
LABOUR
0106 Carpenter 2nd class 197.00 day 0.33 day 65.01
0114 Beldar 190.00 day 0.33 day 62.70
TOTAL 1178.43
Add 5 % for water, electricity, sundries and other 58.92
overhead charges
TOTAL 1237.35
Add 10 % for contractor's profit 123.74
MATERIALS
1301 S.C.I. soil, waste and vent single socketed pipe 1.80 917.15 each 10.5 each 9630.08
metres long:75mm dia as per IS: 1729
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.0011 cum 0.94
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.005 day 1.00
TOTAL 369.83
Add 5 % for water, electricity, sundries and other 18.49
overhead charges
TOTAL 388.32
0304 Stone Aggregate (Single size) : 10 mm nominal size 850.00 cum 0.0011 cum 0.94
0009 Hire charges of 1 BHP water supply pump 200.00 day 0.005 day 1.00
TOTAL 359.83
Add 5 % for water, electricity, sundries and other 17.99
overhead charges
TOTAL 377.82
Add 10 % for contractor's profit 37.78
Cost of 5.00 bat clamps 415.60
Cost of 1.00 bat clamp 83.12
Say 83.00
18.34 Providing and fixing sand cast iron S&S bend with access door of required degree as per IS : 1729, insertion rubber
washer 3 mm thick, bolts and nuts:
18.34.1 100 mm dia
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1309 S.C.I. bend with access door 100mm dia as per IS: 327.60 each 1 each 327.60
1729
1722 Rubber insertions for 100 mm dia pipe joints 14.50 each 1 each 14.50
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 361.95
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 333.45
Add 5 % for water, electricity, sundries and other 16.67
overhead charges
TOTAL 350.12
Add 10 % for contractor's profit 35.01
Cost for 1 no. 385.13
Say 385.00
18.36 Providing and fixing sand cast iron S&S heel rest sanitary bend as per IS : 1729:
18.36.2 75 mm dia
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1330 S.C.I. heel rest bend 75mm dia as per IS: 1729 235.20 each 1 each 235.20
LABOUR
0107 Fitter 1st class 207.00 day 0.04 day 8.28
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 251.08
Add 5 % for water, electricity, sundries and other 12.55
overhead charges
TOTAL 263.63
Add 10 % for contractor's profit 26.36
Cost for 1 no. 289.99
Say 290.00
18.37 Providing and fixing sand cast iron S&S double equal junction with access door of required degree as per IS : 1729,
insertion rubber washer 3 mm thick, bolts and nuts:
18.37.1 100x100x100x100mm
Code Description Rate Unit Qty Total
1722 Rubber insertions for 100 mm dia pipe joints 14.50 each 1 each 14.50
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 623.05
Add 5 % for water, electricity, sundries and other 31.15
overhead charges
TOTAL 654.20
Add 10 % for contractor's profit 65.42
Cost for 1 no. 719.62
Say 720.00
18.37 Providing and fixing sand cast iron S&S double equal junction with access door of required degree as per IS : 1729,
insertion rubber washer 3 mm thick, bolts and nuts:
18.37.2 75x75x75x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1318 S.C.I. double equal junctions75x75x75x75 mm dia 401.10 each 1 each 401.10
with access door as per IS: 1729
1721 Rubber insertions for 80 mm dia pipe joints 11.00 each 1 each 11.00
LABOUR
0107 Fitter 1st class 207.00 day 0.04 day 8.28
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 427.98
Add 5 % for water, electricity, sundries and other 21.40
overhead charges
TOTAL 449.38
Add 10 % for contractor's profit 44.94
Cost for 1 no. 494.32
Say 494.00
18.38 Providing and fixing sand cast iron S&S double equal plain junction of required degree as per IS : 1729:
18.38.1 100x100x100x100 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1317 S.C.I. plain double equal 550.90 each 1 each 550.90
junctions100x100x100x100 mm dia as per IS: 1729
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 570.75
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 455.05
Add 5 % for water, electricity, sundries and other 22.75
overhead charges
TOTAL 477.80
Add 10 % for contractor's profit 47.78
Cost for 1 no. 525.58
Say 526.00
18.39 Providing and fixing sand cast iron S&S single equal junction with access door of required degree as per IS : 1729,
insertion rubber washer 3 mm thick, bolts and nuts:
18.39.2 75x75x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 401.35
Add 5 % for water, electricity, sundries and other 20.07
overhead charges
TOTAL 421.42
Add 10 % for contractor's profit 42.14
Cost for 1 no. 463.56
Say 464.00
18.40 Providing and fixing sand cast iron S&S single equal plain junction of required degree as per IS : 1729 :
18.40.2 75x75x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1311 S.C.I. plain single equal junctions75x75x75 mm dia 262.50 each 1 each 262.50
as per IS: 1729
LABOUR
0107 Fitter 1st class 207.00 day 0.04 day 8.28
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 278.38
Add 5 % for water, electricity, sundries and other 13.92
overhead charges
TOTAL 292.30
Add 10 % for contractor's profit 29.23
Cost for 1 no. 321.53
Say 322.00
1722 Rubber insertions for 100 mm dia pipe joints 14.50 each 1 each 14.50
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 530.65
Add 5 % for water, electricity, sundries and other 26.53
overhead charges
TOTAL 557.18
Add 10 % for contractor's profit 55.72
Cost for 1 no. 612.90
Say 613.00
18.42 Providing and fixing sand cast iron S&S double unequal junction of required degree as per IS : 1729 :
18.42.1 100x100x75x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1322 S.C.I. S&S plain double unequal junctions : 462.70 each 1 each 462.70
100x100x75x75 mm dia as per IS: 1729
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 482.55
Add 5 % for water, electricity, sundries and other 24.13
overhead charges
TOTAL 506.68
Add 10 % for contractor's profit 50.67
Cost for 1 no. 557.35
Say 557.00
18.43 Providing and fixing sand cast iron S&S single unequal junction with access door of required degree as per IS : 1729,
insertion rubber washer 3 mm thick, bolts and nuts complete:
18.43.1 100x100x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1321 S.C.I. S&S single unequal junctions: 100x100x75 410.20 each 1 each 410.20
mm dia with access door as per IS: 1729
1722 Rubber insertions for 100 mm dia pipe joints 14.50 each 1 each 14.50
LABOUR
18.44.1 100x100x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1320 S.C.I. S&S plain single unequal junctions : 381.50 each 1 each 381.50
100x100x75 mm dia as per IS: 1729
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 401.35
Add 5 % for water, electricity, sundries and other 20.07
overhead charges
TOTAL 421.42
Add 10 % for contractor's profit 42.14
Cost for 1 no. 463.56
Say 464.00
18.45 Providing and fixing sand cast iron S&S double equal plain invert branch of required degree as per IS : 1729:
18.45.1 100x100x100x100 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1327 S.C.I. double equal invert branch of required 540.40 each 1 each 540.40
degree 100x100x100x100 mm dia as per IS: 1729
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 560.25
Add 5 % for water, electricity, sundries and other 28.01
overhead charges
TOTAL 588.26
Add 10 % for contractor's profit 58.83
Cost for 1 no. 647.09
Say 647.00
18.45 Providing and fixing sand cast iron S&S double equal plain invert branch of required degree as per IS : 1729:
18.45.2 75x75x75x75 mm
LABOUR
0107 Fitter 1st class 207.00 day 0.04 day 8.28
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 394.58
Add 5 % for water, electricity, sundries and other 19.73
overhead charges
TOTAL 414.31
Add 10 % for contractor's profit 41.43
Cost for 1 no. 455.74
Say 456.00
18.46 Providing and fixing sand cast iron S&S single equal plain invert branch of required degree as per IS : 1729:
18.46.1 100x100x100 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1325 S.C.I. single equal invert branch of required degree 478.10 each 1 each 478.10
100x100x100 mm dia as per IS: 1729
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 497.95
Add 5 % for water, electricity, sundries and other 24.90
overhead charges
TOTAL 522.85
Add 10 % for contractor's profit 52.29
Cost for 1 no. 575.14
Say 575.00
18.46 Providing and fixing sand cast iron S&S single equal plain invert branch of required degree as per IS : 1729:
18.46.2 75x75x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1324 S.C.I. single equal invert branch of required 364.00 each 1 each 364.00
degree75x75x75 mm dia as per IS: 1729
LABOUR
0107 Fitter 1st class 207.00 day 0.04 day 8.28
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 379.88
Add 5 % for water, electricity, sundries and other 18.99
overhead charges
18.47.1 100x100x75x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1329 S.C.I. double unequal invert branch of required 602.70 each 1 each 602.70
degree 100x100x75x75 mm dia as per IS: 1729
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 622.55
Add 5 % for water, electricity, sundries and other 31.13
overhead charges
TOTAL 653.68
Add 10 % for contractor's profit 65.37
Cost for 1 no. 719.05
Say 719.00
18.48 Providing and fixing sand cast iron S&S single unequal plain invert branch of required degree as per IS : 1729:
18.48.1 100x100x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1328 S.C.I. single unequal invert branch of required 434.00 each 1 each 434.00
degree100x100x75 mm dia as per IS: 1729
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 453.85
Add 5 % for water, electricity, sundries and other 22.69
overhead charges
TOTAL 476.54
Add 10 % for contractor's profit 47.65
Cost for 1 no. 524.19
Say 524.00
18.49 Providing and fixing sand cast iron S&S off set as per IS: 1729.
18.49.1 75 mm dia, 76 mm projected
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1332 S.C.I. S&S, 76 mm offset for 75 mm dia pipe as per 176.40 each 1 each 176.40
IS: 1729
1722 Rubber insertions for 100 mm dia pipe joints 14.50 each 1 each 14.50
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 230.35
Add 5 % for water, electricity, sundries and other 11.52
overhead charges
TOTAL 241.87
Add 10 % for contractor's profit 24.19
Cost for 1 no. 266.06
Say 266.00
18.50 Providing and fixing sand cast iron S&S door piece as per IS: 1729:
18.50.2 75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1338 S.C.I. door pieces 75 mm dia as per IS: 1729 140.00 each 1 each 140.00
1721 Rubber insertions for 80 mm dia pipe joints 11.00 each 1 each 11.00
LABOUR
0107 Fitter 1st class 207.00 day 0.04 day 8.28
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 166.88
Add 5 % for water, electricity, sundries and other 8.34
overhead charges
TOTAL 175.22
Add 10 % for contractor's profit 17.52
Cost for 1 no. 192.74
Say 193.00
18.51 Providing and fixing sand cast iron S&S terminal guard as per IS: 1729:
18.51.1 100 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1343 Slotted cowl (terminal guard ) 100 mm dia as per 224.00 each 1 each 224.00
IS: 1729
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 243.85
18.54.1 100 mm
Code Description Rate Unit Qty Total
Details of cost for one joint
MATERIALS
1698 Pig lead 125.00 kg 0.98 kg 122.50
3606 Spun yarn 40.00 kg 0.11 kg 4.40
3501 Kerosene oil 30.00 litre 0.75 litre 22.50
LABOUR
0107 Fitter 1st class 207.00 day 0.12 day 24.84
0114 Beldar 190.00 day 0.12 day 22.80
TOTAL 197.04
Add 5 % for water, electricity, sundries and other 9.85
overhead charges
TOTAL 206.89
Add 10 % for contractor's profit 20.69
Cost of one joint 227.58
Say 228.00
18.54 Providing lead caulked joints to sand cast iron/ centrifugally cast (spun) iron pipes and fittings of diameter:
18.54.2 75 mm
Code Description Rate Unit Qty Total
Details of cost for one joint
MATERIALS
1698 Pig lead 125.00 kg 0.98 kg 122.50
3606 Spun yarn 40.00 kg 0.11 kg 4.40
3501 Kerosene oil 30.00 litre 0.56 litre 16.80
LABOUR
0107 Fitter 1st class 207.00 day 0.1 day 20.70
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 183.40
Add 5 % for water, electricity, sundries and other 9.17
overhead charges
TOTAL 192.57
Add 10 % for contractor's profit 19.26
Cost of one joint 211.83
Say 212.00
18.55 Providing and fixing M.S. stays and clamps for sand cast iron/ centrifugally cast (spun) iron pipes of diameter :
18.55.1 100 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
2431 Clamps and M.S. stays including bolts and nuts for 33.00 each 1 each 33.00
100 mm pipe
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
18.55.2 75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
2433 Clamps and M.S. stays including bolts and nuts for 29.00 each 1 each 29.00
75 mm pipe
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 48.85
Add 5 % for water, electricity, sundries and other 2.44
overhead charges
TOTAL 51.29
Add 10 % for contractor's profit 5.13
Cost for 1 no 56.42
Say 56.50
18.56 Providing and fixing sand cast iron S&S trap of self cleansing design with screwed down or hinged grating with or
without vent arm as per IS: 1729 complete, including cost of cutting and making good the walls and floors :
MATERIALS
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 378.60
Add 5 % for water, electricity, sundries and other 18.93
overhead charges
TOTAL 397.53
Add 10 % for contractor's profit 39.75
Cost for 1 no. 437.28
Say 437.00
18.58 Providing fixing and push on jointing sand cast iron S&S bend with access door of required degree as per IS: 3989,
insertion rubber washer 3 mm thick, bolts and nuts including EPDM rubber gasket complete:.
18.58.2 75 mm dia
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1404 75 mm sand cast iron bend with access door 268.60 each 1 each 268.60
including cost of bolts and nuts
1721 Rubber insertions for 80 mm dia pipe joints 11.00 each 1 each 11.00
LABOUR
0107 Fitter 1st class 207.00 day 0.04 day 8.28
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 329.25
Add 5 % for water, electricity, sundries and other 16.46
overhead charges
TOTAL 345.71
Add 10 % for contractor's profit 34.57
Cost for 1 no. 380.28
Say 380.00
18.59 Providing fixing and push on jointing sand cast iron S&S plain bend of required degree as per IS: 3989 including
EPDM rubber gasket complete::
18.59.2 75 mm dia
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1406 75 mm sand cast iron plain bend as per IS: 3989 221.00 each 1 each 221.00
LABOUR
0107 Fitter 1st class 207.00 day 0.04 day 8.28
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 236.88
Add 5 % for water, electricity, sundries and other 11.84
overhead charges
TOTAL 248.72
Add 10 % for contractor's profit 24.87
Cost for 1 no. 273.59
Say 274.00
18.60 Providing fixing and push on jointing sand cast iron S&S heel rest sanitary bend as per IS: 3989 including EPDM
rubber gasket complete::
18.60.1 100 mm dia
Code Description Rate Unit Qty Total
Details of cost for one no.
18.61.1 100x100x100x100mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1415 S.C.I. double equal junctions 100x100x100x100 657.90 each 1 each 657.90
mm dia with access door as per IS: 3989
1722 Rubber insertions for 100 mm dia pipe joints 14.50 each 1 each 14.50
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 692.25
Add 5 % for water, electricity, sundries and other 34.61
overhead charges
TOTAL 726.86
18.61.2 75x75x75x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1416 S.C.I. double equal junctions 75x75x75x75 mm dia 498.95 each 1 each 498.95
with access door as per IS: 3989
1721 Rubber insertions for 80 mm dia pipe joints 11.00 each 1 each 11.00
LABOUR
0107 Fitter 1st class 207.00 day 0.04 day 8.28
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 525.83
Add 5 % for water, electricity, sundries and other 26.29
overhead charges
TOTAL 552.12
Add 10 % for contractor's profit 55.21
Cost for 1 no. 607.33
Say 607.00
18.62 Providing fixing and push on jointing sand cast iron S&S double equal plain junction of required degree as per IS:
3989 including EPDM rubber gasket complete:
18.62.1 100x100x100x100 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1413 S.C.I. plain double equal 632.40 each 1 each 632.40
junctions100x100x100x100 mm dia as per IS: 3989
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 652.25
Add 5 % for water, electricity, sundries and other 32.61
overhead charges
TOTAL 684.86
Add 10 % for contractor's profit 68.49
Cost for 1 no. 753.35
Say 753.00
18.62 Providing fixing and push on jointing sand cast iron S&S double equal plain junction of required degree as per IS:
3989 including EPDM rubber gasket complete:
18.62.2 75x75x75x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
18.63.1 100x100x100 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1411 S.C.I. single equal junctions 100x100x100 mm dia 503.20 each 1 each 503.20
with access door as per IS: 3989
1722 Rubber insertions for 100 mm dia pipe joints 14.50 each 1 each 14.50
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 537.55
Add 5 % for water, electricity, sundries and other 26.88
overhead charges
TOTAL 564.43
Add 10 % for contractor's profit 56.44
Cost for 1 no. 620.87
Say 621.00
18.63 Providing fixing and push on jointing sand cast iron S&S single equal junction with access door of required degree as
per IS: 3989, insertion rubber washer 3 mm thick, bolts and nuts including EPDM rubber gasket complete:
18.63.2 75x75x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1412 S.C.I. single equal junctions 75x75x75 mm dia with 334.90 each 1 each 334.90
access door as per IS: 3989
1721 Rubber insertions for 80 mm dia pipe joints 11.00 each 1 each 11.00
LABOUR
0107 Fitter 1st class 207.00 day 0.04 day 8.28
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 361.78
Add 5 % for water, electricity, sundries and other 18.09
overhead charges
TOTAL 379.87
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 474.60
Add 5 % for water, electricity, sundries and other 23.73
overhead charges
TOTAL 498.33
Add 10 % for contractor's profit 49.83
Cost for 1 no. 548.16
Say 548.00
18.64 Providing fixing and push on jointing sand cast iron S&S single equal plain junction of required degree as per IS:
3989 including EPDM rubber gasket complete::
18.64.2 75x75x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1410 S.C.I. plain single equal junctions 75x75x75 mm dia 291.55 each 1 each 291.55
as per IS: 3989
LABOUR
0107 Fitter 1st class 207.00 day 0.04 day 8.28
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 307.43
Add 5 % for water, electricity, sundries and other 15.37
overhead charges
TOTAL 322.80
Add 10 % for contractor's profit 32.28
Cost for 1 no. 355.08
Say 355.00
18.65 Providing fixing and push on jointing sand cast iron S&S double unequal junction with access door of required
degree as per IS: 3989, insertion rubber washer 3 mm thick, bolts and nuts including EPDM rubber gasket complete:
18.65.1 100x100x75x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1420 Sand cast iron S&S double unequal junctions: 811.75 each 1 each 811.75
100x100x75x75 mm dia with access door as per IS:
3989
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 846.10
Add 5 % for water, electricity, sundries and other 42.31
overhead charges
TOTAL 888.41
Add 10 % for contractor's profit 88.84
Cost for 1 no. 977.25
Say 977.00
18.66 Providing fixing and push on jointing sand cast iron S&S double unequal junction of required degree as per IS: 3989
including EPDM rubber gasket complete:
18.66.1 100x100x75x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1419 Sand cast iron S&S plain double unequal junctions : 731.85 each 1 each 731.85
100x100x75x75 mm dia as per IS: 3989
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 751.70
Add 5 % for water, electricity, sundries and other 37.59
overhead charges
TOTAL 789.29
Add 10 % for contractor's profit 78.93
Cost for 1 no. 868.22
Say 868.00
18.67 Providing fixing and push on jointing sand cast iron S&S single unequal junction with access door of required degree
as per IS: 3989, insertion rubber washer 3 mm thick, bolts and nuts including EPDM rubber gasket complete:
18.67.1 100x100x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1418 Sand cast iron S&S single unequal junctions: 623.90 each 1 each 623.90
100x100x75 mm dia with access door as per IS:
3989
1722 Rubber insertions for 100 mm dia pipe joints 14.50 each 1 each 14.50
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 658.25
Add 5 % for water, electricity, sundries and other 32.91
overhead charges
TOTAL 691.16
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 576.60
Add 5 % for water, electricity, sundries and other 28.83
overhead charges
TOTAL 605.43
Add 10 % for contractor's profit 60.54
Cost for 1 no. 665.97
Say 666.00
18.69 Providing fixing and push on jointing sand cast iron S&S double equal plain invert branch of required degree as per
IS: 3989 including EPDM rubber gasket complete:
18.69.1 100x100x100x100 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1423 S.C.I. double equal invert branch of required 639.20 each 1 each 639.20
degree 100x100x100x100 mm dia as per IS: 3989
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 659.05
Add 5 % for water, electricity, sundries and other 32.95
overhead charges
TOTAL 692.00
Add 10 % for contractor's profit 69.20
Cost for 1 no. 761.20
Say 761.00
18.69 Providing fixing and push on jointing sand cast iron S&S double equal plain invert branch of required degree as per
IS: 3989 including EPDM rubber gasket complete:
18.69.2 75x75x75x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1424 S.C.I. double equal invert branch of required 513.40 each 1 each 513.40
degree 75x75x75x75 mm dia as per IS: 3989
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 609.75
Add 5 % for water, electricity, sundries and other 30.49
overhead charges
TOTAL 640.24
Add 10 % for contractor's profit 64.02
Cost for 1 no. 704.26
Say 704.00
18.70 Providing fixing and push on jointing sand cast iron S&S single equal plain invert branch of required degree as per IS:
3989 including EPDM rubber gasket complete:
18.70.2 75x75x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1422 S.C.I. single equal invert branch of required degree 438.60 each 1 each 438.60
75x75x75 mm dia as per IS: 3989
LABOUR
0107 Fitter 1st class 207.00 day 0.04 day 8.28
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 454.48
Add 5 % for water, electricity, sundries and other 22.72
overhead charges
TOTAL 477.20
Add 10 % for contractor's profit 47.72
Cost for 1 no. 524.92
Say 525.00
18.71 Providing fixing and push on jointing sand cast iron S&S double unequal plain invert branch of required degree as
per IS: 3989 including EPDM rubber gasket complete:
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 899.60
Add 5 % for water, electricity, sundries and other 44.98
overhead charges
TOTAL 944.58
Add 10 % for contractor's profit 94.46
Cost for 1 no. 1039.04
Say 1039.00
18.72 Providing fixing and push on jointing sand cast iron S&S single unequal plain invert branch of required degree as per
IS: 3989 including EPDM rubber gasket complete:
18.72.1 100x100x75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1425 S.C.I. single unequal invert branch of required 636.65 each 1 each 636.65
degree 100x100x75 mm dia as per IS: 3989
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 656.50
Add 5 % for water, electricity, sundries and other 32.83
overhead charges
TOTAL 689.33
Add 10 % for contractor's profit 68.93
Cost for 1 no. 758.26
Say 758.00
18.73 Providing fixing and push on jointing sand cast iron S&S off sets as per IS: 3989 including EPDM rubber gasket
complete:
18.73.1 75 mm dia, 76 mm projected
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1428 S.C.I. S&S, 75 mm offset for 75 mm dia pipe as per 232.90 each 1 each 232.90
IS: 3990
LABOUR
0107 Fitter 1st class 207.00 day 0.04 day 8.28
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 248.78
1722 Rubber insertions for 100 mm dia pipe joints 14.50 each 1 each 14.50
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 246.85
Add 5 % for water, electricity, sundries and other 12.34
overhead charges
TOTAL 259.19
Add 10 % for contractor's profit 25.92
Cost for 1 no. 285.11
Say 285.00
18.74 Providing fixing and push on jointing sand cast iron S&S door piece as per IS: 3989 including EPDM rubber gasket
complete:
18.74.2 75 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1434 S.C.I. door pieces 75 mm dia pipe as per IS: 3989 153.00 each 1 each 153.00
1721 Rubber insertions for 80 mm dia pipe joints 11.00 each 1 each 11.00
LABOUR
0107 Fitter 1st class 207.00 day 0.04 day 8.28
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 179.88
Add 5 % for water, electricity, sundries and other 8.99
overhead charges
TOTAL 188.87
Add 10 % for contractor's profit 18.89
Cost for 1 no. 207.76
Say 208.00
18.75 Providing fixing and push on jointing sand cast iron S&S terminal guard as per IS: 3989 including EPDM rubber
gasket complete:
18.75.1 100 mm
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
1435 S.C.I. Slotted cowl (terminal guard ) 100 mm dia 240.55 each 1 each 240.55
pipe as per IS: 3989
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
18.77.2 75 mm
1929 UPVC single equal Tee (without door) 75x75x75 87.45 each 1 each 87.45
mm
1935 UPVC bend 45° 75 mm 33.25 each 1 each 33.25
1937 UPVC plain bend 75 mm 38.00 each 1 each 38.00
LABOUR
0107 Fitter 1st class 207.00 day 0.25 day 51.75
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 391.75
Add 5 % for water, electricity, sundries and other 19.59
overhead charges
TOTAL 411.34
Add 10 % for contractor's profit 41.13
Cost of 4 nos 452.47
Rate for 1 no 113.11
Say 113.00
18.77 Providing and fixing on wall face UV stabilized Unplasticised - PVC moulded fittings/ accessories having 3.2mm wall
thickness for Rigid PVC pipes conforming to IS : 13592 (heavy) jointing with seal ring conforming to IS : 5382 leaving
10 mm gap for thermal expansion.
18.77.3 110 mm
Code Description Rate Unit Qty Total
Details of cost for 4 accessories
1932 UPVC single equal Tee (with door) 110x110x110 155.55 each 1 each 155.55
mm
1930 UPVC single equal Tee (without door) 110x110x110 118.15 each 1 each 118.15
mm
1936 UPVC bend 45° 110 mm 61.60 each 1 each 61.60
1938 UPVC plain bend 110 mm 78.10 each 1 each 78.10
LABOUR
0107 Fitter 1st class 207.00 day 0.3 day 62.10
0114 Beldar 190.00 day 0.3 day 57.00
TOTAL 532.50
Add 5 % for water, electricity, sundries and other 26.63
overhead charges
TOTAL 559.13
Add 10 % for contractor's profit 55.91
Cost of 4 nos 615.04
Rate for 1 no 153.76
Say 154.00
18.77 Providing and fixing on wall face UV stabilized Unplasticised - PVC moulded fittings/ accessories having 3.2mm wall
thickness for Rigid PVC pipes conforming to IS : 13592 (heavy) jointing with seal ring conforming to IS : 5382 leaving
10 mm gap for thermal expansion.
18.77.4 150 mm
Code Description Rate Unit Qty Total
Details of cost for 4 accessories
1917 UPVC single equal Tee (without door) 110x110x110 236.33 each 1 each 236.33
mm
18.77.6 75 mm
Code Description Rate Unit Qty Total
Details of cost for 1 coupler
1947 UPVC Doouble "Y" 75mm 92.10 each 1 each 92.10
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 111.95
Add 5 % for water, electricity, sundries and other 5.60
overhead charges
TOTAL 117.55
Add 10 % for contractor's profit 11.76
Cost of 1 coupler 129.31
Say 129.00
18.77 Providing and fixing on wall face UV stabilized Unplasticised - PVC moulded fittings/ accessories having 3.2mm wall
thickness for Rigid PVC pipes conforming to IS : 13592 (heavy) jointing with seal ring conforming to IS : 5382 leaving
10 mm gap for thermal expansion.
18.77.7 110 mm
Code Description Rate Unit Qty Total
Details of cost for 1 coupler
1948 UPVC Doouble "Y" 110mm_x000D_ 174.05 each 1 each 174.05
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 193.90
Add 5 % for water, electricity, sundries and other 9.70
overhead charges
TOTAL 203.60
Add 10 % for contractor's profit 20.36
Cost of 1 coupler 223.96
18.77.9 75 mm
Code Description Rate Unit Qty Total
Details of cost for 1 coupler
1939 UPVC vent covel 75mm 9.80 each 1 each 9.80
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 29.65
Add 5 % for water, electricity, sundries and other 1.48
overhead charges
TOTAL 31.13
Add 10 % for contractor's profit 3.11
Cost of 1 coupler 34.24
Say 34.00
18.77 Providing and fixing on wall face UV stabilized Unplasticised - PVC moulded fittings/ accessories having 3.2mm wall
thickness for Rigid PVC pipes conforming to IS : 13592 (heavy) jointing with seal ring conforming to IS : 5382 leaving
10 mm gap for thermal expansion.
18.77.10 110 mm
Code Description Rate Unit Qty Total
Details of cost for 1 coupler
1940 UPVC vent covel 110mm 18.10 each 1 each 18.10
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 37.95
Add 5 % for water, electricity, sundries and other 1.90
overhead charges
TOTAL 39.85
Add 10 % for contractor's profit 3.99
Cost of 1 coupler 43.84
Say 44.00
18.77 Providing and fixing on wall face UV stabilized Unplasticised - PVC moulded fittings/ accessories having 3.2mm wall
thickness for Rigid PVC pipes conforming to IS : 13592 (heavy) jointing with seal ring conforming to IS : 5382 leaving
10 mm gap for thermal expansion.
18.77.12 75 mm
Code Description Rate Unit Qty Total
Details of cost for 1 coupler
1941 UPVC access door cap 75mm 23.15 each 1 each 23.15
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 43.00
Add 5 % for water, electricity, sundries and other 2.15
overhead charges
TOTAL 45.15
18.77.13 110 mm
Code Description Rate Unit Qty Total
Details of cost for 1 coupler
1942 UPVC access door cap 110mm 31.30 each 1 each 31.30
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 51.15
Add 5 % for water, electricity, sundries and other 2.56
overhead charges
TOTAL 53.71
Add 10 % for contractor's profit 5.37
Cost of 1 coupler 59.08
Say 59.00
18.77 Providing and fixing on wall face UV stabilized Unplasticised - PVC moulded fittings/ accessories having 3.2mm wall
thickness for Rigid PVC pipes conforming to IS : 13592 (heavy) jointing with seal ring conforming to IS : 5382 leaving
10 mm gap for thermal expansion.
18.78.1 75 mm
Code Description Rate Unit Qty Total
Details of cost for 5 nos.
Materials
1933 UPVC pipe clip 75 mm 10.80 each 5 each 54.00
18.78.2 110 mm
Code Description Rate Unit Qty Total
Details of cost for 5 nos.
Materials
1934 UPVC pipe clip 110 mm 14.15 each 5 each 70.75
2813 Hard wood Plug 50x50x50mm 7.00 each 10 each 70.00
5.9 Cement Mortar C.M. 1:4 (1 cement : 4 coarse sand) 2654.27 cum 0.002 cum 5.31
(Rate as per item No 5.9)
Labour :-
0107 Fitter 1st class 207.00 day 0.1 day 20.70
0104 Mason 2nd class 197.00 day 0.25 day 49.25
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 263.51
Add 5 % for water, electricity, sundries and other 13.18
overhead charges
TOTAL 276.69
Add 10 % for contractor's profit 27.67
Cost of 5 Nos. 304.36
Cost of 1 No. 60.87
Say 61.00
18.79 Painting sand cast iron/ centrifugally cast (spun) iron soil, waste vent pipes and fittings with paint of any colour over
a coat of primer (of approved quality) for new work :
18.79.1 100 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost for 10 metres
MATERIALS
Perimeter = 3.14x110 mm =345.71
Area 10x0.3457 = 3.46 sqm
Priming coat
Extra Labour
0111 Painter 197.00 day 0.05 day 9.85
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 242.41
Add 5 % for water, electricity, sundries and other 0.97
overhead charges on all except (A) i.e. on (242.41 -
223.06) = 19.35
TOTAL 243.38
Add 10 % for contractor's profit on all except (A) 2.03
i.e. on (243.38 - 223.06) = 20.32
Cost of 10 metres 245.41
Cost of 1 metre 24.54
Say 24.50
18.79 Painting sand cast iron/ centrifugally cast (spun) iron soil, waste vent pipes and fittings with paint of any colour over
a coat of primer (of approved quality) for new work :
18.79.2 75 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost for 10 metres
MATERIALS
Perimeter = 3.14x82 mm =257.71
Area 10x0.2577 =2.577 sqm say 2.60 sq. m for
outer surface
Priming coat
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 2.6 sqm 44.90
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 2.6 sqm 122.72
Extra Labour
0111 Painter 197.00 day 0.05 day 9.85
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 186.97
Add 5 % for water, electricity, sundries and other 0.97
overhead charges on all except (A) i.e. on (186.97 -
167.62) = 19.35
TOTAL 187.94
Add 10 % for contractor's profit on all except (A) 2.03
i.e. on (187.94 - 167.62) = 20.32
Cost of 10 metres 189.97
Cost of 1 metre 18.99
Say 19.00
18.80 Repainting sand cast iron/ centrifugally cast iron (spun) iron, soil, waste, vent pipes and fittings with paint of any
colour such as chocolate, grey or buff etc :
18.80.1 100 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost for 10 metres
Painting one coat with paint of any colour such as
chocolate,grey or buff etc.
LABOUR (Extra)
0111 Painter 197.00 day 0.05 day 9.85
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 123.43
Add 5 % for water, electricity, sundries and other 0.97
overhead charges on all except (A) i.e. on (123.43 -
104.08) = 19.35
TOTAL 124.40
Add 10 % for contractor's profit on all except (A) 2.03
i.e. on (124.40 - 104.08) = 20.32
Cost of 10 metres 126.43
Cost of 1 metre 12.64
Say 12.50
18.80 Repainting sand cast iron/ centrifugally cast iron (spun) iron, soil, waste, vent pipes and fittings with paint of any
colour such as chocolate, grey or buff etc :
18.80.2 75 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost for 10 metres
Painting one coat with paint of any colour such as
chocolate,grey or buff etc.
14.23.0.2 Painting on old work (Rate as per item no 14.23.2) 30.08 sqm 2.577 sqm 77.52
LABOUR (Extra)
0111 Painter 197.00 day 0.03 day 5.91
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 89.13
Add 5 % for water, electricity, sundries and other 0.58
overhead charges on all except (A) i.e. on (89.13 -
77.52) = 11.61
TOTAL 89.71
Add 10 % for contractor's profit on all except (A) 1.22
i.e. on (89.71 - 77.52) = 12.19
Cost of 10 metres 90.93
Cost of 1 metre 9.09
Say 9.10
18.81 Providing and fixing M.S. holder bat clamp of approved design to sand cast iron/ cast iron (spun) pipes comprising of
M.S. flat brackets made of 50x5mm flat of specified shape, projecting 75mm outside the wall surface and fixed on
wall with 4nos, 6mm dia expansion hold fasteners including drilling necessary holes in brick wall/ CC/ RCC surface
and the cost of bolts etc. The pipes shall be fixed to the already fixed brackets with the help of 30mm x1.6mm
galvanised M.S. flats of specified shape and of total length 420mm and shall be fixed with M.S. nuts, bolts, &
washers of size 25x6mm, one bolts on each side of the pipe.
18.81.1 Total bracket length 580mm of approved shape and design (for single, 100mm dia pipe).
Code Description Rate Unit Qty Total
Details of cost for 5 nos.
MATERIALS
M.S. flats 50x5mm 50x0.58= 2.90m
@ 1.97 kg/ metre = 5.71 kg.
M.S. flats 30x1.6mm 5x0.42 = 2.10m.
priming coat
5x0.58x0.11=0.32
5x0.42x0.063=0.13
0.45 sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.45 sqm 7.77
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 0.45 sqm 21.24
LABOUR:-
0107 Fitter 1st class 207.00 day 0.15 day 31.05
0110 Blacksmith 2nd class 197.00 day 0.05 day 9.85
0114 Beldar 190.00 day 0.2 day 38.00
MACHINERY
0031 Hire charges of Portable Electric Drill Machine 50.00 day 1.2 day 60.00
Total 593.73
Add 5 % for water, electricity, sundries and other 28.24
overhead charges on all except (A) i.e. on (593.73 -
29.01) = 564.72
Total 621.97
Add 10 % for contractor's profit on all except (A) 59.30
i.e. on (621.97 - 29.01) = 592.96
Cost for 5 Nos. 681.27
Cost for 1 nos. 136.25
Say 136.00
18.81 Providing and fixing M.S. holder bat clamp of approved design to sand cast iron/ cast iron (spun) pipes comprising of
M.S. flat brackets made of 50x5mm flat of specified shape, projecting 75mm outside the wall surface and fixed on
wall with 4nos, 6mm dia expansion hold fasteners including drilling necessary holes in brick wall/ CC/ RCC surface
and the cost of bolts etc. The pipes shall be fixed to the already fixed brackets with the help of 30mm x1.6mm
galvanised M.S. flats of specified shape and of total length 420mm and shall be fixed with M.S. nuts, bolts, &
washers of size 25x6mm, one bolts on each side of the pipe.
18.81.2 Total bracket length 810mm of approved shape and design (for two, 100mm dia pipes).
Code Description Rate Unit Qty Total
Details of cost for 5 nos.
MATERIALS
M.S. flats 50x5mm 50x0.81= 4.05m
@ 1.97 kg/ metre = 7.98 kg.
M.S. flats 30x1.6mm 5x2x0.42 = 4.20m.
0.38kg/metre = 1.60kg.
Total = 9.58kg.
Add wastage 5% = 0.48kg.
Total = 10.06 kg.
priming coat
5x0.81x0.11=0.45
5x2x0.42x0.063=0.26
0.71 sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.71 sqm 12.26
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 0.71 sqm 33.51
LABOUR:-
0107 Fitter 1st class 207.00 day 0.15 day 31.05
0110 Blacksmith 2nd class 197.00 day 0.05 day 9.85
0114 Beldar 190.00 day 0.2 day 38.00
MACHINERY
0031 Hire charges of Portable Electric Drill Machine 50.00 day 1.2 day 60.00
Total 756.41
Add 5 % for water, electricity, sundries and other 35.53
overhead charges on all except (A) i.e. on (756.41 -
45.77) = 710.64
Total 791.94
Add 10 % for contractor's profit on all except (A) 74.62
i.e. on (791.94 - 45.77) = 746.17
Cost for 5 Nos. 866.56
Cost for 1 nos. 173.31
Say 173.00
18.81 Providing and fixing M.S. holder bat clamp of approved design to sand cast iron/ cast iron (spun) pipes comprising of
M.S. flat brackets made of 50x5mm flat of specified shape, projecting 75mm outside the wall surface and fixed on
wall with 4nos, 6mm dia expansion hold fasteners including drilling necessary holes in brick wall/ CC/ RCC surface
and the cost of bolts etc. The pipes shall be fixed to the already fixed brackets with the help of 30mm x1.6mm
galvanised M.S. flats of specified shape and of total length 420mm and shall be fixed with M.S. nuts, bolts, &
washers of size 25x6mm, one bolts on each side of the pipe.
18.81.3 Total bracket length 1040mm of approved shape and design (for three, 100mm dia pipes).
Code Description Rate Unit Qty Total
Details of cost for 5 nos.
MATERIALS
M.S. flats 50x5mm 50x1.04= 5.20m
@ 1.97 kg/ metre = 10.24 kg.
M.S. flats 30x1.6mm 5x3x0.42 = 6.30m.
0.38kg/metre = 2.39kg.
Total = 12.63kg.
Add wastage 5% = 0.63kg.
Total = 13.26 kg.
1009 Structurals such as tees,angles channels and R.S. 4560.00 quintal 0.1326 quintal 604.66
joists
0950 Wedge expansion hold fastner 1/4" or 6 mm 5.65 each 20 each 113.00
priming coat
LABOUR
0107 Fitter 1st class 207.00 day 0.17 day 35.19
0110 Blacksmith 2nd class 197.00 day 0.1 day 19.70
0114 Beldar 190.00 day 0.27 day 51.30
MACHINERY
0031 Hire charges of Portable Electric Drill Machine 50.00 day 1.2 day 60.00
Total 946.38
Add 5 % for water, electricity, sundries and other 44.19
overhead charges on all except (A) i.e. on (946.38 -
62.53) = 883.85
Total 990.57
Add 10 % for contractor's profit on all except (A) 92.80
i.e. on (990.57 - 62.53) = 928.04
Cost for 5 Nos. 1083.37
Cost for 1 nos. 216.67
Say 217.00
19.1.1 PN - 16 Pipe, 16 mm OD
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
Length = 10m
30% for fittings and wastage etc. = 3m
Total = 13m
1901 Poly propylene- Random - Co - Polymer (PPR) pipes 37.00 metre 13 metre 481.00
SDR 7.4 - 16 Outer dia
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.001 cum 3.36
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1 day 190.00
TOTAL 881.36
Add 5 % for water, electricity, sundries and other 44.07
overhead charges
TOTAL 925.43
Add 10 % for contractor's profit 92.54
Cost for 10 metre 1017.97
Cost for 1 metre 101.79
Say 102.00
19.1 Providing and fixing on wall surface 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V stabilized &
anti - microbial fusion welded, having thermal stability for hot & cold water supply including all PP - R plain & brass
threaded polypropylene random fittings including fixing the pipe with clamps at 1.00 m spacing, testing of joints
complete.
19.1.2 PN - 16 Pipe, 20 mm OD
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
Length = 10m
30% for fittings and wastage etc. = 3m
Total = 13m
1902 Poly propylene - Random - Co - Polymer (PPR) 57.00 metre 13 metre 741.00
pipes SDR 7.4 - 20mm Outer dia.
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.001 cum 3.36
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 1.15 day 238.05
0114 Beldar 190.00 day 1.15 day 218.50
TOTAL 1200.91
Add 5 % for water, electricity, sundries and other 60.05
overhead charges
TOTAL 1260.96
Add 10 % for contractor's profit 126.10
Cost for 10 metre 1387.06
19.1.3 PN - 16 Pipe, 25 mm OD
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
Length = 10m
30% for fittings and wastage etc. = 3m
Total = 13m
1903 Poly propylene - Random - Co - polymer (PPR) 88.00 metre 13 metre 1144.00
pipes SDR 7.4 - 25 mm outer dia.
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.001 cum 3.36
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 1.2 day 248.40
0114 Beldar 190.00 day 1.2 day 228.00
TOTAL 1623.76
Add 5 % for water, electricity, sundries and other 81.19
overhead charges
TOTAL 1704.95
Add 10 % for contractor's profit 170.50
Cost for 10 metre 1875.45
Cost for 1 metre 187.54
Say 188.00
19.1 Providing and fixing on wall surface 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V stabilized &
anti - microbial fusion welded, having thermal stability for hot & cold water supply including all PP - R plain & brass
threaded polypropylene random fittings including fixing the pipe with clamps at 1.00 m spacing, testing of joints
complete.
19.1.4 PN - 16 Pipe, 32 mm OD
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
Length = 10m
30% for fittings and wastage etc. = 3m
Total = 13m
1904 Poly propylene - Random - Co - poymer (PPR) pipes 142.00 metre 13 metre 1846.00
SDR 7.4 - 32 mm Outer dia.
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.001 cum 3.36
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 1.2 day 248.40
0114 Beldar 190.00 day 1.2 day 228.00
TOTAL 2325.76
Add 5 % for water, electricity, sundries and other 116.29
overhead charges
TOTAL 2442.05
19.1.5 PN - 16 Pipe, 40 mm OD
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
Length = 10m
30% for fittings and wastage etc. = 3m
Total = 13m
1905 Poly propylene - Random - Co - polymer (PPR) 213.00 metre 13 metre 2769.00
pipes SDR 7.4 - 40mm Outer dia.
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.001 cum 3.36
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 1.5 day 310.50
0114 Beldar 190.00 day 1.5 day 285.00
TOTAL 3367.86
Add 5 % for water, electricity, sundries and other 168.39
overhead charges
TOTAL 3536.25
Add 10 % for contractor's profit 353.63
Cost for 10 metre 3889.88
Cost for 1 metre 388.98
Say 389.00
19.1 Providing and fixing on wall surface 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V stabilized &
anti - microbial fusion welded, having thermal stability for hot & cold water supply including all PP - R plain & brass
threaded polypropylene random fittings including fixing the pipe with clamps at 1.00 m spacing, testing of joints
complete.
19.1.6 PN - 16 Pipe, 50 mm OD
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
Length = 10m
30% for fittings and wastage etc. = 3m
Total = 13m
1906 Poly propylene - Random - Co - polymer (PPR) 333.00 metre 13 metre 4329.00
pipes SDR 7.4 - 50mm Outer dia.
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.001 cum 3.36
(Rate as per item No 5.8)
LABOUR
0107 Fitter 1st class 207.00 day 1.5 day 310.50
0114 Beldar 190.00 day 1.5 day 285.00
TOTAL 4927.86
19.2.1 PN - 16 Pipe, 16 mm OD
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
3 layer PP-R pipe = 10 m +
Add 30% for fittings, clamps and wastage etc. = 3 m
Total qty = 13 m
1901 Poly propylene- Random - Co - Polymer (PPR) pipes 37.00 metre 13 metre 481.00
SDR 7.4 - 16 Outer dia
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.001 cum 3.36
(Rate as per item No 5.8)
LABOUR
0102 Mason 1st class 207.00 day 0.5 day 103.50
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1.5 day 285.00
TOTAL 1079.86
Add 5 % for water, electricity, sundries and other 53.99
overhead charges
TOTAL 1133.85
Add 10 % for contractor's profit 113.39
Cost for 10 metre 1247.24
Cost for 1 metre 124.72
Say 125.00
19.2 Providing and fixing in concealed in wall 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply including all PP - R
plain & brass threaded polypropylene random fittings including fixing the pipe with clamps at 1.00 m spacing,
cutting chases and making good the same, testing of joints complete.
19.2.2 PN - 16 Pipe, 20 mm OD
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
3 layer PP-R pipe = 10 m +
Add 30% for fittings, clamps and wastage etc. = 13
m
Total qty = 13 m
1902 Poly propylene - Random - Co - Polymer (PPR) 57.00 metre 13 metre 741.00
pipes SDR 7.4 - 20mm Outer dia.
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.001 cum 3.36
(Rate as per item No 5.8)
19.2.3 PN - 16 Pipe, 25 mm OD
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
3 layer PP-R pipe = 10 m +
Add 30% for fittings, clamps and wastage etc. = 13
m
Total qty = 13 m
1903 Poly propylene - Random - Co - polymer (PPR) 88.00 metre 13 metre 1144.00
pipes SDR 7.4 - 25 mm outer dia.
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.001 cum 3.36
(Rate as per item No 5.8)
LABOUR
0102 Mason 1st class 207.00 day 0.5 day 103.50
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1.5 day 285.00
TOTAL 1742.86
Add 5 % for water, electricity, sundries and other 87.14
overhead charges
TOTAL 1830.00
Add 10 % for contractor's profit 183.00
Cost for 10 metre 2013.00
Cost for 1 metre 201.30
Say 201.00
19.2 Providing and fixing in concealed in wall 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4 U V
stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water supply including all PP - R
plain & brass threaded polypropylene random fittings including fixing the pipe with clamps at 1.00 m spacing,
cutting chases and making good the same, testing of joints complete.
19.2.4 PN - 16 Pipe, 32 mm OD
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
3 layer PP-R pipe = 10 m +
19.3.1 PN - 16 Pipe, 16 mm OD
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
3 layer PP-R pipe = 10 m +
Add 15% for fittings and wastage etc. =1.5 m
19.3.2 PN - 16 Pipe, 20 mm OD
Code Description Rate Unit Qty Total
19.3.3 PN - 16 Pipe, 25 mm OD
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
3 layer PP-R pipe = 10 m +
Add 15% for fittings and wastage etc. =1.5 m
19.3.4 PN - 16 Pipe, 32 mm OD
Code Description Rate Unit Qty Total
19.3.5 PN - 16 Pipe, 40 mm OD
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
3 layer PP-R pipe = 10 m +
Add 15% for fittings and wastage etc. =1.5 m
19.3.6 PN - 16 Pipe, 50 mm OD
Code Description Rate Unit Qty Total
19.3.8 PN - 16 Pipe, 75 mm OD
Code Description Rate Unit Qty Total
19.3.9 PN - 16 Pipe, 90 mm OD
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
3 layer PP-R pipe = 10 m +
Add 15% for fittings and wastage etc. =1.5 m
Total qty = 13 m
1951 Chlorinated Polyvinyl - chloride (CPVC) pipe - 16 42.65 metre 13 metre 554.45
Outer dia
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.001 cum 3.36
(Rate as per item No 5.8)
LABOUR
0102 Mason 1st class 207.00 day 0.5 day 103.50
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1.5 day 285.00
TOTAL 1153.31
Add 5 % for water, electricity, sundries and other 57.67
overhead charges
TOTAL 1210.98
Add 10 % for contractor's profit 121.10
Cost for 10 metre 1332.08
Cost for 1 metre 133.20
Say 133.00
19.5 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water
supply including all CPVC plain & brass threaded fittings i/c fixing the pipe with clamps at 1.00 m spacing. This
includes jointing of pipes & fittings with one step CPVC solvent cement and the cost of cutting chases and making
good the same including testing of joints complete as per direction of Engineer in Charge._x000D_
CONCEALED WORK including cutting chases and making good the walls etc.,
Total qty = 13 m
1953 Chlorinated Polyvinyl - chloride (CPVC) pipe - 25 95.55 metre 13 metre 1242.15
mm outer dia.
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.001 cum 3.36
(Rate as per item No 5.8)
LABOUR
0102 Mason 1st class 207.00 day 0.5 day 103.50
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1.5 day 285.00
TOTAL 1841.01
Add 5 % for water, electricity, sundries and other 92.05
overhead charges
TOTAL 1933.06
Add 10 % for contractor's profit 193.31
Cost for 10 metre 2126.37
Cost for 1 metre 212.63
Say 213.00
Total qty = 13 m
1954 Chlorinated Polyvinyl - chloride (CPVC) pipe - 32 143.35 metre 13 metre 1863.55
mm Outer dia.
5.8 Cement Mortar C.M. 1:3 (1 cement : 3 coarse sand) 3356.27 cum 0.001 cum 3.36
(Rate as per item No 5.8)
LABOUR
0102 Mason 1st class 207.00 day 0.5 day 103.50
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1.5 day 285.00
TOTAL 2462.41
Add 5 % for water, electricity, sundries and other 123.12
overhead charges
TOTAL 2585.53
Add 10 % for contractor's profit 258.55
Cost for 10 metre 2844.08
Cost for 1 metre 284.40
Say 284.00
19.6 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water
supply including all CPVC plain & brass threaded fittings. This included jointing of pipes & fittings with one step
CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge._x000D_
EXTERNAL WORK
TOTAL 1712.60
Add 10 % for contractor's profit on all except (A) 168.67
i.e. on (1712.60 - 25.92) = 1686.68
TOTAL 2702.05
Add 10 % for contractor's profit on all except (A) 266.58
i.e. on (2702.05 - 36.28) = 2665.77
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
TOTAL 160.35
Add 5 % for water, electricity, sundries and other 8.02
overhead charges
TOTAL 168.37
Add 10 % for contractor's profit 16.84
Cost of one no. 185.21
Say 185.00
19.13 Providing and fixing 15 mm nominal bore Brass bib/stop cock of approved quality:
19.13.2 Bib cock (350 grams)
Code Description Rate Unit Qty Total
Details of cost for one no.
Materials :-
2001 Brass bib-cock 15 mm dia (350 grams) 194.65 each 1 each 194.65
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
TOTAL 205.00
Add 5 % for water, electricity, sundries and other 10.25
overhead charges
TOTAL 215.25
Add 10 % for contractor's profit 21.53
Cost of one no. 236.78
Say 237.00
19.13 Providing and fixing 15 mm nominal bore Brass bib/stop cock of approved quality:
19.13.3 Stop cock (350 grams)
Code Description Rate Unit Qty Total
Details of cost for one no.
Materials :-
2002 Brass stop-cock 15 mm dia (350 grams) 194.65 each 1 each 194.65
LABOUR
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 3303.10
Add 5 % for water, electricity, sundries and other 165.16
overhead charges
TOTAL 3468.26
Add 10 % for contractor's profit 346.83
Cost for 10 No. 3815.09
Cost for 1 No. 381.50
Say 382.00
19.14 Providing and fixing 15 mm nominal bore C.P. brass fittings of approved make and conforming to IS:8931 including
C.P. brass extension if required:
19.14.2 Long nose bib cock (500 grams)
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials:
2004 C.P. Brass long nose bibcock 15 mm (500 grams) 364.95 each 10 each 3649.50
2021 C.P. Brass extension piece 15 mm nominal bore 43.80 each 2 each 87.60
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 3935.60
Add 5 % for water, electricity, sundries and other 196.78
overhead charges
TOTAL 4132.38
Add 10 % for contractor's profit 413.24
Cost for 10 No. 4545.62
Cost for 1 No. 454.56
Say 455.00
2021 C.P. Brass extension piece 15 mm nominal bore 43.80 each 2 each 87.60
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 3692.60
Add 5 % for water, electricity, sundries and other 184.63
overhead charges
TOTAL 3877.23
Add 10 % for contractor's profit 387.72
Cost for 10 No. 4264.95
Cost for 1 No. 426.49
Say 426.00
19.14 Providing and fixing 15 mm nominal bore C.P. brass fittings of approved make and conforming to IS:8931 including
C.P. brass extension if required:
19.14.4 Piller Cock (400 grams)
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials:
2000 C.P. Brass pillercock 15 mm (400 grams) 325.00 each 10 each 3250.00
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 3448.50
Add 5 % for water, electricity, sundries and other 172.43
overhead charges
TOTAL 3620.93
Add 10 % for contractor's profit 362.09
Cost for 10 No. 3983.02
Cost for 1 No. 398.30
Say 398.00
19.14 Providing and fixing 15 mm nominal bore C.P. brass fittings of approved make and conforming to IS:8931 including
C.P. brass extension if required:
19.14.5 Two way bib cock (800 grams)
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials:
2008 C.P. Brass two way bib cock 583.95 each 10 each 5839.50
2021 C.P. Brass extension piece 15 mm nominal bore 43.80 each 2 each 87.60
LABOUR
2021 C.P. Brass extension piece 15 mm nominal bore 43.80 each 2 each 87.60
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 4276.60
Add 5 % for water, electricity, sundries and other 213.83
overhead charges
TOTAL 4490.43
Add 10 % for contractor's profit 449.04
Cost for 10 No. 4939.47
Cost for 1 No. 493.94
Say 494.00
19.14 Providing and fixing 15 mm nominal bore C.P. brass fittings of approved make and conforming to IS:8931 including
C.P. brass extension if required:
19.14.7 Angle valve for basin mixer and geyser points (450 grams)
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials:
2007 C.P. Brass angle valve 15 mm (450 grams) 301.70 each 10 each 3017.00
2021 C.P. Brass extension piece 15 mm nominal bore 43.80 each 2 each 87.60
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 3303.10
Add 5 % for water, electricity, sundries and other 165.16
overhead charges
TOTAL 3468.26
Add 10 % for contractor's profit 346.83
Cost for 10 No. 3815.09
LABOUR
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1 day 190.00
TOTAL 10801.10
Add 5 % for water, electricity, sundries and other 540.06
overhead charges
TOTAL 11341.16
Add 10 % for contractor's profit 1134.12
Cost for 10 No. 12475.28
Cost for 1 No. 1247.52
Say 1248.00
19.14 Providing and fixing 15 mm nominal bore C.P. brass fittings of approved make and conforming to IS:8931 including
C.P. brass extension if required:
19.14.9 Kitchen sink mixer with cast swivel spout (1000 grams)
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials:
2010 C.P. Brass Kitchen Sink Mixer 15 mm (1000 grams) 1031.65 each 10 each 10316.50
2021 C.P. Brass extension piece 15 mm nominal bore 43.80 each 2 each 87.60
LABOUR
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1 day 190.00
TOTAL 10801.10
Add 5 % for water, electricity, sundries and other 540.06
overhead charges
TOTAL 11341.16
Add 10 % for contractor's profit 1134.12
Cost for 10 No. 12475.28
Cost for 1 No. 1247.52
Say 1248.00
19.14 Providing and fixing 15 mm nominal bore C.P. brass fittings of approved make and conforming to IS:8931 including
C.P. brass extension if required:
19.14.10 Wall mixer with elegant knob (1400 grams)
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials:
LABOUR
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1 day 190.00
TOTAL 15472.60
Add 5 % for water, electricity, sundries and other 773.63
overhead charges
TOTAL 16246.23
Add 10 % for contractor's profit 1624.62
Cost for 10 No. 17870.85
Cost for 1 No. 1787.08
Say 1787.00
19.14 Providing and fixing 15 mm nominal bore C.P. brass fittings of approved make and conforming to IS:8931 including
C.P. brass extension if required:
19.14.11 Hand shower set with flexible extension pipe
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials:
2012 C.P. Brass Hand shower set with flexible extension 632.60 each 10 each 6326.00
pipe 15 mm
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 6524.50
Add 5 % for water, electricity, sundries and other 326.23
overhead charges
TOTAL 6850.73
Add 10 % for contractor's profit 685.07
Cost for 10 No. 7535.80
Cost for 1 No. 753.58
Say 754.00
19.14 Providing and fixing 15 mm nominal bore C.P. brass fittings of approved make and conforming to IS:8931 including
C.P. brass extension if required:
19.14.12 Bottle trap set with extension pipes
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials:
2013 C.P. Brass Bottle trap set with extension pipe 389.30 each 10 each 3893.00
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 4091.50
Add 5 % for water, electricity, sundries and other 204.58
overhead charges
TOTAL 4296.08
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 2330.10
Add 5 % for water, electricity, sundries and other 116.51
overhead charges
TOTAL 2446.61
Add 10 % for contractor's profit 244.66
Cost for 10 No. 2691.27
Cost for 1 No. 269.12
Say 269.00
19.14 Providing and fixing 15 mm nominal bore C.P. brass fittings of approved make and conforming to IS:8931 including
C.P. brass extension if required:
19.14.16 Towel rail (600mm long x 20mm dia)
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials:
2017 C.P. Brass Tower rail 600x20mm 272.50 each 10 each 2725.00
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 2923.50
Add 5 % for water, electricity, sundries and other 146.18
overhead charges
TOTAL 3069.68
Add 10 % for contractor's profit 306.97
Cost for 10 No. 3376.65
Cost for 1 No. 337.66
Say 338.00
19.14 Providing and fixing 15 mm nominal bore C.P. brass fittings of approved make and conforming to IS:8931 including
C.P. brass extension if required:
19.14.17 Towel ring (150 mm dia)
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials:
2029 C.P. Brass Tower ring 150 mm dai 200.00 each 10 each 2000.00
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 2198.50
Add 5 % for water, electricity, sundries and other 109.93
overhead charges
TOTAL 2308.43
Add 10 % for contractor's profit 230.84
Cost for 10 No. 2539.27
Cost for 1 No. 253.92
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 15274.10
Add 5 % for water, electricity, sundries and other 763.71
overhead charges
TOTAL 16037.81
Add 10 % for contractor's profit 1603.78
Cost for 10 No. 17641.59
Cost for 1 No. 1764.15
Say 1764.00
19.14 Providing and fixing 15 mm nominal bore C.P. brass fittings of approved make and conforming to IS:8931 including
C.P. brass extension if required:
19.14.19 Health foscet (hand jet) with flexible connection pipe (for WC)
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials:
2028 Health foscet (hand jet) with flexible connection 650.00 set 10 set 6500.00
pipe (for WC)
LABOUR
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 6698.50
Add 5 % for water, electricity, sundries and other 334.93
overhead charges
TOTAL 7033.43
Add 10 % for contractor's profit 703.34
Cost for 10 No. 7736.77
Cost for 1 No. 773.67
Say 774.00
19.14 Providing and fixing 15 mm nominal bore C.P. brass fittings of approved make and conforming to IS:8931 including
C.P. brass extension if required:
19.14.20 CP brass water jet to be fixed in seat cover of WC with flexible connection pipe
Code Description Rate Unit Qty Total
Details of cost for 10 nos.
Materials:
2027 CP brass water jet to be fixed in seat cover of WC 480.00 set 10 set 4800.00
with flexible connection pipe
TOTAL 63.71
Add 10 % for contractor's profit on all except (A) 2.03
i.e. on (63.71 - 43.39) = 20.32
Cost of 10 metre 65.74
Cost of one metre 6.57
Say 6.60
19.21 Painting G.I. pipes and fittings with synthetic enamel white paint over a red oxide zinc chromate priming coat, both
of approved quality for new work:
19.21.2 20 mm diameter pipe.
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Perimeter = 0.0845 metre
Area = 10x0.0845 sqm. = 0.845 sqm.
Priming coat-
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 0.845 sqm 39.88
TOTAL 74.79
Add 10 % for contractor's profit on all except (A) 2.03
i.e. on (74.79 - 54.47) = 20.32
Cost of 10 metre 76.82
Cost of one metre 7.68
Say 7.70
19.21 Painting G.I. pipes and fittings with synthetic enamel white paint over a red oxide zinc chromate priming coat, both
of approved quality for new work:
19.21.3 25 mm diameter pipe.
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Perimeter = 0.1061 metre
Area = 10x0.1061 sqm. = 1.061 sqm.
Priming coat-
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 1.061 sqm 50.08
TOTAL 92.78
Add 10 % for contractor's profit on all except (A) 2.44
i.e. on (92.78 - 68.40) = 24.38
Cost of 10 metre 95.22
Cost of one metre 9.52
Say 9.50
19.21 Painting G.I. pipes and fittings with synthetic enamel white paint over a red oxide zinc chromate priming coat, both
of approved quality for new work:
19.21.4 32 mm diameter pipe.
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Perimeter = 0.1334 metre
Area = 10x0.1334 sqm. = 1.334 sqm.
Priming coat-
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 1.334 sqm 62.96
TOTAL 114.44
Add 10 % for contractor's profit on all except (A) 2.84
i.e. on (114.44 - 86.00) = 28.44
Cost of 10 metre 117.28
Cost of one metre 11.72
Say 11.50
19.21 Painting G.I. pipes and fittings with synthetic enamel white paint over a red oxide zinc chromate priming coat, both
of approved quality for new work:
19.21.5 40 mm diameter pipe.
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Perimeter = 0.1520 metre
Area = 10x0.1520 sqm. = 1.520 sqm.
Priming coat-
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 1.52 sqm 71.74
TOTAL 130.50
Add 10 % for contractor's profit on all except (A) 3.25
i.e. on (130.50 - 97.99) = 32.51
Cost of 10 metre 133.75
Cost of one metre 13.37
Say 13.50
19.21 Painting G.I. pipes and fittings with synthetic enamel white paint over a red oxide zinc chromate priming coat, both
of approved quality for new work:
19.21.6 50 mm diameter pipe.
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Perimeter = 0.1894 metre
TOTAL 162.75
Add 10 % for contractor's profit on all except (A) 4.06
i.e. on (162.75 - 122.11) = 40.64
Cost of 10 metre 166.81
Cost of one metre 16.68
Say 16.50
19.22 Repainting G.I. pipes and fittings with synthetic enamel white paint of approved quality:
19.22.1 15 mm diameter pipe.
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Painting one coat with white paint on old work.
14.23.0.2 Painting on old work (Rate as per item no 14.23.2) 30.08 sqm 0.673 sqm 20.24
LABOUR
Extra labour for confined work
0111 Painter 197.00 day 0.02 day 3.94
0114 Beldar 190.00 day 0.02 day 3.80
TOTAL 27.98
Add 5 % for water, electricity, sundries and other 0.39
overhead charges on all except (A) i.e. on (27.98 -
20.24) = 7.74
TOTAL 28.37
Add 10 % for contractor's profit on all except (A) 0.81
i.e. on (28.37 - 20.24) = 8.13
Cost of 10 metre 29.18
Cost of one metre 2.91
Say 2.90
19.22 Repainting G.I. pipes and fittings with synthetic enamel white paint of approved quality:
19.22.2 20 mm diameter pipe.
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Painting one coat with white paint on old work.
LABOUR
Extra labour for confined work
0111 Painter 197.00 day 0.02 day 3.94
0114 Beldar 190.00 day 0.02 day 3.80
TOTAL 33.16
Add 5 % for water, electricity, sundries and other 0.39
overhead charges on all except (A) i.e. on (33.16 -
25.42) = 7.74
TOTAL 33.55
Add 10 % for contractor's profit on all except (A) 0.81
i.e. on (33.55 - 25.42) = 8.13
Cost of 10 metre 34.36
Cost of one metre 3.43
Say 3.40
19.22 Repainting G.I. pipes and fittings with synthetic enamel white paint of approved quality:
19.22.3 25 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Painting one coat with white paint on old work.
14.23.0.2 Painting on old work (Rate as per item no 14.23.2) 30.08 sqm 1.061 sqm 31.91
LABOUR
Extra labour for confined work
0111 Painter 197.00 day 0.03 day 5.91
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 43.52
Add 5 % for water, electricity, sundries and other 0.58
overhead charges on all except (A) i.e. on (43.52 -
31.91) = 11.61
TOTAL 44.10
Add 10 % for contractor's profit on all except (A) 1.22
i.e. on (44.10 - 31.91) = 12.19
Cost of 10 metre 45.32
Cost of one metre 4.53
Say 4.50
19.22 Repainting G.I. pipes and fittings with synthetic enamel white paint of approved quality:
19.22.4 32 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Painting one coat with white paint on old work.
14.23.0.2 Painting on old work (Rate as per item no 14.23.2) 30.08 sqm 1.334 sqm 40.13
LABOUR
Extra labour for confined work
0111 Painter 197.00 day 0.03 day 5.91
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 52.32
Add 10 % for contractor's profit on all except (A) 1.22
i.e. on (52.32 - 40.13) = 12.19
Cost of 10 metre 53.54
Cost of one metre 5.35
Say 5.40
19.22 Repainting G.I. pipes and fittings with synthetic enamel white paint of approved quality:
19.22.5 40 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Painting one coat with white paint on old work.
14.23.0.2 Painting on old work (Rate as per item no 14.23.2) 30.08 sqm 1.52 sqm 45.72
LABOUR
Extra labour for confined work
0111 Painter 197.00 day 0.04 day 7.88
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 61.20
Add 5 % for water, electricity, sundries and other 0.77
overhead charges on all except (A) i.e. on (61.20 -
45.72) = 15.48
TOTAL 61.97
Add 10 % for contractor's profit on all except (A) 1.63
i.e. on (61.97 - 45.72) = 16.25
Cost of 10 metre 63.60
Cost of one metre 6.36
Say 6.40
19.22 Repainting G.I. pipes and fittings with synthetic enamel white paint of approved quality:
19.22.6 50 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Painting one coat with white paint on old work.
14.23.0.2 Painting on old work (Rate as per item no 14.23.2) 30.08 sqm 1.894 sqm 56.97
LABOUR
Extra labour for confined work
0111 Painter 197.00 day 0.04 day 7.88
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 72.45
Add 5 % for water, electricity, sundries and other 0.77
overhead charges on all except (A) i.e. on (72.45 -
56.97) = 15.48
TOTAL 73.22
Add 10 % for contractor's profit on all except (A) 1.63
i.e. on (73.22 - 56.97) = 16.25
14.22.0.4 Painting with anti-corosive bitumastic paint (Rate 38.51 sqm 0.673 sqm 25.92
as per Item No 14.22.4)
LABOUR
Extra labour for confined work
0111 Painter 197.00 day 0.03 day 5.91
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 37.53
Add 5 % for water, electricity, sundries and other 0.58
overhead charges on all except (A) i.e. on (37.53 -
25.92) = 11.61
TOTAL 38.11
Add 10 % for contractor's profit on all except (A) 1.22
i.e. on (38.11 - 25.92) = 12.19
Cost of 10 metre 39.33
Cost of one metre 3.93
Say 3.90
19.23 Painting G.I. pipes and fittings with two coats of anti-corrosive bitumastic paint of approved quality:
19.23.2 20 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Painting with anti-corrosive paint two coats.
14.22.0.4 Painting with anti-corosive bitumastic paint (Rate 38.51 sqm 0.845 sqm 32.54
as per Item No 14.22.4)
LABOUR
Extra labour for confined work
0111 Painter 197.00 day 0.03 day 5.91
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 44.15
Add 5 % for water, electricity, sundries and other 0.58
overhead charges on all except (A) i.e. on (44.15 -
32.54) = 11.61
TOTAL 44.73
Add 10 % for contractor's profit on all except (A) 1.22
i.e. on (44.73 - 32.54) = 12.19
Cost of 10 metre 45.95
Cost of one metre 4.59
Say 4.60
19.23 Painting G.I. pipes and fittings with two coats of anti-corrosive bitumastic paint of approved quality:
19.23.3 25 mm diameter pipe
14.22.0.4 Painting with anti-corosive bitumastic paint (Rate 38.51 sqm 1.061 sqm 40.86
as per Item No 14.22.4)
LABOUR
Extra labour for confined work
0111 Painter 197.00 day 0.04 day 7.88
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 56.34
Add 5 % for water, electricity, sundries and other 0.77
overhead charges on all except (A) i.e. on (56.34 -
40.86) = 15.48
TOTAL 57.11
Add 10 % for contractor's profit on all except (A) 1.63
i.e. on (57.11 - 40.86) = 16.25
Cost of 10 metre 58.74
Cost of one metre 5.87
Say 5.90
19.23 Painting G.I. pipes and fittings with two coats of anti-corrosive bitumastic paint of approved quality:
19.23.4 32 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Painting with anti-corrosive paint two coats.
14.22.0.4 Painting with anti-corosive bitumastic paint (Rate 38.51 sqm 1.334 sqm 51.37
as per Item No 14.22.4)
LABOUR
Extra labour for confined work
0111 Painter 197.00 day 0.05 day 9.85
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 70.72
Add 5 % for water, electricity, sundries and other 0.97
overhead charges on all except (A) i.e. on (70.72 -
51.37) = 19.35
TOTAL 71.69
Add 10 % for contractor's profit on all except (A) 2.03
i.e. on (71.69 - 51.37) = 20.32
Cost of 10 metre 73.72
Cost of one metre 7.37
Say 7.40
19.23 Painting G.I. pipes and fittings with two coats of anti-corrosive bitumastic paint of approved quality:
19.23.5 40 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Painting with anti-corrosive paint two coats.
14.22.0.4 Painting with anti-corosive bitumastic paint (Rate 38.51 sqm 1.52 sqm 58.54
as per Item No 14.22.4)
TOTAL 82.92
Add 10 % for contractor's profit on all except (A) 2.44
i.e. on (82.92 - 58.54) = 24.38
Cost of 10 metre 85.36
Cost of one metre 8.53
Say 8.50
19.23 Painting G.I. pipes and fittings with two coats of anti-corrosive bitumastic paint of approved quality:
19.23.6 50 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Painting with anti-corrosive paint two coats.
14.22.0.4 Painting with anti-corosive bitumastic paint (Rate 38.51 sqm 1.894 sqm 72.94
as per Item No 14.22.4)
LABOUR
Extra labour for confined work
0111 Painter 197.00 day 0.07 day 13.79
0114 Beldar 190.00 day 0.07 day 13.30
TOTAL 100.03
Add 5 % for water, electricity, sundries and other 1.35
overhead charges on all except (A) i.e. on (100.03 -
72.94) = 27.09
TOTAL 101.38
Add 10 % for contractor's profit on all except (A) 2.84
i.e. on (101.38 - 72.94) = 28.44
Cost of 10 metre 104.22
Cost of one metre 10.42
Say 10.50
19.23 Painting G.I. pipes and fittings with two coats of anti-corrosive bitumastic paint of approved quality:
19.23.7 65 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Painting with anti-corrosive paint two coats.
14.22.0.4 Painting with anti-corosive bitumastic paint (Rate 38.51 sqm 2.387 sqm 91.92
as per Item No 14.22.4)
LABOUR
Extra labour for confined work
0111 Painter 197.00 day 0.08 day 15.76
0114 Beldar 190.00 day 0.08 day 15.20
TOTAL 122.88
TOTAL 124.43
Add 10 % for contractor's profit on all except (A) 3.25
i.e. on (124.43 - 91.92) = 32.51
Cost of 10 metre 127.68
Cost of one metre 12.76
Say 13.00
19.23 Painting G.I. pipes and fittings with two coats of anti-corrosive bitumastic paint of approved quality:
19.23.8 80 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Painting with anti-corrosive paint two coats.
14.22.0.4 Painting with anti-corosive bitumastic paint (Rate 38.51 sqm 2.796 sqm 107.67
as per Item No 14.22.4)
LABOUR
Extra labour for confined work
0111 Painter 197.00 day 0.09 day 17.73
0114 Beldar 190.00 day 0.09 day 17.10
TOTAL 142.50
Add 5 % for water, electricity, sundries and other 1.74
overhead charges on all except (A) i.e. on (142.50 -
107.67) = 34.83
TOTAL 144.24
Add 10 % for contractor's profit on all except (A) 3.66
i.e. on (144.24 - 107.67) = 36.57
Cost of 10 metre 147.90
Cost of one metre 14.79
Say 15.00
19.24 Providing and filling fine sand or coarser grade all-round the G.I. pipes in external work.
19.24.1 15 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost of sand filling alround 15mm dia.
pipe 10 metre long.
Width of sand filling = 300mm
Depth of sand filling
Under the pipe = 75mm+
Above the pipe = 150mm+
Max. external dia of pipe = 21.8mm
= 246.8mm say 247mm
Quantity of sand = 10x0.30x0.247 = 0.744 cum.
= 0.74 cum.
MATERIAL
0254 Fine sand 360.00 cum 0.74 cum 266.40
LABOUR
= 0.750 cum
MATERIAL
0254 Fine sand 360.00 cum 0.75 cum 270.00
LABOUR
0114 Beldar 190.00 day 0.2 day 38.00
Add 5 % for water, electricity, sundries and other 15.40
overhead charges
TOTAL 308.00
Add 10 % for contractor's profit 30.80
Cost of 10 metre 338.80
Cost of one metre 33.88
Say 34.00
19.24 Providing and filling fine sand or coarser grade all-round the G.I. pipes in external work.
19.24.3 25 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost of sand filling alround 25mm dia.
pipe 10 metre long.
Width of sand filling = 300mm
Depth of sand filling
Under the pipe = 75mm+
Above the pipe = 150mm+
Max. external dia of pipe = 34.2mm
= 259.2 Say 259mm
Quantity of sand = 10x0.30x0.259 = 0.777 cum.+
= 1.43 cum.
Cost of sand filling for 10 metre pipe
MATERIAL
0254 Fine sand 360.00 cum 1.43 cum 514.80
LABOUR
0114 Beldar 190.00 day 0.35 day 66.50
Add 5 % for water, electricity, sundries and other 29.07
overhead charges
TOTAL 581.30
Add 10 % for contractor's profit 58.13
Cost of 10 metre 639.43
Cost of one metre 63.94
Say 64.00
19.24 Providing and filling fine sand or coarser grade all-round the G.I. pipes in external work.
19.24.10 150 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost of sand filling alround 150mm dia.
pipe 10 metre long.
Width of sand filling = 300mm
Depth of sand filling
Under the pipe = 75mm+
Above the pipe = 150mm+
Max. external dia of pipe = 166.5mm
= 391.50mm Say 0.392m
Quantity of sand = 10x0.60x0.392 = 2.35 cum.+
= 2.13 cum.
Labour
0107 Fitter 1st class 207.00 day 0.25 day 51.75
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 5596.75
Add 5 % for water, electricity, sundries and other 279.84
overhead charges
TOTAL 5876.59
Add 10 % for contractor's profit 587.66
Cost of 1 quintal 6464.25
Say 6464.00
19.27 Providing and laying flanged C.I. standard specials such as tees, bends, collars, tapers, caps etc., suitable for flanged
jointing as per IS : 1538 :
19.27.1 Upto 300 mm dia.
Code Description Rate Unit Qty Total
Details of cost for 1 quintal
Materials :-
1551 Flanged C.I. standard specials upto 300 mm dia 5500.00 quintal 1 quintal 5500.00
(heavy class)
LABOUR
0107 Fitter 1st class 207.00 day 0.25 day 51.75
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 5646.75
Add 5 % for water, electricity, sundries and other 282.34
overhead charges
TOTAL 5929.09
Add 10 % for contractor's profit 592.91
Cost for one quintal 6522.00
Say 6522.00
19.28 Providing and laying S&S C.I. Standard specials suitable for mechanical jointing as per IS : 13382
19.28.1 Upto 300 mm dia
Code Description Rate Unit Qty Total
Details of cost for 1 quintal
Materials :-
1571 S&S Centrifugally (Spun) C.I. Pipe specials suitable 8200.00 quintal 1 quintal 8200.00
for mechanical joint as per I.S. 13382 upto 300mm
dia
Labour
0107 Fitter 1st class 207.00 day 0.25 day 51.75
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 13846.75
Add 5 % for water, electricity, sundries and other 692.34
overhead charges
TOTAL 14539.09
Add 10 % for contractor's profit 1453.91
Cost of 1 quintal 15993.00
Say 15993.00
19.31 Providing and placing in position C.I. sluice valves category “A” (Make: Kirloskar Bros. Ltd., Indian Valve Co. (IVC),
Fouress Engineers Pvt. Ltd., WAG) (with cap) complete:
19.31.1 100 mm diameter
Labour
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 2 day 380.00
TOTAL 29687.00
Add 5 % for water, electricity, sundries and other 1484.35
overhead charges
TOTAL 31171.35
Add 10 % for contractor's profit 3117.14
Cost of 10 valves 34288.49
Cost of 1 valve 3428.84
Say 3429.00
19.31 Providing and placing in position C.I. sluice valves category “A” (Make: Kirloskar Bros. Ltd., Indian Valve Co. (IVC),
Fouress Engineers Pvt. Ltd., WAG) (with cap) complete:
19.31.2 125 mm diameter
Code Description Rate Unit Qty Total
Details of cost for 10 sluice valves
Materials :-
1622 C.I.sluice valve (with caps) 125 mm dia (Category-A) 3500.00 each 10 each 35000.00
Labour
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 2 day 380.00
TOTAL 35587.00
Add 5 % for water, electricity, sundries and other 1779.35
overhead charges
TOTAL 37366.35
Add 10 % for contractor's profit 3736.64
Cost of 10 valves 41102.99
Cost of 1 valve 4110.29
Say 4110.00
19.31 Providing and placing in position C.I. sluice valves category “A” (Make: Kirloskar Bros. Ltd., Indian Valve Co. (IVC),
Fouress Engineers Pvt. Ltd., WAG) (with cap) complete:
19.31.3 150 mm diameter
Code Description Rate Unit Qty Total
Details of cost for 10 sluice valves
Materials :-
1623 C.I.sluice valve (with caps) 150 mm dia (Category-A) 4300.00 each 10 each 43000.00
Labour
0107 Fitter 1st class 207.00 day 1.1 day 227.70
0114 Beldar 190.00 day 2.2 day 418.00
TOTAL 43645.70
Add 5 % for water, electricity, sundries and other 2182.29
overhead charges
Labour
0107 Fitter 1st class 207.00 day 1.1 day 227.70
0114 Beldar 190.00 day 2.2 day 418.00
TOTAL 92745.70
Add 5 % for water, electricity, sundries and other 4637.29
overhead charges
TOTAL 97382.99
Add 10 % for contractor's profit 9738.30
Cost of 10 valves 107121.29
Cost of 1 valve 10712.12
Say 10712.00
19.32 Providing and placing in position C.I. sluice valves category “B” (Makes / vendors other then Category "A" will be
considered in category “B”) (with cap) complete:
19.32.1 100 mm diameter
Code Description Rate Unit Qty Total
Details of cost for 10 sluice valves
Materials :-
1601 C.I.sluice valve (with caps) 100 mm dia (Category-B) 2410.00 each 10 each 24100.00
Labour
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 2 day 380.00
TOTAL 24687.00
Add 5 % for water, electricity, sundries and other 1234.35
overhead charges
TOTAL 25921.35
Add 10 % for contractor's profit 2592.14
Cost of 10 valves 28513.49
Cost of 1 valve 2851.34
Say 2851.00
19.32 Providing and placing in position C.I. sluice valves category “B” (Makes / vendors other then Category "A" will be
considered in category “B”) (with cap) complete:
19.32.2 125 mm diameter
Code Description Rate Unit Qty Total
Details of cost for 10 sluice valves
Labour
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 2 day 380.00
TOTAL 26587.00
Add 5 % for water, electricity, sundries and other 1329.35
overhead charges
TOTAL 27916.35
Add 10 % for contractor's profit 2791.64
Cost of 10 valves 30707.99
Cost of 1 valve 3070.79
Say 3071.00
19.32 Providing and placing in position C.I. sluice valves category “B” (Makes / vendors other then Category "A" will be
considered in category “B”) (with cap) complete:
19.32.3 150 mm diameter
Code Description Rate Unit Qty Total
Details of cost for 10 sluice valves
Materials :-
1603 C.I.sluice valve (with caps) 150 mm dia (Category-B) 3600.00 each 10 each 36000.00
Labour
0107 Fitter 1st class 207.00 day 1.1 day 227.70
0114 Beldar 190.00 day 2.2 day 418.00
TOTAL 36645.70
Add 5 % for water, electricity, sundries and other 1832.29
overhead charges
TOTAL 38477.99
Add 10 % for contractor's profit 3847.80
Cost of 10 valves 42325.79
Cost of 1 valve 4232.57
Say 4233.00
19.32 Providing and placing in position C.I. sluice valves category “B” (Makes / vendors other then Category "A" will be
considered in category “B”) (with cap) complete:
19.32.4 200 mm diameter
Code Description Rate Unit Qty Total
Details of cost for 10 sluice valves
Materials :-
1604 C.I.sluice valve (with caps) 200 mm dia (Category-B) 7500.00 each 10 each 75000.00
Labour
0107 Fitter 1st class 207.00 day 1.1 day 227.70
0114 Beldar 190.00 day 2.2 day 418.00
TOTAL 75645.70
Add 5 % for water, electricity, sundries and other 3782.29
overhead charges
TOTAL 79427.99
Add 10 % for contractor's profit 7942.80
1020 M.S. Bolts and nuts 16 mm dia 60 mm long 6.60 each 80 each 528.00
Labour-
0107 Fitter 1st class 207.00 day 0.5 day 103.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 966.50
Add 5 % for water, electricity, sundries and other 48.33
overhead charges
TOTAL 1014.83
Add 10 % for contractor's profit 101.48
Cost for 10 joints 1116.31
Cost for one joint 111.63
Say 112.00
19.35 Providing flanged joints to double flanged C.I./ D.I. pipes, valves and specials including rubber insertion 3mm thick,
suitable bolts and nuts and testing of joints complete:
19.35.3 125 mm diameter pipe
1021 M.S. Bolts and nuts 16 mm dia 65 mm long 8.60 each 80 each 688.00
Labour-
0107 Fitter 1st class 207.00 day 0.6 day 124.20
0114 Beldar 190.00 day 1.2 day 228.00
TOTAL 1200.20
Add 5 % for water, electricity, sundries and other 60.01
overhead charges
TOTAL 1260.21
Add 10 % for contractor's profit 126.02
Cost for 10 joints 1386.23
Cost for one joint 138.62
Say 139.00
19.35 Providing flanged joints to double flanged C.I./ D.I. pipes, valves and specials including rubber insertion 3mm thick,
suitable bolts and nuts and testing of joints complete:
19.35.4 150 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost for 10 joints
Materials :-
1724 Rubber insertions for 150 mm dia pipe joints 18.00 each 10 each 180.00
1022 M.S. Bolts and nuts 20 mm dia 65 mm long 13.45 each 80 each 1076.00
Labour-
0107 Fitter 1st class 207.00 day 0.7 day 144.90
0114 Beldar 190.00 day 1.4 day 266.00
TOTAL 1666.90
Add 5 % for water, electricity, sundries and other 83.35
overhead charges
TOTAL 1750.25
Add 10 % for contractor's profit 175.03
Cost for 10 joints 1925.28
Cost for one joint 192.52
Say 193.00
19.35 Providing flanged joints to double flanged C.I./ D.I. pipes, valves and specials including rubber insertion 3mm thick,
suitable bolts and nuts and testing of joints complete:
19.35.5 200 mm diameter pipe
Code Description Rate Unit Qty Total
Details of cost for 10 joints
Materials :-
1725 Rubber insertions for 200 mm dia pipe joints 23.00 each 10 each 230.00
1023 M.S. Bolts and nuts 20 mm dia 70 mm long 14.50 each 80 each 1160.00
Labour-
0107 Fitter 1st class 207.00 day 0.8 day 165.60
1024 M.S. Bolts and nuts 20 mm dia 75 mm long 15.50 each 120 each 1860.00
Labour-
0107 Fitter 1st class 207.00 day 0.8 day 165.60
0114 Beldar 190.00 day 1.6 day 304.00
TOTAL 2679.60
Add 5 % for water, electricity, sundries and other 133.98
overhead charges
TOTAL 2813.58
Add 10 % for contractor's profit 281.36
Cost for 10 joints 3094.94
Cost for one joint 309.49
Say 309.00
19.36 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including testing of joints and
including the cost of rubber gasket :
19.36.1 100 mm dia pipes
Code Description Rate Unit Qty Total
Details of cost for 50 Joints
Materials :-
1701 Ring rubber gaskets for S&S joint conforming to I.S 30.00 each 50 each 1500.00
5382 of S.B.R quality 100mm dia
Labour
0107 Fitter 1st class 207.00 day 2 day 414.00
0114 Beldar 190.00 day 2 day 380.00
TOTAL 2294.00
Add 5 % for water, electricity, sundries and other 114.70
overhead charges
TOTAL 2408.70
Add 10 % for contractor's profit 240.87
Cost for 50 joints 2649.57
Cost for 1 joint 52.99
Say 53.00
Labour
0107 Fitter 1st class 207.00 day 3 day 621.00
0114 Beldar 190.00 day 3 day 570.00
TOTAL 3091.00
Add 5 % for water, electricity, sundries and other 154.55
overhead charges
TOTAL 3245.55
Add 10 % for contractor's profit 324.56
Cost for 50 joints 3570.11
Cost for 1 joint 71.40
Say 71.50
19.36 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including testing of joints and
including the cost of rubber gasket :
19.36.3 200 mm dia pipes
Code Description Rate Unit Qty Total
Details of cost for 50 Joints
Materials :-
1703 Ring rubber gaskets for S&S joint conforming to I.S 66.00 each 50 each 3300.00
5382 of S.B.R quality 200mm dia
Labour
0107 Fitter 1st class 207.00 day 4 day 828.00
0114 Beldar 190.00 day 4 day 760.00
TOTAL 4888.00
Add 5 % for water, electricity, sundries and other 244.40
overhead charges
TOTAL 5132.40
Add 10 % for contractor's profit 513.24
Cost for 50 joints 5645.64
Cost for 1 joint 112.91
Say 113.00
19.36 Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes including testing of joints and
including the cost of rubber gasket :
19.36.4 250 mm dia pipes
Code Description Rate Unit Qty Total
Details of cost for 50 Joints
Materials :-
1704 Ring rubber gaskets for S&S joint conforming to I.S 78.00 each 50 each 3900.00
5382 of S.B.R quality 250mm dia
Labour
Materials:
1661 Double acting air valve 50 mm 4000.00 each 10 each 40000.00
LABOUR
0107 Fitter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.4 day 76.00
TOTAL 40117.40
Add 5 % for water, electricity, sundries and other 2005.87
overhead charges
TOTAL 42123.27
Add 10 % for contractor's profit 4212.33
Cost for 10 air valves 46335.60
Cost for 1 air valves 4633.56
Say 4634.00
19.37 Providing and placing in position C.I. double acting air valve of approved make.
19.37.2 80 mm dia
Code Description Rate Unit Qty Total
Details of cost for 10 no. double acting air vaves
Materials:
1662 Double acting air valve 80 mm 5200.00 each 10 each 52000.00
LABOUR
0107 Fitter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.4 day 76.00
TOTAL 52117.40
Add 5 % for water, electricity, sundries and other 2605.87
overhead charges
TOTAL 54723.27
Add 10 % for contractor's profit 5472.33
Cost for 10 air valves 60195.60
Cost for 1 air valves 6019.56
Say 6020.00
19.37 Providing and placing in position C.I. double acting air valve of approved make.
Materials:
1663 Double acting air valve 100 mm 6800.00 each 10 each 68000.00
LABOUR
0107 Fitter 1st class 207.00 day 0.2 day 41.40
0114 Beldar 190.00 day 0.4 day 76.00
TOTAL 68117.40
Add 5 % for water, electricity, sundries and other 3405.87
overhead charges
TOTAL 71523.27
Add 10 % for contractor's profit 7152.33
Cost for 10 air valves 78675.60
Cost for 1 air valves 7867.56
Say 7868.00
19.38 Providing and fixing enclosed type water meter (bulk type) conforming to IS : 2373 and tested by Municipal Board
complete with bolts, nuts, rubber insertions etc. (The tail pieces if required will be paid separately) :
LABOUR
0107 Fitter 1st class 207.00 day 0.8 day 165.60
0114 Beldar 190.00 day 1.6 day 304.00
TOTAL 8936.90
Add 5 % for water, electricity, sundries and other 446.85
overhead charges
TOTAL 9383.75
Add 10 % for contractor's profit 938.38
Cost for 1 water meter 10322.13
Say 10322.00
19.38 Providing and fixing enclosed type water meter (bulk type) conforming to IS : 2373 and tested by Municipal Board
complete with bolts, nuts, rubber insertions etc. (The tail pieces if required will be paid separately) :
LABOUR
0107 Fitter 1st class 207.00 day 0.8 day 165.60
0114 Beldar 190.00 day 1.6 day 304.00
TOTAL 12893.15
LABOUR
0107 Fitter 1st class 207.00 day 0.8 day 165.60
0114 Beldar 190.00 day 1.6 day 304.00
TOTAL 20426.10
Add 5 % for water, electricity, sundries and other 1021.31
overhead charges
TOTAL 21447.41
Add 10 % for contractor's profit 2144.74
Cost for 1 water meter 23592.15
Say 23592.00
19.38 Providing and fixing enclosed type water meter (bulk type) conforming to IS : 2373 and tested by Municipal Board
complete with bolts, nuts, rubber insertions etc. (The tail pieces if required will be paid separately) :
LABOUR
0107 Fitter 1st class 207.00 day 0.8 day 165.60
0114 Beldar 190.00 day 1.6 day 304.00
TOTAL 24800.85
Add 5 % for water, electricity, sundries and other 1240.04
overhead charges
TOTAL 26040.89
Add 10 % for contractor's profit 2604.09
Cost for 1 water meter 28644.98
Say 28645.00
19.39 Providing and fixing C.I. dirt box strainer for bulk type water meter with nuts, bolts, rubber insertions etc. complete
conforming to IS : 2373 :
19.39.1 80 mm dia
Code Description Rate Unit Qty Total
Details of cost for on no. dirt box strainer
MATERIALS
3608 Fuel wood 450.00 quintal 0.373 quintal 167.85
3501 Kerosene oil 30.00 litre 0.379 litre 11.37
LABOUR
0108 Fitter 2nd class 197.00 day 0.5 day 98.50
0114 Beldar 190.00 day 4 day 760.00
TOTAL 5107.71
Add 5 % for water, electricity, sundries and other 51.89
overhead charges on all except (A) i.e. on (5107.71
- 4069.99) = 1037.72
TOTAL 5159.60
Add 10 % for contractor's profit on all except (A) 108.96
i.e. on (5159.60 - 4069.99) = 1089.61
MATERIALS
3608 Fuel wood 450.00 quintal 0.466 quintal 209.70
3501 Kerosene oil 30.00 litre 0.379 litre 11.37
LABOUR
0108 Fitter 2nd class 197.00 day 0.75 day 147.75
0114 Beldar 190.00 day 4.5 day 855.00
TOTAL 5258.88
Add 5 % for water, electricity, sundries and other 61.19
overhead charges on all except (A) i.e. on (5258.88
- 4035.06) = 1223.82
TOTAL 5320.07
Add 10 % for contractor's profit on all except (A) 128.50
i.e. on (5320.07 - 4035.06) = 1285.01
TOTAL 5448.34
Add 10 % for contractor's profit on all except (A) 146.57
i.e. on (5448.34 - 3982.66) = 1465.68
MATERIALS
3608 Fuel wood 450.00 quintal 0.653 quintal 293.85
3501 Kerosene oil 30.00 litre 0.568 litre 17.04
LABOUR
0108 Fitter 2nd class 197.00 day 1 day 197.00
0114 Beldar 190.00 day 5.5 day 1045.00
TOTAL 5470.67
Add 5 % for water, electricity, sundries and other 77.64
overhead charges on all except (A) i.e. on (5470.67
- 3917.78) = 1552.89
TOTAL 5548.31
Add 10 % for contractor's profit on all except (A) 163.05
i.e. on (5548.31 - 3917.78) = 1630.53
MATERIALS
3608 Fuel wood 450.00 quintal 0.84 quintal 378.00
3501 Kerosene oil 30.00 litre 0.7576 litre 22.73
LABOUR
0108 Fitter 2nd class 197.00 day 1.25 day 246.25
0114 Beldar 190.00 day 6.5 day 1235.00
TOTAL 6014.36
Add 5 % for water, electricity, sundries and other 94.10
overhead charges on all except (A) i.e. on (6014.36
- 4132.38) = 1881.98
TOTAL 6108.46
Add 10 % for contractor's profit on all except (A) 197.61
i.e. on (6108.46 - 4132.38) = 1976.08
TOTAL 1211.46
Add 10 % for contractor's profit on all except (A) 38.62
i.e. on (1211.46 - 825.27) = 386.19
TOTAL 870.99
Add 10 % for contractor's profit on all except (A) 70.87
i.e. on (870.99 - 162.34) = 708.65
Cost for 10 holes 941.86
Cost for 1 hole 94.18
Say 94.00
19.45 Making chases upto 7.5x7.5 cm in walls including making good and finishing with matching surface after housing
G.I. pipe etc.
Code Description Rate Unit Qty Total
Details of cost for 10 metres
MATERIAL
TOTAL 426.99
Add 10 % for contractor's profit on all except (A) 30.82
i.e. on (426.99 - 118.81) = 308.18
Cost for 10 metre 457.81
Cost for 1 metre 45.78
Say 46.00
19.46 Making hole upto 20x20 cm and embedding pipes upto 150 mm diameter in masonry and filling with cement
concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) including disposal of
malba.
TOTAL 675.22
Add 10 % for contractor's profit on all except (A) 2.17
i.e. on (675.22 - 653.48) = 21.74
Cost for 10 metre 677.39
Cost for 1 metre 67.73
Say 67.50
3.1.0.1 Cement concrete 1:5:10 (stone aggregate 20mm) 2409.03 cum 0.04 cum 96.36
(Rate as per Item No 3.1.1)
(iii) Second class brick work in cement mortar 1:4
(1 Cement : 4 coarse sand) in foundations and
plinth
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.075 cum 300.75
per item No 7.1.2)
(iv) 12mm cement plaster 1:3 (1 Cement : 3 Coarse
sand) finished with a floating coat of neat cement.
1.20x0.50=0.60sqm.
0.30x0.30=0.09sqm.
=0.69sqm. Say 0.70sqm.
11.2.0.2 12mm plaster with CM 1:4 (Rate as per Item No 102.93 sqm 0.7 sqm 72.05
11.2.2)
11.5 Neat cement punning (Rate as per Item No 11.5) 33.13 sqm 0.7 sqm 23.19
2421 Surface box for stop cock 100.00 each 1 each 100.00
(vii) Cement concrete 1:2:4 (1 Cement : 2 Coarse
sand ; 4 graded stone aggregate 20mm nominal
size)
TOTAL 743.26
3.32mx0.19mx0.75m=0.473cum.
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.473 cum 1896.74
per item No 7.1.2)
(iv) 12mm cement plaster 1:3 (1 Cement : 3 Coarse
sand) finished with a floating coat of neat cement.
2.40x0.75=1.80sqm.
0.60x0.60=0.36sqm.
=2.16sqm.
11.2.0.2 12mm plaster with CM 1:4 (Rate as per Item No 102.93 sqm 2.16 sqm 222.33
11.2.2)
11.5 Neat cement punning (Rate as per Item No 11.5) 33.13 sqm 2.16 sqm 71.56
2422 Surface box for sluice valve 185.00 each 1 each 185.00
(vii) Cement concrete 1:2:4 (1 Cement : 2 Coarse
sand ; 4 graded stone aggregate 20mm nominal
size)
0.165cum.x80kg/cum. = 13.2kg.
3.12.0.4 MS reinforcement (Rate as per Item No 3.13.4) 53.65 kg 13.2 kg 708.18
TOTAL 4624.91
Add 10 % for contractor's profit on all except (A) 19.43
i.e. on (4624.91 - 4430.66) = 194.25
= 2.85cum.
1.1.0.1 Excavation in all kind of soft soil (Rate as per item 184.59 cum 2.85 cum 526.08
no 1.1.1)
1.17 Fillig excavated soft soil (Rate as per item no 1.17) 64.95 cum 2.85 cum 185.11
4.52mx0.19mx1.00m= 0.86cum.
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.86 cum 3448.62
per item No 7.1.2)
(iv) 12mm cement plaster 1:3 (1 Cement : 3 Coarse
sand) finished with a floating coat of neat cement.
3.60mx1.00m=3.60sqm.
0.90mx0.90m=0.81sqm.
=4.41sqm.
2422 Surface box for sluice valve 185.00 each 1 each 185.00
(vii) Cement concrete 1:2:4 (1 Cement : 2 Coarse
sand ; 4 graded stone aggregate 20mm nominal
size)
TOTAL 7993.76
Add 10 % for contractor's profit on all except (A) 19.43
i.e. on (7993.76 - 7799.51) = 194.25
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 1.087 cum 4358.89
per item No 7.1.2)
(iv) 12mm cement plaster 1:3 (1 Cement : 3 Coarse
sand) finished with a floating coat of neat cement.
4.80mx1.00m=4.80sqm.
1.20mx1.20m=1.44sqm.
=6.42sqm.
11.2.0.2 12mm plaster with CM 1:4 (Rate as per Item No 102.93 sqm 6.42 sqm 660.81
11.2.2)
11.5 Neat cement punning (Rate as per Item No 11.5) 33.13 sqm 6.42 sqm 212.69
2422 Surface box for sluice valve 185.00 each 1 each 185.00
(vii) Cement concrete 1:2:4 (1 Cement : 2 Coarse
sand ; 4 graded stone aggregate 20mm nominal
size)
TOTAL 11001.91
Add 10 % for contractor's profit on all except (A) 19.43
i.e. on (11001.91 - 10807.66) = 194.25
3.32mx0.19mx0.75m=0.473cum
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.473 cum 1896.74
per item No 7.1.2)
(iv) 12mm cement plaster 1:3 (1 Cement : 3 Coarse
sand) finished with a floating coat of neat cement.
2.40mx0.75m=1.80sqm.
0.90mx0.90m=0.36sqm.
=2.16sqm.
11.2.0.2 12mm plaster with CM 1:4 (Rate as per Item No 102.93 sqm 2.16 sqm 222.33
11.2.2)
11.5 Neat cement punning (Rate as per Item No 11.5) 33.13 sqm 2.16 sqm 71.56
2422 Surface box for sluice valve 185.00 each 1 each 185.00
(vii) Cement concrete 1:2:4 (1 Cement : 2 Coarse
sand ; 4 graded stone aggregate 20mm nominal
size)
0.131cumx80kg/cum. = 10.48kg.
3.12.0.4 MS reinforcement (Rate as per Item No 3.13.4) 53.65 kg 10.48 kg 562.25
TOTAL 4336.91
Add 10 % for contractor's profit on all except (A) 19.43
i.e. on (4336.91 - 4142.66) = 194.25
= 1.09cum.
1.1.0.1 Excavation in all kind of soft soil (Rate as per item 184.59 cum 1.09 cum 201.20
no 1.1.1)
1.17 Fillig excavated soft soil (Rate as per item no 1.17) 64.95 cum 1.09 cum 70.80
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.287 cum 1150.88
per item No 7.1.2)
(iv) 12mm cement plaster 1:3 (1 Cement : 3 Coarse
sand) finished with a floating coat of neat cement.
2.10mx0.50m=1.05sqm.
0.60mx0.45m=0.27sqm.
=1.32sqm.
11.2.0.2 12mm plaster with CM 1:4 (Rate as per Item No 102.93 sqm 1.32 sqm 135.87
11.2.2)
11.5 Neat cement punning (Rate as per Item No 11.5) 33.13 sqm 1.32 sqm 43.73
2423 Surface box for water meter 205.00 each 1 each 205.00
TOTAL 4111.79
Add 10 % for contractor's profit on all except (A) 21.53
i.e. on (4111.79 - 3896.54) = 215.25
3.1.0.1 Cement concrete 1:5:10 (stone aggregate 20mm) 2409.03 cum 1.48 cum 3565.36
(Rate as per Item No 3.1.1)
Total 3565.36
Add 5 % for water, electricity, sundries and other 0.00
overhead charges on all except (A) i.e. on (3565.36
- 3565.36) = 0.00
3.1.0.1 Cement concrete 1:5:10 (stone aggregate 20mm) 2409.03 cum 1.81 cum 4360.34
(Rate as per Item No 3.1.1)
Total 4360.34
Add 5 % for water, electricity, sundries and other 0.00
overhead charges on all except (A) i.e. on (4360.34
- 4360.34) = 0.00
3.1.0.1 Cement concrete 1:5:10 (stone aggregate 20mm) 2409.03 cum 2.11 cum 5083.05
(Rate as per Item No 3.1.1)
Total 5083.05
Add 5 % for water, electricity, sundries and other 0.00
overhead charges on all except (A) i.e. on (5083.05
- 5083.05) = 0.00
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.13 cum 521.30
per item No 7.1.2)
Cement concrete 1:2:4 ( 1 cement : 2 coarse sand :
4 graded stone aggregate 20 mm nominal size)
11.2.0.2 12mm plaster with CM 1:4 (Rate as per Item No 102.93 sqm 0.29 sqm 29.85
11.2.2)
TOTAL 1266.38
Add 5 % for water, electricity, sundries and other 23.50
overhead charges on all except (A) i.e. on (1266.38
- 796.38) = 470.00
TOTAL 1289.88
Add 10 % for contractor's profit on all except (A) 49.35
i.e. on (1289.88 - 796.38) = 493.50
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.13 cum 521.30
per item No 7.1.2)
Cement concrete 1:2:4 ( 1 cement : 2 coarse sand :
4 graded stone aggregate 20 mm nominal size)
11.2.0.2 12mm plaster with CM 1:4 (Rate as per Item No 102.93 sqm 0.3 sqm 30.88
11.2.2)
TOTAL 1313.32
Add 5 % for water, electricity, sundries and other 27.00
overhead charges on all except (A) i.e. on (1313.32
- 773.32) = 540.00
TOTAL 1340.32
Add 10 % for contractor's profit on all except (A) 56.70
i.e. on (1340.32 - 773.32) = 567.00
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.13 cum 521.30
per item No 7.1.2)
11.2.0.2 12mm plaster with CM 1:4 (Rate as per Item No 102.93 sqm 0.16 sqm 16.47
11.2.2)
TOTAL 1403.91
Add 5 % for water, electricity, sundries and other 32.25
overhead charges on all except (A) i.e. on (1403.91
- 758.91) = 645.00
TOTAL 1436.16
Add 10 % for contractor's profit on all except (A) 67.73
i.e. on (1436.16 - 758.91) = 677.25
LABOUR
0107 Fitter 1st class 207.00 day 0.4 day 82.80
0114 Beldar 190.00 day 0.4 day 76.00
TOTAL 3158.80
Add 0.25% for jointing of pipes 7.90
Add 5 % for water, electricity, sundries and other 158.34
overhead charges
TOTAL 3325.04
Add 10 % for contractor's profit 332.50
Cost for 10 metre 3657.54
Cost for 1 metre 365.75
Say 366.00
20.6 Providing, lowering, laying, aligning, fixing in position at and jointing at all level/ depths ISI marked HDPE pipes of
PE-100 grade and PN 6 for sewer application as per IS 14333-1996 (amended upto date) in trenches in complete
including all material, labour, testing and commissioning as per direction of Engineer._x000D_
Note : E/w to be measured and paid separately.
LABOUR
LABOUR
0107 Fitter 1st class 207.00 day 0.4 day 82.80
0114 Beldar 190.00 day 0.4 day 76.00
TOTAL 10058.80
Add 0.25% for jointing of pipes 25.15
Add 5 % for water, electricity, sundries and other 504.20
overhead charges
TOTAL 10588.15
Add 10 % for contractor's profit 1058.82
Cost for 10 metre 11646.97
Cost for 1 metre 1164.69
Say 1165.00
20.7 Constructing brick masonry manhole with well burnt modular clay bricks crushing strength not less than 35kg/cm2
in cement mortar 1:4 ( 1 cement : 4 coarse sand), R.C.C. top slab with 1:2:4 mix (1 cement : 2 coarse sand : 4 graded
stone aggregate 20 mm nominal size), foundation in cement concrete 1:4:8 mix (1 cement : 4 coarse sand : 8 graded
stone aggregate 40mm nominal size) inside plastering 12mm thick with cement mortar 1:3 (1 cement : 3 coarse
sand) finished with floating coat of neat cement and making channels in cement concrete 1:2:4 (1 cement : 2 coarse
sand : 4 graded stone aggregate 20mm nominal size) finished with a floating coat of neat cement complete as per
standard design :
20.7.1 Inside size 90x80 cm and 45 cm deep including C.I. cover with frame (light duty) 455x610 mm internal dimensions
total weight of cover and frame to be not less than 38 kg (weight of cover 23 kg and weight of frame 15 kg) :
3.1.0.2 Cement concrete 1:4:8 (stone aggregate 20mm) 2658.51 cum 0.43 cum 1143.16
(Rate as per Item No 3.1.2)
Brick work with bricks of class designation 75 in
foundation & plinth in cement mortar 1:4 (1
cement : 4 coarse sand)
=0.280cum
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.28 cum 1122.81
per item No 7.1.2)
Cement concrete 1:2:4 (1 cement : 2 coarse sand :
4 graded stone aggregate 20 mm nominal size) for
benching
LABOUR
Extra labour for making channel :
0102 Mason 1st class 207.00 day 0.1 day 20.70
2221 C.I. Rectangular cover 455x610 mm with frame 1710.00 each 1 each 1710.00
(low duty) 38 kg
TOTAL 6435.11
Add 5 % for water, electricity, sundries and other 86.54
overhead charges on all except (A) i.e. on (6435.11
- 4704.41) = 1730.70
TOTAL 6521.65
Add 10 % for contractor's profit on all except (A) 181.72
i.e. on (6521.65 - 4704.41) = 1817.24
20.7.2 Inside size 120x90 cm and 90 cm deep including C.I. cover with frame (medium duty) 500 mm internal diameter,
total weight of cover and frame to be not less than 116 kg (weight of cover 58 kg and weight of frame 58 kg) :
3.1.0.2 Cement concrete 1:4:8 (stone aggregate 20mm) 2658.51 cum 0.55 cum 1462.18
(Rate as per Item No 3.1.2)
Brick work with bricks of class designation 75 in
foundation & plinth in cement mortar 1:4 (1
cement : 4 coarse sand)
= 0.771 cum
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.771 cum 3091.73
per item No 7.1.2)
Cement concrete 1:2:4 (1 cement : 2 coarse sand :
4 graded stone aggregate 20 mm nominal size) for
benching
LABOUR
Extra labour for making channel :
0102 Mason 1st class 207.00 day 0.15 day 31.05
2223 C.I. 500 mm dia cover with frame (medium duty) 5220.00 each 1 each 5220.00
116 kg
TOTAL 13634.48
Add 5 % for water, electricity, sundries and other 262.55
overhead charges on all except (A) i.e. on
(13634.48 - 8383.43) = 5251.05
TOTAL 13897.03
Add 10 % for contractor's profit on all except (A) 551.36
i.e. on (13897.03 - 8383.43) = 5513.60
20.7.3 Inside size 120x90 cm and 90 cm deep including C.I. cover with frame (heavy duty) 560 mm internal diameter, total
weight of cover and frame to be not less than 208 kg (weight of cover 108 kg and weight of frame 100 kg) :
3.1.0.2 Cement concrete 1:4:8 (stone aggregate 20mm) 2658.51 cum 0.55 cum 1462.18
(Rate as per Item No 3.1.2)
Brick work with bricks of class designation 75 in
foundation & plinth in cement mortar 1:4 (1
cement : 4 coarse sand)
11.5 Neat cement punning (Rate as per Item No 11.5) 33.13 sqm 2.41 sqm 79.84
LABOUR
Extra labour for making channel :
0102 Mason 1st class 207.00 day 0.15 day 31.05
2225 C.I. 560 mm dia cover with frame (Heavy duty) 208 9360.00 each 1 each 9360.00
KG
TOTAL 17521.67
Add 5 % for water, electricity, sundries and other 469.55
overhead charges on all except (A) i.e. on
(17521.67 - 8130.62) = 9391.05
TOTAL 17991.22
Add 10 % for contractor's profit on all except (A) 986.06
i.e. on (17991.22 - 8130.62) = 9860.60
20.7.4 Inside size 90x80 cm and 45 cm deep including RCC cover with frame 450x600 mm internal dimensions.
3.1.0.2 Cement concrete 1:4:8 (stone aggregate 20mm) 2658.51 cum 0.43 cum 1143.16
(Rate as per Item No 3.1.2)
Brick work with bricks of class designation 75 in
foundation & plinth in cement mortar 1:4 (1
cement : 4 coarse sand)
=0.280cum
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.28 cum 1122.81
per item No 7.1.2)
Cement concrete 1:2:4 (1 cement : 2 coarse sand :
4 graded stone aggregate 20 mm nominal size) for
benching
LABOUR
Extra labour for making channel :
0102 Mason 1st class 207.00 day 0.1 day 20.70
2231 Rectangular shape 600x450 mm precast R.C.C. 750.00 each 1 each 750.00
manhole cover with frame - L.D. - 25
TOTAL 5475.11
Add 5 % for water, electricity, sundries and other 38.54
overhead charges on all except (A) i.e. on (5475.11
- 4704.41) = 770.70
TOTAL 5513.65
Add 10 % for contractor's profit on all except (A) 80.92
i.e. on (5513.65 - 4704.41) = 809.24
20.7.5 Inside size 120x90 cm and 90 cm deep including RCC cover with frame 500 mm internal diameter.
Code Description Rate Unit Qty Total
Details of cost for 1 manhole
MATERIALS
Cement concrete 1:4:8 (1 cement : 4 coarse sand :
8 graded stone aggregate 40 mm nominal size)
3.1.0.2 Cement concrete 1:4:8 (stone aggregate 20mm) 2658.51 cum 0.55 cum 1462.18
(Rate as per Item No 3.1.2)
Brick work with bricks of class designation 75 in
foundation & plinth in cement mortar 1:4 (1
cement : 4 coarse sand)
= 0.771 cum
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.771 cum 3091.73
per item No 7.1.2)
Cement concrete 1:2:4 (1 cement : 2 coarse sand :
4 graded stone aggregate 20 mm nominal size) for
benching
LABOUR
Extra labour for making channel :
0102 Mason 1st class 207.00 day 0.15 day 31.05
2235 Circular shape 500 mm dia precast R.C.C. manhole 660.00 each 1 each 660.00
cover with frame - M.D. - 10
TOTAL 9074.48
Add 5 % for water, electricity, sundries and other 34.55
overhead charges on all except (A) i.e. on (9074.48
- 8383.43) = 691.05
TOTAL 9109.03
Add 10 % for contractor's profit on all except (A) 72.56
i.e. on (9109.03 - 8383.43) = 725.60
TOTAL 3754.83
Add 5 % for water, electricity, sundries and other 0.00
overhead charges on all except (A) i.e. on (3754.83
- 3754.83) = 0.00
TOTAL 4473.21
Add 5 % for water, electricity, sundries and other 0.00
overhead charges on all except (A) i.e. on (4473.21
- 4473.21) = 0.00
Curved on plan
3.14x1.14x0.074x0.19 = 0.050
3.14x(1.14+0.79)/2x0.711x0.19 = 0.409
= 0.459
Deduct arch ring and portion of pipe
2x½x3.14x0.25mx0.19x0.10 m = 0.014 cum
2x0.25x3.14x0.15x0.15x0.19 = 0.006 cum
= 0.020 cum
Net quantity 0.459-0.020 = 0.439 Say
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.44 cum 1764.41
per item No 7.1.2)
Brick work in arches with 75 class designation brick
in cement mortar 1:3 ( 1 cement : 3 fine sand )
For benching :
3.14/4x(0.91+0.82)2x0.23 (average depth) =0.135
cum
Less pipe : 0.91x3.14/4x(0.15)2 = (-) 0.016 cum
LABOUR
Extra labour for making channel :
0102 Mason 1st class 207.00 day 0.1 day 20.70
2236 Circular shape 560 mm dia SFRC manhole cover 1100.00 each 1 each 1100.00
with frame - H.D. - 20
TOTAL 5796.59
Add 5 % for water, electricity, sundries and other 56.04
overhead charges on all except (A) i.e. on (5796.59
- 4675.89) = 1120.70
TOTAL 5852.63
Add 10 % for contractor's profit on all except (A) 117.67
i.e. on (5852.63 - 4675.89) = 1176.74
3.14x(0.91+0.19)x0.19x0.76=0.50
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.5 cum 2005.01
per item No 7.1.2)
Cement concrete 1:2:4 (1 cement : 2 coarse sand :
4 graded stone 20mm nominal size)
12mm cement plaster 1:3 (1 cement : 3 coarse
sand)
3.14x0.91x0.76=2.17
11.2.0.2 12mm plaster with CM 1:4 (Rate as per Item No 102.93 sqm 2.17 sqm 223.36
11.2.2)
Total 2300.26
Add 5 % for water, electricity, sundries and other 0.00
overhead charges on all except (A) i.e. on (2300.26
- 2300.26) = 0.00
TOTAL 153.95
Add 10 % for contractor's profit on all except (A) 14.21
i.e. on (153.95 - 11.88) = 142.07
Cost for 1 no. 168.16
Say 168.00
20.11 Providing M.S. foot rests including fixing in manholes with 20x20x10 cm cement concrete blocks 1:3:6 (1 cement : 3
coarse sand : 6 graded stone aggregate 20 mm nominal size) as per standard design:
20.11.2 With 20 mm diameter round bar
Code Description Rate Unit Qty Total
Details of cost for one M.S foot rests
MATERIALS
+ 5% wastage = 0.019 q
1002 Mild steel round bar above 12 mm dia 4013.00 quintal 0.019 quintal 76.25
Cement concrete 1:3:6 ( 1 cement : 3 coarse sand :
6 graded stone aggregate 20 mm nominal size)
TOTAL 123.65
Add 10 % for contractor's profit on all except (A) 11.18
i.e. on (123.65 - 11.88) = 111.77
Cost for 1 no. 134.83
Say 135.00
20.12 Providing orange colour safety foot rest of minimum 6 mm thick plastic encapsulated as per IS : 10910 on 12mm dia
steel bar conforming to IS : 1786 having minimum cross section as 23 mmx25mm and over all minimum length 263
mm and width as 165mm with minimum 112 mm space between protruded legs having 2 mm tread on top surface
by ribbing or chequering besides necessary and adequate anchoring projections on tail length on 138 mm as per
standard drawing and suitable to with stand the bend test and chemical resistance test as per specifications and
having manufacture's permanent identification mark to be visible even after fixing, including fixing in manholes
with 30x20x15 cm cement concrete block 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal
size) complete as per design.
TOTAL 157.82
Add 10 % for contractor's profit on all except (A) 13.11
i.e. on (157.82 - 26.73) = 131.09
Cost for 1 no. 170.93
Say 171.00
20.13 Replacement of M.S. foot rests in manholes including dismantling concrete blocks and fixing with 20x20x10 cm
cement concrete blocks 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) :
TOTAL 204.71
Add 10 % for contractor's profit on all except (A) 19.28
i.e. on (204.71 - 11.88) = 192.83
Cost for 1 no. 223.99
Say 224.00
20.13 Replacement of M.S. foot rests in manholes including dismantling concrete blocks and fixing with 20x20x10 cm
cement concrete blocks 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) :
TOTAL 174.42
Add 10 % for contractor's profit on all except (A) 16.25
i.e. on (174.42 - 11.88) = 162.54
Cost for 1 no. 190.67
Say 191.00
20.14 Supplying and fixing C.I. cover without frame for manholes :
TOTAL 950.42
Add 10 % for contractor's profit on all except (A) 80.83
i.e. on (950.42 - 142.08) = 808.34
Cost for 1 no. 1031.25
Say 1031.00
20.15 Providing and fixing in position precast R.C.C. manhole cover and frame L D- 2.5 of required shape and approved
quality
20.15.2 Square shape 450mm internal dimensions
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
2232 Square shape 450x450 mm precast R.C.C. manhole 650.00 each 1 each 650.00
cover with frame - L.D. - 25
Cement concrete 1:2:4 ( 1 cement : 2 coarse sand :
4 grade stone aggregate 20 mm nominal size )
TOTAL 809.90
Add 10 % for contractor's profit on all except (A) 70.33
i.e. on (809.90 - 106.56) = 703.34
Cost for 1 no. 880.23
Say 880.00
20.15 Providing and fixing in position precast R.C.C. manhole cover and frame L D- 2.5 of required shape and approved
quality
20.15.3 Circular shape 450mm internal diameter
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
2233 Circular shape 450 mm dia precast R.C.C. manhole 570.00 each 1 each 570.00
cover with frame - L.D. - 25
Cement concrete 1:2:4 ( 1 cement : 2 coarse sand :
4 grade stone aggregate 20 mm nominal size )
TOTAL 725.90
Add 10 % for contractor's profit on all except (A) 61.93
i.e. on (725.90 - 106.56) = 619.34
Cost for 1 no. 787.83
Say 788.00
20.16 Providing and fixing in position precast R.C.C. manhole cover and frame M D- 10 of required shape and approved
quality
20.16.1 Square shape 450mm internal dimension
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
2234 Rectangular shape 500x500 mm precast R.C.C. 690.00 each 1 each 690.00
manhole cover with frame - M.D. - 10
Cement concrete 1:2:4 ( 1 cement : 2 coarse sand :
4 grade stone aggregate 20 mm nominal size )
TOTAL 891.59
Add 10 % for contractor's profit on all except (A) 74.95
i.e. on (891.59 - 142.08) = 749.51
Cost for 1 no. 966.54
Say 967.00
20.16 Providing and fixing in position precast R.C.C. manhole cover and frame M D- 10 of required shape and approved
quality
20.16.2 Circular shape 500mm internal diameter
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
2235 Circular shape 500 mm dia precast R.C.C. manhole 660.00 each 1 each 660.00
cover with frame - M.D. - 10
Cement concrete 1:2:4 ( 1 cement : 2 coarse sand :
4 grade stone aggregate 20 mm nominal size )
TOTAL 824.57
Add 10 % for contractor's profit on all except (A) 71.80
i.e. on (824.57 - 106.56) = 718.01
Cost for 1 no. 896.37
Say 896.00
20.17 Providing and fixing in position precast circular 560mm internal dia SFRC/ R.C.C. manhole cover or cover and frame
of approved quality:
20.17.1 Cover and frame H D - 20
Code Description Rate Unit Qty Total
Details of cost for one no.
MATERIALS
TOTAL 1317.45
Add 10 % for contractor's profit on all except (A) 119.67
i.e. on (1317.45 - 120.76) = 1196.69
TOTAL 1434.50
Add 10 % for contractor's profit on all except (A) 132.79
i.e. on (1434.50 - 106.56) = 1327.94
2x0.35x0.35 =0.25
11.2.0.2 12mm plaster with CM 1:4 (Rate as per Item No 102.93 sqm 0.25 sqm 25.73
11.2.2)
11.5 Neat cement punning (Rate as per Item No 11.5) 33.13 sqm 0.25 sqm 8.28
LABOUR
(For cutting holes average size 30x30 cm in 23 cm
thick wall and making channel etc.)
0102 Mason 1st class 207.00 day 0.3 day 62.10
0114 Beldar 190.00 day 0.3 day 57.00
TOTAL 188.63
Add 5 % for water, electricity, sundries and other 5.96
overhead charges on all except (A) i.e. on (188.63 -
69.53) = 119.10
TOTAL 194.59
Add 10 % for contractor's profit on all except (A) 12.51
i.e. on (194.59 - 69.53) = 125.06
Cost for 1 connection 207.10
Say 207.00
20.19 Making connection of drain or sewer line with existing manhole including breaking into and making good the walls,
floors with cement concrete 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
cement plastered on both sides with cement mortar 1:3 (1 cement : 3 coarse sand) finished with a floating coat of
neat cement and making necessary channels for the drain etc. complete :
2x0.40x0.40 =0.32
11.2.0.2 12mm plaster with CM 1:4 (Rate as per Item No 102.93 sqm 0.32 sqm 32.94
11.2.2)
11.5 Neat cement punning (Rate as per Item No 11.5) 33.13 sqm 0.32 sqm 10.60
LABOUR
(For cutting holes average size 30x30 cm in 23 cm
thick wall and making channel etc.)
0102 Mason 1st class 207.00 day 0.3 day 62.10
0114 Beldar 190.00 day 0.3 day 57.00
TOTAL 198.16
Add 5 % for water, electricity, sundries and other 5.96
overhead charges on all except (A) i.e. on (198.16 -
79.06) = 119.10
TOTAL 204.12
Add 10 % for contractor's profit on all except (A) 12.51
i.e. on (204.12 - 79.06) = 125.06
Cost for 1 connection 216.63
Say 217.00
20.19 Making connection of drain or sewer line with existing manhole including breaking into and making good the walls,
floors with cement concrete 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
cement plastered on both sides with cement mortar 1:3 (1 cement : 3 coarse sand) finished with a floating coat of
neat cement and making necessary channels for the drain etc. complete :
= 0.0173 cum
3.1.0.4 Cement concrete 1:2:4 (stone aggregate 20mm) 3551.90 cum 0.17 cum 603.82
(Rate as per Item No 3.1.4)
12 mm cement plater 1:3 ( 1 cement : 3 coarse
sand ) finished with a floating coat of neat cement
LABOUR
(For cutting holes average size 50x50 cm in 23 cm
thick wall and making channel etc.)
0102 Mason 1st class 207.00 day 0.45 day 93.15
0114 Beldar 190.00 day 0.45 day 85.50
TOTAL 864.11
Add 5 % for water, electricity, sundries and other 8.93
overhead charges on all except (A) i.e. on (864.11 -
685.46) = 178.65
TOTAL 873.04
Add 10 % for contractor's profit on all except (A) 18.76
i.e. on (873.04 - 685.46) = 187.58
Cost for 1 connection 891.80
Say 892.00
20.20 Providing sand cast iron drop connection externally for 60 cm drop from branch sewer line to main sewer manhole
including inspection and cleaning eye with chain and lid, sand cast iron drop pipe and bend encased all-round with
cement concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size) with all centring
and shuttering required, cutting holes in walls and making good with brick work in cement mortar 1:4 (1 cement : 4
coarse sand) plastered with cement mortar 1:3 (1 cement : 3 coarse sand) on inside of the manhole wall lead
caulked joints between sand cast iron pipes and fittings, stiff cement mortar 1:1 (1 cement : 1 fine sand) joints
between sand cast iron tee and S.W. pipe, making required channels complete as per standard design and
specifications :
= 0.007 cum
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.007 cum 28.07
per item No 7.1.2)
Cement concrete 1:5:10 (1 cement : 5 fine sand :
10 graded stone aggregate 40 mm nominal size)
TOTAL 3967.14
Add 10 % for contractor's profit on all except (A) 310.70
i.e. on (3967.14 - 860.14) = 3107.00
2444 Clearing eye with chain and lid 150 mm dia 50.00 each 1 each 50.00
1306 S.C.I. plain bend 100mm dia as per IS: 1729 275.80 each 1 each 275.80
1304 S.C.I. Tee 150 mm as per IS: 1729 940.80 each 1 each 940.80
Brick work in cement mortar 1:4 (1 cement : 4
coarse sand)
0.20x0.20x0.19 = 0.008 cum
Less pipe 0.25x3.14x0.15x0.15x0.19=0.003 cum
= 0.005 cum
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.005 cum 20.05
per item No 7.1.2)
Cement concrete 1:5:10 (1 cement : 5 fine sand :
10 graded stone aggregate 40 mm nominal size)
TOTAL 6004.14
Add 10 % for contractor's profit on all except (A) 490.85
i.e. on (6004.14 - 1095.68) = 4908.46
TOTAL 1359.34
TOTAL 2084.43
Add 10 % for contractor's profit on all except (A) 126.15
i.e. on (2084.43 - 822.98) = 1261.45
16.43.0.1 Demolition of C.C 1:3:6 or richer (Rate as per Item 329.18 cum 0.43 cum 141.55
16.43.1)
Dismantling of secon class brick work in cement
mortar 1:4 (1 cement : 4 coarse sand)
LABOUR
0114 Beldar 190.00 day 0.08 day 15.20
TOTAL 487.51
Add 5 % for water, electricity, sundries and other 0.76
overhead charges on all except (A) i.e. on (487.51 -
472.31) = 15.20
TOTAL 488.27
Add 10 % for contractor's profit on all except (A) 1.60
i.e. on (488.27 - 472.31) = 15.96
Cost of one no 489.87
Say 490.00
20.22 Dismantling of manhole including R.C.C. top slab, C.I. cover with frame including stacking of useful materials near
the site and disposal of unserviceable materials into municipal dumps within 50 m lead :
16.43.0.1 Demolition of C.C 1:3:6 or richer (Rate as per Item 329.18 cum 0.55 cum 181.05
16.43.1)
Dismantling of secon class brick work in cement
mortar 1:4 (1 cement : 4 coarse sand)
LABOUR
0114 Beldar 190.00 day 0.08 day 15.20
TOTAL 774.81
Add 5 % for water, electricity, sundries and other 0.76
overhead charges on all except (A) i.e. on (774.81 -
759.61) = 15.20
TOTAL 775.57
Add 10 % for contractor's profit on all except (A) 1.60
i.e. on (775.57 - 759.61) = 15.96
Cost of one no 777.17
Say 777.00
20.22 Dismantling of manhole including R.C.C. top slab, C.I. cover with frame including stacking of useful materials near
the site and disposal of unserviceable materials into municipal dumps within 50 m lead :
= 0.290 cum
16.43.0.2 Demolition of C.C 1:3:6 or richer (Rate as per Item 548.63 cum 0.29 cum 159.10
16.43.2)
Dismantling of R.C.C slab of 1:2:4 (1 cement : 2
coarse sand : 4 grade stone aggregate 20 mm
nominal size)
LABOUR
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 1181.52
Add 5 % for water, electricity, sundries and other 1.90
overhead charges on all except (A) i.e. on (1181.52
- 1143.52) = 38.00
TOTAL 1183.42
Add 10 % for contractor's profit on all except (A) 3.99
i.e. on (1183.42 - 1143.52) = 39.90
16.43.0.2 Demolition of C.C 1:3:6 or richer (Rate as per Item 548.63 cum 1.18 cum 647.38
16.43.2)
Dismantling of second class brick work in cement
mortar 1:4 (1 cement : 4 coarse sand 8 )
Curved on plan
3.14x1.45x0.24x0.19 = 0.207
3.14x(1.45+0.79)/2x1.32x0.19 = 0.883
= 1.09
Duduct portion of pipe
2x3.14/4x(0.15)2x0.19 = 0.006 cum
Net quantity 1.09-0.006 = 1.084 cum Say 1.31 cum
16.3.0.3 Demolition of Brick work in CM (Rate as per Item 263.34 cum 1.084 cum 285.46
16.3.3)
Dismantaling cement concrete 1:2:4 (1 cement : 2
coarse sand : 4 gradeed stone aggregate 20 mm
nominal size)
For benching :
3.14/4x(1.22)2x0.23 = 0.269 cum
Less pipe :1.22x3.14/4x(0.15)2(-) = 0.0216 cum
TOTAL 1159.27
Add 10 % for contractor's profit on all except (A) 3.99
i.e. on (1159.27 - 1119.37) = 39.90
TOTAL 284.65
Add 10 % for contractor's profit on all except (A) 2.39
i.e. on (284.65 - 260.71) = 23.94
Cost for one metre 287.04
Say 287.00
20.23 Dismantling of manhole for extra for depth of manholes dismantled:
20.23.2 Rectangular manhole 120x90 cm beyond 90 cm depth
Code Description Rate Unit Qty Total
Details of cost for one metre
Dismantling of second class brick work in cement
mortar 1:5 (1 Cement : 5 fine sand)
5.12x0.23x1.0m = 1.178 cum Say 1.18 cum
16.3.0.3 Demolition of Brick work in CM (Rate as per Item 263.34 cum 1.18 cum 310.74
16.3.3)
LABOUR
0114 Beldar 190.00 day 0.12 day 22.80
TOTAL 333.54
Add 5 % for water, electricity, sundries and other 1.14
overhead charges on all except (A) i.e. on (333.54 -
310.74) = 22.80
TOTAL 334.68
Add 10 % for contractor's profit on all except (A) 2.39
i.e. on (334.68 - 310.74) = 23.94
Cost for one metre 337.07
Say 337.00
20.23 Dismantling of manhole for extra for depth of manholes dismantled:
20.23.3 Rectangular arch type manhole 140x90 cm beyond 2.45m and upto 4.25 m depth
Code Description Rate Unit Qty Total
Details of cost of dismantling one manhole 4.25m
deep
Dismantling IInd class brick work in cement mortar
1:4 (1 Cement : 4 Coarse sand) for 2.45 depth
Total 512.64
Add 10 % for contractor's profit on all except (A) 0.00
i.e. on (512.64 - 512.64) = 0.00
Cost for 1.8 metre depth 512.64
Cost for 1 metre depth 284.80
Say 285.00
20.23 Dismantling of manhole for extra for depth of manholes dismantled:
20.23.4 Circular manhole 1.22m diameter beyond 1.68 m and upto 2.29 m depth
Code Description Rate Unit Qty Total
Details of cost for 0.61 m depth
3.14x1.45x0.23x0.61=0.64
16.3.0.3 Demolition of Brick work in CM (Rate as per Item 263.34 cum 0.64 cum 168.54
16.3.3)
LABOUR
0114 Beldar 190.00 day 0.04 day 7.60
TOTAL 176.14
Add 5 % for water, electricity, sundries and other 0.38
overhead charges on all except (A) i.e. on (176.14 -
168.54) = 7.60
TOTAL 176.52
Add 10 % for contractor's profit on all except (A) 0.80
i.e. on (176.52 - 168.54) = 7.98
20.24.1 Rectangular manhole 90x80 cm with rectangular cover 600x450 mm of grade LD - 2.5
Code Description Rate Unit Qty Total
Details of cost for one manhole
Dismantling of R.C.C slab of 1:2:4 (1 cement : 2
coarse sand : 4 aggregate stone 20 mm nominal
size) = 1.36x1.26x0.15 = 0.257 cum
TOTAL 850.25
Add 10 % for contractor's profit on all except (A) 1.00
i.e. on (850.25 - 840.27) = 9.98
Cost of one no 851.25
Say 851.00
20.24 Raising manhole with cover and frame slab to required level including dismantling existing slab, taking out the
existing CI frame & cover of manhole and raising it upto ground/ road level, refixing of frame and cover in cement
concrete 1:2:4 (1 cement : 2 coarse sand : 4 crushed stone aggregate 20mm) all around the frame, including making
good the damage, form work, curing, complete. (Brick work of raising depth of manhole to be paid separately)
20.24.2 Rectangular manhole 120x90 cm with circular cover 500 mm dia of grade MD - 10
Code Description Rate Unit Qty Total
TOTAL 1340.23
Add 10 % for contractor's profit on all except (A) 1.00
i.e. on (1340.23 - 1330.25) = 9.98
Cost of one no 1341.23
Say 1341.00
20.24 Raising manhole with cover and frame slab to required level including dismantling existing slab, taking out the
existing CI frame & cover of manhole and raising it upto ground/ road level, refixing of frame and cover in cement
concrete 1:2:4 (1 cement : 2 coarse sand : 4 crushed stone aggregate 20mm) all around the frame, including making
good the damage, form work, curing, complete. (Brick work of raising depth of manhole to be paid separately)
20.24.3 Rectangular manhole 120x90 cm with circular cover 560 mm dia of grade HD - 20
Code Description Rate Unit Qty Total
Details of cost for one manhole
Dismantling of R.C.C slab of 1:2:4 (1 cement : 2
coarse sand : 4 aggregate stone 20 mm nominal
size)
TOTAL 1244.06
Add 10 % for contractor's profit on all except (A) 1.20
i.e. on (1244.06 - 1232.09) = 11.97
20.24.4 Circular manhole 140 cm dia with circular cover 600 mm dia of grade EHD - 35
Code Description Rate Unit Qty Total
Details of cost for one manhole
Dismantling of C.C slab of 1:2:4 (1 cement : 2
coarse sand : 4 aggregate stone 20 mm nominal
size)
3.1.0.4 Cement concrete 1:2:4 (stone aggregate 20mm) 3551.90 cum 0.31 cum 1101.09
(Rate as per Item No 3.1.4)
LABOUR
0114 Beldar 190.00 day 0.06 day 11.40
TOTAL 1350.59
Add 5 % for water, electricity, sundries and other 0.57
overhead charges on all except (A) i.e. on (1350.59
- 1339.19) = 11.40
TOTAL 1351.16
3.1.0.1 Cement concrete 1:5:10 (stone aggregate 20mm) 2409.03 cum 0.18 cum 433.63
(Rate as per Item No 3.1.1)
Brick work in bricks of clas designation 75 in
cement mortar 1:4 ( 1 cement : 4 coarse sand)
3.1.0.4 Cement concrete 1:2:4 (stone aggregate 20mm) 3551.90 cum 0.1 cum 355.19
(Rate as per Item No 3.1.4)
Form work
2x2.82x0.15 m = 0.846 sqm Say 0.85 sqm
2.1.0.7 Form work for suspended floors (Rate as per Item 235.29 sqm 0.85 sqm 200.00
No 2.1.7)
0338 Precast R.C.C. grating with frame 500x450 mm 650.00 each 1 each 650.00
horizontal grating
LABOUR
0102 Mason 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 2768.01
Add 5 % for water, electricity, sundries and other 33.49
overhead charges on all except (A) i.e. on (2768.01
- 2098.16) = 669.85
TOTAL 2801.50
3.1.0.1 Cement concrete 1:5:10 (stone aggregate 20mm) 2409.03 cum 0.17 cum 409.54
(Rate as per Item No 3.1.1)
Brick work in bricks of clas designation 75 in
cement mortar 1:4 ( 1 cement : 4 coarse sand)
3.1.0.4 Cement concrete 1:2:4 (stone aggregate 20mm) 3551.90 cum 0.06 cum 213.11
(Rate as per Item No 3.1.4)
Form work
0.45x0.45 m = 0.202 sqm
0.45x0.20 m = 0.09 sqm
outside slab : 3.40x0.075 m = 0.255 sqm
= 0.547 sqm Say 0.55 sqm
2.1.0.7 Form work for suspended floors (Rate as per Item 235.29 sqm 0.55 sqm 129.41
No 2.1.7)
Mild steel reinforcement for R.C.C work
0.062 cum @ 80 kg/cum = 4.96 kg
3.12.0.4 MS reinforcement (Rate as per Item No 3.13.4) 53.65 kg 4.96 kg 266.10
0339 Precast R.C.C. grating with frame 450x100 mm 305.00 each 1 each 305.00
vertical grating
LABOUR
0102 Mason 1st class 207.00 day 0.05 day 10.35
0114 Beldar 190.00 day 0.05 day 9.50
TOTAL 2960.96
Add 5 % for water, electricity, sundries and other 16.24
overhead charges on all except (A) i.e. on (2960.96
- 2636.11) = 324.85
TOTAL 2977.20
Add 10 % for contractor's profit on all except (A) 34.11
i.e. on (2977.20 - 2636.11) = 341.09
3.1.0.1 Cement concrete 1:5:10 (stone aggregate 20mm) 2409.03 cum 0.29 cum 698.62
(Rate as per Item No 3.1.1)
Brick work in bricks of clas designation 75 in
cement mortar 1:4 ( 1 cement : 4 coarse sand)
3.1.0.4 Cement concrete 1:2:4 (stone aggregate 20mm) 3551.90 cum 0.06 cum 213.11
(Rate as per Item No 3.1.4)
R.C.C. 1:2:4 (1 cement : 2 coarse sand : 4 graded
stone aggregate 20 mm nominal size) in lintels
0338 Precast R.C.C. grating with frame 500x450 mm 650.00 each 1 each 650.00
horizontal grating
0339 Precast R.C.C. grating with frame 450x100 mm 305.00 each 1 each 305.00
vertical grating
LABOUR
0102 Mason 1st class 207.00 day 0.1 day 20.70
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 5058.42
TOTAL 5108.16
Add 10 % for contractor's profit on all except (A) 104.44
i.e. on (5108.16 - 4063.72) = 1044.44
20.28.1 Inside dimensions 455x610 mm and 45 cm deep for single pipe line :
Code Description Rate Unit Qty Total
Details of cost for one chamber
Cement concrete 1:5:10 (1 cement : 5 fine sand :
10 graded stone aggregate 40 mm nominal size)
3.1.0.1 Cement concrete 1:5:10 (stone aggregate 20mm) 2409.03 cum 0.2 cum 481.81
(Rate as per Item No 3.1.1)
Brick work in bricks of clas designation 75 in
cement mortar 1:4 ( 1 cement : 4 coarse sand)
TOTAL 3530.69
Add 5 % for water, electricity, sundries and other 85.50
overhead charges on all except (A) i.e. on (3530.69
- 1820.69) = 1710.00
TOTAL 3616.19
Add 10 % for contractor's profit on all except (A) 179.55
i.e. on (3616.19 - 1820.69) = 1795.50
20.28.2 Inside dimensions 500x700 mm and 45 cm deep for pipe line with one or two inlets :
Code Description Rate Unit Qty Total
Details of cost of one no.
Cement concrete 1:5:10 (1 cement : 5 fine sand :
10 graded stone aggregate 40 mm nominal size)
2221 C.I. Rectangular cover 455x610 mm with frame 1710.00 each 1 each 1710.00
(low duty) 38 kg
14.43 Painting with coaltar (Rate as per item no 14.43) 20.42 sqm 0.6 sqm 12.25
TOTAL 4091.66
Add 5 % for water, electricity, sundries and other 85.50
overhead charges on all except (A) i.e. on (4091.66
- 2381.66) = 1710.00
TOTAL 4177.16
Add 10 % for contractor's profit on all except (A) 179.55
i.e. on (4177.16 - 2381.66) = 1795.50
20.28.3 Inside dimensions 600x 850 mm and 45 cm deep for pipe line with three or more inlets :
Code Description Rate Unit Qty Total
Details of cost of one
Cement concrete 1:5:10 (1 cement : 5 fine sand :
10 graded stone aggregate 40 mm nominal size)
2221 C.I. Rectangular cover 455x610 mm with frame 1710.00 each 1 each 1710.00
(low duty) 38 kg
14.43 Painting with coaltar (Rate as per item no 14.43) 20.42 sqm 0.6 sqm 12.25
TOTAL 4629.27
Add 5 % for water, electricity, sundries and other 85.50
overhead charges on all except (A) i.e. on (4629.27
- 2919.27) = 1710.00
TOTAL 4714.77
20.29.1 Inside dimensions 450x600 mm and 45 cm deep for single pipe line :
Code Description Rate Unit Qty Total
Details of cost for one chamber
Cement concrete 1:5:10 (1 cement : 5 fine sand :
10 graded stone aggregate 40 mm nominal size)
3.1.0.1 Cement concrete 1:5:10 (stone aggregate 20mm) 2409.03 cum 0.2 cum 481.81
(Rate as per Item No 3.1.1)
Brick work in bricks of clas designation 75 in
cement mortar 1:4 ( 1 cement : 4 coarse sand)
3.2.0.1 Cement concrete 1:1.5:3 (stone aggregate 20mm) 4162.91 cum 0.02 cum 83.26
(Rate as per Item No 3.2.1)
Form work
Outer periphery 2.10 m
2.1.0.4 Form work on Edge (Rate as per Item No 2.1.4) 33.87 metre 2.1 metre 71.13
TOTAL 1529.96
Add 5 % for water, electricity, sundries and other 0.00
overhead charges on all except (A) i.e. on (1529.96
- 1529.96) = 0.00
TOTAL 1529.96
Add 10 % for contractor's profit on all except (A) 0.00
i.e. on (1529.96 - 1529.96) = 0.00
Cost of one chamber 1529.96
Say 1530.00
20.29 Providing and constructing brick masonry chamber for underground pipe and bends with well burnt modular clay
bricks crushing strength not less than 35kg/cm2 in cement mortar 1:4 (1 cement : 4 coarse sand) RCC cover of
suitable size and 75mm thick with 1:1.5:3 mix (1 cement :1.5 coarse sand : 3 graded stone aggregate 20 mm nominal
size) including reinforcement 8mm dia bars at 150mm both ways and MS hooks for lifting, including foundation
concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size), inside plastering 12 mm
thick with cement mortar 1:3 (1 cement : 3 coarse sand) finished smooth with a floating coat of neat cement on
walls and bed concrete etc. complete as per standard design :
20.29.2 Inside dimensions 500x700 mm and 45 cm deep for pipe line with one or two inlets :
Code Description Rate Unit Qty Total
Details of cost of one no.
Cement concrete 1:5:10 (1 cement : 5 fine sand :
10 graded stone aggregate 40 mm nominal size)
TOTAL 1703.25
Add 5 % for water, electricity, sundries and other 0.00
overhead charges on all except (A) i.e. on (1703.25
- 1703.25) = 0.00
TOTAL 1703.25
Add 10 % for contractor's profit on all except (A) 0.00
i.e. on (1703.25 - 1703.25) = 0.00
Cost of one chamber 1703.25
Say 1703.00
20.29 Providing and constructing brick masonry chamber for underground pipe and bends with well burnt modular clay
bricks crushing strength not less than 35kg/cm2 in cement mortar 1:4 (1 cement : 4 coarse sand) RCC cover of
suitable size and 75mm thick with 1:1.5:3 mix (1 cement :1.5 coarse sand : 3 graded stone aggregate 20 mm nominal
size) including reinforcement 8mm dia bars at 150mm both ways and MS hooks for lifting, including foundation
concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size), inside plastering 12 mm
thick with cement mortar 1:3 (1 cement : 3 coarse sand) finished smooth with a floating coat of neat cement on
walls and bed concrete etc. complete as per standard design :
20.29.3 Inside dimensions 600x 850 mm and 45 cm deep for pipe line with three or more inlets :
Code Description Rate Unit Qty Total
Details of cost of one
Cement concrete 1:5:10 (1 cement : 5 fine sand :
10 graded stone aggregate 40 mm nominal size)
TOTAL 2619.24
Add 5 % for water, electricity, sundries and other 0.00
overhead charges on all except (A) i.e. on (2619.24
- 2619.24) = 0.00
TOTAL 2619.24
Add 10 % for contractor's profit on all except (A) 0.00
i.e. on (2619.24 - 2619.24) = 0.00
Cost of one chamber 2619.24
Say 2619.00
20.30 Providing and constructing brick work for extra depth beyond 45 cm of brick masonry chamber with well burnt
modular clay bricks crushing strength not less than 35kg/cm2 in cement mortar 1:4 (1 cement : 4 coarse sand) with
inside plastering 12 mm thick with cement mortar 1:3 (1 cement : 3 coarse sand) finished smooth with a floating
coat of neat cement on walls:
TOTAL 2615.62
Add 5 % for water, electricity, sundries and other 0.00
overhead charges on all except (A) i.e. on (2615.62
- 2615.62) = 0.00
TOTAL 2852.85
Add 5 % for water, electricity, sundries and other 0.00
overhead charges on all except (A) i.e. on (2852.85
- 2852.85) = 0.00
TOTAL 3321.89
Add 5 % for water, electricity, sundries and other 0.00
overhead charges on all except (A) i.e. on (3321.89
- 3321.89) = 0.00
Single matting
LABOUR
0102 Mason 1st class 207.00 day 0.15 day 31.05
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 1522.89
Add 5 % for water, electricity, sundries and other 60.18
overhead charges on all except (A) i.e. on (1522.89
- 319.34) = 1203.55
TOTAL 1583.07
Add 10 % for contractor's profit on all except (A) 126.37
i.e. on (1583.07 - 319.34) = 1263.73
Labour-
0121 Mistry 207.00 day 1 day 207.00
0114 Beldar 190.00 day 4 day 760.00
"Extra labour to assist M/C operator &_x000D_
security"
0114 Beldar 190.00 day 2 day 380.00
0122 Chokidar 190.00 day 1 day 190.00
TOTAL 10277.00
Add 5 % for water, electricity, sundries and other 513.85
overhead charges
TOTAL 10790.85
Add 10 % for contractor's profit 1079.09
Cost of 40 metre 11869.94
Rate of 1 metre 296.74
Say 297.00
21.1 Boring/drilling bore well perfectly vertical for the specified depth suitable to receive required dia for casing/ strainer
pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing
and submitting strata chart/bore log, including hire & running charges of all equipments, tools, plants &
machineries required for the job, all complete as per direction of Engineer–in-charge upto 90 metre depth below
ground level.
Labour-
0121 Mistry 207.00 day 1 day 207.00
Labour-
0121 Mistry 207.00 day 1 day 207.00
0114 Beldar 190.00 day 4 day 760.00
"Extra labour to assist M/C operator &_x000D_
security"
0114 Beldar 190.00 day 2 day 380.00
0122 Chokidar 190.00 day 1 day 190.00
TOTAL 10277.00
Add 5 % for water, electricity, sundries and other 513.85
overhead charges
TOTAL 10790.85
Add 10 % for contractor's profit 1079.09
Cost of 35 metre 11869.94
Rate of 1 metre 339.14
Say 339.00
21.1 Boring/drilling bore well perfectly vertical for the specified depth suitable to receive required dia for casing/ strainer
pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing
and submitting strata chart/bore log, including hire & running charges of all equipments, tools, plants &
machineries required for the job, all complete as per direction of Engineer–in-charge upto 90 metre depth below
ground level.
Labour-
0121 Mistry 207.00 day 1 day 207.00
0114 Beldar 190.00 day 4 day 760.00
"Extra labour to assist M/C operator &_x000D_
security"
0114 Beldar 190.00 day 2 day 380.00
0122 Chokidar 190.00 day 1 day 190.00
TOTAL 10277.00
Add 5 % for water, electricity, sundries and other 513.85
overhead charges
TOTAL 10790.85
Add 10 % for contractor's profit 1079.09
Cost of 32 metre 11869.94
Rate of 1 metre 370.93
Say 371.00
21.1 Boring/drilling bore well perfectly vertical for the specified depth suitable to receive required dia for casing/ strainer
pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing
and submitting strata chart/bore log, including hire & running charges of all equipments, tools, plants &
machineries required for the job, all complete as per direction of Engineer–in-charge upto 90 metre depth below
ground level.
Labour-
0121 Mistry 207.00 day 1 day 207.00
0114 Beldar 190.00 day 4 day 760.00
"Extra labour to assist M/C operator &_x000D_
security"
0114 Beldar 190.00 day 2 day 380.00
0122 Chokidar 190.00 day 1 day 190.00
TOTAL 10277.00
Labour-
0121 Mistry 207.00 day 1 day 207.00
0114 Beldar 190.00 day 4 day 760.00
"Extra labour to assist M/C operator &_x000D_
security"
0114 Beldar 190.00 day 2 day 380.00
0122 Chokidar 190.00 day 1 day 190.00
TOTAL 10277.00
Add 5 % for water, electricity, sundries and other 513.85
overhead charges
TOTAL 10790.85
Add 10 % for contractor's profit 1079.09
Cost of 34 metre 11869.94
Rate of 1 metre 349.11
Say 349.00
21.1 Boring/drilling bore well perfectly vertical for the specified depth suitable to receive required dia for casing/ strainer
pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing
and submitting strata chart/bore log, including hire & running charges of all equipments, tools, plants &
machineries required for the job, all complete as per direction of Engineer–in-charge upto 90 metre depth below
ground level.
Labour-
0121 Mistry 207.00 day 1 day 207.00
0114 Beldar 190.00 day 4 day 760.00
"Extra labour to assist M/C operator &_x000D_
security"
0114 Beldar 190.00 day 2 day 380.00
0122 Chokidar 190.00 day 1 day 190.00
TOTAL 10277.00
Add 5 % for water, electricity, sundries and other 513.85
overhead charges
TOTAL 10790.85
Add 10 % for contractor's profit 1079.09
Cost of 30 metre 11869.94
Rate of 1 metre 395.66
Say 396.00
21.1 Boring/drilling bore well perfectly vertical for the specified depth suitable to receive required dia for casing/ strainer
pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing
and submitting strata chart/bore log, including hire & running charges of all equipments, tools, plants &
machineries required for the job, all complete as per direction of Engineer–in-charge upto 90 metre depth below
ground level.
Labour-
0121 Mistry 207.00 day 1 day 207.00
0114 Beldar 190.00 day 4 day 760.00
"Extra labour to assist M/C operator &_x000D_
security"
0114 Beldar 190.00 day 2 day 380.00
0122 Chokidar 190.00 day 1 day 190.00
TOTAL 10277.00
Add 5 % for water, electricity, sundries and other 513.85
overhead charges
TOTAL 10790.85
Add 10 % for contractor's profit 1079.09
Cost of 26 metre 11869.94
Rate of 1 metre 456.53
Labour-
0121 Mistry 207.00 day 1 day 207.00
0114 Beldar 190.00 day 4 day 760.00
"Extra labour to assist M/C operator &_x000D_
security"
0114 Beldar 190.00 day 2 day 380.00
0122 Chokidar 190.00 day 1 day 190.00
TOTAL 10277.00
Add 5 % for water, electricity, sundries and other 513.85
overhead charges
TOTAL 10790.85
Add 10 % for contractor's profit 1079.09
Cost of 36 metre 11869.94
Rate of 1 metre 329.72
Say 330.00
21.2 Boring/drilling bore well perfectly vertical for the specified depth suitable to receive required dia for casing/ strainer
pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing
and submitting strata chart/bore log, including hire & running charges of all equipments, tools, plants &
machineries required for the job, all complete as per direction of Engineer–in-charge beyond 90 metre & upto 150
metre depth below ground level.
Labour-
Labour-
0121 Mistry 207.00 day 1 day 207.00
0114 Beldar 190.00 day 4 day 760.00
"Extra labour to assist M/C operator &_x000D_
security"
0114 Beldar 190.00 day 2 day 380.00
0122 Chokidar 190.00 day 1 day 190.00
TOTAL 10277.00
Add 5 % for water, electricity, sundries and other 513.85
overhead charges
TOTAL 10790.85
Add 10 % for contractor's profit 1079.09
Cost of 32 metre 11869.94
Rate of 1 metre 370.93
Say 371.00
21.2 Boring/drilling bore well perfectly vertical for the specified depth suitable to receive required dia for casing/ strainer
pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing
and submitting strata chart/bore log, including hire & running charges of all equipments, tools, plants &
machineries required for the job, all complete as per direction of Engineer–in-charge beyond 90 metre & upto 150
metre depth below ground level.
Labour-
0121 Mistry 207.00 day 1 day 207.00
0114 Beldar 190.00 day 4 day 760.00
"Extra labour to assist M/C operator &_x000D_
security"
0114 Beldar 190.00 day 2 day 380.00
0122 Chokidar 190.00 day 1 day 190.00
TOTAL 10277.00
Add 5 % for water, electricity, sundries and other 513.85
overhead charges
TOTAL 10790.85
Add 10 % for contractor's profit 1079.09
Cost of 30 metre 11869.94
Rate of 1 metre 395.66
Say 396.00
21.2 Boring/drilling bore well perfectly vertical for the specified depth suitable to receive required dia for casing/ strainer
pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing
and submitting strata chart/bore log, including hire & running charges of all equipments, tools, plants &
machineries required for the job, all complete as per direction of Engineer–in-charge beyond 90 metre & upto 150
metre depth below ground level.
Labour-
0121 Mistry 207.00 day 1 day 207.00
0114 Beldar 190.00 day 4 day 760.00
"Extra labour to assist M/C operator &_x000D_
security"
0114 Beldar 190.00 day 2 day 380.00
0122 Chokidar 190.00 day 1 day 190.00
Labour-
0121 Mistry 207.00 day 1 day 207.00
0114 Beldar 190.00 day 4 day 760.00
"Extra labour to assist M/C operator &_x000D_
security"
0114 Beldar 190.00 day 2 day 380.00
0122 Chokidar 190.00 day 1 day 190.00
TOTAL 10277.00
Add 5 % for water, electricity, sundries and other 513.85
overhead charges
TOTAL 10790.85
Add 10 % for contractor's profit 1079.09
Cost of 32 metre 11869.94
Rate of 1 metre 370.93
Say 371.00
21.2 Boring/drilling bore well perfectly vertical for the specified depth suitable to receive required dia for casing/ strainer
pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing
and submitting strata chart/bore log, including hire & running charges of all equipments, tools, plants &
machineries required for the job, all complete as per direction of Engineer–in-charge beyond 90 metre & upto 150
metre depth below ground level.
Labour-
0121 Mistry 207.00 day 1 day 207.00
0114 Beldar 190.00 day 4 day 760.00
"Extra labour to assist M/C operator &_x000D_
security"
0114 Beldar 190.00 day 2 day 380.00
0122 Chokidar 190.00 day 1 day 190.00
TOTAL 10277.00
Add 5 % for water, electricity, sundries and other 513.85
overhead charges
TOTAL 10790.85
Add 10 % for contractor's profit 1079.09
Cost of 28 metre 11869.94
Rate of 1 metre 423.92
Say 424.00
21.2 Boring/drilling bore well perfectly vertical for the specified depth suitable to receive required dia for casing/ strainer
pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing
and submitting strata chart/bore log, including hire & running charges of all equipments, tools, plants &
machineries required for the job, all complete as per direction of Engineer–in-charge beyond 90 metre & upto 150
metre depth below ground level.
Labour-
0121 Mistry 207.00 day 1 day 207.00
0114 Beldar 190.00 day 4 day 760.00
"Extra labour to assist M/C operator &_x000D_
security"
0114 Beldar 190.00 day 2 day 380.00
0122 Chokidar 190.00 day 1 day 190.00
TOTAL 10277.00
Add 5 % for water, electricity, sundries and other 513.85
overhead charges
TOTAL 10790.85
Add 10 % for contractor's profit 1079.09
Cost of 25 metre 11869.94
Labour-
0108 Fitter 2nd class 197.00 day 0.2 day 39.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 3927.40
Add 5 % for water, electricity, sundries and other 196.37
overhead charges
TOTAL 4123.77
Add 10 % for contractor's profit 412.38
Cost of 10 metre 4536.15
Cost of 1 metre 453.61
Say 454.00
21.3 Supplying, assembling, lowering and fixing in vertical position in bore well, unplasticized PVC medium well casing
(CM) pipe of required dia, conforming to IS: 12818, including required hire and labour charges, fittings & accessories
etc. all complete, for all depths, as per direction of Engineer –in-charge.
Labour-
0108 Fitter 2nd class 197.00 day 0.2 day 39.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 4107.40
Add 5 % for water, electricity, sundries and other 205.37
overhead charges
TOTAL 4312.77
Add 10 % for contractor's profit 431.28
Cost of 10 metre 4744.05
Cost of 1 metre 474.40
Say 474.00
21.3 Supplying, assembling, lowering and fixing in vertical position in bore well, unplasticized PVC medium well casing
(CM) pipe of required dia, conforming to IS: 12818, including required hire and labour charges, fittings & accessories
etc. all complete, for all depths, as per direction of Engineer –in-charge.
Labour-
0108 Fitter 2nd class 197.00 day 0.2 day 39.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 4677.40
Add 5 % for water, electricity, sundries and other 233.87
overhead charges
TOTAL 4911.27
Add 10 % for contractor's profit 491.13
Cost of 10 metre 5402.40
Cost of 1 metre 540.24
Say 540.00
21.3 Supplying, assembling, lowering and fixing in vertical position in bore well, unplasticized PVC medium well casing
(CM) pipe of required dia, conforming to IS: 12818, including required hire and labour charges, fittings & accessories
etc. all complete, for all depths, as per direction of Engineer –in-charge.
Labour-
0108 Fitter 2nd class 197.00 day 0.2 day 39.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 8427.40
Add 5 % for water, electricity, sundries and other 421.37
overhead charges
TOTAL 8848.77
Add 10 % for contractor's profit 884.88
Cost of 10 metre 9733.65
Cost of 1 metre 973.36
Say 973.00
21.4 Supplying, assembling, lowering and fixing in vertical position in bore well unplasticized PVC medium well screen
(RMS) slotted pipes with ribs, conforming to IS: 12818, including hire & labour charges, fittings & accessories etc. all
complete, for all depths, as per direction of Engineer-in-charge.
Labour-
0108 Fitter 2nd class 197.00 day 0.2 day 39.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 3977.40
Labour-
0108 Fitter 2nd class 197.00 day 0.2 day 39.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 4367.40
Add 5 % for water, electricity, sundries and other 218.37
overhead charges
TOTAL 4585.77
Add 10 % for contractor's profit 458.58
Cost of 10 metre 5044.35
Cost of 1 metre 504.43
Say 504.00
21.4 Supplying, assembling, lowering and fixing in vertical position in bore well unplasticized PVC medium well screen
(RMS) slotted pipes with ribs, conforming to IS: 12818, including hire & labour charges, fittings & accessories etc. all
complete, for all depths, as per direction of Engineer-in-charge.
Labour-
0108 Fitter 2nd class 197.00 day 0.2 day 39.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 4727.40
Add 5 % for water, electricity, sundries and other 236.37
overhead charges
TOTAL 4963.77
Add 10 % for contractor's profit 496.38
Cost of 10 metre 5460.15
Cost of 1 metre 546.01
Say 546.00
Labour-
0108 Fitter 2nd class 197.00 day 0.2 day 39.40
0114 Beldar 190.00 day 0.2 day 38.00
TOTAL 8477.40
Add 5 % for water, electricity, sundries and other 423.87
overhead charges
TOTAL 8901.27
Add 10 % for contractor's profit 890.13
Cost of 10 metre 9791.40
Cost of 1 metre 979.14
Say 979.00
21.5 Supplying, assembling, lowering and fixing in vertical position in bore well, ISI marked G.I. casing pipe (Plain)
medium class in 4 to 7 meters length one end fitted with socket as per IS: 1239 (Part-1&Part-2) 1992 with IVth
revision (Up-to-date amendments), of reputed & approved make, including required hire & labour charges, fittings &
accessories, all complete, for all depths, as per direction of Engineer- in-charge.
21.7.1 100 mm nominal size dia having minimum wall thickness 5.0 mm
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Material
1791 100 mm dia ERW (Electric Resistance Welded) FE 750.00 metre 10 metre 7500.00
410 mild steel screwed and socketed/ plain ended
pipes, conforming to IS: 4270
Labour-
0108 Fitter 2nd class 197.00 day 0.5 day 98.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 7788.50
Add 5 % for water, electricity, sundries and other 389.43
overhead charges
TOTAL 8177.93
Add 10 % for contractor's profit 817.79
Cost of 10 metre 8995.72
Cost of 1 metre 899.57
Say 900.00
21.7 Supplying, assembling, lowering and fixing in vertical position in bore well, ERW (Electric Resistance Welded) FE 410
mild steel screwed and socketed/ plain ended casing pipes of required dia, conforming to IS: 4270, of reputed &
approved make, including required hire & labour charges, fittings & accessories, all complete, for all depths, as per
direction of Engineer-in-charge.
21.7.2 125 mm nominal size dia having minimum wall thickness 5.0 mm
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Material
1790 125 mm dia ERW (Electric Resistance Welded) FE 900.00 Metre 10 Metre 9000.00
410 mild steel screwed and socketed/ plain ended
pipes, conforming to IS: 4270
Labour-
0108 Fitter 2nd class 197.00 day 0.5 day 98.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 9288.50
Add 5 % for water, electricity, sundries and other 464.43
overhead charges
TOTAL 9752.93
Add 10 % for contractor's profit 975.29
Cost of 10 metre 10728.22
Cost of 1 metre 1072.82
Say 1073.00
21.7.3 150 mm nominal size dia having minimum wall thickness 5.0 mm
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Material
1792 150 mm dia ERW (Electric Resistance Welded) FE 1042.00 metre 10 metre 10420.00
410 mild steel screwed and socketed/ plain ended
pipes, conforming to IS: 4270
Labour-
0108 Fitter 2nd class 197.00 day 0.5 day 98.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 10708.50
Add 5 % for water, electricity, sundries and other 535.43
overhead charges
TOTAL 11243.93
Add 10 % for contractor's profit 1124.39
Cost of 10 metre 12368.32
Cost of 1 metre 1236.83
Say 1237.00
21.7 Supplying, assembling, lowering and fixing in vertical position in bore well, ERW (Electric Resistance Welded) FE 410
mild steel screwed and socketed/ plain ended casing pipes of required dia, conforming to IS: 4270, of reputed &
approved make, including required hire & labour charges, fittings & accessories, all complete, for all depths, as per
direction of Engineer-in-charge.
21.7.4 200 mm nominal size dia having minimum wall thickness 5.4 mm
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Material
1793 200 mm dia ERW (Electric Resistance Welded) FE 1250.00 metre 10 metre 12500.00
410 mild steel screwed and socketed/ plain ended
pipes, conforming to IS: 4270
Labour-
0108 Fitter 2nd class 197.00 day 0.5 day 98.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 12788.50
Add 5 % for water, electricity, sundries and other 639.43
overhead charges
TOTAL 13427.93
Add 10 % for contractor's profit 1342.79
Cost of 10 metre 14770.72
Cost of 1 metre 1477.07
Say 1477.00
21.8 Supplying, assembling, lowering and fixing in vertical position in bore well, ERW (Electric Resistance Welded) FE 410
plain slotted (having slot of size 1.6/3.2 mm) mild steel threaded and socketed / plain bevel ended pipe (type A) of
required dia, conforming to IS: 8110, of reputed and approved make, having wall thickness not less than 5.40 mm,
including hire & labour charges, fittings & accessories, all complete, for all depths, as per direction of Engineer-in-
charge.
Labour-
0108 Fitter 2nd class 197.00 day 0.5 day 98.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 7888.50
Add 5 % for water, electricity, sundries and other 394.43
overhead charges
TOTAL 8282.93
Add 10 % for contractor's profit 828.29
Cost of 10 metre 9111.22
Cost of 1 metre 911.12
Say 911.00
21.8 Supplying, assembling, lowering and fixing in vertical position in bore well, ERW (Electric Resistance Welded) FE 410
plain slotted (having slot of size 1.6/3.2 mm) mild steel threaded and socketed / plain bevel ended pipe (type A) of
required dia, conforming to IS: 8110, of reputed and approved make, having wall thickness not less than 5.40 mm,
including hire & labour charges, fittings & accessories, all complete, for all depths, as per direction of Engineer-in-
charge.
21.8.2 125 mm nominal size dia having minimum wall thickness 5.0 mm
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Material
1798 125 mm dia slotted ERW (Electric Resistance 910.00 Metre 10 Metre 9100.00
Welded) FE 410 mild steel screwed and socketed/
plain ended pipes, conforming to IS: 4270
Labour-
0108 Fitter 2nd class 197.00 day 0.5 day 98.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 9388.50
Add 5 % for water, electricity, sundries and other 469.43
overhead charges
TOTAL 9857.93
Add 10 % for contractor's profit 985.79
Cost of 10 metre 10843.72
Cost of 1 metre 1084.37
Say 1084.00
21.8 Supplying, assembling, lowering and fixing in vertical position in bore well, ERW (Electric Resistance Welded) FE 410
plain slotted (having slot of size 1.6/3.2 mm) mild steel threaded and socketed / plain bevel ended pipe (type A) of
required dia, conforming to IS: 8110, of reputed and approved make, having wall thickness not less than 5.40 mm,
including hire & labour charges, fittings & accessories, all complete, for all depths, as per direction of Engineer-in-
charge.
21.8.3 150 mm nominal size dia having minimum wall thickness 5.0 mm
Code Description Rate Unit Qty Total
Labour-
0108 Fitter 2nd class 197.00 day 0.5 day 98.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 10808.50
Add 5 % for water, electricity, sundries and other 540.43
overhead charges
TOTAL 11348.93
Add 10 % for contractor's profit 1134.89
Cost of 10 metre 12483.82
Cost of 1 metre 1248.38
Say 1248.00
21.8 Supplying, assembling, lowering and fixing in vertical position in bore well, ERW (Electric Resistance Welded) FE 410
plain slotted (having slot of size 1.6/3.2 mm) mild steel threaded and socketed / plain bevel ended pipe (type A) of
required dia, conforming to IS: 8110, of reputed and approved make, having wall thickness not less than 5.40 mm,
including hire & labour charges, fittings & accessories, all complete, for all depths, as per direction of Engineer-in-
charge.
21.8.4 200 mm nominal size dia having minimum wall thickness 5.0 mm
Code Description Rate Unit Qty Total
Details of cost for 10 metre
Material
1796 200 mm dia slotted ERW (Electric Resistance 1260.00 metre 10 metre 12600.00
Welded) FE 410 mild steel screwed and socketed/
plain ended pipes, conforming to IS: 4270
Labour-
0108 Fitter 2nd class 197.00 day 0.5 day 98.50
0114 Beldar 190.00 day 1 day 190.00
TOTAL 12888.50
Add 5 % for water, electricity, sundries and other 644.43
overhead charges
TOTAL 13532.93
Add 10 % for contractor's profit 1353.29
Cost of 10 metre 14886.22
Cost of 1 metre 1488.62
Say 1489.00
21.9 Gravel packing in tube well construction in accordance with IS: 4097, including providing gravel fine/ medium/
coarse, in required grading & sizes as per actual requirement, all complete as per direction of Engineer-in-charge.
1021 M.S. Bolts and nuts 16 mm dia 65 mm long 8.60 each 4 each 34.40
Labour-
0108 Fitter 2nd class 197.00 day 0.02 day 3.94
0114 Beldar 190.00 day 0.02 day 3.80
TOTAL 1000.92
Add 5 % for water, electricity, sundries and other 2.11
overhead charges on all except (A) i.e. on (1000.92
- 958.78) = 42.14
TOTAL 1003.03
Add 10 % for contractor's profit on all except (A) 4.43
i.e. on (1003.03 - 958.78) = 44.25
Cost of 1 No 1007.46
Say 1007.00
21.12 Providing and fixing M.S. clamp of required dia to the top of casing/ housing pipe of tube well as per IS: 2800 (part
I), including necessary bolts & nuts of required size complete.
21.12.2 125 mm clamp.
Code Description Rate Unit Qty Total
Details of cost for 1 No
Material
Clamps made of MS flat of size 100x10mm thick
1x2.05mt.x7.80 kg per mt.=15.99 kg.
9.1 Steel work Single section (Rate as per Item No 9.1) 61.46 kg 15.99 kg 982.75
1021 M.S. Bolts and nuts 16 mm dia 65 mm long 8.60 each 4 each 34.40
Labour-
0108 Fitter 2nd class 197.00 day 0.02 day 3.94
0114 Beldar 190.00 day 0.02 day 3.80
TOTAL 1024.89
Add 5 % for water, electricity, sundries and other 2.11
overhead charges on all except (A) i.e. on (1024.89
- 982.75) = 42.14
TOTAL 1027.00
Add 10 % for contractor's profit on all except (A) 4.43
i.e. on (1027.00 - 982.75) = 44.25
Cost of 1 No 1031.43
Say 1031.00
21.12 Providing and fixing M.S. clamp of required dia to the top of casing/ housing pipe of tube well as per IS: 2800 (part
I), including necessary bolts & nuts of required size complete.
21.12.3 150 mm clamp.
Code Description Rate Unit Qty Total
Details of cost for 1 No
1021 M.S. Bolts and nuts 16 mm dia 65 mm long 8.60 each 4 each 34.40
Labour-
0108 Fitter 2nd class 197.00 day 0.02 day 3.94
0114 Beldar 190.00 day 0.02 day 3.80
TOTAL 1048.85
Add 5 % for water, electricity, sundries and other 2.11
overhead charges on all except (A) i.e. on (1048.85
- 1006.71) = 42.14
TOTAL 1050.96
Add 10 % for contractor's profit on all except (A) 4.43
i.e. on (1050.96 - 1006.71) = 44.25
Cost of 1 No 1055.39
Say 1055.00
21.12 Providing and fixing M.S. clamp of required dia to the top of casing/ housing pipe of tube well as per IS: 2800 (part
I), including necessary bolts & nuts of required size complete.
21.12.4 200 mm clamp.
Code Description Rate Unit Qty Total
Details of cost for 1 No
Material
Clamps made of MS flat of size 100x10mm thick
1x2.40 mt.x7.80 kg per mt.=18.72 kg.
9.1 Steel work Single section (Rate as per Item No 9.1) 61.46 kg 18.72 kg 1150.53
1021 M.S. Bolts and nuts 16 mm dia 65 mm long 8.60 each 4 each 34.40
Labour-
0108 Fitter 2nd class 197.00 day 0.02 day 3.94
0114 Beldar 190.00 day 0.02 day 3.80
TOTAL 1192.67
Add 5 % for water, electricity, sundries and other 2.11
overhead charges on all except (A) i.e. on (1192.67
- 1150.53) = 42.14
TOTAL 1194.78
Add 10 % for contractor's profit on all except (A) 4.43
i.e. on (1194.78 - 1150.53) = 44.25
Cost of 1 No 1199.21
Say 1199.00
21.13 Providing and fixing Bail plug/ Bottom plug of required dia to the bottom of pipe assembly of tube well as per
IS:2800 (part I).
21.13.1 100 mm dia
Code Description Rate Unit Qty Total
Details of cost for 1 No
Material
1968 M.S bail plug 100 mm dia 125.00 each 1 each 125.00
Labour-
Labour-
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 747.50
Add 5 % for water, electricity, sundries and other 37.38
overhead charges
TOTAL 784.88
Add 10 % for contractor's profit 78.49
Cost of 1 cum. 863.37
Say 863.00
21.14 Supplying, filling, spreading & leveling stone boulders/ Gravels/ Coarse sand, in recharge pit, in the required layers
and thickness, for all leads & lifts, all complete as per direction of Engineer-in-charge. (excavation of pit will be paid
separately).
21.14.2 Gravels of size range 5 mm to 10 mm, over the existing layer of boulders
Code Description Rate Unit Qty Total
Details of cost for 1 cum.
Material
0309 Gravel 5 mm to 10 mm 650.00 cum 1 cum 650.00
Labour-
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 697.50
Add 5 % for water, electricity, sundries and other 34.88
overhead charges
TOTAL 732.38
Add 10 % for contractor's profit 73.24
Cost of 1 cum. 805.62
Say 806.00
21.14.3 Coarse sand of size range 1.5 mm to 2 mm over existing layer of gravel
Code Description Rate Unit Qty Total
Details of cost for 1 cum.
Material
0253 Coarse sand 360.00 cum 1 cum 360.00
Labour-
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 407.50
Add 5 % for water, electricity, sundries and other 20.38
overhead charges
TOTAL 427.88
Add 10 % for contractor's profit 42.79
Cost of 1 cum. 470.67
Say 471.00
21.15 Providing and placing in position India Mark II hand pump with 32 mm diameter riser pipe assembly complete with
all accessories (riser pipe and plunger rod to be paid separately).
Code Description Rate Unit Qty Total
Details of cost for 1 No
Material
1797 India Mark II hand pump with 32 mm diameter 5100.00 each 1 each 5100.00
Labour
0108 Fitter 2nd class 197.00 day 0.5 day 98.50
0114 Beldar 190.00 day 0.5 day 95.00
TOTAL 5293.50
Add 5 % for water, electricity, sundries and other 264.68
overhead charges
TOTAL 5558.18
Add 10 % for contractor's profit 555.82
Cost of 1 No 6114.00
Say 6114.00
21.16 Providing ISI Mark 32 mm dia G.I. ( B class) riser pipe and M.S. plunger rod in 3 meter length socketed on one end as
per IS: 1239 ( Part I) 1990 with up to date amendments and socket as per IS: 2062/1990 up to date amendments.
LABOUR
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 188.54
Add 5 % for water, electricity, sundries and other 3.88
overhead charges on all except (A) i.e. on (188.54 -
111.04) = 77.50
TOTAL 192.42
Add 10 % for contractor's profit on all except (A) 8.14
i.e. on (192.42 - 111.04) = 81.38
Cost per cum. 200.56
Say 201.00
22.3 Supplying and stacking sludge at site including royalty, loading, unloading and carriage upto 5 km (sludge measured
in stacks will be reduced by 8% for payment).
Code Description Rate Unit Qty Total
Details of cost for 1 cum.
MATERIAL
3623 Royalty for sludge 90.00 cum 1 cum 90.00
1.26.0.2 Carriage of Sludge (Rate as per Item No. 1.26.2) 88.89 cum 1 cum 88.89
LABOUR
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 226.39
Add 5 % for water, electricity, sundries and other 6.88
overhead charges on all except (A) i.e. on (226.39 -
88.89) = 137.50
TOTAL 233.27
LABOUR
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 216.39
Add 5 % for water, electricity, sundries and other 6.38
overhead charges on all except (A) i.e. on (216.39 -
88.89) = 127.50
TOTAL 222.77
Add 10 % for contractor's profit on all except (A) 13.39
i.e. on (222.77 - 88.89) = 133.88
Cost per cum. 236.16
Say 236.00
22.5 Rough dressing the trenched ground including breaking clods.
Code Description Rate Unit Qty Total
Details of cost for 100sqm.
Labour :
0114 Beldar 190.00 day 0.25 day 47.50
TOTAL 47.50
Add 5 % for water, electricity, sundries and other 2.38
overhead charges
TOTAL 49.88
Add 10 % for contractor's profit 4.99
Cost for 100 Sqm. 54.87
Cost for 1 Sqm. 0.54
Say 0.50
22.6 Uprooting weeds from the trenched area after 10 to 15 days of its flooding with water including disposal of
uprooted vegetation.
Code Description Rate Unit Qty Total
Details of cost for 100sqm.
Labour :
0114 Beldar 190.00 day 0.75 day 142.50
TOTAL 142.50
Add 5 % for water, electricity, sundries and other 7.13
overhead charges
TOTAL 149.63
Add 10 % for contractor's profit 14.96
Cost for 100 Sqm. 164.59
Cost for 1 Sqm. 1.64
LABOUR
0110 Blacksmith 2nd class 197.00 day 2 day 394.00
0114 Beldar 190.00 day 1 day 190.00
TOTAL 2060.73
Add 5 % for water, electricity, sundries and other 97.33
overhead charges on all except (A) i.e. on (2060.73
- 114.11) = 1946.62
TOTAL 2158.06
Add 10 % for contractor's profit on all except (A) 204.40
i.e. on (2158.06 - 114.11) = 2043.95
LABOUR
0110 Blacksmith 2nd class 197.00 day 0.13 day 25.61
0114 Beldar 190.00 day 0.07 day 13.30
TOTAL 364.03
Add 5 % for water, electricity, sundries and other 16.00
overhead charges on all except (A) i.e. on (364.03 -
44.11) = 319.92
TOTAL 380.03
Add 10 % for contractor's profit on all except (A) 33.59
i.e. on (380.03 - 44.11) = 335.92
Cost for one tree guard 413.62
Say 414.00
22.17 Making tree guard 53 cm dia. and 1.3 m high as per design from empty coal tar drums supplied free by the
department including providing and fixing 2 nos. M.S. sheet rings 50 x 0.5 mm with rivets complete in all respects
including painting inside and outside of tree guard with :
22.17.2 Two or more coats of synthetic enamel paint of approved quality shade over a priming coat.
Code Description Rate Unit Qty Total
Details of cost for one tree guard-
MATERIAL
2643 Putty for wall finshing 42.40 kg 0.5 kg 21.20
1016 Mild steel rivets 4350.80 quintal 0.008 quintal 34.81
3608 Fuel wood 450.00 quintal 0.5 quintal 225.00
Applying priming coat of red oxide
½x2x22/7x0.53x1.30 = 2.16 sqm.
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 2.16 sqm 37.30
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 2.16 sqm 101.95
LABOUR
0110 Blacksmith 2nd class 197.00 day 0.13 day 25.61
0114 Beldar 190.00 day 0.07 day 13.30
TOTAL 459.17
Add 5 % for water, electricity, sundries and other 16.00
overhead charges on all except (A) i.e. on (459.17 -
139.25) = 319.92
TOTAL 475.17
LABOUR
0110 Blacksmith 2nd class 197.00 day 0.19 day 37.43
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 292.03
Add 5 % for water, electricity, sundries and other 11.20
overhead charges on all except (A) i.e. on (292.03 -
68.00) = 224.03
TOTAL 303.23
Add 10 % for contractor's profit on all except (A) 23.52
i.e. on (303.23 - 68.00) = 235.23
Cost for one tree guard 326.75
Say 327.00
22.18 Making tree guard 53 cm dia. and 2 m high as per design from empty coal tar drums supplied free by the
department including providing and fixing four legs 40 cm long of 30 x 3 mm M.S. flat riveted to tree guard and
providing and fixing 2 nos. M.S. sheet rings 50 x 0.5 mm with rivets complete in all respects including painting inside
and outside of tree guard with :
22.18.2 Two or more coats of synthetic enamel paint of approved quality and shade over a priming coat.
Code Description Rate Unit Qty Total
Details of cost for one tree guard-
MATERIAL
1013 Mild steel sheets for tanks 4575.00 quintal 0.004 quintal 18.30
1016 Mild steel rivets 4350.80 quintal 0.019 quintal 82.67
3608 Fuel wood 450.00 quintal 0.02 quintal 9.00
LABOUR
0110 Blacksmith 2nd class 197.00 day 0.19 day 37.43
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 438.72
Add 5 % for water, electricity, sundries and other 11.20
overhead charges on all except (A) i.e. on (438.72 -
214.69) = 224.03
TOTAL 449.92
Add 10 % for contractor's profit on all except (A) 23.52
i.e. on (449.92 - 214.69) = 235.23
Cost for one tree guard 473.44
Say 473.00
22.19 Edging with modular well burnt clay bricks of crushing strength not less than 25kg/ sqcm laid dry length wise
including excavation, refilling, consolidating with hand packing and spreading neatly surplus earth within a lead of
50 m :
LABOUR
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1 day 190.00
PAINTING of Iron Bracket = 10x0.25x4x0.05 = 0.5
sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.5 sqm 8.64
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 0.5 sqm 23.60
TOTAL 2789.04
Add 5 % for water, electricity, sundries and other 137.84
overhead charges on all except (A) i.e. on (2789.04
- 32.24) = 2756.80
TOTAL 2926.88
Add 10 % for contractor's profit on all except (A) 289.46
i.e. on (2926.88 - 32.24) = 2894.64
LABOUR
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1 day 190.00
PAINTING of Iron Bracket = 10x0.25x4x0.05 = 0.5
sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.5 sqm 8.64
14.21)
TOTAL 4859.04
Add 5 % for water, electricity, sundries and other 241.34
overhead charges on all except (A) i.e. on (4859.04
- 32.24) = 4826.80
TOTAL 5100.38
Add 10 % for contractor's profit on all except (A) 506.81
i.e. on (5100.38 - 32.24) = 5068.14
LABOUR
0107 Fitter 1st class 207.00 day 1.1 day 227.70
0114 Beldar 190.00 day 1.1 day 209.00
PAINTING of Iron Bracket = 10x0.25x4x0.05 = 0.5
sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.5 sqm 8.64
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 0.5 sqm 23.60
TOTAL 7700.14
Add 5 % for water, electricity, sundries and other 383.40
overhead charges on all except (A) i.e. on (7700.14
- 32.24) = 7667.90
TOTAL 8083.54
Add 10 % for contractor's profit on all except (A) 805.13
i.e. on (8083.54 - 32.24) = 8051.30
LABOUR
0107 Fitter 1st class 207.00 day 1.2 day 248.40
0114 Beldar 190.00 day 1.2 day 228.00
PAINTING of Iron Bracket = 10x0.25x4x0.05 = 0.5
sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.5 sqm 8.64
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 0.5 sqm 23.60
TOTAL 10941.44
Add 5 % for water, electricity, sundries and other 545.46
overhead charges on all except (A) i.e. on
(10941.44 - 32.24) = 10909.20
TOTAL 11486.90
Add 10 % for contractor's profit on all except (A) 1145.47
i.e. on (11486.90 - 32.24) = 11454.66
LABOUR
0107 Fitter 1st class 207.00 day 1.25 day 258.75
0114 Beldar 190.00 day 1.25 day 237.50
PAINTING of Iron Bracket = 10x0.25x4x0.05 = 0.5
sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.5 sqm 8.64
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 0.5 sqm 23.60
TOTAL 16012.09
Add 5 % for water, electricity, sundries and other 798.99
overhead charges on all except (A) i.e. on
(16012.09 - 32.24) = 15979.85
TOTAL 16811.08
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 1.85 sqm 87.32
LABOUR
0111 Painter 197.00 day 0.07 day 13.79
0114 Beldar 190.00 day 0.07 day 13.30
TOTAL 146.36
Add 5 % for water, electricity, sundries and other 1.35
overhead charges on all except (A) i.e. on (146.36 -
119.27) = 27.09
TOTAL 147.71
Add 10 % for contractor's profit on all except (A) 2.84
i.e. on (147.71 - 119.27) = 28.44
Cost for 10 metre 150.55
Cost for 1 metre 15.05
Say 15.00
23.2 Painting for M.S. pipe with a coat of red oxide primer and two or more coats of synthetic enamel paint of approved
colour and Quality to give an even shade including surface preparation.
23.2.2 65mm dia.
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
Area = 22/7 x 72.2 x10 = 2.33 sqm
Priming coat-
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 2.33 sqm 40.24
14.21)
Painting two coats with synthetic enamel paint
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 2.33 sqm 109.98
TOTAL 182.73
Add 10 % for contractor's profit on all except (A) 3.25
i.e. on (182.73 - 150.22) = 32.51
Cost for 10 metre 185.98
Cost for 1 metre 18.59
Say 18.50
23.2 Painting for M.S. pipe with a coat of red oxide primer and two or more coats of synthetic enamel paint of approved
colour and Quality to give an even shade including surface preparation.
23.2.3 80mm dia.
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
Area = 22/7 x 88 x10 = 2.8 sqm
Priming coat-
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 2.8 sqm 48.36
14.21)
Painting two coats with synthetic enamel paint
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 2.8 sqm 132.16
TOTAL 221.16
Add 10 % for contractor's profit on all except (A) 4.06
i.e. on (221.16 - 180.52) = 40.64
Cost for 10 metre 225.22
Cost for 1 metre 22.52
Say 22.50
23.2 Painting for M.S. pipe with a coat of red oxide primer and two or more coats of synthetic enamel paint of approved
colour and Quality to give an even shade including surface preparation.
23.2.4 100mm dia.
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
Area = 22/7 x 109.2 x10 = 3.44 sqm
Priming coat-
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 3.44 sqm 59.41
14.21)
Painting two coats with synthetic enamel paint
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 3.44 sqm 162.37
TOTAL 262.42
Add 10 % for contractor's profit on all except (A) 4.06
i.e. on (262.42 - 221.78) = 40.64
Cost for 10 metre 266.48
Cost for 1 metre 26.64
Say 26.50
23.2 Painting for M.S. pipe with a coat of red oxide primer and two or more coats of synthetic enamel paint of approved
colour and Quality to give an even shade including surface preparation.
23.2.5 150mm dia.
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
Area = 22/7 x 159.6 x10 = 5.05 sqm
Priming coat-
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 5.05 sqm 87.21
14.21)
Painting two coats with synthetic enamel paint
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 5.05 sqm 238.36
TOTAL 366.21
Add 10 % for contractor's profit on all except (A) 4.06
i.e. on (366.21 - 325.57) = 40.64
Cost for 10 metre 370.27
Cost for 1 metre 37.02
Say 37.00
23.3 Providing and wrapping 4 mm thick of approved make and quality bitumen based anti rust felt over MS pipe with
overlap of 25 mm to make an impermeable layer including painting with one coat of bitumastic paint before felt
complete. (Only on MS pipe to be laid in soil below ground).
23.3.1 80 mm dia
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
Felt Area = ((22/7 x 88)+25) x10 = 3.05 sqm
3309 Bitumen based anti corrossive felt 4mm thick to 214.00 sqm 3.05 sqm 652.70
wrap on MS pipe
Painting one coat with bitumastic paint on
75/80mm dia pipe
TOTAL 815.19
Add 10 % for contractor's profit on all except (A) 74.63
i.e. on (815.19 - 68.90) = 746.29
Cost for 10 metre 889.82
Cost for 1 metre 88.98
Say 89.00
23.3 Providing and wrapping 4 mm thick of approved make and quality bitumen based anti rust felt over MS pipe with
overlap of 25 mm to make an impermeable layer including painting with one coat of bitumastic paint before felt
complete. (Only on MS pipe to be laid in soil below ground).
3309 Bitumen based anti corrossive felt 4mm thick to 214.00 sqm 3.69 sqm 789.66
wrap on MS pipe
Painting one coat with bitumastic paint on 100mm
dia pipe
14.38.0.3 Rate as per Item No. 14.38.3 of SH:DISTEMPERING, 8.87 metre 10 metre 88.70
PAINTING AND FINISHING
LABOUR
0111 Painter 197.00 day 0.15 day 29.55
0114 Beldar 190.00 day 0.15 day 28.50
TOTAL 936.41
Add 5 % for water, electricity, sundries and other 42.39
overhead charges on all except (A) i.e. on (936.41 -
88.70) = 847.71
TOTAL 978.80
Add 10 % for contractor's profit on all except (A) 89.01
i.e. on (978.80 - 88.70) = 890.10
Cost for 10 metre 1067.81
Cost for 1 metre 106.78
Say 107.00
23.3 Providing and wrapping 4 mm thick of approved make and quality bitumen based anti rust felt over MS pipe with
overlap of 25 mm to make an impermeable layer including painting with one coat of bitumastic paint before felt
complete. (Only on MS pipe to be laid in soil below ground).
TOTAL 1386.96
Add 10 % for contractor's profit on all except (A) 125.19
i.e. on (1386.96 - 135.10) = 1251.86
Labour
0107 Fitter 1st class 207.00 day 2.5 day 517.50
0114 Beldar 190.00 day 5 day 950.00
TOTAL 35612.70
Add 5 % for water, electricity, sundries and other 1780.64
overhead charges
TOTAL 37393.34
Add 10 % for contractor's profit 3739.33
Cost of 10 valves 41132.67
Cost of 1 valve 4113.26
Say 4113.00
23.4 Providing, installation, testing and commissioning of dual plate non-return valve of following sizes confirming to IS:
5312 complete with rubber gasket, GI bolts, nuts, washers etc. as required.
23.4.2 100mm dia
Code Description Rate Unit Qty Total
Details of cost for 10 valves
Materials :-
2066 100 mm dia dual plate check valve PN 1.6 4152.00 each 10 each 41520.00
Labour
0107 Fitter 1st class 207.00 day 2.5 day 517.50
0114 Beldar 190.00 day 5 day 950.00
TOTAL 45047.90
Add 5 % for water, electricity, sundries and other 2252.40
overhead charges
TOTAL 47300.30
Add 10 % for contractor's profit 4730.03
Cost of 10 valves 52030.33
Cost of 1 valve 5203.03
Say 5203.00
23.4 Providing, installation, testing and commissioning of dual plate non-return valve of following sizes confirming to IS:
5312 complete with rubber gasket, GI bolts, nuts, washers etc. as required.
23.4.3 150mm dia
Code Description Rate Unit Qty Total
Details of cost for 10 valves
Materials :-
2067 150 mm dia dual plate check valve PN 1.6 6800.00 each 10 each 68000.00
2074 Rubber insertions for 150 mm dia pipe joints 18.00 each 10 each 180.00
Labour
0107 Fitter 1st class 207.00 day 2.5 day 517.50
0114 Beldar 190.00 day 5 day 950.00
TOTAL 72587.02
Add 5 % for water, electricity, sundries and other 3629.35
overhead charges
TOTAL 76216.37
Add 10 % for contractor's profit 7621.64
Cost of 10 valves 83838.01
Cost of 1 valve 8383.80
Say 8384.00
23.5 Supplying, fixing, testing and commissioning of flanged butterfly valve PN 1.6, with Bronze/Gunmetal seat duly ISI
marked complete with Nuts, Bolts, washers, gaskets, conforming to IS: 13095 of following sizes as required.
Labour
0107 Fitter 1st class 207.00 day 2.5 day 517.50
0114 Beldar 190.00 day 5 day 950.00
TOTAL 24322.70
Add 5 % for water, electricity, sundries and other 1216.14
overhead charges
TOTAL 25538.84
Add 10 % for contractor's profit 2553.88
Cost of 10 valves 28092.72
Cost of 1 valve 2809.27
Say 2809.00
23.5 Supplying, fixing, testing and commissioning of flanged butterfly valve PN 1.6, with Bronze/Gunmetal seat duly ISI
marked complete with Nuts, Bolts, washers, gaskets, conforming to IS: 13095 of following sizes as required.
Labour
0107 Fitter 1st class 207.00 day 2.5 day 517.50
0114 Beldar 190.00 day 5 day 950.00
TOTAL 29967.90
Add 5 % for water, electricity, sundries and other 1498.40
overhead charges
TOTAL 31466.30
Add 10 % for contractor's profit 3146.63
Cost of 10 valves 34612.93
Cost of 1 valve 3461.29
Say 3461.00
23.5 Supplying, fixing, testing and commissioning of flanged butterfly valve PN 1.6, with Bronze/Gunmetal seat duly ISI
marked complete with Nuts, Bolts, washers, gaskets, conforming to IS: 13095 of following sizes as required.
Labour
0107 Fitter 1st class 207.00 day 2.5 day 517.50
0114 Beldar 190.00 day 5 day 950.00
TOTAL 42047.02
Add 5 % for water, electricity, sundries and other 2102.35
overhead charges
TOTAL 44149.37
Add 10 % for contractor's profit 4414.94
Cost of 10 valves 48564.31
Cost of 1 valve 4856.43
Say 4856.00
23.6 Providing and fixing C.I. double flanged sluice valves rated to PN 1.6 with C.I. Wheel bolts, nuts, washers 3mm thick
insertion rubber gasket including matching flanges table E, complete.
23.6.1 100mm dia
Code Description Rate Unit Qty Total
Details of cost for 10 sluice valves
Materials :-
1621 C.I.sluice valve (with caps) 100 mm dia (Category-A) 2910.00 each 10 each 29100.00
Labour
0107 Fitter 1st class 207.00 day 2 day 414.00
0114 Beldar 190.00 day 2 day 380.00
TOTAL 29894.00
Add 5 % for water, electricity, sundries and other 1494.70
overhead charges
TOTAL 31388.70
Add 10 % for contractor's profit 3138.87
Cost of 10 valves 34527.57
Cost of 1 valve 3452.75
Say 3453.00
23.6 Providing and fixing C.I. double flanged sluice valves rated to PN 1.6 with C.I. Wheel bolts, nuts, washers 3mm thick
insertion rubber gasket including matching flanges table E, complete.
23.6.2 150mm dia
Code Description Rate Unit Qty Total
Details of cost for 10 sluice valves
Materials :-
1623 C.I.sluice valve (with caps) 150 mm dia (Category-A) 4300.00 each 10 each 43000.00
Labour
0107 Fitter 1st class 207.00 day 2.5 day 517.50
0114 Beldar 190.00 day 2.5 day 475.00
TOTAL 43992.50
Add 5 % for water, electricity, sundries and other 2199.63
overhead charges
TOTAL 46192.13
LABOUR
0107 Fitter 1st class 207.00 day 0.1 day 20.70
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 974.70
Add 5 % for water, electricity, sundries and other 48.74
overhead charges
TOTAL 1023.44
Add 10 % for contractor's profit 102.34
Cost for 1 no 1125.78
Say 1126.00
23.10 Providing and fixing Flow switches suitable for fixing in 50mm to 150mm dia pipe line, complete with all accessories
to provide indication in annunciator panel.
Code Description Rate Unit Qty Total
Details of cost for 1 no
Materials:
3904 Flow switches suitable for fixing in 50mm to 2800.00 each 1 each 2800.00
150mm dia pipe line, complete with all accessories
to provide indication in annuciator panel.
LABOUR
0107 Fitter 1st class 207.00 day 0.1 day 20.70
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 3119.70
Add 5 % for water, electricity, sundries and other 155.99
overhead charges
TOTAL 3275.69
Add 10 % for contractor's profit 327.57
Cost for 1 no 3603.26
Say 3603.00
LABOUR
0107 Fitter 1st class 207.00 day 0.1 day 20.70
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 1084.70
Add 5 % for water, electricity, sundries and other 54.24
overhead charges
TOTAL 1138.94
Add 10 % for contractor's profit 113.89
Cost for 1 no 1252.83
Say 1253.00
23.12 Supplying and installing pressure gauge of 100 mm Ø., 0-300 PSI or 0-21 kg per cm square fitted with 12/15 mm Ø.
pad cock valve, and G.I. pipe, elbow etc. as per requirement in approved manner.
Code Description Rate Unit Qty Total
Details of cost for 1 no
Materials:
3906 Pressure gauge 100 mm dia dial, 0-300 PSI or 0-21 500.00 each 1 each 500.00
Kg/cm2
Add for fixing accessories @ 10% of above "A" 50.00
3907 12/15 mm dia pad cock valve 60.00 each 1 each 60.00
LABOUR
0107 Fitter 1st class 207.00 day 0.1 day 20.70
0114 Beldar 190.00 day 0.1 day 19.00
TOTAL 649.70
Add 5 % for water, electricity, sundries and other 32.49
overhead charges
TOTAL 682.19
Add 10 % for contractor's profit 68.22
Cost for 1 no 750.41
Say 750.00
23.13 Providing and fixing 15 mm dia, Quartzoid bulb type G.M. Sprinkler Head set to operate at 680C of approved make
chrome plated complete in all respect as required.
Code Description Rate Unit Qty Total
Details of cost for 1 no
Materials:
3911 G.M. Sprinkler Head 15 mm dia with Quartzoid 850.00 each 1 each 850.00
bulb type set to operate at 68 degree celcius
LABOUR
0107 Fitter 1st class 207.00 day 0.05 day 10.35
2072 Rubber insertions for 80 mm dia pipe joints 16.00 each 1 each 16.00
2075 Bolts and nuts 96.00 kg 1 kg 96.00
LABOUR
0107 Fitter 1st class 207.00 day 0.15 day 31.05
0114 Beldar 190.00 day 0.15 day 28.50
TOTAL 5817.55
Add 5 % for water, electricity, sundries and other 290.88
overhead charges
TOTAL 6108.43
Add 10 % for contractor's profit 610.84
Cost for 1 no 6719.27
Say 6719.00
23.19 Supplying and fixing double headed internal hydrant valve with instantaneous Gun metal couplings of 63 mm dia
with cast iron wheel ISI marked conforming to IS: 5290 (Type - A) with blank Gunmetal cap and chain as required.
2072 Rubber insertions for 80 mm dia pipe joints 16.00 each 1 each 16.00
2075 Bolts and nuts 96.00 kg 1 kg 96.00
4 Nos Bolts and nuts of size 16mm dia 100mm long
weight @ 0.248792kg each = 0.9952 kg
LABOUR
0107 Fitter 1st class 207.00 day 0.15 day 31.05
0114 Beldar 190.00 day 0.15 day 28.50
TOTAL 9971.55
Add 5 % for water, electricity, sundries and other 498.58
overhead charges
TOTAL 10470.13
Add 10 % for contractor's profit 1047.01
Cost for 1 no 11517.14
Say 11517.00
23.20 Supplying and erecting orifice plate having 6 mm thickness, 140 mm outer dia at every single outlet hydrant valve as
per specification.
Code Description Rate Unit Qty Total
Details of cost for 1 no
Materials:
3909 Orifice plate of 6 mm thickness, 140 mm outer dia 350.00 each 1 each 350.00
for single outlet hydrant valve
LABOUR
0107 Fitter 1st class 207.00 day 0.01 day 2.07
0114 Beldar 190.00 day 0.01 day 1.90
TOTAL 353.97
LABOUR
0107 Fitter 1st class 207.00 day 0.03 day 6.21
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 3053.91
Add 5 % for water, electricity, sundries and other 152.70
overhead charges
TOTAL 3206.61
Add 10 % for contractor's profit 320.66
Cost for 1 no 3527.27
Say 3527.00
23.23 Supplying and fixing 63 mm dia, 15 mtr long Flax canvas hose pipe with 63 mm dia Male and Female Stainless Steel-
IS: 3444 Grade-1 couplings duly binded with GI wire, rivets etc. conforming to IS: 636 (Type -A) as required.
LABOUR
0107 Fitter 1st class 207.00 day 0.03 day 6.21
0114 Beldar 190.00 day 0.03 day 5.70
TOTAL 8820.91
Add 5 % for water, electricity, sundries and other 441.05
overhead charges
TOTAL 9261.96
Add 10 % for contractor's profit 926.20
Cost for 1 no 10188.16
Say 10188.00
23.24 Supplying & fixing 63 mm dia Stainless Steel IS: 3444 Grade-1 branch pipe with 20 mm dia (nominal internal) Gun
Metal nozzle conforming to IS: 903, suitable for instantaneous coupling connection to connect hose pipe coupling as
required.
LABOUR
0107 Fitter 1st class 207.00 day 0.01 day 2.07
0114 Beldar 190.00 day 0.01 day 1.90
TOTAL 2582.97
Add 5 % for water, electricity, sundries and other 129.15
overhead charges
TOTAL 2712.12
Add 10 % for contractor's profit 271.21
Cost for 1 no 2983.33
Say 2983.00
23.25 Supplying and fixing of MS hose cabinet box of made of 2 mm thick MS sheet and 40 x 40 x 5mm angle iron with
front openable cover having 6 mm thick glazed glass viewing window i/c necessary locking arrangement, on existing
wall/ brick platform etc complete as required.
2072 Rubber insertions for 80 mm dia pipe joints 16.00 each 1 each 16.00
2075 Bolts and nuts 96.00 kg 1 kg 96.00
4 Nos Bolts and nuts of size 16mm dia 100mm long
weight @ 0.248792kg each = 0.9952 kg
LABOUR
0107 Fitter 1st class 207.00 day 0.15 day 31.05
0114 Beldar 190.00 day 0.15 day 28.50
TOTAL 10765.55
Add 5 % for water, electricity, sundries and other 538.28
overhead charges
TOTAL 11303.83
Add 10 % for contractor's profit 1130.38
Cost for 1 no 12434.21
Say 12434.00
23.32 Supplying and fixing 2 way Fire Brigade Connection of cast iron body with 2 Nos. Gun metal male instantaneous
inlet couplings complete with cap and chain conforming to IS: 904 including connection to existing MS pipe line
complete as required.
2072 Rubber insertions for 80 mm dia pipe joints 16.00 each 1 each 16.00
2075 Bolts and nuts 96.00 kg 1 kg 96.00
4 Nos Bolts and nuts of size 16mm dia 100mm long
weight @ 0.248792kg each = 0.9952 kg
LABOUR
0107 Fitter 1st class 207.00 day 0.15 day 31.05
0114 Beldar 190.00 day 0.15 day 28.50
TOTAL 7971.55
Add 5 % for water, electricity, sundries and other 398.58
overhead charges
TOTAL 8370.13
Add 10 % for contractor's profit 837.01
Cost for 1 no 9207.14
Say 9207.00
23.33 Providing and fixing standard fireman's axe (tested for 20000 Volts) with heavy insulated rubber handle. (ISI
marked)
Code Description Rate Unit Qty Total
Details of cost for 1 no
Materials:
LABOUR
0107 Fitter 1st class 207.00 day 0.02 day 4.14
0114 Beldar 190.00 day 0.02 day 3.80
TOTAL 2107.94
Add 5 % for water, electricity, sundries and other 105.40
overhead charges
TOTAL 2213.34
Add 10 % for contractor's profit 221.33
Cost for 1 no 2434.67
Say 2435.00
23.34 Providing and constructing masonry chamber 90x90 x100 cms inside with 35 class designation fly ash brick work in
cement mortar 1:4 (1 cement : 4 coarse sand) for water meter/ sluice valve/ etc, M.S. cover of size 600mm x 600mm
with M.S. frame and 6mm thick sheet with locking arrangement etc complete.
= 2.85cum.
1.1.0.1 Excavation in all kind of soft soil (Rate as per item 184.59 cum 2.85 cum 526.08
no 1.1.1)
1.17 Fillig excavated soft soil (Rate as per item no 1.17) 64.95 cum 2.85 cum 185.11
4.52mx0.19mx1.00m= 0.86cum.
7.1.0.2 Brick work class designation 35 in CM 1:4 (Rate as 4010.02 cum 0.86 cum 3448.62
per item No 7.1.2)
(iv) 12mm cement plaster 1:3 (1 Cement : 3 Coarse
sand) finished with a floating coat of neat cement.
3.60mx1.00m=3.60sqm.
0.90mx0.90m=0.81sqm.
=4.41sqm.
11.2.0.2 12mm plaster with CM 1:4 (Rate as per Item No 102.93 sqm 4.41 sqm 453.92
11.2.2)
11.5 Neat cement punning (Rate as per Item No 11.5) 33.13 sqm 4.41 sqm 146.10
2422 Surface box for sluice valve 185.00 each 1 each 185.00
(vii) Cement concrete 1:2:4 (1 Cement : 2 Coarse
sand ; 4 graded stone aggregate 20mm nominal
size)
TOTAL 7796.15
Add 5 % for water, electricity, sundries and other 9.25
overhead charges on all except (A) i.e. on (7796.15
- 7611.15) = 185.00
TOTAL 7805.40
Add 10 % for contractor's profit on all except (A) 19.43
i.e. on (7805.40 - 7611.15) = 194.25
TOTAL 19523.23
LABOUR
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1 day 190.00
PAINTING of Iron Bracket = 3.14x0.3x1.5 = 1.41
sqm + 10% for bracket = 1.55 sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 1.55 sqm 26.77
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 1.55 sqm 73.16
TOTAL 11386.93
Add 5 % for water, electricity, sundries and other 564.35
overhead charges on all except (A) i.e. on
(11386.93 - 99.93) = 11287.00
TOTAL 11951.28
Add 10 % for contractor's profit on all except (A) 1185.14
i.e. on (11951.28 - 99.93) = 11851.35
23.1.1 25 mm dia.
Code Description Rate Unit Qty Total
Details of cost for 10 metre
MATERIALS
1812 M.S. pipes "C" class 25 mm dia 150.00 metre 10 metre 1500.00
Add for accessories such as Tee, bend, elbow, 450.00
suitable size hanging bars, steel fastners for
hanging arrangement etc @ 20@ of above "A"
LABOUR
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1 day 190.00
PAINTING of Iron Bracket = 10x0.025*3.14 = 0.785
sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 0.785 sqm 13.56
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 0.785 sqm 37.05
TOTAL 2397.61
Add 5 % for water, electricity, sundries and other 119.88
overhead charges on all except
TOTAL 2517.49
Add 10 % for contractor's profit on all except 251.75
LABOUR
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1 day 190.00
PAINTING of Iron Bracket = 10x0.032*3.14=1.00
sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 1 sqm 17.27
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 1 sqm 47.20
TOTAL 2731.47
Add 5 % for water, electricity, sundries and other 136.57
overhead charges on all except
TOTAL 2868.04
Add 10 % for contractor's profit on all except 286.80
23.1 Supply, erection, jointing, testing & commissioning of "C" Class MS pipes (as per IS: 1239) including necessary specials
such as tees, bends, flanges reducers etc., complete on wall/ ceiling. The pipes to be erected on wall or suspended
from beams, RCC roof slabs with suitable size MS bars/ angle irons including painting of metal part except pipe line.
LABOUR
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1 day 190.00
PAINTING of Iron Bracket = 10x0.040x3.14 = 1.256
sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 1.256 sqm 21.69
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 1.256 sqm 59.28
TOTAL 2767.97
Add 5 % for water, electricity, sundries and other 138.40
overhead charges on all except
TOTAL 2906.37
Add 10 % for contractor's profit on all except 290.64
LABOUR
0107 Fitter 1st class 207.00 day 1 day 207.00
0114 Beldar 190.00 day 1 day 190.00
PAINTING of Iron Bracket = 10x0.2x3.14 =6.28 sqm
14.21 Priming coat of Red Oxide (Rate as per Item No 17.27 sqm 6.28 sqm 108.46
14.21)
14.22.0.2 Painting on new work (Rate as per item no 14.22.2) 47.20 sqm 6.28 sqm 296.42
TOTAL 17049.87
Add 5 % for water, electricity, sundries and other 852.49
overhead charges on all except
TOTAL 17902.37
Add 10 % for contractor's profit on all except 1790.24
50mm dia.
Supply, erection, jointing, testing & commissioning of "C" Class MS pipes (as per IS: 1239) including necessary specials
such as tees, bends, flanges reducers etc., complete on wall/ ceiling. The pipes to be erected on wall or suspended from
beams, RCC roof slabs with suitable size MS bars/ angle irons including painting of metal part except pipe line.
65mm dia.
Supply, erection, jointing, testing & commissioning of "C" Class MS pipes (as per IS: 1239) including necessary specials
such as tees, bends, flanges reducers etc., complete on wall/ ceiling. The pipes to be erected on wall or suspended from
beams, RCC roof slabs with suitable size MS bars/ angle irons including painting of metal part except pipe line.
65mm dia.
Supply, erection, jointing, testing & commissioning of "C" Class MS pipes (as per IS: 1239) including necessary specials
such as tees, bends, flanges reducers etc., complete on wall/ ceiling. The pipes to be erected on wall or suspended from
beams, RCC roof slabs with suitable size MS bars/ angle irons including painting of metal part except pipe line.
65mm dia.